Freezing reinforcement construction method for soft soil aquifer below existing station
By setting up specific freezing areas in shield construction and using freezing media for freezing construction, combined with the design of orifice sealing device and temperature-controlled holes, the impact of freezing, melting, and sinking on the subway station is solved, and geological stability and construction safety are achieved ensures the normal operation of the station.
Patent Information
- Application Number
- CN202411014701.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-26
- Publication Date
- 2024-11-15
AI Technical Summary
In shield construction, the freezing and melting phenomenon caused by the freezing method causes irreversible damage to existing subway stations. How to avoid or reduce the impact of freezing and melting on the station is an urgent problem.
By setting up a cylindrical freezing area below the existing station, and setting up work wells, annular areas and thickened areas in the freezing area, and using freezing medium for freezing construction, ensuring the uniformity of the expansion of the frozen area and reducing the impact on the building above. The orifice sealing device, pressure relief holes and temperature control holes are used to control temperature and pressure, and the layout and construction process of the frozen holes are optimized to reduce interference to the station.
Effectively consolidate geology, prevent sand and water surges, reduce the impact of freezing, swelling, molten sinking, and sinking on the station, ensure construction safety and accuracy, reduce the impact on existing subway stations, and ensure the normal operation of the station and the safety of passengers.
Smart Images

Figure CN118958991A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of shield construction, and in particular to a method for freezing and reinforcing a soft soil aquifer beneath an existing station. Background Art
[0002] When a new subway line passes under an existing subway station, it is necessary to dig a tunnel under the existing subway station. The tunnel is excavated using a shield machine. The technology for excavating tunnels in soil layers with stable geological conditions is relatively mature. However, in soft soil layers with unstable geological conditions, especially in the presence of pressurized water layers in the bottom layer of soft soil, shield construction is more difficult.
[0003] In actual construction, the difficulties faced by construction workers are mainly poor stability of the confined water layer, difficulty in shield construction, and easy occurrence of dangerous situations such as sand and water gushing. In order to enable the normal construction of shield construction, the freezing method is often used to stabilize the geology, that is, to freeze the soft soil confined water layer. Specifically, holes are drilled in the aquifer and pipes are driven in, and circulating liquid nitrogen is introduced to freeze the strata around the pipes to form a hard frozen soil shell. In this way, it can not only ensure the stability of the strata, but also play a water-isolating role, thereby ensuring the normal construction of the shield operation.
[0004] However, when the tunnel passes under an existing subway station, since the frozen area is located below the floor of the existing subway station, the use of conventional freezing methods will produce a technical defect of frost heave and thaw settlement, that is, the soil layer will expand after freezing, and the expansion of the soil layer will act on the subway station above, causing the station building to rise, and then after waiting for the soil layer to melt, it will sink again. Therefore, the frost heave and thaw settlement of the soil layer will cause irreversible damage to the existing subway station.
[0005] Therefore, how to avoid the frost heave and thaw settlement phenomenon when using the freezing method for construction, or how to reduce the impact of the frost heave and thaw settlement phenomenon on existing subway stations, has become an urgent problem to be solved in this field. Summary of the invention
[0006] This application provides a method for freezing and reinforcing the soft soil aquifer under an existing station, which can freeze the soil layer to ensure the normal progress of shield construction without causing a significant impact on the existing subway station. The following technical solutions are specifically adopted: A freezing reinforcement construction method for a soft soil aquifer under an existing station comprises the following steps: S1. Determine a frozen area, wherein the frozen area is set directly below the existing subway station, and the frozen area includes a cylindrical area, wherein the cylindrical area is set horizontally; the diameter of the cylindrical area is larger than the diameter of the shield tunnel, and the central axis of the cylindrical area coincides with the central axis of the shield tunnel; S2. Setting a working well: Setting a working well on one side of the existing subway station and making the working well located on one side of the frozen area in the horizontal direction; S3, drilling construction, drilling freezing holes into the freezing area from the working well; S4, installing the freezing pipe into the freezing hole; S5, freezing construction, setting up a freezing station, connecting the freezing pipe to the freezing station and transporting the freezing medium into the freezing area, and completing the freezing construction of the freezing area.
