Road-occupation-free construction method for secondary lining construction of single-track railway tunnel
By changing the trolley reinforcement plan and setting up a concrete pouring pumping station, the problem of low construction efficiency in the construction of the second lining of a single-line railway tunnel is solved, and rapid construction and efficient production are achieved.
Patent Information
- Application Number
- CN202411190423.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-28
- Publication Date
- 2024-11-12
AI Technical Summary
During the construction of the second lining of a single-line railway tunnel, the reinforcement support system of the trolley formwork and the concrete conveying pump and other equipment occupied insufficient construction space, resulting in low construction efficiency and increased time and capital costs.
By changing the trolley reinforcement plan, the temporary cross braces between the two longitudinal beams at the bottom of the trolley were cancelled, oblique braces and tie rods were set up to reinforce the trolley, and a concrete pouring pumping station was arranged at a fixed spacing in the tunnel, and the shunting hole was used as a pumping station. , reduce the impact on construction channels.
It has achieved the failure to occupy the main transportation road during the second lining casting process, improved construction efficiency, reduced the impact on the construction of the palm surface, shortened the construction period, and improved production efficiency and equipment utilization.
Smart Images

Figure CN118933882A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of tunnel construction and relates to a method for constructing a secondary lining of a single-track railway tunnel without occupying the road. Background Art
[0002] Due to the small cross-sectional clearance of single-track railway tunnels, during the pouring of secondary lining concrete, the trolley formwork reinforcement support system, concrete pumps, and concrete transport vehicles often occupy limited construction space. This separates the mechanical equipment and transport vehicles required for construction between the tunnel face and the secondary lining trolley outside the lining trolley and the tunnel face, seriously affecting the construction process between the secondary lining and the tunnel face, reducing the utilization rate of personnel and machinery, and increasing time and financial costs. Summary of the Invention
[0003] The technical problem to be solved by the present invention is to provide a construction method for the secondary lining construction of a single-track railway tunnel without occupying the road, which can solve the problem of low construction efficiency caused by the occupation of the road during the secondary lining concrete construction.
[0004] The technical solution adopted by the present invention is: a non-roadside construction method for the secondary lining construction of a single-track railway tunnel, which is: according to the force system of the secondary lining pouring working condition, by changing the trolley reinforcement scheme, the temporary cross brace between the two longitudinal beams at the bottom of the trolley is cancelled, and the trolley is reinforced by setting diagonal braces between the bottom edge of the formwork and the filling surface, and setting tie rods in the cavity formed between the holes set in the bottom formwork of the trolley and the top of the cast small side wall; the diagonal braces and tie rods are arranged at fixed intervals in a set number along the length direction of both sides of the trolley, and the concrete pouring pumping stations used during pouring are arranged at fixed intervals in the tunnel.
[0005] A method for constructing a secondary lining in a single-track railway tunnel without occupying the road comprises the following specific steps: Step 1: Drill holes and plant reinforcement bars at the top of the small side wall according to the measurement points to obtain temporary anchoring steel bars. Connect the 5mm steel plate and temporary anchoring steel bars through the holes reserved in the bottom formwork of the trolley and fit them to the top of the small side wall. Step 2: Set diagonal braces on both sides of the bottom mold of the trolley. The diagonal braces use screw jacks. The top of the screw jacks is connected to the side molds and located at the template seam of the side molds. The bottom of the screw jacks is retracted to the edge of the filling surface; Step 3: Use the small shelter tunnel to expand into a shunting tunnel. When pouring the secondary lining, use the nearest shunting tunnel as a concrete pouring pumping station and place the delivery pump in the tunnel chamber of the shunting tunnel; Step 4: Configure the pumping pipe according to the distance between the shunting tunnel and the lining trolley; Step 5. The shunting holes near the working face and the secondary lining should be managed more strictly. That is, the shunting holes near the working face are used for vehicles to wait and give way, and the shunting holes near the secondary lining are used for pouring the secondary lining.
[0006] Furthermore, in the above step one, the anchor steel bar hole at the top of the small side wall is 20cm deep and 22mm in diameter; φ22 threaded steel temporary anchor steel bars are installed, buried 20cm in the concrete and exposed 20cm, and a horizontal external tie rod anchor plate is added to the bottom of the secondary lining trolley longitudinal beam. A square groove that can be adjusted up and down is set in the middle of the anchor plate to facilitate the installation of the tie rod; the tie rod includes a fixed plate and a temporary plate. The fixed plate includes φ25 fine-rolled threaded steel and a 5mm steel plate fixedly connected to it. The temporary plate is a 5mm steel plate. The fixed plate and the temporary plate are connected by bolts. After the secondary lining is poured, the temporary plate is used as a loss, and the fixed plate can be reused. The longitudinal spacing is 1.5m, distributed at the bottom of the longitudinal beams on both sides of the trolley. The size (height) of the horizontal external tie rod anchor plate should be able to meet the setting of all lining types undertaken by the secondary lining trolley to avoid multiple investments. The tie rod end should be effectively connected to the embedded steel bars or secondary lining steel bars and anchor bars.
