Steel sheet pile wall structure for underwater local scouring adjustment and treatment and construction method of steel sheet pile wall structure

By designing the steel sheet pile wall structure for underwater local erosion and treatment, including vertical and side-by-side steel sheet piles, reinforcement and drainage parts, the problems of inflexible structure and high maintenance costs in the existing technology are solved, and the large-scale water conservancy projects are realized. Effectively erode and regulate treatment and long-term stability.

CN118958333APending Publication Date: 2024-11-15CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410861592.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-28
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

In existing water conservancy projects, the structures such as concrete berths and gabion nets are not flexible enough, and it is difficult to adapt to complex water flow conditions. The maintenance cost of laying pipeline structures is high and the treatment effect is limited. The ecological method is only suitable for small rivers or lakes, and it cannot effectively solve large-scale water conservancy. Local flushing problems of the project.

Method used

Design a steel sheet pile wall structure for underwater local erosion and treatment, including steel sheet piles, reinforcement parts and drainage parts arranged vertically side by side, and are pushed into the riverbed one by one through hydraulic pile hammers to ensure the linearity and integrity of the wall, and carry out the Anti-corrosion coating and stiffener ribs are welded, combined with special connections and bolts, to monitor verticality and position in real time to form a stable steel sheet pile wall.

Benefits of technology

It effectively inhibits abnormal flow of water flow and silt, improves construction safety and efficiency, ensures the long-term stability and treatment effect of steel sheet pile walls, is suitable for large-scale water conservancy projects, and solves the problems of structural flexibility and maintenance costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958333A_ABST
    Figure CN118958333A_ABST
Patent Text Reader

Abstract

The invention discloses a steel sheet pile wall structure for underwater local scouring adjustment and treatment and a construction method thereof, the steel sheet pile wall structure comprises bearing platforms, a plurality of steel sheet piles vertically arranged between the bearing platforms side by side, and a reinforcing part arranged on the steel sheet piles and used for enhancing the bending resistance and sliding resistance of the steel sheet piles; the drainage part is arranged on the steel sheet pile, and the drainage part is used for keeping water pressure balance inside and outside the steel sheet pile; according to the steel sheet pile wall structure for underwater local scouring adjustment and treatment and the construction method thereof, the problems that an existing concrete protection dam, a gabion net and other structures are not flexible enough and are difficult to adapt to complex water flow conditions are solved, and laying of a pipeline structure needs high maintenance cost; the problems that an ecological mode is only suitable for small rivers or lakes, and the scour regulation and treatment effect on large-scale water conservancy projects is not remarkable enough are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of water conservancy engineering, and in particular to a steel sheet pile wall structure for underwater local scour regulation and a construction method thereof. Background Art

[0002] In the construction of water conservancy projects, especially when constructing bridge piers near existing bridges, the scouring effect of water flow often causes serious scouring problems in local areas. This scouring not only affects construction safety, but may also cause instability or even damage to the bridge piers.

[0003] In the prior art, the serious scour problems caused by local areas are mainly addressed by using structures such as concrete embankments and gabions to block water flow and fix the riverbed. However, these structures are not flexible enough and are difficult to adapt to complex water flow conditions. Pipes are also laid on the riverbed to guide water flow and reduce sediment deposition in specific areas, but laying pipeline structures requires high maintenance costs and has limited effect on regulating local scour. There are also ecological methods such as planting aquatic plants or establishing artificial wetlands to improve water quality and reduce scour, but ecological methods are usually only suitable for smaller rivers or lakes, and the scour regulation effect on large-scale water conservancy projects is not significant enough. Summary of the invention

[0004] The purpose of the present invention is to provide a steel sheet pile wall structure for underwater local scour regulation and a construction method thereof, so as to solve the problems that existing concrete protection embankments, gabions and other structures are not flexible enough and difficult to adapt to complex water flow conditions, the laying of pipeline structures requires high maintenance costs and has limited effect on the regulation of local scour, and the ecological method is only applicable to smaller rivers or lakes and has insufficient effect on the scour regulation of large-scale water conservancy projects.

