Benefit evaluation method and device for coke ash content change and storage medium

By using a method for evaluating the benefits of changes in coke ash content, the problem of assessing the impact of coke ash content variations on the economic benefits of blast furnace ironmaking was solved. This method provides a reasonable range for coke price reductions, avoids economic losses, and improves work efficiency and the accuracy of data support.

CN118942570APending Publication Date: 2024-11-12YUN NAN YU XI YU KUN GANG TIE JI TUAN YOU XIAN GONG SI
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410787337.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-18
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The lack of an evaluation method in the current technology to accurately measure the impact of changes in coke ash content on the economic benefits of blast furnace ironmaking has led to unreasonable reductions in coke prices and economic losses.

Method used

This paper provides a method for evaluating the benefits of changes in coke ash content. By obtaining the chemical composition of benchmark coke ash content and high-ash coke, the paper calculates the feedstock for blast furnace ironmaking, calculates the amount of iron and fuel required to produce 1 ton of molten iron, obtains the daily molten iron output and steel output, calculates the cost and profit of molten iron, compares the daily profit of the two types of coke, and evaluates the benefits of changes in coke ash content.

Benefits of technology

It enables accurate evaluation of the impact of coke ash content changes on the economic benefits of blast furnace ironmaking, provides a reasonable range for coke price reductions, avoids economic losses caused by biased empirical data, and improves work efficiency and the accuracy of data support.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118942570A_ABST
    Figure CN118942570A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of blast furnace ironmaking, and particularly discloses a coke ash content change benefit evaluation method and device and a storage medium. The method comprises the steps that the average coke ash content under the normal production condition is obtained to serve as the standard coke ash content, the standard coke ash content is increased by a preset percentage, and the high-ash-content coke ash content is obtained; for blast furnace ironmaking production of the matched reference coke and the high-ash-content coke, performing burdening calculation of blast furnace ironmaking, and respectively obtaining comprehensive charging grades of the matched reference coke and the high-ash-content coke during blast furnace ironmaking; respectively obtaining the iron material quantity and the fuel quantity required for producing 1 ton of molten iron, the daily molten iron yield and the daily steel yield when the standard coke and the high-ash-content coke are used for blast furnace ironmaking; respectively obtaining the consumption of sintered ore, pellet ore and lump ore required by each ton of iron; daily profits are obtained respectively, and the benefit of coke ash content change is evaluated by comparing the daily profits when the two kinds of coke are used.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of blast furnace ironmaking, and in particular to a method, device and storage medium for evaluating the benefits of changes in coke ash content. Background Art

[0002] The ash content of ironmaking coke is an important basis for evaluating the quality of coke. The ash content of coke has a negative impact on the quality of coke. When the ash content of coke entering the factory increases, the price of coke needs to be reduced. In the past, there was no detailed and accurate calculation of the reduction in the price of coke when the ash content of coke increased, based on the actual production and market conditions. Instead, it was roughly estimated based on other factories or past experience, and the same empirical data was used regardless of the coke price and the profit per ton of steel. When the coke price and the profit per ton of steel change greatly, this empirical data will have a large deviation, and the price reduction will be too small, causing great economic losses to Party A (the party purchasing coke). Therefore, it is necessary to provide a benefit evaluation method for the change of coke ash content, and to make a more reasonable and accurate calculation of the impact of the change of ironmaking coke composition on the coke price. Summary of the invention

[0003] The purpose of the present application is to provide a method, device and storage medium for evaluating the benefits of changes in coke ash content, so as to solve the problem in the prior art that an evaluation method is needed to reflect the impact of changes in coke ash content on the economic benefits of blast furnace ironmaking.

[0004] To achieve the above-mentioned purpose, the embodiment of the present application provides a method for evaluating the benefit of coke ash content change, comprising the following steps: obtaining the average ash content of coke under normal production conditions as a reference coke ash content, increasing the reference coke ash content by a preset percentage to obtain a high-ash coke ash content, performing a batching calculation for blast furnace ironmaking production using the reference coke and the high-ash coke, and respectively obtaining the comprehensive furnace entry grade when the reference coke and the high-ash coke are used for blast furnace ironmaking;

[0005] Obtain the amount of iron material and fuel required to produce 1 ton of molten iron when using standard coke and high-ash coke for blast furnace ironmaking, as well as the daily molten iron output and daily steel output;

[0006] Obtain the consumption of sintered ore, pelletized ore and lump ore per ton of iron when using standard coke and high-ash coke for blast furnace ironmaking;

[0007] The molten iron cost was calculated for blast furnace ironmaking using base coke and high-ash coke, and the cost per ton of steel corresponding to the two types of coke was obtained. Then the corresponding profit per ton of steel and daily profit were derived. The benefit of changes in coke ash content was evaluated by comparing the daily profits when the two types of coke were used.

[0008] Optionally, for blast furnace ironmaking production using reference coke and high-ash coke, the batching calculation for blast furnace ironmaking is performed, and the comprehensive furnace entry grades when the reference coke and high-ash coke are used for blast furnace ironmaking are obtained, respectively, specifically including:

[0009] Based on the chemical composition of benchmark coke and high-ash coke, as well as the chemical composition of the iron materials required for blast furnace ironmaking, the proportioning calculation is carried out according to the set slag basicity and molten iron silicon content, and the proportions of various iron materials when using benchmark coke and high-ash coke are obtained respectively. Then, based on the iron content of each iron material, the comprehensive furnace entry grade when using benchmark coke and high-ash coke for blast furnace ironmaking is obtained respectively.