[0007] Furthermore, in the above step 2, screw jacks are set on both sides of the bottom form of the trolley to support the connection between the top and the side form. The position is located at the template seam (the template seams are reinforced) with an angle of about 30°. The bottom of the diagonal support is retracted to the filling edge without affecting driving. The diagonal support is set at a spacing of 1.5m, with a total of 7 sets. The purpose of reinforcing the bottom form is achieved by rotating the screw jack.
[0008] Furthermore, in the above step three, the small avoidance tunnel is expanded into a shunting tunnel with a spacing of 120m / tunnel. When the second lining is poured, the nearest shunting tunnel is used as a pumping station, and the delivery pump is placed in the tunnel to work. The size of the shunting tunnel is 5.6m high, 9m wide and 8.5m deep.
[0009] Furthermore, in the above step 4, the pumping pipe is installed against the edge of the channel; the vehicle-mounted pump is placed in the concrete pumping station and tested with pipeline lubricant. If there is any fault, it is repaired in time. Before concrete mixing, check whether the raw materials meet the specifications, measure the moisture content of sand and gravel, and prepare the construction mix ratio according to the length of the on-site pumping pipe. Before leaving the station, the experimenter checks the slump of the concrete, which is 160mm~200mm according to the length of the pumping pipe. The slump is measured again after the concrete arrives at the site. If it does not meet the requirements, it will be returned to the factory for processing.
[0010] Beneficial effects of the present invention: Compared with the prior art, the present invention changes the trolley reinforcement scheme according to the stress system of the secondary lining pouring working condition, cancels the temporary horizontal brace between the two longitudinal beams at the bottom of the trolley, and reinforces the trolley by setting an oblique brace between the bottom edge of the formwork and the filling surface, and setting a tie rod between the trolley formwork and the poured small side wall concrete; a certain concrete pouring pumping station (integrated tunnel) is set at a fixed interval to exchange space for time, thereby solving the problem of occupying the main transportation road during the secondary lining pouring, so as to ensure that during the entire process of the secondary lining pouring, each process from the secondary lining to the face can be constructed normally, and the vehicle transportation channel will not be occupied due to the secondary lining pouring This technology significantly impacts tunnel construction schedules, ensuring that lining concrete pouring does not affect face construction, achieving the goal of rapid single-track tunnel construction. Conventional secondary lining pouring processes require an average of 15 hours of road occupation (3 hours for support, pipe installation, and pump placement to achieve pouring conditions; 10 hours for concrete pouring; and 2 hours for support, pipe removal, and pump removal). Within these 15 hours of road occupation, process planning, face support (with scaffolding, anchors, and mesh) and subsequent blasthole construction can eliminate at least 5 hours of road occupation. Each secondary lining bin poured affects face construction by 10 hours. This technology reduces this impact by 10 hours. Based on an average of eight bins per month for a single secondary lining, this reduces the impact on face construction by 80 hours per month, equivalent to 3.3 days. This technology allows for an additional 15 meters of Grade III surrounding rock, 9 meters of Grade IV surrounding rock, and 6 meters of Grade V surrounding rock to be completed each month, significantly improving per capita productivity and reducing losses. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 This is a three-dimensional schematic diagram of the secondary lining construction trolley for a single-track railway tunnel; Figure 2 This is a front view structural diagram of the secondary lining construction trolley for a single-track railway tunnel; Figure 3 for Figure 2 A schematic diagram of the enlarged structure of the middle part A; Figure 4 This is a schematic diagram of the vault structure; Figure 5 This is a left-side structural diagram of a secondary lining construction trolley for a single-track railway tunnel; Figure 6 for Figure 5 Schematic diagram of the BB cross-section structure; Figure 7 for Figure 2 Schematic diagram of the CC cross-section structure; Figure 8 for Figure 7 Schematic diagram of the DD cross-section structure; Figure 9 for Figure 7 Schematic diagram of the EE cross-section structure; Figure 10 for Figure 9Partial schematic diagram of the middle vault structure; Figure 11 This is a schematic diagram of the front structure of the trolley before widening; Figure 12 This is a schematic diagram of the vault structure before widening; Figure 13 This is a schematic diagram of the three-dimensional structure of the door platform; Figure 14 Schematic diagram of the three-dimensional structure of the column; Figure 15 It is a schematic diagram of the rear view structure of the column; Figure 16 for Figure 15 Schematic diagram of the AA section structure; Figure 17 It is a schematic diagram of the structure of the column from the right side; Figure 18 for Figure 17 Schematic diagram of the BB cross-section structure; Figure 19 This is a stress analysis diagram of the bottom longitudinal beam of the secondary lining trolley. In the figure, F1 represents the concrete extrusion force and the vibrating pushing force; F2 represents the deadweight of the side formwork. Figure 20 This is the support additional force state analysis diagram; in the figure, F 1-1 Additional force of bottom diagonal support; F 2-1 Horizontal external pull additional force; Figure 21 It is a construction flow chart; Figure 22 This is a front view structural diagram of the auxiliary assembly suspension device for the secondary lining trolley frame of a single-track tunnel; Figure 23 This is a front view structural diagram of the auxiliary assembly suspension device for the secondary lining trolley frame of a single-track tunnel (after the installation of the traveling trolley); Figure 24 This is a schematic diagram of the right-side installation structure of the auxiliary assembly suspension device for the secondary lining trolley frame of a single-track tunnel. DETAILED DESCRIPTION
[0012] The present invention will be further described below with reference to the accompanying drawings and specific embodiments.
