Invisible channel device of closed-loop brick making production line
By designing an invisible channel device on the closed-loop brick production line, the telescopic conveyor line closes the channel gap when there are no personnel or equipment, and opening the channel when there are personnel or equipment, the channel interference problem is solved and the efficient operation of the production line and material flow is maintained. .
Patent Information
- Application Number
- CN202410976366.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-20
- Publication Date
- 2024-11-19
AI Technical Summary
When a closed-loop brick production line requires personnel or equipment to enter and exit, the reserved channels will interfere with the high-speed operation of the production line and affect the efficiency of automated production.
Design an invisible channel device, by installing a telescopic conveyor line that can be displaced in the length direction on the pre-sequence conveyor line, the telescopic conveyor line is shifted backward when there is no personnel or equipment entering and exiting, and the telescopic conveyor line is connected to the post-sequence conveyor line to close the channel gap. Form a complete conveying line body; when personnel and equipment enter and exit, the telescopic conveying line retracts forward to the inside of the previous conveying line, and completely retracts to open the channel.
While providing an effective channel, it is possible to minimize interference to the operation of the brick production line, maintain efficient automated production, and the channel does not occupy the surrounding space when it is opened and does not affect the normal movement of materials.
Smart Images

Figure CN118977317A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of brick making equipment, and in particular relates to an invisible channel device of a closed-loop brick making production line. Background Art
[0002] Brick production line refers to an unburned brick production line built on brick machine equipment. The brick machine equipment vibrates and compacts the unburned brick blanks in the pressing mold to form brick blanks, and after curing, the unburned brick products are formed. With the development of technology, brick machine equipment has become increasingly intelligent and automated. By configuring auxiliary lines such as feeding lines and brick discharge lines for brick machine equipment, an automated brick production line has been realized. A closed-loop brick production line refers to a closed-loop brick production line, which is characterized by: after the brick machine equipment presses the brick blanks into shape, the brick discharge line transports the pads carrying the brick blanks, and the pads and brick blanks are sent to the curing line for curing. After the curing is completed, the bricks are separated from the plates, and the brick blanks enter the packaging and delivery process, and the pads are reflowed to the brick machine equipment. It can be seen that compared with the existing in-line brick production line, the closed-loop brick production line realizes the circular utilization of brick pads, so the production line does not need personnel to assist in the turnover of the pads, so the line requires fewer people and has higher production efficiency, which is the development direction of the brick production line.
[0003] Although the closed-loop brick production line has a higher level of automation, it does not completely eliminate the need for human intervention. Usually, the central control room is set in the middle of the ring line, and special operation and maintenance personnel monitor the operation of the production line. Some materials also need to be moved into or out of the ring line by forklifts and other facilities, which requires a reserved channel for the closed-loop brick production line. However, the reserved channel is obviously in conflict with the high-speed operation characteristics of the brick production line. Designing an effective channel that minimizes interference with the operation of the line is a demand in the industry. Summary of the invention
[0004] The purpose of the present invention is to provide an invisible channel device for a closed-loop brick production line, which provides an effective channel while minimizing interference with the operation of the line.
[0005] The technical solution adopted by the present invention is: an invisible channel device of a closed-loop brick-making production line, comprising a preceding conveyor line and a succeeding conveyor line, a channel gap is arranged between the rear end of the preceding conveyor line and the front end of the succeeding conveyor line, a telescopic conveyor line which can be displaced along the length direction is arranged on the preceding conveyor line, and the channel gap is closed when the telescopic conveyor line is displaced backward to a position where its rear end is docked with the front end of the succeeding conveyor line; the preceding conveyor line comprises two preceding support beams supported by preceding brackets and a preceding line conveying assembly, the telescopic conveyor line comprises a telescopic line frame and a telescopic line conveying assembly, track assemblies are arranged between the two sides of the telescopic line frame and the preceding support beams, and a telescopic line translation assembly for driving the telescopic line frame to move along the track assembly is also installed on the preceding conveyor line; the succeeding conveyor line comprises two succeeding support beams supported by succeeding brackets and a succeeding line conveying assembly.
[0006] Preferably, the track assembly includes a guide track installed and fixed on the inner side of the preceding support beam and a track wheel installed on the side of the telescopic wire frame, and the track wheel rolls and moves along the guide track on this side.
