BIM (Building Information Modeling)-based pipeline comprehensive support
By adopting BIM-based integrated pipeline support and BIM detection and allocation methods in construction projects, the problems of pipeline crossing and overlapping are solved, and the neat collection and layout optimization of pipelines are achieved, the construction efficiency and accuracy of pipeline layout are improved, and the construction is ensured smooth construction. Proceed and provide data support.
Patent Information
- Application Number
- CN202411555745.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-04
- Publication Date
- 2025-01-14
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In construction projects, pipeline layout is affected by factors such as construction site conditions, coordination of multiple majors and technical differences, resulting in frequent problems of pipeline crossing and overlapping, affecting the construction progress and quality, and inconvenient pipeline collection and organization.
Using BIM-based integrated pipeline bracket, including a substrate fixed to the wall, main support pipe and adjustment screw, the pipeline is fixed through clamp assembly, and three-dimensional modeling and collision detection are used to use BIM technology, and real-time monitoring of pipelines is combined with wireless sensor networks. Parameters, optimize pipeline layout.
It realizes neat collection and stable fixation of pipelines, prevents cross-over and overlap problems, improves construction efficiency and the accuracy and rationality of pipeline layout, ensures smooth construction, and provides data support for later maintenance.
Smart Images

Figure CN119309072A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of pipeline supports of BIM, and in particular to a pipeline integrated support based on BIM. Background Art
[0002] The application of BIM (Building Information Modeling) in construction projects is first reflected in its role as the core information platform for the entire life cycle of the project. From the initial design stage of the project, the BIM model integrates all-round data such as the building's geometry, structural information, material properties, and equipment configuration, providing the design team with a highly visual and interactive working environment. This not only helps designers express their design intent more accurately, but also predicts building performance through simulation analysis, discovers and solves potential problems in advance, thereby optimizing the design plan and reducing later design changes and rework.
[0003] Secondly, the application of BIM in the construction stage of building projects is also extremely important. Through the BIM model, the construction team can understand the design intent more accurately and achieve refined management of the construction process. The BIM model can guide the layout, material management, progress control and other aspects of the construction site, improve construction efficiency and reduce resource waste. At the same time, BIM's collision detection function can detect and resolve conflict problems in construction in advance, reduce the workload of on-site coordination, and ensure smooth construction. In addition, the BIM model can also provide basic data support for later operation and maintenance management, helping owners to better manage and maintain building facilities.
[0004] However, in the actual construction process of construction projects, pipeline layout is often affected by multiple factors such as construction site conditions, multi-professional coordination and technical differences, resulting in frequent pipeline crossing and overlapping problems, inconvenience in pipeline collection and organization, and affecting construction progress and quality. Summary of the invention
[0005] In order to facilitate the collection and organization of pipelines, the present application provides a BIM-based pipeline integrated bracket.
[0006] In the first aspect, the present application provides a BIM-based pipeline integrated support adopting the following technical solution: A BIM-based pipeline integrated bracket comprises a base plate fixed on a wall, the base plate is fixed with a plurality of fixing mechanisms, the fixing mechanisms comprise a main support tube fixedly connected to the base plate, an adjusting screw is slidably arranged in the main support tube, a clamp assembly for fixing pipelines is fixedly connected to one end of the adjusting screw away from the base plate, and the pipelines correspond to the clamps one-to-one.
[0007] By adopting the above technical solution, the base plate is fixedly connected to the wall, the main support tube is fixed on the base plate, the adjusting screw is slidably arranged in the adjusting screw, the clamp assembly fixes the pipeline, and the pipeline corresponds to the clamp one by one, so that the pipeline can be collected and organized more neatly.
[0008] Preferably, the clamp assembly includes a lower support plate arranged below the outer circumferential surface of the pipeline, the adjusting screw is fixedly connected to the lower support plate, the clamp assembly also includes an upper connecting plate arranged on the pipeline, and a locking assembly is arranged between the two end surfaces of the upper connecting plate and the two end surfaces of the lower support plate, and the locking assembly includes a mounting plate fixedly connected to the end surface of the upper connecting plate and a side plate fixedly connected to the end surface of the lower support plate, the mounting plate is provided with a locking hole, the side plate is provided with a connecting hole, the side surface of the connecting hole is provided with a sliding groove, the sliding groove is inserted with a locking strip, and the end of the locking strip away from the bottom surface of the sliding groove is inserted in the locking hole.
