Deep broken ore body high-strength isolation layer-side wall cast-in-place pile group-anchor cable net space bearing structure construction method

By building high-strength reinforced concrete isolation layer and side-spray cast pile group in deep mines, forming an anchor cable net, and through grouting reinforcement, the problems of side-spray stability and large-span mining of broken ore bodies in deep mines are solved, and the problems of side-spray stability and large-span mining of broken ore bodies in deep mines are improved. Mining efficiency and safety reduce costs.

CN118933867AActive Publication Date: 2024-11-12CHINA MINMETALS CHANGSHA MINING RES INST
View PDF 12 Cites 0 Cited by

Patent Information

Application Number
CN202411076473.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-07
Publication Date
2024-11-12
Estimated Expiration
2044-08-07

AI Technical Summary

Technical Problem

The prior art is difficult to effectively control the side stability of crushed ore bodies in deep mines and efficient mining over large spans, resulting in low mining efficiency and high cost.

Method used

The high-strength isolation layer of deep crushed ore body-sided cast pile group-anchored cable net space bearing structure construction method is adopted. By dividing the ore body before mining, high-strength reinforced concrete isolation layer and sided cast pile group are constructed to form interlaced Anchor cable net and reinforced by grouting to stabilize the side aid.

Benefits of technology

It improves mining efficiency, reduces mining costs, ensures the stability of the mining side, increases the length and height of the mining site, increases the structural parameters of the mining site, and realizes safe and efficient mining of crushed ore bodies.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933867A_ABST
    Figure CN118933867A_ABST
Patent Text Reader

Abstract

The invention provides a deep broken ore body high-strength isolation layer-side wall cast-in-place pile group-anchor cable net space bearing structure construction method, and relates to the technical field of underground mine mining. Firstly, an ore body is divided into an upper ore body and a lower ore body. A high-strength reinforced concrete isolation layer is constructed in the upper ore body in a route construction mode, and after construction is completed, a lateral wall cast-in-place pile group of the lower ore body is constructed. According to the method, on one hand, a high-strength reinforced concrete isolation layer is constructed by using an access mining method in cooperation with anchor cable-reinforcing mesh supporting according to the mining condition of deep ore rock crushing; and on the other hand, side wall cast-in-place pile groups of broken surrounding rocks and ore bodies are used. After the whole high-strength isolation layer-side wall cast-in-place pile group-anchor cable net space bearing structure is constructed, the anchor cables in the two directions are mutually staggered to form an anchor cable net, unstable rock stratums on the side wall of the stope are woven into a whole through grouting, and finally grouting reinforcement is conducted through grouting holes, the whole anchor cable net is fixed, and the side wall is kept stable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of underground mining technology, and in particular to a method for constructing a spatial bearing structure of a deep broken ore body high-strength isolation layer-side wall cast-in-place pile group-anchor cable net, which is applied to the reconstruction of the mining environment during the mining of broken ore and rock. Background Art

[0002] With the continuous exploitation of mineral resources, resource development at home and abroad has advanced into deep areas. As the depth of the ore body increases, the characteristics of high geotemperature, high geostress, high osmotic pressure and susceptibility to disturbance become apparent, marking that the exploitation of mineral resources has entered another stage and will face many technical difficulties in mining. In addition, if the surrounding rock or ore body is broken, the difficulty of mining will be greatly increased.

[0003] In the prior art, the invention patent with the patent application number CN201210076204.4 and the name “Induced Collapse Mining Method under Artificial False Roof” discloses a mining method under artificial false bottom, which directly installs 1-2 layers of steel pipe piles on the steeply inclined mining site roof and reinforces the roof with grouting, or directly cements reinforced concrete to replace the ore body, forming an artificial false roof, and then gradually pulls the bottom along the direction of the mining site, and gradually cuts off the connection between the ore body and the upper plate and the lower plate by deep hole pre-splitting blasting, inducing the ore body to fall naturally, and preventing the mining site ore body from surging through one or more middle sections of the upper part during the falling process, thereby protecting the upper waterproof layer from damage. However, this technical solution does not involve the reinforcement of the side walls of the mining site, so it is not beneficial to increase the length of the mining site. In addition, the artificial false roof solution cannot achieve the effect of long-term stable control of the mining site roof, and cannot form a stable mining space to prepare for filling.

