Steel pipe water pressure test clamp and use method thereof

By designing hydraulic telescopic rods and steel pipe hydraulic pressure test fixtures for driving motors, the problems of low efficiency and inaccurate positioning of steel pipes in the prior art are solved, and efficient testing and accurate positioning of multiple steel pipes are achieved.

CN118980474APending Publication Date: 2024-11-19YANGZHOU JIAHUA PIPE IND CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411048499.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

The existing steel pipe hydraulic test fixtures have low working efficiency and can only test one steel pipe at a time. They are prone to inaccurate positioning during the installation process, resulting in failure of inspection and increasing the workload of staff.

Method used

A steel pipe hydraulic test fixture including the main frame unit and the clamping and fixing unit was designed. The hydraulic telescopic rod and the driving motor were used to achieve automatic clamping and hydraulic testing of the steel pipe, and the accuracy of the steel pipe was achieved through the loading rack and the inclined plate. Positioning and multi-tube testing simultaneously.

Benefits of technology

The working efficiency of steel pipe hydraulic testing is improved, the positioning inaccurate during installation is prevented, and the simultaneous testing of multiple steel pipes is achieved, reducing the workload of staff.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118980474A_ABST
    Figure CN118980474A_ABST
Patent Text Reader

Abstract

The invention discloses a steel pipe water pressure test fixture and a use method thereof.The steel pipe water pressure test fixture is characterized in that a main body frame unit comprises a square frame and first fixing plates symmetrically and fixedly connected to the upper ends of the two sides of the square frame, and a baffle is fixedly connected to the end, away from the square frame, of each first fixing plate; a plurality of second sliding plates which are uniformly distributed are slidably connected to the square frame, and an inclined plate is fixedly connected to the feeding frame; the clamping and fixing unit comprises a plurality of supporting frames evenly and fixedly connected to the upper end in the square frame, each supporting frame is slidably connected with a fixing base, the upper end of each second hydraulic telescopic rod is fixedly connected with a third fixing plate, and each second rotating wheel is slidably connected with the corresponding supporting frame. According to the steel pipe water pressure test fixture, the phenomenon of inaccurate positioning in the mounting process of the steel pipes is prevented, and the steel pipe water pressure test fixture can test a plurality of steel pipes at the same time, so that the working efficiency of the steel pipe water pressure test fixture can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of water pressure testing, and in particular to a steel pipe water pressure testing fixture and a use method thereof. Background Art

[0002] In recent years, with the development of industrialization and urbanization, pipeline systems have been widely used in various fields, such as oil, natural gas, chemical industry, water supply, drainage, etc. These pipeline systems need to withstand different degrees of pressure, so testing the pressure resistance of pipelines has become a necessary step. People often use manual methods to perform water pressure tests, that is, manually apply pressure and observe whether leakage occurs. This method has many limitations, such as the accuracy of the test results is affected by the operator's technical level and subjective judgment, and the test efficiency is low.

[0003] The existing steel pipe water pressure test fixture can usually only test one steel pipe at a time, which has low work efficiency. When testing, employees need to manually install it on the test equipment, and inaccurate positioning will inevitably occur during the installation process, which will lead to detection failure and increase the workload of the staff. Summary of the invention

[0004] The purpose of this section is to summarize some aspects of embodiments of the present invention and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the specification abstract and the invention title of this application to avoid blurring the purpose of this section, the specification abstract and the invention title, and such simplifications or omissions cannot be used to limit the scope of the present invention.

[0005] In view of the problems existing in the above-mentioned existing steel pipe water pressure testing fixture and its use method, the present invention is proposed.

[0006] Therefore, the purpose of the present invention is to provide a steel pipe water pressure testing fixture and a method of using the same, which is suitable for solving the problem that the existing steel pipe water pressure testing fixture can usually only test one steel pipe at a time during operation, and the working efficiency is low. When conducting the test, employees need to manually install it on the test equipment, and inaccurate positioning will inevitably occur during the installation process, which will lead to detection failure, thereby increasing the workload of the staff.

