Eight-split spacer mounting device
By designing a fully automatic eight-splitting spacer installation device, the automatic installation of high-voltage line spacer is achieved by using the grab and locking mechanism, which solves the problems of manual installation hazards and low efficiency, and improves the safety and applicability of the installation.
Patent Information
- Application Number
- CN202411451474.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-17
- Publication Date
- 2024-11-15
AI Technical Summary
The installation of spacer rods for existing high-voltage lines requires manual climbing to high places, which is dangerous and inefficient, making it difficult to achieve automated installation.
An eight-divided spacer mounting device including a fixing frame, a grab longitudinal frame, a grab transverse frame, a first grab mechanism and a locking mechanism is designed, and the slide rail, a grab motor, a grab roller, a longitudinal Components such as frame rotary motor, cross frame motor and locking robot arm realize the functions of fully automatic grabbing and installation of spacer rods.
It realizes fully automatic installation of spacer rods on high-voltage lines, improves working safety and efficiency, and is suitable for installation of spacer rods of different voltages and specifications, reducing the risk of manual operation.
Smart Images

Figure CN118970732A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of high-voltage line operation equipment, and in particular to an eight-split spacer rod installation device. Background Art
[0002] High-voltage transmission lines are supported by several towers. The conductors are laid on each tower to form a high-voltage transmission network. There is a large height difference between the high-voltage line and the ground to ensure a safe distance between the high-voltage line and the ground. The high-voltage line also requires irregular maintenance, such as removing damaged or aging spacers and installing new spacers. The existing manual installation method requires manual climbing to a line nearly 100 meters high and wearing isolation clothing. Therefore, it is not only dangerous but also inefficient during operation. Summary of the invention
[0003] The present invention aims to solve the above problems and provide an eight-split spacer rod installation device.
[0004] The present invention comprises a fixed frame, a grabbing longitudinal frame, a grabbing transverse frame, a grabbing mechanism and a locking mechanism, wherein the grabbing mechanism comprises a first grabbing mechanism and a second grabbing mechanism, wherein the first grabbing mechanism is arranged at the bottom of the fixed frame and can grab the wire at the top, the grabbing longitudinal frame is rotatably arranged at the bottom of the fixed frame, the middle part of the grabbing transverse frame is slidably connected to the grabbing longitudinal frame and can move axially along the grabbing longitudinal frame, the second grabbing mechanism is arranged at both ends of the grabbing transverse frame, the second grabbing mechanism can grab the wire corresponding to it and make an outward expansion or inward movement along the grabbing transverse frame, one end of the locking mechanism is fixed to the fixed frame, and one end of the locking mechanism is fixed to the fixed frame. A buckle is provided at the end, and the buckle can buckle the lock of the spacer bar. The first grasping mechanism can be used to walk on the wire, change the spacing of the top wires, and open or tighten the top wires. Secondly, a second grasping mechanism is provided on the grasping cross bar, so that the second grasping mechanism that grasps the wire can carry the wire to move laterally outward or inward, and the grasping cross bar can be adjustably arranged on the grasping longitudinal bar, so that the second grasping mechanism that grasps the wire can move longitudinally, which makes it easy to grasp the wire and place it in the lock of the spacer bar, thereby realizing fully automatic installation of the spacer bar. In addition, the locking mechanism can buckle the lock.
[0005] Specifically, the first grabbing mechanism includes a grabbing slide rail, a grabbing slide bar, a grabbing motor and a grabbing roller. The grabbing slide rail is fixed to the bottom of the fixed frame, and the grabbing slide bar is arranged below the grabbing slide rail through a support member. The output end of the grabbing motor is connected to the input end of the grabbing slide bar, and a grabbing roller is arranged on the grabbing slide bar. The top of the grabbing roller is slidably connected to the grabbing slide rail. Driving the grabbing motor can drive the grabbing slide bar to rotate, thereby driving the grabbing roller to slide axially along the grabbing slide rail and drive the wire to expand or retract. The grabbing roller is set up to act as a roller and also has a wire grabbing function, and drives the grabbing roller to move horizontally through the grabbing slide bar, thereby driving the wire to move horizontally. Therefore, it is convenient to grab the wire to the lock buckle corresponding to the spacer bar, and complete the step of placing the wire in the lock buckle of the spacer bar.
