Device and method for in-situ detection of formation temperature and pressure data at bottom of mine drill hole

The device, which uses a microchip loading section and a soluble metal shell, solves the problems of large measurement errors and complex installation in coal mine gas extraction and hydraulic fracturing processes, and achieves efficient and accurate gas pressure and temperature measurement, thereby improving mining efficiency and safety.

CN118933739APending Publication Date: 2024-11-12CHINA UNIV OF MINING & TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411232744.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-04
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

Existing technologies for coal mine gas extraction and hydraulic fracturing in mines suffer from problems such as low accuracy of manual data reading, complex equipment installation, large measurement errors, and inability to monitor temperature in real time, resulting in inaccurate measurement results and high costs.

Method used

The device, which employs a microchip loading section and a soluble metal shell, automatically records gas pressure and temperature through the microchip. Combined with the dissolution of the soluble metal shell under special working conditions, it enables bottom hole data acquisition, simplifying the installation process and improving measurement accuracy.

Benefits of technology

It improves the accuracy and efficiency of measuring raw gas pressure and temperature in coal seams, reduces the maintenance requirements of measuring equipment, ensures the accuracy and security of data, and improves mining efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933739A_ABST
    Figure CN118933739A_ABST
Patent Text Reader

Abstract

The invention discloses a device and method for in-situ detection of formation temperature and pressure data at the bottom of a mine drill hole, and relates to the technical field of coal mine safety mining. The invention comprises the device for in-situ detection of the formation temperature and pressure data at the bottom of the mine drill hole and the use method of the device for in-situ detection of the formation temperature and pressure data at the bottom of the mine drill hole. According to the device, the soluble metal shell is adopted to achieve data collection of the bottom of a downward drill hole, the soluble metal shell has good dissolvability and can be dissolved under a certain condition, and possibility can be provided for collection of hole bottom temperature and pressure data under special working conditions; the original gas pressure and temperature of a coal seam can be directly measured, the measurement precision is improved, errors of gas parameters measured at a hole opening are avoided, meanwhile, the direct novel gas measurement mode is simple in structure, measurement steps are simpler and more efficient, the complexity of installation of a traditional sensor is eliminated, and the maintenance requirement of measurement equipment is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of safe mining of coal mines, and in particular to a device and a method for in-situ detection of stratum temperature and pressure data at the bottom of a mine borehole. Background Art

[0002] Gas disasters are one of the most important disasters in coal mine safety production in my country. Before coal mining, coal seams must be pre-extracted to reduce the gas content in the coal seams to ensure safe and efficient production in coal mines. At present, the main method of coal mine gas extraction is to carry out through-layer drilling and along-layer drilling in underground coal mine tunnels, and use water ring vacuum pumps for negative pressure extraction. In addition, before gas extraction, it is necessary to measure the original gas pressure of the coal seam and the gas content of the coal seam to determine the gas content and physical properties of the coal seam. When the permeability of the coal seam is poor, it is also necessary to combine the hydraulic fracturing process to enhance the permeability of the coal seam and improve the efficiency of gas extraction.

[0003] At present, the original gas pressure of coal seams is generally measured in real time through orifice pressure gauges, and the gas pressure is recorded by manual and electronic pressure gauges. Although this method has the advantages of low cost and simple operation, it also has limitations, such as: ①: Manual reading data is greatly affected by subjective and environmental factors, the accuracy and reliability of the reading data are low, and the amount of data from manual reading is small. The limited amount of data cannot support further analysis and research on coal seam physical parameters; ②: The installation process of the electronic pressure gauge is complicated, which results in a long time and high labor cost for measuring the original gas pressure of the coal seam; ③: When the passage between the hole mouth and the hole bottom is blocked by coal powder or water, the gas pressure measurement fails.

