Railway goods yard comprehensive operation capability calculation method and system
By comprehensively calculating the capabilities of each operation link of the railway freight yard, the problem of single operation capacity calculation in the existing technology is solved, and a more accurate assessment of the operation capacity of the railway freight yard is provided to help optimize the organization of railway freight transportation.
Patent Information
- Application Number
- CN202410969238.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-18
- Publication Date
- 2024-11-15
AI Technical Summary
The calculation of the operating capacity of the railway freight yard is single, and the ability to calculate the different operating links is lacking, resulting in the calculated operating capacity often exceeding the actual capacity.
Provide a method for calculating the comprehensive operating capacity of railway freight yards. By obtaining station operation information, basic capabilities such as garage decomposition capabilities, container loading and unloading line operation capabilities, etc., and combining operation organization factors, the comprehensive operating capacity is determined.
This makes the calculated comprehensive operating capacity of railway freight yards more in line with production reality, provides more accurate decision-making basis, reduces calculation errors, and optimizes the organization of railway freight transportation.
Smart Images

Figure CN118966965A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of railway transportation, and in particular to a method and system for calculating the comprehensive operating capacity of a railway freight yard. Background Art
[0002] The operational capacity of a railway freight yard includes: the capacity of picking up and delivering cars in the freight yard, that is, the number of cars that a shunting locomotive can pick up and deliver in a day; the loading and unloading capacity, that is, the number of cars that can be loaded and unloaded in a day; the cargo space capacity, that is, the number of cars that can be loaded and unloaded in the freight yard in a day; the cargo handling capacity, that is, the number of cars that can be moved out and in by handling machinery and manpower in a day. The above-mentioned capabilities must be coordinated to give full play to the operational capacity of the freight yard. Otherwise, any weakness in any of the capabilities can limit the capacity of the entire freight yard.
[0003] However, the current calculation of railway freight yard operating capacity only remains at the design level, based on the capacity calculation of facilities. It is a single calculation of railway loading and unloading capacity, warehousing capacity, and vehicle pickup and delivery capacity. It lacks capacity calculation of different operating links such as railway operation, loading and unloading, resulting in the calculated operating capacity often being greater than the actual capacity. Summary of the invention
[0004] The technical problem to be solved by the present invention is that the current calculation of railway freight yard operating capacity is single and lacks the capacity calculation of different operating links, resulting in the calculated operating capacity often being greater than the actual capacity. In order to solve this technical problem, the present invention provides a method and system for calculating the comprehensive operating capacity of a railway freight yard.
[0005] The technical solution of the present invention to solve the above technical problems is as follows: a method for calculating the comprehensive operating capacity of a railway freight yard, comprising the following steps: obtaining station operating information of the railway freight yard to be evaluated, the station operating information being equipment operating information, personnel operating information, and operating information of the coordination between personnel and equipment in the railway freight yard to be evaluated; calculating the basic capacity of the railway freight yard to be evaluated according to the station operating information, the basic capacity of the railway freight yard including at least one of the shunting yard unmarshaling capacity, the station's operating train receiving and dispatching capacity, the container loading and unloading line operating capacity, the loading and unloading equipment production capacity, the container yard turnover capacity, and the road handling capacity; determining the comprehensive operating capacity of the railway freight yard of the railway to be evaluated based on the station operating information and the basic capacity of the railway freight yard.
[0006] The beneficial effects of the present invention are as follows: the method for calculating the comprehensive operating capacity of a railway freight yard of the present invention is oriented to each link of the production operation of the railway freight yard, fully considers the coordination of each link of facilities and equipment and operation organization, and objectively calculates the comprehensive operating capacity of the railway freight yard in combination with the actual railway operation and freight transportation. Different factors such as facility capacity, equipment utilization efficiency and organizational connection are considered in the calculation process, so that the calculated comprehensive operating capacity of the railway freight yard is more in line with the actual production, thereby providing a decision-making basis for further optimizing the organization of railway freight transportation.
[0007] Based on the above technical solution, the present invention can also be improved as follows.
[0008] Furthermore, the calculation of the station's operating train receiving and dispatching capacity includes: calculating the total time required for the pick-up and delivery operations based on the station operation information; calculating the departure yard throughput capacity and the throat throughput capacity based on the station operation information and the total time required for the pick-up and delivery operations; calculating the station's operating train receiving and dispatching capacity based on the station operation information, the departure yard throughput capacity and the throat throughput capacity.
[0009] The beneficial effect of adopting the above further scheme is: according to the total time required for the pick-up and delivery operations, the throughput capacity of the departure yard and the throat throughput capacity are calculated respectively, and then the train receiving and dispatching capacity of this station is calculated based on the throughput capacity of the departure yard and the throat throughput capacity, taking into account the mutual influence between different operation links, thereby reducing the error between the calculated capacity and the actual capacity.
[0010] Further, the total time required for the vehicle pickup and delivery operation is calculated according to the station operation information, including: obtaining the locomotive preparation operation time t within one day from the station operation information 整备 , The driver cannot use the time of the machine adjustment within a day 司 , the average number of cars that need to be picked up and delivered at the station in one day Q 取送 , average length of trucks l, effective length of the lead-out line used for picking up, delivering and shunting vehicles L 牵 , the average time consumed for a pick-up and delivery operation t 取送 If the shunting machine is a special shunting machine in the railway freight yard to be evaluated, the available time T of a shunting machine at the station in one day is calculated. 调机 :T 调机 =1440-t 整备 -t 司机 If the shunting machine is a common shunting machine for at least two freight stations, the average effective operation time of the shunting machine in the station in one day is obtained from the station operation information, which is used as the available time T of a shunting machine in the station in one day. 调机 If the locomotive in the railway freight yard to be evaluated is capable of picking up and delivering the entire train, the number of pickup and delivery times n is calculated according to the following formula: 取送 :n取送 =T 调机 / t 取送 ; Otherwise, calculate the number of pick-up and delivery times n according to the following formula 取送 :n 取送 =min(Q 取送 l / L 牵 , T 调机 / t 取送 ); Calculate the total time required for the pick-up and delivery operation based on the number of pick-up and delivery operations and the average time consumed for one pick-up and delivery operation.
[0011] The beneficial effect of adopting the above further scheme is: a method for calculating the total time required for the pick-up and delivery operation is provided, and during the calculation process, the specific operating conditions in the station are taken into account, that is, whether the shunting locomotive is a dedicated shunting locomotive for this station and whether the main locomotive has the conditions for picking up and delivering the entire train, so that the calculated total time required for the pick-up and delivery operation is consistent with the actual situation, thereby improving the accuracy of the calculation of the total time required for the pick-up and delivery operation.
