Method for automatically dismounting tail-slipping steel wire rope during overturning of hoisting steel pipe pile
By using the electromechanical control system and hydraulic pin shaft of lifting steel pipe pile turnover device in offshore wind power construction, the tailed wire rope is automatically removed, which solves the safety hazards and low efficiency caused by manual operation, and realizes efficient and safe wire rope Demolition process.
Patent Information
- Application Number
- CN202411249639.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-06
- Publication Date
- 2024-11-19
AI Technical Summary
In offshore wind power construction, the removal of the tailed wire rope of steel pipe piles requires manual operation, which poses safety hazards and is inefficient, especially in high altitudes and harsh marine environments, which is difficult to ensure construction safety and efficiency.
The lifting steel pipe pile turnover device is adopted, including the electromechanical control system and hydraulic pin shaft. The tailed wire rope is automatically removed through the remote control of the unpinning mechanism to reduce manual intervention, ensure safety and improve efficiency.
It realizes the automatic removal of tailed wire ropes in high altitudes and harsh environments, improves construction efficiency, ensures the safety of operators, and reduces the workload of hydraulic pipeline management.
Smart Images

Figure CN118978082A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of large-scale offshore wind power hoisting, and in particular relates to a method for automatically removing a tail wire rope when a hoisting steel pipe pile is turned over. Background Art
[0002] The lifting and turning over of steel pipe piles of offshore wind power monopile foundation generally adopts the lifting operation of double main hooks of crane ship, one main hook is connected to the upper lifting ear of pile body, and the other main hook is connected to the tail wire rope at the bottom of pile. However, with the large-scale offshore wind power generation structure, its foundation structure and weight are getting bigger and bigger. At present, the weight of steel pipe piles of monopile foundation reaches about 2200t. Due to the lifting weight limit of crane ship, its double main hook lifting capacity can meet the lifting requirements, but the single hook lifting capacity has gradually failed to meet the lifting requirements of steel pipe piles. To improve the applicability of crane ship, one main hook of crane ship is connected to the top wire rope, and one main hook is connected to the tail wire rope at the bottom of steel pipe pile. However, the tail wire rope needs to be removed after lifting. The wire rope is unhooked at high altitude and needs to be operated manually. The personal safety of operators cannot be guaranteed under the conditions of high altitude and harsh environment at sea, and the manual operation construction efficiency is low. Summary of the invention
[0003] The invention mainly aims to overcome the shortcomings of the prior art and provides a method for automatically removing the tail wire rope when turning over a hoisting steel pipe pile.
[0004] The present invention is achieved through the following technical solutions:
[0005] A method for automatically removing a tail wire rope when turning over a hoisting steel pipe pile, the method using a hoisting steel pipe pile turning over device, the hoisting steel pipe pile turning over device comprising a steel pipe pile, a first main hook, a second main hook, a first lifting belt, a second lifting belt, a remote control pin removal mechanism, a tail wire rope and a tail clamp;
[0006] The steel pipe pile is located on a transport ship, a first main hook of a crane ship is connected to the upper end of a first lifting belt, a lower end of the first lifting belt is hung on a lifting lug of the steel pipe pile, a second main hook of the crane ship is connected to the upper end of a second lifting belt, the tail wire rope is connected to the lower end of the second lifting belt through a remote control release mechanism, a tail clamp is installed at the other end of the tail wire rope, and the tail clamp is connected to the tail end of the steel pipe pile;
[0007] The remote control pin-release mechanism comprises an electromechanical control system, a shackle and a hydraulic pin shaft, the hydraulic pin shaft is installed at the moving end of the electromechanical control system, and the shackle and the hydraulic pin shaft are fixedly connected;
[0008] The method for automatically removing the tail wire rope when the hoisting steel pipe pile turns over comprises the following steps:
[0009] Step 1, operating the electromechanical control system so that the electromechanical control system controls the hydraulic pin shaft to retract and disengage the shackle;
