Concrete prefabricated pipe gallery structure and construction method of concrete prefabricated pipe gallery

By using the structure of track groups and grouting parts in the construction of concrete prefabricated pipe gallery, the problems of high assembly difficulty and poor sealing are solved, and more efficient construction and a more stable pipe gallery structure are achieved.

CN119553718APending Publication Date: 2025-03-04MCC CAPITAL ENGINEERING & RESEARCH INC LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202311125861.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-09-01
Publication Date
2025-03-04

AI Technical Summary

Technical Problem

There is a problem that the concrete prefabricated pipe gallery is difficult to assemble during the construction process, and it is difficult to ensure the overall sealing of the pipe gallery.

Method used

The structure is adopted that includes a pad, a track group, a grouting part, a sealant and a plurality of prefabricated pipe sections. The track group is used to move the prefabricated pipe sections in a longitudinal direction to adjust the position, set the spacing between the track group to construct the sealant, and a grouting part is provided between the pad and the prefabricated pipe section to uniformly bear the force.

Benefits of technology

It improves construction efficiency, prevents the damage of the waterproof layer at the bottom of the prefabricated pipe joint, ensures the sealing and overall stability of the pipe corridor, and solves the problem of stress concentration in traditional processes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119553718A_ABST
    Figure CN119553718A_ABST
Patent Text Reader

Abstract

The invention provides a concrete prefabricated pipe gallery structure and a construction method of a concrete prefabricated pipe gallery. The concrete prefabricated pipe gallery structure comprises cushion blocks, a track set, a grouting part, sealant and a plurality of prefabricated pipe joints, and the prefabricated pipe joints are distributed in the longitudinal direction; a track group is fixed on the cushion block, the prefabricated pipe joints are arranged on the track group, and the track group is located at the joint of every two adjacent prefabricated pipe joints; the track set comprises a first track and a second track which are distributed in the longitudinal direction at intervals, the first track corresponds to one of the two adjacent prefabricated pipe joints, and the second track corresponds to the other one of the two adjacent prefabricated pipe joints. A track group interval is arranged between the first track and the second track; a grouting part is arranged between the cushion block and the prefabricated pipe joint; and the sealant is arranged between every two adjacent prefabricated pipe sections, and the technical problems that the assembling difficulty of a concrete prefabricated pipe gallery is large, and the overall sealing performance of the pipe gallery is difficult to guarantee are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of prefabricated assembled pipe corridors, and in particular to a prefabricated concrete pipe corridor structure and a construction method of the prefabricated concrete pipe corridor. Background Art

[0002] The application of integrated pipe corridors in municipal pipelines effectively alleviates the contradiction between land resource shortage and urban functional requirements, and improves the utilization rate of underground space. It avoids the problem of repeated excavation and construction of the road surface in busy areas, and effectively solves the problems of "street zippers" and "spider webs in the sky". Prefabricated prefabricated pipe corridors are widely used because of their great advantages in quality and construction period, which is conducive to the green construction of urban infrastructure. Prefabricated pipe corridors are cast in sections in the factory, and the assembly process is used on site to form an integrated pipe corridor.

[0003] Prefabricated pipe corridors also face many technical problems: pipe segments are prefabricated in the factory, while the concrete cushion is cast on site. The prefabricated pipe segments are placed directly on the cushion in a "hard-on-hard" manner. It is impossible for the two to fit completely, and stress concentration will inevitably occur in local positions of the bottom plate. As time goes by, fatigue cracks will occur in the pipe corridor, affecting the overall safety and stability of the pipe corridor. Furthermore, the prefabricated pipe segments are placed on the cushion, and the sealant on the outside of the bottom plate at the splicing position of the pipe segments is difficult to apply. These will affect the normal operation and use of the pipe corridor in the later stage and reduce the durability of the pipe corridor. In addition, the construction and equipment of the prefabricated pipe corridor are more complicated, requiring a larger working surface. Summary of the invention

[0004] The purpose of the present invention is to provide a prefabricated concrete pipe gallery structure and a construction method of a prefabricated concrete pipe gallery, so as to solve the technical problem that the prefabricated concrete pipe gallery is difficult to assemble and it is difficult to ensure the overall sealing of the pipe gallery.

