Boost and capacity increasing method and power transmission tower
By installing composite cross-load components on the original transmission tower, boosting and capacity increase, the problems of long construction cycles and tight land resources in the traditional method are solved, and efficient and low-cost transmission tower boosting and capacity increase are achieved, which improves the transmission efficiency and Resistance ability.
Patent Information
- Application Number
- CN202411097857.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-11-19
AI Technical Summary
When existing transmission lines face load growth, traditional boost capacity enhancement methods require demolition and reconstruction of transmission lines, resulting in long construction cycles, high costs and tight land resources.
By obtaining the design information of the original transmission tower, analyzing and calculating and generating the modified design input conditions, designing composite cross-load components, adjusting their structure to increase the voltage and increase capacity on the basis of the original tower, omitting the overhanging insulator string, and raising the height of the wire hanging point , reduce the width of the corridor.
It has achieved step-up and capacity increase without dismantling the original transmission line, reduced construction cycle and cost, improved transmission efficiency and anti-fouling, wind and lightning resistance, and reduced operation and maintenance workload and cost.
Smart Images

Figure CN118981853A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of electric power transmission, and in particular to a method for increasing voltage and capacity and a transmission tower. Background Art
[0002] Transmission towers are pole-shaped or tower-shaped structures that support overhead transmission line conductors and overhead ground wires, and keep a certain distance between the transmission line conductors and the ground wires, and between the transmission line conductors and the ground wires and the earth. With the development of the economy, the regional load has increased year by year, and the original traditional transmission lines can no longer meet the growing demand of existing user loads. To solve this problem, it is necessary to increase the transmission capacity of the transmission lines.
[0003] At present, the common way to increase capacity is to dismantle the original transmission line and rebuild a new transmission line with a higher voltage level. This method has the problems of long construction period and high cost. At the same time, as the voltage level of the transmission line increases, the width of the corridor becomes wider, which inevitably requires additional land acquisition. For areas with limited land resources, it is difficult to implement and the land acquisition cost is high.
[0004] Therefore, a new method of voltage increase and capacity increase is urgently needed. The original transmission lines are retained, and the voltage of the original towers is increased based on the original transmission towers. Composite crossarms are used to eliminate the suspended insulator strings and raise the height of the conductor hanging points. Compared with the construction of new transmission lines with higher voltage levels, not only the corridor width is reduced, but the effective transmission efficiency can also be improved. Summary of the invention
[0005] Based on this, it is necessary to provide a method for increasing voltage and capacity and a transmission tower to address the technical problems mentioned above.
[0006] The present application provides a method for increasing voltage and capacity, comprising: obtaining original design information of an original transmission tower to be modified, obtaining the voltage level and transmission capacity of the modified transmission tower after the voltage is increased; performing analysis and calculation based on the original design information, the voltage level and the transmission capacity, and generating design input conditions for the modified transmission tower; performing electrical design and structural design of the modified transmission tower based on the design input conditions, determining the design of a composite cross-arm assembly and performing matching connection design between the composite cross-arm assembly and the original transmission tower, adjusting the design of the composite cross-arm assembly, and obtaining final design parameters of the modified transmission tower; designing a construction plan based on the final design parameters, and preparing the composite cross-arm assembly; performing construction according to the construction plan, hanging the conductor on the composite cross-arm assembly, and obtaining the modified transmission tower.
[0007] Among them, the construction plan includes: shutting down the original transmission tower; temporarily suspending or removing the conductors and ground wires hanging on the original transmission tower; removing the original crossarm of the original transmission tower; modifying the tower head of the original transmission tower; suspending the composite crossarm assembly and installing it to the tower head; suspending the conductors hanging on the original transmission tower to the composite crossarm assembly, and suspending the ground wires hanging on the original transmission tower to the tower head, or, installing new conductors on the composite crossarm assembly and installing new ground wires on the tower head.
[0008] Among them, after the conductors and ground wires suspended on the original transmission tower are temporarily suspended or removed, and before the composite cross-arm assembly is suspended, a temporary reinforcement device is installed on the tower head; after the composite cross-arm assembly is suspended and installed on the tower head, the temporary reinforcement device is removed.
[0009] Among them, the construction plan includes: shutting down the original transmission tower; temporarily suspending or removing the conductors and ground wires hanging on the original transmission tower; separating the tower head and the tower body of the original transmission tower, transporting the tower head to the ground and removing the original crossarm of the original transmission tower; installing a composite crossarm assembly on the tower head; suspending the tower head and the composite crossarm assembly and installing them to the tower body; suspending the conductors hanging on the original transmission tower to the composite crossarm assembly, and suspending the ground wires hanging on the original transmission tower to the tower head, or, installing new conductors on the composite crossarm assembly and installing a new ground wire on the tower head.
[0010] Among them, the conductors suspended on the original transmission tower are hung on the composite cross-arm assembly, and the ground wires suspended on the original transmission tower are hung on the tower head, or new conductors are installed on the composite cross-arm assembly. Before installing the new ground wire on the tower head, it also includes: dismantling the original ground wire bracket of the original transmission tower and installing a new ground wire bracket on the tower head.
[0011] Among them, the hanging height of the conductor on the composite cross-arm assembly is higher than the hanging height of the conductor on the original transmission tower.
[0012] Among them, the modification of the tower head of the original transmission tower includes: providing at least one of a mounting hole, a mounting plate, and a truss on the tower head.
[0013] The suspension adopts a suspension mechanism, and the suspension mechanism includes at least one of a drone, a crane, a helicopter, or a pulley block.
[0014] Among them, the installation height of the composite cross arm assembly is higher than the height of the original cross arm, and the height of the new ground wire bracket is higher than the height of the original ground wire bracket.
[0015] Among them, the original design information includes the tower diagram of the original transmission tower, conductor type, ground wire type, line cross-section diagram, and design meteorological conditions.
[0016] Among them, the design input conditions include tower head layout, transmission tower load, conductor-to-ground distance, vertical line distance, conductor-to-ground electrical distance, conductor sag, conductor load, and electromagnetic parameters; the final design parameters include corridor width, transmission capacity, and component structure dimensions.
[0017] The present application also provides a transmission tower, which is transformed by using any of the above-mentioned voltage-boosting and capacity-increasing methods for voltage-boosting and capacity-increasing. The transmission tower includes a main tower structure, which defines a reference horizontal plane, which is used to maintain a parallel setting with the earth's horizontal plane; the main tower structure includes a tower body and a tower head, the tower head includes a first curved arm and a second curved arm, the first curved arm and the second curved arm are arranged at the top of the tower body, and the space between the first curved arm and the second curved arm is used to form a middle phase assembly space, and the middle phase assembly space has a top space opening; a composite cross-arm assembly, the composite cross-arm assembly is arranged at the tower head, the composite cross-arm assembly includes a middle phase composite cross-arm and two side phase composite cross-arms; wherein the middle phase composite cross-arm is arranged in the middle phase assembly space, the two side phase composite cross-arms are respectively arranged on the first curved arm and the second curved arm of the tower head, and the two side phase composite cross-arms are both located outside the middle phase assembly space; a hanging wire assembly, the hanging wire assembly is used to connect the conductor, the number of the hanging wire assemblies is configured to be at least three, the middle phase composite cross-arm is provided with at least one hanging wire assembly, and each side phase composite cross-arm is provided with at least one hanging wire assembly.
