Slope protection structure suitable for complex terrain of reservoir area hydro-fluctuation belt
By using a planting blanket structure in the drawdown zone of the reservoir area, combined with geotextile and basalt fiber layers, the problems of soil erosion and vegetation growth were solved, the survival rate of vegetation and soil stability were improved, and the environment of the reservoir area was improved.
Patent Information
- Application Number
- CN202411325357.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-23
- Publication Date
- 2024-11-15
AI Technical Summary
The soil in the drawdown zone of the reservoir is easily affected by water level fluctuations, leading to erosion and difficulties in vegetation growth. Existing vegetation reinforcement methods are costly to maintain and ineffective, making it difficult to stabilize the soil structure.
The planting blanket structure consists of a geotextile layer and a basalt fiber layer, with a planting mechanism and anchor bolts for fixation. The planting blanket is equipped with soil-containing bags and a covering layer, which is suitable for complex terrain in the drawdown zone of the reservoir area and improves vegetation survival rate and soil stability.
It reduces soil erosion, increases vegetation survival rate, enhances slope stability, improves the aesthetics of the reservoir area, and adapts to the impact of water level changes.
Smart Images

Figure CN118958217A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of reservoir bank slope protection, and in particular to a slope protection structure suitable for complex terrain in a drawdown zone of a reservoir area. Background Art
[0002] The drawdown zone of a reservoir refers to the land area that appears and disappears periodically when the water level of the reservoir changes. This area is located between the normal water level and the minimum water level of the reservoir. When the water level rises, this part of the area will be flooded; when the water level drops, this part of the area will reappear.
[0003] The water level of a reservoir usually fluctuates due to factors such as seasonal precipitation and reservoir operation. The periodic rise and fall of the water level may cause soil erosion in the drawdown zone, especially when the water level drops, and the exposed soil is easily eroded by wind and rain. This erosion destroys the structure of the soil and reduces its ability to support plant roots. At the same time, soil erosion is usually accompanied by nutrient loss, especially in the case of rain erosion. This makes the soil in the drawdown zone barren and difficult to support plant growth. In addition, due to the periodic changes in the water level, the soil in the drawdown zone may find it difficult to accumulate organic matter. The reduction of organic matter will affect the fertility and microbial activity of the soil, thereby affecting the growth of plants. The above reasons make it difficult for vegetation to survive in the drawdown zone of the reservoir area for a long time, which will further lead to increased soil erosion and form a vicious circle.
[0004] Soil loss in the drawdown zone may lead to unstable soil structure, especially on steep slopes. This instability may lead to landslides and mudslides during natural events such as heavy rainfall or earthquakes, posing a serious threat to downstream areas. Secondly, when vegetation in the drawdown zone degrades, large areas of bare land and dead plants will significantly reduce the visual appeal of the area. This change in landscape may have a negative impact on local tourism.
[0005] At present, the main method to alleviate soil erosion in the drawdown zone of the reservoir area is to reinforce the vegetation. Plants that are resistant to flooding and drought, such as certain herbs and shrubs, are planted to stabilize the soil and reduce erosion. However, this method requires precise selection of plant species suitable for specific environmental conditions, which need to survive quickly in a small amount of soil and are also affected by rainfall and reservoir water levels. Therefore, this method may require a lot of maintenance and care in the early stage, with a low success rate, and is likely to cause a waste of resources and poor results. Summary of the invention
[0006] In order to solve the technical problems raised in the background technology, the present invention provides a slope protection structure suitable for the complex terrain of the drawdown zone in the reservoir area.
[0007] The present invention is implemented by the following technical scheme: a slope protection structure suitable for complex terrain in the drawdown zone of a reservoir area, comprising a planting blanket laid on the slope of the drawdown zone of the reservoir area, anchor rods for fixing the planting blanket, and a plurality of planting mechanisms for planting green plants arranged on the planting blanket, wherein the planting blanket comprises a geotextile layer and a basalt fiber layer.