[0007] In order to solve the above technical problems, the present invention provides the following technical solutions: a steel pipe water pressure test fixture and a method of using the same, comprising:

[0008] A main frame unit, comprising a square frame and first fixed plates symmetrically fixedly connected to the upper ends of both sides of the square frame, each of the first fixed plates being slidably connected to a first sliding plate, the upper end of the first sliding plate being fixedly connected to a support plate, the support plate being fixedly connected to a support seat, a plurality of evenly distributed circular openings being fixedly opened on the support seat, each of the circular openings being fixedly connected to a fixed cylinder, a side of the fixed cylinder away from the square frame being fixedly connected to a hose, a side of the fixed cylinder away from the hose being fixedly connected to a nozzle, first hydraulic telescopic rods being fixedly connected to both sides of the square frame close to the first fixed plate, and the upper end of each of the first hydraulic telescopic rods being fixedly connected to the first sliding plate;

[0009] The clamping and fixing unit includes a plurality of support frames evenly fixedly connected to the upper end of the square frame, each of the support frames is slidably connected to a fixed seat, a plurality of evenly distributed fixed blocks are fixedly connected to one side of the upper end of the fixed seat, a plurality of sliding blocks are slidably connected to the upper end of the fixed seat away from the fixed block, a connecting plate is fixedly connected to the bottom of the sliding block, an elliptical opening is fixedly opened on the connecting plate, a square opening is fixedly opened in the fixed seat, a driving motor is fixedly connected to the square opening, and a gear is fixedly connected to the output shaft of the driving motor, each of the two ends of the fixed seat is symmetrically fixedly connected to a first rotating wheel, each of the first rotating wheels is slidably connected to the support frame, a second fixed plate is fixedly connected to the fixed seat near the center of one side of the support frame, a plurality of evenly distributed second rotating wheels are fixedly connected to the second fixed plate, and each of the second rotating wheels is slidably connected to the support frame.

[0010] As a preferred solution of the steel pipe water pressure testing fixture described in the present invention, wherein: a loading rack is fixedly connected to the side of the square frame away from the supporting frame, the loading rack is made of manganese steel material, the loading rack is fixedly connected to a supporting platform, and the loading rack is fixedly connected to an inclined plate.

[0011] As a preferred solution of the steel pipe water pressure testing fixture described in the present invention, each of the fixed block and the sliding block is fixedly provided with a V-shaped groove, and the grooves on the fixed block and the sliding block are arranged relative to each other.

[0012] As a preferred solution of the steel pipe water pressure testing fixture described in the present invention, the connecting plate is slidably connected to the fixing seat, the bottom of the elliptical opening is fixedly connected with a rack, and the rack is meshed with the gear.

[0013] As a preferred solution of the steel pipe water pressure test fixture described in the present invention, a rubber block is fixedly connected to the nozzle, the rubber block is arranged in a circular ring shape, and the diameter of the inner wall of the steel pipe matches the diameter of the rubber block.

[0014] As a preferred solution of the steel pipe water pressure testing fixture described in the present invention, wherein: a baffle is fixedly connected to the end of each of the first fixed plates away from the square frame, a plurality of evenly distributed second sliding plates are slidably connected to the square frame, and each of the second sliding plates is fixedly provided with a plurality of semicircular grooves.

[0015] As a preferred solution of the steel pipe water pressure testing fixture described in the present invention, wherein: a plurality of second hydraulic telescopic rods are fixedly connected to the upper end of the square frame, each of the second hydraulic telescopic rods is fixedly connected to the upper end of a third fixed plate, and the third fixed plate is fixedly connected to the bottom of the fixed seat.

[0016] A method for using a steel pipe water pressure test, the method is applicable to any of the above test fixtures, and the method comprises the following steps:

[0017] S1: placing the steel pipes to be subjected to the water pressure test on the loading rack, and tilting the plate so that the steel pipes fall onto the second sliding plate;

[0018] S2: The fixing seat fixedly connected to the upper end of the second hydraulic telescopic rod is moved upward by the second hydraulic telescopic rod, and the output shaft of the driving motor is rotated to rotate the gear, so that the connecting plate slides, and the sliding block fixedly connected to the connecting plate moves, so as to clamp the steel pipe;

[0019] S3: Water is flowed into the steel pipe through a hose and a nozzle to perform a water pressure test on the steel pipe.