[0010] Optionally, the step of respectively obtaining the comprehensive charging grade of the blast furnace when using the reference coke and the high-ash coke for blast furnace ironmaking specifically includes:

[0011] Using the formula: comprehensive charging grade = sintered ore proportion × sintered ore iron content + pellet ore proportion × pellet ore iron content + lump ore proportion × lump ore iron content, the comprehensive charging grade when using base coke and high ash coke for blast furnace ironmaking is obtained respectively.

[0012] Optionally, the step of obtaining the amount of iron required to produce 1 ton of molten iron when using the reference coke and the high-ash coke for blast furnace ironmaking specifically includes:

[0013] The formula: the amount of iron required to produce 1 ton of molten iron = 1 × iron content in molten iron / recovery rate of iron element / comprehensive furnace grade, is used to obtain the amount of iron required to produce 1 ton of molten iron when using standard coke and high-ash coke for blast furnace ironmaking.

[0014] When obtaining the reference coke, the amount of fuel required to produce 1 ton of molten iron specifically includes:

[0015] Obtain the amount of fuel required for a blast furnace to produce 1 ton of molten iron using standard coke under normal production conditions;

[0016] When obtaining high-ash coke, the amount of fuel required to produce 1 ton of molten iron specifically includes:

[0017] Using a fixed coal ratio, the calculation is based on a 1% increase in coke ash content and a 2% increase in coke ratio. The comprehensive furnace grade is increased or decreased by 1%, and the fuel ratio is decreased or increased by 1.75%. The coke ratio when high-ash coke is used for blast furnace smelting is obtained. The coke ratio is then added to the coal ratio to obtain the amount of fuel required to produce 1 ton of molten iron.

[0018] The daily molten iron output when obtaining the benchmark coke is specifically comprised of:

[0019] Obtain the daily molten iron output of the blast furnace when equipped with reference coke under normal production conditions;

[0020] The method of obtaining the daily molten iron output when using high-ash coke specifically includes:

[0021] According to the principle that when the ash content of coke increases by 1%, the molten iron output increases by 2.5%; and when the comprehensive furnace grade increases or decreases by 1%, the output increases or decreases by 2.5%, the comprehensive furnace grade when high-ash coke is used is compared with the comprehensive furnace grade when standard coke is used, and the daily molten iron output when high-ash coke is used can be calculated;

[0022] The daily steel production when using the base coke and the high-ash coke for blast furnace ironmaking is obtained respectively, specifically including:

[0023] Using the formula: daily steel production = (daily molten iron production / ton of steel water consumption) × steelmaking billet qualification rate × steel rolling process yield rate, the corresponding daily steel production when using base coke and high-ash coke can be obtained respectively.

[0024] Optionally, the consumption of sintered ore, pelletized ore, and lump ore required to obtain one ton of iron specifically includes:

[0025] Using the formula:

[0026] The consumption of sintered ore per ton of iron = the amount of iron required to produce 1 ton of molten iron × the proportion of sintered ore.

[0027] The lump ore consumption required for one ton of iron = the amount of iron required to produce one ton of molten iron × lump ore ratio,

[0028] The consumption of pellets per ton of iron = the amount of iron required to produce 1 ton of molten iron × the proportion of pellets.

[0029] The consumption of sintered ore, pelletized ore and lump ore required to obtain a ton of iron.

[0030] Optionally, the molten iron cost is calculated for blast furnace ironmaking using reference coke and high-ash coke, respectively, and specifically includes:

[0031] Obtaining the unit prices of various raw materials and fuels required for blast furnace ironmaking, including coal powder, sintered ore, pelletized ore, and lump ore, obtaining the unit price of benchmark coke, and obtaining the unit price of high-ash coke, wherein the unit price of the high-ash coke is lower than the unit price of the benchmark coke by a preset value;

[0032] The cost of a ton of iron is calculated based on the consumption of sintered ore, pelletized ore, and lump ore required for a ton of iron, as well as the coke ratio and coal ratio, plus the capacity energy consumption, wages and benefits, spare parts and auxiliary materials consumption, and coal gas and dust ash recovery costs.

[0033] Optionally, the cost per ton of steel corresponding to the use of two types of cokes respectively comprises:

[0034] Using the formula: cost per ton of steel = cost per ton of iron + processing fee of steelmaking process + processing fee of steel rolling process, the corresponding cost per ton of steel is obtained when using standard coke and high ash coke;

[0035] The corresponding profit per ton of steel and daily profit are obtained respectively, specifically including:

[0036] Using the formula: profit per ton of steel = selling price per ton of steel - cost per ton of steel, we can get the corresponding profit per ton of steel when using standard coke and high-ash coke;

[0037] Using the formula: daily profit = daily steel output × profit per ton of steel, we can obtain the corresponding daily profit when using base coke and high-ash coke.

[0038] Optionally, after respectively obtaining the corresponding profit per ton of steel and daily profit, the method further includes:

[0039] Correct the preset value that the unit price of high-ash coke is lower than the unit price of benchmark coke until the daily profits corresponding to the use of benchmark coke and high-ash coke are equal, and the preset percentage increase in coke ash content is obtained, and the reasonable value to which the coke price should be lowered is obtained.

[0040] To achieve the above-mentioned purpose, the present application also provides a benefit evaluation device for coke ash content change, comprising: a storage device; and

[0041] A processor connected to the memory, the processor being configured to execute the steps of the method as described above.

[0042] To achieve the above objectives, the present application also provides a computer storage medium on which a computer program is stored, wherein the computer program implements the steps of the above method when executed by a machine.