[0004] In addition, in the process of hydraulic fracturing in mines, accurately obtaining the temperature and pressure data of the fracturing layer plays a vital role in evaluating the fracturing effect. At present, the field generally collects data such as orifice pressure or pump pressure to invert the fracturing pressure and injection pressure of the target formation. Although this method has been widely used, it still has shortcomings: ①: The fracturing string in the tunnel is relatively long. The length of the string in the straight hole is greater than 100m, and the length of the string in the directional hole is generally greater than 1000m. The longer the string, the greater the error in the pressure inversion result; ②: The installation process of the orifice electronic pressure gauge is complicated and the cost is high, which increases the construction time, labor cost and economic cost; ③: When monitoring pressure, due to the limitation of installation space, a single pressure gauge is generally used for measurement. When an error occurs in the measured pressure, it cannot be detected and corrected in time.

[0005] ④: The existing methods cannot measure the temperature of the fracturing formation, especially for long-distance directional holes, the inversion results of the formation temperature have large errors; In view of the above problems, the inventors proposed a device and method for in-situ detection of stratum temperature and pressure data at the bottom of a mine borehole to solve the above problems. Summary of the invention

[0006] In order to solve the above problems, the purpose of the present invention is to provide a device and method for in-situ detection of stratum temperature and pressure data at the bottom of a mine borehole.

[0007] In order to solve the above technical problems, the present invention adopts the following technical solutions: a device for in-situ detection of formation temperature and pressure data at the bottom of a mine borehole, the detection device comprising a liquid pump, a stop valve, a pressure gauge, a conversion joint, a high-pressure hose, a liquid injection steel pipe, a hole sealer, a one-way valve group and a microchip loading section; One end of the high-pressure hose is mounted on the water outlet of the liquid pump, the conversion joint connects the two ends of the high-pressure hose to the liquid injection steel pipe and the pressure gauge respectively, the stop valve is mounted on the end of the high-pressure hose close to the liquid pump, the hole sealer is mounted on the end of the high-pressure hose away from the liquid pump, and the microchip loading section is arranged on the end of the high-pressure hose away from the liquid pump; A microchip capsule is arranged in the microchip loading section, and the chip in the microchip capsule automatically records the gas pressure and temperature.

[0008] Preferably, the outer wall of the microchip capsule is provided with a soluble metal shell, the soluble metal shell is made of any one of aluminum-magnesium alloy and aluminum-zinc alloy, and a small hole communicating with the microchip capsule is provided in the middle of the soluble metal shell.

[0009] Preferably, a hollow tube column is provided in the microchip loading section, a blind hole is provided at one end of the hollow tube column, a microchip loading area is provided at the center of the hollow tube column, a guide groove is opened on the inner wall of the hollow tube column, four guide grooves are provided, and a stopcock is provided at the open end of the guide groove.

[0010] Preferably, a shallow groove is provided on the outer wall of the hollow tube column, the shallow groove is used to place a microchip, the surface of the shallow groove is covered with a mesh cover plate, and the number of the guide grooves is one.

[0011] The present invention also provides a method for using a device for in-situ detection of stratum temperature and pressure data at the bottom of a mine borehole, the method comprising the steps of measuring the original gas pressure and temperature of a coal seam in an upward, horizontal or downward borehole in a rock tunnel and the steps of measuring the in-situ temperature and pressure at the bottom of the hole during long-distance directional drilling hydraulic fracturing.

[0012] Preferably, the step of measuring the original gas pressure of the coal seam drilled upward or horizontally in the tunnel comprises: S1. Use a drilling rig to drill a hole upward or horizontally in a rock tunnel to the target coal seam, and continue drilling to a certain depth to install a hole sealer; S2. After drilling, clean and check the inner wall of the hole. After the construction meets the standards, install the microchip loading section to the top of the liquid injection steel pipe, install the hole sealer and the liquid injection steel pipe, use the conversion joint to connect the two ends of the high-pressure hose to the liquid injection steel pipe and the pressure gauge respectively, and then connect the liquid pump, stop valve and pressure gauge in sequence; S3, start the liquid pump to pump in the sealing mucus, so that the hole sealer expands and seals the drill hole. At the same time, when the liquid pressure in the injection steel pipe exceeds the minimum pressure of the one-way valve, the mucus flows out of the one-way valve, fills and seals the space between the two hole sealers (the hole sealer seals the liquid, and the sealing mucus seals the gas); S4. After the sealing is completed, the microchip in the sealing microchip loading section will automatically record the gas pressure. After a certain period of time, the microchip loading section is removed and the microchip is taken out. Special equipment is used to read the data stored in the microchip to complete the measurement of the original gas pressure of the coal seam drilled upward or horizontally.

