Low mountain and hill landform limit curvature municipal steel box girder walking pushing device and construction method
The step-by-step jacking device for municipal steel box girders with extreme curvature in low hilly terrain, which uses segmental assembly and differential cumulative sliding, utilizes hydraulic cylinders to drive the installation of steel box girders with small curvature radii. This solves the construction problem of steel box girders in low hilly terrain and achieves efficient and economical construction results.
Patent Information
- Application Number
- CN202411362911.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-27
- Publication Date
- 2024-11-19
AI Technical Summary
In hilly terrain, the construction of curved steel box girders is difficult, especially the jacking construction of steel box girders with small curvature radii, which cannot meet the construction requirements and makes it impossible to close roads for construction.
A step-by-step jacking device for municipal steel box girders with extreme curvature in low hilly terrain is adopted, which involves segmental assembly and differential cumulative sliding. It includes a horizontal pushing mechanism and a jacking mechanism. The device uses hydraulic cylinders to drive horizontal sliding, correction and lifting to realize the installation of steel box girders with small curvature radius.
This technology enables the installation of steel box girders with small curvature radii, allowing construction to be carried out on sites where roads cannot be closed, thus shortening the construction period, reducing costs, and improving construction efficiency.
Smart Images

Figure CN118979446A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of steel box girder walking jacking construction, and in particular to a walking jacking device and a construction method for a municipal steel box girder with an extreme curvature in low mountain and hilly landforms. Background Art
[0003] As cities develop, traffic becomes congested, buildings become dense, and streets become difficult to widen. Viaducts are often used to solve these problems. Such bridges can disperse traffic density and improve transportation efficiency. In addition, in inter-city highways or railways, in order to avoid intersections with other lines, save land, To reduce the subsidence of the roadbed, this type of viaduct can be used without the embankment. Due to the limitations of existing buildings and line requirements, viaducts are mostly curved bridges and slope bridges. The upper structure of the viaduct line bridge generally adopts simply supported beams or continuous beams. When using simply supported beams, in order to ensure smooth driving on the bridge deck, it is often made into a simple supported beam with continuous bridge deck. If the continuous beam and the pier top are rigidly connected, it becomes a continuous rigid frame bridge. When the span of the bridge is not large, a plate structure can be used for the sake of beauty. The thickness of the plate can be constant, or it can only change along the transverse direction of the bridge. There are also mushroom-shaped structures. When the span is large, it is often made into a rib or box section (see solid web beam bridge). The bridge deck extends out from both sides of the box section to expand the bridge deck, and narrow piers are used below to form a "spine-type" structure. Especially in curved bridges, it is more beautiful, practical, and economical, and is very popular.
[0004] The Z8 ramp bridge (Z8P8-Z8P11) of the supporting road of Shenzhen Yantian Port Trailer Comprehensive Service Center is a double-box steel box girder structure with a longitudinal slope of 3.6-5% and a transverse slope of 2.0%. There is a superelevation change at Z8P10-Z8P11. Since the bridge piers Z8P8-Z8P10 cross the Yanpai Expressway, Yanpai Expressway ramp, Wutongshan Viaduct, and auxiliary road, it is impossible to set up a support on the ground for high-altitude bulk loading. At the same time, the traffic volume of Yanpai Expressway is very large, especially there are many heavy semi-trailers, and the road cannot be closed during construction. The steel box girder is an arc structure with a central curvature of about 70m. It is one of the few steel box girders with a small curvature radius known in China and even internationally. There are great difficulties and challenges in construction. The original plan of using steel box girder hoisting cannot meet the construction requirements of the above situation.
[0005] Therefore, it is a problem worthy of study to provide a walking jacking device and construction method for municipal steel box girders with extreme curvature in low mountain and hilly terrain with "segment-by-segment assembly and differential cumulative sliding". Summary of the invention
[0006] The purpose of the present invention is to provide a walking jacking device and a construction method for a municipal steel box girder with extreme curvature in hilly landforms with the features of "assembling in sections and accumulating differential sliding".