[0006] Specifically, the top of the grabbing vertical frame is arranged on the bottom of the fixed frame through the vertical frame rotation motor and can drive the grabbing vertical frame to rotate, a vertical frame slide rail is arranged on the front of the grabbing vertical frame, a vertical frame guide shaft is arranged on the side, a vertical frame guide motor is arranged on the end of the vertical frame guide shaft, a horizontal frame slide groove is arranged in the middle of the grabbing horizontal frame, and a grabbing connecting piece is also arranged on the grabbing horizontal frame, the vertical frame guide shaft passes through the grabbing connecting piece and can drive the grabbing horizontal frame to move axially along the grabbing vertical frame, thereby driving the second grabbing mechanism on the grabbing horizontal frame to move axially up and down, and the grabbing horizontal frame is arranged on the grabbing vertical frame, and the two ends of the grabbing horizontal frame are used to fix the second grabbing mechanism. Therefore, the second grabbing mechanism can follow the grabbing horizontal frame to perform axial movement on the grabbing vertical frame, so that the present design can be applicable to the installation of eight-split spacer bars of different voltages and specifications, thereby improving the overall applicability.
[0007] Specifically, there are three grabbing horizontal frames, which are arranged in sequence from top to bottom, and the three vertical frame guide shafts are staggered in sequence. The staggered vertical frame guide shafts can improve the utilization of space, making the overall design more compact, reasonable and beautiful.
[0008] Specifically, the second grasping mechanism includes a cross-frame motor, a cross-frame slide rail, a cross-frame guide shaft and a cross-frame clamp. The cross-frame slide rail is arranged at the end of the grasping cross-frame, and the cross-frame clamp is arranged on the cross-frame slide rail. The cross-frame guide shaft penetrates the cross-frame clamp and can drive the cross-frame clamp to move axially on the cross-frame slide rail. A cross-frame motor is arranged at the end of the cross-frame guide shaft. The cross-frame motor is used to drive the cross-frame guide shaft to move, and the cross-frame clamp is driven to move through the cross-frame guide shaft, so that the cross-frame clamp can move laterally, thereby improving the overall flexibility.
[0009] Specifically, the locking mechanism includes a robotic arm, one end of which is fixed on the fixed frame, and the other end is provided with a locking assembly. The robotic arm can drive the locking assembly to the locking buckle of each spacer rod, and buckle the wire in the locking buckle of the spacer rod through the locking assembly. The locking assembly can be driven to the locking buckle on each spacer rod by the robotic arm, thereby completing the buckling of the lock.
[0010] Specifically, the locking assembly includes a locking frame, a locking plate and a locking drive. The locking frame is fixed at the end of the robotic arm. A locking opening is provided in the locking frame. The locking plate is provided in the locking opening. The locking drive is located outside the locking opening and is connected to the locking plate through a locking shaft. Driving the locking drive can drive the locking plate to move axially, thereby compressing or increasing the space in the locking opening, and then locking the buckle of the spacer rod. The locking assembly is transported to the buckle of the split rod so that the buckle is located in the locking opening, and then the buckle is squeezed by the locking plate to cause the buckle to lock.
[0011] Specifically, the locking frame is "F"-shaped, and the locking drive includes a locking motor and a locking shaft. The locking motor is slidably connected to the locking frame through a connecting body. One end of the locking shaft is connected to the locking motor, and the other end extends and passes through the locking frame to be connected to the locking plate. Beneficial Effects
[0012] By arranging a second grabbing mechanism on the grabbing cross bar, the second grabbing mechanism for grabbing the wire can carry the wire to perform a lateral outward expansion or inward movement, and the grabbing cross bar can be adjustably arranged on the grabbing longitudinal bar, so that the second grabbing mechanism for grabbing the wire can move longitudinally, thereby facilitating the grabbing of the wire and placing it into the lock of the spacer bar, thereby realizing fully automatic installation of the spacer bar. In addition, the locking mechanism can lock the lock. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 : is a schematic diagram of the overall structure of the present invention; Figure 2 :for Figure 1 A schematic diagram of the structure of the grabbing horizontal frame and the grabbing vertical frame in coordination state; Figure 3 : A schematic diagram of the structure of grabbing the longitudinal axis of the present invention; Figure 4 : A schematic structural diagram of the second gripping mechanism of the present invention; Figure 5 : Schematic diagram of the overall structure of the locking mechanism of the present invention; Figure 6 : A schematic structural diagram of the locking assembly of the present invention.