[0018] Among them, the middle-phase composite cross-arm includes a plurality of first oblique-stayed insulating rods and a plurality of first pillar insulating rods, one ends of all the first oblique-stayed insulating rods are respectively connected to different positions of the first curved arm and the second curved arm, and all the first oblique-stayed insulating rods have an angle with the reference horizontal plane, one ends of all the first pillar insulating rods are respectively connected to different positions of the first curved arm and the second curved arm, and all the first pillar insulating rods have an angle with the reference horizontal plane, the other ends of all the first oblique-stayed insulating rods and the other ends of all the first pillar insulating rods are connected to form a middle-phase node in the middle-phase assembly space, and the middle-phase node is provided with at least one hanging wire assembly.
[0019] Wherein, each side phase composite cross arm comprises a plurality of second oblique-stayed insulating rods and a plurality of second supporting insulating rods, one ends of all the second oblique-stayed insulating rods in each side phase composite cross arm are respectively connected to different positions of the tower head, and all the second oblique-stayed insulating rods in each side phase composite cross arm have an angle with the reference horizontal plane, one ends of all the second supporting insulating rods in each side phase composite cross arm are respectively connected to different positions of the tower head, and all the second supporting insulating rods in each side phase composite cross arm have an angle with the reference horizontal plane, the other ends of all the second oblique-stayed insulating rods in each side phase composite cross arm and the other ends of all the second supporting insulating rods are connected to form a side phase node outside the middle phase assembly space, and the side phase node is provided with at least one hanging wire assembly.
[0020] Among them, the wire hanging assembly includes: a connecting hardware, one end of which is connected to the middle phase node; a wire support, which is connected to the other end of the connecting hardware, wherein the wire support has a supporting inner cavity inside, and the supporting inner cavity is used to pass the wire.
[0021] In the above-mentioned voltage increase and capacity increase method, the transmission capacity of the transmission line is increased by modifying the traditional transmission tower, removing the original cross arm structure of the original transmission tower to be modified, such as iron cross arm, steel cross arm, etc., and installing a new composite cross arm assembly to increase the electrical clearance to meet the voltage increase and capacity increase requirements. The voltage increase and capacity increase method provided in this application has the following technical effects: (1) Using composite cross arm assemblies for voltage increase and capacity increase, omitting the suspended insulator string, raising the wire hanging height, reducing wind swing, and increasing the voltage without changing the tower; (2) Increasing the transmission voltage can reduce line loss and improve the effective transmission efficiency; (3) In the working condition where the corridor is limited and the voltage needs to be increased, the composite cross arm assembly has low economic cost, high transformation efficiency, and is very competitive; (4) After the voltage increase and capacity increase, the transmission tower has significantly improved the ability to resist pollution, wind, and lightning; (5) The removal of traditional insulators can greatly reduce the workload and cost of later operation and maintenance. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 A schematic diagram of the plan structure of a transmission tower provided in one embodiment of the present application.
[0023] Figure 2 A schematic diagram of the three-dimensional structure of a transmission tower provided in one embodiment of the present application.
[0024] Figure 3 A schematic diagram of the structure of a tower head and a ground wire bracket provided in one embodiment of the present application.
[0025] Figure 4 A schematic diagram of the partial assembly structure of a first oblique-stayed insulating rod, a first support insulating rod and a middle-phase connecting assembly provided for one embodiment of the present application.
[0026] Figure 5 A schematic diagram of the partial assembly structure of a second oblique-stayed insulating rod, a second support insulating rod and an edge-connecting component located on one side provided for one embodiment of the present application.
[0027] Figure 6 A schematic diagram of the partial assembly structure of a second oblique-stayed insulating rod, a second support insulating rod and an edge-phase connecting component located on the other side provided for one embodiment of the present application.
[0028] Figure 7 A schematic structural diagram of a transmission tower with a shielding ring provided in one embodiment of the present application.
[0029] Figure 8 For Figure 7Schematic diagram of the three-dimensional structure of the transmission tower shown.
[0030] Fig. 9 A schematic structural diagram of a transmission tower with a shielding ring provided in accordance with another embodiment of the present application.
[0031] Fig.10 For Fig. 9 Schematic diagram of the three-dimensional structure of the transmission tower shown.
[0032] Fig.11 It is a schematic diagram of the planar structure of a wine glass tower in the prior art. DETAILED DESCRIPTION
[0033] In order to make the above-mentioned purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present application. However, the present application can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present application, so the present application is not limited by the specific embodiments disclosed below. If these terms "first" and "second" appear, these terms are only used for descriptive purposes and cannot be understood as indicating or implying relative importance or implicitly indicating the number of indicated technical features.
[0034] The voltage-boosting and capacity-increasing method of the present application is used to transform the traditional transmission tower to increase the transmission capacity of the transmission line, dismantle the original crossarm structure of the original transmission tower to be transformed, such as iron crossarms, steel crossarms, etc., and install new composite crossarm assemblies to increase the electrical clearance to meet the voltage-boosting and capacity-increasing requirements. The composite crossarm assembly is assembled from insulating composite materials and metal joints, and the structure and main material specifications can be flexibly adjusted according to the actual design load. It is not only insulated itself, but also has good mechanical properties. After the voltage-boosting and capacity-increasing of the traditional transmission tower, the traditional suspension insulator string can be omitted, and the conductor is suspended on the composite crossarm assembly through a shorter hanging wire fitting, which raises the conductor hanging height, reduces the wind deviation amplitude, can increase the insulation distance between the conductive part and the tower body, release the safety gap, and can ensure that the length of the composite crossarm assembly is the same or similar to the length of the original crossarm before and after the transformation, meeting the voltage-boosting and capacity-increasing requirements within a certain range. Furthermore, there is no need to dismantle the original transmission line and build a new higher voltage level transmission line, so the original tower can be boosted, which requires less material, short construction period, low cost, and low construction cost. There is no need for large-scale land acquisition, which solves the corridor problem and reduces land acquisition costs. After the voltage is boosted, the transmission capacity is increased to meet the rapidly growing load requirements. For the sake of ease of description, this article refers to the traditional transmission tower before voltage boosting and capacity increase as the original transmission tower to be modified, and the transmission tower after voltage boosting and capacity increase as the modified transmission tower. Taking the traditional wine glass tower as the original transmission tower to be modified as an example, the voltage boosting and capacity increase method of this application can be used to Fig.11The original transmission tower shown in the figure was transformed into Figures 1 to 6 Transmission tower shown after modification. Figures 1 to 6 As shown, the modified transmission tower after voltage increase and capacity increase includes a main tower structure 1000, a composite cross arm assembly 2000 and a hanging wire assembly 3000. Among them, the main tower structure 1000 may be limited to a reference horizontal plane 1000a, which is a constructed virtual plane and does not actually exist. It is only used as an auxiliary reference when describing the relationship between the main tower structure 1000 and the ground. For example, when the modified transmission tower is installed on the ground, the reference horizontal plane 1000a of the main tower structure 1000 is ensured to be parallel to the earth's horizontal plane, that is, the modified transmission tower is installed vertically relative to the ground. In addition, the reference horizontal plane 1000a is also used to determine the angle and direction of the composite cross arm assembly 2000 set on the main tower structure 1000, which can be seen below.