[0012] Furthermore, the calculation formula for calculating the station operation train receiving and dispatching capacity based on the station operation information, the arrival and departure yard throughput capacity, and the throat throughput capacity is:
[0013] N 本站接发 ={[N 1 -2*(n 客 -n 不停站通过货物列车 )],N 到发};
[0014] Among them, N 本站接发 N is the station's train receiving and dispatching capacity, 1 is the throat passing capacity, n 客 is the number of passenger trains, n 不停站通过货物列车 N is the number of freight trains passing through without stopping. 到发 To achieve the ability to pass the departure point.
[0015] The beneficial effect of adopting the above further scheme is: providing a calculation method for the station's operating train receiving and dispatching capacity, by combining the departure yard's through-capacity and the throat's through-capacity to calculate the station's operating train receiving and dispatching capacity, fully considering the correlation between various aspects of operating capacity, and reducing the error between the calculation result and the actual value.
[0016] Furthermore, the calculation of the operating capacity of the container loading and unloading lines includes: obtaining the operating capacity of each loading and unloading line, the daily container loading and unloading truck ratio of each loading and unloading line, and the average number of standard containers loaded on each truck from the station operation information; calculating the loading operating capacity and unloading operating capacity of each loading and unloading line according to the operating capacity of each loading and unloading line and the daily container loading and unloading truck ratio of each loading and unloading line; summing up the loading operating capacity of each loading and unloading line and the unloading operating capacity of each loading and unloading line to obtain the total loading operating capacity and the total unloading operating capacity; calculating the operating capacity of the container loading and unloading line according to the total loading operating capacity, the total unloading operating capacity and the average number of standard containers loaded on each truck.
[0017] The beneficial effect of adopting the above further scheme is: providing a method for calculating the operating capacity of the container loading and unloading line, and the calculated operating capacity of the container loading and unloading line is used to calculate and analyze the comprehensive operating capacity of the railway freight yard, providing a basis for calculating the comprehensive operating capacity of the railway freight yard.
[0018] Furthermore, the calculation formula for the production capacity of the loading and unloading equipment is:
[0019] Q 装卸 =k 1 K 2 QUR 技 ;
[0020] Among them, Q 装卸 is the production capacity of loading and unloading equipment, K 1 is the mechanical time utilization coefficient, K 2 is the mechanical load utilization coefficient, t is the loading and unloading operation time, Q 技 For technical production capacity around the clock.
[0021] The beneficial effect of adopting the above further scheme is: providing a method for calculating the production capacity of loading and unloading equipment, the calculation of the production capacity of loading and unloading equipment not only considers the influence of the performance of the machinery itself, but also considers the human factor, so that the calculation result is more accurate.
[0022] Furthermore, the calculation of the container yard turnover capacity includes: obtaining the maximum storage capacity of the container yard, the average turnover time of the arriving containers, the average turnover time of the departing containers, and the average turnover time of the transshipment containers from the station operation information; calculating the arrival container turnover capacity, the departing container turnover capacity, and the transshipment container turnover capacity of each container area in the container yard according to the maximum storage capacity of the container yard, the average turnover time of the arriving containers, the average turnover time of the departing containers, and the average turnover time of the transshipment containers; calculating the container yard turnover capacity according to the arrival container turnover capacity of each container area, the departing container turnover capacity of each container area, and the transshipment container turnover capacity of each container area.
[0023] The beneficial effect of adopting the above further scheme is: a method for calculating the turnover capacity of a container yard is provided, and the calculated turnover capacity of the container yard is used to calculate and analyze the comprehensive operating capacity of the railway freight yard, making the reference factors for calculating the comprehensive operating capacity of the railway freight yard more comprehensive, thereby improving the calculation accuracy.
[0024] Furthermore, the calculation formula of the road carrying capacity is:
[0025] Q 搬运 =n 汽 T 1 p / t 装卸 ;
[0026] Among them, n 汽 is the number of vehicles that can be loaded and unloaded simultaneously in the operation area, T 1 is the time that the freight yard is available for vehicles to pick up and deliver goods in a day, t 装卸 is the average loading and unloading time of each vehicle, and p is the number of standard containers loaded on each vehicle.
[0027] The beneficial effect of adopting the above further scheme is: a method for calculating road handling capacity is provided, and the calculated road handling capacity is used to calculate and analyze the comprehensive operating capacity of the railway freight yard, making the reference factors for calculating the comprehensive operating capacity of the railway freight yard more comprehensive, thereby improving the calculation accuracy.
[0028] Furthermore, the calculation formula for determining the comprehensive operation capacity of the railway freight yard of the railway to be evaluated based on the station operation information and the basic capacity of the railway freight yard is:
[0029]
[0030] in, is the comprehensive operating capacity of the railway freight yard, q is the average number of standard containers loaded on each railway freight car, and c 编组is the average number of trains at the station, N 本站接发 is the station's train receiving and dispatching capacity, θ 1 is the reduction factor of the throat capacity at the first pick-up and delivery vehicle end, θ 2 is the reduction factor of cargo line loading and unloading capacity, θ 3 is the reduction factor of the throat capacity at the second pick-up and delivery vehicle end, δ 1 is the proportion of boxes that do not fall to the ground, δ 2 is the operation influence coefficient, M is an infinite constant, For container loading and unloading line operation capacity, For the total loading and unloading equipment production capacity, is the turnover capacity of the container yard, Q 搬运 For road carrying capacity.
[0031] The beneficial effect of adopting the above further scheme is that the calculation of the comprehensive operating capacity of the railway freight yard fully considers the influence of each link of the railway freight yard's production operation, and calculates the comprehensive operating capacity of the railway freight yard by comprehensively considering various influencing factors, so that the error between the calculation result and the actual capacity is small and the accuracy is high.