[0004] The invention patent with the patent application number CN202210694904.3 and the name of “Artificial False Bottom and Manufacturing Method of Thin Vein Mining Field” discloses an artificial false bottom of thin vein mining field. The artificial false bottom is arranged in the mining tunnel, including an internal structure and a functional filling body filled in the internal structure; the artificial false bottom is fixed in the tunnel surrounding rock by a connector and is integrated with the tunnel surrounding rock. The internal structure includes an upper steel mesh, a lower steel mesh and a composite beam arranged between the upper steel mesh and the lower steel mesh; the functional filling body is composed of foam concrete and toughened polypropylene synthetic fiber. The artificial false bottom replaces the top and bottom pillars of the mining field of thin veins, and there is no need to reserve it during the mining process, thus avoiding the recycling of the artificial false bottom in the later stage. However, this technical solution also does not solve the problem of stability control of the side walls of the broken ore body. At the same time, this technical solution is mainly aimed at small-span mining fields with thin ore veins, and cannot achieve large-span and efficient mining of broken ore bodies.

[0005] Therefore, designing a method for constructing a spatial bearing structure of a deep broken ore body with high-strength isolation layer-side cast-in-place pile group-anchor cable net is of great significance to ensure the safe and efficient mining of broken ore bodies in deep mines. Summary of the invention

[0006] In view of the current problems of difficult mining, low safety and low efficiency in broken ore bodies in deep mines, the present invention provides a method for constructing a spatial bearing structure of a high-strength isolation layer-side wall cast-in-place pile group-anchor net for deep broken ore bodies, so as to improve the mining efficiency of deep broken ore bodies, reduce mining costs and achieve safe and efficient mining.

[0007] The present invention provides a method for constructing a deep broken ore body high-strength isolation layer-side cast-in-place pile group-anchor cable net space bearing structure, comprising the following steps:

[0008] S1, before mining the deep crushed ore body, the ore body is divided into the upper ore body and the lower ore body;

[0009] The lower ore body is divided into a first-step ore room and a second-step ore pillar. The first-step ore room is as high as the lower ore body and is 6-8m wide. The second-step ore pillar is as high as the lower ore body and is 8-12m wide. The first-step ore room and the second-step ore pillar are alternately spaced, and the first-step ore room is mined first, and then the second-step ore pillar is mined.

[0010] S2, constructing a high-strength reinforced concrete isolation layer in the upper ore body by means of access construction, the access direction being perpendicular to the direction of the stope; the high-strength reinforced concrete isolation layer is composed of a single-layer access and has a thickness of 2-2.5 m;

[0011] The upper ore body is divided into a one-step stope of the approach method and a two-step stope of the approach method, and mining is carried out in two steps; the one-step stope of the approach method and the two-step stope of the approach method are alternately mined one by one, and the one-step stope of the approach method is mined first, and then the two-step stope of the approach method is mined;

[0012] After the first step of the approach method is completed, the high-strength reinforced concrete isolation layer is constructed, and after the construction is completed, the second step of the approach method is carried out;

[0013] S3, after the mining is completed, a group of side cast-in-place piles of the lower ore body is constructed;

[0014] S31, corresponding to the boundary between the first-step ore room and the second-step ore pillar in the lower ore body, using a drilling rig to construct a left-slanted anchor cable hole, a right-slanted anchor cable hole and a grouting hole downward;

[0015] S32, construct the left oblique anchor cable, right oblique anchor cable and vertical anchor cable of the grouting pile respectively, and reinforce them by grouting;

[0016] S33, 15-20cm of crushed stone is laid on the floor of the stope, and the size of the crushed stone is controlled between 2-5cm;

[0017] S34, then lay the steel mesh, which is arranged at the bottom, top and two sides;