[0010] Step 2, firstly insert the lower end of the second sling into the upper end of the shackle, then align the upper end of the tail wire rope with the position of the motion track of the hydraulic pin shaft in the shackle, and then operate the electromechanical control system to control the hydraulic pin shaft to extend, so that the shackle reaches a closed state, and then the upper end of the tail wire rope is hung on the hydraulic pin shaft, and then the tail clamp connected to the other end of the tail wire rope is connected to the tail end of the steel pipe pile;
[0011] Step 3, connecting the second main hook to the upper end of the second sling, connecting the first main hook to the first sling, and then hanging the first sling on the lifting ears on both sides of the steel pipe pile;
[0012] Step 4, adjusting the positions of the first main hook and the second main hook so that the first main hook and the second main hook are aligned with the axis position of the steel pipe pile;
[0013] Step 5, the first main hook and the second main hook of the crane ship are lifted simultaneously until the tail wire rope is stressed to a straight state, and the front and rear ends of the steel pipe pile are separated from the transport ship at the same time, and then the first main hook is lifted, and the second main hook remains stationary, so that the front end of the steel pipe pile is higher than the rear end, and then the crane ship moves to one side, so that the first main hook and the second main hook of the crane ship hoist the steel pipe pile away from the transport ship, and move the steel pipe pile above the mud surface;
[0014] Step 6, lowering the first main hook and the second main hook simultaneously until the bottom of the rear end of the steel pipe pile contacts the mud surface, so that the tail wire rope is no longer stressed, and the tail clamp is detached from the tail end of the steel pipe pile under the action of gravity;
[0015] Step 7, operating the electromechanical control system to control the hydraulic pin shaft to retract and disengage from the shackle, at which time the tail wire rope is disengaged from the hydraulic pin shaft;
[0016] Step 8, lifting the first main hook, while the crane vessel moves toward the rear end of the steel pipe pile, at which time the steel pipe pile rotates clockwise with the tail end of the steel pipe pile as the origin until the steel pipe pile is vertically turned over.
[0017] In the above technical solution, the first main hook is connected to the upper ends of the two first slings, and the lower ends of the two first slings are hung on the lifting ears on the left and right sides of the steel pipe pile.
[0018] In the above technical solution, the shackle and the hydraulic pin are fixedly connected by bolts.
[0019] In the above technical solution, the tail wire rope is connected to a recovery sling, and the recovery sling is connected to the auxiliary hook of the crane vessel.
[0020] In the above technical solution, in step 2, after the tail clamp connected to the other end of the tail wire rope is connected to the tail end of the steel pipe pile, the recovery sling connected to the tail wire rope is connected to the auxiliary hook of the crane ship.
[0021] In the above technical solution, in step 5, after the front and rear ends of the steel pipe pile are simultaneously separated from the transport ship, the lifting is suspended to stabilize the steel pipe pile to reach a stable state.
[0022] In the above technical solution, in step 7, after the tail wire rope is detached from the hydraulic pin shaft, the auxiliary hook of the crane vessel is lifted, so that the recovery sling connected to the auxiliary hook lifts the tail wire rope to recover the tail wire rope.
[0023] The advantages and beneficial effects of the present invention are:
[0024] (1) In the present invention, an electromechanical control system is provided to control the extension and retraction of the hydraulic pin shaft, thereby achieving the separation of the tail wire rope from the shackle, and thus eliminating the need for manual operation to remove the tail wire rope, thereby ensuring the personal safety of operators under harsh conditions at high altitudes and at sea, and improving work efficiency.
[0025] (2) The present invention replaces the hydraulic pipeline system with an electromechanical control system, which saves the construction personnel from the work of managing the hydraulic pipeline during the lifting and control process, thus reducing the workload. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a structural schematic diagram of the present invention.
[0027] Figure 2 It is a front view of the remote control stock removal mechanism in the present invention.
[0028] Figure 3 It is a schematic diagram of the connection relationship between the remote control pin release mechanism, the second sling and the tail wire rope in the present invention.