[0032] In order to solve the above technical problems, the present invention also provides a railway freight yard comprehensive operation capacity calculation system, comprising:
[0033] A data acquisition module is used to acquire station operation information of the railway freight yard to be evaluated, wherein the station operation information is equipment operation information, personnel operation information, and operation information of coordination between personnel and equipment in the railway freight yard to be evaluated;
[0034] A basic capacity calculation module, used to calculate the basic capacity of the railway freight yard to be evaluated according to the station operation information, wherein the basic capacity of the railway freight yard includes at least one of the following: the shunting yard unmarshaling capacity, the station operation train receiving and dispatching capacity, the container loading and unloading line operation capacity, the loading and unloading equipment production capacity, the container yard turnover capacity and the road handling capacity;
[0035] The comprehensive operation capacity calculation module is used to determine the comprehensive operation capacity of the railway freight yard of the railway to be evaluated based on the station operation information and the basic capacity of the railway freight yard. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1 It is a schematic flow chart of a method for calculating the comprehensive operating capacity of a railway freight yard according to the present invention;
[0037] Figure 2 It is a structural schematic diagram of the railway freight yard comprehensive operating capacity calculation system of the present invention. DETAILED DESCRIPTION
[0038] The principles and features of the present invention are described below. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.
[0039] Embodiment 1
[0040] like Figure 1 As shown, this embodiment provides a method for calculating the comprehensive operating capacity of a railway freight yard, comprising the following steps: obtaining station operating information of the railway freight yard to be evaluated, wherein the station operating information is equipment operating information, personnel operating information, and operating information of the coordination between personnel and equipment in the railway freight yard to be evaluated; calculating the basic capacity of the railway freight yard of the railway freight yard to be evaluated according to the station operating information, wherein the basic capacity of the railway freight yard includes at least one of the shunting yard unmarshaling capacity, the station's operating train receiving and dispatching capacity, the container loading and unloading line operating capacity, the loading and unloading equipment production capacity, the container yard turnover capacity, and the road transportation capacity; determining the comprehensive operating capacity of the railway freight yard of the railway to be evaluated based on the station operating information and the basic capacity of the railway freight yard.
[0041] Among them, the station operation information includes all data information used to calculate the comprehensive operation capacity of the railway freight yard. Specifically, it includes the preparation operation time of the shunting machine within a day, the time that the driver cannot use the shunting machine within a day, the average number of cars that the station needs to pick up and deliver within a day, the average length of the truck, the effective length of the pull-out line used for picking up and delivering cars, the average time consumed for a pick-up and delivery operation, the effective operation time of the shunting machine at the station every day, the effective length of the longest arrival and departure line at the station, the number of trains arriving at the station on the same day, the number of trains departing from the station on the same day, the total time occupied by each arrival and departure line in the arrival and departure yard within a day, the total fixed operation time of each arrival and departure line in the arrival and departure yard, the number of available arrival and departure lines, the empty fee coefficient, the average time required to occupy the marshaling line to marshal a train, the number of marshaling lines converted, the total fixed operation time in the shunting yard, the total time occupied by the throat, the total fixed operation time using each throat part, the number of operations in each direction, the number of passenger trains, and the number of freight trains passing through the station without stopping. , the operating capacity of each loading and unloading line, the ratio of containers to trucks loaded and unloaded per day on each loading and unloading line, the average number of standard containers loaded on each truck, the mechanical time utilization coefficient, the mechanical load utilization coefficient, the loading and unloading operation time, the technical production capacity of one day and night, the maximum storage capacity of the container yard, the average turnover time of containers arriving at the container slot, the average turnover time of containers leaving the container slot, the average turnover time of containers in the transit container slot, the number of vehicles that can be loaded and unloaded at the same time in the operation area, the time that the freight yard can provide vehicles with goods for delivery in one day and night, the average loading and unloading operation time of each vehicle, the number of standard containers loaded on each vehicle, the average number of train formations at the station, the reduction coefficient of the throat capacity of the first delivery vehicle end, the reduction coefficient of the cargo line loading and unloading capacity, the reduction coefficient of the throat capacity of the second delivery vehicle end, the proportion of containers that do not fall to the ground, the operation impact coefficient, etc. The sources of station operation information include but are not limited to querying from the station's historical data, determining by realistic methods, and manually given.
[0042] The method for calculating the comprehensive operating capacity of a railway freight yard in the embodiment of the present invention is oriented to each link of the railway freight yard production operation, fully considers the coordination of each link of facilities and equipment and operation organization, and objectively calculates the comprehensive operating capacity of the railway freight yard in combination with the actual railway operation and freight transportation. Different factors such as facility capacity, equipment utilization efficiency and organizational connection are considered in the calculation process, so that the calculated comprehensive operating capacity of the railway freight yard is more in line with the actual production, thereby providing a decision-making basis for further optimizing the organization of railway freight transportation.
[0043] Optionally, in an embodiment, the calculation of the station's operating train receiving and dispatching capacity includes: calculating the total time required for the pick-up and delivery operations based on the station operation information; calculating the departure yard throughput capacity and the throat throughput capacity based on the station operation information and the total time required for the pick-up and delivery operations; calculating the station's operating train receiving and dispatching capacity based on the station operation information, the departure yard throughput capacity and the throat throughput capacity.
[0044] According to the total time required for the pick-up and delivery operations, the throughput capacity of the departure yard and the throat throughput capacity are calculated respectively, and then the train receiving and dispatching capacity of this station is calculated based on the throughput capacity of the departure yard and the throat throughput capacity, taking into account the mutual influence between different operation links, thereby reducing the error between the calculated capacity and the actual capacity.
[0045] Optionally, in an embodiment, calculating the total time required for the vehicle pickup and delivery operation according to the station operation information includes: obtaining the machine dispatching preparation operation time t within one day from the station operation information 整备 , The driver cannot use the time of the machine adjustment within a day 司机 , the average number of cars that need to be picked up and delivered at the station in one day Q 取送 , average length of trucks l, effective length of the lead-out line used for picking up, delivering and shunting vehicles L 牵 , the average time consumed for a pick-up and delivery operation t 取送 If the shunting machine is a special shunting machine in the railway freight yard to be evaluated, the available time T of a shunting machine at the station in one day is calculated. 调机 :T 调机 =1440-t 整备 -t 司机 If the shunting machine is a common shunting machine for at least two freight stations, the average effective operation time of the shunting machine in the station in one day is obtained from the station operation information, which is used as the available time T of a shunting machine in the station in one day. 调机 If the locomotive in the railway freight yard to be evaluated is capable of picking up and delivering the entire train, the number of pickup and delivery times n is calculated according to the following formula: 取送 :n 取送 =T 调机 / t 取送 ; Otherwise, calculate the number of pick-up and delivery times n according to the following formula 取送 :n 取送 =min(Q 取送 I / L 牵 , T 调机 / t 取送 ); Calculate the total time required for the pick-up and delivery operation based on the number of pick-up and delivery operations and the average time consumed for one pick-up and delivery operation.