[0043] The embodiments of the present application have the following advantages:

[0044] The embodiment of the present application provides a method for evaluating the benefits of changes in coke ash content, including: obtaining an average ash content of coke under normal production conditions as a benchmark coke ash content, increasing the benchmark coke ash content by a preset percentage to obtain a high-ash coke ash content, and performing a batching calculation for blast furnace ironmaking production using the benchmark coke and the high-ash coke, and respectively obtaining a comprehensive furnace entry grade when the benchmark coke and the high-ash coke are used for blast furnace ironmaking; and obtaining the production of 1 ton of iron when the benchmark coke and the high-ash coke are used for blast furnace ironmaking. The amount of iron and fuel required for blast furnace ironmaking, as well as the daily molten iron output and daily steel output; obtain the consumption of sintered ore, pelletized ore and lump ore per ton of iron when using base coke and high-ash coke for blast furnace ironmaking; calculate the molten iron cost for blast furnace ironmaking using base coke and high-ash coke, and obtain the cost per ton of steel corresponding to the use of the two types of coke, and then obtain the corresponding profit per ton of steel and daily profit, and evaluate the benefits of changes in coke ash content by comparing the daily profits when the two types of coke are used.

[0045] Through the above method, firstly, the average ash content of coke under normal production conditions is obtained as the benchmark coke ash content, and then a preset ash content increase percentage is set to simulate the use of high-ash coke. Then, the batching calculation and comprehensive furnace grade analysis are performed on the blast furnace ironmaking production equipped with benchmark coke and high-ash coke, and the key data such as the amount of iron material, the amount of fuel, the daily molten iron output, and the daily steel output required to produce 1 ton of molten iron are further obtained. On this basis, by calculating the consumption of sintered ore, pelletized ore, and lump ore required for a ton of iron, and calculating the cost of molten iron, the cost and profit per ton of steel corresponding to the use of two types of coke are obtained. Finally, by comparing the daily profits when the two types of coke are used, the benefits of the change in coke ash content are evaluated. Thereby solving the problem of the need for an evaluation method in the prior art to reflect the impact of coke ash changes on the economic benefits of blast furnace ironmaking. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] In order to more clearly illustrate the implementation methods of the present application or the technical solutions in the prior art, the following briefly introduces the drawings required for the implementation methods or the description of the prior art. Obviously, the drawings described below are only exemplary, and for ordinary technicians in this field, other implementation drawings can be derived from the provided drawings without creative work.

[0047] Figure 1 A flow chart of a method for evaluating the benefits of coke ash content changes provided in at least one embodiment of the present application;

[0048] Figure 2 A module block diagram of a benefit evaluation device for coke ash content variation provided in at least one embodiment of the present application. DETAILED DESCRIPTION

[0049] The following is a description of the implementation of the present application by specific specific embodiments. People familiar with the technology can easily understand other advantages and effects of the present application from the contents disclosed in this specification. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.

[0050] It should be noted that the steps in the claims and description of the present application may be executed substantially in parallel or in reverse order under appropriate circumstances, depending on the functions involved.

[0051] In addition, the technical features involved in the different embodiments of the present application described below can be combined with each other as long as they do not conflict with each other.

[0052] An embodiment of the present application provides a method for evaluating the benefits of coke ash content changes, referring to Figure 1 , Figure 1 A flow chart of a method for evaluating the benefits of changes in coke ash content is provided in at least one embodiment of the present application. It should be understood that the method may also include additional boxes not shown and / or the boxes shown may be omitted, and the scope of the present application is not limited in this respect.

[0053] At step 101, the average ash content of coke under normal production conditions is obtained as the benchmark coke ash content, and the benchmark coke ash content is increased by a preset percentage to obtain the high-ash coke ash content. For blast furnace ironmaking production using the benchmark coke and the high-ash coke, the blast furnace ironmaking ingredients are calculated, and the comprehensive furnace entry grades when the benchmark coke and the high-ash coke are used for blast furnace ironmaking are respectively obtained.

[0054] Specifically, according to local raw material conditions, the average ash content of coke under normal production conditions is used as a benchmark, and the benchmark coke is the coke under normal production conditions (for example, the ash content is 13.8%), and the ash content of another coke is increased by 1% (for example, 14.8%, called high-ash coke). For blast furnace ironmaking production using these two cokes, the batching calculation for blast furnace ironmaking is performed. The chemical composition of the two cokes (the ash content of the cokes is 13.8% and 14.8%, respectively) and the chemical composition of the iron materials (sintered ore, pelletized ore, lump ore, etc.) required for blast furnace ironmaking are listed in the batching calculation table, and the batching calculation is performed according to the set slag basicity and molten iron silicon content. The proportion of various iron materials when the two cokes are used is obtained, and then the comprehensive furnace grade (i.e., the iron content of the furnace iron materials, in %) when the two cokes are used for blast furnace ironmaking is obtained according to the iron content of each iron material. In some embodiments, the calculation formula is: comprehensive furnace grade = sintered ore ratio × sintered ore iron content + pellet ore ratio × pellet ore iron content + lump ore ratio × lump ore iron content.

[0055] At step 102, the amount of iron material and fuel required to produce 1 ton of molten iron when using the base coke and the high-ash coke for blast furnace ironmaking, as well as the daily molten iron output and daily steel output are obtained respectively.

[0056] Specifically, the amount of iron material is the ore consumption, the unit is t / t, and the amount of fuel is the fuel ratio, the unit is t / t. Fuel ratio = coke ratio + coal ratio.

[0057] In some embodiments, the iron content in the molten iron (in %) and the recovery rate of the iron element (in %) are set, and the amount of iron material (ore consumption) required to produce 1 ton of molten iron = 1×iron content in the molten iron / recovery rate of the iron element / comprehensive grade of the furnace. The amount of iron material required to produce 1 ton of molten iron when the two types of coke are used for blast furnace ironmaking can be obtained.