[0009] By adopting the above technical solution, an upper connecting plate is arranged above the pipeline, and a locking assembly is arranged between the upper connecting plate and the lower supporting plate. One end of the locking strip in the locking assembly is inserted into the sliding groove, and the other end is inserted into the locking hole on the mounting plate, thereby preventing the mounting plate on the upper connecting plate from being separated from the connecting hole opened on the side plate, thereby improving the stability of the pipeline during the connection process, so that the pipeline can be more stably fixed on the pipeline bracket.
[0010] Preferably, a strip-shaped hole is opened on the side of the side panel, the strip-shaped hole is connected to the sliding groove, the length direction of the strip-shaped hole is consistent with the opening direction of the sliding groove, and a push-pull block is fixedly connected to the side of the locking strip, and the push-pull block is inserted in the strip-shaped hole.
[0011] By adopting the above technical scheme, the push-pull block fixedly connected to the locking strip is inserted into the strip hole opened on the side plate, so that when the locking strip slides in the sliding groove, the push-pull block inserted in the strip hole can prevent the locking strip from escaping from the strip hole, thereby reducing the occurrence of the locking strip escaping from the sliding groove, resulting in the locking assembly being unable to achieve the locking effect, and improving the stability of the locking effect of the locking assembly. At the same time, the locking assembly can be unlocked by toggling the push-pull block, thereby facilitating the disassembly of the upper connecting plate.
[0012] Preferably, a compression spring is provided in the sliding groove, one end of the compression spring is fixedly connected to the bottom surface of the sliding groove, and one end of the compression spring away from the bottom surface of the sliding groove is fixedly connected to the end surface of the locking strip.
[0013] By adopting the above technical solution, the compression spring can provide the locking bar with an elastic force away from the bottom surface of the sliding groove when the locking bar slides into the sliding groove, so that the locking bar always keeps one end inserted in the locking hole in a natural state, thereby improving the stability of the locking effect of the locking assembly.
[0014] Preferably, a first inclined surface is formed on the end surface of the locking strip away from the compression spring, and the first inclined surface is located at the top of the end surface of the locking strip.
[0015] By adopting the above technical solution, a first inclined surface is provided on the locking strip. During the process of inserting the mounting plate into the connecting hole, when the mounting plate contacts the first inclined surface, as the mounting plate continues to be inserted, the mounting plate can push the locking strip into the sliding groove, and under the elastic force of the compression spring, when the locking strip reaches the locking hole, the compression spring can push the locking strip so that the locking strip can be inserted into the locking hole, thereby realizing automatic locking of the locking assembly and improving the work efficiency of the installation work.
[0016] Preferably, a second inclined surface that can interfere with the first inclined surface is provided at one end of the mounting plate away from the upper connecting plate.
[0017] By adopting the above technical solution, during the process of inserting the mounting plate into the connecting hole, when the second inclined surface on the mounting plate contacts the first inclined surface of the first inclined surface, as the mounting plate continues to be inserted, the second inclined surface on the mounting plate can push the locking strip into the sliding groove, and under the elastic force of the compression spring, when the locking strip reaches the locking hole, the compression spring can push the locking strip so that the locking strip can be inserted into the locking hole, thereby realizing automatic locking of the locking assembly and improving the work efficiency of the installation work.
[0018] Preferably, an intermediate tube is threadedly connected to the adjusting screw, a main support tube is arranged outside the intermediate tube, a limiting ring is fixedly connected to the outer circumference of the intermediate tube, an annular limiting ring groove is opened on the inner circumference of the main support tube, the limiting ring is inserted in the limiting ring groove, and a driving component for driving the adjusting screw to rotate is arranged on the base plate.