[0046] Among them, the preparation time of the shunting machine in one day includes the time taken by the shunting machine for refueling, maintenance, equipment repair and other preparation operations in one day. The time that the driver cannot use the shunting machine in one day includes the time that the driver cannot use the shunting machine due to activities such as shift handover and eating in one day. The preparation time of the shunting machine in one day, the time that the driver cannot use the shunting machine in one day, and the average number of cars that need to be picked up and sent in one day at the station are all obtained by statistical historical data. The method for obtaining the average effective operation time of the shunting machine in one day at the station is: obtain the effective operation time of the shunting machine in the station every day through historical data, and then take the average of the effective operation time of the shunting machine in the station every day to obtain the average effective operation time of the shunting machine in one day at the station. The average number of cars that need to be picked up and sent in one day at the station, that is, the average number of cars that need to be picked up and sent in one day when the station performs the pick-up and delivery operations, is obtained by querying the historical operation data of the station. The effective length of the pull-out line is defined as the start of the outer turnout of the throat area of the yard or freight yard, or the outer side of the shunting signal, to the car stop at the end of the pull-out line. If the station shunting yard and freight cars are arranged in a longitudinal arrangement, the effective length of the longest departure line at the station is used as the effective length of the lead-out line for shunting to calculate the number of pick-ups and delivery cars. For the number of pick-ups and delivery cars, one pick-up car is counted as one and one delivery car is counted as one.
[0047] In this embodiment, according to the number of times of picking up and delivering vehicles and the average time consumed by one picking up and delivering vehicle operation, the calculation formula for calculating the total time required for the picking up and delivering vehicle operation is: 取送 =n 取送 *t 取送 ; Among them, T 取送 The total time required for vehicle pick-up and delivery operations.
[0048] A method for calculating the total time required for the pick-up and delivery operation is provided, and during the calculation process, the specific operating conditions in the station are taken into account, that is, whether the shunting locomotive is a dedicated shunting locomotive for this station and whether the main locomotive has the conditions for picking up and delivering the entire train, so that the calculated total time required for the pick-up and delivery operation is consistent with the actual situation, thereby improving the accuracy of the calculation of the total time required for the pick-up and delivery operation.
[0049] The throughput capacity of the departure yard refers to the total number of trains in each direction that can be received and dispatched at the departure yard in one day and night. In the embodiment, the calculation formula of the throughput capacity of the departure yard is: N 到发 =N 到 +N 发 ; Among them, N 到发 N is the throughput capacity of the departure and arrival terminal, 到 To reach the operational capacity, N 发 is the departure operation capacity. The calculation formula for the arrival operation capacity is: N 到 =n 到 / K 到发 ; where n到 K is the number of trains arriving at the station on that day, 到发 is the utilization rate of the departure line. The calculation formula for departure operation capacity is: N 发 =n 发 / K 到发 ; where n 发 The number of trains departing from the station on that day.
[0050] Utilization rate of arrival and departure line K 到发 The calculation formula is:
[0051]
[0052] Among them, T 2 It is the total time occupied by each arrival and departure track in the arrival and departure yard within a day. It can be determined by realistic methods, specifically: the time from the time when all trains enter the arrival and departure track to the time when they leave the arrival and departure track on that day is obtained through the actual reporting data of the train in the railway train dispatching command system (TDCS), and the time occupied by the arrival and departure track within a day is obtained. ∑t 固1 M is the total fixed operation time of each arrival and departure line in the arrival and departure yard, and the total time required for the preparation time of the arrival and departure line and the pick-up and delivery operations. 到 Y is the number of available firing lines. 空 It is the empty cost coefficient, and the empty cost coefficient is 0.15-0.20 based on experience or determined by simulation.
[0053] The marshaling capacity of a shunting yard refers to the number of trains that can be disassembled and marshaled in a shunting yard in one day and night. In the embodiment, the marshaling capacity of a shunting yard is calculated according to the following formula:
[0054]
[0055] Among them, N 编组 is the marshaling capacity of the shunting yard, t 编组 M is the average time required to occupy the marshaling line to marshal a train. 编 is the number of marshaling line conversions. If the marshaling line length is greater than the length of a full-axle train, the number of marshaling line conversions is 1; otherwise, it is reduced according to the ratio of the marshaling line length to the full-axle train length. For example, if the ratio of the marshaling line length to the full-axle train length is 0.9, the number of marshaling line conversions is 0.9. ∑t 固2 It is the total time of fixed operations in the shunting yard. The total time of fixed operations in the shunting yard is the total time occupied by the marshalling line preparation time and the car picking and delivering operations.
[0056] The throat capacity refers to the sum of the maximum number of trains that can pass through the throat switch groups of each approach in the throat area. In the embodiment, according to the station operation information and the total time required for the pick-up and delivery operations, the specific steps for calculating the throat capacity are: calculate the utilization rate of each part of the throat according to the following formula:
[0057]
[0058] Among them, K 咽喉 is the throat utilization rate, T 3 is the total time of occupying the throat, ∑t 固3 It is the total fixed operation time of the throat section, the total time required for the throat section preparation time and the pick-up and delivery operations.
[0059] Calculate the throat capacity N in each direction separately (方向,接 / 发) :N (方向,接 / 发) =n (方向,接 / 发) / K (方向,接 / 发) ; where n (方向,接 / 发) is the number of operations in this direction, K (方向,接 / 发) is the throat utilization rate in this direction.
[0060] The throat capacity in each direction is summed up to obtain the total capacity for receiving and sending trains. The specific formula is: N 1 =∑N (方向,接 / 发) ; where N 1 It is the total capacity of receiving and dispatching trains, that is, the throat passing capacity. It should be noted that the passing trains are counted twice, that is, the number of passing trains is counted for both receiving and dispatching trains.
[0061] The station's operating train receiving and dispatching capacity refers to the total number of trains that the station can receive and dispatch in each direction in one day and night. Optionally, in an embodiment, the calculation formula for calculating the station's operating train receiving and dispatching capacity based on the station's operating information, the arrival and departure yard's throughput capacity, and the throat throughput capacity is:
[0062] N 本站接发 ={[N 1 -2*(n 客 -n 不停站通过货物列车 )],N 到发};
[0063] Among them, N 本站接发 N is the station's train receiving and dispatching capacity, 1 is the throat passing capacity, n 客 is the number of passenger trains, N 到发 It is the passing capacity of the departure and arrival field. 不停站通过货物列车 It is the number of freight trains passing through the station without stopping, that is, the number of freight trains passing through the station but not stopping at the station.