[0035] like Figure 1 As shown, the main tower structure 1000 includes a tower body 1100 and a tower head 1200. The tower body 1100 is the basic structure of the entire modified transmission tower, which is used for installation in direct contact with the ground and serves as the installation foundation of the entire modified transmission tower. The tower head 1200 is set on the tower body 1100 and is mainly used to set the composite cross arm assembly 2000, the ground wire bracket 4000, the conductor 100 and the ground wire, etc. Figures 1 to 3 As shown, the tower head 1200 includes a first curved arm 1210 and a second curved arm 1220, and the first curved arm 1210 and the second curved arm 1220 are arranged at the top of the tower body 1100, and the first curved arm 1210 and the second curved arm 1220 are arranged in a left-right symmetrical manner. At this time, the space enclosed between the first curved arm 1210 and the second curved arm 1220 can be used to form a middle phase assembly space 1000b.
[0036] Since the bottoms of the first curved arm 1210 and the second curved arm 1220 are connected to the tower body 1100, and the tops of the first curved arm 1210 and the second curved arm 1220 are not connected to each other, the middle phase assembly space 1000b formed between the first curved arm 1210 and the second curved arm 1220 has a top space opening 1000c facing upward, so that the first curved arm 1210 and the second curved arm 1220 form a structure similar to a "U" shape with the tower body 1100. Moreover, the first curved arm 1210 and the second curved arm 1220 can both include an upper curved arm and a lower curved arm connected up and down. Taking the first curved arm 1210 as an example, the lower curved arm is used to be arranged at the top of the tower body 1100 and connected to the tower body 1100, while the upper curved arm is located at the top of the lower curved arm and is used to be connected to the ground wire bracket 4000. The second curved arm 1220 is similarly not described in detail.
[0037] Continue reading Figure 3As shown, the composite cross arm assembly 2000 is arranged at the tower head 1200, and the composite cross arm assembly 2000 is used to connect the conductor 100 at the tower head 1200, and the conductor 100 includes the conductor 100 of the middle phase and the conductor 100 of the side phase. Therefore, the composite cross arm assembly 2000 may include a middle phase composite cross arm 2100 and two side phase composite cross arms 2200, wherein the middle phase composite cross arm 2100 is arranged in the middle phase assembly space 1000b of the main tower structure 1000, so that the middle phase composite cross arm 2100 can be used to connect the conductor 100 of the middle phase in the middle phase assembly space 1000b, and the two side phase composite cross arms 2200 can be arranged on the left and right sides of the tower head 1200, and are used to connect the conductor 100 of the side phase on the left and right sides of the tower head 1200 (i.e., the outside of the middle phase assembly space 1000b).
[0038] like Figure 3 As shown, the middle phase composite cross arm 2100 includes a plurality of first inclined insulating rods 2110 and a plurality of first support insulating rods 2120, one end of all the first inclined insulating rods 2110 are respectively connected to different positions of the first curved arm 1210 and the second curved arm 1220, and all the first inclined insulating rods 2110 have an angle with the reference horizontal plane 1000a, for example, Figure 3 In the embodiment, one end of all first inclined insulating rods 2110 facing the left and right sides is symmetrically connected to the first curved arm 1210 and the second curved arm 1220, and the connection positions of all first inclined insulating rods 2110 on the first curved arm 1210 or the second curved arm 1220 are also symmetrically arranged. Similarly, one end of all first supporting insulating rods 2120 is respectively connected to different positions of the first curved arm 1210 and the second curved arm 1220, and all first supporting insulating rods 2120 have an angle with the reference horizontal plane 1000a, for example, Figure 3 In the figure, one end of all first pillar insulating rods 2120 facing the left and right sides is symmetrically connected to the first curved arm 1210 and the second curved arm 1220, and the connection positions of all first pillar insulating rods 2120 on the first curved arm 1210 or the second curved arm 1220 are also symmetrically arranged on the left and right sides.
[0039] Moreover, after one end of all the first inclined insulating rods 2110 and all the first pillar insulating rods 2120 are connected at the first curved arm 1210 and the second curved arm 1220, the other ends of all the first inclined insulating rods 2110 and the other ends of all the first pillar insulating rods 2120 are also connected to form a middle phase node in the middle phase assembly space 1000b. In one embodiment, in the direction from the middle phase node to the first curved arm 1210 or the second curved arm 1220, the height of the plurality of first inclined insulating rods 2110 gradually increases, and in the direction from the middle phase node to the first curved arm 1210 or the second curved arm 1220, the height of the plurality of first pillar insulating rods 2120 gradually decreases, thereby forming a structure as shown in FIG. Figure 3 The mid-phase composite crossarm 2100 is shown in FIG.
[0040] like Figure 3 As shown, in one embodiment, the middle phase composite cross arm 2100 includes a middle phase connecting component 2130, and the middle phase connecting component 2130 is used to form a middle phase node. Figure 4 As shown, the middle phase connection assembly 2130 includes a middle phase node hardware 2131, a plurality of first inclined rod end hardware 2111 and a plurality of first pillar rod end hardware 2121, one end of the first inclined rod end hardware 2111 is detachably connected to the middle phase node hardware 2131, the other end of each first inclined rod end hardware 2111 is connected to the end of a first inclined insulating rod 2110, one end of the first pillar rod end hardware 2121 is detachably connected to the middle phase node hardware 2131, and the other end of each first pillar rod end hardware 2121 is connected to the end of a first pillar insulating rod 2120. In addition, those skilled in the art can also realize the connection between the middle phase connection assembly 2130 and the first inclined insulating rod 2110 and the first pillar insulating rod 2120 through other detachable methods according to actual needs, which is not limited here.
[0041] The number of hanging wire assemblies 3000 is configured to be at least three, and the hanging wire assemblies 3000 are used to connect the conductor 100. At this time, the middle phase node of the middle phase composite cross arm 2100 is provided with at least one hanging wire assembly 3000, and after the middle phase conductor 100 is connected to the hanging wire assembly 3000 on the middle phase composite cross arm 2100, the hanging wire assembly 3000 has a lower droop height relative to the middle phase node, and the conductor 100 is also lower than the middle phase node.
[0042] Therefore, compared to Fig.11In the original transmission tower shown in the figure, in the modified transmission tower after voltage increase and capacity increase, the hanging wire assembly 3000 can be designed to be shorter according to the requirements. The shorter hanging wire assembly 3000 can make the relative distance between the middle phase conductor 100 and the middle phase node closer, increase the distance between the middle phase conductor 100 and the ground, and meet the requirement of increasing the ground clearance value of the conductor 100 after voltage increase. Moreover, the wind deflection has a small effect on the length of the middle phase composite cross arm 2100, so that the clearance between the conductor 100 and the main tower structure 100 after voltage increase still meets the requirements.
[0043] A plurality of first inclined insulating rods 2110 and a plurality of first supporting insulating rods 2120 are connected as a middle phase node, which can meet the electrical clearance after voltage boosting. The conductor 100 is connected to the middle phase node through a hanging wire assembly 3000, which also lifts the conductor 100 of the middle phase, and can also meet the requirement for increased ground clearance of the conductor 100 after voltage boosting.