[0019] By adopting the above technical solution, the intermediate tube is threadedly connected to the adjusting screw, the main support tube is sleeved outside the intermediate tube, a limiting ring is fixedly connected to the outer circumference of the intermediate tube, an annular limiting ring groove is opened on the inner circumference of the main support tube, and the limiting ring is inserted in the limiting ring groove. When the driving component drives the intermediate tube to rotate, under the limiting action of the limiting ring, the adjusting screw can drive the pipeline to move away from the substrate, so that the pipeline can be lifted, thereby facilitating the inspection and replacement of a specific pipeline.
[0020] Preferably, a blocking block is fixedly connected to the bottom of the outer circumference of the adjusting screw, a guide groove is opened on the inner circumference of the main support tube, the length direction of the guide groove is consistent with the axial direction of the main support tube, and the blocking block is inserted in the guide groove.
[0021] By adopting the above technical solution, the blocking block is inserted in the guide groove. When the intermediate tube is rotated, the blocking block prevents the adjusting screw from rotating along with the intermediate tube, so that the adjusting screw moves only along the axial direction of the intermediate tube as much as possible, thereby improving the adjustment efficiency of the pipeline support.
[0022] Preferably, the driving assembly includes a first gear fixedly connected to the intermediate tube, the first gear is located on the side of the main support tube away from the base plate, an electric motor is fixedly connected to the base plate, the output shaft of the motor is arranged perpendicular to the base plate, a second gear is fixedly connected to the output shaft of the motor, and the second gear is meshed with the first gear.
[0023] By adopting the above technical solution, the first gear is fixedly connected to the intermediate tube, the first gear is located on the side of the main support tube away from the base plate, an electric motor is fixedly connected to the base plate, the output shaft of the motor is arranged perpendicular to the base plate, the output shaft of the motor is fixedly connected to the second gear, the second gear is meshed with the first gear, when the motor is started, the motor can drive the first gear to rotate through the second gear, so that the first gear can drive the adjusting screw to slide outside the main support tube through the intermediate tube, so that a specific pipeline can be propped up, which is convenient for inspection and replacement of the specific pipeline.
[0024] In the second aspect, the present application provides a BIM detection and deployment method for a pipeline integrated support, which adopts the following technical solution: A BIM detection and deployment method for a pipeline integrated support comprises the following steps: S1: using BIM technology to perform three-dimensional modeling of buildings, control equipment, motors, pipelines, etc.; S2: introducing parametric design to flexibly adjust parameters such as the size, position and angle of the pipeline support according to actual needs; S3: performing collision check on the established model through the visualization model and collision detection function of the BIM software; S4: combining wireless sensor network technology, installing sensors on key pipeline supports to monitor parameters such as stress and vibration of the pipeline in real time; S5: adjusting and optimizing the pipeline layout according to the collision detection result.
[0025] By adopting the above technical solutions, BIM technology is used to perform three-dimensional modeling of buildings and electromechanical equipment pipelines, and the visual model and collision detection function of BIM software are used to perform collision checks on the established models. Through intuitive three-dimensional views, it is possible to pre-discover and solve the intersection and overlap problems between pipelines. At the same time, according to the collision detection results, the pipeline layout is adjusted and optimized to ensure the smooth progress of construction. Parametric design is introduced to flexibly adjust the size, position, angle and other parameters of the pipeline support according to actual needs to improve the accuracy and rationality of the pipeline layout. Combined with wireless sensor network technology, sensors are installed on key pipeline supports to monitor the stress, vibration and other parameters of the pipeline in real time, providing data support for subsequent pipeline maintenance and management.