[0064] A calculation method for the station's operating train receiving and dispatching capacity is provided. The station's operating train receiving and dispatching capacity is calculated by combining the departure yard's throughput capacity and the throat's throughput capacity, fully considering the correlation between various operating capacities and reducing the error between the calculation result and the actual value.
[0065] Optionally, in an embodiment, the calculation of the operating capacity of the container loading and unloading lines includes: obtaining the operating capacity of each loading and unloading line, the daily container loading and unloading truck ratio of each loading and unloading line, and the average number of standard containers loaded on each truck from the station operation information; calculating the loading operating capacity and unloading operating capacity of each loading and unloading line according to the operating capacity of each loading and unloading line and the daily container loading and unloading truck ratio of each loading and unloading line; summing up the loading operating capacity of each loading and unloading line and the unloading operating capacity of each loading and unloading line to obtain the total loading operating capacity and the total unloading operating capacity; calculating the operating capacity of the container loading and unloading line according to the total loading operating capacity, the total unloading operating capacity and the average number of standard containers loaded on each truck.
[0066] The operating capacity of a container loading and unloading line refers to the maximum amount of container loading and unloading that a loading and unloading line can complete in one day and night. Among them, the daily container loading and unloading truck ratio of each loading and unloading line is calculated based on the historical operation data of the station for a period of time, including: the proportion of trucks that only load but do not unload in container loading and unloading operations α 只装不卸 , the proportion of trucks that only unload but do not load in container loading and unloading operations α 只卸不装 and the proportion of trucks that load and unload containers during loading and unloading operations α 又装又卸 , the sum of the three is 1. Containers include many types, such as flat rack containers, tank containers, side-opening door containers, etc. Standard containers refer to internationally used standard containers built and used in accordance with the international standards formulated by the 104th Technical Committee of the National Organization for Standardization.
[0067] The loading capacity of each loading and unloading line is calculated according to the following formula: N 装 =N 2 *(α 只装不卸 +2α 又装又卸 ), where N 2 is the operating capacity of the loading and unloading line, N 装 is the loading capacity of the loading and unloading line. The unloading capacity of each loading and unloading line is calculated according to the following formula: N 卸 =N 2 *(α 只卸不装 +2α 又装又卸 ), where N 卸is the unloading capacity of the loading and unloading line. When calculating the loading and unloading capacity of each loading and unloading line, you can calculate each loading and unloading line according to different yards and then sum them up. You can also calculate separately according to the operating area, such as the heavy container area, empty container area, and medium container area. The parameter values used for calculation should be determined according to the actual situation of each cargo area of the inspected cargo yard.
[0068] The loading capacity of each loading and unloading line and the unloading capacity of each loading and unloading line are summed up to obtain the total loading capacity and the total unloading capacity, which are calculated according to the following formula: in, is the total capacity of loading operations, It is the total capacity for unloading operations.
[0069] The container loading and unloading line operating capacity is calculated based on the total loading capacity, the total unloading capacity and the average number of standard containers loaded on each truck. The calculation formula is: Where q is the average number of standard containers loaded on each truck.
[0070] A calculation method for the operating capacity of container loading and unloading lines is provided. The calculated operating capacity of container loading and unloading lines is used to calculate and analyze the comprehensive operating capacity of railway freight yards, providing a basis for the calculation of the comprehensive operating capacity of railway freight yards.
[0071] Optionally, in an embodiment, the calculation formula for the production capacity of the loading and unloading equipment is:
[0072] Q 装卸 =k 1 K 2 QUR 技 ;
[0073] Among them, Q 装卸 is the production capacity of loading and unloading equipment, K 1 is the mechanical time utilization coefficient, K 2 is the mechanical load utilization coefficient, t is the loading and unloading operation time, Q 技 For technical production capacity around the clock.
[0074] The production capacity of loading and unloading equipment refers to the amount of cargo loading and unloading that can be completed per hour by loading and unloading machinery under certain specific working conditions. Among them, the loading and unloading operation time is one day or one hour. The mechanical time utilization coefficient represents the ratio of the number of hours that the machinery can be used for actual work in a day and night to the total time of a day and night. The mechanical time utilization coefficient depends on the fixed operation time, the workers' shift time, the workers' meal time, the machinery refueling and charging maintenance time, etc. The mechanical load utilization coefficient represents the ratio of the number of containers handled by the machinery in an average working cycle to the rated number of containers. For container loading and unloading machinery, the mechanical load utilization coefficient is 1.0 to 2.0.
[0075] A calculation method for the production capacity of loading and unloading equipment is provided. The calculation method of the production capacity of loading and unloading equipment not only considers the influence of the performance of the machinery itself, but also considers the human factors, making the calculation result more accurate.
[0076] The container yard turnover capacity refers to the number of vehicles that can be loaded and unloaded in the yard every day and night. Optionally, in an embodiment, the calculation of the container yard turnover capacity includes: obtaining the maximum storage capacity of the container yard, the average turnover time of the arrival container, the average turnover time of the departure container, and the average turnover time of the transit container from the station operation information; calculating the arrival container turnover capacity, the departure container turnover capacity, and the transit container turnover capacity of each container area in the container yard according to the maximum storage capacity of the container yard, the average turnover time of the arrival container, the average turnover time of the departure container, and the average turnover time of the transit container; calculating the container yard turnover capacity according to the arrival container turnover capacity of each container area, the departure container turnover capacity of each container area, and the transit container turnover capacity of each container area.
[0077] A container yard is a place in a container terminal or in the surrounding area of a terminal for the delivery and storage of containers. There are different areas in a container yard. For example, there are empty container storage areas, container disassembly and assembly areas, refrigeration areas, residual container areas, heavy container storage areas, and temporary storage areas. A container slot is a place designated for the storage of containers in a container yard or container warehouse. Generally, a yard or warehouse is divided into several parts and numbered, and each part is called a container slot. Generally, a slot for storing a 20-foot container is called a standard container slot. For example, in the container entry process, after the container arrives at the container yard, it is determined in which container area the container is stored according to the type of container entrusted, and then the slot is selected manually, semi-automatically, or fully automatically, and the container is placed on the selected slot to complete the entry of the container.
