Power transformer operation condition verification system and method
Through the power transformer operating condition verification system, power transformers and thyristor groups are used to provide rated voltage and control output current, and reduce external power absorption through power feedback, solving the problem of large power supply power demand during verification of large power transformers, and achieving a long time Possibility of verification.
Patent Information
- Application Number
- CN202411162764.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-23
- Publication Date
- 2024-11-12
AI Technical Summary
Large power transformers require rated voltage and rated capacity during operating conditions verification, which leads to excessive demand for power supply and is difficult to achieve long-term verification.
A power transformer operating condition verification system is designed, including power transformer, transformer to be tested, rectifier transformer, rectifier thyristor group, converter thyristor group and converter transformer. By adjusting the trigger angle of power transformer and thyristor group, the rated voltage is provided. And control the output current, rectifying and inverting power supply back to the external power supply, reducing the system's power absorption of the external power supply.
It greatly reduces the power demand for external power supplies, reduces the power consumed by the system, and is easy to verify in long-term operating conditions.
Smart Images

Figure CN118937854A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power transformers, and in particular to a system and method for verifying the operating conditions of power transformers. Background Art
[0002] Large power transformers need to be verified under various operating conditions, and they need to work at rated voltage and rated capacity. Since large power transformers have very large capacity, if they are to work at rated voltage and rated capacity, they need to be provided with extremely high power supply. This high power demand for power supply makes it difficult to verify power transformers for a long time. Summary of the invention
[0003] The present invention solves the technical problem of how to reduce the power demand of the power transformer operating condition verification on the power supply by providing a power transformer operating condition verification system and method.
[0004] On the one hand, the present invention provides the following technical solutions:
[0005] A power transformer operating condition verification system includes a power transformer, a transformer to be tested, a rectifier transformer, a rectifier thyristor group, a commutation thyristor group and a commutation transformer;
[0006] The primary winding of the power transformer is connected to an external power supply, the secondary winding of the power transformer is connected to the primary winding of the transformer to be tested, the secondary winding of the transformer to be tested is connected to the primary winding of the rectifier transformer, the secondary winding of the rectifier transformer is connected to the AC input end of the rectifier thyristor group, the DC output end of the rectifier thyristor group is connected to the DC input end of the commutation thyristor group, the AC output end of the commutation thyristor group is connected to the secondary winding of the converter transformer, and the primary winding of the converter transformer is connected to the external power supply.
[0007] Optionally, the rectifier transformer has two secondary windings, one of which is star-connected and the other is delta-connected; the rectifier transformer and the rectifier thyristor group form a 12-pulse controllable rectifier circuit.
[0008] Optionally, the converter transformer has two secondary windings, one of which is star-connected and the other is delta-connected; and the commutation thyristor group consists of 12 thyristors.
[0009] Optionally, a smoothing reactor is connected between the positive pole of the DC output end of the rectifying thyristor group and the negative pole of the DC input end of the commutating thyristor group, and between the negative pole of the DC output end of the rectifying thyristor group and the positive pole of the DC input end of the commutating thyristor group.
[0010] Optionally, circuit breakers are connected between the external power supply and the power transformer, between the power transformer and the transformer to be tested, between the transformer to be tested and the rectifier transformer, and between the converter transformer and the external power supply.
[0011] Optionally, the external power source is a power grid.
[0012] On the other hand, the present invention also provides the following technical solutions:
[0013] A method for verifying the operating condition of a power transformer is applied to any of the above-mentioned systems for verifying the operating condition of a power transformer, and the method comprises:
[0014] Adjusting the tapping position of the secondary winding of the power transformer so that the output voltage of the power transformer is the rated voltage of the transformer to be tested;
[0015] Adjusting the trigger angles of the rectifier thyristor group and the commutation thyristor group to control the output current of the transformer to be tested;
[0016] Detect various performance parameters of the transformer to be tested, and verify the performance of the transformer to be tested according to the performance parameters.
[0017] Optionally, adjusting the trigger angles of the rectifying thyristor group and the commutating thyristor group to control the output current of the transformer to be tested includes:
[0018] The trigger angles of the rectifying thyristor group and the commutating thyristor group are adjusted to control the output current of the transformer to be tested to be the rated current.