[0058] In some embodiments, the amount of fuel required to produce 1 ton of molten iron in a blast furnace equipped with reference coke under normal production conditions (i.e., the fuel ratio, in t / t) is calculated, and the fuel ratio includes the coal ratio (the amount of coal powder required for a ton of iron) and the coke ratio (the amount of coke required for a ton of iron, including coke and coke diced in the furnace), calculated on a dry basis. A fixed coal ratio is used, and then the calculation is performed according to the increase of 1% in the ash content of the coke and the increase of 2% in the coke ratio, and the comprehensive increase or decrease of 1% in the furnace grade and the decrease or increase of 1.75% in the fuel ratio, to obtain the coke ratio when high-ash coke is used for blast furnace smelting, and then the coke ratio is added to the coal ratio to obtain the fuel ratio.

[0059] In some embodiments, the daily molten iron output when using the reference coke under normal production conditions is calculated. Then, according to the fact that the molten iron output increases by 2.5% when the ash content of coke increases by 1% and the output increases or decreases by 2.5% when the comprehensive furnace grade increases or decreases by 1%, the comprehensive furnace grade when using high-ash coke is compared with the comprehensive furnace grade when using the reference coke, and the daily molten iron output when using high-ash coke is calculated.

[0060] In some embodiments, the steelmaking process's molten iron consumption per ton (in t / t), the steelmaking billet qualification rate (in %), and the steel rolling process's yield rate (in %) are set, and the daily steel production = (daily molten iron production / ton of steelmaking consumption) × steelmaking billet qualification rate × steel rolling process's yield rate can be obtained. The daily steel production corresponding to the use of two types of coke is obtained.

[0061] In step 103, the consumption of sintered ore, pelletized ore and lump ore per ton of iron when using the base coke and the high-ash coke for blast furnace ironmaking is obtained respectively.

[0062] In some embodiments, the sintering ore consumption required for one ton of iron = the amount of iron material (ore consumption) required to produce one ton of molten iron × the sintering ore ratio,

[0063] The lump ore consumption required for one ton of iron = the amount of iron material (ore consumption) required to produce one ton of molten iron × lump ore ratio,

[0064] The consumption of pellets required for one ton of iron = the amount of iron required to produce one ton of molten iron (ore consumption) × the ratio of pellets.

[0065] At step 104, the molten iron cost is calculated for blast furnace ironmaking using base coke and high-ash coke, respectively, and the cost per ton of steel corresponding to the two types of coke is obtained, and then the corresponding profit per ton of steel and daily profit are obtained, and the benefit of the change in coke ash content is evaluated by comparing the daily profit when the two types of coke are used.

[0066] In some embodiments, the unit prices of various raw materials such as coal powder, sintered ore, pelletized ore, and lump ore required for blast furnace ironmaking are obtained, and the unit price of benchmark coke is obtained. Then, for the unit price of high-ash coke, it is first assumed that it is lower than the unit price of benchmark coke by a certain preset data, and this preset data is x (for example, x=40 is first assumed), and the unit price of high-ash coke = benchmark coke unit price-x is obtained. Then, according to the consumption of sintered ore, pelletized ore, and lump ore required to produce 1 ton of molten iron, as well as the coke ratio and coal ratio, the above data are included in the cost calculation table, and the capacity energy consumption, wages and benefits, spare parts and auxiliary material consumption, coal gas and dust ash recovery, etc. are added. Thus, the cost per ton of iron is calculated.

[0067] In some embodiments, based on past production practices, the processing fees of the steelmaking process and the steel rolling process under normal production conditions are calculated. The cost per ton of steel = the cost of a ton of iron + the processing fee of the steelmaking process + the processing fee of the steel rolling process. The corresponding cost per ton of steel when two types of coke are used can be obtained.

[0068] In some embodiments, profit per ton of steel = selling price per ton of steel - cost per ton of steel, which can be used to calculate the corresponding profit per ton of steel when two types of coke are used.

[0069] In some embodiments, daily profit = daily steel production × profit per ton of steel can be used to obtain the daily profit corresponding to the use of two types of coke. By comparing the daily profits, the benefits of the change in coke ash content can be evaluated.

[0070] In some embodiments, the method further includes: correcting the x value, and finally obtaining a reasonable value that the coke price should be reduced when the coke ash content increases by 1%.

[0071] Specifically, compare the daily profits corresponding to the use of two types of coke, and then correct the x value. When the daily profits corresponding to the use of the two types of coke are equal, the x value at this time is the reasonable value to which the coke price should be lowered under the current conditions (including a certain steel selling price, benchmark coke unit price, coal powder unit price, sintered ore, pelletized ore and lump ore unit price, etc.). When the coke ash content increases by 1%, the coke price should be lowered.

[0072] Example of calculation results:

[0073] For example, when the benchmark coke unit price is RMB 2,250 / ton, this calculation method is used to calculate the extent to which the coke unit price should be reduced if the coke ash content increases by 1%. See Table 1 for details.

[0074] Table 1:

[0075] Profit per ton of steel (yuan / ton) Ash content increases by 1%, coke unit price should be reduced (yuan / ton) -100 31 0 38 100 45 200 52 300 59

[0076] When the benchmark coke unit price is RMB 2,550 / ton, this calculation method is used to work out the extent to which the coke unit price should be reduced if the coke ash content increases by 1%. See Table 2 for details.

[0077] Table 2:

[0078] Profit per ton of steel (yuan / ton) Ash content increases by 1%, coke unit price should be reduced (yuan / ton) -100 41 0 47.8 100 54.8 200 61.8 300 68.8

[0079] Referring to Table 1 and Table 2, it can be seen that when the coke price is higher or the profit per ton of steel is higher, the coke price should drop more when the ash content increases by 1%.