[0029] In the figure, steel pipe pile 1, lifting lug 1.1, first main hook 2, second main hook 3, first lifting belt 4, second lifting belt 5, remote control unpinning mechanism 6, electromechanical control system 6.1, shackle 6.2, hydraulic pin shaft 6.3, tail wire rope 7, recovery lifting belt 8, tail clamp m.
[0030] For ordinary technicians in this field, other relevant drawings can be obtained based on the above drawings without any creative work. DETAILED DESCRIPTION
[0031] In order to enable those skilled in the art to better understand the technical solution of the present invention, the technical solution of the present invention is further described below in conjunction with specific embodiments.
[0032] Embodiment 1
[0033] A method for automatically removing the tail wire rope when turning over a hoisting steel pipe pile, the method using a hoisting steel pipe pile turning over device, the hoisting steel pipe pile turning over device, see attached Figure 1-3 , including a steel pipe pile 1, a first main hook 2, a second main hook 3, a first sling 4, a second sling 5, a remote control unpinning mechanism 6, a tail wire rope 7, a recovery sling 8 and a tail clamp m.
[0034] The steel pipe pile 1 is located on a transport ship (not shown in the figure), the first main hook 2 of the crane ship (not shown in the figure) is connected to the upper ends of two first slings 4, the lower ends of the two first slings 4 are hung on the lifting ears 1.1 on the left and right sides of the steel pipe pile 1, the second main hook 3 of the crane ship (not shown in the figure) is connected to the upper end of the second sling 5, the tail wire rope 7 is connected to the lower end of the second sling 5 through a remote control unpinning mechanism 6, the other end of the tail wire rope 7 is installed with a tail clamp m, and the tail clamp m is connected to the tail end of the steel pipe pile 1.
[0035] The remote control release mechanism 6 comprises an electromechanical control system 6.1, a shackle 6.2 and a hydraulic pin 6.3. The hydraulic pin 6.3 is installed at the moving end of the electromechanical control system 6.1. The hydraulic pin 6.3 is used to hang the tail wire rope 7. The shackle 6.2 and the hydraulic pin 6.3 are fixedly connected by bolts. The upper part of the shackle 6.2 is used to hang the second sling 5. The hydraulic pin 6.3 can be remotely controlled and extended in the shackle 6.2 under the control of the electromechanical control system 6.1. Therefore, when the hydraulic pin 6.3 retracts, the tail wire rope 7 can be separated from the hydraulic pin 6.3. The tail wire rope 7 is connected with a recovery sling 8. When the tail wire rope 7 is separated from the hydraulic pin 6.3, the upper part of the recovery sling 8 is connected with an auxiliary hook (not shown in the figure) of a crane ship (not shown in the figure). The auxiliary hook rises and pulls the recovery sling 8, and the recovery sling 8 pulls the tail wire rope 7 to recover the tail wire rope 7.