[0019] Optionally, adjusting the trigger angles of the rectifying thyristor group and the commutating thyristor group to control the output current of the transformer to be tested includes:
[0020] The trigger angles of the rectifying thyristor group and the commutating thyristor group are continuously adjusted to continuously change the output current of the transformer to be tested.
[0021] Optionally, adjusting the trigger angles of the rectifying thyristor group and the commutating thyristor group to control the output current of the transformer to be tested includes:
[0022] The trigger angles of the rectifying thyristor group and the commutating thyristor group are adjusted to control the output current of the transformer to be tested to be greater than the rated current of the transformer to be tested.
[0023] One or more technical solutions provided by the present invention have at least the following technical effects or advantages:
[0024] The system of the present invention includes a power transformer, a transformer to be tested, a rectifier transformer, a rectifier thyristor group, a commutation thyristor group and a converter transformer. The power transformer can provide a rated voltage for the transformer to be tested. The rectifier transformer, the rectifier thyristor group, the commutation thyristor group and the converter transformer serve together as the load of the transformer to be tested, and also serve together as a path for electric energy feedback to feed electric energy back to an external power supply. Electric energy feedback can greatly reduce the external power energy absorbed by the system. The electric energy consumed by the entire system is mainly the loss of the power transformer, the transformer to be tested, the rectifier transformer, the rectifier thyristor group, the commutation thyristor group and the converter transformer, which is much less than the capacity of the transformer to be tested, greatly reducing the power demand for the external power supply, and facilitating long-term working condition verification. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings in the following description are some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying any creative work.
[0026] Figure 1 Schematic diagram of a power transformer operating condition verification system according to an embodiment of the present invention;
[0027] Figure 2 Another schematic diagram of a power transformer operating condition verification system according to an embodiment of the present invention;
[0028] Figure 3 The present invention is a flowchart of a method for verifying the operating condition of a power transformer in an embodiment of the present invention.
[0029] Description of reference numerals:
[0030] 10-power transformer; 20-transformer to be tested; 30-rectifier transformer; 40-rectifier thyristor group; 50-commutation thyristor group; 60-commutation transformer; 70-smoothing reactor; 80-circuit breaker. DETAILED DESCRIPTION
[0031] The embodiments of the present invention solve the technical problem of how to reduce the power demand of the power transformer operating condition verification on the power supply by providing a power transformer operating condition verification system and method.
[0032] In order to better understand the technical solution of the present invention, the technical solution of the present invention will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0033] like Figure 1As shown, the power transformer operating condition verification system of the embodiment of the present invention includes a power transformer, a transformer to be tested, a rectifier transformer, a rectifier thyristor group, a commutation thyristor group and a commutation transformer;
[0034] Among them, the primary winding of the power transformer is connected to an external power supply, the secondary winding of the power transformer is connected to the primary winding of the transformer to be tested, the secondary winding of the transformer to be tested is connected to the primary winding of the rectifier transformer, the secondary winding of the rectifier transformer is connected to the AC input end of the rectifier thyristor group, the DC output end of the rectifier thyristor group is connected to the DC input end of the commutation thyristor group, the AC output end of the commutation thyristor group is connected to the secondary winding of the converter transformer, and the primary winding of the converter transformer is connected to the external power supply.
