Enterprise carbon emission real-time metering system
By designing a real-time measurement system for enterprise carbon emissions and collecting and calculating carbon emission data in real time, the problems of inaccurate and lag of carbon emissions in the existing technology are solved, and real-time and accurate measurement of enterprise carbon emissions and product carbon footprints are achieved.
Patent Information
- Application Number
- CN202411119383.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-15
- Publication Date
- 2024-11-19
AI Technical Summary
The existing technology cannot achieve real-time and accurate measurement of enterprise carbon emissions, resulting in inaccurate accounting of carbon emissions and product carbon footprints, and there is lag.
A real-time measurement system for enterprise carbon emissions is designed, including a total carbon emission measurement system and multiple data entry systems. Through the human-computer interactive interface, model database and carbon emission correlation database, carbon emission correlations are collected and calculated in real time during enterprise operation. Data, providing real-time carbon emission information.
Real-time and accurate measurement of enterprise carbon emissions and product carbon footprints has been achieved, breaking down the barriers of traditional carbon metrology technology, and solving the inaccuracy and lag problems caused by accounting rather than measurement.
Smart Images

Figure CN118982149A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of carbon emissions, and in particular to a real-time carbon emission measurement system for an enterprise. Background Art
[0002] Carbon emissions refer to greenhouse gas emissions from a certain entity, such as a company, and all its facilities, equipment, personnel, etc. that involve energy consumption and emissions during a certain period of time. Greenhouse gases include carbon dioxide (C02), methane (CH4), nitrous oxide (N2O), hydrofluorocarbons (HFC), perfluorocarbons (PFC) and nitrogen trifluoride (NF3). The calculation result of a company's carbon emissions during the target period is the weighted sum of the various greenhouse gas emissions generated by the company's energy consumption and emission facilities, equipment, personnel, etc., expressed in carbon dioxide equivalent (CO2e), with the unit of kgCO2e or tCO2e.
[0003] A carbon footprint is the total amount of greenhouse gas (GHG) emissions caused directly and indirectly by a person, organization, event or product, expressed in carbon dioxide equivalent (CO2e).
[0004] Carbon footprint is an indicator of greenhouse gas emissions. Research institutions introduced this concept when identifying and evaluating the carbon emissions of products.
[0005] Product Carbon Footprint (PCF) refers to the total greenhouse gas emissions of a product at each stage of its life cycle, that is, the accumulation of various greenhouse gas emissions from multiple stages such as raw material mining, product production (or service provision), distribution, use to final disposal / recycling.
[0006] When calculating the carbon footprint of a product, you can choose to quantify it based on the "cradle to gate", "gate to gate" or "cradle to grave" methods. "Cradle to gate" (B2B) means that the carbon accounting of the product is done until the product leaves the factory. This method is generally applicable to non-end-consumption products, such as steel, cement, glass, ceramics, concrete, etc. "Cradle to grave" (B2C) not only considers the emissions from the production and transportation of raw materials, but also the emissions from the use and disposal stages of the product. This method is generally applicable to consumer-end products, such as mobile phones, computers, cars, etc.
[0007] Whether it is the emissions from the entire supply chain from "cradle to gate" or the emissions from the entire value chain from "cradle to grave", the accounting boundary is the entire stage from the development of natural resources in the production system to the end of life (including recycling activities).
[0008] For enterprises, determining the carbon footprint of products is the first step in reducing corporate carbon emissions. It helps companies truly understand the impact of products on climate change and take feasible measures to reduce carbon emissions in the supply chain. For export manufacturing companies, calculating product carbon footprint is the only way to improve international competitiveness and break down international carbon tax barriers.