[0013] Preferably, the step of measuring the original gas pressure of the coal seam drilled downward in the tunnel comprises: S1. Use a drilling rig to drill a directional borehole upward in the rock tunnel to the target coal seam, and install a hole sealer in the horizontal section; S2. After drilling, clean and inspect the inner wall of the borehole. After the construction meets the standards, install the microchip loading section to the top of the liquid injection steel pipe, install the hole sealer and the liquid injection steel pipe, use the conversion joint to connect the two ends of the high-pressure hose to the liquid injection steel pipe and the pressure gauge respectively, and connect the liquid pump, stop valve and pressure gauge in turn; S3, start the liquid pump to pump in the sealing mucus, so that the hole sealer expands and seals the drill hole. At the same time, when the liquid pressure in the injection steel pipe exceeds the minimum pressure of the one-way valve, the mucus flows out of the one-way valve, fills and seals the space between the two hole sealers (the hole sealer seals the liquid, and the sealing mucus seals the gas); S4. After the hole is sealed, the microchip capsule wrapped in a soluble metal shell in the hole will automatically record the gas pressure. When the original gas pressure measurement is completed, the hole sealing device is removed and water is injected into the borehole until the water level is close to the ground level of the tunnel; S5. After the soluble metal shell is dissolved, the microchip capsule will float to the water surface because its density is lower than that of water. The microchip capsule on the water surface is recovered and the data stored in the microchip is read using special equipment to complete the measurement of the original gas pressure of the coal seam drilled deep vertically downward.

[0014] Preferably, the application steps of the microchip in the long-distance directional drilling hydraulic fracturing process include: S1. Use a drilling rig to drill a directional borehole upward in the rock tunnel to the target coal seam, and install a hole sealer in the horizontal section; S2. After drilling, clean and check the inner wall of the borehole. After the construction meets the standards, the installation order of the bottom hole fracturing tool from the bottom of the hole to the hole mouth is: hole sealer, one-way valve group, microchip loading section, hole sealer, liquid injection steel pipe, use the conversion joint to connect the two ends of the high-pressure hose to the liquid injection steel pipe and the pressure gauge respectively, and then connect the liquid pump, stop valve and pressure gauge in turn; S3, start the liquid pump, pump fracturing fluid into the liquid injection steel pipe, so that the two sealers expand and seal the borehole at the same time. After the sealing is completed, continue to pump fracturing fluid. When the fracturing fluid pressure in the liquid injection steel pipe is greater than the minimum opening pressure of the one-way valve group, the fracturing fluid begins to flow into the coal seam to be fractured, and the microchip in the microchip loading section will automatically record the fracturing fluid pressure; S4. After the hydraulic fracturing is completed, the microchip loading section is removed and the microchip is taken out. The data stored in the microchip is read using special equipment to complete the pressure and temperature measurement during the long-distance directional drilling hydraulic fracturing process.

[0015] Compared with the prior art, the present invention has the following beneficial effects: 1. In the present invention, a soluble metal shell is used to realize data collection at the bottom of the borehole. The soluble metal shell has good solubility and dissolves under certain conditions, which can provide the possibility of collecting temperature and pressure data at the bottom of the hole under special working conditions; 2. In the present invention, two installation structures of the drilling wandering collector in the pipe column are set to improve the assembly efficiency and data collection accuracy. One is a blind hole hollow pipe column structure, and the other is a shallow groove fixed structure. After placement, it can be covered and fixed with a mesh cage. The blind hole hollow pipe column structure is suitable for situations where higher data transmission requirements and liquid conduction are required, ensuring the accuracy and security of the data. The shallow groove fixed structure is simple and convenient, suitable for installation requirements in most scenarios, and can quickly and effectively fix the microchip collector; 3. In the present invention, it is proposed that the pipe column loaded with the microchip can be connected to the injection pipe column of the hole sealer, which can directly measure the original gas pressure and temperature of the coal seam, improve the measurement accuracy, and avoid the error of measuring gas parameters at the hole mouth. At the same time, this new direct gas measurement method has a simple structure, simpler and more efficient measurement steps, eliminates the complexity of traditional sensor installation, and reduces the maintenance requirements of the measurement equipment; 4. The present invention proposes an application method of a microchip in the hydraulic fracturing process. The microchip is used to directly monitor the temperature and pressure in the fracturing borehole, making the monitoring of the temperature and pressure in the hydraulic fracturing process simpler and more efficient, helping engineers obtain more accurate data, enabling engineers to better control the fracturing process, and improving mining efficiency and safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0017] Figure 1 It is a schematic diagram of the structure of the microchip detection device of the present invention.

