By using the method of concealed roof venting pipes, the venting pipes are hidden in the roof structure, which solves the problem of easy damage and leakage of traditional venting holes, and achieves better waterproofing and aesthetics.
Patent Information
- Application Number
- CN202411255556.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-09
- Publication Date
- 2024-11-19
AI Technical Summary
Traditional roof vents are easily damaged by impacts, leading to leaks and poor roof waterproofing.
The construction method of concealed roof exhaust pipes is adopted, in which the exhaust pipes are buried in the main structure of the roof, and the exhaust outlets are concealed through the parapet wall or exhaust duct to avoid direct exposure of the exhaust holes.
Without altering the ventilation function, the risk of damage to the vents from impacts is reduced, the roof's waterproofing and aesthetics are improved, and ventilation is enhanced.
Smart Images

Figure CN118979597A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a construction method for a concealed roof exhaust pipe. Background Art
[0002] The traditional roofing method usually leaves exhaust channels with a spacing of about 6m in the roof slope layer and insulation layer. The exhaust duct runs vertically and horizontally, and exhaust holes are left vertically at the intersection, and exhaust hole protection piers are made on the outside of the exhaust holes. The exhaust holes of traditional exhaust roofs are easily damaged by collisions and leaks, and the roof waterproofing effect is poor. At present, with the development of new construction engineering technology, the traditional exhaust roof construction method is no longer suitable for use requirements.
[0003] The information disclosed in this background technology section is only intended to enhance the understanding of the overall background of the invention and should not be regarded as an acknowledgment or any form of suggestion that the information constitutes the prior art already known to a person skilled in the art. Summary of the invention
[0004] In order to overcome the defects of the prior art, a construction method of a concealed roof exhaust pipe is provided to solve the problem that the exhaust holes of the traditional exhaust roof are easily damaged by collision and leak, and the roof waterproofing effect is poor.
[0005] To achieve the above object, a construction method for a concealed roof exhaust pipe is provided, comprising the following steps:
[0006] Constructing the main roof structure, burying an exhaust pipe in the main roof structure, and extending one end of the exhaust pipe to the position of the parapet wall or exhaust duct on the main roof structure;
[0007] Casting a leveling layer on the main roof structure;
[0008] Laying a waterproof layer on the leveling layer;
[0009] The parapet wall or the exhaust duct is cast on the main roof structure, and one end of the exhaust pipe is buried in the parapet wall or the exhaust duct, so that the end of the exhaust pipe extends to the outside of the parapet wall or the inside of the exhaust duct.
[0010] Furthermore, before pouring the leveling layer on the main roof structure, a slope layer and a thermal insulation layer are poured on the main roof structure.
[0011] The beneficial effect of the present invention is that the construction method of the concealed roof exhaust pipe of the present invention improves the traditional practice without changing the exhaust function, and the exhaust pipe of the exhaust roof is buried under the waterproof layer, and the exhaust port is permanently concealed by the exhaust pipe system secretly installed on the parapet or the wall protruding from the roof structure. The concealed exhaust pipe does not leave an exhaust hole on the roof, which reduces roof obstacles, increases practicality and aesthetics, and can overcome the disadvantage that the exhaust hole of the traditional exhaust roof is easily damaged by collision and leakage, ensuring smooth roof exhaust and roof waterproofing. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Other features, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:
[0013] Figure 1 This is a schematic diagram of an exhaust pipe arranged in a parapet according to an embodiment of the present invention.
[0014] Figure 2 It is a schematic diagram of an exhaust pipe arranged in an exhaust duct according to an embodiment of the present invention. DETAILED DESCRIPTION
[0015] The present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the relevant invention, rather than to limit the invention. It is also necessary to explain that, for ease of description, only the parts related to the invention are shown in the accompanying drawings.
[0016] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0017] Reference Figure 1 and Figure 2 As shown, the present invention provides a construction method for a concealed roof exhaust pipe, comprising the following steps:
[0018] S1. Construct the main roof structure and bury the exhaust pipe in the main roof structure. Extend one end of the exhaust pipe to the parapet or exhaust duct on the main roof structure.
[0019] 1. Draw the roof exhaust duct construction layout according to the roof drawings and design requirements. The vertical and horizontal spacing of the exhaust duct shall not exceed 6m, and about 5m is appropriate. The exhaust duct shall run vertically and horizontally and be connected with the exhaust pipe reserved on the wall.
[0020] 2. Reserve exhaust holes on the wall according to the exhaust duct layout diagram. The exhaust holes should be located where they are not easily damaged by collisions and where there are no obstacles. The height of the exhaust holes should be no less than 350mm from the roof.
[0021] 3. When a residential project has a smoke exhaust duct protruding from the roof, the exhaust pipe outlet can also be directly extended into the roof smoke exhaust duct.
[0022] 4. Clean the roof base and use ink lines to mark the location of the exhaust pipe network. This location is also the location of the grid joints of the slope layer, insulation layer and leveling layer. The slope layer and insulation layer are constructed according to the design requirements, and the grid joints are filled with corresponding loose materials, and the filling height is lower than one exhaust pipe diameter at the bottom of the waterproof layer.