[0005] The above-mentioned purpose of the present invention can be achieved by adopting the following technical solutions:

[0006] The present invention provides a concrete prefabricated pipe gallery structure, comprising: a cushion block, a track group, a grouting part, a sealant and a plurality of prefabricated pipe sections, wherein the plurality of prefabricated pipe sections are distributed in the longitudinal direction;

[0007] The track group is fixed on the cushion block, the prefabricated pipe section is arranged on the track group, and the track group is located at the junction of two adjacent prefabricated pipe sections;

[0008] The track group includes a first track and a second track spaced apart in the longitudinal direction, the first track corresponds to one of two adjacent prefabricated pipe sections, and the second track corresponds to the other of the two adjacent prefabricated pipe sections; and a track group spacing is provided between the first track and the second track;

[0009] The grouting part is arranged between the cushion block and the prefabricated pipe section; and the sealant is arranged between two adjacent prefabricated pipe sections.

[0010] In a preferred embodiment, a pipe segment spacing is provided between two adjacent prefabricated pipe segments, and a lower opening of the pipe segment spacing is located above the middle of the track group spacing; and the sealant is provided in the pipe segment spacing.

[0011] In a preferred embodiment, the pipe segment intervals are provided with glue-applying anti-leakage auxiliary strips, and the sealant is formed on the glue-applying anti-leakage auxiliary strips.

[0012] In a preferred embodiment, the prefabricated pipe segment is outer-cased with a plurality of vertically distributed sealing rings, and the sealing rings are at least partially located in the pipe segment spacing.

[0013] In a preferred embodiment, the cushion block is provided with an embedded part, and the first rail and the second rail are both welded to the embedded part.

[0014] In a preferred embodiment, the concrete prefabricated pipe gallery structure includes a plurality of the pads spaced apart in the longitudinal direction, and the pads correspond to the junctions of two adjacent prefabricated pipe sections.

[0015] In a preferred embodiment, the cross section of the prefabricated pipe segment is in the shape of a rectangular frame.

[0016] In a preferred embodiment, the prefabricated pipe segment is provided with a plurality of reserved holes, and the reserved holes are located at the corners of the prefabricated pipe segment; positioning columns are provided in the corresponding reserved holes of two adjacent prefabricated pipe segments.

[0017] The present invention provides a construction method of a prefabricated concrete pipe gallery, which is used to construct the above-mentioned prefabricated concrete pipe gallery structure. The construction method comprises:

[0018] constructing pads on the foundation;

[0019] A first rail and a second rail are installed on the pad, wherein the first rail and the second rail are spaced apart in the longitudinal direction;

[0020] Hoisting the prefabricated pipe segments onto the first rail and the second rail;

[0021] Applying sealant between two adjacent prefabricated pipe sections;

[0022] Grouting is performed between the cushion block and the prefabricated pipe section to form a grouting portion.

[0023] In a preferred embodiment, grease is applied to the upper surface of the first rail and the upper surface of the second rail before the prefabricated pipe segment is hoisted.

[0024] The characteristics and advantages of the present invention are:

[0025] During the construction of the concrete prefabricated pipe gallery structure provided by the present invention, after the prefabricated pipe segment is placed on the track group by a crane, it can be moved along the track group to adjust the position, thereby releasing the crane, solving the problem of completely relying on the crane when adjusting the position of the pipe segment, and helping to improve work efficiency. When the prefabricated pipe segment moves along the first track and the second track in the track group, the friction force on the bottom of the prefabricated pipe segment is small, which helps to prevent damage to the preset waterproof layer at the bottom of the prefabricated pipe segment, ensure the waterproof performance of the later pipe gallery, and protect the integrity of the pipe segment structure layer. A track group spacing is set between the first track and the second track, which makes it possible to set a sealant between two adjacent prefabricated pipe segments, solving the problem of sealant construction on the outer side of the bottom plate at the joint of the prefabricated pipe segment, thereby ensuring the sealing of the joint of the pipe segment and the integrity of the pipe gallery. A grouting part is set between the pad and the prefabricated pipe segment by grouting, and the space between the prefabricated pipe segment and the pad is filled with grouting to ensure that the prefabricated pipe segment is evenly stressed and prevent stress concentration at the bottom. This solves the problem of stress concentration between the pipe segment and the concrete cushion layer in traditional processes and ensures the overall safety and stability of the concrete prefabricated pipe gallery structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0027] Figure 1 A schematic diagram of the installation plan of the prefabricated concrete pipe gallery structure provided by the present invention;

[0028] Figure 2 for Figure 1 The cross-sectional view along the ZZ direction;

[0029] Figure 3 for Figure 2 A local enlarged view of point A in FIG.

[0030] Figure 4 for Figure 1 A cross-sectional view taken along the HH direction;

[0031] Figure 5 for Figure 4 A local enlarged view of point B in FIG.

[0032] Figure 6 A schematic diagram of the construction method of the prefabricated concrete pipe gallery provided by the present invention.

[0033] Description of Figure Numbers:

[0034] 1. Track group; 11. First track; 12. Second track; 13. Track group spacing;

[0035] 3. Pads; 2. Embedded parts;

[0036] 4. Grouting part; 5. Bolt hole; 8. Positioning and fastening bolts;

[0037] 6. Prefabricated pipe sections; 61. Pipe section spacing;

[0038] 7. Sealant; 10. Glue leak-proof auxiliary strip;

[0039] 9. Sealing ring. DETAILED DESCRIPTION

[0040] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0041] Solution 1

[0042] The present invention provides a prefabricated concrete pipe gallery structure, such as Figure 1-Figure 5 As shown, it includes: a cushion block 3, a track group 1, a grouting part 4, a sealant 7 and a plurality of prefabricated pipe segments 6, and the plurality of prefabricated pipe segments 6 are distributed in the longitudinal direction; a track group 1 is fixed on the cushion block 3, and the prefabricated pipe segments 6 are arranged on the track group 1, and the track group 1 is located at the intersection of two adjacent prefabricated pipe segments 6; the track group 1 includes a first track 11 and a second track 12 distributed in the longitudinal direction at intervals, the first track 11 corresponds to one of the two adjacent prefabricated pipe segments 6, and the second track 12 corresponds to the other of the two adjacent prefabricated pipe segments 6; and a track group spacing 13 is arranged between the first track 11 and the second track 12; a grouting part 4 is arranged between the cushion block 3 and the prefabricated pipe segment 6; and the sealant 7 is arranged between two adjacent prefabricated pipe segments 6.

[0043] During the construction of the concrete prefabricated pipe gallery structure provided by the present invention, after the prefabricated pipe segment 6 is placed on the track group 1 by a crane, it can be moved along the track group 1 to adjust its position, thereby releasing the crane, solving the problem of completely relying on the crane when adjusting the position of the pipe segment, and is conducive to improving work efficiency.

[0044] When the prefabricated pipe segment 6 moves along the first track 11 and the second track 12 in the track group 1, the friction force on the bottom of the prefabricated pipe segment 6 is small, which is beneficial to prevent damage to the preset waterproof layer at the bottom of the prefabricated pipe segment 6, ensure the waterproof performance of the later pipeline corridor, and protect the integrity of the pipe segment structural layer.

[0045] A track group spacing 13 is set between the first track 11 and the second track 12, which makes it possible to set the sealant 7 between two adjacent prefabricated pipe sections 6, solves the construction problem of the sealant 7 on the outer side of the bottom plate at the joint of the prefabricated pipe sections 6, thereby ensuring the sealing of the pipe section joints and the integrity of the pipe gallery.