[0014] Among them: 10, fixed frame; 20, grabbing longitudinal frame; 30, grabbing transverse frame; 40, second grabbing mechanism; 50, locking mechanism; 60, first grabbing mechanism; 201, rotary motor; 202, longitudinal frame guide motor; 203, longitudinal frame guide shaft; 204, longitudinal frame slide rail; 301, transverse frame motor; 302, transverse frame slide rail; 303, transverse frame guide shaft; 304, transverse frame clamp; 501, mechanical arm; 502, locking assembly; 503, locking frame; 504, locking piece; 505, locking mouth; 506, locking motor; 507, locking shaft; 601, locking roller; 602, grabbing slide bar; 603, grabbing motor; 604, grabbing slide rail. DETAILED DESCRIPTION
[0015] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0016] In the description of the present invention, it should be noted that the terms "middle", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "inside", "outside", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", etc., are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.
[0017] Embodiment 1: The present invention aims to provide an eight-split spacer rod installation device: Before describing the specific embodiments, the eight-split spacer bar is described first. The eight-split spacer bar includes a body and lock buckles. There are eight lock buckles, so it is an eight-split spacer bar.
[0018] Please combine Figure 1-6Referring to the present invention, the present invention includes a fixed frame 10, a grabbing longitudinal frame 20, a grabbing transverse frame 30, a grabbing mechanism and a locking mechanism 50. The grabbing mechanism includes a first grabbing mechanism 60 and a second grabbing mechanism 40. The first grabbing mechanism 60 is arranged at the bottom of the fixed frame 10 and can grab the wire at the top. The grabbing longitudinal frame 20 is rotatably arranged at the bottom of the fixed frame 10. The middle part of the grabbing transverse frame 30 is slidably connected to the grabbing longitudinal frame 20 and can move axially along the grabbing longitudinal frame 20. The second grabbing mechanism 40 is arranged at both ends of the grabbing transverse frame 30. The second grabbing mechanism 40 can grab the wire corresponding to it and make an outward expansion or inward movement along the grabbing transverse frame 30. The locking mechanism 50 One end is fixed on the fixing frame 10, and the other end is provided with a buckle, and the buckle can buckle the lock of the spacer bar. The first grasping mechanism 60 can be used to walk on the wire, change the spacing of the top wire, and pull the top wire apart or tighten it. Secondly, by arranging the second grasping mechanism 40 on the grasping cross bar, the second grasping mechanism 40 for grasping the wire can carry the wire to move laterally outward or inward, and the grasping cross bar can be adjustably arranged on the grasping longitudinal bar, so that the second grasping mechanism 40 for grasping the wire can move longitudinally, so as to facilitate the grasping of the wire and place it into the buckle of the spacer bar, thereby realizing the fully automatic installation of the spacer bar. In addition, the locking mechanism 50 can buckle the buckle.
[0019] Specifically, the first grabbing mechanism 60 includes a grabbing slide rail 604, a grabbing slide bar 602, a grabbing motor 603 and a grabbing roller. The grabbing slide rail 604 is fixed to the bottom of the fixed frame 10. The grabbing slide bar 602 is arranged below the grabbing slide rail 604 through a support member. The output end of the grabbing motor 603 is connected to the input end of the grabbing slide bar 602. The grabbing slide bar 602 is provided with a grabbing roller. The top of the grabbing roller is slidably connected to the grabbing slide rail. On 604, driving the grabbing motor 603 can drive the grabbing slide bar 602 to rotate, thereby driving the grabbing roller to slide axially along the grabbing slide rail 604, and driving the wire to expand or retract. The grabbing roller set up has a roller function and also has a wire grabbing function, and drives the grabbing roller to move horizontally through the grabbing slide bar 602, thereby driving the wire to move horizontally, so it is convenient to grab the wire into the lock buckle corresponding to the spacer bar, completing the step of placing the wire in the lock buckle of the spacer bar.