[0007] By adopting the above technical solution, the frozen area can effectively stabilize the geology and prevent the danger of sand and water gushing during shield construction. At the same time, a cylindrical area is set for freezing, which can expand evenly around it during the freezing process, thereby avoiding the main upward expansion in the conventional freezing method and thus affecting the existing buildings, ensuring that the existing buildings are not damaged. At the same time, a working well is set up to facilitate the drilling of freezing holes in the frozen area.
[0008] Preferably, the freezing area also includes an annular area arranged at one end of the cylindrical area, and the annular area is coaxial with the cylindrical area; the inner diameter of the annular area is the same as the diameter of the shield tunnel, and the outer diameter is the same as the diameter of the cylindrical area.
[0009] By adopting the above technical solution, the annular frozen area has less impact on the buildings above it when freezing, and the annular frozen area can guide the shield machine, which is conducive to the smooth progress of shield construction.
[0010] Preferably, the freezing area also includes a thickened area, which is arranged at the bottom of the cylindrical area. The thickened area is arranged in an arc shape that fits the cylindrical area, and both sides of the thickened area extend to the median line of the cylindrical area in the height direction.
[0011] By adopting the above technical solution, the setting of the thickened area helps to enhance the supporting force at the bottom of the shield tunnel and prevent the loosening of the bottom geology.
[0012] Preferably, in step S3, before drilling the freezing hole, a positioning hole is firstly drilled on the working well wall, and an orifice pipe is arranged in the positioning hole; the orifice pipe is inserted in the positioning hole and fixedly connected to the working well wall.
[0013] By adopting the above technical solution, it helps to accurately locate the position of the freezing hole and improve construction accuracy.
[0014] Preferably, the orifice pipe is further provided with an orifice sealing device; the orifice sealing device comprises a gate valve, the gate valve is provided with an inlet and an outlet, the inlet is connected to the orifice pipe, and the outlet is fixedly connected with a sleeve; When drilling a freezing hole, the drill rod of the drilling equipment passes through the casing, the gate valve and the orifice pipe in sequence, and drills the freezing hole in the frozen area.
[0015] By adopting the above technical solution, the drill rod of the drilling equipment will pass through the casing, gate valve and orifice pipe in sequence. The orifice sealing device can effectively prevent mud and other impurities from entering the working well, keeping the construction environment clean. And by closing the gate valve in time, sand and water gushing can be avoided. In addition, the casing can be used to guide the drill rod, which can effectively ensure the drilling accuracy of the freezing hole.
[0016] Preferably, in step S4, when installing the freezing pipe, the freezing pipe is fixedly connected to the orifice pipe.
[0017] By adopting the above technical solution, the stability and sealing of the freezing pipe can be ensured, thereby improving the freezing effect.
[0018] Preferably, a pressure relief hole and a temperature control hole are also provided above the freezing area; and in step S3, a pressure relief hole and a temperature control hole are drilled from the working well toward the top of the freezing area, a plurality of pressure relief holes and temperature control holes are provided, and the pressure relief holes and temperature control holes are alternately arranged in sequence in the horizontal direction.
[0019] By adopting the above technical solution, the temperature above the frozen area can be adjusted through the temperature control holes to prevent the frozen area from extending upward and affecting the existing subway stations, while the pressure relief holes can relieve the water pressure and expansion pressure in the soil during the freezing process of the frozen area, thereby reducing the impact of freezing construction on existing buildings.
[0020] Preferably, the part of the cylindrical area that overlaps with the shield tunnel is the inner ring area, and the rest is the outer ring area; in step S3, the freezing holes include inner ring holes drilled on the inner ring area and outer ring holes drilled on the outer ring area; In step S4, after the freezing pipe is installed in the outer ring hole, the gap between the outer ring hole and the freezing pipe is sealed by grouting; In step S5, after the freezing construction is completed, the freezing pipes in the outer circle holes are cut, and the freezing pipes in the inner circle holes are pulled out.