[0046] By grouting, a grouting part 4 is set between the cushion block 3 and the prefabricated pipe segment 6, and the space between the prefabricated pipe segment 6 and the cushion block 3 is filled with grouting to ensure that the prefabricated pipe segment 6 is evenly stressed and prevent stress concentration at the bottom, thereby solving the stress concentration problem between the pipe segment and the concrete cushion layer in the traditional process and ensuring the overall safety and stability of the concrete prefabricated pipe gallery structure. Preferably, grouting is performed between the foundation soil and the bottom of the prefabricated pipe segment 6, so that the grouting part 4 is not only formed between the cushion block 3 and the prefabricated pipe segment 6, but can also fill the space between the foundation and the prefabricated pipe segment 6 with grouting.

[0047] The prefabricated pipe segment 6 may be a prefabricated standard segment pipe segment. Figure 4 and Figure 5 As shown, a pipe segment spacing 61 is provided between two adjacent prefabricated pipe segments 6, and the lower opening of the pipe segment spacing 61 is located above the middle of the track group spacing 13; the sealant 7 is provided in the pipe segment spacing 61. The area of ​​the pipe segment spacing 61 close to the cushion block 3 is blocked by the cushion block 3, so it is difficult to apply the sealant 7. By providing the track group spacing 13, the sealant 7 can be applied to the area of ​​the pipe segment spacing 61 close to the cushion block 3 through the track group spacing 13, so that the sealant 7 can also be applied to the outer side of the bottom plate of the prefabricated pipe segment 6, thereby ensuring the integrity of the sealant 7 and improving the sealing of the joint of the prefabricated pipe segment 6.

[0048] Furthermore, the pipe segment spacing 61 is provided with a glue anti-leakage auxiliary strip 10, and the sealant 7 is formed on the glue anti-leakage auxiliary strip 10, so as to ensure the flatness and regularity of the sealant 7 on the outer side of the bottom plate of the prefabricated pipe segment 6, prevent the occurrence of poor bonding, ensure the sealing effect, and improve the overall sealing of the pipe gallery. Specifically, the glue anti-leakage auxiliary strip 10 can be firmly pasted at the bottom end of the splicing seam of the bottom plate of the prefabricated pipe segment 6.

[0049] In one embodiment, the outer shell of the prefabricated pipe segment 6 is provided with a plurality of vertically distributed sealing rings 9, and the sealing rings 9 are at least partially located in the pipe segment spacing 61. Figure 4 and Figure 5 As shown, the outer wall of the prefabricated pipe section 6 is provided with a groove, the sealing ring 9 is positioned in the groove, and the sealing ring 9 is at least partially located in the pipe section spacing 61 and abuts against the adjacent prefabricated pipe section 6, thereby improving the sealing of the joint. The sealing ring 9 is preferably a rubber composite sealing ring 9.

[0050] In one embodiment, the cushion block 3 is provided with an embedded part 2, and the first rail 11 and the second rail 12 are both welded to the embedded part 2. Figure 2 and Figure 3 As shown, the first rail 11 and the second rail 12 can be steel rails. A rail group spacing 13 is set between the first rail 11 and the second rail 12 in the same rail group 1, and a spacing is also set between the rail groups 1 distributed longitudinally, that is, the first rail 11 and the second rail 12 are distributed longitudinally, which is not full-length and segmental, which greatly saves costs while ensuring the smooth implementation of the project.

[0051] The pad 3 may be a concrete pad 3, which may be cast in situ on the foundation surface. Figure 1 and Figure 4 As shown, the concrete prefabricated pipe gallery structure includes a plurality of pads 3 distributed at intervals along the longitudinal direction, and the pads 3 correspond to the intersections of two adjacent prefabricated pipe sections 6.

[0052] In one embodiment. Figure 2 As shown, the cross section of the prefabricated pipe segment 6 is in the shape of a rectangular frame. However, the cross section of the prefabricated pipe segment 6 is not limited to a rectangular shape, and may also be in a circular, elliptical, polygonal or irregular shape.