[0020] Specifically, the top of the grabbing vertical frame 20 is arranged at the bottom of the fixed frame 10 through the vertical frame rotation motor 201 and can drive the grabbing vertical frame 20 to rotate, the front of the grabbing vertical frame 20 is provided with a vertical frame slide rail 204, the side is provided with a vertical frame guide shaft 203, the end of the vertical frame guide shaft 203 is provided with a vertical frame guide motor 202, the middle of the grabbing horizontal frame 30 is provided with a horizontal frame slide groove, the grabbing horizontal frame 30 is also provided with a grabbing connecting piece, the vertical frame guide shaft 203 passes through the grabbing connecting piece to drive The grabbing cross frame 30 moves axially along the grabbing longitudinal frame 20, thereby driving the second grabbing mechanism 40 on the grabbing cross frame 30 to move axially up and down. The grabbing cross frame 30 is set on the grabbing longitudinal frame 20, and the two ends of the grabbing cross frame 30 are used to fix the second grabbing mechanism 40. Therefore, the second grabbing mechanism 40 can follow the grabbing cross frame 30 to move axially on the grabbing longitudinal frame 20, so that the present design can be applied to the installation of eight-split spacer bars of different voltages and specifications, thereby improving the overall applicability.
[0021] Specifically, there are three grabbing horizontal frames 30, which are arranged in sequence from top to bottom, and the three vertical frame guide shafts 203 are staggered in sequence. The staggered vertical frame guide shafts 203 can improve the utilization of space, making the overall design more compact, reasonable and beautiful.
[0022] It can be understood that the three longitudinal frame guide shafts 203 can be arranged on the left and right sides, that is, the first longitudinal frame guide shaft 203 is arranged on the left side of the grabbing longitudinal frame 20, the second longitudinal frame guide shaft 203 is arranged on the right side of the grabbing longitudinal frame 20, and the third longitudinal frame guide shaft 203 is arranged below the first longitudinal frame guide shaft 203 and is also located on the left side. It can also be arranged in two ways: right and left sides. The right and left arrangement is similar to the above-mentioned method and will not be repeated here.
[0023] Specifically, the second gripping mechanism 40 includes a horizontal frame motor 301, a horizontal frame slide rail 302, a horizontal frame guide shaft 303 and a horizontal frame clamp 304. The horizontal frame slide rail 302 is arranged at the end of the gripping horizontal frame 30, and the horizontal frame clamp 304 is arranged on the horizontal frame slide rail 302. The horizontal frame guide shaft 303 runs through the horizontal frame clamp 304 and can drive the horizontal frame clamp 304 to perform axial movement on the horizontal frame slide rail 302. A horizontal frame motor 301 is arranged at the end of the horizontal frame guide shaft 303. The horizontal frame motor 301 is used to drive the horizontal frame guide shaft 303 to move, and the horizontal frame clamp 304 is driven to move through the horizontal frame guide shaft 303, so that the horizontal frame clamp 304 can move laterally, thereby improving the overall flexibility.
[0024] Specifically, the locking mechanism 50 includes a mechanical arm 501, one end of which is fixed on the fixed frame 10, and the other end is provided with a locking component 502. The mechanical arm 501 can drive the locking component 502 to the locking part of each spacer bar, and the wire can be fastened in the locking part of the spacer bar through the locking component 502. The locking component 502 can be driven to the locking part on each spacer bar by the mechanical arm 501, thereby completing the fastening of the locking part.
[0025] Specifically, the locking assembly 502 includes a locking frame 503, a locking piece 504 and a locking drive. The locking frame 503 is fixed at the end of the robotic arm 501. A locking opening 505 is provided in the locking frame 503. The locking piece 504 is arranged in the locking opening 505. The locking drive is located outside the locking opening 505 and is connected to the locking piece 504 through a locking shaft 507. Driving the locking drive can drive the locking piece 504 to move axially, thereby compressing or increasing the space in the locking opening 505, and then buckling the lock of the spacer rod. The locking assembly 502 is transported to the lock of the split rod so that the lock is located in the locking opening 505, and then the lock is squeezed by the locking piece 504 to cause the lock to be locked.