[0005] To achieve the above object, the present invention provides the following technical solution: a steel sheet pile wall structure for underwater local scour regulation, comprising a cap, and also comprising:

[0006] A plurality of steel sheet piles, wherein the plurality of steel sheet piles are vertically arranged side by side between the caps;

[0007] A reinforcement part, which is arranged on the steel sheet pile, and is used to enhance the bending resistance and anti-slip ability of the steel sheet pile; and

[0008] The drainage part is arranged on the steel sheet pile, and is used to maintain the water pressure balance inside and outside the steel sheet pile.

[0009] Preferably, the plurality of steel sheet piles are fixedly connected.

[0010] Preferably, the reinforcement portion comprises stiffening ribs.

[0011] Preferably, a stiffening rib is fixedly connected to the outer side of each of the steel sheet piles.

[0012] Preferably, the stiffening ribs are welded to the steel sheet piles.

[0013] Preferably, the drainage portion includes a drainage hole opened at the lower portion of the steel sheet pile.

[0014] Preferably, the top of the steel sheet pile is horizontal and the bottom of the steel sheet pile is sharp.

[0015] Preferably, a connecting rod is fixedly connected between the caps, a positioning groove is provided on the connecting rod, and a plurality of the steel sheet piles are fixed between the connecting rods.

[0016] A method for constructing a steel sheet pile wall structure for underwater local scour regulation, using the steel sheet pile wall structure for underwater local scour regulation, the method comprising the following steps:

[0017] S1: Conduct a detailed survey of underwater topography and water flow conditions, design the layout and dimensions of the steel sheet pile wall based on this, apply anti-corrosion coating to the steel sheet piles and weld stiffeners;

[0018] S2: Use special connectors and bolts to connect the steel sheet piles. After the connection is completed, the entire steel sheet pile wall is subjected to a water pressure test to check for leakage or instability;

[0019] S3: The steel sheet piles are driven into the riverbed one by one by a hydraulic pile hammer. During the piling process, the verticality and position of the steel sheet piles are monitored in real time to ensure the linearity and integrity of the wall.

[0020] It can be seen from the above technical solution that the present invention has the following beneficial effects:

[0021] The steel sheet pile wall structure for underwater local scour regulation and its construction method can solve the scour problem when a new bridge is built near an existing bridge by vertically arranging a plurality of steel sheet piles side by side between the caps, arranging a reinforcement part for enhancing the bending resistance and anti-slip ability of the steel sheet piles on the steel sheet piles, arranging a drainage part for maintaining the water pressure balance inside and outside the steel sheet piles on the steel sheet piles, applying an anti-corrosion coating on the steel sheet piles and welding stiffening ribs, and driving the steel sheet piles into the riverbed one by one by a hydraulic pile hammer. During the piling process, the verticality and position of the steel sheet piles are monitored in real time to ensure that the wall The linearity and integrity of the steel sheet pile wall can effectively regulate the water flow and inhibit the abnormal flow of sediment, thereby avoiding the occurrence of local scour, improving the efficiency and safety of construction, ensuring the long-term stability and regulation effect of the steel sheet pile wall, and solving the problems that the existing concrete protection embankment, gabion mesh and other structures are not flexible enough to adapt to complex water flow conditions, the laying of pipeline structures requires high maintenance costs, and the regulation effect on local scour is limited; the ecological method is only applicable to smaller rivers or lakes, and the scour regulation effect on large-scale water conservancy projects is not significant enough. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0023] Figure 2 It is a schematic diagram of the process of the present invention.