[0044] Therefore, in the structural design of the above-mentioned middle-phase composite crossarm 2100 of the modified transmission tower, the middle-phase composite crossarm 2100 can adjust and control the height of the middle-phase node formed in the middle-phase composite crossarm 2100 relative to the ground by adjusting the connection positions of all the first inclined insulating rods 2110 and all the first pillar insulating rods 2120 on the first curved arm 1210 and the second curved arm 1220, and at the same time adaptively adjusting the angles of all the first inclined insulating rods 2110 and all the first pillar insulating rods 2120 relative to the reference horizontal plane 1000a, and adaptively adjusting the hanging length of the hanging wire assembly 3000 to adjust the height of the middle-phase conductor 100 relative to the ground.
[0045] Based on the structural design of the middle phase composite cross arm 2100, the original cross arm structure can be replaced on the original transmission tower. Figures 1 to 3 The modified middle phase composite cross arm 2100 shown in the figure adjusts the height of the middle phase conductor 100, so that the conductor 100 can be increased without dismantling the original main tower structure 1000, thereby achieving the transformation of increasing voltage and capacity. Figure 1 and Fig.11 As shown, in one embodiment, the main tower structure of the original transmission tower and the main tower structure 1000 of the modified transmission tower after voltage boosting and capacity increase are the same structure, including the slight differences in the height and size of the tower body 1100, the tower head 1200 and the ground wire support 4000, which are all identified as the same structure of the main tower structure 1000, and therefore the same reference numerals are used for ease of description.
[0046] Continue reading Figure 3As shown, two side phase composite cross arms 2200 are respectively arranged on the first curved arm 1210 and the second curved arm 1220 of the tower head 1200, and the two side phase composite cross arms 2200 are both located outside the middle phase assembly space 1000b. Each side phase composite cross arm 2200 includes a plurality of second inclined insulating rods 2210 and a plurality of second supporting insulating rods 2220, one end of all the second inclined insulating rods 2210 in each side phase composite cross arm 2200 is respectively connected to different positions of the tower head 1200, and all the second inclined insulating rods 2210 in each side phase composite cross arm 2200 have an angle with the reference horizontal plane 1000a. At the same time, one end of all the second supporting insulating rods 2220 in each side phase composite cross arm 2200 is respectively connected to different positions of the tower head 1200, and all the second supporting insulating rods 2220 in each side phase composite cross arm 2200 have an angle with the reference horizontal plane 1000a.
[0047] The other ends of all the second inclined insulating rods 2210 and the other ends of all the second supporting insulating rods 2220 in each side phase composite cross arm 2200 are connected to form a side phase node outside the middle phase assembly space, for example Figure 3 As shown, the two side-phase composite crossarms 2200 located on the left and right sides of the tower head 1200 each construct a side-phase node on the left and right sides of the tower head 1200, and a hanging wire assembly 3000 is provided at the side-phase nodes of the two side-phase composite crossarms 2200. The hanging wire assembly 3000 is consistent with the hanging wire assembly 3000 provided on the middle-phase composite crossarm 2100. After the side-phase conductor 100 is connected to the hanging wire assembly 3000 on the side-phase composite crossarm 2200, the conductor 100 can be made lower than the side-phase node due to the lower drooping height of the hanging wire assembly 3000 relative to the side-phase node.
[0048] In one embodiment, in the direction from the edge phase node to the first curved arm 1210 or the second curved arm 1220, the height of the plurality of second inclined insulating rods 2210 gradually increases, and in the direction from the edge phase node to the first curved arm 1210 or the second curved arm 1220, the height of the plurality of second supporting insulating rods 2220 gradually decreases, thereby forming a Figure 3 The two side composite cross arms 2200 shown in FIG.
[0049] like Figure 3 As shown, in one embodiment, the side phase composite cross arm 2200 includes a side phase connection component 2230, and the side phase connection component 2230 is used to form a side phase node. Figure 5As shown, the side phase connection assembly 2230 includes a side phase node hardware 2231, a plurality of second inclined tie rod end hardware 2211 and a plurality of second support rod end hardware 2221, one end of the second inclined tie rod end hardware 2211 is detachably connected to the side phase node hardware 2231, the other end of each second inclined tie rod end hardware 2211 is connected to the end of a second inclined insulating rod 2210, one end of the second support rod end hardware 2221 is detachably connected to the side phase node hardware 2231, and the other end of each second support rod end hardware 2221 is connected to the end of a second support insulating rod 2220. In addition, those skilled in the art can also realize the connection between the side phase connection assembly 2230 and the second inclined insulating rod 2210 and the second support insulating rod 2220 through other detachable methods according to actual needs, which is not limited here.
[0050] For the same reason, the hanging wire assembly 3000 set on the side phase composite cross arm 2200 can also be designed to be shorter according to the requirements. The shorter hanging wire assembly 3000 can make the relative distance between the side phase conductor 100 and the side phase node closer, increase the distance between the side phase conductor 100 and the ground, and meet the requirement of increasing the ground clearance of the conductor 100 after boosting. Moreover, the smaller influence of the wind deviation on the length of the side phase composite cross arm 2200 makes the clearance between the conductor 100 and the main tower structure 100 after boosting still meet the requirements. Multiple second inclined insulating rods 2210 and multiple second support insulating rods 2220 are used to connect as the side phase node, which can meet the electrical clearance after boosting. The conductor 100 is connected to the side phase node through the hanging wire assembly 3000, which also raises the side phase conductor 100, and can also meet the requirement of increasing the ground clearance of the conductor 100 after boosting.
[0051] Therefore, in the structural design of the above-mentioned side-phase composite crossarm 2200 of the modified transmission tower, the side-phase composite crossarm 2200 can adjust and control the height of the side-phase node formed in the side-phase composite crossarm 2200 relative to the ground by adjusting the connection positions of all the second inclined insulating rods 2210 and all the second supporting insulating rods 2220 on the first curved arm 1210 and the second curved arm 1220, and at the same time adaptively adjusting the angles of all the second inclined insulating rods 2210 and all the second supporting insulating rods 2220 relative to the reference horizontal plane 1000a, and adaptively adjusting the hanging length of the hanging wire assembly 3000 to adjust the height of the side phase conductor 100 relative to the ground.
[0052] Based on the structural design of the side phase composite cross arm 2200, the original cross arm structure can be replaced on the main tower structure 1000 of the original transmission tower. Figures 1 to 3The modified side phase composite cross arm 2200 shown in the figure adjusts the height of the side phase conductor 100, so that the conductor 100 of the side phase can be raised without dismantling the original main tower structure 1000, thereby realizing the transformation of boosting voltage and increasing capacity.
[0053] Continue reading Figure 4 In one embodiment, the hanging wire assembly 3000 includes a connecting fitting 3100 and a wire support 3200, one end of the connecting fitting 3100 is connected to the middle phase node fitting 2131, and the wire support 3200 is connected to the other end of the connecting fitting 3100, wherein the connecting fitting 3100 can be a connecting plate of fixed length, or can also be formed by a plurality of connecting plates fixedly connected in sequence. The connecting plate can be a PT adjustment plate, a parallel hanging plate, etc., and different connecting plates can be selected according to actual working conditions to be hinged into the connecting fitting 3100, so that it has different lengths to meet different wire height requirements to the ground. The wire support 3200 has a supporting inner cavity 3200a inside, and the supporting inner cavity 3200a is used to pass the wire 100. For example, the wire support 3200 can be a wire clamp having a supporting wire 100 and other similar structures that can support the wire 100, which are not limited here. Therefore, in order to stably pass the wire 100, the wire support 3200 can be designed to be straight and have a certain length. Therefore, the supporting inner cavity 3200a of the wire support 3200 is also adaptively presented as a straight inner cavity. The straight inner cavity has a straight trajectory. The wire 100 is movably passed through the supporting inner cavity 3200a along the straight trajectory of the supporting inner cavity 3200a, so that the wire 100 can be passed through the supporting inner cavity 3200a of the wire support 3200 along the length direction of the wire support 3200, and a stable package is formed based on the length design of the wire support 3200.