[0078] Specifically, calculate the arrival container turnover capacity N of each container area separately 到: Calculate the outgoing container turnover capacity N of each container area separately 发 : Calculate the transit container turnover capacity N of each container area separately 中转 : Among them, N 到 is the container turnover capacity, N 发 N is the turnover capacity of the outgoing container. 中转 is the turnover capacity of transshipment containers, N 堆存 It is the maximum storage capacity of the container yard. It is the average turnover time of containers arriving at the container slot, that is, the average time from the landing to the departure of the container arriving at the container slot. It is the average turnover time of the container dispatched from the container slot, that is, the average time from the landing to the departure of the container dispatched from the container slot. The average turnover time of containers at the transshipment slot, that is, the average time from the landing to the departure of containers at the transshipment slot. The average turnover time of containers at the arrival slot, the average turnover time of containers at the departure slot, and the average turnover time of containers at the transshipment slot are determined by counting the usage of each slot. If there is no specific statistical data, it is determined according to the values in Table 10.2.9 of the "Code for Design of Railway Stations and Hubs" (GB50091-2006).
[0079] One transshipment operation can be recorded as one loading operation plus one unloading operation, so the calculation formula for the turnover capacity of the container yard is: in, The turnover capacity of the container yard.
[0080] A calculation method for the turnover capacity of a container yard is provided. The calculated turnover capacity of a container yard is used to calculate and analyze the comprehensive operating capacity of a railway freight yard, making the reference factors for calculating the comprehensive operating capacity of a railway freight yard more comprehensive, thereby improving the calculation accuracy.
[0081] Road handling capacity refers to the number of vehicles that are moved out, in or out of the cargo yard in one day and night using handling machinery, tools and manpower. Optionally, in an embodiment, the calculation formula of the road handling capacity is:
[0082] Q 搬运 =n 汽 T 1 p / t 装卸 ;
[0083] Among them, n 汽 is the number of vehicles that can be loaded and unloaded simultaneously in the operation area, T 1 It is the time that the freight yard is available for vehicles to pick up and deliver goods in a day. 装卸is the average loading and unloading operation time for each vehicle, that is, the time from the vehicle stopping at the loading and unloading location to the time when the operation is completed and leaves the loading and unloading location. p is the number of standard containers loaded on each vehicle.
[0084] A calculation method for road handling capacity is provided, and the calculated road handling capacity is used to calculate and analyze the comprehensive operating capacity of the railway freight yard, making the reference factors for calculating the comprehensive operating capacity of the railway freight yard more comprehensive, thereby improving the calculation accuracy.
[0085] Optionally, in an embodiment, the calculation formula for determining the comprehensive operation capacity of the railway freight yard of the railway to be evaluated based on the station operation information and the basic capacity of the railway freight yard is:
[0086]
[0087] in, is the comprehensive operating capacity of the railway freight yard, q is the average number of standard containers loaded on each railway freight car, and c 编组 is the average number of trains at the station, N 本站接发 is the station's train receiving and dispatching capacity, θ 1 is the reduction factor of the throat capacity at the first pick-up and delivery vehicle end, θ 2 is the reduction factor of cargo line loading and unloading capacity, θ 3 is the reduction factor of the throat capacity at the second pick-up and delivery vehicle end, δ 1 is the proportion of boxes that do not fall to the ground, δ 2 is the operation influence coefficient, M is an infinite constant, For container loading and unloading line operation capacity, For the total loading and unloading equipment production capacity, is the turnover capacity of the container yard, Q 搬运 For road carrying capacity.
[0088] For a railway freight station, its total capacity depends on the capacity bottleneck of the large system composed of various equipment. Considering the possible capacity loss between different equipment during the operation coordination process, the calculation formula for the comprehensive operation capacity of the railway freight yard is added to characterize the invalid capacity caused by the incoordination of operations between different types of equipment.
[0089] Specifically, the reduction coefficient of the throat capacity at the first pick-up and delivery end is used to indicate the reduction of the throat capacity at the pick-up and delivery end due to the station's plane layout. The coefficient is 1 for the horizontal row of the departure / shunting yard and the freight yard, and 0.98 for the vertical row. The reduction coefficient of the cargo line loading and unloading capacity is used to indicate the reduction of the cargo line loading and unloading capacity due to the form of the cargo line. The coefficient is 1 for the through-type cargo line and 0.99 for the end-type cargo line. The reduction coefficient of the throat capacity at the second pick-up and delivery end indicates the reduction of the throat capacity at the pick-up and delivery end due to the pick-up and delivery operation. The coefficient is 1 for the pick-up and delivery operation that does not cut the main line, and 0.96 for the one that cuts the main line. The proportion of containers that do not land on the ground indicates that if the container does not land on the ground, the loading and unloading operation is carried out directly between the railway freight car and the road vehicle, and the container yard is not occupied. The operation impact coefficient indicates that if it is only in the form of a train, the use of the shunting line can be ignored. Otherwise, the time required to occupy the shunting line is considered. If shunting / assembly / marshaling (proportion) operation is not performed, the coefficient is 0, otherwise it is 1.
[0090] The calculation of the comprehensive operating capacity of the railway freight yard fully considers the influence of each link of the railway freight yard's production and operation. By comprehensively considering various influencing factors, the comprehensive operating capacity of the railway freight yard is calculated, so that the error between the calculation result and the actual capacity is small and the accuracy is high.
[0091] Embodiment 2
[0092] Based on the same principle as the method for calculating the comprehensive operating capacity of a railway freight yard described in the first embodiment, this embodiment provides a system for calculating the comprehensive operating capacity of a railway freight yard, such as Figure 2 As shown, including:
[0093] A data acquisition module is used to acquire station operation information of the railway freight yard to be evaluated, wherein the station operation information is equipment operation information, personnel operation information, and operation information of coordination between personnel and equipment in the railway freight yard to be evaluated;
[0094] A basic capacity calculation module, used to calculate the basic capacity of the railway freight yard to be evaluated according to the station operation information, wherein the basic capacity of the railway freight yard includes at least one of the following: the shunting yard unmarshaling capacity, the station operation train receiving and dispatching capacity, the container loading and unloading line operation capacity, the loading and unloading equipment production capacity, the container yard turnover capacity and the road handling capacity;
[0095] The comprehensive operation capacity calculation module is used to determine the comprehensive operation capacity of the railway freight yard of the railway to be evaluated based on the station operation information and the basic capacity of the railway freight yard.