[0007] The object of the present invention is achieved in that: A walking jacking device for municipal steel box girders with extreme curvature in low mountain and hilly terrain includes a horizontal pushing mechanism for pushing the steel box girder in the horizontal direction, a jacking mechanism located on one side of the horizontal pushing mechanism and used to push the steel box girder upward to disengage the steel box girder from the horizontal pushing mechanism and thereby retract the horizontal pushing mechanism, the horizontal pushing mechanism includes a sliding base, a horizontal sliding assembly located on the sliding base and pushing the steel box girder to move, a load supporting assembly located on the top of the horizontal sliding assembly and used to support the steel box girder, the jacking mechanism includes a jacking base, a deviation correction assembly located on the jacking base, a lifting assembly located on the deviation correction assembly, and a deviation correction top beam located on the top of the lifting assembly.
[0008] The horizontal sliding assembly includes a sliding shoe located on the sliding base and moving along the length direction of the sliding base, a first pushing cylinder with one end fixed to the sliding shoe and the other end located outside the sliding shoe, and a support frame with a bottom fixedly connected to the sliding base and located below the first pushing cylinder for supporting the first pushing cylinder.
[0009] The support frame includes a first vertical plate and a second vertical plate whose bottom is fixedly connected to the sliding base and symmetrically arranged, a third vertical plate located between the first vertical plate and the second vertical plate and whose two ends are respectively fixedly connected to the first vertical plate and the second vertical plate, and a placement groove located above the third vertical plate.
[0010] The sliding shoe includes a sliding plate located above the sliding base and moving along the length direction of the sliding base, a vertical frame fixedly connected to the sliding plate at the bottom and symmetrically arranged, and a flat plate fixedly connected to the top of the vertical frame; a first mounting plate for fixing the first push cylinder is provided between the vertical frames.
[0011] The load supporting assembly includes a sliding top beam.
[0012] The lifting assembly comprises a second pushing cylinder whose bottom is fixedly connected to the deviation correcting assembly.
[0013] The correcting assembly includes a second connecting plate fixedly connected to the front and rear sides of the jacking base, a second mounting plate fixedly connected to the second connecting plate, a third pushing cylinder fixed to the second mounting plate, a first connecting plate fixedly connected to the telescopic end of the third pushing cylinder, a correcting plate fixedly connected to the first connecting plate and located on the jacking base, and the second pushing cylinder is fixedly connected to the upper surface of the correcting plate.
[0014] A method for constructing a municipal steel box girder with an extreme curvature in low mountain and hilly terrain by walking, comprising the following steps: Step 1: Set up assembly brackets and platforms at piers Z8P6~Z8P8, install walking jacking devices on the jacking support system, and assemble steel box girder segments 1, 2 and the front guide beam structure in sections on the assembly platform; Step 2: Debug the walking jacking device. After confirming that the steel box girder structure and the temporary support system meet the quality requirements, use the walking jacking device to slide the main beam forward along the axial arc for a set distance; Step 3: Adjust the line shape of the front bridge body and the left and right offset of the steel box girder, assemble segment 3 on the tire frame, and connect it with the front steel box girder to form a whole, waiting for the next overall jacking; Step 4: Repeat the above steps 1 to 3 until the steel box girder is installed.
[0015] The beneficial effects of the present invention are as follows: the jacking device of the present invention is a combined structure, the horizontal push mechanism is a horizontal sliding assembly and a load support assembly, which supports the self-weight load of the sliding component and provides driving force for the horizontal friction force generated during sliding. One end of the horizontal sliding assembly is connected to the reaction device in the form of a hinge point, and the other end is connected to the load support assembly; the jacking mechanism is a lifting assembly and a horizontal deviation correction assembly, which is a device for replacing the self-weight load of the structure and the horizontal deviation correction of the component during sliding. The horizontal sliding, deviation correction and lifting are all driven by hydraulic cylinders; the present invention is assembled in sections, differential accumulated sliding, and realizes the installation of steel box girders with small curvature radius, and can be used in construction sites where road closures cannot be carried out, keeping the original road running, and creating good economic benefits for the society. After the development of this technology, it has been verified and applied in this project. Under the guidance of this technology, the reasonable use of measures and materials can greatly reduce the installation of tire frames, shorten the construction period and optimize the machinery selection, and reduce construction costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a structural schematic diagram of the present invention; Figure 2 It is a structural schematic diagram of the horizontal push mechanism of the present invention; Figure 3 It is a structural schematic diagram of the sliding base of the present invention; Figure 4 It is a schematic diagram