[0018] Figure 2 This is a schematic diagram of the installation structure of the microchip detection device of the present invention on the pipe column.

[0019] Figure 3 This is another schematic diagram of the installation structure of the microchip detection device of the present invention on the pipe column.

[0020] Figure 4 The figure is a schematic diagram of the application method of the microchip of the present invention in the measurement of the original gas pressure of the coal seam.

[0021] Figure 5 Another schematic diagram of the application method of the microchip of the present invention in measuring the original gas pressure of coal seams.

[0022] Figure 6 It is a schematic diagram of the application method of the microchip of the present invention in the process of hydraulic fracturing.

[0023] In the figure: 1. liquid pump; 2. stop valve; 3. pressure gauge; 4. conversion joint; 5. high-pressure hose; 6. liquid injection steel pipe; 7. hole sealer; 8. microchip loading section; 9. rock tunnel; 10. coal seam; 11. rock layer 1; 12. rock layer 2; 13. one-way valve group; 20. microchip capsule; 30. soluble metal shell; 40. small hole; 50. hollow pipe column; 60. microchip loading area; 70. guide groove; 80. plug; 90. shallow groove; 100. mesh cover. DETAILED DESCRIPTION

[0024] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0025] Embodiment 1: Figure 1 , 2 , 4 and Figure 5As shown, the present invention provides a device for in-situ detection of formation temperature and pressure data at the bottom of a mine borehole, the detection device comprising a liquid pump 1, a stop valve 2, a pressure gauge 3, a conversion joint 4, a high-pressure hose 5, a liquid injection steel pipe 6, a hole sealer 7, a one-way valve group 13 and a microchip loading section 8; One end of the high-pressure hose 5 is assembled at the water outlet end of the liquid pump 1, the conversion joint 4 connects the two ends of the high-pressure hose 5 to the liquid injection steel pipe 6 and the pressure gauge 3 respectively, the stop valve 2 is assembled at the end of the high-pressure hose 5 close to the liquid pump 1, the hole sealer 7 is assembled at the end of the high-pressure hose 5 away from the liquid pump 1, and the microchip loading section 8 is arranged at the end of the high-pressure hose 5 away from the liquid pump 1; A microchip capsule 20 is arranged in the microchip loading section 8, and the chip in the microchip capsule 20 automatically records the gas pressure and temperature.

[0026] The outer wall of the microchip capsule 20 is provided with a soluble metal shell 30 . The soluble metal shell 30 is made of any one of aluminum-magnesium alloy and aluminum-zinc alloy. A small hole 40 communicating with the microchip capsule 20 is provided in the middle of the soluble metal shell 30 .

[0027] A hollow tube column 50 is arranged in the microchip loading section 8, a blind hole is arranged at one end of the hollow tube column 50, a microchip loading area 60 is arranged at the center position of the hollow tube column 50, a guide groove 70 is opened on the inner wall of the hollow tube column 50, four guide grooves 70 are arranged, and a plug 80 is arranged at the open end of the guide groove 70.

[0028] The present invention also provides a method for using the device for in-situ detecting stratum temperature and pressure data at the bottom of a mine borehole. The method includes the steps of measuring the original gas pressure of a coal seam drilled upward, horizontally or downward.