[0013] Example 1: Figures 1 to 24 As shown, a method for constructing a secondary lining of a single-track railway tunnel without occupying the road is provided, the method comprising the following steps: Step 1: Ensure the delivery and acceptance of materials required for the trolley formwork reinforcement system, conduct quality inspection of the pumping pipeline, conduct trial operation of the on-board pump, and conduct system training and learning preparation for operators.
[0014] Step 2: Measure and stake out, position the lining trolley, and measure the clearance dimensions of the initial support section to ensure that the section dimensions meet the design requirements. Measure the embedded positions of the fixed-point temporary horizontal tie rod anchor reinforcements.
[0015] Step 3: Installation of temporary anchor steel bars. According to the measurement points, use a handheld electric drill to drill temporary anchor steel bar holes at the top of the small side wall. The depth is 20 cm and the drill hole diameter is 22 mm. Install φ22 threaded steel temporary anchor steel bars, bury them 20 cm into the concrete, and expose 20 cm.
[0016] Step 4: Install the external pulling device. Connect the 5mm steel plate with the temporary anchor steel bar through the reserved holes in the bottom formwork of the trolley. Use φ25 high-quality rolled threaded steel bar to bolt the horizontal external pull rod anchor plate at the bottom of the secondary lining trolley longitudinal beam to the 5mm steel plate at the end of the temporary anchor steel bar. The longitudinal spacing is 1.5m and is distributed at the bottom of the longitudinal beams on both sides of the trolley.
[0017] Step 5: Reinforce the trolley and formwork. Screw jacks are set on both sides of the trolley bottom formwork with a longitudinal spacing of 1.5m. The length is adjusted according to the effective traffic clearance size. The top of the screw jack is connected to the side touch and is located at the template seam. The bottom is retracted to the edge of the filling surface. The purpose of reinforcing the bottom formwork is achieved by rotating the screw jack. The screw jacks configured on the bottom longitudinal beams on both sides of the trolley are adjusted. The bottom of the screw jack is in close contact with the walking rails. Relying on the gravity of the trolley and the friction between the rails and the screw jacks, the purpose of braking the lining trolley is achieved.
[0018] Step 6: Debug and confirm the pumping pipe and vehicle-mounted pump. Prepare the pumping pipe according to the distance between the shunting tunnel and the lining trolley. The shunting tunnel and concrete pumping station are set up at a spacing of 120m. The concrete pumping distance is controlled at 10 to 60m. The pumping pipe is installed close to the edge of the channel. The vehicle-mounted pump is placed in the concrete pumping station and tested with pipeline lubricant. If there is any fault, it should be repaired in time.
[0019] Step 7: Concrete preparation. Before concrete preparation, check whether the raw materials meet the specifications, measure the moisture content of the sand and gravel, and prepare the construction mix ratio according to the length of the on-site pumping pipeline. Before leaving the station, the tester checks the slump of the concrete. The slump should be 160mm to 200mm according to the length of the pumping pipeline to prevent concrete clogging. After the concrete arrives at the site, the slump is measured again. If it does not meet the requirements, it will be returned to the factory for processing.
[0020] Step 8: Concrete pouring. The concrete pouring should be strictly organized according to the principle of feeding window by window and left-right symmetry. The vertical layering should not be greater than 50cm. It should be vibrated and compacted in time. After pouring to the elevation of three windows, the concrete should be leveled, vibrated and the windows closed to pour the vault concrete.
[0021] Step 9: Cut off the tie rod and polish the appearance. During the concrete curing period, the remaining steel plate after the formwork pulling device is cut is manually cut and polished with a grinder to ensure a flawless appearance.
[0022] Using a truck-mounted pump instead of a ground pump solves problems such as long traction time, low pumping pressure, and low pumping efficiency. Truck-mounted pumps are suitable for construction on multiple working surfaces and offer flexible deployment. They can also serve as backup equipment if a pump failure prevents continuous concrete operation, resolving equipment failures quickly.
[0023] During the construction process, traffic controllers are deployed to direct and coordinate the construction vehicles and concrete pouring vehicles on the face to prevent traffic jams that affect the pouring speed and quality. The present invention is applicable to the secondary lining concrete construction of small-section tunnels, and the construction process features are as follows: (1) Low cost, strong applicability and operability.
[0024] (2) The trolley template reinforcement system is easy to operate and saves space.
[0025] (3) Space is exchanged for time, enabling parallel operation of the tunnel face and secondary lining in small-section tunnels.
