Lining construction method of water delivery tunnel
By first lining the bottom plate in the construction of the water transmission tunnel, then lining the side top arch according to the surrounding rock category, and using hydraulic trolleys to achieve mechanical equipment, the safety and quality problems of construction under complex geological conditions are solved and the construction efficiency is improved and security.
Patent Information
- Application Number
- CN202411258278.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-09
- Publication Date
- 2024-11-12
AI Technical Summary
The construction of water transmission tunnels faces geological disaster risks under complex geological conditions, and the construction technology is complex, making it difficult to reasonably choose the construction method and sequence, which affects the safety and quality of the project.
A lining construction method for water transmission tunnels is adopted, including first conducting the bottom plate lining construction, then conducting the side top arch lining construction according to the surrounding rock category, and the passage of mechanical equipment is achieved through self-propelled hydraulic trestles and hydraulic steel mold trests, and controlling the passage of mechanical equipment. Concrete pouring and excavation are carried out simultaneously.
It improves construction progress and safety, optimizes the allocation of construction resources, reduces costs, achieves the goals of low input and high output, and ensures project quality and safety.
Smart Images

Figure CN118933897A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel construction, in particular to a lining construction method for a water conveyance tunnel. Background Art
[0002] A water conveyance tunnel refers to a tunnel-type water conveyance structure, which is often used in hydraulic structures. The construction of a water conveyance tunnel needs to pass through areas with complex terrain and changeable geological conditions, which brings great difficulties to the construction. Tunnel engineering needs to pass through various geological layers, such as rocks, soil layers, faults, etc. The properties and stability of these geological layers vary greatly, which brings great uncertainty to the construction. The complex geological conditions make the construction process of tunnel engineering prone to geological disasters, such as landslides, water gushing, rock bursts, etc., which seriously threaten the safety of construction workers. At the same time, the construction technology of tunnel engineering is complex, involving excavation, support, lining, ventilation, drainage and other aspects. During the construction process, how to reasonably select the construction method, construction sequence and construction parameters has become a key problem. In addition, the measurement and positioning technology of tunnel engineering is high, and it is necessary to accurately grasp the direction and position of the tunnel to ensure the smooth progress of the tunnel engineering. Summary of the invention
[0003] The object of the present invention is to provide a lining construction method for a water conveyance tunnel.
[0004] The present invention is implemented by the following technical solution: A lining construction method for a water conveyance tunnel comprises the following steps:
[0005] (1) Carry out base lining construction;
[0006] (2) The side arch lining construction shall be carried out after the bottom lining has advanced more than three units;
[0007] (3) Control the distance between concrete pouring and excavation face according to the surrounding rock type.
[0008] In order to better implement the method of the present invention, further, in the step (1), the specific process of performing the bottom plate lining construction is as follows:
[0009] (1.1) Install the lining trolley;
[0010] (1.2) Clean the foundation surface and construction joints, and accept the inspection by all parties after the cleaning is completed;
[0011] (1.3) Complete the processing and installation of steel bars, and inspect and accept the installed steel bars;
[0012] (1.4) Positioning the self-propelled hydraulic trestle trolley;
[0013] (1.5) Install the head plate and carry out water-stopping construction. After the construction is completed, open the warehouse for acceptance;
[0014] (1.6) Transport concrete, carry out the concrete pouring process, and finally carry out concrete curing;
[0015] (1.7) Repeat the above steps and proceed to the next section lining.
[0016] In order to better implement the method of the present invention, further, in the step (1.2), the cleaning process of the foundation surface is as follows: the bottom cleaning is first performed with an excavator to remove a large amount of slag blocks, and then manually cleaned. After cleaning, a full-section scanner is used to scan, and the under-excavated parts are processed. After processing, they are scanned again to form data. Finally, manual cleaning is performed. When manually cleaning the bottom, loose rocks are removed with a triangular shovel, and then the gravel in the rock cracks is cleaned with a bamboo brush, and then high-pressure wind or high-pressure water is used to rinse. After repeated multiple times, the acceptance standard is met.
[0017] In order to better implement the method of the present invention, further, in the step (1.2), the cleaning process of the construction joint is: using a high-pressure water roughening machine to perform roughening treatment. Roughening is performed from left to right along a wide band-shaped trajectory where the jet contacts the concrete surface, with a small amount of overlap, completely removing the cement latex on the concrete surface, slightly exposing small stones, that is, the total area of small stones with a particle size of more than 5.0 mm accounts for 20% to 30% of the roughening area, and the unevenness is controlled within ±2mm3mm without damaging the aggregate.
[0018] In order to better implement the method of the present invention, further, in the step (2), the specific process of carrying out the side top arch lining construction is:
[0019] (2.1) Monitoring and measurement to determine the time for lining application;
[0020] (2.2) Make good preparations for construction;
[0021] (2.3) Confirm that the lining trolley is in place and tie the steel bars that match the lining;
[0022] (2.4) Mobile trolley;
[0023] (2.4) applying a release agent on the template surface;
[0024] (2.5) Positioning the lining trolley through the template installation process;
[0025] (2.6) Apply annular waterstop strips or waterstop belts;
[0026] (2.7) Conduct quality inspection;
[0027] (2.8) pouring concrete;
[0028] (2.9) After the concrete solidifies, remove the formwork and carry out concrete curing;
[0029] (2.10) Repeat the above steps and proceed to the next lining section.