[0021] By adopting the above technical solution, the influence of the frozen pipes in the inner circle holes on the subsequent shield construction can be avoided. Grouting and fixing the frozen pipes in the outer circle holes can effectively improve the stability of the frozen pipes, thereby ensuring the normal progress of the freezing construction.
[0022] Preferably, in step S3, when drilling the freezing holes, the freezing holes in the outer circle area are drilled first, and then the freezing holes in the inner circle area are drilled; When drilling the freezing holes in the outer ring area, take the median line in the height direction of the cylindrical area, first drill the freezing holes above the median line, and then drill the freezing holes below the median line; when drilling the freezing holes in the inner ring area, first drill the freezing holes above the median line, and then drill the freezing holes below the median line; The freezing area is also provided with a temperature measuring hole, and the freezing hole is drilled first, and then the temperature measuring hole is drilled.
[0023] By adopting the above technical solution, by constructing several freezing holes in sequence from top to bottom and from outside to inside, it is possible to ensure effective forming of the freezing holes and reduce the probability of freezing hole collapse, thereby ensuring the orderly progress of the freezing construction.
[0024] Preferably, in step S3, after the freezing hole is drilled, an inclination measurement process and a leak test process are performed; The inclinometer process uses an inclinometer tube and a waterproof flashlight; the waterproof flashlight is fixed to the end of the inclinometer tube, the inclinometer tube is inserted into the bottom of the freezing hole, the flashlight wick is observed through the theodolite eyepiece, and the vertical reading of the theodolite is read when the wick and the crosshairs in the theodolite eyepiece coincide, and compared with the designed vertical angle of the freezing hole, the vertical deviation of the freezing pipe hole is calculated; In the leak test process, a fluid is introduced into the freezing hole using a pressure device and a certain pressure is maintained, and the range of pressure changes within a given time is observed.
[0025] By adopting the above technical solution, the inclination measurement process can ensure the hole forming accuracy of the freezing hole, thereby ensuring that the action range of the freezing pipe is within the ideal range, thereby ensuring the formation of the designed freezing area and ensuring the smooth progress of the freezing construction. The leak test process can ensure the normal operation of the freezing pipe.
[0026] In summary, the present invention includes at least one of the following beneficial technical effects: 1. Through specially designed freezing areas (including cylindrical areas, annular areas and thickened areas), this method can effectively stabilize the geology, thereby preventing dangerous situations such as sand and water gushing that may occur during shield construction, and ensuring the smooth progress of construction; 2. Through the setting of the orifice sealing device, pressure relief hole and temperature control hole, this method not only improves the safety and accuracy of construction, but also can monitor and adjust the temperature and pressure of the freezing area in real time, ensuring the stability and controllability of the construction process; 3. By optimizing the layout and construction process of the freezing holes (including the division of inner and outer circle holes, grouting and plugging, and pulling out the freezing pipes), this method can reduce the interference and impact on existing subway stations, ensuring the normal operation of the stations and the safety of passengers. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1It is a schematic diagram of the relative position relationship between the existing subway station, the working shaft and the freezing area in the embodiment of the present application; Figure 2 is a schematic structural diagram of a vertical cross section of a freezing area in an embodiment of the present application; Figure 3 is a schematic structural diagram of a horizontal cross section of a freezing area in an embodiment of the present application; Figure 4 It is a schematic diagram of the structure of the orifice tube and the orifice sealing device in the embodiment of the present application.
[0028] Markings in the attached figure: 1. Frozen area; 11. Cylindrical area; 12. Annular area; 13. Thickened area; 2. Pressure relief hole; 3. Temperature control hole; 4. Orifice pipe; 5. Orifice sealing device; 51. Gate valve; 52. Casing; 6. Drill rod; 7. Existing subway station; 8. Working well. DETAILED DESCRIPTION
[0029] The following is combined with Figure 1-4 The present invention is described in further detail.