[0020] The beneficial effects of the present invention are as follows: the steel pipe is dropped into the semicircular groove on the second sliding plate through the inclined plate on the loading rack, and then the second hydraulic telescopic rod is started, and the upper end of the second hydraulic telescopic rod is extended, so that the fixed seat fixedly connected to the upper end of the second hydraulic telescopic rod moves upward, and then the output shaft of the driving motor is rotated, so that the gear fixedly connected to the output shaft of the driving motor is rotated, and because the gear is meshed with the rack, the connecting plate is moved, so that the sliding block fixedly connected to the upper end of the connecting plate is moved, so that the steel pipe can be clamped by the fixed block and the sliding block;

[0021] Then start the first hydraulic telescopic rod, and move the upper end of the first hydraulic telescopic rod to move the first sliding plate, thereby moving the support seat fixedly connected to the first sliding plate, so that the nozzle fixedly connected on the support seat is fixedly connected to the inner wall of the steel pipe, so that the steel pipe water pressure test fixture can fix and clamp the steel pipe, preventing the occurrence of inaccurate positioning of the steel pipe during the installation process, and the steel pipe water pressure test fixture can test multiple steel pipes at the same time, thereby improving the working efficiency of the steel pipe water pressure test fixture. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. Among them:

[0023] Figure 1 This is a schematic diagram of the overall structure of a steel pipe water pressure test fixture proposed by the present invention;

[0024] Figure 2 This is a front view structural schematic diagram of a steel pipe water pressure test fixture proposed by the present invention;

[0025] Figure 3 This is a schematic diagram of the structure of a clamping and fixing unit of a steel pipe water pressure test fixture proposed by the present invention;

[0026] Figure 4 A schematic diagram of the internal structure of a steel pipe water pressure test fixture proposed by the present invention;

[0027] Figure 5 This is a left-side structural schematic diagram of a steel pipe water pressure test fixture proposed by the present invention.

[0028] Figure 6 The present invention provides a schematic diagram of the process steps of a method for using a steel pipe water pressure testing fixture.

[0029] Description of the drawings: 100 main frame unit, 101 square frame, 102 first fixed plate, 103 first sliding plate, 104 support plate, 105 support seat, 106 fixed cylinder, 107 hose, 108 nozzle, 109 first hydraulic telescopic rod, 110 baffle, 111 rubber block, 200 clamping and fixing unit, 201 support frame, 202 fixed seat, 203 fixed block, 204 sliding block, 205 connecting plate, 206 elliptical opening, 207 driving motor, 208 gear, 209 rack, 210 first rotating wheel, 211 second fixed plate, 212 second rotating wheel, 213 loading rack, 214 support platform, 215 tilting plate, 216 second sliding plate, 217 second hydraulic telescopic rod, 218 third fixed plate. DETAILED DESCRIPTION

[0030] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.

[0031] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0032] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.

[0033] Secondly, the present invention is described in detail with reference to the schematic diagram. When describing the embodiments of the present invention in detail, for the sake of convenience, the cross-sectional diagrams showing the device structure will not be partially enlarged according to the general scale, and the schematic diagrams are only examples, which should not limit the scope of protection of the present invention. In addition, in actual production, the three-dimensional dimensions of length, width and depth should be included.

[0034] Example

[0035] Reference Figure 1 - Figure 6 , as an embodiment of the present invention, provides a steel pipe water pressure testing fixture, including a main frame unit 100 and a clamping and fixing unit 200.

[0036] The main frame unit 100 includes a square frame 101 and first fixed plates 102 symmetrically fixedly connected to the upper ends of both sides of the square frame 101, a baffle 110 is fixedly connected to each first fixed plate 102 at one end away from the square frame 101, a plurality of evenly distributed second sliding plates 216 are slidably connected to the square frame 101, and a plurality of semicircular grooves are fixedly opened on each second sliding plate 216, a first sliding plate 103 is slidably connected to each first fixed plate 102, a support plate 104 is fixedly connected to the upper end of the first sliding plate 103, a support seat 105 is fixedly connected to the support plate 104, a plurality of evenly distributed circular openings are fixedly opened on the support seat 105, a fixed cylinder 106 is fixedly connected to each circular opening, and a hose 107 is fixedly connected to the fixed cylinder 106 at one side away from the square frame 101;

[0037] A nozzle 108 is fixedly connected to the fixed cylinder 106 on the side away from the hose 107, and a rubber block 111 is fixedly connected to the nozzle 108. The rubber block 111 is set in a circular shape, and the diameter of the inner wall of the steel pipe matches the diameter of the rubber block 111. The square frame 101 is fixedly connected to both sides close to the first fixed plate 102, and the upper end of each first hydraulic telescopic rod 109 is fixedly connected to the first sliding plate 103. A loading rack 213 is fixedly connected to the side of the square frame 101 away from the support frame 201. The loading rack 213 is made of manganese steel material, and a supporting platform 214 is fixedly connected to the loading rack 213, and an inclined plate 215 is fixedly connected to the loading rack 213;