[0030] In order to better implement the method of the present invention, further, the construction preparation in step (2.4) includes
[0031] (2.2.1) Check the centerline horizontal layout;
[0032] (2.2.2) Laying of lining trolley track.
[0033] In order to better implement the method of the present invention, further, the positioning process of the lining trolley in step (2.5) includes
[0034] (2.5.1) Horizontal positioning of the mold;
[0035] (2.5.2) Centerline positioning mold;
[0036] (2.5.3) Installation of embedded parts.
[0037] In order to better implement the method of the present invention, further, in step (2.8), the concrete is transported by a transport vehicle or pumped by a transport pump.
[0038] In order to better implement the method of the present invention, further, the trolley used in the bottom plate lining construction is a self-propelled hydraulic trestle trolley, and the trolley used in the side top arch lining is a hydraulic steel mold trolley.
[0039] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0040] (1) The present invention provides a construction method for a water conveyance tunnel, which can be used in a targeted manner according to the particularity of the water conveyance tunnel, and can meet the construction requirements of excavating and lining the water conveyance tunnel at the same time, thereby accelerating the construction progress;
[0041] (2) The present invention adopts a self-propelled hydraulic trestle to cross the bottom plate pouring working surface, ensuring the passage of mechanical equipment to achieve synchronization of tunnel excavation and lining, improving the level of engineering technology and construction equipment, ensuring construction safety and engineering quality, accelerating construction progress, and reducing engineering costs;
[0042] (3) The present invention combines the characteristics of water diversion tunnel projects, adopts advanced construction technology, applies scientific organizational methods, and allocates resources such as funds, labor, large-scale construction machinery and equipment, and materials on the principle of meeting construction requirements and having a slight surplus. The construction sequence is reasonably arranged and the construction plan is optimized according to the principle of minimizing costs and maximizing efficiency. Balanced and continuous production is organized; a mathematical model is established with key lines as the center to optimize construction period and resources; energy is saved and consumption is reduced to achieve the goal of low input and high output. BRIEF DESCRIPTION OF THE DRAWINGS
[0043] Other features, objects and advantages of the present invention will become more apparent from the detailed description of non-limiting embodiments with reference to the following drawings:
[0044] Figure 1 This is a process flow chart of the bottom plate lining construction process of the present invention;
[0045] Figure 2 This is a process flow chart of the construction of the side top arch lining in the present invention;
[0046] Figure 3 It is a schematic diagram of the longitudinal section arrangement of the self-propelled hydraulic trestle trolley in the present invention;
[0047] Figure 4 It is a schematic diagram of the longitudinal section arrangement of the side top arch hydraulic steel mold trolley in the present invention;
[0048] Figure 5 It is a schematic diagram of the cross-section arrangement of the side top arch hydraulic steel mold trolley in the present invention; DETAILED DESCRIPTION
[0049] In order to make the purpose, process conditions and advantages of the present invention more clearly understood, the present invention is further described in detail in conjunction with the following embodiments, but the embodiments of the present invention are not limited thereto. Without departing from the above-mentioned technical ideas of the present invention, various substitutions and changes are made according to the common technical knowledge and customary means in the field, which should all be included in the scope of the present invention. The specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0050] Embodiment 1:
[0051] This embodiment provides a lining construction method for a water conveyance tunnel, comprising the following steps:
[0052] (1) Carry out base lining construction;
[0053] (2) The side arch lining construction shall be carried out after the bottom lining has advanced more than three units;
[0054] (3) Control the distance between concrete pouring and excavation face according to the surrounding rock type.
[0055] Embodiment 2:
[0056] Based on the above embodiment, this embodiment further defines the specific process of bottom plate lining construction in step (1), such as Figure 1 As shown, the following steps are included:
[0057] (1.1) Install the lining trolley;
[0058] (1.2) Clean the foundation surface and construction joints, and accept the inspection by all parties after the cleaning is completed;
[0059] (1.3) Complete the processing and installation of steel bars, and inspect and accept the installed steel bars;
[0060] (1.4) Positioning the self-propelled hydraulic trestle trolley;
[0061] (1.5) Install the head plate and carry out water-stopping construction. After the construction is completed, open the warehouse for acceptance;
[0062] (1.6) Transport concrete, carry out the concrete pouring process, and finally carry out concrete curing;
[0063] (1.7) Repeat the above steps and proceed to the next section lining.
[0064] The other parts of this embodiment are the same as those of the above embodiment and will not be described in detail.