[0026] Specifically, the locking frame 503 is "F"-shaped, and the locking drive includes a locking motor 506 and a locking shaft 507. The locking motor 506 is slidably connected to the locking frame 503 through a connector. One end of the locking shaft 507 is connected to the locking motor 506, and the other end extends through the locking frame 503 and is connected to the locking plate 504.
[0027] During specific use, the whole is placed on the wire by manual or drone delivery. Here, the drone delivery method is taken as an example. The entire fixed frame 10 is lifted by the drone. At the same time, the grabbing longitudinal frame 20 is controlled by controlling the longitudinal frame rotation motor 201 to keep it parallel to the width of the fixed frame 10. At this time, the drone is dropped and the grabbing roller falls on the wire.
[0028] At this time, the longitudinal frame guide motor 202 is driven to rotate, thereby driving the axial movement of the grabbing cross frame 30, thereby increasing the height of the grabbing cross frame 30 on the grabbing longitudinal frame 20, until the horizontal height of the cross frame clamp 304 on the grabbing cross frame 30 is higher than the corresponding wire height, the longitudinal frame guide motor 202 is stopped, and the rotary motor 201 is started to drive the grabbing longitudinal frame 20 and the grabbing cross frame 30 located on the grabbing longitudinal frame 20 to rotate 90 degrees clockwise or counterclockwise, so that each corresponding cross frame clamp 304 is located directly above each corresponding wire.
[0029] At this time, the horizontal frame motor 301 in each second grasping mechanism 40 is adjusted laterally to drive the horizontal frame guide shaft 303 to perform corresponding actions, so that each horizontal frame clamp 304 is located directly above each corresponding wire, and the vertical frame guide motor 202 is driven in reverse to make the grasping horizontal frame 30 descend. Since the horizontal frame clamp 304 is located directly above the wire, the grasping horizontal frame 30 after descending drives the horizontal frame clamp 304 to move downward, and then grasps the corresponding wire, and then controls the lateral movement of the horizontal frame clamp 304 through the horizontal frame guide shaft 303, and controls the longitudinal movement of the horizontal frame clamp 304 through the vertical frame guide shaft 203, until the wire is placed in the lock of the spacer rod.
[0030] Then, the locking assembly 502 is transported to the lock by the robotic arm 501, and the lock is located inside the locking opening 505. At this time, the locking drive drives the locking piece 504 to move, compressing the space inside the locking opening 505, and then pushing the locks to engage with each other. At this time, the locking of the spacer rod lock is completed, and the remaining locks can be locked in the above manner.
[0031] The above shows and describes the basic principles, main features and advantages of the present invention; technicians in this industry should understand that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only preferred examples of the present invention and are not used to limit the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements all fall within the scope of the present invention to be protected; the scope of protection claimed by the present invention is defined by the attached claims and their equivalents.
Claims
1. An eight-split spacer bar installation device, comprising a fixing frame (10), a grabbing longitudinal frame (20), a grabbing transverse frame (30), a grabbing mechanism and a locking mechanism (50), characterized in that: The grabbing mechanism comprises a first grabbing mechanism (60) and a second grabbing mechanism (40), wherein the first grabbing mechanism (60) is arranged at the bottom of the fixing frame (10) and can grab the wire at the top, the grabbing longitudinal frame (20) is rotatably arranged at the bottom of the fixing frame (10), the middle part of the grabbing transverse frame (30) is slidably connected to the grabbing longitudinal frame (20) and can move axially along the grabbing longitudinal frame (20), the second grabbing mechanism (40) is arranged at both ends of the grabbing transverse frame (30), the second grabbing mechanism (40) can grab the corresponding wire and make an outward expansion or inward movement along the grabbing transverse frame (30), one end of the locking mechanism (50) is fixed to the fixing frame (10), and the other end is provided with a buckle, and the buckle can buckle the locking buckle of the spacer rod.