of the structure of the sliding shoe of the present invention; Figure 5 It is a structural schematic diagram of the jacking mechanism of the present invention; Figure 6 It is a structural schematic diagram of the jacking base of the present invention; Figure 7 This is a schematic diagram of the structure of the deviation-correcting sliding shoe of the present invention; Figure 8 It is a schematic diagram of the structure of the present invention when the construction is completed; Fig. 9 for Figure 8 A top view of Fig.10 It is a schematic diagram of the structure of the present invention during the construction of the segments 1 and 2; Fig.11 for Fig.10A top view of Fig.12 It is a schematic diagram of the structure of the present invention during the construction of the segments 1 and 2; Fig.13 for Fig.12 A top view of Fig.14 It is a schematic diagram of the structure of the present invention during the construction of the segments 1, 2 and 3; Fig.15 for Fig.14 A top view of Fig.16 It is a schematic diagram of the structure of the present invention during the construction of the segments 1, 2 and 3; Fig.17 for Fig.16 Top view The figure shows: a horizontal pushing mechanism 1, a lifting mechanism 2, a sliding base 11, a sliding shoe 12, a sliding plate 121, a vertical frame 122, a flat plate 123, a first mounting plate 124, a first pushing cylinder 13, a sliding top beam 14, a first supporting frame 15, a first vertical plate 151, a second vertical plate 152, a third vertical plate 153, a placement groove 154, a lifting base 21, a second pushing cylinder 22, a correction assembly 23, a third pushing cylinder 231, a first connecting plate 232, a second mounting plate 233, a second connecting plate 234, a correction plate 235, and a correction top beam 24. DETAILED DESCRIPTION
[0017] The present invention is further described below in conjunction with the accompanying drawings and embodiments. Example 1
[0018] like Figure 1As shown, a walking jacking device for municipal steel box girders with extreme curvature in low mountain and hilly terrain includes a horizontal pushing mechanism 1 for pushing the steel box girder in the horizontal direction, and a jacking mechanism 2 located at the right end of the horizontal pushing mechanism 1 and used to push the steel box girder upward to disengage the steel box girder from the horizontal pushing mechanism 1, thereby retracting the horizontal pushing mechanism 1. The horizontal pushing mechanism 1 includes a sliding base 11, a horizontal sliding assembly located on the sliding base 11 and pushing the steel box girder to move, and a load supporting assembly located on the top of the horizontal sliding assembly and used to support the steel box girder. The jacking mechanism 2 includes a jacking base 21, a deviation correction assembly 23 located on the jacking base, a lifting assembly located on the deviation correction assembly 23, and a deviation correction top beam 24 located on the top of the lifting assembly. The deviation correction assembly 23 is used to correct the position of the lifting assembly in the front and rear directions. The lifting assembly is used to lift the steel box girder to disengage the steel box girder from the load supporting assembly so as to reset the horizontal sliding assembly to facilitate pushing the steel box girder again. The jacking base 21 and the sliding base 11 are fixed to the temporary support frame through connecting parts to support the horizontal push mechanism and the jacking mechanism; the horizontal push mechanism 1 is a horizontal sliding component and a load support component, which supports the self-weight load of the sliding component and provides driving force for the horizontal friction force generated during sliding. One end of the horizontal sliding component is connected to the reaction device in the form of a hinge point, and the other end is connected to the load support component; the jacking mechanism is a lifting component and a correction component, which is a device for replacing the self-weight load of the structure and horizontal correction of the component during sliding. The horizontal sliding, correction and lifting actions are all driven by hydraulic cylinders; the present invention is assembled section by section, differential accumulated sliding, to achieve the installation of steel box girders with a small curvature radius, and can be used in construction sites where roads cannot be closed.
[0019] like Figures 2 to 4 As shown, the horizontal sliding assembly includes a sliding shoe 12 located on the sliding base 11 and moving along the length direction of the sliding base 11, a first push cylinder 13 fixed to the sliding shoe 12 at one end and located outside the sliding shoe 12 at the other end, and a support frame 15 fixedly connected to the sliding base 11 at the bottom and located below the first push cylinder 13 for supporting the first push cylinder 13. The support frame 15 is used to support the first push cylinder 13, and the support frame 15 is located at the left end of the sliding base 11. The support frame 15 includes a first vertical plate 151 and a second vertical plate 152 fixedly connected to the sliding base 11 at the bottom and symmetrically arranged, a third vertical plate 153 located between the first vertical plate 151 and the second vertical plate 152 and fixedly connected to the first vertical plate 151 and the second vertical plate 152 at both ends, and a placement groove 154 located above the third vertical plate 153. One end of the first push cylinder 13 is connected to the sliding shoe 12 through a bolt assembly, and the other end of the first push cylinder 13 is connected to the reaction device. The first push cylinder 13 pushes the sliding shoe 12, the load supporting assembly and the steel box girder to move horizontally along the length direction of the sliding base 11 to promote the movement of the steel box girder.