[0065] Embodiment 3:
[0066] Based on the above embodiment, this embodiment further defines that in step (2), the specific process of carrying out the side top arch lining construction is as follows: Figure 2 As shown, the following steps are included:
[0067] (2.1) Monitoring and measurement to determine the time for lining application;
[0068] (2.2) Make good preparations for construction, including the horizontal layout inspection of the center line and the laying of the lining trolley track;
[0069] (2.3) Confirm that the lining trolley is in place and tie the steel bars that match the lining;
[0070] (2.4) Mobile trolley;
[0071] (2.4) applying a release agent on the template surface;
[0072] (2.5) Positioning the lining trolley through the template installation process; including horizontal positioning of the template, centerline positioning of the template, and installation of embedded parts;
[0073] (2.6) Apply annular waterstop strips or waterstop belts;
[0074] (2.7) Conduct quality inspection;
[0075] (2.8) Concrete pouring is completed by conveying concrete by a conveyor truck or by pumping concrete by a conveying pump;
[0076] (2.9) After the concrete solidifies, remove the formwork and carry out concrete curing;
[0077] (2.10) Repeat the above steps and proceed to the next lining section.
[0078] The other parts of this embodiment are the same as those of the above embodiment and will not be described in detail.
[0079] Embodiment 4:
[0080] This embodiment further defines the lining equipment based on the above embodiment.
[0081] Bottom lining trolley:
[0082] The bottom plate lining is carried out by a self-propelled hydraulic trestle trolley, such as Figure 3 As shown, the effective working length of the self-propelled hydraulic trestle is 24m, and the total length is 45m, which can ensure the concrete pouring of one warehouse bottom plate and the reinforcement binding construction of the other warehouse bottom plate. The bottom plate is excavated in place at one time, and the trestle erection height is increased by setting up the approach bridge to ensure the working space for the bottom plate reinforcement binding and concrete pouring process. The trestle is moved when the transportation is idle.
[0083] Side arch lining trolley:
[0084] The tunnel side arch lining is constructed with a hydraulic steel formwork trolley. The effective working length of the trolley is 12m and the total length is 12.1m. The main tunnel excavation and side arch pouring are carried out simultaneously, which requires the passage of various pipelines and supporting mechanical equipment on the excavation working surface. Therefore, the lining trolley is designed as a gantry, with space reserved on the left and right sides and the inside of the arch position template. The side arch lining trolley is arranged as follows: Figure 4 , Figure 5 shown.
[0085] Mechanical equipment passage: The clearance size of the lining trolley portal is 3.6m×4.32m (width×height). The tunnel excavation construction of this section mainly passes dump trucks and concrete tankers. The size of the selected mechanical equipment is smaller than the clearance of the lining trolley portal to ensure the normal construction of the excavation working surface during concrete pouring.
[0086] Passage of various pipelines: power supply lines, high-pressure air ducts, water supply pipes, and drainage pipes in the tunnel pass through the reserved spaces on both sides, and ventilation pipes pass through the reserved space at the arch position. Fengshui pipelines are arranged with brackets for support, and cables are laid with galvanized hanging cable hooks. During the assembly process, the lining steel mold trolley ensures that various pipelines in the tunnel pass through the lining steel mold trolley. After the lining steel mold trolley completes the pouring of one warehouse of concrete, it moves to the front of the next warehouse, removes the bracket and cable hook about 30m in the forward direction of the lining steel mold trolley, and the lining steel mold trolley passes through the pipeline and moves forward. The poured concrete section is welded with a bracket and a cable hook on the pre-buried steel plate during pouring, and the Fengshui and electricity pipelines are placed on the bracket and hook to ensure that the Fengshui and electricity pipelines do not sink. The other parts of this embodiment are the same as the above embodiment and will not be repeated.
[0087] Embodiment 5:
[0088] Based on the above embodiments, the present embodiment further limits the lining construction content, and the construction content mainly includes: concrete mix design, cleaning of foundation surface, steel bar installation, water stop installation, formwork installation, formwork calibration, concrete mixing, transportation, pouring, maintenance, protection, defect repair and other contents. During the construction process, the design requirements and specifications are strictly followed. The specific construction process is as follows.
[0089] (1) Cleaning the foundation and treating the construction joints
[0090] (1.1) Cleaning the base surface
[0091] The bottom cleaning is first done by excavators to remove a large amount of slag, and then by manual cleaning. After cleaning, it is scanned with a full-section scanner to process the under-excavated parts, and then scanned again to form data. Finally, it is done manually to perform the final cleaning. When cleaning the bottom manually, loose rocks are removed with a triangular shovel, and then the gravel in the rock cracks is cleaned with a bamboo brush, and then washed with high-pressure wind or high-pressure water. After repeated multiple times, it reaches the acceptance standard.
[0092] (1.2) Construction joint treatment
[0093] Use a high-pressure water blasting machine for blasting. Brush from left to right along the wide band track where the jet contacts the concrete surface, with a small amount of overlap. Completely remove the cement emulsion on the concrete surface, slightly expose small stones, that is, the total area of small stones with a particle size of more than 5.0mm accounts for 20% to 30% of the blasting area, and the convexity is controlled within ±2mm to 3mm without damaging the aggregate.
[0094] The other parts of this embodiment are the same as those of the above embodiment and will not be described in detail.