[0018] The main and secondary reinforcements of the two sides of the steel mesh are all made of 8-12mm diameter threaded steel bars, with a spacing of 0.2-0.3m. The intersection of the main and secondary reinforcements is tied firmly with iron wires with a diameter of 10-12mm. Then, 0.8-1.0m long and 18-22mm diameter connecting threaded steel bars are inserted into the horizontal connecting threaded steel holes and the inclined connecting threaded steel holes. The two sides of the steel mesh and the connecting threaded steel bars are tied tightly with iron wires with a diameter of 10-12mm to fix the steel mesh on the two sides;

[0019] The main reinforcement of the bottom reinforcement mesh is made of threaded steel with a diameter of 12-18mm, with a spacing of 0.4-0.7m, and the secondary reinforcement is made of threaded steel with a diameter of 8-12mm, with a spacing of 0.2-0.3m. The main reinforcement is at the bottom and the secondary reinforcement is at the top. The intersection of the main reinforcement and the secondary reinforcement is tied firmly with iron wire with a diameter of 10-12mm. The intersection of the bottom reinforcement mesh and the two connecting threaded steel bars is tied firmly with iron wire with a diameter of 10-12mm.

[0020] The laying of main reinforcement and secondary reinforcement of the top reinforcement mesh is consistent with that of the bottom reinforcement mesh;

[0021] S35, after the reinforcement is laid, a 0.3m-0.6m thick retaining wall is built at the entrance with hollow slag bricks or cement hollow bricks; a high-strength isolation layer artificial ceiling with side anchor cables is laid with concrete. The concrete meets the C25 level strength requirements. The width of the high-strength isolation layer artificial ceiling is 3-4m, the thickness is 2-2.5m, and the length direction needs to exceed the boundaries of the mining area at both ends by 2-3m.

[0022] As a further improvement of the present invention, the side support cast-in-place pile group includes 10-15 groups of left-slanted anchor cable holes, right-slanted anchor cable holes and grouting holes to form an anchor cable network that is staggered with each other.

[0023] As a further improvement of the present invention, the diameter of the left inclined anchor hole is 60-70mm, and the angle with the ground is 100°-110°; the diameter of the right inclined anchor hole is 60-70mm, and the angle with the ground is 70°-80°; the diameter of the grouting hole is 150-250mm and is drilled perpendicular to the ground.

[0024] As a further improvement of the present invention, the left inclined anchor cable hole, the right inclined anchor cable hole and the grouting hole are staggered by 0.3-0.5m front, back, left and right, and the anchor cables in the same direction are on the same plane.

[0025] As a further improvement of the present invention, in step S32, the construction process of the grouting pile is as follows: a disc locator is placed on the grouting hole and fixed, and then the prepared anchor cable is inserted into the anchor cable hole corresponding to the disc locator, and the anchor cable lowering speed is controlled until the anchor cable reaches the bottom of the hole, and this step is repeated until all the anchor cables are placed; then grouting is performed into the grouting hole until the slurry overflows, and the construction of the grouting pile is completed.

[0026] As a further improvement of the present invention, the disc locator includes a grouting hole arranged in the middle and a plurality of anchor holes arranged around the outer circumference of the grouting hole; and 4-8 anchor holes are arranged on the disc locator.

[0027] As a further improvement of the present invention, the size of the disc positioner is consistent with the size of the grouting hole.

[0028] As a further improvement of the present invention, the approach method one-step stope and the approach method two-step stope of the upper ore body are spatially cross-arranged with the approach method one-step mine room and two-step mine pillar of the lower ore body.

[0029] As a further improvement of the present invention, the spans of the first-step stope of the approach method and the second-step stope of the approach method are both 3 to 4 meters.

[0030] As a further improvement of the present invention, in step S2, constructing a high-strength reinforced concrete isolation layer includes the following steps: constructing vertically upward anchor cables on the top plate of the access road, the length of the anchor cables is 10-12m, the row spacing is 1.5-1.8m, the hole spacing is 1.5-1.8m, and the exposed section of the anchor cables is reserved for 2.5-3.0m; at 0.4-0.5m from the bottom plate on both sides of the access road, the horizontal connecting threaded steel drill holes are drilled every 0.8-1.2m, and the drilling depth is 0.5-1.0m; at 2.0-2.5m from the bottom plate on both sides of the access road, the inclined connecting threaded steel drill holes are drilled every 0.8-1.2m, the drilling depth is 0.5-1.0m, and the drilling inclination angle is 0-45°.

