Unloading construction method for large steel structure roof
By setting displacement and stress monitoring points on large steel structure roofs, establishing simulation models and optimizing the disassembly sequence of support frames, the problem of unconsidered stress on tree column branches is solved, and the effect of avoiding cracking risks during unloading is achieved. , ensuring construction safety and structural integrity.
Patent Information
- Application Number
- CN202411057311.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2024-11-19
AI Technical Summary
During the unloading construction of large steel structure roofs, it is difficult for the existing technology to effectively consider the stress of the branches of tree columns, resulting in the risk of cracking or breaking of branch points, and the support and disassembly of existing pillars and roofs is not suitable for trees Type column affects structural safety.
By setting displacement monitoring points and stress monitoring points on the steel structure roof, establishing a simulation model, making a support frame disassembly sequence table, and optimizing the disassembly sequence through real-time monitoring data and simulation data, ensuring that the branches of the tree columns are in the unloading process There will be no risk of cracking or other risks.
Through real-time monitoring and simulation verification, the optimized disassembly sequence can be effectively avoided and the risk of cracking of tree column branches can be ensured, ensuring the safety and structural integrity of the construction process.
Smart Images

Figure CN118979634A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of steel structure construction, and in particular to an unloading construction method for a large steel structure roof. Background Art
[0002] With the development of large steel structure buildings in recent years, more and more construction units use steel structures to build large buildings, such as large stations, sports venues or exhibition halls, etc., and tree-shaped columns as the main supporting structure have beautiful appearance, good supporting strength and effect, and can meet the complex support requirements of the top.
[0003] The steel structure of the roof is installed by lifting and hoisting. During the construction process, many temporary supports and lifting brackets are set up. After the construction is completed, it must be unloaded. The unloading process is a complex process of interaction between the main structure and the bracket, and it is a process of gradual transfer of structural force and redistribution of internal force. The bracket changes from a load-bearing state to a load-free state, while the main structure transitions from an installed state to a designed stress state. In this process, there are many factors that affect the safety of the structure. The design of the bracket, the selection of the unloading scheme, and the effective control of the unloading process will have a great impact on the structure itself. There are many connection points between the tree-shaped column and the roof, and the displacement and stress changes are complex. The existing support and disassembly method of ordinary pillars and roofs is directly used in the support and disassembly of the tree-shaped column and the roof, which easily makes the branch force of the tree-shaped column not taken into account, resulting in the risk of cracking or even breaking at the branch point of the tree-shaped column. Summary of the invention
[0004] In view of the above-mentioned deficiencies in the prior art, the present invention provides an unloading construction method for a large steel structure roof connected to a roof with tree-shaped columns.
[0005] In order to achieve the above-mentioned object of the invention, the technical solution adopted by the present invention is:
[0006] A method for unloading a large steel structure roof is provided, which comprises the following steps:
[0007] S1: Select displacement monitoring points on the steel structure roof, and select stress monitoring points on the tree-shaped columns and supporting trusses;
[0008] S2: Set up the simulation model of the steel structure roof and tree-shaped columns, and mark the displacement monitoring points and stress monitoring points in the simulation model;
[0009] S3: numbering the support frames to be disassembled, making a support frame disassembly sequence table, disassembling the support frames along the numbers in the simulation model, and recording the simulation data of the displacement monitoring points and stress monitoring points when each support frame of the simulation model is disassembled;
[0010] S4: dismantle the physical support frame according to the dismantling sequence table. Each time a support frame is dismantled, the data of the displacement monitoring point and the stress monitoring point are compared with the simulation data, and the data offset is calculated;
[0011] S5: When the data offset is greater than the threshold, the disassembly of the next support frame is suspended, and the data of the real displacement monitoring point and the stress monitoring point are used to update the simulation model. The updated simulation model is used to simulate and verify and optimize the unloading sequence of the remaining support frames, and the unloading construction plan after simulation verification and optimization is used to continue the disassembly construction; otherwise, the disassembly construction is continued according to the disassembly sequence table until all the support frames are disassembled.