[0053] like Figure 2 and Figure 4 As shown, the prefabricated pipe segment 6 is provided with a plurality of reserved holes, and the reserved holes are located at the corners of the prefabricated pipe segment 6; positioning columns are provided in the corresponding reserved holes of two adjacent prefabricated pipe segments 6. The positioning columns cooperate with the corresponding reserved holes of two adjacent prefabricated pipe segments 6 to accurately position the prefabricated pipe segments 6 and ensure that the gaps between the prefabricated pipe segments 6 are of the designed size.

[0054] Furthermore, the reserved hole is a bolt hole 5, the positioning column is a positioning fastening bolt 8, the size of the bolt hole 5 should be coordinated with the positioning fastening bolt 8, the positioning fastening bolt 8 is inserted into the bolt hole 5, and the positioning fastening bolt 8 is tightened to accurately position the prefabricated pipe section 6. During the process of tightening the positioning fastening bolt 8, the prefabricated pipe section 6 moves on the first track 11 and the second track 12, and the friction force when the bottom of the prefabricated pipe section 6 moves is small, which is convenient for adjusting the position of the prefabricated pipe section 6.

[0055] The concrete prefabricated pipe gallery structure provided by the present invention casts a cushion block 3 on the foundation at the joint of the prefabricated pipe section 6, and a track group 1 is arranged above the cushion block 3. The bottom surface of the prefabricated pipe section 6 directly contacts the first track 11 or the second track 12 in the track group 1. The first track 11 and the second track 12 provide support for the prefabricated pipe section 6, and make the prefabricated pipe section 6 easy to move longitudinally to adjust the position. The prefabricated pipe section 6 does not need to be provided with a pre-buried structure at the bottom in advance for movement to adjust the position. The spacing between the first track 11 or the second track 12 provides the possibility of implementing the sealant 7 on the outside of the bottom plate of the splicing seam of the bottom plate of the prefabricated pipe section 6, facilitates the construction of the sealant 7, solves the problem of the construction of the sealant 7 on the outside of the bottom plate at the joint of the prefabricated pipe section 6, ensures the sealing of the joint of the prefabricated pipe section 6, ensures the overall integrity of the pipe gallery, and provides an economical, convenient and safe implementation plan for the fixing and installation of the assembled prefabricated pipe gallery.

[0056] Solution 2

[0057] The present invention provides a construction method of a prefabricated concrete pipe gallery, which is used to construct the above-mentioned prefabricated concrete pipe gallery structure, such as Figure 6 As shown, the construction method includes: step S10, constructing a cushion block 3 on the foundation; step S20, installing a first track 11 and a second track 12 on the cushion block 3, and the first track 11 and the second track 12 are spaced apart in the longitudinal direction; step S30, hoisting the prefabricated pipe segment 6 onto the first track 11 and the second track 12; step S40, constructing a sealant 7 between two adjacent prefabricated pipe segments 6; step S50, grouting and filling between the cushion block 3 and the prefabricated pipe segment 6 to form a grouting portion 4.

[0058] By adopting this construction method, the prefabricated pipe segment 6 can be moved along the track group 1 to adjust its position, thereby releasing the crane, solving the problem of completely relying on the crane when adjusting the position of the pipe segment, and being beneficial to improving work efficiency; when the prefabricated pipe segment 6 moves along the first track 11 and the second track 12 in the track group 1, the friction force on the bottom of the prefabricated pipe segment 6 is small, which is beneficial to preventing damage to the preset waterproof layer at the bottom of the prefabricated pipe segment 6, ensuring the waterproof performance of the later pipe gallery, and protecting the integrity of the pipe segment structure layer; a track group spacing 13 is set between the first track 11 and the second track 12, providing the possibility for the construction of the sealant 7, solving the problem of the construction of the sealant 7 on the outer side of the bottom plate at the joint of the prefabricated pipe segment 6, thereby ensuring the sealing of the joint of the pipe segment and the integrity of the pipe gallery; the construction method adopts post-grouting, and the grouting part 4 grouts and fills the space between the prefabricated pipe segment 6 and the cushion block 3, ensuring that the prefabricated pipe segment 6 is evenly stressed, preventing stress concentration at the bottom, solving the problem of stress concentration between the pipe segment and the concrete cushion layer in the traditional process, and ensuring the overall safety and stability of the concrete prefabricated pipe gallery structure. Preferably, grouting is performed between the foundation soil and the bottom of the prefabricated pipe segment 6 , so that the grouting portion 4 is not only formed between the cushion block 3 and the prefabricated pipe segment 6 , but also the space between the foundation and the prefabricated pipe segment 6 can be filled with grouting.