[0008] As a further improvement of the above scheme, the planting mechanism includes a covering layer made of basalt fiber, and the covering layer is sewn into one with the planting blanket through knitting thread, and a soil bag is formed between the covering layer and the planting blanket, and the soil required for planting plants is stored in the soil bag.
[0009] As a further improvement of the above scheme, a soil pit corresponding to the soil bag is pre-excavated on the slope of the drawdown zone of the reservoir area. Setting the soil pit can make the soil of the planting mechanism be located in the pit, and it is not easy for the soil to escape with the water flow.
[0010] As a further improvement of the above scheme, a notch corresponding to the soil pit is opened on the planting blanket, and the planting mechanism includes an annular plate, a clamping unit and a cylindrical soil containing unit, the soil containing unit contains a coating layer, the clamping unit is used to fix one end of the coating layer in the soil containing unit to the inner wall of the annular plate, the cylindrical coating layer is placed in the soil pit and filled with soil, and the annular plate is fixed in position by a fixing rod inserted into the slope.
[0011] It can facilitate and quickly construct and improve greening efficiency.
[0012] As a further improvement of the above scheme, two covering layers are provided and the covering layers are unfolded into a rectangular shape, and a docking mechanism is passed between the two ends of the two covering layers respectively. The docking mechanism and the two covering layers can quickly form a soil-containing unit.
[0013] As a further improvement of the above scheme, the docking mechanism includes a strip plate and a center axis, wherein two slots are provided in the strip plate, a center hole penetrating the strip plate is provided between the two slots, the center axis is rotatably passed through the center hole, and two connecting grooves are also provided in the strip plate, the connecting grooves connect the center hole and the slots, a gear ring is mounted on the outer side of the center axis, a gear plate meshing with the gear ring is slidably installed in the connecting groove, and a pressure plate is movably provided in the two slots, one end of the pressure plate is connected to the adjacent gear plate, and the pressure plate is used to press the coating layer inserted into the slot.
[0014] The two covering layers are conveniently and quickly butted end to end to form a cylindrical structure covering the soil.
[0015] As a further improvement of the above solution, a plurality of protrusions are distributed on the surface of the pressing plate, which can further stably clamp the end of the coating layer.
[0016] As a further improvement of the above solution, the outer end of the central shaft is in the shape of a screw, and a locking ring is spirally installed on the outer end of the central shaft, and one end surface of the locking ring is used to contact the outer surface of the strip plate to fix the central shaft.
[0017] As a further improvement of the above solution, the length of the strip plate is smaller than the width of the coating layer, so that after the two coating layers form a cylindrical structure, the top of the structure can be pressed and fixed by the pressing unit.
[0018] As a further improvement of the above scheme, the clamping unit includes an annular plate 2 and several clamping plates. A connecting tube is coaxially arranged on the top surface of the annular plate 1. The annular plate 2 and the connecting tube are spirally connected. A movable plate is connected to one side of each clamping plate. The other end of the movable plate is used for sliding and plugging with the inner wall of the annular plate 2. A protrusion is fixed on the bottom surface of the movable plate. Several push rods corresponding to the protrusions are circumferentially distributed on the top surface of the annular plate 1. As the annular plate 2 and the connecting tube are spirally connected, the top end of the push rod contacts the outer side surface of the protrusion to push the movable plate to slide, so that the cylindrical covering layer in the soil holding unit is fixed between the clamping plate and the inner wall of the annular plate 1.
[0019] Compared with the prior art, the present invention has the following beneficial effects:
[0020] The slope protection structure proposed in the present invention comprises a planting blanket laid on the slope of the drawdown zone of the reservoir area, anchor rods for fixing the planting blanket, a plurality of planting mechanisms for planting green plants are arranged on the planting blanket, and the planting blanket comprises a geotextile layer and a basalt fiber layer.