[0023] 5. Exhaust pipe selection and processing
[0024] The exhaust pipe uses UPVC plastic pipe with a diameter of 32-50mm. Use a bench drill to drill A150 air holes along the entire length of the UPVC plastic pipe, drill 4 holes in a circle, and drill holes in an interlaced manner. The air holes must be drilled through the pipe wall. After drilling, remove the burrs and debris around the holes to avoid blockage.
[0025] 6. Exhaust pipe construction
[0026] 1) According to the exhaust pipeline, the UPVC plastic pipes with air holes drilled are bonded to each other into a net. Cross four-way joints or T-shaped three-way joints are used to connect the exhaust pipes vertically and horizontally. Cross four-way joints or T-shaped three-way joints are used to connect the straight sections. 90° or 45° elbows are used at the turns.
[0027] 2) Before bonding pipes and fittings, wipe the inside of the socket and the outside of the plug at the joint with cotton yarn or dry cloth to keep the bonded surfaces clean and free of dust, sand and water marks.
[0028] 3) Before bonding, test-insert the two pipes once to ensure that the insertion depth and fit meet the requirements and mark the insertion depth of the socket on the surface of the insertion end. The insertion depth of the pipe end into the socket shall not be less than 20mm.
[0029] 4) Use a brush to quickly apply adhesive to the joint surface of the outside of the plug and the inside of the socket, insert the pipe end into the socket, and squeeze the pipe end to the depth of the marked mark. To prevent the interface from slipping, the insertion force should be maintained for no less than 30 seconds.
[0030] 5) After the socket joint is bonded, it should be left to cure for no less than 20 minutes.
[0031] 6) Place the bonded exhaust pipe network in the partition joint and glue it to the exhaust pipe pre-buried in the wall.
[0032] S2. Pour the leveling layer on the main roof structure.
[0033] S3. Lay a waterproof layer on the leveling layer.
[0034] In this embodiment, before pouring the leveling layer on the main roof structure, the slope layer and the insulation layer are poured on the main roof structure.
[0035] When constructing the leveling layer, keep the top surface of the exhaust pipe level with the leveling layer or slightly lower than the leveling layer, and do not damage the exhaust pipe during construction.
[0036] S4. Cast a parapet or exhaust duct on the main roof structure, and bury one end of the exhaust pipe in the parapet or the exhaust duct so that the end of the exhaust pipe extends to the outside of the parapet or the inside of the exhaust duct.
[0037] The construction method of the concealed roof exhaust pipe of the present invention pre-buries the roof exhaust pipe in advance when the main roof structure is constructed, and conceals the exhaust pipe in the roof parapet or the roof exhaust duct.
[0038] To prevent the exhaust pipe from being blocked, plugs are used to seal the pre-buried exhaust pipe openings. Construction of roof exhaust pipe network, connecting exhaust pipes. Installation of exhaust outlets of finished exhaust pipes. On-site technical review and construction quality acceptance.
[0039] The construction method of the concealed roof exhaust pipe of the present invention improves the traditional practice without changing the exhaust function, and the exhaust pipe of the exhaust roof is buried under the waterproof layer, and the exhaust port is permanently concealed by the exhaust pipe system secretly installed on the parapet or the wall protruding from the roof structure. The concealed exhaust pipe does not leave an exhaust hole on the roof, which reduces roof obstacles, increases practicality and aesthetics, and can overcome the disadvantage that the exhaust hole of the traditional exhaust roof is easily damaged by collision and leakage, ensuring smooth roof exhaust and roof waterproofing.
[0040] The construction method of the concealed roof exhaust pipe of the present invention ensures that the exhaust pipe network is unobstructed and the steam collection effect is easily guaranteed. The construction method of the concealed roof exhaust pipe of the present invention makes the exhaust pipe port concealed and beautiful, and improves the practicality of the roof.
[0041] The roof constructed by the construction method of the concealed roof exhaust pipe of the present invention has good integrity and an overall beautiful effect.
[0042] The construction method of the concealed roof exhaust pipe of the present invention reduces the leakage risk of the roof waterproof layer after the construction and has a good waterproof effect.
[0043] The construction method of the concealed roof exhaust pipe of the present invention achieves the purpose of saving working hours, improving efficiency, reducing energy consumption and reducing costs.
[0044] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the inventive concept. For example, the above features are replaced with (but not limited to) technical features with similar functions disclosed in the present application.
Claims
1. A construction method for a concealed roof exhaust pipe, characterized in that: The following steps are involved: Constructing the main roof structure, burying an exhaust pipe in the main roof structure, and extending one end of the exhaust pipe to the position of the parapet wall or exhaust duct on the main roof structure; Casting a leveling layer on the main roof structure; Laying a waterproof layer on the leveling layer; The parapet wall or the exhaust duct is cast on the main roof structure, and one end of the exhaust pipe is buried in the parapet wall or the exhaust duct, so that the end of the exhaust pipe extends to the outside of the parapet wall or the inside of the exhaust duct.