[0026] The method of the present invention is simple to operate, highly efficient, low-cost, and provides guaranteed quality. Taking the Baoshan Tunnel on the Dali-Ruili Railway as an example, the conventional secondary lining pouring process requires an average of 15 hours of road occupation (3 hours for support, pipeline installation, and pump placement to achieve pouring conditions; 10 hours for concrete pouring; and 2 hours for support, pipeline removal, and pump removal). Within these 15 hours of road occupation, process planning is performed, and face support (with scaffolding, anchors, and mesh) and blastholes for the next blast are installed. This eliminates at least 5 hours of road occupation. Each second lining pouring bin affects face construction by 10 hours. Using this method, this 10-hour impact is reduced.
[0027] Based on an average of eight bins per month for a single secondary lining, this reduces the impact on face construction by 80 hours per month, equivalent to 3.3 days. This translates to an additional 15 meters of Grade III surrounding rock, 9 meters of Grade IV surrounding rock, and 6 meters of Grade V surrounding rock being completed each month, significantly improving per capita productivity and reducing losses.
[0028] The method of the present invention generates a total direct economic benefit of 6.18 million yuan, with significant economic benefits.
[0029] The single-track railway tunnel secondary lining construction trolley adopted in the above method includes a portal frame 1, a power walking mechanism 2, a diagonal brace 3 and a pull rod 4. Four power walking mechanisms 2 are installed at the four corners of the portal frame 1. The four power walking mechanisms 2 are placed on two tracks 5 in pairs. The two tracks 5 are fixedly connected to the grooves 7 on both sides of the filling surface 6. A cantilever beam 8 is provided at the bottom of the portal frame 1. The cantilever beam 8 is provided with a vertical strip hole 9, through which a pull rod 4 passes. The pull rod 4 is fixedly connected to the top of the precast side wall 10 at one end facing the tunnel side wall, and the other end passes through the vertical strip hole 9 and is fixedly connected by an anchor plate 11 and a nut 12. One end of the diagonal brace 3 rests on the inner side of the groove 7, and the other end rests on the template seam of the side form 13. Multiple diagonal braces 3 and pull rods 4 are arranged on both sides of the portal frame 1 along its length.
[0030] In order to achieve reuse, the outer end of the pull rod 4 is fixedly connected to a fixed plate 14, and the top of the side wall 10 is fixedly connected to a temporary plate 22 through a temporary anchoring steel bar 15. The fixed plate 14 and the temporary plate 22 are fixedly connected by bolts. This structure is easy to install, the connection is stable and reliable, and it can be reused after disassembly.
[0031] In order to improve the stability of the door frame, the door frame 1 includes multiple door frames 101 and bottom longitudinal beams 102. The two free ends at the bottom of the multiple door frames 101 are fixedly connected to the two bottom longitudinal beams 102 and are evenly arranged along the length direction of the bottom longitudinal beams 102. Multiple upper longitudinal beams 103 are fixedly connected between two adjacent door frames 101. Each door frame 101 includes a top crossbeam 104 and a column 105. The two ends of the top crossbeam 104 are fixedly connected to two columns 105 at the bottom. Each column 105 is an arc-shaped column. The arc-shaped columns are provided to increase the passing space under the door frame while improving the rigidity and strength, thereby increasing the width of the vehicle passing. Each column 105 includes a side panel 124, an inner arc panel 125 and an outer arc panel 126. Two side panels 124 are symmetrically fixedly connected between the inner arc panel 125 and the outer arc panel 126 to form a wide top and narrow bottom. Empty tube structure, the upper and lower ends of the empty tube structure are respectively fixedly connected with an upper closed flange plate 127 and a lower closed flange plate 128, and a reinforcement plate 129 is fixedly connected between the two side plates 124. The outer arc plate 126 is provided with an opening 130 for inserting a hydraulic jack for supporting the side formwork. The hydraulic jack is movably inserted into the opening and hinged to the column 105. A reinforcement sub-plate 131 is arranged on the outside of the hinge hole to facilitate the installation of the hydraulic jack, and the hinge is located inside to improve the support stability. The radius of the outer arc plate 126 is 12012000mm, and the inner arc plate 126 includes an arc segment plate 132 and a straight segment plate 133 from top to bottom. The two columns 105 of adjacent door frames 101 are fixedly connected by a fork-type scissors support 122, which can provide stability for the door platform. Cantilever beams 123 are installed at the front and rear ends of the door platform 1. The cantilever beams are convenient for installing ladders and operating platforms.
[0032] In order to adapt to the lining width of different secondary linings of a single tunnel, an arch structure is installed above the top crossbeam 104. The arch structure is a structure with variable transverse length, including a left section top arch 106 and a right section top arch 107. A detachable widening hydraulic cylinder 108 is hinged between the left section top arch 106 and the right section top arch 107 and the top crossbeam 104. A detachable intermediate arch widening crossbeam 109 is fixedly connected between the left section top arch 106 and the right section top arch 107. 107 rests against the middle section and both side sections of the top crossbeam 104. When in use, the widening hydraulic cylinder is installed. By loosening the central joints of the left and right sections of all the arch structures, the widening hydraulic cylinder is controlled to open the left and right halves of the arch structure. After reaching the set width, the middle arch widening crossbeam is installed to complete the widening operation. The widening hydraulic cylinder and the bottom formwork are removed and opened and supported by controlling the length of the hydraulic cylinder. The widened second lining trolley can adapt to the use of the new widening formwork, which is more convenient for adapting to the processing of different variable cross-sections in a single tunnel, and the cost is greatly reduced.