[0012] Furthermore, the calculation formula for data offset is:
[0013]
[0014] Among them, λ i is the distance factor; L i is the distance between the ith displacement monitoring point and the pth support frame; T i ' ,p is the displacement change value of the ith displacement monitoring point before and after the pth support frame is disassembled; T i,p is the displacement change value of the ith displacement monitoring point in the simulation model before and after the pth support frame is disassembled; ε j is the proportional factor between the distance between the jth stress monitoring point and the nearest tree-shaped column and the stress; P′ i,p is the stress change value of the jth stress monitoring point before and after the pth support frame is disassembled; P i,p is the stress change value of the jth stress monitoring point in the simulation model before and after the pth support frame is disassembled; m is the total number of displacement monitoring points; n is the total number of stress monitoring points.
[0015] Furthermore, the displacement monitoring point is the projection point of each branch point of the tree-shaped column perpendicular to the roof; the stress monitoring point is the center point of each branch of the tree-shaped column and the connection point between the supporting truss and the tree-shaped column branch.
[0016] Furthermore, the method for making the support frame disassembly sequence table is as follows:
[0017] A1: Collect the distance between the pth support frame and the center of the roof And the distance between the support frame and the three nearest tree-shaped columns and the supporting truss connection points
[0018] A2: Calculate the disassembly impact score of the pth support frame according to the disassembly impact score calculation formula. The disassembly impact score calculation formula is:
[0019]
[0020] A3: Sort the disassembly order of the support frame according to the disassembly impact score. The smaller the disassembly impact score, the higher the order.
[0021] Furthermore, the specific steps of simulation verification and optimization of the support frame disassembly sequence are as follows:
[0022] B1: According to the support frame disassembly sequence table, the support frame is disassembled in the simulation model and the stress changes at the stress monitoring points are recorded;
[0023] B2: After the kth support frame in the disassembly sequence table is disassembled, if the first situation occurs: any stress monitoring point detects that the changed stress value is greater than the corresponding tree-type column branch stress threshold, enter step B3; if the second situation occurs: any stress monitoring point detects that the stress change is greater than the change threshold, enter step B4; if both the first and second situations occur at the same time, enter step B3; otherwise, enter step B5;
[0024] B3: Go back twice to disassemble the support frame; at this time, the k-2 support frame in the original disassembly sequence list has been disassembled, and the k-1 support frame has not been disassembled; find the symmetrical point along the center of the roof where the k-1 support frame is connected to the roof, and take the support frame closest to the symmetrical point that has not been disassembled as the k-1 support frame in the new disassembly sequence list, and return to B2 to continue disassembly judgment;
[0025] B4: Go back once to disassemble the support frame; at this time, the k-1th support frame in the original disassembly sequence list has been disassembled, and the kth support frame has not been disassembled; the support frame closest to the kth support frame is used as the kth support frame in the new disassembly sequence list, and return to B2 to continue disassembly judgment;
[0026] B5: All support frames are completely disassembled, and the optimized support frame disassembly sequence table is output.
[0027] Furthermore, after preparing the support frame disassembly sequence table in step S3, a simulation verification and optimization is performed before entering step S4.
[0028] The beneficial effects of the present invention are:
[0029] The present invention sets displacement monitoring points on the steel structure roof, stress monitoring points on the tree-type columns and the supporting trusses, sets a supporting frame disassembly sequence table, compares the real-time monitoring data with the simulation data of the simulation model, and guides the actual disassembly construction according to the offset obtained by comparison, so that the entire support unloading construction process can fully take into account the changes of the tree-type columns. Through the setting and verification and optimization of the disassembly sequence, it can be ensured that during the disassembly of the support rod, the branches of the tree-type columns will not have the risk of cracking. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a schematic diagram of the process of the present invention. DETAILED DESCRIPTION
[0031] The specific implementation modes of the present invention are described below so that those skilled in the art can understand the present invention. However, it should be clear that the present invention is not limited to the scope of the specific implementation modes. For those of ordinary skill in the art, as long as various changes are within the spirit and scope of the present invention as defined and determined by the attached claims, these changes are obvious, and all inventions and creations utilizing the concept of the present invention are protected.