[0080] Through the above method, firstly, the average ash content of coke under normal production conditions is obtained as the benchmark coke ash content, and then a preset ash content increase percentage is set to simulate the use of high-ash coke. Then, the batching calculation and comprehensive furnace grade analysis are performed on the blast furnace ironmaking production equipped with benchmark coke and high-ash coke, and the key data such as the amount of iron material, the amount of fuel, the daily molten iron output, and the daily steel output required to produce 1 ton of molten iron are further obtained. On this basis, by calculating the consumption of sintered ore, pelletized ore, and lump ore required for a ton of iron, and calculating the cost of molten iron, the cost and profit per ton of steel corresponding to the use of two types of coke are obtained. Finally, by comparing the daily profits when the two types of coke are used, the benefits of the change in coke ash content are evaluated. Thereby solving the problem of the need for an evaluation method in the prior art to reflect the impact of coke ash changes on the economic benefits of blast furnace ironmaking.

[0081] Specifically, through the above method, it is possible to more accurately determine the extent to which the unit price of coke should be reduced when the ash content of coke increases, so as to have a clear idea in mind, provide data support for production control and procurement work, and play a guiding and optimizing role in production and procurement work. After adopting this calculation method, it is obtained that when the ash content increases at different coke prices and different tons of steel profits, the coke price should be reduced by how much, and it is concluded that when the coke price is higher or the profit per ton of steel is higher, the ash content and sulfur content increase, the coke price should decrease more. Moreover, coke is a bulk raw fuel, and the quantity purchased each time is relatively large. By adopting this test method, a more reasonable price reduction range can be obtained to prevent the economic losses to the enterprise due to the small price reduction range caused by empirical data. For example, when the ash content of a batch of incoming coke increases by 1%, if according to previous empirical data, 5 yuan will be deducted per ton, and the corresponding coke quantity for each batch is at least 20,000 tons, the economic loss of 100,000 yuan will be caused due to the small deduction. By adopting this method, similar economic losses can be avoided. Through the unified evaluation method, all calculation processes are programmed. As long as the original data is input, the calculation can be automatically performed within a few minutes to obtain the results, which improves work efficiency accordingly. It prevents the lack of a unified calculation method, which results in a lot of time and energy spent on meetings, discussions, calculations using different methods, or manual calculations, and then comparative analysis, thereby saving calculation time, simplifying the workflow, and improving work efficiency.

[0082] Figure 2 A block diagram of a benefit evaluation device for coke ash content variation provided in at least one embodiment of the present application. The device comprises:

[0083] Memory 201; and a processor 202 connected to the memory 201, the processor 202 being configured to: obtain an average ash content of coke under normal production conditions as a reference coke ash content, increase the reference coke ash content by a preset percentage to obtain a high-ash coke ash content, perform batching calculations for blast furnace ironmaking using the reference coke and the high-ash coke, and respectively obtain comprehensive furnace entry grades when the reference coke and the high-ash coke are used for blast furnace ironmaking;

[0084] Obtain the amount of iron material and fuel required to produce 1 ton of molten iron when using standard coke and high-ash coke for blast furnace ironmaking, as well as the daily molten iron output and daily steel output;

[0085] Obtain the consumption of sintered ore, pelletized ore and lump ore per ton of iron when using standard coke and high-ash coke for blast furnace ironmaking;

[0086] The molten iron cost was calculated for blast furnace ironmaking using base coke and high-ash coke, and the cost per ton of steel corresponding to the two types of coke was obtained. Then the corresponding profit per ton of steel and daily profit were derived. The benefit of changes in coke ash content was evaluated by comparing the daily profits when the two types of coke were used.

[0087] In some embodiments, the processor 202 is further configured to: for blast furnace ironmaking production using reference coke and high-ash coke, perform batching calculation for blast furnace ironmaking, and respectively obtain the comprehensive furnace entry grade when using reference coke and high-ash coke for blast furnace ironmaking, specifically including:

[0088] Based on the chemical composition of benchmark coke and high-ash coke, as well as the chemical composition of the iron materials required for blast furnace ironmaking, the proportioning calculation is carried out according to the set slag basicity and molten iron silicon content, and the proportions of various iron materials when using benchmark coke and high-ash coke are obtained respectively. Then, based on the iron content of each iron material, the comprehensive furnace entry grade when using benchmark coke and high-ash coke for blast furnace ironmaking is obtained respectively.

[0089] In some embodiments, the processor 202 is further configured to: the step of respectively obtaining the comprehensive furnace grades when using the reference coke and the high-ash coke for blast furnace ironmaking specifically includes:

[0090] Using the formula: comprehensive charging grade = sintered ore proportion × sintered ore iron content + pellet ore proportion × pellet ore iron content + lump ore proportion × lump ore iron content, the comprehensive charging grade when using base coke and high ash coke for blast furnace ironmaking is obtained respectively.

[0091] In some embodiments, the processor 202 is further configured to: the step of obtaining the amount of iron required to produce 1 ton of molten iron when using the reference coke and the high-ash coke for blast furnace ironmaking specifically includes:

[0092] The formula: the amount of iron required to produce 1 ton of molten iron = 1 × iron content in molten iron / recovery rate of iron element / comprehensive furnace grade, is used to obtain the amount of iron required to produce 1 ton of molten iron when using standard coke and high-ash coke for blast furnace ironmaking.

[0093] When obtaining the reference coke, the amount of fuel required to produce 1 ton of molten iron specifically includes:

[0094] Obtain the amount of fuel required for a blast furnace to produce 1 ton of molten iron using standard coke under normal production conditions;

[0095] When obtaining high-ash coke, the amount of fuel required to produce 1 ton of molten iron specifically includes:

[0096] Using a fixed coal ratio, the calculation is based on a 1% increase in coke ash content and a 2% increase in coke ratio. The comprehensive furnace grade is increased or decreased by 1%, and the fuel ratio is decreased or increased by 1.75%. The coke ratio when high-ash coke is used for blast furnace smelting is obtained. The coke ratio is then added to the coal ratio to obtain the amount of fuel required to produce 1 ton of molten iron.