[0020] The sliding shoe 12 includes a sliding plate 121 located above the sliding base 11 and moving along the length direction of the sliding base 11, a vertical frame 122 symmetrically arranged and fixedly connected to the sliding plate 121 by welding, and a flat plate 123 fixedly connected to the top of the vertical frame 122 by a bolt assembly; a first mounting plate 124 for fixing the first push cylinder 13 is arranged between the vertical frames 122. The load support assembly includes a sliding top beam 14, and a cushion pier and a cushion plate can be arranged on the top of the sliding top beam 14 to meet the use requirements.
[0021] like Figures 5 to 7 As shown, the lifting assembly includes a second jacking cylinder 22 whose bottom is fixedly connected to the deviation correction assembly 23. The deviation correction assembly 23 includes a second connecting plate 232 fixedly connected to the front and rear sides of the jacking base 21, a second mounting plate 233 fixedly connected to the second connecting plate 232, a third jacking cylinder 231 fixed to the second mounting plate 233, a first connecting plate 232 fixedly connected to the telescopic end of the third jacking cylinder 231, a deviation correction plate 235 fixedly connected to the first connecting plate 232 and located on the jacking base 21, the second jacking cylinder 22 is fixedly connected to the upper surface of the deviation correction plate 235, two third jacking cylinders 231 are provided, and the two third jacking cylinders 231 are symmetrically arranged on the front and rear sides of the second jacking cylinder 22, and are used to adjust the position of the second jacking cylinder 22 in the front and rear direction, thereby adjusting the position of the steel box girder.
[0022] The walking jacking and sliding construction technology adopts computer control. Through data feedback and control command transmission, it can fully automatically realize various functions such as certain synchronous jacking action, load balancing, posture correction, operation locking, process display and fault alarm. After calculation and analysis, the maximum jacking point reaction value in the present invention is 2300kN, and the friction coefficient of the sliding base 11 and the sliding plate 121MGA material is 0.2 (the actual friction coefficient of steel to MGA plate without lubrication is about 0.1). The jacking cylinder jacking force is 600kN>2300×0.2=460kN, which can meet the jacking requirements of this project. The crawler machine has a lifting capacity of 3500KN. Two lifting cylinders are installed on each pier support, with a total of 14 lifting cylinders (not used at the same time). The total lifting capacity is 3500×14=49000kN>7000kN (total sliding weight). The lifting capacity of a single jacking point is 3500kN>2300KN, which can meet the construction requirements.
[0023] The hydraulic pump source system provides hydraulic power and completes corresponding actions under the control of various pressure valves and solenoid valves. The present invention uses TJV-60 variable frequency hydraulic pump station with a power of 60KW and a working output pressure of 25MPa. Each pump source can output up to 8 groups of pressure, which can fully meet the use requirements of this project.
[0024] In different projects, the arrangement of the push points and the arrangement of the walking push devices are different. In order to improve the versatility and reliability of the hydraulic sliding equipment, the design of the pump source hydraulic system adopts a modular structure. The number of pump sources is configured according to the arrangement of the push points and the number of walking push devices, and multiple modules can be combined. Each module is based on a pump source system, which can independently control a group of walking push devices, and can be expanded to multiple push points to meet the needs of actual push sliding projects.
[0025] The synchronous control system consists of a power control system, a power drive system, a computer control system, etc. It mainly completes the following two control functions: coordinated control of the movements of cluster crawlers during operation. During the sliding operation, each crawler must coordinate its movements under the control of a computer to create conditions for synchronous sliding.
[0026] The synchronous control between various points is to control the synchronous operation of the crawler through a computer network, so as to keep the synchronous operation of various points of the pushed component to maintain its sliding posture.