[0032] like Figure 1 As shown, a method for unloading a large steel structure roof comprises the following steps:
[0033] S1: Select displacement monitoring points on the steel structure roof, and select stress monitoring points on the tree-shaped columns and supporting trusses;
[0034] S2: Set up the simulation model of the steel structure roof and tree-shaped columns, and mark the displacement monitoring points and stress monitoring points in the simulation model;
[0035] S3: numbering the support frames to be disassembled, making a support frame disassembly sequence table, disassembling the support frames along the numbers in the simulation model, and recording the simulation data of the displacement monitoring points and stress monitoring points when each support frame of the simulation model is disassembled;
[0036] S4: dismantle the physical support frame according to the dismantling sequence table. Each time a support frame is dismantled, the data of the displacement monitoring point and the stress monitoring point are compared with the simulation data, and the data offset is calculated;
[0037] S5: When the data offset is greater than the threshold, the disassembly of the next support frame is suspended, and the data of the real displacement monitoring point and the stress monitoring point are used to update the simulation model. The updated simulation model is used to simulate and verify and optimize the unloading sequence of the remaining support frames, and the unloading construction plan after simulation verification and optimization is used to continue the disassembly construction; otherwise, the disassembly construction is continued according to the disassembly sequence table until all the support frames are disassembled.
[0038] The calculation formula for data offset is:
[0039]
[0040] Among them, λ i is the distance factor; L i is the distance between the ith displacement monitoring point and the pth support frame; T i ' ,p is the displacement change value of the ith displacement monitoring point before and after the pth support frame is disassembled; T i,pis the displacement change value of the ith displacement monitoring point in the simulation model before and after the pth support frame is disassembled; ε j is the proportional factor between the distance between the jth stress monitoring point and the nearest tree-shaped column and the stress; P i ' ,p is the stress change value of the jth stress monitoring point before and after the pth support frame is disassembled; P i,p is the stress change value of the jth stress monitoring point in the simulation model before and after the pth support frame is disassembled; m is the total number of displacement monitoring points; n is the total number of stress monitoring points.
[0041] The displacement monitoring point is the projection point of each branch point of the tree-shaped column perpendicular to the roof; the stress monitoring point is the center point of each branch of the tree-shaped column and the connection point between the supporting truss and the tree-shaped column branch.
[0042] The method for making the support frame disassembly sequence table is as follows:
[0043] A1: Collect the distance between the pth support frame and the center of the roof And the distance between the support frame and the three nearest tree-shaped columns and the supporting truss connection points
[0044] A2: Calculate the disassembly impact score of the pth support frame according to the disassembly impact score calculation formula. The disassembly impact score calculation formula is:
[0045]
[0046] A3: Sort the disassembly order of the support frame according to the disassembly impact score. The smaller the disassembly impact score, the higher the order.
[0047] The specific steps of simulation verification and optimization of the support frame disassembly sequence are as follows:
[0048] B1: According to the support frame disassembly sequence table, the support frame is disassembled in the simulation model and the stress changes at the stress monitoring points are recorded;
[0049] B2: After the kth support frame in the disassembly sequence table is disassembled, if the first situation occurs: any stress monitoring point detects that the changed stress value is greater than the corresponding tree-type column branch stress threshold, enter step B3; if the second situation occurs: any stress monitoring point detects that the stress change is greater than the change threshold, enter step B4; if both the first and second situations occur at the same time, enter step B3; otherwise, enter step B5;
[0050] B3: Go back twice to disassemble the support frame; at this time, the k-2 support frame in the original disassembly sequence list has been disassembled, and the k-1 support frame has not been disassembled; find the symmetrical point along the center of the roof where the k-1 support frame is connected to the roof, and take the support frame closest to the symmetrical point that has not been disassembled as the k-1 support frame in the new disassembly sequence list, and return to B2 to continue disassembly judgment;
[0051] B4: Go back once to disassemble the support frame; at this time, the k-1th support frame in the original disassembly sequence list has been disassembled, and the kth support frame has not been disassembled; the support frame closest to the kth support frame is used as the kth support frame in the new disassembly sequence list, and return to B2 to continue disassembly judgment;
[0052] B5: All support frames are completely disassembled, and the optimized support frame disassembly sequence table is output.
[0053] After making the support frame disassembly sequence table in step S3, a simulation verification and optimization are performed, and then step S4 is entered.