[0095] Embodiment 6:
[0096] Based on the above embodiments, this embodiment further defines the specific contents of steel bar manufacturing and installation. The tunnel lining steel bars are double-layer steel bars. Positioning bars are arranged in each layer of steel bars, and then annular bars are installed, and finally longitudinal bars are arranged.
[0097] (1) Steel bar processing
[0098] (1.1) Rust removal of steel bars: Use sandpaper, sand tray, wire brush, sandblasting, and rust removal machine to remove rust so that the surface is clean and free of oil stains, paint stains, rust, etc.
[0099] (1.2) Cutting of steel bars: Steel bars are cut by mechanical cutting.
[0100] (1.3) Bending of steel bars
[0101] Before the steel bar is bent and formed, a large sample drawing is placed at a ratio of 1:1 in the steel bar processing plant as a standard for the ratio of steel bar bending and forming. The bending of the steel bar and the hook at the end are processed according to the design requirements. The allowable deviation of steel bar bending processing is shown in Table 1.
[0102] Table 1: Allowable deviation of the bar after processing
[0103]
[0104]
[0105] (1.3.1) For the end of the hot-rolled ribbed steel bar under tension, when the design requires the use of a right-angle hook, the bending diameter d of the straight hook shall not be less than 5 times the diameter of the steel bar, and a straight section of not less than 3 times the diameter of the steel bar shall be left at the end of the hook. The steel bar shall be bent into a smooth curve, and its bending radius shall not be less than 12 times the diameter of the steel bar (ribbed steel bar).
[0106] (1.3.2) Steel bar bending and forming process: Mark the steel bars before bending. For steel bars with complex shapes, mark the positions of each bending point according to the dimensions indicated on the steel bar material label; formulate a more reasonable operation sequence according to different steel bar bending forms to facilitate bending.
[0107] Manual bending: Select the appropriate wrench according to the diameter of the steel bar, and then select the span. When manually bending, the steel bar must be placed flat, the wrench must be flat, and the force must be even. It cannot swing up and down to avoid warping of the bent steel bar. The longitudinal ribs of threaded steel bars are often twisted. When bending, the wrench should be adjusted according to the twisting of the ribs to prevent warping after bending.
[0108] Mechanical bending: Select a suitable mandrel, determine the position of the steel bar bending point and mandrel, and use a hook bending machine for bending.
[0109] (1.4) Stacking of finished and semi-finished steel bars
[0110] The steel bars made on site should be lifted and placed gently to avoid deformation caused by falling on the ground. They should be marked with identification tags according to the numbers to avoid missing any. After the finished steel bars are counted and confirmed to be correct, they should be stacked in the designated finished product stacking area.
[0111] (2) Measuring the positioning ribs
[0112] After the four parties passed the joint acceptance, the positioning steel bars were measured and installed. The positioning steel bars were 2 meters in the circumferential direction and 2 meters in the longitudinal direction. The triangular brackets were fixed and holes were drilled with an electric drill. The hole depth was 10 cm. The 20 steel bars were anchored with anchoring agents. After the positioning steel bars were installed, the position of the circumferential bars was marked on each positioning bar.
[0113] (3) Steel bar installation
[0114] (3.1) Installation of circumferential ribs
[0115] First, place the circumferential reinforcement at the bottom according to the calculated quantity, and then install the longitudinal positioning reinforcement. The longitudinal positioning reinforcement is welded to the positioning reinforcement according to the measured mark. Make sure the welding is firm. After welding, weld and tie the circumferential reinforcement one by one according to the designed spacing; the joints of two adjacent steel bars should be staggered at an angle of 45°.
[0116] Secondly, the steel bar welding shall be carried out by arc welding or double-protected welding. In addition to meeting the strength requirements, it shall be carried out in accordance with the following provisions:
[0117] (3.1.1) The length of the lap joint and the length of the weld shall comply with the specifications.
[0118] The lap length of the steel bars used in this project shall not be less than 10d.
[0119] (3.1.2) The ends of the lap joint reinforcement should be pre-bent to ensure that the axes of the lap reinforcement are on the same straight line.
[0120] (3.1.3) The steel bar joints shall be lap welded, with the weld height h ≥ 0.25d and not less than 4mm, and the weld width 0.7d and not less than 10mm.
[0121] (3.1.4) The support bar and the welded steel bar should be fixed at 4 points. When lap welding, 2 points should be used for fixation. The tack weld should be at least 20 mm away from the end of the support bar or the lap end.
[0122] (3.1.5) Each time you change the steel grade, diameter, welding rod type or welder, make two tensile test pieces with the same material, welding conditions and parameters. When the test results are both greater than the tensile strength of the steel grade, welding can be carried out.
[0123] (3.1.6) Quality inspection: When the joint is tapped with a small hammer, the steel bar makes a crisp sound; the surface of the joint weld is smooth, without gaps, cracks and large metal weld nodules. The allowable deviation of its defects and dimensions is controlled according to Table 2.
[0124] Table 2 Permissible deviations of defect dimensions of arc welded steel bar joints
[0125]
[0126]
[0127] Note: d is the diameter of the steel bar (mm). (2) When the allowable deviation in the table has two values for the same item, the more severe value should be used for control.