[0035] Among them, the external power supply can be a power grid or a high-power power supply. When verifying the operating condition of the transformer under test, if the working voltage of the transformer under test is lower than the rated voltage, the verification result is unreliable; if the working voltage of the transformer under test is higher than the rated voltage, the transformer under test may be damaged due to overexcitation. Therefore, it is necessary to make the transformer under test work at the rated voltage. The power transformer is used to provide the rated voltage for the transformer under test. By adjusting the tap position of the secondary winding of the power transformer, the output voltage of the power transformer can be adjusted, that is, the working voltage of the transformer under test can be adjusted. The rectifier transformer and the rectifier thyristor group are used to rectify the AC output of the transformer to be tested, and the commutation thyristor group and the commutation transformer are used to invert the DC output of the rectifier thyristor group and feed back the electric energy to the external power supply. When the external power supply is the power grid, the electric energy is fed back to the power grid. Considering that if the transformer to be tested is not loaded, the transformer to be tested will have no output current and be in a no-load state, and the working condition verification cannot be completed, the rectifier transformer, the rectifier thyristor group, the commutation thyristor group and the commutation transformer are used together as the load of the transformer to be tested, and also as the path for electric energy feedback. Electric energy feedback can greatly reduce the external power energy absorbed by the system. The electric energy consumed by the entire system is mainly the loss of the power transformer, the transformer to be tested, the rectifier transformer, the rectifier thyristor group, the commutation thyristor group and the commutation transformer, which is much less than the capacity of the transformer to be tested, greatly reducing the power demand for the external power supply, and facilitating long-term working condition verification.
[0036] Specifically, Figure 2As shown, the rectifier transformer can have two secondary windings, one of which is star-connected and the other is angle-connected; the rectifier transformer and the rectifier thyristor group form a 12-pulse controllable rectifier circuit. The rectifier thyristor group consists of 12 thyristors, and the 12 thyristors are turned on in turn in each power frequency cycle. The rectifier thyristor group requires 12 sequential trigger pulses synchronized with the AC system, and the interval between the pulses is 30°. The rectifier current can be controlled by adjusting the trigger angle of the rectifier thyristor, that is, the output current of the transformer to be tested can be controlled. The trigger angle of the rectifier thyristor group is between 0 and 90°. The converter transformer can have two secondary windings, one of which is star-connected and the other is angle-connected; the converter transformer and the commutation thyristor group form an active inverter circuit. The commutation thyristor group consists of 12 thyristors, and the 12 thyristors are turned on in turn in each power frequency cycle. The rectifier thyristor group requires 12 sequential trigger pulses synchronized with the AC system, with a spacing of 30° between pulses. The current fed into the external power supply can be controlled by adjusting the trigger angle of the commutation thyristor, and the electric energy absorbed by the transformer to be tested can be fed back to the external power supply in conjunction with the controllable rectifier circuit. The trigger angle of the commutation thyristor group is between 90 and 180°.
[0037] Furthermore, considering that the DC power output by the rectifier thyristor group will fluctuate, such as Figure 2 As shown, smoothing reactors can be connected between the positive pole of the DC output end of the rectifier thyristor group and the negative pole of the DC input end of the commutation thyristor group, and between the negative pole of the DC output end of the rectifier thyristor group and the positive pole of the DC input end of the commutation thyristor group, for filtering the DC power output by the rectifier thyristor group and reducing the ripple of the DC power.
[0038] Furthermore, in order to better control system startup and power-off, such as Figure 2 As shown, circuit breakers may be connected between the external power supply and the power transformer, between the power transformer and the transformer to be tested, between the transformer to be tested and the rectifier transformer, and between the converter transformer and the external power supply.
[0039] like Figure 3 As shown, an embodiment of the present invention also provides a method for verifying the operating condition of a power transformer applied to any of the above power transformer operating condition verification systems, including:
[0040] Step S1, adjusting the tap position of the secondary winding of the power transformer so that the output voltage of the power transformer is the rated voltage of the transformer to be tested;
[0041] Step S2, adjusting the trigger angles of the rectifier thyristor group and the commutation thyristor group to control the output current of the transformer to be tested;
[0042] Step S3, detecting various performance parameters of the transformer to be tested, and verifying the performance of the transformer to be tested according to the performance parameters.
[0043] Step S1 is used to make the transformer under test operate at the rated voltage. Wherein, step S2 may include: adjusting the trigger angle of the rectifier thyristor group and the commutation thyristor group to control the output current of the transformer under test to be the rated current. The output current of the transformer under test is the rated current, which means that the transformer under test operates in the rated load state, so that the operating condition of the transformer under the rated state can be verified. Step S2 may also include: constantly adjusting the trigger angle of the rectifier thyristor group and the commutation thyristor group to constantly change the output current of the transformer under test. The output current of the transformer under test is constantly changing, which means that the load state of the transformer under test is constantly changing, so that the load mutation adaptability of the transformer under test can be verified. Step S2 may also include: adjusting the trigger angle of the rectifier thyristor group and the commutation thyristor group to control the output current of the transformer under test to be greater than the rated current of the transformer under test. The output current of the transformer under test is greater than the rated current of the transformer under test, which means that the transformer under test operates in an overload state, so that the overload resistance of the transformer under test can be verified. In step S3, the performance parameters of the transformer to be tested may include current, voltage, temperature rise, vibration, gas content in oil, etc. The specific verification strategy is not introduced in detail here. After the verification test, the insulation material inside the transformer to be tested can also be extracted for aging performance analysis.