[0024] In the figure: 1. Capping platform; 2. Steel sheet pile; 3. Reinforcement part; 31. Stiffening rib; 4. Drainage part; 41. Drainage hole; 5. Connecting rod; 6. Positioning groove. DETAILED DESCRIPTION

[0025] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0026] like Figure 1As shown, a steel sheet pile wall structure for underwater local scour regulation includes a cap 1, a plurality of steel sheet piles 2, a reinforcement part 3 and a drainage part 4. The plurality of steel sheet piles 2 are vertically arranged side by side between the caps 1, the reinforcement part 3 is arranged on the steel sheet piles 2, and the drainage part 4 is arranged on the steel sheet piles 2. The reinforcement part 3 is used to enhance the bending resistance and anti-slip ability of the steel sheet piles 2, and the drainage part 4 is used to maintain the internal and external water pressure balance of the steel sheet piles 2, apply an anti-corrosion coating to the steel sheet piles 2 and weld the stiffening ribs 31, and drive the steel sheet piles 2 into the riverbed one by one by a hydraulic pile hammer. During the piling process, the verticality and position of the steel sheet piles 2 are monitored in real time to ensure the linearity and integrity of the wall. For the scour problem when a new bridge is built near an existing bridge or when a new bridge is built near the existing bridge, the water flow can be effectively regulated to suppress the abnormal flow of sediment, thereby avoiding the occurrence of local scour, improving the efficiency and safety of the construction, and ensuring the long-term stability and regulation effect of the steel sheet pile 2 wall.

[0027] like Figure 1 As shown, a plurality of the steel sheet piles 2 are fixedly connected to each other. When the steel sheet piles 2 are connected in units, special connectors and bolts are used to ensure the firmness and sealing of the connection. The reinforcement portion 3 includes a stiffening rib 31. Each steel sheet pile 2 is fixedly connected to the outer side with a stiffening rib 31. The stiffening rib 31 is welded to the steel sheet pile 2. The drainage portion 4 includes a drainage hole 41. The drainage hole 41 is provided at the lower part of the steel sheet pile 2. The top of the steel sheet pile 2 is horizontal and the bottom of the steel sheet pile 2 is sharp. A connecting rod 5 is fixedly connected between the caps 1. A positioning groove 6 is provided on the connecting rod 5. A plurality of steel sheet piles 2 are fixed between the connecting rods 5.

[0028] A method for constructing a steel sheet pile wall structure for underwater local scour regulation is also provided, using a steel sheet pile wall structure for underwater local scour regulation, the method comprising the following steps:

[0029] S1: Conduct a detailed survey of underwater topography and water flow conditions, design the layout and dimensions of the steel sheet pile wall based on this, apply anti-corrosion coating to the steel sheet piles and weld stiffeners;

[0030] S2: Use special connectors and bolts to connect the steel sheet piles. After the connection is completed, the entire steel sheet pile wall is subjected to a water pressure test to check for leakage or instability;

[0031] S3: The steel sheet piles are driven into the riverbed one by one by a hydraulic pile hammer. During the piling process, the verticality and position of the steel sheet piles are monitored in real time to ensure the linearity and integrity of the wall.

[0032] In the specific implementation process, the steel sheet pile 2 wall of the present invention is designed as a series of interconnected steel sheet pile units, each unit has a specific shape and size to adapt to different hydrogeological conditions and construction requirements. The design of the steel sheet pile 2 unit takes into account the principles of hydrodynamics to ensure its stability and effectiveness underwater. One end of the steel sheet pile 2 unit is designed to be a sharp shape for easy insertion into the riverbed, and the other end is designed to be a wide plane to facilitate the connection of adjacent steel sheet pile units to form a continuous wall structure.

[0033] The length and shape of the steel sheet pile 2 wall cannot be too short during the actual setting process, and it must be ensured to exceed the quicksand diffusion line. If a wider setting is adopted, it can be arranged in an arc shape.

[0034] In order to ensure the stability of the steel sheet pile 2 wall, stiffening ribs 31 are arranged on the outside of each steel sheet pile 2 unit. These stiffening ribs 31 not only enhance the bending resistance of the steel sheet pile 2, but also provide additional anti-slip capability to prevent the impact of water flow on the steel sheet pile 2 wall and the erosion of mud and sand. In addition, drainage holes 41 are designed on the inside of the steel sheet pile 2 unit to balance the water pressure inside the wall and reduce the instability of the steel sheet pile 2 wall caused by the water pressure difference.