[0033] In order to facilitate the support stability of the trolley during walking and use, the bottom of the above-mentioned bottom longitudinal beam 102 is abutted with a screw jack 16, and the lower end of the screw jack 16 abuts on the door-shaped base 17. The door-shaped base 17 spans the track 5 and is placed in the groove 6. There are multiple screw jacks 16, which are evenly arranged along the length direction of the two bottom longitudinal beams 102. The two ends of the bottom longitudinal beam 102 are fixedly connected with support sleeves 18, and the support sleeves 18 are movable through the support columns 19. The lower end of the support column 19 is fixedly connected to the power walking mechanism 2, and the upper end is fixedly connected to the cylinder rod end of the lifting hydraulic cylinder 20. The cylinder seat of the lifting hydraulic cylinder 20 is fixedly connected to the support pier 21 set on one side of the column 105. This structure is convenient for walking and stable support during use.
[0034] In order to achieve stable support, each column 105 is larger at the top and smaller at the bottom, and the cross-section has a laterally gradually changing size, which provides good load-bearing stability, especially for the narrow structure of a single tunnel (the load-bearing problem when the ratio of the highest height to the widest width is between 1.2-1.5).
[0035] In order to facilitate assembly, the top arch 106 of the left section and the top arch 107 of the right section both include a bottom crossbeam 110, a lower sliding longitudinal beam 111, an outer short column 112 and an inner high column 113. The bottom crossbeam 110 is made of multiple pieces and is evenly spaced along the length of the vehicle. The bottom of the left side is fixedly connected to the lower sliding longitudinal beam 111. A sliding plate 114 is provided at the bottom of the lower sliding longitudinal beam 111. The two ends of the sliding plate 114 are upwardly tilted, and downwardly bent limiting side plates are provided on the front and rear sides to form a slide groove structure. Through this slide groove structure, directional stability can be achieved during movement. Fixed sliding, the sliding plate 114 rests on the upper left section of the top crossbeam 104, and the end of the sliding longitudinal beam 111 is hinged to the widening end of the hydraulic cylinder 108. The left and right sides above each bottom crossbeam 110 are respectively detachably fixedly connected with an outer short column 112 and an inner high column 113. The outer short column 112 and the inner high column 113 are detachably fixedly connected to the bottom of the single-sided top mold 115. The single-sided top mold 115 is fixedly connected to the outer end of the bottom crossbeam 110 near the inner side of the lower end. The two ends of the middle arch widening crossbeam 109 are detachably fixedly connected to the inner ends of the two bottom crossbeams 110. The upper surface of the top widening beam 109 is detachably fixedly connected to the bottom of the two upper sliding longitudinal beams 116. The upper surfaces of the two upper sliding longitudinal beams 116 are fixedly connected to the top widening top mold 119 through two rows of middle columns 118. The two upper sliding longitudinal beams 116 are placed on the middle section of the top crossbeam 104. The top of the middle section of the two top crossbeams 104 at the front end and the rear end of the door frame 1 is fixedly connected with a limit door frame 117. The upper sliding longitudinal beam 116 is located at each top crossbeam 104. Two symmetrical sliding plates 120 are set up above and below. The sliding plate 120 and the sliding plate The first 114 has the same structural shape, and the second sliding plate 120 can respectively rest on the upper end surface of the middle part of the top beam 104 and the bottom surface of the beam of the limiting door frame 117. The limiting door frame 117 is provided to play a horizontal and vertical limiting protection role. The side columns on both sides of the limiting door frame 117 are horizontally spirally connected with a detachable pushing screw 121. The inner end of the pushing screw 121 rests on the upper sliding longitudinal beam 116. Through the two pushing screws 121 set at the front and rear of the trolley, the single upper sliding longitudinal beam 116 can be pushed toward the center, and then slide to the middle arch widened beam, which is convenient for movement.
[0036] Before widening Figure 11-12As shown, the bottom left side of the bottom crossbeam 110 of the left section top arch 106 and the right section top arch 107 is detachably fixedly connected to the sliding longitudinal beam 111, and the upper right side is detachably fixedly connected to the upper sliding longitudinal beam 116. The lower sliding longitudinal beam 111 is placed on the upper surfaces of both sides of the four top crossbeams 104, and is provided with a sliding plate 114 for auxiliary sliding. The sliding plate 114 rests on the upper surfaces of the two side sections of the top crossbeam 104, and the sliding plate 2 120 at the lower end of the upper sliding longitudinal beam 116 rests on the top of the middle section of the top crossbeam 104, and is connected to two symmetrical top molds 115 through two middle columns 118 above.