2. The eight-split spacer bar installation device according to claim 1, characterized in that: The first grabbing mechanism (60) includes a grabbing rail (604), a grabbing slide bar (602), a grabbing motor (603) and a grabbing roller. The grabbing rail (604) is fixed to the bottom of the fixed frame (10). The grabbing slide bar (602) is arranged below the grabbing rail (604) through a support member. The output end of the grabbing motor (603) is connected to the input end of the grabbing slide bar (602). A grabbing roller is arranged on the grabbing slide bar (602). The top of the grabbing roller is slidably connected to the grabbing rail (604). Driving the grabbing motor (603) can drive the grabbing slide bar (602) to rotate, thereby driving the grabbing roller to slide axially along the grabbing rail (604) and drive the wire to expand or retract.
3. The eight-split spacer bar installation device according to claim 1, characterized in that: The top of the grabbing longitudinal frame (20) is arranged at the bottom of the fixed frame (10) through a longitudinal frame rotary motor (201) and can drive the grabbing longitudinal frame (20) to rotate. The front of the grabbing longitudinal frame (20) is provided with a longitudinal frame slide rail (204), and the side is provided with a longitudinal frame guide shaft (203). The end of the longitudinal frame guide shaft (203) is provided with a longitudinal frame guide motor (202). The middle of the grabbing transverse frame (30) is provided with a transverse frame slide groove. The grabbing transverse frame (30) is also provided with a grabbing connecting plate. The longitudinal frame guide shaft (203) passes through the grabbing connecting plate and can drive the grabbing transverse frame (30) to move axially along the grabbing longitudinal frame (20), thereby driving the second grabbing mechanism (40) on the grabbing transverse frame (30) to move axially up and down.
4. The eight-split spacer bar installation device according to claim 3 is characterized in that: There are three grabbing horizontal frames (30), which are arranged in sequence from top to bottom, and the three vertical frame guide shafts (203) are arranged in sequence in a staggered manner.
5. The eight-split spacer bar installation device according to claim 1, characterized in that: The second gripping mechanism (40) comprises a horizontal frame motor (301), a horizontal frame slide rail (302), a horizontal frame guide shaft (303) and a horizontal frame clamping claw (304); the horizontal frame slide rail (302) is arranged at the end of the gripping horizontal frame (30); the horizontal frame clamping claw (304) is arranged on the horizontal frame slide rail (302); the horizontal frame guide shaft (303) passes through the horizontal frame clamping claw (304) and can drive the horizontal frame clamping claw (304) to perform axial movement on the horizontal frame slide rail (302); a horizontal frame motor (301) is arranged at the end of the horizontal frame guide shaft (303); the horizontal frame motor (301) is used to drive the horizontal frame guide shaft (303) to move.
6. The eight-split spacer bar installation device according to claim 1, characterized in that: The locking mechanism (50) comprises a mechanical arm (501), one end of which is fixed to the fixing frame (10), and the other end of which is provided with a locking assembly (502). The mechanical arm (501) can drive the locking assembly (502) to the locking position of each spacer bar, and the wire can be buckled in the locking assembly of the spacer bar through the locking assembly (502).
7. The eight-split spacer bar installation device according to claim 6, characterized in that: The locking assembly (502) includes a locking frame (503), a locking piece (504) and a locking drive. The locking frame (503) is fixed to the end of the mechanical arm (501). A locking opening (505) is provided in the locking frame (503). The locking piece (504) is arranged in the locking opening (505). The locking drive is located outside the locking opening (505) and is connected to the locking piece (504) via a locking shaft (507). Driving the locking drive can drive the locking piece (504) to move axially, thereby compressing or increasing the space in the locking opening (505), and then buckling the spacer rod.
8. The eight-split spacer bar installation device according to claim 1, characterized in that: The locking frame (503) is in an "F" shape, and the locking drive comprises a locking motor (506) and a locking shaft (507). The locking motor (506) is slidably connected to the locking frame (503) through a connecting body. One end of the locking shaft (507) is connected to the locking motor (506), and the other end extends and passes through the locking frame (503) to be connected to the locking piece (504).