[0007] Preferably, a U-shaped bottom connecting frame is installed below the front of the telescopic wire frame, and the bottom connecting frame is fixedly connected to the telescopic wire translation assembly.
[0008] Preferably, the telescopic wire conveying assembly includes a first driving motor installed on a bottom connecting frame, a group of sprockets are installed in the middle and rear of the telescopic wire frame, and the sprocket in the middle is linked by a first linkage shaft, a first conveying chain is installed between the two sprockets on each side of the telescopic wire frame, and the sprocket on the output shaft of the first driving motor is connected to the sprocket arranged in the middle of the first linkage shaft by a first transmission chain.
[0009] Preferably, the telescopic line translation assembly includes two sets of sprockets installed on the front preceding bracket and the rear preceding bracket, and a second conveying chain is installed between the sprockets on each side, and the two front sprockets are linked by a second linkage shaft, and a second drive motor is also installed on the front preceding bracket, and the sprocket on its output shaft is connected to the sprocket in the middle of the second linkage shaft by a second transmission chain.
[0010] Preferably, the preceding line conveying assembly includes a third driving motor and a third linkage shaft installed on the rear preceding bracket, two sets of sprockets are installed at the front and rear ends of the two preceding support beams, and a third conveying chain is provided on the sprocket on each side and the sprocket located at the end of the third linkage shaft, and the sprocket on the third driving motor is connected to the sprocket on the third linkage shaft by a third transmission chain.
[0011] Preferably, the subsequent line conveying assembly includes a fourth drive motor and a fourth linkage shaft installed on the subsequent support, two sets of sprockets are installed at the front and rear ends of the two subsequent support beams, and a fourth conveying chain is provided on the sprocket on each side and the sprocket located at the end of the fourth linkage shaft, and the sprocket on the fourth drive motor and the sprocket on the fourth linkage shaft are connected by a fourth transmission chain.
[0012] Preferably, a positioning cone is installed at the rear end of the telescopic wire frame, and a positioning sleeve is installed at the front end of the subsequent support beam. When the telescopic wire frame moves backward to the terminal position, the positioning cone is inserted into the positioning sleeve to achieve positioning.
[0013] Preferably, a connecting beam is installed between the middle parts of two subsequent supporting beams.
[0014] The advantages and positive effects of the present invention are:
[0015] The present invention provides an invisible channel device of a closed-loop brick-making production line with a reasonable structural design. A telescopic conveyor line that can move forward and backward is installed on a preceding conveyor line. During normal production, the telescopic conveyor line is extended backward until it docks with a succeeding conveyor line, so that a completed conveyor line body can be formed and the channel gap is closed. When personnel and machines need to enter and exit the annular line body, the telescopic conveyor line is retracted forward to the inside of the preceding conveyor line to open the channel gap. Therefore, the channel device of the present invention minimizes interference with the operation of the line body while providing an effective channel, thereby maintaining the efficient operation of the automated production line.
[0016] On the other hand, when the channel device in the present invention forms a channel opening, the telescopic conveyor line is completely retracted into the interior of the preceding conveyor line, so it is an invisible channel, that is, when the channel is opened, it will not occupy any surrounding space and will not affect the normal movement of materials on the preceding conveyor line. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a main structural schematic diagram of the present invention;
[0018] Figure 2 yes Figure 1 Schematic diagram of the three-dimensional structure of the middle and front conveyor lines and the telescopic conveyor lines from the upper perspective;
[0019] Figure 3 yes Figure 1 Schematic diagram of the three-dimensional structure of the middle front conveyor line and the telescopic conveyor line from the lower perspective;
[0020] Figure 4 yes Figure 1 Schematic diagram of the three-dimensional structure from the upper perspective of the middle and later conveyor lines.
[0021] In the figure:
[0022] 1. Precursor bracket; 2. Precursor support beam; 3. Bottom connecting frame; 4. Telescopic line conveying assembly; 4-1. First drive motor; 4-2. First linkage shaft; 4-3. First conveying chain; 4-4. First transmission chain; 5. Telescopic line translation assembly; 5-1. Second conveying chain; 5-2. Second linkage shaft; 5-3. Second drive motor; 5-4. Second transmission chain; 6. Precursor line conveying assembly; 6-1. Third conveying chain; 6-2. Third linkage shaft; 6-3. Third transmission chain; 6-4. Third drive motor; 7. Channel gap; 8. Post-sequence bracket; 9. Post-sequence support beam; 10. Post-sequence line conveying assembly; 10-1. Fourth drive motor; 10-2. Fourth linkage shaft; 10-3. Fourth conveying chain; 10-4. Fourth transmission chain; 11. Guide track; 12. Track wheel; 13. Telescopic line frame; 14. Positioning cone; 15. Connecting beam. DETAILED DESCRIPTION
[0023] In order to further understand the content, features and effects of the present invention, the following embodiments are given to explain in detail.