[0026] In summary, the present application includes at least one of the following beneficial technical effects: 1. The base plate is fixedly connected to the wall, the main support pipe is fixed on the base plate, the adjusting screw is slidably set in the adjusting screw, the clamp assembly fixes the pipeline, and the pipeline corresponds to the clamp one by one, so that the pipeline can be collected and sorted more neatly; 2. The push-pull block fixedly connected to the locking strip is inserted into the strip hole provided on the side plate, so that when the locking strip slides in the sliding groove, the push-pull block inserted in the strip hole can prevent the locking strip from being separated from the strip hole, thereby reducing the occurrence of the situation where the locking strip is separated from the sliding groove and the locking assembly cannot achieve the locking effect, and improving the stability of the locking effect of the locking assembly. At the same time, the locking assembly can be unlocked by toggling the push-pull block, thereby facilitating the disassembly of the upper connecting plate; 3. Use BIM technology to perform three-dimensional modeling of buildings and electromechanical equipment pipelines, and use the visualization model and collision detection function of BIM software to perform collision checks on the established models. Through intuitive three-dimensional views, it is possible to pre-discover and solve the intersection and overlap problems between pipelines. At the same time, according to the collision detection results, adjust and optimize the pipeline layout to ensure the smooth progress of construction. Introduce parametric design to flexibly adjust the size, position, angle and other parameters of pipeline supports according to actual needs to improve the accuracy and rationality of pipeline layout. Combined with wireless sensor network technology, sensors are installed on key pipeline supports to monitor the stress, vibration and other parameters of the pipeline in real time, providing data support for subsequent pipeline maintenance and management. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a schematic diagram of the overall structure of the pipeline support in the embodiment of the present application.
[0028] Figure 2 It is a cross-sectional view of the pipeline support in the embodiment of the present application.
[0029] Figure 3 yes Figure 2 Partial cross-sectional view at point A in the middle.
[0030] Explanation of the accompanying drawings: 1. fixing mechanism; 11. clamp assembly; 111. lower support plate; 1111. side plate; 1112. connecting hole; 1113. sliding groove; 1114. strip hole; 112. upper connecting plate; 1121. mounting plate; 11211. second inclined surface; 1122. locking hole; 12. adjusting screw; 121. blocking block; 13. intermediate tube; 131. limiting ring; 14. main support tube; 141. limiting ring groove; 142. guide slide groove; 17. locking assembly; 171. locking strip; 1711. first inclined surface; 172. push-pull block; 173. compression spring; 2. pipeline; 3. driving assembly; 31. motor; 32. first gear; 33. second gear; 4. substrate. DETAILED DESCRIPTION
[0031] The following is combined with Figure 1-3 This application is described in further detail.
[0032] The present application embodiment discloses a pipeline integrated support based on BIM. Figure 1 and Figure 2 As shown, the pipeline support includes a base plate 4, an adjusting screw 12, an intermediate tube 13, a main support tube 14 and a fixing mechanism 1. The base plate 4 is fixed on the wall, and a plurality of fixing mechanisms 1 for fixing the pipeline 2 are fixedly connected on the side of the base plate 4 away from the wall. The pipeline 2 corresponds to the fixing mechanism 1 one by one, and the fixing mechanism 1 is linearly and equidistantly distributed on the base plate 4. In the length direction of the pipeline 2, a plurality of pipeline supports are equidistantly arranged, so that the pipeline 2 can be collected and sorted more systematically.
[0033] Reference Figure 2 and Figure 3 As shown, the fixing mechanism 1 includes a clamp assembly 11, which corresponds to the pipeline 2 one by one. The clamp assembly 11 includes a lower support plate 111 and an upper support plate. The lower support plate 111 is an arc-shaped plate. The concave surface of the lower support plate 111 is in contact with the bottom outer peripheral surface of the pipeline 2. The adjusting screw 12 is vertically fixedly connected to the middle part of the bottom surface of the lower support plate 111. The intermediate tube 13 is threadedly connected to the outer peripheral surface of the adjusting screw 12, and an annular limiting ring 131 is fixedly connected to the outer peripheral surface of the intermediate tube 13.
[0034] Reference Figure 2 and Figure 3 As shown, the main support tube 14 is vertically set up on the ground, and the main support tube 14 is sleeved outside the intermediate tube 13. The outer circumference of the intermediate tube 13 is gap-matched with the inner circumference of the main support tube 14. An annular limiting ring 131 groove is opened on the inner circumference of the main support tube 14, and the limiting ring 131 is inserted in the limiting ring 131 groove, which prevents the intermediate tube 13 from moving up and down in the main support tube 14 and enables the intermediate tube 13 to rotate in the main support tube 14.