Claims
1. A method for unloading construction of a large steel structure roof, characterized in that: The steps include: S1: Select displacement monitoring points on the steel structure roof, and select stress monitoring points on the tree-shaped columns and supporting trusses; S2: Set up the simulation model of the steel structure roof and tree-shaped columns, and mark the displacement monitoring points and stress monitoring points in the simulation model; S3: numbering the support frames to be disassembled, making a support frame disassembly sequence table, disassembling the support frames along the numbers in the simulation model, and recording the simulation data of the displacement monitoring points and stress monitoring points when each support frame of the simulation model is disassembled; S4: dismantle the physical support frame according to the dismantling sequence table. Each time a support frame is dismantled, the data of the displacement monitoring point and the stress monitoring point are compared with the simulation data, and the data offset is calculated; S5: When the data offset is greater than the threshold, the disassembly of the next support frame is suspended, and the data of the real displacement monitoring point and the stress monitoring point are used to update the simulation model. The updated simulation model is used to simulate and verify and optimize the unloading sequence of the remaining support frames, and the unloading construction plan after simulation verification and optimization is used to continue the disassembly construction; otherwise, the disassembly construction is continued according to the disassembly sequence table until all the support frames are disassembled.
2. The unloading construction method of a large steel structure roof according to claim 1 is characterized in that: The calculation formula of the data offset is: Among them, λ i is the distance factor; L i is the distance between the ith displacement monitoring point and the pth support frame; T′ i,p is the displacement change value of the ith displacement monitoring point before and after the pth support frame is disassembled; T i,p is the displacement change value of the ith displacement monitoring point in the simulation model before and after the pth support frame is disassembled; ε j is the proportional factor between the distance between the jth stress monitoring point and the nearest tree-shaped column and the stress; P′ i,p is the stress change value of the jth stress monitoring point before and after the pth support frame is disassembled; P i,p is the stress change value of the jth stress monitoring point in the simulation model before and after the pth support frame is disassembled; m is the total number of displacement monitoring points; n is the total number of stress monitoring points.
3. The unloading construction method of a large steel structure roof according to claim 1 is characterized in that: The displacement monitoring points are the projection points of each branch point of the tree-shaped column perpendicular to the roof; the stress monitoring points are each bifurcation point of the tree-shaped column and the connection points between the supporting trusses and the tree-shaped column branches.
4. The unloading construction method of a large steel structure roof according to claim 1 is characterized in that: The method for making the support frame disassembly sequence table is as follows: A1: Collect the distance between the pth support frame and the center of the roof And the distance between the support frame and the three nearest tree-shaped columns and the supporting truss connection points A2: Calculate the disassembly impact score of the pth support frame according to the disassembly impact score calculation formula. The disassembly impact score calculation formula is: A3: Sort the disassembly order of the support frame according to the disassembly impact score. The smaller the disassembly impact score, the higher the order.
5. The unloading construction method of a large steel structure roof according to claim 1 is characterized in that: The specific steps of simulation verification and optimization of the support frame disassembly sequence are as follows: B1: According to the support frame disassembly sequence table, the support frame is disassembled in the simulation model and the stress changes at the stress monitoring points are recorded; B2: After the kth support frame in the disassembly sequence table is disassembled, if the first situation occurs: any stress monitoring point detects that the changed stress value is greater than the corresponding tree-type column branch stress threshold, enter step B3; if the second situation occurs: any stress monitoring point detects that the stress change is greater than the change threshold, enter step B4; if both the first and second situations occur at the same time, enter step B3; Otherwise, go to step B5; B3: Go back twice to disassemble the support frame; at this time, the k-2 support frame in the original disassembly sequence list has been disassembled, and the k-1 support frame has not been disassembled; find the symmetrical point along the center of the roof where the k-1 support frame is connected to the roof, and take the support frame closest to the symmetrical point that has not been disassembled as the k-1 support frame in the new disassembly sequence list, and return to B2 to continue disassembly judgment; B4: Back off once to disassemble the support frame; At this time, the k-1th support frame in the original disassembly sequence list has been disassembled, and the kth support frame has not been disassembled; the support frame closest to the kth support frame is used as the kth support frame in the new disassembly sequence list, and the process returns to B2 to continue the disassembly judgment; B5: All support frames are completely disassembled, and the optimized support frame disassembly sequence table is output.
6. The unloading construction method of a large steel structure roof according to claim 5 is characterized in that: After making the support frame disassembly sequence table in step S3, a simulation verification and optimization are performed, and then step S4 is entered.
Citation Information
Patent Citations
Stress removing and reinforcing method used for steel construction truss
CN102890739A
Large-span steel structure support unloading monitoring method
CN109781368A
Deformation and stress synchronous control method in roof unloading process
CN110196989A