[0024] See also Figure 1 The invisible channel device of the closed-loop brick-making production line of the present invention comprises a preceding conveyor line and a succeeding conveyor line, a channel gap 7 is provided between the rear end of the preceding conveyor line and the front end of the succeeding conveyor line, a telescopic conveyor line which can be shifted along the length direction is provided on the preceding conveyor line, and the channel gap 7 is closed when the telescopic conveyor line shifts backward to a position where its rear end is docked with the front end of the succeeding conveyor line.
[0025] The operating principle is: when there are no people or machines entering or exiting the annular line body, the telescopic conveyor line moves backward to the end position, at which time the rear end of the telescopic conveyor line docks with the front end of the subsequent conveyor line, and the channel gap 7 is closed to form a complete line body. The materials on the line body (usually referring to the pad carrying the brick blanks or the pad after the brick plate is separated) can flow and move normally along the line body; when there are people or machines entering or exiting the annular line body, the material transportation is suspended, and the telescopic conveyor line moves forward to the initial position until it is completely retracted into the interior of the preceding conveyor line, at which time the channel gap 7 is fully expanded.
[0026] See also Figure 2 and Figure 3 , we can see that:
[0027] The preceding conveyor line includes two preceding support beams 2 supported by a preceding support 1 and a preceding conveyor assembly 6. The telescopic conveyor line includes a telescopic line frame 13 and a telescopic line conveyor assembly 4. A track assembly is provided between the two sides of the telescopic line frame 13 and the preceding support beam 2. A telescopic line translation assembly 5 is also installed on the preceding conveyor line to drive the telescopic line frame 13 to move along the track assembly. The telescopic conveyor line is driven to shift forward and backward by the telescopic line translation assembly 5 to open and close the channel gap 7. The preceding conveyor line conveyor assembly 6 and the telescopic conveyor assembly 4 of the telescopic conveyor line are used to drive the material to shift.
[0028] In this embodiment, the track assembly includes a guide track 11 fixed to the inner side of the preceding support beam 2 and a track wheel 12 installed on the side of the telescopic line frame 13, and the track wheel 12 rolls along the guide track 11 on this side. When the telescopic conveyor line is telescopically displaced, the cooperation between the track wheel 12 and the guide track 11 can significantly improve the stability of the telescopic conveyor line during displacement.
[0029] A U-shaped bottom connecting frame 3 is installed at the lower front part of the telescopic wire frame 13, and the bottom connecting frame 3 is fixedly connected to the telescopic wire translation assembly 5. That is to say, the telescopic wire translation assembly 5 realizes the forward and backward driving displacement of the telescopic wire frame 13 and its accessory components by applying a forward or backward dragging effect to the bottom connecting frame 3.
[0030] In this embodiment, the telescopic wire conveying assembly 4 includes a first driving motor 4-1 installed on the bottom connecting frame 3, a group of sprockets are installed in the middle and rear of the telescopic wire frame 13, and the middle sprocket is linked by a first linkage shaft 4-2, and a first conveying chain 4-3 is installed between the two sprockets on each side of the telescopic wire frame 13. The sprocket on the output shaft of the first driving motor 4-1 is connected to the sprocket arranged in the middle of the first linkage shaft 4-2 by a first transmission chain 4-4.
[0031] The first driving motor 4-1 drives the first linkage shaft 4-2 to rotate forward or reversely through the first transmission chain 4-4, and the first conveying chains 4-3 on both sides move forward or reversely, and the material above falls between the two first conveying chains 4-3 and is supported by the two first conveying chains 4-3. When the two first conveying chains 4-3 move synchronously, the material is moved.