[0035] Reference Figure 2 and Figure 3 As shown, the top end surface of the intermediate tube 13 is higher than the top end surface of the main support tube 14, and two first gears 32 are fixedly connected to the top of the outer circumference of the intermediate tube 13. The two first gears 32 are symmetrically distributed along the circumferential direction of the intermediate tube 13, and the two first gears 32 are both horizontally arranged. A blocking block 121 is fixedly connected to the bottom of the outer circumference of the adjusting screw 12, and a guide groove 142 is provided on the inner circumference of the main support tube 14. The length direction of the guide groove 142 is consistent with the axial direction of the main support tube 14, and the blocking block 121 is inserted into the guide groove 142.
[0036] Reference Figure 2 and Figure 3 As shown, a side plate 1111 is horizontally fixedly connected to the upper end surface of the lower support plate 111, and a connection hole 1112 is opened on the top surface of the side plate 1111. Two side plates 1111 are fixedly connected to the lower support plate 111, and the two side plates 1111 are respectively fixedly connected to the two end surfaces of the lower support plate 111. The upper connecting plate 112 is arranged on the upper part of the outer peripheral surface of the pipeline 2, and both ends of the upper connecting plate 112 are vertically fixedly connected to mounting plates 1121, and the two mounting plates 1121 are respectively inserted into the two connecting holes 1112, and a locking assembly 17 is arranged between the mounting plate 1121 and the inner side wall of the connecting hole 1112.
[0037] Reference Figure 2 and Figure 3 As shown, the locking assembly 17 includes a locking strip 171, a push-pull block 172 and a compression spring 173. A locking hole 1122 is provided on the mounting plate 1121, a sliding groove 1113 is provided on the side of the connecting hole 1112 away from the lower supporting plate 111, one end of the locking strip 171 is inserted into the sliding groove 1113, and the other end of the locking strip 171 is inserted into the locking hole 1122. A first inclined surface 1711 is provided on the end surface of the locking strip 171 away from the bottom surface of the sliding groove 1113, and the first inclined surface 1711 is provided on the top of the end surface of the locking strip 171. A second inclined surface 11211 that can conflict with the first inclined surface 1711 is provided on the end of the mounting plate 1121 away from the upper connecting plate 112.
[0038] Reference Figure 2 and Figure 3As shown, the top surface of the side plate 1111 is provided with a strip hole 1114, which is a strip hole 1114, which is connected to the sliding groove 1113, and the length direction of the strip hole 1114 is consistent with the length direction of the sliding groove 1113. The push-pull block 172 is fixedly connected to the top surface of the locking strip 171, and the push-pull block 172 is inserted into the strip hole 1114, which reduces the situation that the locking strip 171 is separated from the sliding groove 1113, resulting in the locking assembly 17 being unable to achieve the locking effect. The top surface of the push-pull block 172 is higher than the top surface of the side plate 1111. One end of the compression spring 173 is fixedly connected to the bottom surface of the sliding groove 1113, and the other end of the compression spring 173 is fixedly connected to the end surface of the locking strip 171 close to the bottom surface of the sliding groove 1113.
[0039] Reference Figure 1 and Figure 2 As shown, the fixing mechanism 1 also includes a driving assembly 3, which includes a first gear 32 fixedly connected to the intermediate pipe 13, the first gear 32 is located on the side of the main support pipe 14 away from the base plate 4, a motor 31 is fixedly connected to the base plate 4, the output shaft of the motor 31 is arranged perpendicular to the base plate 4, a second gear 33 is fixedly connected to the output shaft of the motor 31, and the second gear 33 is meshed with the first gear 32. The control mechanism of the motor 31 is connected to the control system of the BIM, and the rise and fall of a specific pipeline 2 can be controlled through the control end of the BIM system, so as to facilitate the detection and replacement of a specific pipeline 2.