[0128] (3.2) Longitudinal rib installation
[0129] After the annular reinforcement is installed, the longitudinal reinforcement is installed from the middle to both sides according to the designed spacing and tied securely. Acceptance is carried out after the installation is completed.
[0130] Tie-up of steel bars
[0131] The positions of the joints of the tensile reinforcement are staggered. When the tied joint is used, in any overlap length section or in a section of 35d and not less than 50cm when the welded joint is used, the percentage of the cross-sectional area of the reinforcement with the joint to the total cross-sectional area of the reinforcement shall comply with the provisions of Table 3.
[0132] Table 3 Permissible percentage of joint area of stressed steel bars
[0133]
[0134] Note: The joint location should be at a place with less stress, and as few joints as possible should be set on the same steel bar.
[0135] The other parts of this embodiment are the same as those of the above embodiment and will not be described in detail.
[0136] Embodiment 7:
[0137] Based on the above embodiment, this embodiment further defines the specific content of water-stopping construction, which specifically includes:
[0138] (1) W-type copper sheet water stop
[0139] (1.1) Construction requirements
[0140] (1.1.1) Copper waterstop is used for lining concrete structural joints. In principle, a structural joint is set every 3 to 5 casting sections in the tunnel.
[0141] (1.1.2) The thickness of the W-type copper waterstop is 1.2mm and the width is 600mm.
[0142] (1.1.3) When using copper strip to process waterstop, the tensile strength shall not be less than 205MPa, the elongation shall not be less than 20%, and the chemical composition and physical and mechanical properties of the copper waterstop shall meet the requirements of "Copper and Copper Alloy Strip" (GB / T2059-2017).
[0143] (1.1.4) Provide the supervisor with detailed information and test results of copper waterstop for approval, and all waterstop materials used must be submitted to the supervisor for approval.
[0144] (1.2) Construction method
[0145] (1.2.1) The water-stop copper sheet is processed by mechanical cutting. It is strictly forbidden to use iron tools to hammer the surface of the copper sheet during the processing.
[0146] (1.2.2) The water-stop copper sheet is processed by cold pressing with a mold. After forming, its surface is inspected. If there are cracks (marks), it will be disposed of as scrap and the quality of the same batch of materials will be re-inspected.
[0147] (1.2.3) After processing, water-stop copper sheets of different specifications should be labeled or marked with other signs to distinguish them and facilitate installation.
[0148] (1.2.4) After the waterstop is processed, the quality manager will check the height, width, flatness of the waterstop flange, etc. of the copper nose, and put it into use only if it passes the inspection.
[0149] (1.2.5) The waterstop copper sheets are transported from the processing workshop to the construction site using a material transport vehicle. During the transportation process, the vehicle speed is controlled to ensure that the waterstop is not damaged during transportation.
[0150] (1.2.6) Gas welding is used for water-stop welding. Before welding, the welding wire and weldment should be cleaned. Wire brush or sandpaper should be used to remove surface oil and adsorbed gas. Neutral flame should be used for welding. Before welding, the weldment should be preheated at 400-500℃. Overlap welding is used for joint welding of copper water-stop, and the overlap length should be greater than 20mm.
[0151] (1.3) Quality inspection
[0152] (1.3.1) Appearance quality inspection: After welding is completed, visual inspection or measurement is used to check whether the weld is flat and smooth, whether the axis butt error meets the design requirements and whether the overlap length is not less than 20mm.
[0153] (1.3.2) Joint penetration test: The specific test method is as follows: drip kerosene on the weld and sprinkle chalk dust or dry lime on the other side. Wait one minute and then observe whether there is kerosene leakage in the weld on the other side. If there is any moisture, mark it with chalk and re-weld it.
[0154] (2) Rubber water stop strip
[0155] (2.1) Construction requirements
[0156] (2.1.1) Rubber waterstops are mainly used in tunnel lining construction joints.
[0157] (2.1.2) The rubber water stop strip shall be in rectangular shape with a width of not less than 30 mm and a thickness of not less than 20 mm.
[0158] (2.1.3) The appearance quality of the rubber waterstop shall comply with Article 5.2 of "Polymer Waterproof Materials Part 3: Water-Swelling Rubber" (GB18173.3-2014).
[0159] (2.1.4) The dimensional tolerance of rubber waterstop shall comply with Article 5.1 of "Polymer Waterproof Materials Part 3 Water-Swellable Rubber" (GB18173.3-2014).
[0160] (2.2) Construction method
[0161] Install wooden strips with the same width as the water-expandable waterstop strips at the designed position of the concrete head plate in advance. After pouring, chisel out the wooden strips to form a groove, which is a circumferential type. The groove of the longitudinal construction joint is pressed out by wooden strips before the initial setting of the concrete. The water-expandable waterstop strips are embedded in the grooves to complete the waterstop installation. The joints of the waterstop strips are connected by vulcanization.
[0162] After the water stop is installed, the next step of concrete pouring should be carried out in time. If the time interval between concrete pouring is long, plastic film should be used to protect the joints of the water stop to prevent pollution and avoid blisters.