[0038] The clamping and fixing unit 200 includes a plurality of support frames 201 uniformly fixedly connected to the inner upper end of the square frame 101, each support frame 201 is slidably connected to a fixed seat 202, a plurality of second hydraulic telescopic rods 217 are fixedly connected to the inner upper end of the square frame 101, a third fixed plate 218 is fixedly connected to the upper end of each second hydraulic telescopic rod 217, the third fixed plate 218 is fixedly connected to the bottom of the fixed seat 202, a plurality of uniformly distributed fixed blocks 203 are fixedly connected to one side of the upper end of the fixed seat 202, a plurality of sliding blocks 204 are slidably connected to the side of the upper end of the fixed seat 202 away from the fixed block 203, each fixed block 203 and the sliding block 204 are fixedly provided with a V-shaped groove, the grooves provided on the fixed block 203 and the sliding block 204 are arranged oppositely, a connecting plate 205 is fixedly connected to the bottom of the sliding block 204, the connecting plate 205 is slidably connected to the fixed seat 202, a rack 209 is fixedly connected to the bottom of the elliptical opening 206, and the rack 209 is meshed with the gear 208;

[0039] An elliptical opening 206 is fixedly opened on the connecting plate 205, a square opening is fixedly opened in the fixing seat 202, a driving motor 207 is fixedly connected to the square opening, a gear 208 is fixedly connected to the output shaft of the driving motor 207, first rotating wheels 210 are symmetrically fixedly connected to both ends of each fixing seat 202, each first rotating wheel 210 is slidably connected to the support frame 201, a second fixing plate 211 is fixedly connected to the center of one side of the fixing seat 202 near the support frame 201, a plurality of evenly distributed second rotating wheels 212 are fixedly connected to the second fixing plate 211, and each second rotating wheel 212 is slidably connected to the support frame 201.

[0040] A method for using a steel pipe water pressure test is applicable to any of the above test fixtures, and the method comprises the following steps:

[0041] S1: placing the steel pipes to be subjected to the water pressure test on the loading rack 213, and allowing the plurality of steel pipes to fall onto the second sliding plate 216 by means of the tilting plate 215;

[0042] S2: The fixing seat 202 fixedly connected to the upper end of the second hydraulic telescopic rod 217 is moved upward by the second hydraulic telescopic rod 217, and the output shaft of the driving motor 207 is rotated to rotate the gear 208, so that the connecting plate 205 slides, and the sliding block 204 fixedly connected to the connecting plate 205 moves, so as to clamp the steel pipe;

[0043] S3: Water flows into the steel pipe through the hose 107 and the nozzle 108, so as to perform a water pressure test on the steel pipe.

[0044] During use, the steel pipe is dropped into the semicircular groove on the second sliding plate 216 through the inclined plate 215 on the loading rack 213, and then the second hydraulic telescopic rod 217 is started. The upper end of the second hydraulic telescopic rod 217 is extended, so that the fixing seat 202 fixedly connected to the upper end of the second hydraulic telescopic rod 217 moves upward, and then the output shaft of the driving motor 207 is rotated, so that the gear 208 fixedly connected to the output shaft of the driving motor 207 is rotated, and because the gear 208 is meshed with the rack 209, the connecting plate 205 is moved, so that the sliding block 204 fixedly connected to the upper end of the connecting plate 205 is moved, so that the steel pipe can be clamped through the fixed block 203 and the sliding block 204;

[0045] Then start the first hydraulic telescopic rod 109, and move the upper end of the first hydraulic telescopic rod 109 to move the first sliding plate 103, so that the support seat 105 fixedly connected to the first sliding plate 103 moves, so that the nozzle 108 fixedly connected to the support seat 105 is fixedly connected to the inner wall of the steel pipe, so that the steel pipe water pressure test fixture can fix and clamp the steel pipe, preventing the occurrence of inaccurate positioning of the steel pipe during the installation process, and the steel pipe water pressure test fixture can test multiple steel pipes at the same time, thereby improving the working efficiency of the steel pipe water pressure test fixture.

[0046] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.