[0097] The daily molten iron output when obtaining the benchmark coke is specifically comprised of:

[0098] Obtain the daily molten iron output of the blast furnace when equipped with reference coke under normal production conditions;

[0099] The method of obtaining the daily molten iron output when using high-ash coke specifically includes:

[0100] According to the principle that when the ash content of coke increases by 1%, the molten iron output increases by 2.5%; and when the comprehensive furnace grade increases or decreases by 1%, the output increases or decreases by 2.5%, the comprehensive furnace grade when high-ash coke is used is compared with the comprehensive furnace grade when standard coke is used, and the daily molten iron output when high-ash coke is used can be calculated;

[0101] The daily steel production when using the base coke and the high-ash coke for blast furnace ironmaking is obtained respectively, specifically including:

[0102] Using the formula: daily steel production = (daily molten iron production / ton of steel water consumption) × steelmaking billet qualification rate × steel rolling process yield rate, the corresponding daily steel production when using base coke and high-ash coke can be obtained respectively.

[0103] In some embodiments, the processor 202 is further configured to: the consumption of sintered ore, pelletized ore, and lump ore required for obtaining a ton of iron specifically includes:

[0104] Using the formula:

[0105] The consumption of sintered ore per ton of iron = the amount of iron required to produce 1 ton of molten iron × the proportion of sintered ore.

[0106] The lump ore consumption required for one ton of iron = the amount of iron required to produce one ton of molten iron × lump ore ratio,

[0107] The consumption of pellets per ton of iron = the amount of iron required to produce 1 ton of molten iron × the proportion of pellets.

[0108] The consumption of sintered ore, pelletized ore and lump ore required to obtain a ton of iron.

[0109] In some embodiments, the processor 202 is further configured to: calculate the molten iron cost for blast furnace ironmaking using the reference coke and the high-ash coke, respectively, including:

[0110] Obtaining the unit prices of various raw materials and fuels required for blast furnace ironmaking, including coal powder, sintered ore, pelletized ore, and lump ore, obtaining the unit price of benchmark coke, and obtaining the unit price of high-ash coke, wherein the unit price of the high-ash coke is lower than the unit price of the benchmark coke by a preset value;

[0111] The cost of a ton of iron is calculated based on the consumption of sintered ore, pelletized ore, and lump ore required for a ton of iron, as well as the coke ratio and coal ratio, plus the capacity energy consumption, wages and benefits, spare parts and auxiliary materials consumption, and coal gas and dust ash recovery costs.

[0112] In some embodiments, the processor 202 is further configured to: obtain the cost per ton of steel corresponding to the use of two types of coke, specifically including:

[0113] Using the formula: cost per ton of steel = cost per ton of iron + processing fee of steelmaking process + processing fee of steel rolling process, the corresponding cost per ton of steel is obtained when using standard coke and high ash coke;

[0114] The corresponding profit per ton of steel and daily profit are obtained respectively, specifically including:

[0115] Using the formula: profit per ton of steel = selling price per ton of steel - cost per ton of steel, we can get the corresponding profit per ton of steel when using standard coke and high-ash coke;

[0116] Using the formula: daily profit = daily steel output × profit per ton of steel, we can obtain the corresponding daily profit when using base coke and high-ash coke.

[0117] In some embodiments, the processor 202 is further configured to: after respectively obtaining the corresponding profit per ton of steel and daily profit, further include:

[0118] Correct the preset value that the unit price of high-ash coke is lower than the unit price of benchmark coke until the daily profits corresponding to the use of benchmark coke and high-ash coke are equal, and the preset percentage increase in coke ash content is obtained, and the reasonable value to which the coke price should be lowered is obtained.

[0119] The specific implementation method is referred to the aforementioned method embodiment and will not be described in detail here.

[0120] The present application may be a method, an apparatus, a system and / or a computer program product. The computer program product may include a computer-readable storage medium carrying computer-readable program instructions for executing various aspects of the present application.

[0121] Computer readable storage medium can be a tangible device that can hold and store instructions used by an instruction execution device. Computer readable storage medium can be, for example, but not limited to, an electrical storage device, a magnetic storage device, an optical storage device, an electromagnetic storage device, a semiconductor storage device, or any suitable combination thereof. More specific examples (non-exhaustive list) of computer readable storage medium include: a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), a static random access memory (SRAM), a portable compact disk read-only memory (CD-ROM), a digital versatile disk (DVD), a memory stick, a floppy disk, a mechanical encoding device, for example, a punch card or a convex structure in a groove on which instructions are stored, and any suitable combination thereof. The computer readable storage medium used here is not interpreted as a transient signal itself, such as a radio wave or other freely propagating electromagnetic wave, an electromagnetic wave propagated by a waveguide or other transmission medium (for example, a light pulse by an optical fiber cable), or an electrical signal transmitted by a wire.

[0122] The computer-readable program instructions described herein can be downloaded from a computer-readable storage medium to each computing / processing device, or downloaded to an external computer or external storage device via a network, such as the Internet, a local area network, a wide area network, and / or a wireless network. The network can include copper transmission cables, optical fiber transmissions, wireless transmissions, routers, firewalls, switches, gateway computers, and / or edge servers. The network adapter card or network interface in each computing / processing device receives the computer-readable program instructions from the network and forwards the computer-readable program instructions for storage in the computer-readable storage medium in each computing / processing device.