[0040] The implementation principle of a pipeline integrated support based on BIM in the embodiment of the present application is as follows: the base plate 4 is fixedly connected to the wall, the main support pipe 14 is fixed to the base plate 4, the adjusting screw 12 is slidably arranged in the adjusting screw 12, the clamp assembly 11 fixes the pipeline 2, and the pipeline 2 corresponds to the clamp one by one, so that the pipeline 2 can be collected and sorted more neatly. The push-pull block 172 fixedly connected to the locking strip 171 is inserted into the bar hole 1114 opened on the side plate 1111, so that when the locking strip 171 slides in the sliding groove 1113, the push-pull block 172 inserted in the bar hole 1114 can prevent the locking strip 171 from being separated from the bar hole 1114, reducing the occurrence of the locking strip 171 being separated from the sliding groove 1113, resulting in the locking assembly 17 failing to achieve the locking effect, and improving the stability of the locking effect of the locking assembly 17. At the same time, the locking assembly 17 can be unlocked by toggling the push-pull block 172, thereby facilitating the disassembly and replacement of the upper connecting plate 112. The first gear 32 is fixedly connected to the intermediate tube 13. The first gear 32 is located on the side of the main support tube 14 away from the base plate 4. The base plate 4 is fixedly connected to the motor 31. The output shaft of the motor 31 is arranged perpendicular to the base plate 4. The output shaft of the motor 31 is fixedly connected to the second gear 33. The second gear 33 is meshed with the first gear 32. When the motor 31 is started, the motor 31 can drive the first gear 32 to rotate through the second gear 33, so that the first gear 32 can drive the adjusting screw 12 to slide outside the main support tube 14 through the intermediate tube 13, so that a specific pipeline 2 can be propped up, which is convenient for checking and replacing the specific pipeline 2.
[0041] The embodiment of the present application also discloses a BIM detection and deployment method for a pipeline integrated support, comprising the following steps: S1: using BIM technology to perform three-dimensional modeling of buildings, control equipment, motors 31, pipelines 2, etc.; S2: introducing parametric design to flexibly adjust parameters such as the size, position and angle of the pipeline support according to actual needs; S3: performing collision checks on the established model through the visualization model and collision detection function of the BIM software; S4: combining wireless sensor network technology to install sensors on key pipeline supports to monitor the stress, vibration and other parameters of pipeline 2 in real time; S5: adjusting and optimizing the layout of pipeline 2 according to the collision detection results.
[0042] The effect is: using BIM technology to perform three-dimensional modeling of the building and electromechanical equipment pipeline 2, and using the visualization model and collision detection function of the BIM software to perform collision checks on the established model. Through the intuitive three-dimensional view, the intersection and overlap problems between pipelines 2 can be discovered and solved in advance. At the same time, according to the collision detection results, the layout of pipeline 2 is adjusted and optimized to ensure the smooth progress of construction. Parametric design is introduced to flexibly adjust the size, position, angle and other parameters of the pipeline support according to actual needs, so as to improve the accuracy and rationality of the layout of pipeline 2. Combined with wireless sensor network technology, sensors are installed on key pipeline supports to monitor the stress, vibration and other parameters of pipeline 2 in real time, providing data support for the subsequent maintenance and management of pipeline 2.
[0043] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A BIM-based integrated pipeline support, characterized in that: The invention comprises a base plate (4) fixed on a wall, the base plate (4) being fixed with a plurality of fixing mechanisms (1), the fixing mechanisms (1) comprising a main support tube (14) fixedly connected to the base plate (4), an adjusting screw (12) being slidably arranged inside the main support tube (14), a clamp assembly (11) for fixing a pipeline (2) being fixedly connected to one end of the adjusting screw (12) away from the base plate (4), the pipeline (2) corresponding to the clamp one by one.