[0009] At present, the measurement of corporate carbon emissions can only be roughly calculated through historical data, and it is impossible to achieve real-time and accurate measurement. The main problems are as follows:
[0010] 1. Enterprise carbon inventory can only be calculated through energy usage records for a certain period of time or energy purchase and sales contracts of the finance department, electricity invoices, attendance records, etc. The kitchen waste of enterprises with canteens is only estimated based on the number of people;
[0011] 2. Product carbon footprint: In the cradle-to-gate stage, only the carbon emissions of similar products published in the common database can be used as the basis for introduction. However, in reality, even if the product is the same, the process and equipment used are different, and the emissions are different, which leads to inaccurate product carbon footprint calculation;
[0012] 3. Product carbon footprint: At the gate-to-gate stage, the equipment used can clearly distinguish the energy consumption of the product at this stage and accurately count it, but the energy consumption of the product cannot be clearly distinguished and is evenly distributed according to the production output of various products, resulting in inaccurate calculation of the product carbon footprint;
[0013] 4. At present, all accounting results on corporate carbon emissions are lagging and cannot be measured in real time.
[0014] To sum up, how to improve the real-time and accuracy of corporate carbon emissions measurement is an urgent problem to be solved. Summary of the invention
[0015] The present invention aims to solve at least one of the technical problems existing in the prior art, and in particular innovatively proposes a real-time measurement system for enterprise carbon emissions to improve the real-time performance and accuracy of enterprise carbon emissions measurement.
[0016] In order to achieve the above-mentioned purpose of the present invention, the present invention provides a real-time carbon emission measurement system for an enterprise, including a carbon emission measurement system and multiple data entry systems, wherein the carbon emission measurement system has a human-computer interaction interface, a model database, a carbon emission association database, a carbon emission measurement unit and multiple data collection ports, each of which has at least one data entry port, and the data entry port of each data entry system is connected to the data collection port of the carbon emission measurement system in a one-to-one correspondence, wherein:
[0017] The data entry system is used to collect carbon emission related data of each link in the enterprise operation process in real time or according to a preset data collection frequency;
[0018] The carbon emission related database is used to store the carbon emission related data collected by the data entry system;
[0019] The model database is used to store a pre-built carbon emission measurement model;
[0020] The human-computer interaction interface is used to receive carbon emission query information input by a user and display carbon emission information corresponding to the carbon emission query information;
[0021] The carbon emission measurement unit is used to call the corresponding carbon emission associated data in the carbon emission associated database and the corresponding carbon emission measurement model in the model database according to the carbon emission query information input by the user in the human-computer interaction interface, calculate the carbon emission information corresponding to the carbon emission query information, and display the carbon emission information through the human-computer interaction interface.
[0022] Preferably, the plurality of data entry systems include:
[0023] The production data entry system is used to enter the carbon emission-related data corresponding to the production stage of the enterprise's products;
[0024] Office life data entry system, used to enter carbon emission related data corresponding to the office life of enterprise employees;
[0025] as well as
[0026] The electricity data entry system is used to enter carbon emission related data of electricity in enterprise production activities and office life activities.
[0027] Preferably, the plurality of data entry systems further comprises:
[0028] The warehousing data entry system is used to enter the carbon emission related data corresponding to the raw materials warehousing stage of the enterprise; and
[0029] The carbon emission offset data entry system is used to enter carbon emission related data of relevant aspects adopted by enterprises to offset carbon emissions.
[0030] Preferably, the number of data entry ports of the production data entry system is the same as the number of processes in the enterprise product production stage, and each data entry port of each production data entry system is used to enter the carbon emission related data of the corresponding process.
[0031] Preferably, the carbon emission related data entered by the production data entry system includes:
[0032] The equipment power and on / off time information of the equipment used in each process, as well as the name and usage information of the auxiliary materials that will produce greenhouse gases in each process.
[0033] Preferably, the office life data entry system has two data entry ports, one of which is used to enter the carbon emission related data of the enterprise employees' attendance, and the other is used to enter the carbon emission related data of the enterprise employees' dining, wherein:
[0034] The carbon emission-related data of enterprise employee attendance includes the pre-entered information of each employee, attendance distance, transportation used, vehicle type, and employee clock-in information obtained through linkage with the attendance system;
[0035] The carbon emission-related data for corporate employee dining include the power of equipment used in the company canteen every day, equipment on / off time information, amount of natural gas used, name and weight of purchased food, and weight information of kitchen waste generated.