[0032] In this embodiment, the telescopic line translation assembly 5 includes two sets of sprockets installed on the front pre-order bracket 1 and the rear pre-order bracket 1, and a second conveying chain 5-1 is installed between the sprockets on each side, and the two sprockets at the front are linked by a second linkage shaft 5-2, and a second driving motor 5-3 is also installed on the front pre-order bracket 1, and the sprocket on its output shaft is connected to the sprocket in the middle of the second linkage shaft 5-2 by a second transmission chain 5-4. Both sides of the bottom connecting frame 3 are fixedly connected to the two second conveying chains 5-1.
[0033] The second driving motor 5-3 drives the second linkage shaft 5-2 to rotate forward or reversely through the second transmission chain 5-4, and the second conveying chains 5-1 on both sides move forward or reversely, and the bottom connecting frame 3 is dragged forward or backward accordingly to achieve translational displacement.
[0034] In this embodiment, the leading line conveying assembly 6 includes a third driving motor 6-4 and a third linkage shaft 6-2 installed on the rear leading bracket 1, two sets of sprockets are installed at the front and rear ends of the two leading support beams 2, and the sprockets on each side and the sprockets located at the ends of the third linkage shaft 6-2 are provided with a third conveying chain 6-1, and the sprockets on the third driving motor 6-4 and the sprockets on the third linkage shaft 6-2 are connected by a third transmission chain 6-3.
[0035] The third driving motor 6-4 drives the third linkage shaft 6-2 to rotate forward or reversely through the third transmission chain 6-3, and the third conveying chains 6-1 on both sides move forward or reversely, and the material above falls between the two third conveying chains 6-1 and is supported by the two third conveying chains 6-1. When the two third conveying chains 6-1 move synchronously, the material is moved.
[0036] See also Figure 4 , we can see that:
[0037] The subsequent conveying line includes two subsequent supporting beams 9 supported by subsequent brackets 8 and a subsequent line conveying assembly 10. In order to improve the overall structural strength, in this embodiment, a connecting beam 15 is installed between the middle parts of the two subsequent supporting beams 9.
[0038] In this embodiment, the subsequent line conveying assembly 10 includes a fourth drive motor 10-1 and a fourth linkage shaft 10-2 installed on the subsequent bracket 8, two sets of sprockets are installed at the front and rear ends of the two subsequent support beams 9, and the sprockets on each side and the sprockets located at the ends of the fourth linkage shaft 10-2 are provided with a fourth conveying chain 10-3, and the sprockets on the fourth drive motor 10-1 and the sprockets on the fourth linkage shaft 10-2 are connected by a fourth transmission chain 10-4.
[0039] The fourth driving motor 10-1 drives the fourth linkage shaft 10-2 to rotate forward or reversely through the fourth transmission chain 10-4, and the fourth conveying chains 10-3 on both sides move forward or reversely, and the material above falls between the two fourth conveying chains 10-3 and is supported by the two fourth conveying chains 10-3. When the two fourth conveying chains 10-3 move synchronously, the material is moved.
[0040] In this embodiment, a positioning cone 14 is installed at the rear end of the telescopic wire frame 13, and a positioning sleeve is installed at the front end of the subsequent support beam 9. When the telescopic wire frame 13 moves backward to the end position, the positioning cone 14 is inserted into the positioning sleeve to achieve positioning, making the docking more accurate and the docking connection more stable. Due to the combination of the positioning cone 14 and the positioning sleeve, the pressure of the upper material on the telescopic wire frame 13 is transmitted to the subsequent support beam 9, thereby improving the force-bearing and conveying capacity of the sorting.
[0041] How to run:
[0042] The material (usually refers to the pad carrying the brick blank or the pad after the brick plate is separated) moves along the preceding conveyor line to the following line; when there are no personnel or machines entering or exiting the annular line body, the telescopic conveyor line moves backward to the terminal position, at which time the rear end of the telescopic conveyor line docks with the front end of the following conveyor line, and the channel gap 7 is closed to form a complete line body, and the material on the line body can flow and move backward normally along the preceding conveyor line and the telescopic conveyor line; when there are personnel or machines entering or exiting the annular line body, the material transportation is suspended, and the telescopic conveyor line moves forward to the initial position until it is completely retracted into the interior of the preceding conveyor line, at which time the channel gap 7 is fully expanded, the channel is opened, and personnel and machines can enter or exit the annular line body.