[0036] Embodiment 2
[0037] A method for automatically removing a tail wire rope when a steel pipe pile is turned over, comprising the following steps:
[0038] Step 1, operating the electromechanical control system 6.1, so that the electromechanical control system 6.1 controls the hydraulic pin shaft 6.3 to retract and disengage from the shackle 6.2;
[0039] Step 2, firstly insert the lower end of the second sling 5 into the upper end of the shackle 6.2, then align the upper end of the tail wire rope 7 with the position of the motion track of the hydraulic pin shaft 6.3 in the shackle 6.2, and then operate the electromechanical control system 6.1 to make the electromechanical control system 6.1 control the hydraulic pin shaft 6.3 to extend, so that the shackle 6.2 reaches a closed state, and then the upper end of the tail wire rope 7 is hung on the hydraulic pin shaft 6.3, and then the tail clamp m connected to the other end of the tail wire rope 7 is connected to the tail end of the steel pipe pile, and finally the recovery sling 8 connected to the tail wire rope 7 is connected to the auxiliary hook of the crane ship (not shown in the figure);
[0040] Step 3, connecting the second main hook 3 to the upper end of the second sling 5, connecting the first main hook 2 to the two first slings 4, and then hanging the two first slings 4 on the lifting ears 1.1 on the left and right sides of the steel pipe pile 1;
[0041] Step 4, adjusting the positions of the first main hook 2 and the second main hook 3 so that the first main hook 2 and the second main hook 3 are aligned with the axis position of the steel pipe pile 1;
[0042] Step 5, lift the first main hook 2 and the second main hook 3 of the crane ship at the same time until the tail wire rope 7 is stressed to reach a straight state, and the front and rear ends of the steel pipe pile 1 are separated from the transport ship at the same time, then stop lifting, stabilize the steel pipe pile 1, and make it reach a stable state, then lift the first main hook 2, and keep the second main hook 3 still, so that the front end of the steel pipe pile 1 is higher than the rear end, and then move the crane ship to one side, so that the first main hook 2 and the second main hook 3 of the crane ship hoist the steel pipe pile 1 away from the transport ship, and move the steel pipe pile 1 above the mud surface (at this time, the front end of the steel pipe pile 1 above the mud surface is still higher than the rear end);
[0043] Step 6, lowering the first main hook 2 and the second main hook 3 simultaneously until the rear end bottom of the steel pipe pile contacts the mud surface, so that the tail wire rope 7 is no longer stressed, and the tail clamp m is detached from the tail end of the steel pipe pile 1 under the action of gravity;
[0044] Step 7, operating the electromechanical control system 6.1, so that the electromechanical control system 6.1 controls the hydraulic pin shaft 6.3 to retract and disengage from the shackle 6.2, at which time the tail wire rope 7 is disengaged from the hydraulic pin shaft 6.3, and then the auxiliary hook of the crane vessel is lifted, so that the recovery sling 8 connected to the auxiliary hook lifts the tail wire rope 7, and the tail wire rope 7 is recovered;
[0045] Step 8, lifting the first main hook 2, while the crane vessel moves toward the rear end of the steel pipe pile 1, at which time the steel pipe pile 1 rotates clockwise with the tail end of the steel pipe pile 1 as the origin until the steel pipe pile is vertically turned over.
[0046] For ease of explanation, spatial relative terms such as "upper", "lower", "left", "right" and the like are used in the embodiments to illustrate the relationship of one element or feature shown in the figure relative to another element or feature. It should be understood that, in addition to the orientation shown in the figure, the spatial terms are intended to include different orientations of the device in use or operation. For example, if the device in the figure is inverted, the element described as being "under" other elements or features will be positioned "on" other elements or features. Therefore, the exemplary term "under" can include both upper and lower orientations. The device can be positioned in other ways (rotated 90 degrees or in other orientations), and the spatial relative descriptions used here can be interpreted accordingly.
[0047] Furthermore, relational terms such as “first” and “second” and the like are merely used to distinguish one component from another having the same name, but do not necessarily require or imply any such actual relationship or order between these components.
[0048] The present invention is described above by way of example. It should be noted that, without departing from the core of the present invention, any simple deformation, modification or other equivalent replacement that can be made by those skilled in the art without inventive effort falls within the protection scope of the present invention.