[0054] Moreover, if Figure 4 As shown, a curved portion 3210 is provided on at least one end of the wire support 3200 along the straight track. For example, curved portions 3210 are designed at both ends of the wire support 3200, wherein the curved portion 3210 gradually expands outward in a direction perpendicular to the straight track from the central position of the wire support 3200 to at least one end thereof. Figure 4 In the up and down direction shown in , the curved portion 3210 is in a gradually sagging state. Therefore, as the curved portion 3210 gradually sags, the conductor 100 can form a natural sag between the two modified transmission towers as the curved portion 3210 gradually sags, ensuring that the conductor 100 is not tight.
[0055] It can be understood that if there is no structural design of the curved portion 3210, the supporting inner cavity 3200a inside the conductor support 3200 is straight in the horizontal direction, and the conductor 100 will form a horizontally horizontal tight (straight) state between the two modified transmission towers. If the conductor 100 bends downward due to gravity, it will be damaged. Based on the structural design of the curved portion 3210, the conductor 100 will form an arc-shaped state with a droop in the middle between the two modified transmission towers, avoiding the conductor 100 from being damaged. Moreover, as the conductor 100 extends to the two ends of the conductor support 3200, the curved portions 3210 at the two ends of the conductor support 3200 can also avoid the conductor 100 to prevent the sharp ends from cutting the surface of the conductor 100.
[0056] Continue reading Figure 4 As shown, in one embodiment, the hanging wire assembly 3000 further includes a hanging element 3300 and a unit hanger 3400, the hanging element 3300 is connected to the other end of the connecting hardware 3100, the number of the unit hangers 3400 is configured to be at least two, and the plurality of unit hangers 3400 are respectively hinged to different positions of the hanging element 3300, such as Figure 4 As shown, the suspension element 3300 can adopt a structure such as a triangular connecting plate that can centrally connect several unit hangers 3400, which is not limited here. The number of wire supports 3200 is configured to be at least two, so each wire support 3200 can be connected to a unit hanger 3400, and then connected to the other end of the connecting hardware 3100 through the unit hanger 3400 and the suspension element 3300. At this time, multiple unit hangers 3400 can be set at the same time through the suspension element 3300, and multiple wire supports 3200 can be connected using multiple unit hangers 3400 to achieve the connection of multiple wires 100 on the same hanging wire assembly 3000.
[0057] The middle phase node and the side phase node of the composite cross arm assembly 2000 are directly hung with the metal hanging wire assembly 3000, which bears the nominal voltage of the line. The protruding part is very likely to have electric field distortion, and there is a high probability of corona discharge, which affects the life of the hanging wire assembly 3000 and the quality of people's living environment. Figures 7 to 10 In the embodiment, a runway-shaped, semicircular, and other equalizing shielding rings are arranged on the outside of the hanging wire assembly 3000. The shielding rings have a large radius of curvature and a smooth metal surface, so that no extreme electric field distortion will be generated. Therefore, placing the shielding rings on the middle phase node and the side phase node can well cover the protruding metal surface underneath, making the electric field area around the middle phase node and the side phase node uniform, solving the above-mentioned problem. Among them, the shielding ring can be parallel to the cross arm direction or perpendicular to the cross arm direction, playing the same role, that is, preventing the metal fittings from generating corona and making the surrounding electric field area uniform.
[0058] Continue reading Figure 3As shown, in one embodiment, the main tower structure 1000 also includes a ground wire support 4000, and the ground wire support 4000 includes a first ground wire support 4100 and a second ground wire support 4200. The first ground wire support 4100 is arranged at the top of the first curved arm 1210, and the second ground wire support 4200 is arranged at the top of the second curved arm 1220. The top of the first ground wire support 4100 and the top of the second ground wire support 4200 are used to connect the ground wire. For the case of a higher boost voltage, the ground wire support 4000 can be raised, and the middle phase composite cross arm 2100 is appropriately moved up a certain height on the tower head 1200, and the space of the middle phase assembly space 1000b becomes larger, which can meet the requirements of a larger gap after boosting. At the same time, the side phase composite cross arm 2200 is moved up at the same time, and the three-phase conductors 100 are located on the same horizontal plane. The distance between the conductor 100 and the ground is increased to meet the distance requirement of the conductor 100 to the ground, and a higher voltage level boost is achieved.
[0059] The voltage-increasing and capacity-increasing method provided in the present application comprises: obtaining original design information of an original transmission tower to be reconstructed, obtaining the voltage level and transmission capacity of the reconstructed transmission tower after voltage-increasing and capacity-increasing; performing analysis and calculation based on the original design information, voltage level and transmission capacity, and generating design input conditions of the reconstructed transmission tower; performing electrical design and structural design of the reconstructed transmission tower based on the design input conditions, determining the design of a composite cross-arm assembly and performing matching connection design between the composite cross-arm assembly and the original transmission tower, adjusting the design of the composite cross-arm assembly, and obtaining final design parameters of the reconstructed transmission tower; designing a construction plan based on the final design parameters, and preparing a composite cross-arm assembly; and performing construction according to the construction plan, hanging the conductor on the composite cross-arm assembly, and obtaining the reconstructed transmission tower.
[0060] See also Fig.11 When designing the original transmission tower, it was necessary to consider the clearance requirements between the conductor and the tower body 1100 under the condition of wind deflection of the long insulator string. Therefore, the original cross arm length was long and the inter-layer distance was large, which would result in a larger size of the tower head 1200. At the same time, due to the long horizontal projection of the long suspension insulator string after wind deflection, the corridor width was very wide.
[0061] When designing voltage increase and capacity expansion, the original design information of the original transmission tower must be obtained first, including the tower diagram, conductor type, ground wire type, line cross-section diagram, design meteorological conditions and other key information of the original transmission tower. At the same time, the voltage level and transmission capacity of the modified transmission tower must be obtained.
[0062] Based on the original design information and the voltage level and transmission capacity of the modified transmission tower, the analysis and calculation are mainly carried out, which mainly includes electrical layout and transmission tower modeling based on the tower diagram to calculate the transmission tower load, and the wire-to-ground distance check, transmission tower load check, corridor width calculation and transmission capacity comparison calculation according to the wire type and ground wire type, wire-to-ground distance check, transmission tower load calculation and electrical clearance check according to the line section diagram, and wire sag and load calculation according to the design meteorological conditions. In this way, the design input conditions can be obtained, including tower head layout, transmission tower load, wire-to-ground distance, vertical line distance, wire-to-ground electrical distance, wire sag, wire load, and electromagnetic parameters.