[0029] The steps for measuring the original gas pressure of the coal seam by drilling upward or horizontally in the tunnel include: S1, using a drilling rig to drill a borehole in the rock tunnel 9 downward to the target coal seam 10, and continue drilling to a certain depth for installing a hole sealer 7; S2. After drilling, clean and check the inner wall of the borehole. After the construction meets the standards, install the microchip loading section 8 to the top of the liquid injection steel pipe 6, install the hole sealer 7 and the liquid injection steel pipe 6, use the conversion joint 4 to connect the two ends of the high-pressure hose 5 to the liquid injection steel pipe 6 and the pressure gauge 3 respectively, and then connect the liquid pump 1, the stop valve 2 and the pressure gauge 3 in sequence; S3, start the liquid pump 1 to pump in the sealing mucus, so that the hole sealer 7 expands and seals the drill hole. At the same time, when the liquid pressure in the liquid injection steel pipe 6 exceeds the minimum pressure of the one-way valve, the mucus flows out of the one-way valve, fills and seals the space between the two hole sealers 7 (the hole sealer 7 seals the liquid, and the sealing mucus seals the gas); S4. After the sealing is completed, the microchip in the sealing microchip loading section 8 will automatically record the gas pressure. After a certain period of time, the microchip loading section 8 is removed and the microchip is taken out. The data stored in the microchip is read using special equipment to complete the measurement of the original gas pressure of the coal seam drilled upward or horizontally.

[0030] The steps for measuring the original gas pressure of the coal seam drilled down in the tunnel include: S1, using a drilling rig to drill a borehole in the rock tunnel 9 downward to the target coal seam 10, and continue drilling to a certain depth for installing a hole sealer 7; S2. After drilling, clean and check the inner wall of the borehole. After the construction meets the standards, place the microchip capsule 20 wrapped with a soluble metal shell 30 into the borehole, then install the hole sealer 7 and the liquid injection steel pipe 6, use the conversion joint 4 to connect the two ends of the high-pressure hose 5 to the liquid injection steel pipe 6 and the pressure gauge 3 respectively, and then connect the liquid pump 1, the stop valve 2 and the pressure gauge 3 in sequence; S3, start the liquid pump 1 to pump in the sealing mucus, so that the hole sealer 7 expands and seals the drill hole. At the same time, when the liquid pressure in the liquid injection steel pipe 6 exceeds the minimum pressure of the one-way valve, the mucus flows out of the one-way valve, fills and seals the space between the two hole sealers 7 (the hole sealer 7 seals the liquid, and the sealing mucus seals the gas); S4, after the hole is sealed, the microchip capsule 20 wrapped with the soluble metal shell 30 in the hole will automatically record the gas pressure. When the original gas pressure measurement is completed, the hole sealing device is removed, and water is injected into the borehole until the water level is close to the ground height of the tunnel.

[0031] S5. After the soluble metal shell 30 is completely dissolved, the microchip capsule 20 will float to the water surface because its density is lower than that of water. The microchip capsule 20 on the water surface is recovered and the data stored in the microchip is read using a dedicated device to complete the measurement of the original gas pressure of the coal seam drilled deep vertically downward.

[0032] Embodiment 2: Figure 3 As shown: Different from the first embodiment, the outer wall of the hollow tube column 50 is provided with a shallow groove 90, the shallow groove 90 is used to place the microchip, the surface of the shallow groove 90 is covered with a mesh cover plate 100, and the guide groove 70 is set to one.

[0033] Embodiment 3: Figure 6 As shown, different from the first embodiment, the application steps of the microchip in the long-distance directional drilling hydraulic fracturing process include: S1. Use a drilling rig to drill a directional borehole upward in the rock tunnel 9 to the target coal seam 10, and install a hole sealer 7 in the horizontal section; S2. After drilling, clean and check the inner wall of the borehole. After the construction meets the standards, the installation order of the bottom hole fracturing tool from the bottom of the hole to the hole mouth is: hole sealer 7, one-way valve group 13, microchip loading section 8, hole sealer 7, liquid injection steel pipe 6, use conversion joint 4 to connect the two ends of high-pressure hose 5 to liquid injection steel pipe 6 and pressure gauge 3 respectively, and connect liquid pump 1, stop valve 2 and pressure gauge 3 in sequence; S3, start the liquid pump 1, pump the fracturing fluid into the liquid injection steel pipe 6, so that the two hole sealers 7 expand and seal the borehole at the same time. After the hole sealing is completed, continue to pump the fracturing fluid. When the fracturing fluid pressure in the liquid injection steel pipe 6 is greater than the minimum opening pressure of the one-way valve group 13, the fracturing fluid begins to flow into the coal seam 10 that needs to be fractured, and the microchip in the microchip loading section 8 will automatically record the fracturing fluid pressure; S4. After the hydraulic fracturing is completed, the microchip loading section 8 is removed and the microchip is taken out. The data stored in the microchip is read using a dedicated device to complete the pressure and temperature measurement during the long-distance directional drilling hydraulic fracturing process.