[0037] Widening construction process: Install the two widening hydraulic cylinders that need to be installed on one side (one pair is required on the front and rear sides of the trolley) between the top arch 106 of the left section and the top arch 107 of the right section and the top crossbeam 104, loosen the bolts between the two symmetrical bottom crossbeams at the bottom of the top arch of the left section and the bottom of the top arch of the right section, and then loosen the bolts between the top formwork on the left side connected to the top arch of the left section and the top formwork on the right side connected to the top arch of the right section, control the front and rear pairs of widening hydraulic cylinders to open, and when the tension of the widening hydraulic cylinders is applied, the widening hydraulic cylinders will be tightened. Use it to move the top arch of the left section and the top arch of the right section outward respectively. When they reach the set position, release the hydraulic cylinder, install an intermediate arch widening beam 109 between every two bottom beams 110 to connect the two bottom beams 110 into one, install a top widening top mold 119 to fix the top inner ends of the two top molds, loosen the fixed connection between the upper sliding longitudinal beam 116 on the left and the bottom beam on the left, and loosen the top of the intermediate column 118 fixedly connected to the upper sliding longitudinal beam 116 and the left The fixed connection between the top molds is moved to the right. After moving to the set position, the upper sliding longitudinal beam 116 is fixedly connected to the middle arch widening beam 109, the middle column 118 is fixedly connected to the top widening top mold 119, and the inner high column 113 is fixed between the bottom beam 110 on the left and the corresponding top mold. Then, the fixed connection between the upper sliding longitudinal beam 116 on the right and the bottom beam on the right, as well as the top of the middle column 118 fixedly connected to the upper sliding longitudinal beam 116 and the top mold on the right are loosened. The fixed connection between them is moved to the left. After moving to the set position, the upper sliding longitudinal beam 116 is fixedly connected to the middle arch widening crossbeam 109, the middle column 118 is fixedly connected to the top widening top form 119, and the inner high column 113 is installed and fixed between the bottom crossbeam 110 on the side and the corresponding top form. After widening all parts of the arch structure, a widened arch structure is formed, and the side form is widened with the hydraulic jack of the side form, completing the entire trolley widening setting and the widening of the second lining trolley formwork of the single tunnel.
[0038] Example 2: A construction method for a secondary lining construction trolley for a single-track railway tunnel, the method comprising the following specific steps: Step 1: Assemble the trolley. First install the power travel mechanism and the bottom longitudinal beam. After installation, place it stably on the track. Then install the front and rear door frames on the two bottom longitudinal beams and use the auxiliary fixing mechanism to temporarily fix them. After fixing, install the middle door frame and the upper longitudinal beam. Step 2: Install the second lining template to the set position and fix it; Step 3. Set diagonal braces on both sides of the trolley bottom mold. The diagonal braces use screw jacks. The top of the screw jack is connected to the side mold and is located at the template seam of the side mold. The bottom of the screw jack is retracted to the edge of the filling surface.
[0039] Furthermore, the above-mentioned screw jacks have an inclination angle of 30°, and the screw jacks are arranged at intervals of 1.5m, with a total of seven arranged along the length direction of the trolley.
[0040] Auxiliary assembly suspension device used when assembling the trolley, such as Figure 22-24As shown, the auxiliary assembly suspension device includes a portal frame suspension wire rope 2301, an upper longitudinal beam suspension wire rope 2302, a sliding longitudinal beam suspension wire rope 2303 and multiple electric winches 2304. The portal frame suspension wire rope 2301 is tied at one end to the middle of the top side of the portal frame, and the other end is connected to the first electric winch 2304 after passing through the first fixed pulley 2305. The first fixed pulley 2305 is connected to the middle of the top side of the tunnel. The first electric winch 2304 is installed at a height above the ground. Four upper longitudinal beam suspension wire ropes 2302 are arranged symmetrically on the left and right of the tunnel. One end of the two upper longitudinal beam suspension wire ropes 2302 on one side are tied to the two upper longitudinal beams, and the other end passes through the second fixed pulley 2306, the third fixed pulley 2307 and the fourth fixed pulley respectively. The fixed pulley 2308 is then connected to the second electric winch 2304. The second fixed pulley 2306 and the third fixed pulley 2307 are respectively connected to the tunnel wall above the inner upper longitudinal beam and the outer upper longitudinal beam. The fourth fixed pulley 2308 is connected to the tunnel wall above the outer side of the trolley (left or right side). The second winch 2304 is installed on the tunnel floor and is located outside the bottom longitudinal beam. The sliding longitudinal beam suspension wire rope 2303 uses two wires on one side. The two ends are longitudinally tied to the two ends of the sliding longitudinal beam, and the other end is connected to the third electric winch 2304 after passing through the fifth fixed pulley 2309 and the sixth fixed pulley 2310. The fifth fixed pulley 2309 and the sixth fixed pulley 2310 are longitudinally fixedly connected to the top of the tunnel side, which can move the sliding longitudinal beam It is hoisted to the top of the portal frame for installation, and also includes two auxiliary crossbeams 2311 and the seventh fixed pulley 2312 for auxiliary fixing the front and rear ends of the two bottom longitudinal beams. The seventh fixed pulley 2312 and the first fixed pulley 2305 are kept installed in the