[0063] Electrical design and structural design are carried out based on the design input conditions. According to the initially selected conductors, the loads at the lifting points, the requirements for voltage increase and capacity increase, and the tower planning, the tower structure strength check and the foundation check of the original transmission tower are carried out. The boosted load is applied to the model of the original transmission tower to determine the transmission tower component structure that needs to be strengthened or replaced; the load is calculated using the boosted conductors, and the load is applied to the original transmission tower to check the force of the transmission tower component structure. The load calculation will be carried out according to the working conditions. In general, conductors with basically the same deadweight parameters will be selected to ensure that the load on the tower body will not exceed the standard, so there is no need to dismantle and rebuild. If the voltage increase is high and the ground wire bracket needs to be modified to meet the lightning protection requirements, the original ground wire bracket will be dismantled and rebuilt, and some cross materials of the tower body will also be replaced, and the tower body foundation will be checked.
[0064] Combined with the preliminary tower planning and verification, the preliminary design of the composite cross-arm assembly is carried out, including selection and structural design, and the tower planning is further verified. After meeting the overall tower planning and design, further verification of the cross-arm assembly structure design analysis and the corresponding electrical parts including the voltage-equalizing shielding ring and arcing angle design analysis are carried out. Then, combined with the actual working conditions of the boosting and capacity increase, the preliminary design of the composite cross-arm assembly, the tower body reinforcement or replacement design, the transmission tower foundation reinforcement design, the conductor replacement design, etc., the matching connection design of the composite cross-arm assembly and the original transmission tower is carried out, and the design of the composite cross-arm assembly is further adjusted to obtain the final design parameters of the modified transmission tower. The final design parameters include corridor width, transmission capacity, and component structural dimensions. Then, based on the final design parameters, the construction plan is designed, the composite cross-arm assembly is prepared, and the construction is carried out to complete the boosting and capacity increase transformation and obtain the modified transmission tower.
[0065] In one embodiment, the construction plan includes: shutting down the original transmission tower; temporarily suspending or removing the conductors and ground wires hanging from the original transmission tower; removing the original crossarm of the original transmission tower; modifying the tower head of the original transmission tower; suspending the composite crossarm assembly and installing it to the tower head; suspending the conductors hanging from the original transmission tower to the composite crossarm assembly, suspending the ground wires hanging from the original transmission tower to the tower head, or installing new conductors on the composite crossarm assembly and installing new ground wires on the tower head.
[0066] In a specific application scenario, the original transmission tower only includes the original crossarms set on both sides of the tower body. First, the power is turned off, and then the conductors and ground wires are removed, or the conductors and ground wires are temporarily suspended by pulleys or cranes, and then the original crossarms are removed and transported to the ground. Specifically, the original crossarms can be suspended and transported by a suspension mechanism. Removing all the conductors and ground wires is suitable for the reconstruction of the entire line; temporarily suspending the conductors and ground wires is suitable for the reconstruction of a specific original transmission tower or the original transmission tower of a certain line.
[0067] The suspension mechanism includes at least one of a drone, a crane, a helicopter, or a pulley block. The suspension mechanism can be selected from one of the drone, the crane, the helicopter, or the pulley block, or several of them can be selected to achieve stable suspension. Of course, the suspension mechanism can also be other tools besides the above tools, which is not limited here. During the entire suspension process, the entire structure can also be fixed with a windproof rope to prevent it from shaking during the suspension process, thereby avoiding collision with other structures on the tower head and causing damage.
[0068] Then, the tower head of the original transmission tower is modified. Specifically, at least one of the necessary installation holes, installation plates, and trusses is set on the tower head according to the installation requirements to facilitate the subsequent installation of the composite cross-arm assembly. After the composite cross-arm assembly is assembled on the ground, the composite cross-arm assembly is suspended and installed on the tower body through the suspension mechanism. Finally, the conductor and ground wire are installed.
[0069] In another specific application scenario, see Figure 1-Figure 11 The original transmission tower was Fig.11 The wine glass tower has a middle tower window surrounded by a first curved arm 1210, a second curved arm 1220 and a middle phase bridge structure 10, as well as a first side phase angle steel structure 20 located at the first curved arm 1210 and a second side phase angle steel structure 30 located at the second curved arm 1220. The middle phase bridge structure 10, the first side phase angle steel structure 20, the second side phase angle steel structure 30 and the suspension insulators hung thereon are all original cross arms that need to be removed.
[0070] During the construction process, after temporarily hanging or removing the conductors and ground wires hanging on the original transmission tower, a temporary reinforcement device is installed on the tower head before suspending the composite crossarm assembly 2000; after suspending the composite crossarm assembly 2000 and installing it to the tower head, the temporary reinforcement device is removed.
[0071] Specifically, a temporary reinforcement device is provided on the tower head 1200 of the original transmission tower, and the temporary reinforcement device is used to fix the support between the first curved arm 1210 and the second curved arm 1220 of the tower head 1200. In this state, the middle phase bridge structure 10 originally located between the first curved arm 1210 and the second curved arm 1220 is removed. The function of the temporary reinforcement device is to form a temporary support between the first curved arm 1210 and the second curved arm 1220 of the tower head 1200, replacing the original middle phase bridge structure 10, so that the overall structure before and after the transformation remains consistent and the stability of the overall structure is maintained.
[0072] The temporary reinforcement device may adopt a crossbar structure, and the two ends of the crossbar structure may be threadedly connected to the first curved arm 1210 and the second curved arm 1220 of the tower head 1200 by means of threaded connection, or may adopt various connection methods such as lap plate connection, flange connection, cross plug plate connection, etc. In one embodiment, the temporary reinforcement device includes a reinforcement rod and an adjustment component, the reinforcement rod is a rod of fixed length, the adjustment component is arranged at one end of the reinforcement rod, and the adjustment component can be used to adjust the length, and then on the basis of the fixed length of the reinforcement rod, the overall length of the temporary reinforcement device can be adjusted by adjusting the length of the adjustment component itself. The adjustment component may include an adjustment body, a first connection part and a second connection part, and the adjustment body may adopt a variety of retractable structures such as a hydraulic cylinder and a telescopic rod. Those skilled in the art may select a suitable retractable structure according to various factors such as actual pressure requirements and installation convenience, and are not limited here. The temporary reinforcement device only needs to meet the force requirements, stabilize the overall structure of the original transmission tower, and not affect the installation of the middle phase composite cross arm at the back.
[0073] After the middle phase composite cross arm 2100 is installed, the side phase composite cross arm 2200, i.e., the first side phase composite cross arm 2200 and the second side phase composite cross arm 2200 located on the left and right sides of the tower head 1200, can be installed. For example, in one embodiment, the first side phase angle steel structure 20 originally located at the first crank arm 1210 and the second side phase angle steel structure 30 originally located at the second crank arm 1220 need to be removed first, and the assembled first side phase composite cross arm 2200 and the second side phase composite cross arm 2200 are suspended, and the first side phase composite cross arm 2200 is installed on the outside of the first crank arm 1210, and the second side phase composite cross arm 2200 is installed on the outside of the second crank arm 1220. Among them, the assembly of the first side phase composite crossarm 2200 and the second side phase composite crossarm 2200 can be completed on the ground, and the assembly of the first side phase composite crossarm 2200 and the second side phase composite crossarm 2200, as well as the disassembly of the first side phase angle steel structure 20 and the second side phase angle steel structure 30 can all be carried out simultaneously, as long as the first side phase angle steel structure 20 and the second side phase angle steel structure 30 are in a state of being dismantled before the first side phase composite crossarm 2200 and the second side phase composite crossarm 2200 are suspended, the conditions for modifying and installing the side phase composite crossarm 2200 can be met at this time, and the modification and installation of the side phase composite crossarm 2200 can be realized.