[0044] Although the preferred embodiments of the present invention have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the present invention.
[0045] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
Claims
1. A power transformer operating condition verification system, characterized in that: Including power transformer, transformer to be tested, rectifier transformer, rectifier thyristor group, commutation thyristor group and commutation transformer; The primary winding of the power transformer is connected to an external power supply, the secondary winding of the power transformer is connected to the primary winding of the transformer to be tested, the secondary winding of the transformer to be tested is connected to the primary winding of the rectifier transformer, the secondary winding of the rectifier transformer is connected to the AC input end of the rectifier thyristor group, the DC output end of the rectifier thyristor group is connected to the DC input end of the commutation thyristor group, the AC output end of the commutation thyristor group is connected to the secondary winding of the converter transformer, and the primary winding of the converter transformer is connected to the external power supply.
2. The power transformer operating condition verification system according to claim 1, characterized in that: The rectifier transformer has two secondary windings, one of which is star-connected and the other is delta-connected; the rectifier transformer and the rectifier thyristor group form a 12-pulse controllable rectifier circuit.
3. The power transformer operating condition verification system according to claim 1, characterized in that: The converter transformer has two secondary windings, one of which is star-connected and the other is delta-connected; the commutation thyristor group consists of 12 thyristors.
4. The power transformer operating condition verification system according to claim 1, characterized in that: Smoothing reactors are connected between the positive pole of the DC output end of the rectifying thyristor group and the negative pole of the DC input end of the commutating thyristor group, and between the negative pole of the DC output end of the rectifying thyristor group and the positive pole of the DC input end of the commutating thyristor group.
5. The power transformer operating condition verification system according to claim 1, characterized in that: Circuit breakers are connected between the external power supply and the power transformer, between the power transformer and the transformer to be tested, between the transformer to be tested and the rectifier transformer, and between the converter transformer and the external power supply.
6. The power transformer operating condition verification system according to claim 1, characterized in that: The external power source is a power grid.
7. A method for verifying the operating condition of a power transformer, applied to the system according to any one of claims 1 to 6, characterized in that: The method comprises: Adjusting the tapping position of the secondary winding of the power transformer so that the output voltage of the power transformer is the rated voltage of the transformer to be tested; Adjusting the trigger angles of the rectifier thyristor group and the commutation thyristor group to control the output current of the transformer to be tested; Detect various performance parameters of the transformer to be tested, and verify the performance of the transformer to be tested according to the performance parameters.
8. The method for verifying the operating condition of a power transformer according to claim 7, characterized in that: The step of adjusting the trigger angles of the rectifying thyristor group and the commutating thyristor group to control the output current of the transformer to be tested includes: The trigger angles of the rectifying thyristor group and the commutating thyristor group are adjusted to control the output current of the transformer to be tested to be the rated current.
9. The method for verifying the operating condition of a power transformer according to claim 7, characterized in that: The step of adjusting the trigger angles of the rectifying thyristor group and the commutating thyristor group to control the output current of the transformer to be tested includes: The trigger angles of the rectifying thyristor group and the commutating thyristor group are continuously adjusted to continuously change the output current of the transformer to be tested.
10. The method for verifying the operating condition of a power transformer according to claim 7, characterized in that: The step of adjusting the trigger angles of the rectifying thyristor group and the commutating thyristor group to control the output current of the transformer to be tested includes: The trigger angles of the rectifying thyristor group and the commutating thyristor group are adjusted to control the output current of the transformer to be tested to be greater than the rated current of the transformer to be tested.