[0030] The embodiment of the present application discloses a freezing reinforcement construction method for a soft soil aquifer under an existing station, which is aimed at a shield tunnel passing through a soft soil layer, a confined water layer, and passing under an existing subway station 7. Since the geology of the shield area is soft soil with poor bearing capacity, and there is also a confined underground aquifer in the soft soil layer, the soil strength is low and the bearing capacity is limited, which may cause the existing subway station 7 to sink or the tunnel to deform during the construction process. Shield construction of the tunnel in such geology may lead to difficulties in groundwater control during the construction process, increase construction risks and costs, and the instability and unpredictability of the soft soil confined aquifer increase the safety risks during the construction process.
[0031] In the present application, by setting a reasonable freezing area 1, it is possible to achieve freezing reinforcement of the soft soil pressure aquifer, and to effectively control frost heave deformation, thereby reducing the impact on the structure of the existing subway station 7.
[0032] The specific steps include: S1. Determine the frozen area 1, refer to Figure 1 The freezing area 1 is set directly below the existing subway station 7.
[0033] Specifically, refer to Figure 2 and Figure 3 The freezing area 1 includes a cylindrical area 11, which is arranged transversely; the diameter of the cylindrical area 11 is greater than the diameter of the shield tunnel, and the central axis of the cylindrical area 11 coincides with the central axis of the shield tunnel; The freezing area 1 also includes an annular area 12 arranged at one end of the cylindrical area 11 , and the annular area 12 is coaxial with the cylindrical area 11 ; the inner diameter of the annular area 12 is the same as the diameter of the shield tunnel, and the outer diameter is the same as the diameter of the cylindrical area 11 .
[0034] The freezing area 1 also includes a thickened area 13 , which is arranged at the bottom of the cylindrical area 11 . The thickened area 13 is arranged in an arc shape that fits the cylindrical area 11 , and both sides of the thickened area 13 extend to the midline of the cylindrical area 11 in the height direction.
[0035] In actual construction, it is necessary to consider the specific thickness dimensions of the cylindrical area 11, the annular area 12 and the thickened area 13. In the embodiment of the present application, the diameter of the cylindrical area 11 is 4.95m and the length is 3m, and with this as a reference, the outer diameter of the annular area 12 is 4.95m, the inner diameter is 3.55m, and the length is 2m; the length of the thickened area 13 is 5m and the thickness is 0.8m.
[0036] The above dimensions can be flexibly adjusted according to actual construction needs.
[0037] S2, set working well 8, refer to Figure 1 A working well 8 is set on one side of the existing subway station 7, and the working well 8 is located on one side of the frozen area 1 in the horizontal direction, and the working well 8 is located at one end of the cylindrical area 11 facing away from the annular area 12. Because during the shield construction of the tunnel, the shield machine needs to enter from the inside of the annular area 12, pass through the cylindrical area 11 and reach the working well 8. Therefore, the working well 8 also serves as a receiving well for the shield machine.
[0038] In actual construction, since a new subway station is also needed in the new subway line, and the new subway station is built next to the existing subway station 7, the working shaft 8 is set in the foundation pit excavated for the new subway station.
[0039] In addition, if a new subway station is not to be built beside the existing subway station 7 , a working well 8 may be set up only on one side of the existing subway station 7 , and the soil layer below the existing subway station 7 may be frozen and reinforced by the working well 8 .
[0040] S3, drilling construction, refer to Figure 4 A freezing hole is drilled from the working well 8 into the freezing area 1, and before drilling the freezing hole, a positioning hole is first drilled on the wall of the working well 8, and an orifice pipe 4 is arranged in the positioning hole; the orifice pipe 4 is inserted in the positioning hole and fixedly connected to the wall of the working well 8.