[0074] The temporary reinforcement device can be removed after the middle phase composite cross arm 2100 is installed, or after both the middle phase composite cross arm 2100 and the side phase composite cross arm 2200 are installed.
[0075] In another embodiment, the construction plan includes: shutting down the original transmission tower; temporarily suspending or removing the conductors and ground wires hanging from the original transmission tower; separating the tower head and the tower body of the original transmission tower, transporting the tower head to the ground and removing the original crossarm of the original transmission tower; installing a composite crossarm assembly on the tower head; suspending the tower head and the composite crossarm assembly and installing them to the tower body; suspending the conductors hanging from the original transmission tower to the composite crossarm assembly, suspending the ground wires hanging from the original transmission tower to the tower head, or, installing new conductors on the composite crossarm assembly and installing a new ground wire on the tower head.
[0076] For more details, see Figure 1-Figure 11, first ensure that the original transmission tower is powered off, then remove or use a crane or other equipment to temporarily hang the wires and ground wires hanging on the original transmission tower, and then separate the tower head 1200 and the tower body 1100 of the main tower structure 1000 of the original transmission tower. The purpose of separation is to dismantle the tower head 1200 and the middle phase bridge structure 10, the first side phase angle steel structure 20, and the second side phase angle steel structure 30 originally set on the tower head 1200, thereby achieving a one-time dismantling of the above structures. After the dismantling is completed, the above dismantled structure is hoisted from a high place to the ground, and the above structure is replaced and renovated on the ground. First, the original cross arm is removed, that is, the middle phase bridge structure 10, the first side phase angle steel structure 20, and the second side phase angle steel structure 30 are removed from the tower head 1200, and then the composite cross arm assembly 2000 is installed. For example, the assembled composite cross arm assembly 2000 is installed on the first curved arm 1210 and the second curved arm 1220 of the tower head 1200, and the composite cross arm assembly 2000 is used to replace the middle phase bridge structure 10, the first side phase angle steel structure 20, and the second side phase angle steel structure 30. After the installation is completed, the suspended tower head 1200 and the composite cross arm assembly 2000 installed on the tower head 1200 are installed on the tower body 1100, and then the ground wire and the conductor are hung. In this way, the overall construction and renovation of the tower head 1200 is realized. For the voltage increase and capacity increase scheme with a higher degree of voltage increase, it is more convenient to implement the overall renovation and installation of the composite cross arm assembly 2000 on the ground, and the renovation requirements can be met at one time. For another example, the middle phase composite crossarm 2100 is first installed between the first curved arm 1210 and the second curved arm 1220 of the tower head 1200. At this time, the structure formed by the middle phase composite crossarm 2100 and the tower head 1200 is stable and convenient for suspension. Then the tower head 1200 and the middle phase composite crossarm 2100 are suspended and installed on the tower body 1100, and then the two side phase composite crossarms 2200 are suspended and respectively installed on the outside of the first curved arm 1210 and the outside of the second curved arm 1220 of the tower head 1200. In this way, the middle phase composite crossarm 2100 and the side phase composite crossarm 2200 are respectively installed, which reduces the difficulty of suspension.
[0077] For the voltage-boosting and capacity-increasing scheme with a higher voltage-boosting degree, the tower head 1200 of the original transmission tower is difficult to meet the size requirements for the installation of the composite cross-arm assembly 2000. By increasing the installation height of the original ground wire bracket 4000 or extending the length of the original ground wire bracket 4000, the tower head 1200 has more space, and thus the overall structure of the composite cross-arm assembly 2000 can be moved upward when the composite cross-arm assembly 2000 is installed. The installation height of the composite cross-arm assembly 2000 is higher than the height of the original cross-arm, that is, higher than the installation positions of the middle phase bridge structure 10, the first side phase angle steel structure 20, and the second side phase angle steel structure 30 of the original transmission tower, so that a voltage boost to a higher voltage level can be achieved.
[0078] After the voltage is increased, in order to meet the lightning protection requirements, the original ground wire support 4000 is modified, and a new ground wire support 4000 that can meet the lightning protection requirements is installed. The height of the new ground wire support 4000 is higher than the height of the original ground wire support 4000. Similar to the above-mentioned construction scheme, the tower head 1200 and the tower body 1100 of the main tower structure 1000 of the original transmission tower are first separated. After the disassembly is completed, the disassembled structure is hoisted from a high place to the ground, and the replacement and transformation are carried out on the ground. The original cross arm and the original ground wire support 4000 are first removed from the tower head 1200, and then the composite cross arm assembly 2000 and the new ground wire support 4000 are installed. For example, after the composite cross arm assembly 2000 and the new ground wire support 4000 are installed on the tower head 1200, the tower head 1200, the composite cross arm assembly 2000 and the new ground wire support 4000 are suspended and installed on the tower body 1100 together, which can meet the transformation requirements at one time without the need for multiple constructions. For another example, the middle phase composite cross arm 2100 is installed between the first curved arm 1210 and the second curved arm 1220 of the tower head 1200, and then the tower head 1200 and the middle phase composite cross arm 2100 are suspended and installed on the tower body 1100, and then the two side phase composite cross arms 2200 are suspended and installed on the outside of the first curved arm 1210 and the outside of the second curved arm 1220 of the tower head 1200, respectively, and the new ground wire bracket 4000 is suspended and installed on the top of the first curved arm 1210 and the second curved arm 1220 of the tower head 1200. The separate installation can facilitate the suspension and reduce the difficulty of construction. It can be understood that it is only necessary to complete the removal of the original ground wire bracket 4000 of the original transmission tower and install the new ground wire bracket 4000 on the tower head 1200 before hanging the conductor and the ground wire.
[0079] In this embodiment, the modification of the original transmission tower is relatively large. After the tower head 1200 is separated from the tower body 1100, the tower head 1200 can be hoisted as a whole for construction. The operation is convenient and the construction efficiency is high, which can reduce the construction period and cost of the boosting modification project. After the boosting, the transmission capacity is greatly increased to meet the load requirements of the rapidly growing economy.
[0080] The voltage increase and capacity increase method of the present application has the following technical effects: (1) the composite cross-arm assembly is used for voltage increase and capacity increase, the suspended insulator string is omitted, the conductor hanging height is raised, the wind swing is reduced, and the voltage increase does not require tower replacement; (2) Increasing the transmission voltage can reduce line loss and improve the effective transmission efficiency; (3) In the working condition where the corridor is limited and the voltage needs to be increased, the composite cross-arm assembly has low economic cost and high transformation efficiency, and has strong competitiveness; (4) After the voltage increase and capacity increase, the transmission tower has significantly improved the ability to resist pollution, wind, and lightning strikes; (5) The removal of traditional insulators can greatly reduce the workload and cost of later operation and maintenance.
[0081] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0082] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be construed as limiting the scope of the patent application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the patent application shall be subject to the attached claims.
