Construction method for preventing riverway formwork from floating during erecting

Through the combination of embedded steel bars and wall-through bolts, the problem of river formwork is not firmly fixed, and the effect of preventing floatation and improving construction efficiency is achieved. It is suitable for various concrete retaining walls.

CN118958303APending Publication Date: 2024-11-15北京常营建设集团有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411166732.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

When installing concrete retaining walls on both sides of the river, the formwork is not easy to fix, which can easily lead to slow support speed and floating formwork, causing quality accidents.

Method used

Through the combination of embedded steel bars and wall-through bolts, welders are used to weld the wall-through bolts and steel bars or use lead wire to connect horizontal wall-through bolts and steel bar hooks to fix the formwork to prevent floating.

Benefits of technology

It effectively prevents the formwork from floating, improves the support speed, is convenient and fast in construction, and is suitable for concrete retaining walls of different heights.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention provides a construction method for preventing a riverway formwork from floating during erecting, and relates to the field of formwork fixing control. The device comprises embedded steel bars, a supporting formwork, fixing bolts and fixing steel bars. The embedded steel bar is that a steel bar drag hook is embedded into concrete when the concrete is poured; the fixing bolt is used for fixing the through-wall bolt on the template; in the formwork erecting step, formworks are erected on the two sides of the river channel; and the fixing steel bars are used for connecting the through-wall bolts with the steel bars. Formwork expansion and formwork floating can be prevented through the method that a welder welds the through-wall bolt and the steel bar together, and construction is convenient and rapid and the welder is saved through the method that the horizontal through-wall bolt and the steel bar drag hook are connected together through a lead wire.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of template fixing control, and in particular to a construction method for preventing river channel templates from floating up during support. Background Art

[0002] Concrete retaining walls are usually set up on both sides of the river to prevent river bank erosion, protect buildings or infrastructure around the river, and control the flow and sediment movement of the river. Concrete retaining walls can prevent flood impact and sediment erosion of the river bank when the river water surges. They can provide a strong physical barrier to reduce the damage of floods to the river bank and surrounding buildings. Riverbank protection. In areas where river bank erosion is serious, setting up concrete retaining walls can stabilize the soil on the river bank and prevent the soil from being washed away, thereby protecting the vegetation, buildings and infrastructure on the river bank. Diversion and water flow control. The design of concrete retaining walls can help control the direction and flow rate of river water. Sometimes it can be combined with facilities such as sluices to regulate the water level and flow of the river to meet different water resource management needs. Beautification and urban planning. In some cities or towns, setting up beautifully designed concrete retaining walls beside the river can play a role in landscaping and urban planning, while improving the overall environmental quality of the surrounding area.

[0003] At present, when installing concrete retaining walls on both sides of the river, since there is no steel bar in the formwork, it is not easy to fix the formwork when supporting the retaining wall formwork, and it is easy for the formwork to expand and float up, thus causing quality accidents. Summary of the invention

[0004] 1. Technical issues to be resolved

[0005] In view of the deficiencies in the prior art, the present invention provides a construction method for preventing the river channel formwork from floating up during support, thereby solving the problems of slow support speed and difficulty in fixing the formwork.

[0006] (II) Technical solution

[0007] To achieve the above objectives, the present invention is implemented through the following technical solutions: a construction method for preventing the river channel formwork from floating up during support, comprising pre-embedded steel bars, a support formwork, fixing bolts, and fixing steel bars; the pre-embedded steel bars are steel bar hooks embedded in concrete during concrete pouring; the fixing bolts are through-wall bolts fixed to the formwork; the support formwork is to support the formwork on both sides of the river channel; the fixing steel bars are to connect the through-wall bolts and the steel bars together.

[0008] Preferably, the embedded steel bar is a steel bar hook embedded in the middle of the concrete foundation when pouring the concrete foundation, and is fixed by concrete.

[0009] Preferably, the supporting formwork is formed by fixing through-wall bolts on the formwork corresponding to the positions of the steel bar hooks.

[0010] Preferably, the supporting formwork is fixed to the formwork corresponding to the position of the steel bar hook using horizontal through-wall bolts.

[0011] Preferably, the supporting formwork is to install the pre-processed formwork according to the set position and the through-wall bolts on the formwork are in contact with the steel bar hooks, which is convenient for subsequent operations.

[0012] Preferably, the fixing steel bars are achieved by welding through-wall bolts to the steel bars by a welder, thereby achieving the effect of fixing the formwork.

[0013] Preferably, the fixing steel bar is connected together with the horizontal through-wall bolt and the steel bar hook by using lead wire, and two lead wires are fixed on each horizontal through-wall bolt.