[0059] Preferably, in step S50 , the space between the prefabricated pipe segment 6 and the foundation is filled with grouting material without shrinkage to form a grouting portion 4 .

[0060] Furthermore, before hoisting the prefabricated pipe segment 6, grease is applied to the upper surface of the first rail 11 and the upper surface of the second rail 12. By setting the first rail 11 and the second rail 12 and polishing and lubricating the surfaces of the first rail 11 and the second rail 12, it is beneficial to reduce the friction when the bottom of the prefabricated pipe segment 6 moves, facilitate position adjustment, prevent damage to the preset waterproof layer at the bottom of the prefabricated pipe segment 6, ensure the waterproof performance of the later pipe gallery, protect the integrity of the pipe segment structure layer, save costs, and improve construction efficiency.

[0061] In one embodiment of the present invention, after the foundation treatment is completed, a pad block 3 is constructed on the base, and an embedded part 2 is laid on the pad block 3, and a group of track groups 1 are welded at the same time; the track group 1 is lubricated before the prefabricated pipe segment 6 is hoisted; the prefabricated pipe segment 6 is hoisted to the corresponding position, and the positioning fastening bolts 8 are tightened symmetrically in sequence until the designed positioning size is reached. The adjacent prefabricated pipe segments 6 are tightened and installed with the positioning fastening bolts 8. After adjusting and installing in place, the outer side sealant 7 of the bottom plate joint of the prefabricated pipe segment 6 is constructed, and the bottom is fixed by grouting.

[0062] Specifically, the construction steps of the construction method of the prefabricated concrete pipe gallery provided by the present invention include:

[0063] 1) When making the prefabricated pipe section 6, a bolt hole 5 is reserved at the axil corner of the prefabricated pipe section 6, and the size of the bolt hole 5 should be coordinated with the positioning and fastening bolt 8;

[0064] 2) After the foundation surface is compacted and smoothed, the pad block 3 is constructed, and the embedded part 2 is set on the pad block 3;

[0065] 3) A set of track groups 1 are welded on the embedded part 2, and the first track 11 and the second track 12 in the track group 1 are respectively located on both sides of the joint seam of the prefabricated pipe segment 6, and a certain space is reserved between the two first tracks 11 and the second track 12 to facilitate the construction of the sealant 7 after the prefabricated pipe segment 6 is in place. The central position of the reserved space should be basically aligned with the joint seam of the bottom plate of the prefabricated pipe segment 6; the surface, side and end of the first track 11 and the second track 12 are polished and smooth, and the corners are rounded;

[0066] 4) Grease should be applied to the upper surface of the track before hoisting the prefabricated pipe segment 6;

[0067] 5) After the prefabricated pipe section 6 is hoisted onto the track group 1, a glue-applying anti-leakage auxiliary strip 10 is firmly pasted at the bottom end of the joint seam of the bottom plate of the prefabricated pipe section 6 to facilitate the later construction of the sealant 7; the glue-applying anti-leakage auxiliary strip 10 should be made of a flexible material, which can be selected according to the actual situation on site;

[0068] 6) Hoist the prefabricated pipe segment 6 onto the track set 1 and repeat step 5);

[0069] 7) Insert the positioning and fastening bolts 8 into the reserved bolt holes 5, and tighten the positioning and fastening bolts 8 to accurately position the prefabricated pipe sections 6 to ensure that the gaps between the pipe sections are within the designed size;

[0070] 8) Repeat the above steps 5) to 7) to put several prefabricated pipe segments 6 in place;

[0071] 9) After the prefabricated pipe segment 6 is positioned and installed, the sealant 7 on the outside of the joint bottom plate is applied;

[0072] 10) After the construction of the sealant 7 on the outer side of the joint bottom plate is completed, the space between the prefabricated pipe section 6 and the foundation is filled with grouting material without shrinkage to ensure uniform force between the prefabricated pipe section 6 and the foundation and reduce stress concentration; the opening position should be sealed before filling to prevent leakage.