[0096] Specifically, the calculation formula for the comprehensive operating capacity of the railway freight yard is:
[0097]
[0098] in, is the comprehensive operating capacity of the railway freight yard, q is the average number of standard containers loaded on each railway freight car, and c 编组 is the average number of trains at the station, N 本站接发 is the station's train receiving and dispatching capacity, θ 1 is the reduction factor of the throat capacity at the first pick-up and delivery vehicle end, θ 2 is the reduction factor of cargo line loading and unloading capacity, θ 3 is the reduction factor of the throat capacity at the second pick-up and delivery vehicle end, δ 1 is the proportion of boxes that do not fall to the ground, δ 2 is the operation influence coefficient, M is an infinite constant, For container loading and unloading line operation capacity, For the total loading and unloading equipment production capacity, is the turnover capacity of the container yard, Q 搬运 For road carrying capacity.
[0099] The basic capability calculation modules include:
[0100] The station operation train receiving and dispatching capacity calculation unit is used to calculate the total time required for the pick-up and delivery operation according to the station operation information; calculate the departure yard throughput capacity and the throat throughput capacity according to the station operation information and the total time required for the pick-up and delivery operation; calculate the station operation train receiving and dispatching capacity according to the station operation information, the departure yard throughput capacity and the throat throughput capacity; specifically, the calculation formula of the station operation train receiving and dispatching capacity is: N 本站接发 ={[N 1 -2*(n 客 -n 不停站通过货物列车 )],N 到发}; where N 本站接发 N is the station's train receiving and dispatching capacity, 1 is the throat passing capacity, n 客 is the number of passenger trains, n 不停站通过货物列车 N is the number of freight trains passing through without stopping. 到发 To ensure the ability to pass the departure point;
[0101] A container loading and unloading line operation capacity calculation unit is used to obtain the operation capacity of each loading and unloading line, the daily container loading and unloading truck ratio of each loading and unloading line, and the average number of standard containers loaded on each truck from the station operation information; according to the operation capacity of each loading and unloading line and the daily container loading and unloading truck ratio of each loading and unloading line, respectively calculate the loading operation capacity and unloading operation capacity of each loading and unloading line; respectively sum the loading operation capacity and the unloading operation capacity of each loading and unloading line to obtain the total loading operation capacity and the total unloading operation capacity; calculate the container loading and unloading line operation capacity according to the total loading operation capacity, the total unloading operation capacity and the average number of standard containers loaded on each truck;
[0102] The loading and unloading equipment production capacity calculation unit is used to calculate the loading and unloading equipment production capacity Q 装卸 :Q 装卸 =k 1 K 2 QUR 技 ; Among them, Q 装卸 is the production capacity of loading and unloading equipment, K 1 is the mechanical time utilization coefficient, K 2 is the mechanical load utilization coefficient, t is the loading and unloading operation time, Q 技 For the technical production capacity of one day and one night;
[0103] A container yard turnover capacity calculation unit is used to obtain the maximum storage capacity of the container yard, the average turnover time of the arrival container, the average turnover time of the departure container and the average turnover time of the transit container from the station operation information; calculate the arrival container turnover capacity, the departure container turnover capacity and the transit container turnover capacity of each container area in the container yard according to the maximum storage capacity of the container yard, the average turnover time of the arrival container, the average turnover time of the departure container and the average turnover time of the transit container; calculate the container yard turnover capacity according to the arrival container turnover capacity of each container area, the departure container turnover capacity of each container area and the transit container turnover capacity of each container area;
[0104] Road handling capacity calculation unit, used to calculate the road handling capacity Q 搬运 :Q 搬运 =n 汽 T 1 p / t 装卸 ; where n 汽 is the number of vehicles that can be loaded and unloaded simultaneously in the operation area, T 1 is the time that the freight yard is available for vehicles to pick up and deliver goods in a day, t 装卸is the average loading and unloading time of each vehicle, and p is the number of standard containers loaded on each vehicle.
[0105] The station operation train receiving and dispatching capacity calculation unit includes: a total time calculation subunit required for the train pickup and delivery operation, which is used to obtain the locomotive preparation operation time t within one day from the station operation information; 整备 , The driver cannot use the time of the machine adjustment within a day 司机 , the average number of cars that need to be picked up and delivered at the station in one day Q 取送 , average length of trucks I, effective length of the lead-out line used for picking up, delivering and shunting vehicles L 牵 , the average time consumed for a pick-up and delivery operation t 取送 If the shunting machine is a special shunting machine in the railway freight yard to be evaluated, the available time T of a shunting machine at the station in one day is calculated. 调机 :T 调机 =1440-t 整备 -t 司机 v If the shunting machine is a common shunting machine for at least two freight stations, the average effective operation time of the shunting machine in the station in one day is obtained from the station operation information, which is used as the available time T of a shunting machine in the station in one day. 调机 If the locomotive in the railway freight yard to be evaluated is capable of picking up and delivering the entire train, the number of pickup and delivery times n is calculated according to the following formula: 取送 :n 取送 =T 调机 / t 取送 ; Otherwise, calculate the number of pick-up and delivery times n according to the following formula 取送 :n 取送 =min(Q 取送 I / L 牵 , T 调机 / t 取送 ); Calculate the total time required for the pick-up and delivery operation based on the number of pick-up and delivery operations and the average time consumed for one pick-up and delivery operation.
[0106] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0107] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0108] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0109] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0110] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0111] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.
Claims
1. A method for calculating the comprehensive operating capacity of a railway freight yard, characterized in that: The following steps are involved: Acquire station operation information of the railway freight yard to be evaluated, wherein the station operation information is equipment operation information, personnel operation information, and operation information of coordination between personnel and equipment in the railway freight yard to be evaluated; Calculate the basic capacity of the railway freight yard to be evaluated according to the station operation information, wherein the basic capacity of the railway freight yard includes at least one of the following: the unpacking capacity of the shunting yard, the receiving and dispatching capacity of the station operation trains, the operating capacity of the container loading and unloading line, the production capacity of the loading and unloading equipment, the turnover capacity of the container yard, and the road handling capacity; Based on the station operation information and the basic capacity of the railway freight yard, the comprehensive operation capacity of the railway freight yard of the railway to be evaluated is determined.
2. According to claim 1, a method for calculating the comprehensive operating capacity of a railway freight yard is characterized in that: The calculation of the station's operating train receiving and dispatching capacity includes: Calculate the total time required for the vehicle pick-up and delivery operation according to the station operation information; According to the station operation information and the total time required for the vehicle pick-up and delivery operation, the throughput capacity to the departure yard and the throat throughput capacity are calculated respectively; The train receiving and dispatching capacity of the station is calculated according to the station operation information, the arrival and departure yard throughput capacity and the throat throughput capacity.