[0123] The computer program instructions for performing the operation of the present application can be assembler instructions, instruction set architecture (ISA) instructions, machine instructions, machine-related instructions, microcode, firmware instructions, state setting data, or source code or object code written in any combination of one or more programming languages, including object-oriented programming languages, such as Smalltalk, C++, etc., and conventional procedural programming languages, such as "C" language or similar programming languages. Computer-readable program instructions can be executed completely on a user's computer, partially on a user's computer, executed as an independent software package, partially on a user's computer, partially on a remote computer, or completely on a remote computer or server. In the case of a remote computer, the remote computer can be connected to the user's computer through any type of network, including a local area network (LAN) or a wide area network (WAN), or can be connected to an external computer (for example, using an Internet service provider to connect through the Internet). In some embodiments, by using the state information of a computer-readable program instruction to personalize an electronic circuit, such as a programmable logic circuit, a field programmable gate array (FPGA) or a programmable logic array (PLA), the electronic circuit can execute a computer-readable program instruction, thereby realizing various aspects of the present application.

[0124] Various aspects of the present application are described herein with reference to the flowcharts and / or block diagrams of the methods, devices (systems) and computer program products according to the embodiments of the present application. It should be understood that each box in the flowchart and / or block diagram and the combination of each box in the flowchart and / or block diagram can be implemented by computer-readable program instructions.

[0125] These computer-readable program instructions can be provided to a processing unit of a general-purpose computer, a special-purpose computer, or other programmable data processing device, thereby producing a machine, so that when these instructions are executed by the processing unit of the computer or other programmable data processing device, a device that implements the functions / actions specified in one or more boxes in the flowchart and / or block diagram is generated. These computer-readable program instructions can also be stored in a computer-readable storage medium, and these instructions cause the computer, programmable data processing device, and / or other equipment to work in a specific manner, so that the computer-readable medium storing the instructions includes a manufactured product, which includes instructions for implementing various aspects of the functions / actions specified in one or more boxes in the flowchart and / or block diagram.

[0126] Computer-readable program instructions may also be loaded onto a computer, other programmable data processing apparatus, or other device so that a series of operating steps are performed on the computer, other programmable data processing apparatus, or other device to produce a computer-implemented process, thereby causing the instructions executed on the computer, other programmable data processing apparatus, or other device to implement the functions / actions specified in one or more boxes in the flowchart and / or block diagram.

[0127] The flow chart and block diagram in the accompanying drawings show the possible architecture, function and operation of the system, method and computer program product according to multiple embodiments of the present application. In this regard, each square box in the flow chart or block diagram can represent a part of a module, program segment or instruction, and a part of the module, program segment or instruction includes one or more executable instructions for realizing the logical function of the specification. In some alternative implementations, the function marked in the square box can also occur in a sequence different from that marked in the accompanying drawings. For example, two continuous square boxes can actually be executed substantially in parallel, and they can also be executed in the opposite order sometimes, depending on the function involved. It should also be noted that each square box in the block diagram and / or flow chart, and the combination of the square boxes in the block diagram and / or flow chart can be realized by a dedicated hardware-based system that performs the function or action of the specification, or can be realized by a combination of special-purpose hardware and computer instructions.

[0128] Note that, unless otherwise directly stated, all features disclosed in this specification (including any attached claims, abstracts and drawings) may be replaced by alternative features for achieving the same, equivalent or similar purposes. Therefore, unless otherwise explicitly stated, each feature disclosed is only an example of a group of equivalent or similar features. Where used, further, preferably, further and more preferably are simple beginnings for elaborating another embodiment based on the aforementioned embodiment, and the content of the further, preferably, further or more preferably followed by the combination with the aforementioned embodiment constitutes a complete construction of another embodiment. Several further, preferably, further or more preferably settings following the same embodiment can be arbitrarily combined to form another embodiment.

[0129] Although the present application has been described in detail above with general descriptions and specific embodiments, it is obvious to those skilled in the art that some modifications or improvements may be made to the present application. Therefore, these modifications or improvements made without departing from the spirit of the present application all fall within the scope of protection claimed in the present application.

Claims

1. A method for evaluating the benefits of coke ash content changes. It is characterized in that The following steps are involved: The average ash content of coke under normal production conditions is obtained as the benchmark coke ash content, the benchmark coke ash content is increased by a preset percentage to obtain the high-ash coke ash content, and for blast furnace ironmaking production using the benchmark coke and the high-ash coke, the batching calculation of blast furnace ironmaking is performed, and the comprehensive furnace entry grade when the benchmark coke and the high-ash coke are used for blast furnace ironmaking is obtained respectively; Obtain the amount of iron material and fuel required to produce 1 ton of molten iron when using standard coke and high-ash coke for blast furnace ironmaking, as well as the daily molten iron output and daily steel output; Obtain the consumption of sintered ore, pelletized ore and lump ore per ton of iron when using standard coke and high-ash coke for blast furnace ironmaking; The molten iron cost was calculated for blast furnace ironmaking using base coke and high-ash coke, and the cost per ton of steel corresponding to the two types of coke was obtained. Then the corresponding profit per ton of steel and daily profit were derived. The benefit of changes in coke ash content was evaluated by comparing the daily profits when the two types of coke were used.

2. The method for evaluating the benefit of coke ash content variation according to claim 1, It is characterized in that The above-mentioned method of calculating the batching of blast furnace ironmaking using the reference coke and the high-ash coke, and obtaining the comprehensive furnace-feeding grade when the reference coke and the high-ash coke are used for blast furnace ironmaking, specifically includes: Based on the chemical composition of benchmark coke and high-ash coke, as well as the chemical composition of the iron materials required for blast furnace ironmaking, the proportioning calculation is carried out according to the set slag basicity and molten iron silicon content, and the proportions of various iron materials when using benchmark coke and high-ash coke are obtained respectively. Then, based on the iron content of each iron material, the comprehensive furnace entry grade when using benchmark coke and high-ash coke for blast furnace ironmaking is obtained respectively.