[0021] This structure can reduce the impact of factors such as rainfall and reservoir water level fluctuations on plant growth and soil erosion, create a suitable growth environment, and increase the survival rate of transplanted vegetation, thereby improving the stability of the slope, reducing soil loss on the slope, and improving the aesthetics of the reservoir area. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 A schematic diagram of the installation effect of the slope protection structure provided in Example 1 of the present invention;
[0023] Figure 2 A schematic diagram of the structure of an anchor rod and an anchoring end provided in Example 1 of the present invention;
[0024] Figure 3 A schematic diagram of a cross-sectional structure of a slope protection structure provided in Example 2 of the present invention;
[0025] Figure 4 For the present invention Figure 1 A magnified image of point A;
[0026] Figure 5 A three-dimensional diagram of a pressing unit and an annular plate 1 of the present invention;
[0027] Figure 6 A three-dimensional view of the pressing unit and the annular plate 1 of the present invention when viewed from below;
[0028] Figure 7 It is a schematic diagram of the installation of the coating layer and the docking mechanism of the present invention;
[0029] Figure 8 A three-dimensional diagram of the strip board of the present invention and a partial enlarged diagram of its top structure;
[0030] Fig. 9 For the present invention Figure 7 A magnified view of point B;
[0031] Fig.10 It is a schematic diagram of the connection structure of the docking mechanism after the coating layer of the present invention is unfolded.
[0032] Description of main symbols:
[0033] Slope 1, anchor rod 2, anchor end 3, planting blanket 4, covering layer 5, soil pit 6, fixing rod 7, annular plate 1 8, jack 801, connecting tube 9, annular plate 2 10, movable plate 11, protrusion 12, clamping plate 13, docking mechanism 15, top rod 16, strip plate 17, center shaft 18, locking ring 19, slot 20, protrusion 21, pressure plate 22, tooth plate 23, gear ring 24, connecting groove 25, center hole 26. DETAILED DESCRIPTION
[0034] The present invention is further described below in conjunction with the accompanying drawings and specific implementation methods. It should be noted that, under the premise of no conflict, the various embodiments or technical features described below can be arbitrarily combined to form a new embodiment.
[0035] Embodiment 1:
[0036] Reference Figure 1-10 A slope protection structure suitable for complex terrain in a reservoir drawdown zone includes a planting blanket 4 laid on a slope 1 in the reservoir drawdown zone, an anchor rod 2 for fixing the planting blanket 4, and a plurality of planting mechanisms for planting green plants are arranged on the planting blanket 4. The planting blanket 4 includes a geotextile layer and a basalt fiber layer.
[0037] Install the anchor rod 2, and insert the pre-prepared anchor rod into the pre-drilled hole in the rock mass. During the grouting process, select suitable grouting materials to fill the hole to enhance the anchoring effect and improve the stability of the system. Finally, lay the flexible planting blanket 4, and use the anchor end 3 on the anchor system to tightly fix the planting blanket to the rock mass. The specific operation is to first insert the pre-drilled flexible planting blanket 4 into the anchor rod, then install the pad and nut in turn, and finally tighten the nut to achieve the effect of fixing the planting blanket.
[0038] In this scheme, refer to Figure 1-2 The planting mechanism includes a covering layer 5 made of basalt fiber, and the covering layer 5 is sewn into a whole with the planting blanket 4 through knitting thread, and a soil bag is formed between the covering layer 5 and the planting blanket 4, and the soil required for planting plants is stored in the soil bag. The knitting thread can be a synthetic fiber thread: such as a acrylic fiber thread, which has good durability.
[0039] The size of the pores on the final soil bag can be controlled by controlling the diameter and length of the basalt fiber, so that it is suitable for planting soils with different particle sizes.
[0040] Embodiment 2:
[0041] Reference Figure 3-10 The difference between this embodiment and embodiment 1 is that a soil pit 6 corresponding to the soil bag is pre-excavated on the slope of the drawdown zone in the reservoir area. Setting the soil pit can make the soil of the planting mechanism located in the pit, and it is not easy for the soil to escape with the water flow.