2. According to the BIM-based pipeline integrated support according to claim 1, it is characterized by: The clamp assembly (11) comprises a lower support plate (111) arranged below the outer peripheral surface of the pipeline (2), the adjusting screw (12) being fixedly connected to the lower support plate (111), the clamp assembly (11) further comprising an upper connecting plate (112) arranged on the pipeline (2), a locking assembly (17) being arranged between two end surfaces of the upper connecting plate (112) and two end surfaces of the lower support plate (111), the locking assembly (17) comprising a mounting member fixedly connected to the end surface of the upper connecting plate (112), A mounting plate (1121) and a side plate (1111) fixedly connected to the end surface of the lower support plate (111), the mounting plate (1121) is provided with a locking hole (1122), the side plate (1111) is provided with a connecting hole (1112), a sliding groove (1113) is provided on the side surface of the connecting hole (1112), a locking strip (171) is inserted into the sliding groove (1113), and one end of the locking strip (171) away from the bottom surface of the sliding groove (1113) is inserted into the locking hole (1122).
3. The BIM-based pipeline integrated support according to claim 2 is characterized in that: The side surface of the side plate (1111) is provided with a strip-shaped hole (1114), the strip-shaped hole (1114) is connected to the sliding groove (1113), the length direction of the strip-shaped hole (1114) is consistent with the opening direction of the sliding groove (1113), and the side surface of the locking strip (171) is fixedly connected with a push-pull block (172), and the push-pull block (172) is inserted into the strip-shaped hole (1114).
4. The BIM-based integrated pipeline support according to claim 3 is characterized in that: A compression spring (173) is arranged in the sliding groove (1113), one end of the compression spring (173) is fixedly connected to the bottom surface of the sliding groove (1113), and one end of the compression spring (173) away from the bottom surface of the sliding groove (1113) is fixedly connected to the end surface of the locking strip (171).
5. The BIM-based integrated pipeline support according to claim 4 is characterized in that: A first inclined surface (1711) is provided on the end surface of the locking strip (171) away from the compression spring (173), and the first inclined surface (1711) is located at the top of the end surface of the locking strip (171).
6. The BIM-based integrated pipeline support according to claim 5 is characterized in that: One end of the mounting plate (1121) away from the upper connecting plate (112) is provided with a second inclined surface (11211) that can abut against the first inclined surface (1711).
7. The BIM-based integrated pipeline support according to claim 1 is characterized in that: An intermediate tube (13) is threadedly connected to the adjusting screw (12), a main support tube (14) is disposed on the outer surface of the intermediate tube (13), a limiting ring (131) is fixedly connected to the outer circumference of the intermediate tube (13), an annular limiting ring (131) groove is provided on the inner circumference of the main support tube (14), and the limiting ring (131) is inserted into the limiting ring (131) groove. A driving component (3) for driving the adjusting screw (12) to rotate is provided on the base plate (4).
8. The BIM-based integrated pipeline support according to claim 7 is characterized in that: A blocking block (121) is fixedly connected to the bottom of the outer circumference of the adjusting screw rod (12), and a guide groove (142) is provided on the inner circumference of the main support tube (14). The length direction of the guide groove (142) is consistent with the axial direction of the main support tube (14), and the blocking block (121) is inserted into the guide groove (142).
9. The BIM-based integrated pipeline support according to claim 7 is characterized in that: The driving assembly (3) comprises a first gear (32) fixedly connected to the intermediate tube (13); the first gear (32) is located on a side of the main support tube (14) away from the base plate (4); a motor (31) is fixedly connected to the base plate (4); an output shaft of the motor (31) is arranged perpendicular to the base plate (4); a second gear (33) is fixedly connected to the output shaft of the motor (31); the second gear (33) is meshed with the first gear (32).
10. A BIM detection and deployment method for a pipeline integrated support, according to the BIM-based pipeline integrated support according to claim 9, characterized in that: The steps include: S1: Use BIM technology to perform three-dimensional modeling of buildings, control equipment, motors (31), pipelines (2), etc.; S2: Introducing parametric design to flexibly adjust the size, position, angle and other parameters of the pipeline support according to actual needs; S3: Use the visualization model and collision detection function of BIM software to perform collision check on the established model; S4: Combined with wireless sensor network technology, sensors are installed on key pipeline supports to monitor the stress, vibration and other parameters of the pipeline (2) in real time; S5: According to the collision detection result, the layout of the pipeline (2) is adjusted and optimized.