[0163] (2.3) Quality inspection
[0164] (2.3.1) It is strictly forbidden to butt-joint waterstop strips to avoid misalignment and formation of "breaks" during concrete pouring.
[0165] (2.3.2) Waterstop strips must not be soaked in water to allow them to swell before use.
[0166] (2.3.3) It is strictly prohibited to use steel nails to fix waterstop strips.
[0167] (2.3.4) The exposed water stop joint of the front bottom plate of the side arch lining adopts.
[0168] (3) Rubber water stop
[0169] (3.1) Construction requirements
[0170] (3.1.1) Rubber waterstop is mainly used for structural joints.
[0171] (3.1.2) The rubber waterstop is made of elastic polychloroprene rubber that fully complies with Chinese standards, does not contain recycled materials, has a rubber content of more than 50%, and the shape and size of the cross section conform to the type shown in the drawing.
[0172] (3.1.3) The molded multi-rib waterstop is dense and uniform, without pores, gaps, joints and other defects. The appearance quality of the rubber waterstop complies with Article 4.1 of "Polymer Waterproof Materials Part 2: Waterstop" (GB18173.2-2014).
[0173] (3.1.4) The rubber waterstop is symmetrical in shape and its dimensional tolerance complies with Article 4.2 of "Polymer Waterproof Materials Part 2: Waterstop" (GB18173.2-2014).
[0174] (3.1.5) Rubber waterstops used in areas where groundwater is subject to sulfate corrosion or carbonate corrosion shall meet the durability requirements of the design documents.
[0175] (3.1.6) Provide the supervisor with detailed information and test results of the waterstop before construction and put it into use after approval by the supervisor.
[0176] (3.2) Construction method
[0177] Clean the base surface before installing the waterstop, and repair concrete defects with modified epoxy mortar to ensure that the base surface is flat and dry.
[0178] Before installing the waterstop, evenly apply the interface agent on the base surface with a glue layer thickness of 2mm to 3mm. Then firmly stick the rubber waterstop to the glue layer. It is strictly forbidden to punch holes, pull or hang to fix.
[0179] The curing time of the waterstop after installation shall not be less than 48 hours. Reasonable measures shall be taken to protect it during the curing period and no disturbance is allowed.
[0180] After the waterstop is cured, install the waterstop pressure blocks and rubber panels.
[0181] (3.3) Quality inspection
[0182] (3.3.1) Incoming materials must have a product certificate (or material inspection report).
[0183] (3.3.2) When transporting materials, avoid exposure to sunlight, heat sources, oils and harmful solvents, and do not press the finished products.
[0184] (3.3.3) Construction personnel strictly inspect material specifications and appearance for defects.
[0185] (3.3.4) The waterstop must be pasted accurately and firmly, and the joints of two parallel waterstops must be staggered.
[0186] (3.3.5) The dimensions of the rubber water stop shall be measured with a measuring tool, with the thickness accurate to 0.05mm and the width accurate to 1mm.
[0187] (4) Sealing materials
[0188] (4.1) Construction requirements
[0189] The joints of the tunnel structure are filled with polyethylene closed-cell foam waterproof boards, and their performance indicators meet the requirements of "Concrete Joint Sealing Filling Boards" (JC / T2255).
[0190] (4.2) Construction method
[0191] Clean the expansion joints and paste polyethylene closed-cell foam waterproofing sheets on the structural joints on both sides of the copper water stop. The other parts of this embodiment are the same as those of the above embodiment and will not be described in detail.
[0192] Embodiment 8:
[0193] Based on the above embodiment, this embodiment further defines the specific content of the template construction, including the following steps:
[0194] (1) Trolley in place
[0195] The trolley brakes after moving to the warehouse surface, and then the template is accurately adjusted using the template's built-in hydraulic system. The entire process is measured, monitored and checked to ensure that it meets the design requirements after being in place.
[0196] (2) Installation of the head plate
[0197] During the pouring of the first warehouse, the headboards are installed on both sides. The headboards are made of wooden templates and processed on site according to the actual size. When installed, they are flush with the inner edge of the lining trolley and match the surface of the surrounding rock. During continuous pouring, only one side of the headboard is installed. The other parts of this embodiment are the same as the above embodiment and will not be repeated.
[0198] Embodiment 9:
[0199] Based on the above embodiment, this embodiment further defines the specific content of concrete construction, including the following steps:
[0200] The types of cement and grades of lining concrete used are shown in Table 4.
[0201] Table 4 Statistics of cement-based concrete grades
[0202]
[0203] (1) Concrete mixing
[0204] Concrete mix ratio: According to the requirements of the construction drawings and the instructions of the supervisor, the concrete mix ratio design is carried out through indoor test results and submitted to the supervisor for approval, including the mix ratio test plan of the mix ratio test ingredients and their mixing, moulding and curing.