[0041] The orifice pipe 4 also needs to be installed with an orifice sealing device 5; the orifice sealing device 5 includes a gate valve 51, and the gate valve 51 is provided with an inlet and an outlet, the inlet is connected to the orifice pipe 4, and the outlet is fixedly connected with a sleeve 52; When drilling the freezing hole, the drill rod 6 of the drilling equipment passes through the casing 52, the gate valve 51 and the orifice pipe 4 in sequence, and acts in the freezing area 1 to realize the drilling construction of the freezing hole.
[0042] During construction, after the first freezing hole is opened, observe whether there is water or sand gushing out of the freezing hole. If not, continue to drill holes. If the gushing out of water and sand is large, cement slurry should be filled in the freezing hole to stop water and add slurry to the stratum to prevent subsidence.
[0043] When drilling freezing holes, you need to follow a certain sequence, which is as follows: First, the part where the cylindrical area 11 overlaps with the shield tunnel is defined as the inner circle area, and the rest is defined as the outer circle area; secondly, the freezing holes on the freezing area 1 are divided into inner circle holes drilled in the inner circle area and outer circle holes drilled in the outer circle area.
[0044] When drilling freezing holes, first drill the freezing holes in the outer circle area, and then drill the freezing holes in the inner circle area; and, when drilling the freezing holes in the outer circle area, take the midline of the cylindrical area 11 in the height direction, and first drill the freezing holes above the midline, and then drill the freezing holes below the midline; similarly, when drilling the freezing holes in the inner circle area, first drill the freezing holes above the midline, and then drill the freezing holes below the midline.
[0045] A temperature measuring hole is also drilled in the freezing area 1, and the freezing hole should be drilled first, and then the temperature measuring hole.
[0046] After the freezing hole is drilled, the inclinometer process of the freezing hole needs to be carried out. Specifically, the inclinometer process uses an inclinometer tube and a waterproof flashlight. The inclinometer tube is a metal tube or a plastic tube with a certain bending and deformation ability. Fix the waterproof flashlight at the end of the inclinometer tube, insert the inclinometer tube into the freezing hole so that the waterproof flashlight is located at the bottom of the freezing hole, use the theodolite, and use the theodolite eyepiece to observe the flashlight wick through the inclinometer tube. When the wick and the crosshairs in the theodolite eyepiece coincide, read the vertical reading and horizontal degree of the theodolite, and compare them with the vertical angle and horizontal angle of the freezing hole design to check the hole deviation of the freezing hole. According to the deviation, the freezing hole is trimmed to ensure the construction accuracy of the freezing hole.
[0047] A pressure relief hole 2 and a temperature control hole 3 are also provided above the freezing area 1; and in step S3, a pressure relief hole 2 and a temperature control hole 3 are drilled from the working well 8 toward the top of the freezing area 1, and a plurality of pressure relief holes 2 and temperature control holes 3 are provided, and the pressure relief holes 2 and the temperature control holes 3 are alternately arranged in sequence along the horizontal direction.
[0048] By arranging a pressure relief hole and a temperature control hole 3 at the top of the frozen area 1, frost heave deformation can be effectively controlled.
[0049] S4, install the freezing pipe, install the freezing pipe; pass the freezing pipe through the orifice pipe 4 and insert it into the freezing hole, so that the freezing pipe and the orifice pipe 4 are fixedly connected.
[0050] For the outer ring area, after the freezing pipe is installed in the outer ring hole, the gap between the outer ring hole and the freezing pipe needs to be sealed by grouting.
[0051] After the freezing pipe is installed, it is also necessary to conduct a leak test on the freezing pipe. Specifically, the leak test process uses a pressure test device to pass fluid into the freezing hole and maintain a certain pressure, and observe the range of pressure changes within a given time.
[0052] In the embodiment of the present application, the freezing pipe leak test pressure is 0.8MPa. After 30 minutes of pressure test, the pressure drop does not exceed 0.05MPa, and if the pressure remains unchanged for another 15 minutes, it is considered qualified.