[0035] First, a detailed survey of the underwater topography and water flow conditions is conducted, and the layout and size of the steel sheet pile 2 wall are designed based on this. Before construction, the steel sheet pile 2 units are pre-treated, including the application of anti-corrosion coating and the welding of stiffening ribs 31. During construction, professional piling ships and piling equipment are used to accurately locate the position of the steel sheet piles according to the design drawings, and then the steel sheet piles are driven into the riverbed one by one by a hydraulic piling hammer. During the piling process, the verticality and position of the steel sheet pile 2 are monitored in real time to ensure the linearity and integrity of the wall. When connecting the steel sheet pile 2 units, special connectors and bolts are used to ensure the firmness and sealing of the connection. After the connection is completed, the entire steel sheet pile 2 is The wall is subjected to a water pressure test to check for leakage or instability. During the construction process, the water flow velocity, flow direction and sediment concentration should also be monitored regularly to evaluate the conditioning effect of the steel sheet pile 2 wall, and the construction plan should be adjusted according to the monitoring results. After the construction of the steel sheet pile 2 wall is completed, long-term monitoring and maintenance work is required. By setting up underwater monitoring equipment, such as flow meters and sediment concentration meters, underwater environmental data can be collected in real time to evaluate the stability and conditioning effect of the steel sheet pile 2 wall. Once an abnormal situation is found, corresponding maintenance measures should be taken immediately, such as reinforcing the steel sheet pile 2 wall, cleaning up sediment, etc., to ensure the long-term effectiveness of the steel sheet pile 2 wall.

[0036] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A steel sheet pile wall structure for underwater local scour control, comprising a cap (1), characterized in that: Also includes: A plurality of steel sheet piles (2), wherein the plurality of steel sheet piles (2) are vertically arranged side by side between the capping platforms (1); A reinforcement part (3), the reinforcement part (3) being arranged on the steel sheet pile (2), the reinforcement part (3) being used to enhance the bending resistance and anti-slip capability of the steel sheet pile (2); as well as A drainage part (4) is arranged on the steel sheet pile (2), and the drainage part (4) is used to maintain the water pressure balance inside and outside the steel sheet pile (2).

2. The steel sheet pile wall structure for underwater local scour control according to claim 1 is characterized by: The plurality of steel sheet piles (2) are fixedly connected to each other.

3. The steel sheet pile wall structure for underwater local scour control according to claim 1 is characterized by: The reinforcement portion (3) comprises a stiffening rib (31).

4. The steel sheet pile wall structure for underwater local scour control according to claim 3 is characterized by: A stiffening rib (31) is fixedly connected to the outer side of each steel sheet pile (2).

5. The steel sheet pile wall structure for underwater local scour control according to claim 4 is characterized by: The stiffening rib (31) is welded to the steel sheet pile (2).

6. The steel sheet pile wall structure for underwater local scour control according to claim 1 is characterized by: The drainage portion (4) comprises a drainage hole (41) opened at the bottom of the steel sheet pile (2).

7. The steel sheet pile wall structure for underwater local scour control according to claim 1 is characterized by: The top of the steel sheet pile (2) is horizontal, and the bottom of the steel sheet pile (2) is sharp.

8. The steel sheet pile wall structure for underwater local scour control according to claim 1 is characterized by: A connecting rod (5) is fixedly connected between the capping platforms (1), a positioning groove (6) is provided on the connecting rod (5), and a plurality of the steel sheet piles (2) are fixed between the connecting rods (5).

9. A method for constructing a steel sheet pile wall structure for underwater local scour regulation, characterized in that: The method using the steel sheet pile wall structure for underwater local scour control according to any one of claims 1 to 8 comprises the following steps: S1: Conduct a detailed survey of underwater topography and water flow conditions, design the layout and dimensions of the steel sheet pile wall based on this, apply anti-corrosion coating to the steel sheet piles and weld stiffeners; S2: Use special connectors and bolts to connect the steel sheet piles. After the connection is completed, the entire steel sheet pile wall is subjected to a water pressure test to check for leakage or instability; S3: The steel sheet piles are driven into the riverbed one by one by a hydraulic pile hammer. During the piling process, the verticality and position of the steel sheet piles are monitored in real time to ensure the linearity and integrity of the wall.