[0031] The beneficial effects of the present invention are:

[0032] 1. The method for constructing a spatial bearing structure of a high-strength isolation layer-side wall cast-in-place pile group-anchor cable net for a deep crushed ore body provided by the present invention, on the one hand, is aimed at the mining conditions of deep crushed ore rocks, using the approach mining method, coordinated with anchor cable-steel mesh support, to construct a high-strength reinforced concrete isolation layer; on the other hand, it is aimed at the side wall cast-in-place pile group of the crushed surrounding rock and ore body. After the construction of the entire high-strength isolation layer-side wall cast-in-place pile group-anchor cable net spatial bearing structure is completed, the anchor cables in two directions are interlaced to form an anchor cable net, and the unstable rock formations on the side wall of the mining site are "woven" into a whole through grouting, and finally the entire anchor cable net is fixed through grouting reinforcement through the grouting holes to keep the side wall stable.

[0033] Through the coordinated control of cast-in-place pile group and anchor cable net, the physical and mechanical properties of the side wall ore rock are improved, and its ability to resist damage is enhanced. Therefore, even if the length and height of the stope are increased and the exposed area of ​​the side wall is increased, the stability of the side wall of the stope can still be guaranteed. In other words, this side wall control technology ensures the stability of the side wall and provides a stable mining space environment; the exposed area of ​​the side wall is increased, and the length and height of the stope can be enlarged, thereby increasing the stope structural parameters and improving the stope production capacity, providing an engineering application scenario for the safe and efficient mining of broken ore bodies.

[0034] 2. The construction steps and process of the present invention are relatively simple, which can greatly reduce the construction period. Compared with the artificial false roof structure constructed by the double-layer approach method in the same period, it can save more than double the time, thereby achieving overall cost reduction; in addition, combined with the spatial bearing structure of the side wall cast-in-place pile group, efficient mining of medium and deep holes with large spans (10 to 12 meters), long distances (ore body thickness 35 to 40 meters), and large heights (35 to 40 meters) can be achieved. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 A schematic structural diagram of a high-strength isolation layer-side cast-in-place pile group-anchor cable net space bearing structure provided by the present invention;

[0036] Figure 2 For along Figure 1 Schematic diagram of the structure of the high-strength reinforced concrete isolation layer of the upper ore body of the middle AA line;

[0037] Figure 3 For along Figure 2 Side view of the high-strength reinforced concrete isolation layer of the middle BB line;

[0038] Figure 4 For along Figure 3 Top view of the bottom reinforcement mesh at the center CC line;

[0039] Figure 5 A schematic structural diagram of an implementation method of a disc positioner;

[0040] Figure 6 It is a structural schematic diagram of another implementation of the disc positioner. DETAILED DESCRIPTION

[0041] In order to make the purpose, technical solutions and advantages of the present invention more clear, the present invention is described in detail below with reference to the accompanying drawings and specific embodiments.

[0042] It should also be noted that, in order to avoid obscuring the present invention due to unnecessary details, only structures and / or processing steps closely related to the scheme of the present invention are shown in the drawings, while other details that are not closely related to the present invention are omitted.

[0043] In addition, it should be noted that the terms "comprises", "includes" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or apparatus that includes a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or apparatus.

[0044] See also Figures 1 to 6 As shown, the present invention provides a method for constructing a spatial bearing structure of a high-strength isolation layer-side cast-in-place pile group-anchor cable net in a deep broken ore body. The method uses the approach mining method and coordinated anchor cable-steel mesh support to construct a high-strength reinforced concrete isolation layer for the mining conditions of deep broken ore and rock. On the other hand, for the broken surrounding rock and the side cast-in-place pile group of the ore body, the method specifically includes the following steps:

[0045] S1, before mining the deep crushed ore body, the ore body is divided into upper ore body 1 and lower ore body 2;

[0046] The lower ore body 2 is divided into a first-step ore chamber 22 and a second-step ore pillar 23 .