[0027] Operators can observe the hydraulic sliding process and related data and (or) issue control instructions through the hydraulic synchronous computer control system human-machine interface in the central control room.
[0028] The specific use process is as follows: first, the steel box girder is placed on the sliding top beam 14, the two ends of the first jacking oil cylinder 13 are respectively connected to the reaction device and the sliding shoe 12, the sliding shoe 12 is placed on the sliding base 11, and the first jacking oil cylinder 13 is started, and then the first jacking oil cylinder 13 pushes the sliding shoe 12, the sliding top beam 14 and the steel box girder to move on the sliding base 11. After the first jacking oil cylinder 13 is extended to a set length, the telescopic end of the second jacking oil cylinder 22 moves upward to lift the steel box girder, and at the same time, the steel box The beam is separated from the sliding top beam 14. At this time, the telescopic end of the first jacking cylinder 13 is retracted to restore the first jacking cylinder 13 to its original position, and the telescopic end of the second jacking cylinder 22 is retracted to make the steel box beam located at the top of the sliding top beam 14. Repeat the above operation to push the steel box beam forward, that is, the four steps of "pushing", "pushing", "shrinking" and "lowering" are alternately performed to complete a jacking stroke; continue to the next cycle operation, and finally push the steel box beam to the predetermined position through the reciprocating jacking steps. The jacking device is installed at the lower position of the component and supported by setting a temporary jacking structure. Example 2
[0029] A method for constructing a municipal steel box girder with an extreme curvature in low mountain and hilly terrain by walking, comprising the following steps: Step 1: If Figures 10 to 13As shown in the figure, assembly support and platform are set at piers Z8P6~Z8P8. The length of the platform needs to ensure the installation of the steel box beam and the front guide beam of the two segments, which is about 56m long. The walking jacking equipment (a total of 14 sets) is installed on the jacking support system. The inner arc side of the walking equipment is arranged along the arc of R=67m, and the outer arc side is arranged along the arc of R=73m. The single walking equipment, especially the sliding support part, is arranged along the tangent direction of the arc. The steel box beam segment 1, segment 2 and the front guide beam structure are assembled in sections on the assembly platform and welded into a whole. At the same time, patches are placed on the front end of the guide beam and the front and rear ends of the steel box beam, and the starting coordinates of the steel box beam, especially the horizontal coordinates, are recorded using a total station to observe the horizontal displacement data of the structure during the jacking process. At the same time, observation points are set above each walking support system to observe the displacement changes of the column top of the support structure during the jacking process. At this time, the front guide beam is at the edge of the Yanpai Expressway.
[0030] Step 2: Clean up the garbage on the top of the leading beam before it is sent to a high place. After debugging the walking jacking equipment and confirming that the steel box beam structure and the temporary support system meet the quality requirements, the walking equipment lifts the steel box beam structure to separate it from the assembly platform. The structural load is completely transferred to the top of the equipment, and the main beam slides forward along the axial arc for about 16m. During the jacking and sliding process, observe the horizontal displacement changes of the main structure every 2 meters. Once the horizontal offset distance is greater than 5cm, the walking equipment starts the correction adjustment to control its horizontal posture. In theory, the height of the pad on the equipment is adjusted every 2m. During the process, observe the force changes of the equipment at each support point and make timely adjustments. At this time, the leading beam has crossed half of the Yanpai Expressway.
[0031] Step 3: If Figures 14 to 17 As shown in the figure, the first two sections of steel box girders are pushed to the theoretical position and the pushing is stopped to adjust the line shape of the bridge body and the horizontal displacement of the steel box girder, and temporarily fix it. The steel box girder of segment 3 is assembled on the assembly frame and connected with the previous steel box girder to form a whole, waiting for the next overall pushing. The posture is adjusted to match the plan during the process.
[0032] Step 4: Figure 8 and Fig. 9 As shown, repeat the above steps 1 to 3 until the steel box girder is installed.
[0033] Actual application case: The present invention is applied to the Z8 ramp bridge (Z8P8-Z8P11) of the supporting road of Shenzhen Yantian Port Trailer Comprehensive Service Center. It is a double-box steel box girder structure with a longitudinal slope between 3.6-5% and a transverse slope of 2.0%. There is a superelevation change at Z8P10-Z8P11. The present invention is used to successfully erect the steel box girder structure.