Claims
1. A method for increasing voltage and capacity, It is characterized in that include: Obtain the original design information of the original transmission tower to be modified, and obtain the voltage level and transmission capacity of the modified transmission tower after voltage increase and capacity increase; Performing analysis and calculation based on the original design information, the voltage level and the transmission capacity to generate design input conditions for the modified transmission tower; Based on the design input conditions, the electrical design and structural design of the modified transmission tower are performed, the design of the composite cross-arm assembly is determined, and the matching connection design of the composite cross-arm assembly and the original transmission tower is performed, and the design of the composite cross-arm assembly is adjusted to obtain the final design parameters of the modified transmission tower; Designing a construction plan based on the final design parameters and preparing the composite crossarm assembly; According to the construction plan, the conductors are hung on the composite cross arm assembly to obtain the modified transmission tower.
2. The method for increasing voltage and capacity according to claim 1, It is characterized in that The construction plan includes: Cutting off power to the original transmission tower; Temporarily suspend or remove the wires and ground wires suspended on the original transmission tower; dismantling the original cross arm of the original transmission tower; Transforming the tower head of the original transmission tower; Suspending the composite cross arm assembly and installing it to the tower head; The conductor suspended on the original transmission tower is hung on the composite cross-arm assembly, and the ground wire suspended on the original transmission tower is hung on the tower head, or a new conductor is installed on the composite cross-arm assembly, and a new ground wire is installed on the tower head.
3. The method for increasing voltage and capacity according to claim 2, It is characterized in that After temporarily hanging or removing the conductors and ground wires suspended on the original transmission tower, and before hanging the composite cross-arm assembly, a temporary reinforcement device is installed on the tower head; after hanging the composite cross-arm assembly and installing it on the tower head, the temporary reinforcement device is removed.
4. The method for increasing voltage and capacity according to claim 1, It is characterized in that The construction plan includes: Cutting off power to the original transmission tower; Temporarily suspend or remove the wires and ground wires suspended on the original transmission tower; Separating the tower head and the tower body of the original transmission tower, transporting the tower head to the ground and removing the original cross arm of the original transmission tower; Installing the composite cross arm assembly on the tower head; Suspending the tower head and the composite cross arm assembly and installing them to the tower body; The conductor suspended on the original transmission tower is hung on the composite cross-arm assembly, and the ground wire suspended on the original transmission tower is hung on the tower head, or a new conductor is installed on the composite cross-arm assembly, and a new ground wire is installed on the tower head.
5. The method for increasing voltage and capacity according to claim 4, It is characterized in that The method further includes: suspending the conductor suspended on the original transmission tower to the composite cross-arm assembly, suspending the ground wire suspended on the original transmission tower to the tower head, or installing a new conductor on the composite cross-arm assembly. Before installing the new ground wire on the tower head, the method further includes: removing the original ground wire bracket of the original transmission tower, and installing a new ground wire bracket on the tower head.
6. The method for increasing voltage and capacity according to claim 1, It is characterized in that The hanging height of the conductor on the composite cross-arm assembly is higher than the hanging height of the conductor on the original transmission tower.
7. The method for increasing voltage and capacity according to claim 2, It is characterized in that The modification of the tower head of the original transmission tower comprises: providing at least one of a mounting hole, a mounting plate, and a truss on the tower head.
8. The method for increasing voltage and capacity according to claim 2 or 4, It is characterized in that The suspension adopts a suspension mechanism, and the suspension mechanism includes at least one of a drone, a crane, a helicopter, or a pulley block.
9. The method for increasing voltage and capacity according to claim 5, It is characterized in that The installation height of the composite cross arm assembly is higher than the height of the original cross arm, and the height of the new ground wire bracket is higher than the height of the original ground wire bracket.
10. The method for increasing voltage and capacity according to claim 1, It is characterized in that The original design information includes the tower diagram of the original transmission tower, the conductor type, the ground wire type, the line cross-section diagram, and the designed meteorological conditions.
11. The method for increasing voltage and capacity according to claim 1, It is characterized in that The design input conditions include tower head arrangement, transmission tower load, conductor-to-ground distance, vertical line distance, conductor-to-ground electrical distance, conductor sag, conductor load, and electromagnetic parameters; the final design parameters include corridor width, transmission capacity, and component structure dimensions.
12. A transmission tower, It is characterized in that The step-up capacity increasing method according to any one of claims 1 to 11 is used for step-up capacity increasing transformation, wherein the transmission tower comprises a main tower structure, wherein the main tower structure defines a reference horizontal plane, wherein the reference horizontal plane is used to be arranged parallel to the earth's horizontal plane; wherein the main tower structure comprises a tower body and a tower head, wherein the tower head comprises a first curved arm and a second curved arm, wherein the first curved arm and the second curved arm are arranged at the top of the tower body, and the space between the first curved arm and the second curved arm is used to form a middle phase assembly space, wherein the middle phase assembly space has a top space opening; A composite crossarm assembly, wherein the composite crossarm assembly is arranged at the tower head, and the composite crossarm assembly comprises a middle phase composite crossarm and two side phase composite crossarms; wherein the middle phase composite crossarm is arranged in the middle phase assembly space, and the two side phase composite crossarms are respectively arranged at the first curved arm and the second curved arm of the tower head, and the two side phase composite crossarms are both located outside the middle phase assembly space; A hanging wire assembly is used to connect the conducting wires. The number of the hanging wire assemblies is configured to be at least three. The middle phase composite cross arm is provided with at least one hanging wire assembly, and each side phase composite cross arm is provided with at least one hanging wire assembly.
13. The transmission tower according to claim 12, It is characterized in that The middle-phase composite crossarm includes a plurality of first oblique-stayed insulating rods and a plurality of first pillar insulating rods, one ends of all the first oblique-stayed insulating rods are respectively connected to different positions of the first curved arm and the second curved arm, and all the first oblique-stayed insulating rods have an angle with the reference horizontal plane, one ends of all the first pillar insulating rods are respectively connected to different positions of the first curved arm and the second curved arm, and all the first pillar insulating rods have an angle with the reference horizontal plane, the other ends of all the first oblique-stayed insulating rods and the other ends of all the first pillar insulating rods are connected to form a middle-phase node in the middle-phase assembly space, and the middle-phase node is provided with at least one hanging wire assembly.
14. The transmission tower according to claim 12, It is characterized in that Each of the side-phase composite cross-arms comprises a plurality of second oblique-stayed insulating rods and a plurality of second supporting insulating rods, one ends of all the second oblique-stayed insulating rods in each of the side-phase composite cross-arms are respectively connected to different positions of the tower head, and all the second oblique-stayed insulating rods in each of the side-phase composite cross-arms have an angle with the reference horizontal plane, one ends of all the second supporting insulating rods in each of the side-phase composite cross-arms are respectively connected to different positions of the tower head, and all the second supporting insulating rods in each of the side-phase composite cross-arms have an angle with the reference horizontal plane, the other ends of all the second oblique-stayed insulating rods in each of the side-phase composite cross-arms and the other ends of all the second supporting insulating rods are connected to form a side-phase node outside the middle-phase assembly space, and the side-phase node is provided with at least one hanging wire assembly.
15. The transmission tower according to claim 13, It is characterized in that The hanging wire assembly comprises: A connecting hardware, one end of which is connected to the middle phase node; A wire support is connected to the other end of the connecting hardware, wherein the wire support has a support inner cavity inside, and the support inner cavity is used to pass the wire.