Claims
1. A method for automatically removing the tail wire rope when turning over a hoisting steel pipe pile, the method using a hoisting steel pipe pile turning device, the hoisting steel pipe pile turning device is characterized in that: Includes battery racks, air ducts, plenum boxes and air conditioners; It includes a steel pipe pile, a first main hook, a second main hook, a first lifting belt, a second lifting belt, a remote control release mechanism, a tail wire rope and a tail clamp; The steel pipe pile is located on a transport ship, a first main hook of a crane ship is connected to the upper end of a first lifting belt, a lower end of the first lifting belt is hung on a lifting lug of the steel pipe pile, a second main hook of the crane ship is connected to the upper end of a second lifting belt, the tail wire rope is connected to the lower end of the second lifting belt through a remote control release mechanism, a tail clamp is installed at the other end of the tail wire rope, and the tail clamp is connected to the tail end of the steel pipe pile; The remote control pin-release mechanism comprises an electromechanical control system, a shackle and a hydraulic pin shaft, the hydraulic pin shaft is installed at the moving end of the electromechanical control system, and the shackle and the hydraulic pin shaft are fixedly connected; The method for automatically removing the tail wire rope when the hoisting steel pipe pile turns over comprises the following steps: Step 1, operating the electromechanical control system so that the electromechanical control system controls the hydraulic pin shaft to retract and disengage the shackle; Step 2, firstly insert the lower end of the second sling into the upper end of the shackle, then align the upper end of the tail wire rope with the position of the motion track of the hydraulic pin shaft in the shackle, and then operate the electromechanical control system to control the hydraulic pin shaft to extend, so that the shackle reaches a closed state, and then the upper end of the tail wire rope is hung on the hydraulic pin shaft, and then the tail clamp connected to the other end of the tail wire rope is connected to the tail end of the steel pipe pile; Step 3, connecting the second main hook to the upper end of the second sling, connecting the first main hook to the first sling, and then hanging the first sling on the lifting ears on both sides of the steel pipe pile; Step 4, adjusting the positions of the first main hook and the second main hook so that the first main hook and the second main hook are aligned with the axis position of the steel pipe pile; Step 5, the first main hook and the second main hook of the crane ship are lifted simultaneously until the tail wire rope is stressed to a straight state, and the front and rear ends of the steel pipe pile are separated from the transport ship at the same time, and then the first main hook is lifted, and the second main hook remains stationary, so that the front end of the steel pipe pile is higher than the rear end, and then the crane ship moves to one side, so that the first main hook and the second main hook of the crane ship hoist the steel pipe pile away from the transport ship, and move the steel pipe pile above the mud surface; Step 6, lowering the first main hook and the second main hook simultaneously until the bottom of the rear end of the steel pipe pile contacts the mud surface, so that the tail wire rope is no longer stressed, and the tail clamp is detached from the tail end of the steel pipe pile under the action of gravity; Step 7, operating the electromechanical control system to control the hydraulic pin shaft to retract and disengage from the shackle, at which time the tail wire rope is disengaged from the hydraulic pin shaft; Step 8, lifting the first main hook, while the crane vessel moves toward the rear end of the steel pipe pile, at which time the steel pipe pile rotates clockwise with the tail end of the steel pipe pile as the origin until the steel pipe pile is vertically turned over.
2. The method for automatically removing the tail wire rope when turning over a steel pipe pile according to claim 1 is characterized in that The first main hook is connected to the upper ends of the two first slings, and the lower ends of the two first slings are hung on the lifting ears on the left and right sides of the steel pipe pile.
3. The method for automatically removing the tail wire rope when turning over a hoisting steel pipe pile according to claim 1 is characterized in that: The shackle and the hydraulic pin are fixedly connected by bolts.
4. The method for automatically removing the tail wire rope when turning over a steel pipe pile according to claim 1, characterized in that: The tail wire rope is connected to a recovery sling, and the upper part of the recovery sling is connected to an auxiliary hook of a crane ship.
5. The method for automatically removing the tail wire rope when turning over a steel pipe pile according to claim 4, characterized in that: In step 2, after the tail clamp connected to the other end of the tail wire rope is connected to the tail end of the steel pipe pile, the recovery sling connected to the tail wire rope is connected to the auxiliary hook of the crane ship.
6. The method for automatically removing the tail wire rope when turning over a hoisting steel pipe pile according to claim 1, characterized in that: In step 5, after the front and rear ends of the steel pipe pile are simultaneously separated from the transport ship, the lifting is suspended to stabilize the steel pipe pile to a stable state.
7. The method for automatically removing the tail wire rope when turning over a steel pipe pile according to claim 5, characterized in that: In step 7, after the tail wire rope is separated from the hydraulic pin shaft, the auxiliary hook of the crane vessel is lifted, so that the recovery sling connected to the auxiliary hook lifts the tail wire rope to recover the tail wire rope.