[0205] When mixing the ingredients, the test personnel shall adjust the construction mix ratio in time according to the moisture content of sand and stone. The slump of concrete pouring shall be controlled at 140-180mm and reasonably controlled according to the actual situation. The operators of the mixing station shall be trained before taking up their posts and mix the concrete strictly according to the mix ratio. A steel mesh shall be installed on the bucket of the batching machine to filter out oversized gravel, and a special person shall be assigned to remove the oversized gravel. The mixing station manager with rich construction experience shall be responsible for the maintenance of the mixing equipment, especially the batching machine metering system which is prone to failure.
[0206] Concrete mixing: Sand and stone are stored separately. The loader pours sand and stone into the storage hopper and then transports them to the measuring hopper via a belt conveyor. When they reach a certain weight, the weighing rod of the measuring hopper is lifted and contacts the travel switch, the electromagnet is powered off, and the storage hopper door closes automatically using the spring retraction force. Weighing control equipment is installed for sand and stone respectively. When the aggregate reaches the specified weight, the mixer hopper falls and hits the inclined rod on the measuring hopper door, and the sand and stone flow into the upper hopper at the same time. When the hopper is lifted, the measuring hopper door is immediately closed, and the upper hopper transports the sand and stone to the mixer, adds water and cement according to the mix ratio, and starts mixing concrete.
[0207] Before mixing, add water and run the mixer for several minutes to remove the accumulated water, fully moisten the mixing drum, and lubricate the pump tube with mortar. It is strictly forbidden to add mixing materials again before all concrete is discharged, and it is strictly forbidden to use the method of discharging and feeding at the same time. Strictly control the water-cement ratio and slump, and do not arbitrarily increase or decrease the amount of water without the consent of the test personnel.
[0208] Strictly follow the concrete mix ratio during construction and work with a sign next to the mixer. The allowable deviation of concrete raw materials by weight is: cement, admixture, water and additives are ±0.3%, and aggregate is ±0.5%.
[0209] (2) Concrete transportation
[0210] Concrete transportation methods are different: Concrete transportation for inclined shaft branch tunnels is relatively complicated. Chutes are used outside the tunnel to transport concrete from the concrete mixing station to the inclined shaft branch tunnel. In the main tunnel, concrete tank trucks are used to transport concrete directly to the warehouse surface and pump it into the warehouse for construction. Concrete transportation for branch tunnels is relatively simple. Concrete tank trucks are used to transport concrete directly to the warehouse surface and pump it into the warehouse. Vehicles turning around in the tunnel are all carried out in the meeting lane.
[0211] Concrete tank trucks are high-efficiency machines used to transport concrete over long distances. During the transportation process, the concrete mixing drum keeps rotating at a slow speed, so that the concrete mixture in the drum can be continuously stirred to ensure that the concrete will not segregate after long-distance transportation. When transporting concrete, the concrete tank truck controls the stirring speed to 2-4r / min. When transporting concrete in winter, consider adding a thermal insulation jacket to the concrete tank truck to ensure the quality of the concrete.
[0212] Before pumping, the concrete delivery pump should be started to wet the entire pipeline with water, and then mortar should be added to make the pipe wall fully lubricated before pumping concrete. At the beginning of pumping, the hydraulic pressure gauge and working status of each part of the concrete pump should be closely observed. Generally, the outlet of the pump (i.e., the Y-type pipe and the conical pipe) is the most prone to pipe blockage. If the pipe is blocked, immediately reverse the pump 3 to 4 times. If it still does not work, remove the pipe to clear the blockage. The concrete in the hopper must not be less than 20cm. The pumped concrete is fed into the warehouse through the pouring window.
[0213] (3) Concrete pouring
[0214] (3.1) Strictly control the workability of pumped concrete.
[0215] (3.2) Lining concrete is poured from bottom to top using pouring windows layer by layer. By combining the main hopper, main chute, "three-way" diversion trough, diversion series and window chute, the corresponding gate valve is simply operated to make the concrete flow to each working window, so as to realize the pouring of lining concrete window by window.
[0216] (3.3) The interval between concrete pouring shall not exceed 0.5 hours; the mixed concrete shall be poured before initial setting.
[0217] (3.4) Use a cross-section meter to measure the cross section and estimate the amount of concrete to be poured. When the last truck of concrete is poured to cap the concrete, the amount of concrete can be further confirmed to ensure the supply of concrete.
[0218] (3.5) Pre-embed the grouting pipes according to the designed grouting hole layout parameters.
[0219] (4) Concrete vibration
[0220] Concrete is poured from the pouring window, from bottom to top, symmetrically layered, and the free height of the pouring shall not exceed 2.0m. During the concrete pouring process, observe the conditions of the formwork, brackets, steel bars, embedded parts and reserved holes. If deformation or displacement is found, take timely measures to deal with it. The concrete pouring operation shall not be blocked for more than 2 hours due to accidents, otherwise it shall be treated as a joint. After the concrete is poured, it is vibrated with an inserted vibrator. The use of the vibrator must comply with the following regulations:
[0221] ① The vibration time at each vibration point should be until the concrete surface shows floating slurry and no longer sinks significantly. Insert the concrete quickly and pull it out slowly during vibration.