[0034] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. A device for in-situ detection of stratum temperature and pressure data at the bottom of a mine borehole, characterized in that: The detection device comprises a liquid pump (1), a stop valve (2), a pressure gauge (3), a conversion joint (4), a high-pressure rubber hose (5), a liquid injection steel pipe (6), a hole sealer (7), a one-way valve group (13) and a microchip loading section (8); One end of the high-pressure rubber hose (5) is mounted on the water outlet end of the liquid pump (1); the conversion joint (4) connects the two ends of the high-pressure rubber hose (5) to the liquid injection steel pipe (6) and the pressure gauge (3) respectively; the stop valve (2) is mounted on the end of the high-pressure rubber hose (5) close to the liquid pump (1); the hole sealer (7) is mounted on the end of the high-pressure rubber hose (5) away from the liquid pump (1); and the microchip loading section (8) is arranged on the end of the high-pressure rubber hose (5) away from the liquid pump (1); A microchip capsule (20) is arranged in the microchip loading section (8), and the chip in the microchip capsule (20) automatically records formation pressure and temperature.

2. The device for in-situ detection of stratum temperature and pressure data at the bottom of a mine borehole as claimed in claim 1, characterized in that: The outer wall of the microchip capsule (20) is provided with a soluble metal shell (30), the soluble metal shell (30) is made of any one of an aluminum-magnesium alloy and an aluminum-zinc alloy, and a small hole (40) connected to the microchip capsule (20) is provided in the middle of the soluble metal shell (30).

3. The device for in-situ detection of stratum temperature and pressure data at the bottom of a mine borehole as claimed in claim 1, characterized in that: A hollow tube column (50) is arranged in the microchip loading section (8), a blind hole is arranged at one end of the hollow tube column (50), a microchip loading area (60) is arranged at the center of the hollow tube column (50), a guide groove (70) is opened on the inner wall of the hollow tube column (50), four guide grooves (70) are arranged, and a cock (80) is arranged at the open end of the guide groove (70).

4. The device for in-situ detection of stratum temperature and pressure data at the bottom of a mine borehole as claimed in claim 3, characterized in that: The outer wall of the hollow tube column (50) is provided with a shallow groove (90), the shallow groove (90) is used to place a microchip, the surface of the shallow groove (90) is covered with a mesh cover plate (100), and the number of the guide groove (70) is one.

5. A method for using the device for in-situ detection of stratum temperature and pressure data at the bottom of a mine borehole as claimed in any one of claims 1 to 4, characterized in that: The method of use comprises the steps of measuring the original gas pressure and temperature of the coal seam in an upward, horizontal or downward borehole in a rock tunnel and the step of measuring the in-situ temperature and pressure at the bottom of the hole during the long-distance directional drilling hydraulic fracturing process.

6. The method for using the device for in-situ detection of stratum temperature and pressure data at the bottom of a mine borehole as claimed in claim 5, characterized in that: The steps of measuring the original gas pressure of the coal seam by drilling upward or horizontally in the tunnel include: S1, using a drilling rig to drill a borehole in the rock tunnel (9) downward to the target coal seam (10), and continue drilling to a certain depth to install a hole sealer (7); S2. After the drilling is completed, clean and inspect the inner wall of the borehole. After the construction meets the standards, install the microchip loading section (8) to the top of the liquid injection steel pipe (6), install the hole sealer (7) and the liquid injection steel pipe (6), use the conversion joint (4) to connect the two ends of the high-pressure hose (5) to the liquid injection steel pipe (6) and the pressure gauge (3), and then connect the liquid pump (1), the stop valve (2) and the pressure gauge (3) in sequence; S3, start the liquid pump (1) to pump in the sealing mucus, so that the sealing device (7) expands and seals the drilled hole. At the same time, when the liquid pressure in the liquid injection steel pipe (6) exceeds the minimum pressure of the one-way valve, the mucus flows out of the one-way valve, fills and seals the space between the two sealing devices (7) (the sealing device (7) seals the liquid, and the sealing mucus seals the gas); S4. After the hole sealing is completed, the microchip in the hole sealing microchip loading section (8) will automatically record the gas pressure. After a certain period of time, the microchip loading section (8) is removed and the microchip is taken out. The data stored in the microchip is read using a dedicated device to complete the measurement of the original gas pressure of the coal seam drilled upward or horizontally.