Claims

1. A steel pipe water pressure test fixture, It is characterized in that include: The main frame unit (100) comprises a square frame (101) and first fixed plates (102) symmetrically fixedly connected to the upper ends of both sides of the square frame (101), each of the first fixed plates (102) being slidably connected to a first sliding plate (103), the upper end of the first sliding plate (103) being fixedly connected to a support plate (104), the support plate (104) being fixedly connected to a support seat (105), the support seat (105) being fixedly provided with a plurality of evenly distributed circular openings, each of which is The circular opening is fixedly connected to a fixed cylinder (106), a side of the fixed cylinder (106) away from the square frame (101) is fixedly connected to a hose (107), a side of the fixed cylinder (106) away from the hose (107) is fixedly connected to a nozzle (108), and both sides of the square frame (101) close to the first fixed plate (102) are fixedly connected to first hydraulic telescopic rods (109), and the upper end of each of the first hydraulic telescopic rods (109) is fixedly connected to the first sliding plate (103); The clamping and fixing unit (200) comprises a plurality of support frames (201) uniformly fixedly connected to the upper end of a square frame (101), each of the support frames (201) being slidably connected to a fixing seat (202), a plurality of uniformly distributed fixing blocks (203) being fixedly connected to one side of the upper end of the fixing seat (202), a plurality of sliding blocks (204) being slidably connected to the side of the upper end of the fixing seat (202) away from the fixing block (203), a connecting plate (205) being fixedly connected to the bottom of the sliding block (204), an elliptical opening (206) being fixedly opened on the connecting plate (205), and a square opening (206) being fixedly opened in the fixing seat (202). An opening is provided, wherein a driving motor (207) is fixedly connected to the square opening, an output shaft of the driving motor (207) is fixedly connected to a gear (208), both ends of each of the fixing seats (202) are symmetrically fixedly connected to first rotating wheels (210), each of the first rotating wheels (210) is slidably connected to the support frame (201), a second fixing plate (211) is fixedly connected to the center of one side of the support frame (201) on the fixing seat (202), a plurality of evenly distributed second rotating wheels (212) are fixedly connected to the second fixing plate (211), and each of the second rotating wheels (212) is slidably connected to the support frame (201).

2. A steel pipe water pressure test fixture according to claim 1, Features: A loading rack (213) is fixedly connected to the side of the square frame (101) away from the support frame (201); the loading rack (213) is made of manganese steel material; a supporting platform (214) is fixedly connected to the loading rack (213); and an inclined plate (215) is fixedly connected to the loading rack (213).

3. A steel pipe water pressure test fixture according to claim 1, Features: Each of the fixed block (203) and the sliding block (204) is fixedly provided with a V-shaped groove, and the grooves provided on the fixed block (203) and the sliding block (204) are arranged relative to each other.

4. A steel pipe water pressure test fixture according to claim 1, Features: The connecting plate (205) is slidably connected to the fixing seat (202); a rack (209) is fixedly connected to the bottom of the elliptical opening (206); and the rack (209) is meshed with the gear (208).

5. A steel pipe water pressure test fixture according to claim 1, Features: A rubber block (111) is fixedly connected to the nozzle (108), and the rubber block (111) is arranged in a circular ring shape. The diameter of the inner wall of the steel pipe matches the diameter of the rubber block (111).

6. A steel pipe water pressure test fixture according to claim 1, Features: A baffle (110) is fixedly connected to one end of each of the first fixed plates (102) away from the square frame (101), a plurality of evenly distributed second sliding plates (216) are slidably connected to the square frame (101), and a plurality of semicircular grooves are fixedly opened on each of the second sliding plates (216).

7. A steel pipe water pressure test fixture according to claim 1, Features: A plurality of second hydraulic telescopic rods (217) are fixedly connected to the upper end of the square frame (101), and a third fixing plate (218) is fixedly connected to the upper end of each second hydraulic telescopic rod (217), and the third fixing plate (218) is fixedly connected to the bottom of the fixing seat (202).

8. A method for using a steel pipe water pressure test, Features: The method of use is applicable to any one of the test fixtures in claims 1 to 7 above, and the method of use comprises the following steps: S1: placing steel pipes to be subjected to a water pressure test on a loading rack (213), and allowing a plurality of steel pipes to fall onto a second sliding plate (216) by means of an inclined plate (215); S2: The fixing seat (202) fixedly connected to the upper end of the second hydraulic telescopic rod (217) is moved upward by the second hydraulic telescopic rod (217), and the output shaft of the driving motor (207) is rotated to rotate the gear (208), thereby causing the connecting plate (205) to slide, thereby causing the sliding block (204) fixedly connected to the connecting plate (205) to move, thereby achieving clamping of the steel pipe; S3: Water is flowed into the steel pipe through the hose (107) and the nozzle (108), thereby performing a water pressure test on the steel pipe.

Citation Information

Cited By

  • Proportional valve leakage testing device based on adaptive pressure regulation technology

    CN119509853A