[0047] The height of the first-step ore room 22 is the height of the lower ore body 2, and the width is 6-8m; the height of the second-step ore pillar 23 is the height of the lower ore body 2, and the width is 8-12m. The first-step ore room 22 and the second-step ore pillar 23 are alternately spaced, and the first-step ore room 22 is mined first, and then the second-step ore pillar 23 is mined.

[0048] S2, a high-strength reinforced concrete isolation layer 11 is constructed in the upper ore body 1 by means of access construction. The access direction is perpendicular to the mining field direction, and the access dimensions are 3 to 4 m wide and 3 to 4 m high.

[0049] The high-strength reinforced concrete isolation layer 11 consists of a single-layer approach with a thickness of 3 to 4 m;

[0050] In the single-layer approach, the upper ore body 1 is divided into the approach method first step stope 12 and the approach method second step stope 13, and the mining is carried out in two steps. The span of the approach method first step stope 12 and the approach method second step stope 13 are both 3 to 4 meters.

[0051] The first step stope 12 of the approach method and the second step stope 13 of the approach method are alternately spaced, and the approach method first step stope 12 is mined first, and then the second step stope 13 of the approach method is mined;

[0052] After the mining of the stope 12 in step one of the approach method is completed, a high-strength reinforced concrete isolation layer 11 is constructed. After the construction is completed, the mining of the stope 13 in step two of the approach method is carried out.

[0053] The approach method one-step stope 12 and the approach method two-step stope 13 of the upper ore body 1 and the approach method one-step mine room 22 and the two-step mine pillar 23 of the lower ore body 2 are spatially cross-arranged.

[0054] Specifically, in step S2, constructing a high-strength reinforced concrete isolation layer includes the following steps: constructing a vertically upward anchor cable 3 on the top plate of the access road, the length of the anchor cable 3 is 10-12m, the row spacing is 1.5-1.8m, the hole spacing is 1.5-1.8m, and the exposed section of the anchor cable 3 is reserved for 2.5-3.0m; at 0.4-0.5m from the bottom plate on both sides of the access road, horizontal connecting threaded steel drill holes are drilled every 0.8-1.2m, and the drilling depth is 0.5-1.0m; at 2.0-2.5m from the bottom plate on both sides of the access road, inclined connecting threaded steel drill holes are drilled every 0.8-1.2m, the drilling depth is 0.5-1.0m, and the drilling inclination angle is 0-45°, which is convenient for drilling.

[0055] S3, after the mining is completed, the side wall cast-in-place pile group 21 of the lower ore body 2 is constructed;

[0056] S31, use a scraper to clean up the ore, fallen waste rock and other debris remaining on the bottom plate of the mining area, and use a YGZ-90 shallow hole drilling machine to construct downward left inclined anchor cable holes 211, right inclined anchor cable holes 212 and grouting holes 213 corresponding to the boundary between the first step mine room 22 and the second step mine pillar 23 in the lower ore body 2; wherein, the side wall cast-in-place pile group 21 contains multiple groups of left inclined anchor cable holes 211, right inclined anchor cable holes 212 and grouting holes 213, forming an anchor cable network that intersects each other. Generally, there are 10-15 groups.

[0057] In this embodiment, the diameter of the left oblique anchor hole 211 is 60 mm, and the angle with the ground is 105°; the diameter of the right oblique anchor hole 212 is 60 mm, and the angle with the ground is 75°; the diameter of the grouting hole 213 is 150-250 mm, and it is set perpendicular to the ground. It should be understood that according to actual needs, the diameter of the left oblique anchor hole can range from 60-70 mm, and the angle with the ground can be 100°-110°; the diameter of the right oblique anchor hole can range from 60-70 mm, and the angle with the ground can be 70°-80°.

[0058] Preferably, to avoid damage between holes, the left oblique anchor hole 211, the right oblique anchor hole 212, and the grouting hole 213 are staggered 0.3-0.5m front and back, left and right. In addition, the anchors in the same direction are on the same plane to ensure the reinforcement effect of the side wall.

[0059] The disc locator 5 is placed at the mouth of the grouting hole 213 for positioning during the construction of the grouting pile anchor cable. The size of the disc locator 5 is consistent with the size of the grouting hole 213.