Claims
1. A walking jacking device for municipal steel box beams with extreme curvature in low mountain and hilly terrain, characterized by: It includes a horizontal pushing mechanism for pushing the steel box girder in the horizontal direction, and a jacking mechanism located at one side of the horizontal pushing mechanism and used to push the steel box girder upward to disengage the steel box girder from the horizontal pushing mechanism so as to retract the horizontal pushing mechanism. The horizontal pushing mechanism includes a sliding base, a horizontal sliding assembly located on the sliding base and pushing the steel box girder to move, and a load supporting assembly located on the top of the horizontal sliding assembly and used to support the steel box girder. The jacking mechanism includes a jacking base, a deviation correction assembly located on the jacking base, a lifting assembly located on the deviation correction assembly, and a deviation correction top beam located on the top of the lifting assembly.
2. The walking jacking device for municipal steel box beams with extreme curvature in low mountain and hilly terrain according to claim 1 is characterized in that: The horizontal sliding assembly includes a sliding shoe located on the sliding base and moving along the length direction of the sliding base, a first pushing cylinder with one end fixed to the sliding shoe and the other end located outside the sliding shoe, and a support frame with a bottom fixedly connected to the sliding base and located below the first pushing cylinder for supporting the first pushing cylinder.
3. The walking jacking device for municipal steel box beams with extreme curvature in low mountain and hilly terrain according to claim 2 is characterized in that: The support frame includes a first vertical plate and a second vertical plate whose bottom is fixedly connected to the sliding base and symmetrically arranged, a third vertical plate located between the first vertical plate and the second vertical plate and whose two ends are respectively fixedly connected to the first vertical plate and the second vertical plate, and a placement groove located above the third vertical plate.
4. The walking jacking device for municipal steel box beams with extreme curvature in low mountain and hilly terrain according to claim 2 is characterized in that: The sliding shoe includes a sliding plate located above the sliding base and moving along the length direction of the sliding base, a vertical frame fixedly connected to the sliding plate at the bottom and symmetrically arranged, and a flat plate fixedly connected to the top of the vertical frame; a first mounting plate for fixing the first push cylinder is provided between the vertical frames.
5. The walking jacking device for municipal steel box beams with extreme curvature in low mountain and hilly terrain according to claim 1 is characterized in that: The load supporting assembly includes a sliding top beam.
6. The walking jacking device for municipal steel box beams with extreme curvature in low mountain and hilly terrain according to claim 1 is characterized in that: The lifting assembly comprises a second pushing cylinder whose bottom is fixedly connected to the deviation correcting assembly.
7. The walking jacking device for municipal steel box beams with extreme curvature in low mountain and hilly terrain according to claim 6 is characterized in that: The correcting assembly includes a second connecting plate fixedly connected to the front and rear sides of the jacking base, a second mounting plate fixedly connected to the second connecting plate, a third pushing cylinder fixed to the second mounting plate, a first connecting plate fixedly connected to the telescopic end of the third pushing cylinder, a correcting plate fixedly connected to the first connecting plate and located on the jacking base, and the second pushing cylinder is fixedly connected to the upper surface of the correcting plate.
8. A method for construction of municipal steel box beams with extreme curvature in low mountain and hilly terrain, characterized by: The following steps are involved: Step 1: Set up assembly brackets and platforms at piers Z8P6~Z8P8, install walking jacking devices on the jacking support system, and assemble steel box girder segments 1, 2 and the front guide beam structure in sections on the assembly platform; Step 2: Debug the walking jacking device. After confirming that the steel box girder structure and the temporary support system meet the quality requirements, use the walking jacking device to slide the main beam forward along the axial arc for a set distance; Step 3: Adjust the line shape of the front bridge body and the left and right offset of the steel box girder, assemble segment 3 on the tire frame, and connect it with the front steel box girder to form a whole, waiting for the next overall jacking; Step 4: Repeat the above steps 1 to 3 until the steel box girder is installed.
Citation Information
Cited By
Pushing mechanism for steel box girder of cable-stayed bridge
CN120006627A
A jacking mechanism for the steel box girder of a cable-stayed bridge
CN120006627B
Steel beam pushing lifting type operation device and using method thereof
CN121556366A
Method for constructing pedestrian bridge and pedestrian ramp connected to existing building
GB2635011A