middle of the top side of the tunnel. The portal frame suspension wire rope 2301 passes around the seventh fixed pulley 2312 and is connected to the first electric winder. The two auxiliary crossbeams can connect the spiral jack mounting holes at the bottom of the two ends of the bottom longitudinal beams connected to the four walking mechanisms to form the entire bottom walking mechanism assembly, which can walk stably on the track or be locked with iron shoes 2315, which is convenient for the installation of the portal frame and the arch structure. The seventh fixed pulley 2312 can realize the remote suspension of the portal frame and move the walking mechanism assembly after lifting it into the air. After reaching the corresponding position and removing the auxiliary walking wheels, the door frame is lowered and installed in the corresponding position. It also includes auxiliary walking wheels 2313 that are detachably fixed to the bottom of the two columns of the door frame. The auxiliary walking wheels are added to facilitate suspension and dragging. It also includes an eighth fixed pulley 2314. The eighth fixed pulley 2314 is installed on the top of the tunnel in the same longitudinal direction as the fifth fixed pulley 2309 and the sixth fixed pulley 2310, and is located in front of the walking mechanism assembly. The sliding longitudinal beam suspension wire rope 2303 bypasses the eighth fixed pulley 2314 and is connected to the third electric winch 2304, and then the sliding longitudinal beam suspension wire rope 2303 is bypassed by a section of the fixed pulley away from the sliding longitudinal beam, which can avoid interference between the sliding longitudinal beam suspension wire rope 2303 and the suspended sliding longitudinal beam.The suspension of the sliding longitudinal beam is affected by an auxiliary support block 2316, which is located behind the walking mechanism assembly and has a sloped surface on its upper side. Two of them are used to support the two upright posts of the inclined door frame, facilitating the initial suspension of the door frame.
[0041] When in use, the two auxiliary cross beams 2311 are connected to the bottom of the two bottom longitudinal beams 102 to form a walking mechanism assembly (including a power walking mechanism 2). The walking mechanism assembly is located on the track 5, the first fixed pulley 2305 is located at the top front of the walking mechanism assembly, the seventh fixed pulley 2312 is located at the top rear of the walking mechanism assembly, the eighth fixed pulley 2314 is located in front of the walking mechanism assembly, the fifth fixed pulley 2309 and the sixth fixed pulley 2310 are arranged in two rows, respectively, on the upper left and right sides of the walking mechanism assembly, the second fixed pulley 2306 and the third fixed pulley 2307 are arranged in two groups, respectively, on the upper left and right sides of the walking mechanism assembly, and symmetrically arranged. After the auxiliary walking wheels 2313 are installed on the two uprights 105 of the first door frame 101, the door frame is used. The suspension wire rope is tied to the top of the door frame 101, and the first electric winch 2304 is controlled to lift it to the suspended position. The auxiliary walking wheel 2313 is removed, and the walking mechanism assembly is controlled to move toward the side of the suspended door frame 101. When it moves to the first door frame 101 installation position on the front side, it stops and locks (the auxiliary iron shoe 2315 is locked). The winch 2304 and the two columns 105 of the door frame 101 are controlled to lower the position (the column position is manually controlled). The two positioning pins set at the bottom of the two columns 105 are inserted into the bottom longitudinal beam 101 to achieve positioning, and the columns 105 and the bottom longitudinal beam 102 are locked with bolts. The tied door frame suspension wire rope 2301 is removed, and the locking state of the walking mechanism assembly is released. The walking mechanism assembly is controlled to lower the winch 2304 and the two columns 105 of the door frame 101. The walking mechanism assembly returns to the initial position and continues to suspend the second door frame 101. The installation process of the second door frame 101 adopts the installation process of the first door frame 101. After the installation of the second door frame 101 is completed, it is moved to the installation position of the upper longitudinal beam 103 between the first door frame 101 and the second door frame 101. The upper longitudinal beam suspension wire rope 2302 is tied to the corresponding upper longitudinal beam 103 for suspension. After being suspended on the top crossbeam 104 of the door frame 101, the rotation direction is manually controlled to lower it to the installation position and locked with the two door frames 101 with bolts. After completing the installation of the upper longitudinal beam 103 between the first door frame 101 and the second door frame 101, the third door frame 101 is installed, and The upper longitudinal beam 103 between the third gantry 101 and the second gantry 101 is installed, and the process is repeated. After the installation of the last gantry 101 and the upper longitudinal beam 103 is completed, and the installation of the two adjacent gantry 101 is completed, the fork-type scissors support 122 is fixedly connected between the two adjacent gantry 101, and the walking mechanism assembly returns to the starting position. The sliding longitudinal beam suspension wire rope 2303 is tied to the sliding longitudinal beam (upper sliding beam or lower sliding beam) at both ends, and the third electric winch 2304 is controlled to suspend it above the top crossbeam 104. It is manually moved to the top crossbeam 104, and the lifting of the sliding beam is repeated to complete the installation of all sliding longitudinal beams (installation of the lower sliding longitudinal beam and the upper sliding longitudinal beam), and the main frame structure assembly of the walking gantry is completed.An operating platform is built on the top crossbeam 104 to assemble the parts of the vault structure. The parts of the vault structure are suspended by the upper longitudinal beam suspension wire rope 2302.