[0222] ② The moving distance of the vibrating rod shall not be greater than 1.5 times the effective radius of the vibrating rod.
[0223] ③ The distance between the vibrating rod and the formwork should not be greater than 0.5 times of its effective radius, and avoid collision with steel bars, formwork, embedded parts, etc.
[0224] ④ The depth of the vibrator inserted into the lower layer of concrete shall not be less than 50mm.
[0225] (5) Concrete curing
[0226] Concrete curing: After the concrete reaches the demoulding strength specified in the design or specification, it is watered and cured, and the continuous curing time is not less than 28 days. During the curing period, the concrete surface is always kept moist, and a dedicated person is assigned to be responsible for the concrete curing, and detailed records are kept. The other parts of this embodiment are the same as the above embodiment and will not be repeated here.
[0227] Embodiment 10:
[0228] Based on the above embodiment, this embodiment further defines the specific content of concrete protection, and after the bottom plate concrete is poured and cured for 3 days, the trestle is moved, and a layer of slag or graded crushed stone is added after the bottom plate concrete is covered with geotextile to protect the bottom plate concrete, while meeting the conditions for the passage of mechanical equipment. The rest of this embodiment is the same as the above embodiment and will not be repeated.
[0229] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.
Claims
1. A lining construction method for a water conveyance tunnel, characterized in that: The following steps are involved: (1) Carry out base lining construction; (2) The side arch lining construction shall be carried out after the bottom lining has advanced by more than three units; (3) Control the distance between concrete pouring and excavation face according to the surrounding rock type.
2. A lining construction method for a water conveyance tunnel according to claim 1, characterized in that: In step (1), the specific process of bottom plate lining construction is as follows: (1.1) Install the lining trolley; (1.2) Clean the foundation surface and construction joints, and accept the inspection by all parties after the cleaning is completed; (1.3) Complete the processing and installation of steel bars, and inspect and accept the installed steel bars; (1.4) Positioning the self-propelled hydraulic trestle trolley; (1.5) Install the head plate and carry out water-stopping construction. After the construction is completed, open the warehouse for acceptance; (1.6) Transport concrete, carry out the concrete pouring process, and finally carry out concrete curing; (1.7) Repeat the above steps and proceed to the next lining section.
3. A lining construction method for a water conveyance tunnel according to claim 2, characterized in that: In the step (1.2), the cleaning process of the foundation surface is as follows: the bottom is first cleaned by an excavator to remove a large amount of slag, and then cleaned manually; After cleaning, use a full-section scanner to scan and process the under-excavated parts. After processing, scan again to generate data. Finally, manual cleaning is used to carry out the final cleaning. When manually cleaning the bottom, a triangular shovel is used to remove the loose rocks, and then a bamboo brush is used to clean the gravel in the rock cracks. Then high-pressure wind or high-pressure water is used to rinse. After repeated attempts, the acceptance standards are met.
4. A lining construction method for a water conveyance tunnel according to claim 3, characterized in that: In the step (1.2), the cleaning process of the construction joint is: using a high-pressure water flushing machine to perform flushing treatment; The roughening is carried out from left to right along the wide band trajectory where the jet contacts the concrete surface, with a small amount of overlap, to completely remove the cement latex on the concrete surface, leaving only a little small stones. That is, the total area of small stones with a particle size of 5.0 mm or more accounts for 20% to 30% of the roughening area, and the unevenness is controlled within ±2mm3mm without damaging the aggregate.
5. A lining construction method for a water conveyance tunnel according to any one of claims 2 to 4, characterized in that: In step (2), the specific process of carrying out the side top arch lining construction is as follows: (2.1) Monitoring and measurement to determine the time for lining application; (2.2) Make good preparations for construction; (2.3) Confirm that the lining trolley is in place and tie the steel bars that match the lining; (2.4) Mobile trolley; (2.4) Applying a release agent on the template surface; (2.5) Positioning the lining trolley through the template installation process; (2.6) Apply annular waterstop strips or waterstop belts; (2.7) Conduct quality inspection; (2.8) pouring concrete; (2.9) After the concrete solidifies, remove the formwork and carry out concrete curing; (2.10) Repeat the above steps and proceed to the next lining section.
6. A lining construction method for a water conveyance tunnel according to claim 5, characterized in that: The construction preparation in step (2.4) includes (2.2.1) Check the centerline horizontal layout; (2.2.2) Laying of lining trolley track.
7. A lining construction method for a water conveyance tunnel according to claim 6, characterized in that: The positioning process of the lining trolley in step (2.5) includes: (2.5.1) Horizontal positioning of the mold; (2.5.2) Centerline positioning mold; (2.5.3) Installation of embedded parts.
8. A lining construction method for a water conveyance tunnel according to claim 7, characterized in that: In the step (2.8), the concrete is transported by a transport vehicle or pumped by a transport pump.
9. A lining construction method for a water conveyance tunnel according to claim 8, characterized in that: The trolley used in the bottom plate lining construction is a self-propelled hydraulic trestle trolley, and the trolley used in the side top arch lining is a hydraulic steel mold trolley.