[0060] The disc positioner 5 includes a grouting hole 52 disposed in the middle and a plurality of anchor holes 51 disposed around the periphery of the grouting hole 52. Preferably, the disc positioner 5 can be provided with 4-8 anchor holes 51 according to the size of the grouting hole 213, so as to be applicable to ore bodies and surrounding rocks with different degrees of crushing.

[0061] S32, construct the left oblique anchor cable, right oblique anchor cable and vertical anchor cable of the grouting pile respectively, and reinforce them by grouting;

[0062] Specifically, in step S32, the construction process of the grouting pile is as follows: a disc locator 5 is placed on the grouting hole 213 and fixed, and then the prepared anchor cable is inserted into the anchor cable hole 51 corresponding to the disc locator 5, and the anchor cable lowering speed is controlled until the anchor cable reaches the bottom of the hole, and this step is repeated until all the anchor cables are placed; then grouting is performed into the grouting hole 52 until the slurry overflows to complete the construction of the grouting pile.

[0063] S33, 15-20cm of crushed stone 6 is laid on the bottom plate of the stope, and the size of the crushed stone 6 is controlled to be about 5cm, generally 2-5cm;

[0064] S34, then lay the steel mesh, which is arranged at the bottom, top and two sides;

[0065] The main and secondary reinforcements of the two sides of the steel mesh are all made of 8-12mm diameter threaded steel bars, with a spacing of 0.2-0.3m. The intersection of the main and secondary reinforcements is tied firmly with iron wires with a diameter of 10-12mm. Then, 0.8-1.0m long and 18-22mm diameter connecting threaded steel bars are inserted into the horizontal connecting threaded steel holes and the inclined connecting threaded steel holes. The two sides of the steel mesh and the connecting threaded steel bars are tied tightly with iron wires with a diameter of 10-12mm to fix the steel mesh on the two sides;

[0066] The main reinforcement 71 (transverse reinforcement) of the bottom reinforcement net is made of threaded steel with a diameter of 12-18mm, with a spacing of 0.4-0.7m, and the secondary reinforcement 72 (longitudinal reinforcement) is made of threaded steel with a diameter of 8-12mm, with a spacing of 0.2-0.3m. The main reinforcement 71 is at the bottom, and the secondary reinforcement 72 is at the top. The intersection of the main reinforcement 71 and the secondary reinforcement 72 is tied firmly with a wire with a diameter of 10-12mm. The intersection of the bottom reinforcement net and the two connecting threaded steel bars is tied firmly with a wire with a diameter of 10-12mm.

[0067] The laying of the main reinforcement 71 (transverse reinforcement) and the secondary reinforcement 72 (longitudinal reinforcement) of the top reinforcement net is consistent with that of the bottom reinforcement net;

[0068] S35, after the reinforcement is laid, a 0.3-0.6m thick retaining wall is built at the entrance with hollow slag bricks or cement hollow bricks; a high-strength isolation layer artificial ceiling with side anchor cables is laid with concrete. The concrete meets the C25 level strength requirements. The width of the high-strength isolation layer artificial ceiling is 3-4m, the thickness is 2-2.5m, and the length direction needs to exceed the boundaries of the mining area at both ends by 2-3m.

[0069] That is, after the mining of the mining area 12 in the first step of the approach method is completed, a high-strength reinforced concrete isolation layer 11 is constructed. After the construction is completed, the mining of the mining area in the second step of the approach method is carried out. After the mining is completed, the side wall cast-in-place pile group 21 of the lower ore body 2 is constructed according to steps S31-S35, thus completing the construction of the entire high-strength isolation layer-side wall cast-in-place pile group-anchor network space bearing structure.

[0070] With this arrangement, after the construction of the entire high-strength isolation layer-side wall cast-in-place pile group-anchor net space bearing structure is completed, the anchor cables in two directions are intertwined to form an anchor net. The unstable rock formation on the side wall of the mining area is "woven" into a whole through grouting, and finally grouting is reinforced through the grouting holes to fix the entire anchor net and keep the side wall stable.