Claims
1. An invisible channel device for a closed-loop brick production line, characterized by: The invention comprises a preceding conveying line and a succeeding conveying line, wherein a channel gap (7) is arranged between the rear end of the preceding conveying line and the front end of the succeeding conveying line, and a telescopic conveying line which can be displaced along the length direction is arranged on the preceding conveying line, and the channel gap (7) is closed when the telescopic conveying line is displaced backward to a position where its rear end is butted with the front end of the succeeding conveying line; the preceding conveying line comprises two preceding support beams (2) supported by a preceding bracket (1) and a preceding line conveying assembly (6), the telescopic conveying line comprises a telescopic line frame (13) and a telescopic line conveying assembly (4), track assemblies are arranged between the two sides of the telescopic line frame (13) and the preceding support beam (2), and a telescopic line translation assembly (5) for driving the telescopic line frame (13) to move along the track assembly is also installed on the preceding conveying line; the succeeding conveying line comprises two succeeding support beams (9) supported by a succeeding bracket (8) and a succeeding line conveying assembly (10).
2. The invisible channel device of the closed-loop brick production line according to claim 1 is characterized in that: The track assembly comprises a guide track (11) fixedly mounted on the inner side of a preceding support beam (2) and a track wheel (12) mounted on the side of a telescopic wire frame (13); the track wheel (12) rolls and moves along the guide track (11) on this side.
3. The invisible channel device of the closed-loop brick production line according to claim 2, characterized in that: A U-shaped bottom connection frame (3) is installed at the lower front portion of the telescopic wire frame (13), and the bottom connection frame (3) is fixedly connected to the telescopic wire translation assembly (5).
4. The invisible channel device of the closed-loop brick production line according to claim 3 is characterized in that: The telescopic wire conveying assembly (4) comprises a first driving motor (4-1) mounted on a bottom connecting frame (3); a group of sprockets are mounted in the middle and rear of the telescopic wire frame (13), and the sprockets in the middle are linked by a first linkage shaft (4-2); a first conveying chain (4-3) is mounted between two sprockets on each side of the telescopic wire frame (13); and the sprocket on the output shaft of the first driving motor (4-1) is connected to the sprocket in the middle of the first linkage shaft (4-2) by a first transmission chain (4-4).
5. The invisible channel device of the closed-loop brick production line according to claim 4 is characterized in that: The telescopic line translation assembly (5) comprises two groups of sprockets mounted on a front pre-order bracket (1) and a rear pre-order bracket (1), a second conveying chain (5-2) is mounted between the sprockets on each side, and the two front sprockets are linked by a second linkage shaft (5-2), a second driving motor (5-3) is also mounted on the front pre-order bracket (1), and the sprocket on its output shaft is connected to the sprocket in the middle of the second linkage shaft (5-2) by a second transmission chain (5-4).
6. The invisible channel device of the closed-loop brick production line according to claim 5, characterized in that: The preceding line conveying assembly (6) comprises a third driving motor (6-4) and a third linkage shaft (6-2) mounted on a rear preceding support (1); two sets of sprocket wheels are mounted on the front and rear ends of two preceding support beams (2); a third conveying chain (6-1) is provided on the sprocket wheels on each side and the sprocket wheel at the end of the third linkage shaft (6-2); the sprocket wheel on the third driving motor (6-4) and the sprocket wheel on the third linkage shaft (6-2) are connected in transmission by a third transmission chain (6-3).
7. The invisible channel device of the closed-loop brick production line according to claim 6, characterized in that: The subsequent line conveying assembly (10) comprises a fourth driving motor (10-1) and a fourth linkage shaft (10-2) mounted on a subsequent support (8); two sets of sprockets are mounted at the front and rear ends of two subsequent support beams (9); a fourth conveying chain (10-3) is provided on the sprockets on each side and the sprockets located at the ends of the fourth linkage shaft (10-2); the sprockets on the fourth driving motor (10-4) and the sprockets on the fourth linkage shaft (10-2) are connected in transmission by a fourth transmission chain (10-4).
8. The invisible channel device of the closed-loop brick production line according to any one of claims 1 to 7, characterized in that: A positioning cone (14) is installed at the rear end of the telescopic wire frame (13), and a positioning sleeve is installed at the front end of the subsequent support beam (9). When the telescopic wire frame (13) moves backward to the terminal position, the positioning cone (14) is inserted into the positioning sleeve to achieve positioning.
9. The invisible channel device of the closed-loop brick production line according to any one of claims 1 to 7, characterized in that: A connecting beam (15) is installed between the middle parts of two subsequent supporting beams (9).