[0014] Working principle: When pouring the foundation, a steel bar hook is embedded in the middle of the foundation. When supporting the retaining wall formwork, the through-wall bolts are connected with steel bars and welded to the embedded steel bar hooks. After further improvement, the formwork can be fixed with horizontal through-wall bolts, and then the horizontal through-wall bolts are connected to the embedded steel bar hooks with lead wire. Each horizontal through-wall bolt is fixed with two lead wires. This method saves welders and is fast.

[0015] (III) Beneficial effects

[0016] The present invention provides a construction method for preventing river channel templates from floating up during installation. It has the following beneficial effects:

[0017] 1. The method of welding the through-wall bolts and steel bars together by welders can prevent the mold from expanding and floating.

[0018] 2. The method of using lead wire to connect the horizontal through-wall bolts with the steel bar hooks makes the construction convenient, fast and saves welders. DETAILED DESCRIPTION

[0019] The technical solutions in the embodiments of the present invention will be described clearly and completely below in combination with the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0020] Embodiment 1:

[0021] An embodiment of the present invention provides a construction method for preventing a river channel formwork from floating up during support, comprising embedded steel bars, a support formwork, fixing bolts, and fixing steel bars; the embedded steel bars are steel bar hooks embedded in concrete during concrete pouring; the fixing bolts are through-wall bolts fixed to the formwork; the support formwork is to support the formwork on both sides of the river channel; the fixing steel bars are to connect the through-wall bolts and the steel bars together.

[0022] Pre-embedded steel bars are steel bar hooks embedded in the middle of the concrete foundation when pouring the concrete foundation, and are fixed by concrete.

[0023] The supporting formwork is to fix the through-wall bolts on the formwork corresponding to the position of the steel bar hooks.

[0024] The supporting formwork is to install the pre-processed formwork according to the set position and the through-wall bolts on the formwork are in contact with the steel bar hooks to facilitate subsequent operations.

[0025] The steel bars are fixed by welders welding through-wall bolts to the steel bars to achieve the effect of fixing the formwork.

[0026] This method is strong and stable and is suitable for plain concrete retaining walls of all heights.

[0027] Embodiment 2:

[0028] An embodiment of the present invention provides a construction method for preventing a river channel formwork from floating up during support, comprising embedded steel bars, a support formwork, fixing bolts, and fixing steel bars; the embedded steel bars are steel bar hooks embedded in concrete during concrete pouring; the fixing bolts are through-wall bolts fixed to the formwork; the support formwork is to support the formwork on both sides of the river channel; the fixing steel bars are to connect the through-wall bolts and the steel bars together.

[0029] Pre-embedded steel bars are steel bar hooks embedded in the middle of the concrete foundation when pouring the concrete foundation, and are fixed by concrete.

[0030] The supporting formwork is fixed to the formwork corresponding to the position of the steel bar hook using horizontal through-wall bolts.

[0031] The steel bars are fixed by connecting the horizontal through-wall bolts with the steel bar hooks using lead wires, and two lead wires are fixed on each horizontal through-wall bolt.

[0032] This method is convenient, fast and has no restrictions. It is suitable for retaining walls about 1.5 meters high, but not suitable for plain concrete retaining walls that are too high and cast as a whole.

[0033] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A construction method for preventing a river channel formwork from floating up during support, comprising pre-buried steel bars, a support formwork, fixing bolts, and fixing steel bars; characterized in that: The embedded steel bars are steel bar hooks embedded in concrete during concrete pouring; the fixing bolts are through-wall bolts fixed to the formwork; the supporting formwork is to support the formwork on both sides of the river channel; the fixed steel bars are to connect the through-wall bolts and steel bars together.

2. A construction method for preventing river channel formwork from floating up during installation according to claim 1, characterized in that: The embedded steel bar is a steel bar hook embedded in the middle of the concrete foundation when pouring the concrete foundation, and is fixed by the concrete.

3. A construction method for preventing river channel formwork from floating up during installation according to claim 1, characterized in that: The supporting formwork is to fix the through-wall bolts on the formwork corresponding to the position of the steel bar hook.

4. A construction method for preventing river channel formwork from floating up during installation according to claim 1, characterized in that: The supporting formwork is fixed to the formwork corresponding to the position of the steel bar hook by using horizontal through-wall bolts.

5. A construction method for preventing river channel formwork from floating up during installation according to claim 1, characterized in that: The supporting formwork is to install the pre-processed formwork according to the set position and the through-wall bolts on the formwork are in contact with the steel bar hooks, which is convenient for subsequent operations.

6. A construction method for preventing river channel formwork from floating up during installation according to claim 3, characterized in that: The fixing steel bars are welded together by a welder by welding through-wall bolts and steel bars to achieve the effect of fixing the formwork.

7. A construction method for preventing river channel formwork from floating up during installation according to claim 4, characterized in that: The fixing steel bar is connected with the horizontal through-wall bolt and the steel bar hook by using lead wire, and two lead wires are fixed on each horizontal through-wall bolt.