[0071] In summary, the present invention provides a method for constructing a spatial bearing structure of a high-strength isolation layer-side wall cast-in-place pile group-anchor cable net for a deep crushed ore body. On the one hand, it is aimed at the mining conditions of deep rock crushing, using the approach mining method, coordinated with anchor cable-steel mesh support, to construct a high-strength reinforced concrete isolation layer; on the other hand, it is aimed at the side wall cast-in-place pile group of the crushed surrounding rock and ore body. Through the coordinated control of the cast-in-place pile group-anchor cable net, the stability of the side wall is guaranteed, the exposed area of ​​the side wall is increased, the length and height of the mining area can be enlarged, thereby increasing the mining area structural parameters, improving the mining area production capacity, and providing an engineering application scenario for realizing safe and efficient mining of crushed ore bodies.

[0072] The above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solution of the present invention.

Claims

1. A method for constructing a spatial bearing structure of a deep broken ore body with high-strength isolation layer, side cast-in-place pile group and anchor cable net, characterized in that: The steps include: S1, before mining the deep crushed ore body, the ore body is divided into the upper ore body and the lower ore body; The lower ore body is divided into a first-step ore room and a second-step ore pillar. The first-step ore room is as high as the lower ore body and is 6-8m wide. The second-step ore pillar is as high as the lower ore body and is 8-12m wide. The first-step ore room and the second-step ore pillar are alternately spaced, and the first-step ore room is mined first, and then the second-step ore pillar is mined. S2, constructing a high-strength reinforced concrete isolation layer in the upper ore body by means of access construction, the access direction being perpendicular to the direction of the stope; the high-strength reinforced concrete isolation layer is composed of a single-layer access and has a thickness of 2-2.5 m; The upper ore body is divided into a one-step stope of the approach method and a two-step stope of the approach method, and mining is carried out in two steps; the one-step stope of the approach method and the two-step stope of the approach method are alternately mined one by one, and the one-step stope of the approach method is mined first, and then the two-step stope of the approach method is mined; After the first step of the approach method is completed, the high-strength reinforced concrete isolation layer is constructed, and after the construction is completed, the second step of the approach method is carried out; S3, after the mining is completed, a group of side cast-in-place piles of the lower ore body is constructed; S31, corresponding to the boundary between the first-step ore room and the second-step ore pillar in the lower ore body, using a drilling rig to construct a left-slanted anchor hole, a right-slanted anchor hole and a grouting hole downward; S32, construct the left oblique anchor cable, right oblique anchor cable and vertical anchor cable of the grouting pile respectively, and reinforce them by grouting; S33, 15-20cm of crushed stone is laid on the floor of the stope, and the size of the crushed stone is controlled between 2-5cm; S34, then lay the steel mesh, which is arranged at the bottom, top and two sides; The main and secondary reinforcements of the two sides of the steel mesh are all made of threaded steel with a diameter of 8-12mm, with a spacing of 0.2-0.3m. The intersection of the main and secondary reinforcements is tied firmly with wire. Then, 0.8-1.0m long and 18-22mm in diameter connecting threaded steel are inserted into the horizontal connecting threaded steel drill holes and the inclined connecting threaded steel drill holes. The two sides of the steel mesh and the connecting threaded steel are tied tightly with wire to fix the steel mesh to the two sides; The main reinforcement of the bottom reinforcement mesh is made of threaded steel with a diameter of 12-18mm, with a spacing of 0.4-0.7m, and the secondary reinforcement is made of threaded steel with a diameter of 8-12mm, with a spacing of 0.2-0.3m. The main reinforcement is at the bottom and the secondary reinforcement is at the top. The intersection of the main and secondary reinforcements is tied firmly with wire, and the intersection of the bottom reinforcement mesh and the two sides of the threaded steel is tied firmly with wire; The laying of main reinforcement and secondary reinforcement of the top reinforcement mesh is consistent with that of the bottom reinforcement mesh; S35, after the reinforcement is laid, a retaining wall is built at the entrance with hollow slag bricks or cement hollow bricks; a high-strength isolation layer artificial ceiling with side anchor cables is laid with concrete. The concrete meets the C25 level strength requirements. The width of the high-strength isolation layer artificial ceiling is 3-4m, the thickness is 2-2.5m, and the length direction needs to exceed the boundaries of the mining area at both ends by 2-3m.