7. The method for using the device for in-situ detection of stratum temperature and pressure data at the bottom of a mine borehole as claimed in claim 5, characterized in that: The steps of measuring the original gas pressure of the coal seam drilled downward in the tunnel include: S1, using a drilling rig to drill a borehole in the rock tunnel (9) downward to the target coal seam (10), and continue drilling to a certain depth to install a hole sealer (7); S2. After the drilling is completed, clean and inspect the inner wall of the borehole. After the construction meets the standards, place a microchip capsule (20) wrapped in a soluble metal shell (30) into the borehole, then install a hole sealer (7) and a liquid injection steel pipe (6), use a conversion joint (4) to connect the two ends of the high-pressure hose (5) to the liquid injection steel pipe (6) and the pressure gauge (3), respectively, and then connect the liquid pump (1), the stop valve (2) and the pressure gauge (3) in sequence; S3, start the liquid pump (1) to pump in the sealing mucus, so that the sealing device (7) expands and seals the drilled hole. At the same time, when the liquid pressure in the liquid injection steel pipe (6) exceeds the minimum pressure of the one-way valve, the mucus flows out of the one-way valve, fills and seals the space between the two sealing devices (7) (the sealing device (7) seals the liquid, and the sealing mucus seals the gas); S4, after the sealing is completed, the microchip capsule (20) wrapped with a soluble metal shell (30) in the sealing hole will automatically record the gas pressure. When the original gas pressure measurement is completed, the sealing device is removed, and water is injected into the borehole until the water level is close to the ground height of the tunnel; S5. After the soluble metal shell (30) is completely dissolved, the microchip capsule (20) will float to the water surface due to its own density being less than that of water. The microchip capsule (20) on the water surface is recovered and the data stored in the microchip is read using a dedicated device to complete the measurement of the original gas pressure of the coal seam drilled deep vertically downward.

8. The method for using the device for in-situ detection of stratum temperature and pressure data at the bottom of a mine borehole as claimed in claim 5, characterized in that: The application steps of the microchip in the long-distance directional drilling hydraulic fracturing process include: S1, using a drilling rig to drill a directional borehole upward in a rock tunnel (9) to a target coal seam (10), and installing a hole sealer (7) in a horizontal section; S2. After drilling, clean and inspect the inner wall of the borehole. After the construction meets the standards, install the bottom hole fracturing tool in the following order from the bottom of the hole to the hole mouth: hole sealer (7), one-way valve group (13), microchip loading section (8), hole sealer (7), liquid injection steel pipe (6). Use the conversion joint (4) to connect the two ends of the high-pressure hose (5) to the liquid injection steel pipe (6) and the pressure gauge (3), respectively. Then, connect the liquid pump (1), the stop valve (2) and the pressure gauge (3) in sequence. S3, starting the liquid pump (1) and pumping fracturing fluid into the liquid injection steel pipe (6), so that the two hole sealers (7) expand simultaneously to seal the borehole. After the hole sealing is completed, the fracturing fluid is continuously pumped in. When the fracturing fluid pressure in the liquid injection steel pipe (6) is greater than the minimum opening pressure of the one-way valve group (13), the fracturing fluid begins to flow into the coal seam (10) to be fractured, and the microchip in the microchip loading section (8) automatically records the fracturing fluid pressure. S4. After the hydraulic fracturing is completed, the microchip loading section (8) is removed and the microchip is taken out. The data stored in the microchip is read using a dedicated device to complete the pressure and temperature measurement during the long-distance directional drilling hydraulic fracturing process.