3. According to claim 2, a method for calculating the comprehensive operating capacity of a railway freight yard is characterized in that: The total time required for the vehicle pick-up and delivery operation is calculated according to the station operation information, including: Obtain the locomotive preparation operation time t within one day from the station operation information 整备 , The driver cannot use the time of the machine adjustment within a day 司机 , the average number of cars that need to be picked up and delivered at the station in one day Q 取送 , average length of trucks l, effective length of the lead-out line used for picking up, delivering and shunting vehicles L 牵 , the average time consumed for a pick-up and delivery operation t 取送 ; If the shunting machine is a special shunting machine in the railway freight yard to be evaluated, the available time T of a shunting machine at the station in one day is calculated. 调机 :T 调机 =1440-t 整备 -t 司机 If the shunting machine is a common shunting machine for at least two freight stations, the average effective operation time of the shunting machine in the station in one day is obtained from the station operation information, which is used as the available time T of a shunting machine in the station in one day. 调机 ; If the locomotive in the railway freight yard to be evaluated is capable of picking up and delivering the entire train, the number of pickup and delivery times n is calculated according to the following formula: 取送 :n 取送 =T 调机 / t 取送 ; Otherwise, calculate the number of pick-up and delivery times n according to the following formula 取送 :n 取送 =min(Q 取送 I / L 牵 , T 调机 / t 取送 ); The total time required for the vehicle picking-up and delivery operation is calculated according to the number of vehicle picking-up and delivery times and the average time consumed for one vehicle picking-up and delivery operation.
4. According to claim 2, a method for calculating the comprehensive operating capacity of a railway freight yard is characterized in that: The calculation formula for calculating the station operation train receiving and dispatching capacity based on the station operation information, the arrival and departure yard throughput capacity, and the throat throughput capacity is: N 本站接发 ={[N1-2*(n 客 -n 不停站通过货物列车 )],N 到发 }; Among them, N 本站接发 is the station's train receiving and dispatching capacity, N1 is the throat passing capacity, and n 客 is the number of passenger trains, n 不停站通过货物列车 N is the number of freight trains passing through without stopping. 到发 To achieve the ability to pass the departure point.
5. According to claim 1, a method for calculating the comprehensive operating capacity of a railway freight yard is characterized in that: The calculation of the container loading and unloading line operating capacity includes: Obtaining the operating capacity of each loading and unloading line, the daily container loading and unloading ratio of each loading and unloading line to trucks, and the average number of standard containers loaded on each truck from the station operation information; Calculate the loading and unloading capacity of each loading and unloading line according to the operating capacity of each loading and unloading line and the daily container loading and unloading ratio of each loading and unloading line; The loading capacity of each loading and unloading line and the unloading capacity of each loading and unloading line are summed up to obtain the total loading capacity and the total unloading capacity; The container loading and unloading line operating capacity is calculated according to the total loading operation capacity, the total unloading operation capacity and the average number of standard containers loaded on each truck.
6. A method for calculating the comprehensive operating capacity of a railway freight yard according to claim 1, characterized in that: The calculation formula for the production capacity of the loading and unloading equipment is: Q 装卸 =k1K2tQ 技 ; Among them, Q 装卸 is the production capacity of loading and unloading equipment, K1 is the mechanical time utilization coefficient, K2 is the mechanical load utilization coefficient, t is the loading and unloading operation time, Q 技 For technical production capacity around the clock.
7. A method for calculating the comprehensive operating capacity of a railway freight yard according to claim 1, characterized in that: The calculation of the container yard turnover capacity includes: Obtaining the maximum storage capacity of the container yard, the average turnover time of the arriving containers, the average turnover time of the departing containers, and the average turnover time of the transit containers from the station operation information; Calculate the arrival container turnover capacity, the departure container turnover capacity and the transit container turnover capacity of each container area in the container yard according to the maximum storage capacity of the container yard, the average turnover time of the arrival container slot, the average turnover time of the departure container slot and the average turnover time of the transit container slot; The container yard turnover capacity is calculated according to the arrival container turnover capacity of each container area, the departure container turnover capacity of each container area and the transit container turnover capacity of each container area.
8. A method for calculating the comprehensive operating capacity of a railway freight yard according to claim 1, characterized in that: The calculation formula of the road carrying capacity is: Q 搬运 =n 汽 T1p / t 装卸 ; Among them, n 汽 is the number of vehicles that can be loaded and unloaded at the same time in the operation area, T1 is the time that the freight yard can provide for vehicles to pick up and deliver goods in a day, and t 装卸 is the average loading and unloading time of each vehicle, and p is the number of standard containers loaded on each vehicle.
9. A method for calculating the comprehensive operating capacity of a railway freight yard according to claim 1, characterized in that: The calculation formula for determining the comprehensive operation capacity of the railway freight yard of the railway to be evaluated based on the station operation information and the basic capacity of the railway freight yard is: in, is the comprehensive operating capacity of the railway freight yard, q is the average number of standard containers loaded on each railway freight car, and c 编组 is the average number of trains at the station, N 本站接发 is the station's train receiving and dispatching capacity, θ1 is the reduction coefficient of the throat capacity at the first pick-up and delivery end, θ2 is the reduction coefficient of the cargo line loading and unloading capacity, θ3 is the reduction coefficient of the throat capacity at the second pick-up and delivery end, δ1 is the proportion of containers that do not fall to the ground, δ2 is the operation influence coefficient, and M is an infinite constant. For container loading and unloading line operation capacity, is the total loading and unloading equipment production capacity, is the turnover capacity of the container yard, Q 搬运 For road carrying capacity.
10. A railway freight yard comprehensive operation capacity calculation system, characterized in that: include: A data acquisition module is used to acquire station operation information of the railway freight yard to be evaluated, wherein the station operation information is equipment operation information, personnel operation information, and operation information of coordination between personnel and equipment in the railway freight yard to be evaluated; A basic capacity calculation module, used to calculate the basic capacity of the railway freight yard to be evaluated according to the station operation information, wherein the basic capacity of the railway freight yard includes at least one of the following: the shunting yard unmarshaling capacity, the station operation train receiving and dispatching capacity, the container loading and unloading line operation capacity, the loading and unloading equipment production capacity, the container yard turnover capacity and the road handling capacity; The comprehensive operation capacity calculation module is used to determine the comprehensive operation capacity of the railway freight yard of the railway to be evaluated based on the station operation information and the basic capacity of the railway freight yard.