[0042] In this embodiment, a notch (not shown) corresponding to the earth pit 6 is provided on the planting blanket 4, and the notch can be cut in advance before laying, and the planting mechanism includes an annular plate 8, a pressing unit and a cylindrical soil unit, the soil unit contains a coating layer 5 (also made of basalt fiber), and the pressing unit is used to fix one end of the coating layer 5 in the soil unit to the inner wall of the annular plate 8, the cylindrical coating layer 5 is placed in the earth pit 6, and is filled with soil, and the annular plate 8 is fixed in position by a fixing rod 7 inserted into the slope 1, and the fixing rod 7 can use an existing anchor rod. It can facilitate and quickly construct and improve greening efficiency.
[0043] As an optional embodiment of the present invention, the coating layer 5 is provided with two pieces and the coating layer is unfolded in a rectangular shape (refer to Fig.10 ), and a docking mechanism 15 (refer to Figure 7 ), the docking mechanism 15 and the two covering layers 5 can quickly form a soil-containing unit.
[0044] Reference Figure 8 and Fig. 9 The docking mechanism 15 includes a strip plate 17 and a center shaft 18, wherein two slots 20 are provided in the strip plate 17, a center hole 26 penetrating the strip plate 17 is provided between the two slots 20, the center shaft 18 is rotatably penetrated in the center hole 26, and two connecting grooves 25 are also provided in the strip plate 17, the connecting groove 25 connects the center hole 26 and the slot 20, a gear ring 24 is sleeved on the outer side of the center shaft 18, a tooth plate 23 meshing with the gear ring 24 is slidably installed in the connecting groove 25, and a pressure plate 22 is movably provided in the two slots 20, one end of the pressure plate 22 is connected to the adjacent tooth plate 23, and the pressure plate 22 is used to press the coating layer 5 inserted into the slot 20.
[0045] The two covering layers 5 are conveniently and quickly butted end to end to form a cylindrical structure covering the soil.
[0046] In this solution, a plurality of protrusions 21 are distributed on the surface of the pressing plate 22, which can further stably clamp the end of the coating layer.
[0047] It should be noted that, refer to Figure 8 The outer end of the central shaft 18 is in the shape of a screw, and a locking ring 19 is spirally installed on the outer end of the central shaft 18 . One end surface of the locking ring 19 is used to contact the outer surface of the strip plate 17 to fix the central shaft 18 .
[0048] For the convenience of installation and use, as a preferred embodiment of the present invention, the length of the strip plate 17 is smaller than the width of the coating layer 5. This facilitates that after the two coating layers form a cylindrical structure, the top of the structure can be pressed and fixed by the pressing unit.
[0049] In the present scheme, the clamping unit includes an annular plate 10 and several clamping plates 13. A connecting tube 9 is coaxially arranged on the top surface of the annular plate 18. The annular plate 10 and the connecting tube 9 are spirally connected. A movable plate 11 is connected to one side of each clamping plate 13. The other end of the movable plate 11 is used for sliding and plugging with the inner wall of the annular plate 10. A protrusion 12 is fixed to the bottom surface of the movable plate 11. Several push rods 16 corresponding to the protrusions 12 are circumferentially distributed on the top surface of the annular plate 18. As the annular plate 10 and the connecting tube 9 are spirally connected, the top end of the push rod 16 contacts the outer side surface of the protrusion 12 to push the movable plate 11 to slide, so that the cylindrical coating layer 5 in the soil holding unit is fixed between the clamping plate 13 and the inner wall of the annular plate 8.
[0050] A ball is provided at the top of the push rod 16, and the bottom surface of the protrusion 12 is an inclined surface. Through the interference between the two, the movable plate 11 can be pushed to slide. Specifically, a docking hole for docking with the movable plate 11 is provided along the radial direction of the inner wall of the annular plate 10, and a return spring connected to the inner end of the movable plate 11 is provided in the docking hole, so that the movable plate 11 can be automatically reset.
[0051] The above-mentioned embodiments are only preferred embodiments of the present invention and cannot be used to limit the scope of protection of the present invention. Any non-substantial changes and substitutions made by technicians in this field on the basis of the present invention shall fall within the scope of protection required by the present invention.