[0053] S5, freezing construction, setting up a freezing station, connecting the freezing pipe to the freezing station and conveying the freezing medium into the freezing area 1, and completing the freezing construction of the freezing area 1. The freezing medium can be liquid nitrogen or the like.
[0054] After the freezing construction is completed, the frozen pipes in the outer circle holes are cut, and because the inner circle area is located within the subsequent shield advancement contour, the frozen pipes in the inner circle holes need to be pulled out. In order to ensure the smooth removal of the frozen pipes, hot brine with a relatively high temperature can be introduced into the frozen pipes, so that a small part of the frozen soil around the frozen pipes is melted.
[0055] During freezing construction, it is necessary to regularly check the temperature of the freezing pipe and the working conditions of the freezing station to ensure normal construction. Regular monitoring includes: regular inspections of the freezing situation, regular monitoring of the temperature of the temperature measuring holes, and analysis of the expansion speed and thickness of the frozen wall based on the temperature measurement data, and an estimated time for the frozen wall to reach the designed thickness.
[0056] After the freezing construction is completed, the actual situation in the frozen area 1 should be detected through the exploration hole. After the exploration hole is cored, it is checked whether the location is frozen soil and the temperature is measured. When drilling the exploration hole, the hole pipe 4 + valve should be installed, and tools such as wooden plugs should be prepared to prevent water gushing.
[0057] After the above construction steps are completed, if melting and settling still exists, melting and settling grouting construction shall be carried out.
[0058] Inject cement single slurry or cement-water glass double slurry into the frozen area. Controlling ground settlement deformation is the purpose of thaw grouting. Therefore, during the thawing process of the frozen area, it is necessary to strengthen the monitoring of ground deformation, frozen soil temperature, and water and soil pressure behind the frozen wall.
[0059] The timing of melting and settling grouting is when the frozen area has completely melted and the measured tunnel settlement is no more than 0.5mm every half a month without grouting. The timing of melting and settling grouting should fully consider the impact on the adjacent frozen area, control the grouting volume and grouting pressure, and avoid excessive temperature rise and surface settlement in the adjacent frozen area.
[0060] The embodiments of this specific implementation method are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for freezing and reinforcing the soft soil aquifer under an existing station. It is characterized in that The following steps are involved: S1. Determine a frozen area (1), wherein the frozen area (1) is arranged directly below an existing subway station (7), and the frozen area (1) includes a cylindrical area (11), wherein the cylindrical area (11) is arranged horizontally; the diameter of the cylindrical area (11) is greater than the diameter of the shield tunnel, and the central axis of the cylindrical area (11) coincides with the central axis of the shield tunnel; S2, setting a working well (8), setting the working well (8) on one side of the existing subway station (7), and making the working well (8) located on one side of the frozen area (1) in a horizontal direction; S3, drilling construction, drilling a freezing hole from the working well (8) into the freezing area (1); S4, installing the freezing pipe into the freezing hole; S5, freezing construction, setting up a freezing station, connecting the freezing pipe to the freezing station and conveying the freezing medium into the freezing area (1), and completing the freezing construction of the freezing area (1).
2. The freezing reinforcement construction method for the soft soil aquifer under the existing station according to claim 1, It is characterized in that The freezing area (1) further comprises an annular area (12) arranged at one end of the cylindrical area (11), wherein the annular area (12) is coaxial with the cylindrical area (11); the inner diameter of the annular area (12) is the same as the diameter of the shield tunnel, and the outer diameter is the same as the diameter of the cylindrical area (11).
3. The freezing reinforcement construction method for the soft soil aquifer under the existing station according to claim 2, It is characterized in that The freezing area (1) further comprises a thickened area (13), wherein the thickened area (13) is arranged at the bottom of the cylindrical area (11), the thickened area (13) is arranged in an arc shape that fits the cylindrical area (11), and both sides of the thickened area (13) extend to the midline of the cylindrical area (11) in the height direction.