2. The method for constructing a deep broken ore body high-strength isolation layer-side cast-in-place pile group-anchor cable net space bearing structure according to claim 1, characterized in that: The side support cast-in-place pile group includes 10-15 groups of left-slanted anchor cable holes, right-slanted anchor cable holes and grouting holes, forming an anchor cable network that is staggered with each other.

3. The method for constructing a deep broken ore body high-strength isolation layer-side cast-in-place pile group-anchor cable net space bearing structure according to claim 1, characterized in that: The diameter of the left inclined anchor hole is 60-70mm, and the angle with the ground is 100°-110°; the diameter of the right inclined anchor hole is 60-70mm, and the angle with the ground is 70°-80°; the diameter of the grouting hole is 150-250mm, and it is drilled perpendicular to the ground.

4. The method for constructing a deep broken ore body high-strength isolation layer-side cast-in-place pile group-anchor cable net space bearing structure according to claim 3 is characterized in that: The left inclined anchor cable hole, the right inclined anchor cable hole and the grouting hole are staggered 0.3-0.5m front, back, left and right.

5. The method for constructing a deep broken ore body high-strength isolation layer-side cast-in-place pile group-anchor cable net space bearing structure according to claim 1, characterized in that: In step S32, the construction process of the grouting pile is as follows: a disc locator is placed on the grouting hole and fixed, and then the prepared anchor cable is inserted into the anchor cable hole corresponding to the disc locator, and the anchor cable lowering speed is controlled until the anchor cable reaches the bottom of the hole, and this step is repeated until all the anchor cables are placed; then grouting is performed into the grouting hole until the slurry overflows to complete the construction of the grouting pile.

6. The method for constructing a deep broken ore body high-strength isolation layer-side cast-in-place pile group-anchor cable net space bearing structure according to claim 5, characterized in that: The disc positioner comprises a grouting hole arranged in the middle and a plurality of anchor holes arranged around the outer circumference of the grouting hole; and 4-8 anchor holes are arranged on the disc positioner.

7. The method for constructing a deep broken ore body high-strength isolation layer-side cast-in-place pile group-anchor cable net space bearing structure according to claim 5, characterized in that: The size of the disc positioner is consistent with the size of the grouting hole.

8. The method for constructing a deep broken ore body high-strength isolation layer-side cast-in-place pile group-anchor cable net space bearing structure according to claim 1, characterized in that: The approach method one-step stope and the approach method two-step stope of the upper ore body are spatially cross-arranged with the approach of the one-step mine room and the two-step mine pillar of the lower ore body.

9. The method for constructing a deep broken ore body high-strength isolation layer-side cast-in-place pile group-anchor cable net space bearing structure according to claim 1, characterized in that: The spans of the first-step stope of the approach method and the second-step stope of the approach method are both 3 to 4 meters.

10. The method for constructing a deep broken ore body high-strength isolation layer-side cast-in-place pile group-anchor cable net space bearing structure according to claim 1, characterized in that: In step S2, constructing a high-strength reinforced concrete isolation layer includes the following steps: constructing vertically upward anchor cables on the top plate of the access road, the length of the anchor cables is 10-12m, the row spacing is 1.5-1.8m, the hole spacing is 1.5-1.8m, and the exposed section of the anchor cables is reserved for 2.5-3.0m; drilling the horizontally connected threaded steel drill holes every 0.8-1.2m at 0.4-0.5m from the bottom plate on both sides of the access road, and the drilling depth is 0.5-1.0m; drilling the inclined connected threaded steel drill holes every 0.8-1.2m at 2.0-2.5m from the bottom plate on both sides of the access road, and the drilling depth is 0.5-1.0m, and the drilling inclination angle is 0-45°.

Citation Information

Patent Citations

  • Induction caving mining method under artificial false roof

    CN102587915A

  • Artificial false bottom of thin vein stope and manufacturing method of artificial false bottom

    CN114776373A

  • Integral reinforcement method for hanging wall broken surrounding rock long anchor cables

    CN112664194A

  • Pre-control roof filling mining method suitable for close-to-thick and large quaternary system lower broken ore body

    CN114607380A

  • Non-explosive mechanical rock breaking circulating drift filling mining method

    CN114704256A