[0042] The above description is only a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any technician familiar with the technical field can easily think of changes or replacements within the technical scope disclosed by the present invention, which should be included in the scope of protection of the present invention. Therefore, the scope of protection of the present invention should be based on the scope of protection of the claims.
Claims
1. A method for construction of a secondary lining of a single-track railway tunnel without occupying the road, characterized in that: The method is as follows: according to the stress system of the secondary lining pouring working condition, by changing the trolley reinforcement plan, the temporary cross brace between the two longitudinal beams at the bottom of the trolley is cancelled, and the trolley is reinforced by setting an oblique brace between the bottom edge of the formwork and the filling surface, and setting a tie rod in the cavity formed between the hole set in the bottom formwork of the trolley and the top of the poured small side wall; the oblique brace and the tie rod are arranged at a fixed interval along the length direction of both sides of the trolley, and the concrete pouring pumping station used during pouring is arranged at a fixed interval in the tunnel.
2. The method for construction of a secondary lining of a single-track railway tunnel without occupying the road according to claim 1, characterized in that: The method comprises the following specific steps: Step 1: Drill holes and plant reinforcement bars at the top of the small side wall to obtain temporary anchoring reinforcement bars according to the measurement points. Use the reserved holes in the bottom mold of the trolley to connect the 5mm steel plate with the temporary anchoring reinforcement bars and fit them on the top of the small side wall. Step 2: Diagonal braces are set on both sides of the bottom mold of the trolley. The diagonal braces use screw jacks. The top of the screw jacks is connected to the side molds and located at the template seam of the side molds. The bottom of the screw jacks is gathered to the edge of the filling surface and abuts against it. Step 3: Use the small shelter tunnel to expand into a shunting tunnel. When pouring the secondary lining, use the nearest shunting tunnel as a concrete pouring pumping station, and place the delivery pump in the tunnel chamber of the shunting tunnel for operation; Step 4: Configure the pumping pipe according to the distance between the shunting tunnel and the lining trolley; Step 5. The shunting holes near the working face and the secondary lining should be managed more strictly. That is, the shunting holes near the working face are used for vehicles to wait and give way, and the shunting holes near the secondary lining are used for pouring the secondary lining.
3. The method for secondary lining construction of a single-track railway tunnel without occupying the road according to claim 1, characterized in that: In step one, the reinforcement hole for temporary anchoring of reinforcement at the top of the small side wall is 20cm deep and 22mm in diameter; φ22 threaded steel is installed as temporary anchoring reinforcement, buried 20cm in concrete and exposed 20cm, and a horizontal external tie rod anchor plate is added to the bottom of the longitudinal beam of the secondary lining trolley. A square groove that can be adjusted up and down is set in the middle of the horizontal external tie rod anchor plate; the tie rod includes a fixed plate and a temporary plate. The fixed plate includes φ25 fine-rolled threaded steel and a 5mm steel plate fixedly connected to it. The temporary plate is a 5mm steel plate. The fixed plate and the temporary plate are connected by bolts. After the secondary lining is poured, the temporary plate is used as a loss and the fixed plate can be reused. The longitudinal spacing of the tie rods is 1.5m, distributed at the bottom of the longitudinal beams on both sides of the trolley. The size of the horizontal external tie rod anchor plate should be able to meet the setting of all lining types undertaken by the secondary lining trolley, and the tie rod end should be effectively connected to the embedded steel bars or secondary lining steel bars and anchor steel bars.
4. The method for construction of a secondary lining of a single-track railway tunnel without occupying the road according to claim 2, characterized in that: In step 2, screw jacks are set on both sides of the bottom mold of the trolley to support the top connection with the side mold. The position is located at the template seam. The screw jacks have an inclination angle of 30°. The screw jacks are set at intervals of 1.5m, and a total of seven are set along the length of the trolley.
5. The method for construction of a secondary lining of a single-track railway tunnel without occupying the road according to claim 1, characterized in that: In step three, the spacing between shunting tunnels is set at 120m / tunnel, and the size of the shunting tunnel is 5.6m high, 9m wide and 8.5m deep.
6. The method for construction of a secondary lining of a single-track railway tunnel without occupying the road according to claim 1, characterized in that: In step 4, the pumping pipe is installed against the edge of the channel; the vehicle-mounted pump is placed in the concrete pumping station and tested with pipeline lubricant. If there is any fault, it should be repaired in time. Before concrete preparation, check whether the raw materials meet the specifications, measure the moisture content of sand and gravel, and prepare the construction mix ratio according to the length of the on-site pumping pipe. Before leaving the station, the experimenter checks the slump of the concrete, which is 160mm~200mm according to the length of the pumping pipe. After the concrete arrives at the site, the slump is measured again. If it does not meet the requirements, it will be returned to the factory for processing.