4. The freezing reinforcement construction method for the soft soil aquifer under the existing station according to claim 1, It is characterized in that In step S3, before drilling the freezing hole, a positioning hole is first drilled on the wall of the working well (8), and an orifice pipe (4) is arranged in the positioning hole; the orifice pipe (4) is inserted into the positioning hole and fixedly connected to the wall of the working well (8).
5. The freezing reinforcement construction method for the soft soil aquifer under the existing station according to claim 4, It is characterized in that The orifice pipe (4) is also provided with an orifice sealing device (5); the orifice sealing device (5) comprises a gate valve (51); the gate valve (51) is provided with an inlet and an outlet, the inlet is connected to the orifice pipe (4), and the outlet is fixedly connected to a sleeve (52); When drilling a freezing hole in step S3, a drill rod (6) of the drilling equipment passes through the casing (52), the gate valve (51) and the orifice pipe (4) in sequence, and drills a freezing hole in the freezing area (1).
6. The freezing reinforcement construction method for the soft soil aquifer under the existing station according to claim 4, It is characterized in that In step S4, when installing the freezing pipe, the freezing pipe is fixedly connected to the orifice pipe (4).
7. The freezing reinforcement construction method for the soft soil aquifer under an existing station according to claim 1, It is characterized in that A pressure relief hole (2) and a temperature control hole (3) are also provided above the freezing area (1); and in step S3, a pressure relief hole (2) and a temperature control hole (3) are drilled from the working well (8) toward the top of the freezing area (1), a plurality of pressure relief holes (2) and a plurality of temperature control holes (3) are provided, and the pressure relief holes (2) and the temperature control holes (3) are alternately arranged in sequence in a horizontal direction.
8. The freezing reinforcement construction method for the soft soil aquifer under an existing station according to claim 1, It is characterized in that The part of the cylindrical area (11) that overlaps with the shield tunnel is the inner ring area, and the rest is the outer ring area; in step S3, the freezing holes include inner ring holes drilled in the inner ring area and outer ring holes drilled in the outer ring area; In step S4, after the freezing pipe is installed in the outer ring hole, the gap between the outer ring hole and the freezing pipe is sealed by grouting; In step S5, after the freezing construction is completed, the freezing pipes in the outer circle holes are cut, and the freezing pipes in the inner circle holes are pulled out.
9. The freezing reinforcement construction method for the soft soil aquifer under the existing station according to claim 8, It is characterized in that In step S3, when drilling freezing holes, first drill the freezing holes in the outer circle area, and then drill the freezing holes in the inner circle area; When drilling the freezing holes in the outer ring area, take the median line of the cylindrical area (11) in the height direction, first drill the freezing holes above the median line, and then drill the freezing holes below the median line; when drilling the freezing holes in the inner ring area, first drill the freezing holes above the median line, and then drill the freezing holes below the median line; A temperature measuring hole is also drilled in the freezing area (1); and the freezing hole is drilled first, and then the temperature measuring hole is drilled.
10. The freezing reinforcement construction method for the soft soil aquifer under an existing station according to claim 1, It is characterized in that In step S3, after the freezing hole is drilled, an inclination measurement process is performed; The inclinometer process uses an inclinometer tube and a waterproof flashlight; the waterproof flashlight is fixed to the end of the inclinometer tube, the inclinometer tube is inserted into the freezing hole and the waterproof flashlight is located at the bottom of the freezing hole, the flashlight wick is observed through the inclinometer tube through the theodolite eyepiece, and the vertical reading and horizontal degree of the theodolite are read when the wick and the crosshairs in the theodolite eyepiece coincide, and compared with the designed vertical angle and horizontal angle of the freezing hole, so as to check the hole deviation of the freezing hole; In step S4, after the freezing pipe is installed, a leak test is performed, in which a fluid is introduced into the freezing pipe using a pressure test device and a certain pressure is maintained to observe the pressure change range within a given time.