Claims
1. A slope protection structure suitable for complex terrain in a reservoir drawdown zone, comprising a planting blanket laid on the slope of the reservoir drawdown zone, and anchor rods for fixing the planting blanket. It is characterized in that The planting blanket is provided with a plurality of planting mechanisms for planting green plants, and the planting blanket comprises a geotextile layer and a basalt fiber layer.
2. A slope protection structure suitable for complex terrain in the drawdown zone of a reservoir area as claimed in claim 1, It is characterized in that The planting mechanism comprises a covering layer made of basalt fiber, and the covering layer is sewn into one body with the planting blanket through knitting thread, and a soil bag is formed between the covering layer and the planting blanket, and soil required for planting plants is stored in the soil bag.
3. A slope protection structure suitable for complex terrain in the drawdown zone of a reservoir area as claimed in claim 1, It is characterized in that A soil pit corresponding to the soil bags is pre-excavated on the slope of the drawdown zone of the reservoir area.
4. A slope protection structure suitable for complex terrain in the drawdown zone of a reservoir area as claimed in claim 3, It is characterized in that The planting blanket is provided with a notch corresponding to the soil pit, and the planting mechanism includes an annular plate, a clamping unit and a cylindrical soil containing unit, the soil containing unit contains a coating layer, the clamping unit is used to fix one end of the coating layer in the soil containing unit to the inner wall of the annular plate, the cylindrical coating layer is placed in the soil pit and filled with soil, and the annular plate is fixed in position by a fixing rod inserted into the slope.
5. A slope protection structure suitable for complex terrain in the drawdown zone of a reservoir area as claimed in claim 3, It is characterized in that The covering layer is provided with two pieces and the covering layer is unfolded into a rectangular shape, and a docking mechanism is respectively passed between the two ends of the two covering layers. The docking mechanism and the two covering layers can quickly form the soil containing unit.
6. A slope protection structure suitable for complex terrain in the drawdown zone of a reservoir area as claimed in claim 5, It is characterized in that The docking mechanism includes a strip plate and a center axis, wherein the strip plate is provided with two slots, a center hole penetrating the strip plate is provided between the two slots, the center axis is rotatably provided in the center hole, and the strip plate is further provided with two connecting grooves, the connecting grooves connecting the center hole and the slots, a gear ring is sleeved on the outer side of the center axis, a gear plate meshing with the gear ring is slidably installed in the connecting groove, and a pressure plate is movably provided in each of the two slots, one end of the pressure plate is connected to the adjacent gear plate, and the pressure plate is used to press the coating layer inserted into the slot.
7. A slope protection structure suitable for complex terrain in the drawdown zone of a reservoir area as claimed in claim 6, It is characterized in that A plurality of protrusions are distributed on the surface of the pressing plate.
8. A slope protection structure suitable for complex terrain in the drawdown zone of a reservoir area as claimed in claim 7, It is characterized in that The outer end of the central shaft is in the shape of a screw, and a locking ring is spirally installed on the outer end of the central shaft. One end surface of the locking ring is used to contact the outer surface of the strip plate to fix the central shaft.
9. A slope protection structure suitable for complex terrain in the drawdown zone of a reservoir area as claimed in claim 8, It is characterized in that The length of the strip plate is smaller than the width of the covering layer.
10. A slope protection structure suitable for complex terrain in the drawdown zone of a reservoir area as claimed in claim 9, It is characterized in that The clamping unit includes an annular plate 2 and several clamping plates. A connecting tube is coaxially arranged on the top surface of the annular plate 1. The annular plate 2 and the connecting tube are spirally connected. A movable plate is connected to one side of each clamping plate. The other end of the movable plate is used for sliding and plugging with the inner wall of the annular plate 2. A protrusion is fixed on the bottom surface of the movable plate. Several push rods corresponding to the protrusion are circumferentially distributed on the top surface of the annular plate 1. As the annular plate 2 and the connecting tube are spirally connected, the top end of the push rod contacts the outer side surface of the protrusion to push the movable plate to slide, so that the cylindrical covering layer in the soil holding unit is fixed between the clamping plate and the inner wall of the annular plate 1.