3. The benefit evaluation method of coke ash content variation according to claim 1, It is characterized in that The method of obtaining the comprehensive furnace grades when using the reference coke and the high-ash coke for blast furnace ironmaking specifically includes: Using the formula: comprehensive charging grade = sintered ore proportion × sintered ore iron content + pellet ore proportion × pellet ore iron content + lump ore proportion × lump ore iron content, the comprehensive charging grade when using base coke and high ash coke for blast furnace ironmaking is obtained respectively.

4. The method for evaluating the benefit of coke ash content variation according to claim 1, It is characterized in that The method of obtaining the amount of iron required to produce 1 ton of molten iron when using the reference coke and the high-ash coke for blast furnace ironmaking specifically includes: The formula: the amount of iron required to produce 1 ton of molten iron = 1 × iron content in molten iron / recovery rate of iron element / comprehensive furnace grade, is used to obtain the amount of iron required to produce 1 ton of molten iron when using standard coke and high-ash coke for blast furnace ironmaking. When obtaining the reference coke, the amount of fuel required to produce 1 ton of molten iron specifically includes: Obtain the amount of fuel required for a blast furnace to produce 1 ton of molten iron using standard coke under normal production conditions; When obtaining high-ash coke, the amount of fuel required to produce 1 ton of molten iron specifically includes: Using a fixed coal ratio, the calculation is based on a 1% increase in coke ash content and a 2% increase in coke ratio. The comprehensive furnace grade is increased or decreased by 1%, and the fuel ratio is decreased or increased by 1.75%. The coke ratio when high-ash coke is used for blast furnace smelting is obtained. The coke ratio is then added to the coal ratio to obtain the amount of fuel required to produce 1 ton of molten iron. The daily molten iron output when obtaining the benchmark coke is specifically comprised of: Obtain the daily molten iron output of the blast furnace when equipped with reference coke under normal production conditions; The method of obtaining the daily molten iron output when using high-ash coke specifically includes: According to the principle that when the ash content of coke increases by 1%, the molten iron output increases by 2.5%; and when the comprehensive furnace grade increases or decreases by 1%, the output increases or decreases by 2.5%, the comprehensive furnace grade when high-ash coke is used is compared with the comprehensive furnace grade when standard coke is used, and the daily molten iron output when high-ash coke is used can be calculated; The daily steel production when using the base coke and the high-ash coke for blast furnace ironmaking is obtained respectively, specifically including: Using the formula: daily steel production = (daily molten iron production / ton of steel water consumption) × steelmaking billet qualification rate × steel rolling process yield rate, the corresponding daily steel production when using base coke and high-ash coke can be obtained respectively.

5. The method for evaluating the benefit of coke ash content variation according to claim 1, It is characterized in that The consumption of sintered ore, pelletized ore and lump ore required to obtain one ton of iron specifically includes: Using the formula: The consumption of sintered ore per ton of iron = the amount of iron required to produce 1 ton of molten iron × the proportion of sintered ore. The lump ore consumption required for one ton of iron = the amount of iron required to produce one ton of molten iron × lump ore ratio, The consumption of pellets per ton of iron = the amount of iron required to produce 1 ton of molten iron × the proportion of pellets. The consumption of sintered ore, pelletized ore and lump ore required to obtain a ton of iron.

6. The method for evaluating the benefit of coke ash content variation according to claim 1, It is characterized in that The molten iron cost calculation for blast furnace ironmaking using reference coke and high-ash coke specifically includes: Obtaining the unit prices of various raw materials and fuels required for blast furnace ironmaking, including coal powder, sintered ore, pelletized ore, and lump ore, obtaining the unit price of benchmark coke, and obtaining the unit price of high-ash coke, wherein the unit price of the high-ash coke is lower than the unit price of the benchmark coke by a preset value; The cost of a ton of iron is calculated based on the consumption of sintered ore, pelletized ore, and lump ore required for a ton of iron, as well as the coke ratio and coal ratio, plus the capacity energy consumption, wages and benefits, spare parts and auxiliary materials consumption, and coal gas and dust ash recovery costs.

7. The method for evaluating the benefit of coke ash content variation according to claim 6, It is characterized in that The cost per ton of steel corresponding to the use of two types of cokes specifically includes: Using the formula: cost per ton of steel = cost per ton of iron + processing fee of steelmaking process + processing fee of steel rolling process, the corresponding cost per ton of steel is obtained when using standard coke and high ash coke; The corresponding profit per ton of steel and daily profit are obtained respectively, specifically including: Using the formula: profit per ton of steel = selling price per ton of steel - cost per ton of steel, we can get the corresponding profit per ton of steel when using standard coke and high-ash coke; Using the formula: daily profit = daily steel output × profit per ton of steel, we can obtain the corresponding daily profit when using base coke and high-ash coke.

8. The method for evaluating the benefit of coke ash content variation according to claim 1, It is characterized in that After the corresponding profit per ton of steel and daily profit are obtained, it also includes: Correct the preset value that the unit price of high-ash coke is lower than the unit price of benchmark coke until the daily profits corresponding to the use of benchmark coke and high-ash coke are equal, and the preset percentage increase in coke ash content is obtained, and the reasonable value to which the coke price should be lowered is obtained.

9. A benefit evaluation device for coke ash content variation, It is characterized in that include: Memory; as well as A processor connected to the memory, the processor being configured to perform the steps of the method according to any one of claims 1 to 8.

10. A computer storage medium having a computer program stored thereon, It is characterized in that When the computer program is executed by a machine, the steps of the method according to any one of claims 1 to 8 are implemented.

Citation Information

Patent Citations

  • Blast furnace sintering linked low-cost molten iron preparation method

    CN103382513A

  • Coke purchasing decision-making method

    CN113780810A