[0073] The above are only several embodiments of the present invention. Those skilled in the art may make various changes or modifications to the embodiments of the present invention based on the contents disclosed in the application documents without departing from the spirit and scope of the present invention.

Claims

1. A prefabricated concrete pipe gallery structure, characterized in that: include: A pad, a track group, a grouting part, a sealant and a plurality of prefabricated pipe sections, wherein the plurality of prefabricated pipe sections are distributed in the longitudinal direction; The track group is fixed on the cushion block, the prefabricated pipe section is arranged on the track group, and the track group is located at the junction of two adjacent prefabricated pipe sections; The track group includes a first track and a second track spaced apart in the longitudinal direction, the first track corresponds to one of two adjacent prefabricated pipe sections, and the second track corresponds to the other of the two adjacent prefabricated pipe sections; and a track group spacing is provided between the first track and the second track; The grouting part is arranged between the cushion block and the prefabricated pipe section; and the sealant is arranged between two adjacent prefabricated pipe sections.

2. The prefabricated concrete pipe gallery structure according to claim 1 is characterized in that: A pipe segment spacing is arranged between two adjacent prefabricated pipe segments, and a lower opening of the pipe segment spacing is located above the middle of the track group spacing; the sealant is arranged in the pipe segment spacing.

3. The prefabricated concrete pipe gallery structure according to claim 2 is characterized in that: The pipe section intervals are provided with glue-applying anti-leakage auxiliary strips, and the sealant is formed on the glue-applying anti-leakage auxiliary strips.

4. The prefabricated concrete pipe gallery structure according to claim 2, characterized in that: The outer sleeve of the prefabricated pipe segment is provided with a plurality of vertically distributed sealing rings, and the sealing rings are at least partially located in the pipe segment spacing.

5. The prefabricated concrete pipe gallery structure according to claim 1, characterized in that: The cushion block is provided with an embedded part, and the first rail and the second rail are both welded to the embedded part.

6. The prefabricated concrete pipe gallery structure according to claim 5, characterized in that: The concrete prefabricated pipe gallery structure includes a plurality of pads distributed at intervals along the longitudinal direction, and the pads correspond to the intersections of two adjacent prefabricated pipe sections.

7. The prefabricated concrete pipe gallery structure according to claim 1, characterized in that: The cross section of the prefabricated pipe segment is in the shape of a rectangular frame.

8. The prefabricated concrete pipe gallery structure according to claim 7, characterized in that: The prefabricated pipe section is provided with a plurality of reserved holes, and the reserved holes are located at the corners of the prefabricated pipe section; positioning columns are provided in the corresponding reserved holes of two adjacent prefabricated pipe sections.

9. A construction method for a prefabricated concrete pipe gallery, characterized in that: Used for constructing the prefabricated concrete pipe gallery structure according to any one of claims 1 to 8, the construction method comprises: constructing pads on the foundation; A first rail and a second rail are installed on the pad, wherein the first rail and the second rail are spaced apart in the longitudinal direction; Hoisting the prefabricated pipe segments onto the first rail and the second rail; Applying sealant between two adjacent prefabricated pipe sections; Grouting is performed between the cushion block and the prefabricated pipe section to form a grouting portion.

10. The construction method of the prefabricated concrete pipe gallery according to claim 9, characterized in that: Before hoisting the prefabricated pipe segment, apply grease to the upper surface of the first rail and the upper surface of the second rail.

Citation Information

Cited By

  • Underground pipe gallery construction auxiliary device

    CN120311703A