[0036] Preferably, the power data entry system has two data entry ports, one of which is used to enter power electricity data, and the other is used to enter life electricity data.
[0037] The electricity data entry system enters carbon emission-related data in the production activities and office life activities of the enterprise, including power electricity data and life electricity data.
[0038] Preferably, the warehousing data entry system has one data entry port.
[0039] The carbon emission-related data corresponding to the raw material warehousing stage of the enterprise entered into the warehousing data entry system include:
[0040] Basic information of raw materials and the corresponding unit carbon emissions, basic information of transportation and the corresponding unit carbon emissions, as well as basic information of equipment used for pre-warehousing inspection and the corresponding unit carbon emissions.
[0041] Preferably, the basic information of raw materials includes the name, model specification and batch number of the raw materials;
[0042] The basic transportation information includes the distance from the raw material manufacturer to the enterprise, the means of transportation and the transportation quantity;
[0043] The basic information of the equipment used for the pre-warehouse inspection includes the power of the equipment used for the pre-warehouse inspection and the equipment on / off time.
[0044] Preferably, the carbon emission offset data entry system has a data entry port, and the carbon emission related data used by the enterprise to offset carbon emissions entered into the carbon emission offset data entry system include:
[0045] The types of new energy used and the corresponding usage, as well as the types of waste recycling and the corresponding recycling amounts.
[0046] It can be seen from the above scheme that the present invention provides a real-time carbon emission measurement system for enterprises, which breaks the technical barriers of traditional carbon measurement, can realize real-time and accurate measurement of carbon emissions and carbon footprints, and solves the problem of inaccurate and delayed accounting of enterprise carbon emissions and product carbon footprints caused by the current accounting rather than measurement of carbon emissions.
[0047] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:
[0049] Figure 1 It is a system framework diagram of a real-time carbon emission measurement system for an enterprise in a preferred embodiment of the present invention;
[0050] Figure 2 It is a metering flow chart of a real-time metering system for enterprise carbon emissions in a preferred embodiment of the present invention. DETAILED DESCRIPTION
[0051] The exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although the exemplary embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided to enable a more thorough understanding of the present disclosure and to fully convey the scope of the present disclosure to those skilled in the art.
[0052] Those skilled in the art will appreciate that, unless otherwise defined, all terms (including technical and scientific terms) used herein have the same meaning as those generally understood by those skilled in the art in the art to which the present invention belongs. It should also be understood that terms such as those defined in general dictionaries should be understood to have meanings consistent with the meanings in the context of the prior art, and will not be interpreted with idealized or overly formal meanings unless specifically defined.
[0053] The present invention provides a real-time measurement system for carbon emissions of an enterprise, such as Figure 1 , Figure 2As shown, the metering system includes a carbon emission metering system and multiple data entry systems. The carbon emission metering system has a human-computer interaction interface, a model database, a carbon emission related database, a carbon emission metering unit and multiple data collection ports. Each data entry system has at least one data entry port. The data entry ports of each data entry system are connected to the data collection ports of the carbon emission metering system in a one-to-one correspondence.
[0054] The data entry system is used to collect carbon emission-related data at all stages of the enterprise's operation in real time or according to a preset data collection frequency;
[0055] The carbon emission related database is used to store the carbon emission related data collected by the data entry system;
[0056] The model database is used to store pre-built carbon emission measurement models;
[0057] The human-computer interaction interface is used to receive carbon emission query information input by the user and display the carbon emission information corresponding to the carbon emission query information;
[0058] The carbon emission measurement unit is used to call the corresponding carbon emission related data in the carbon emission related database and the corresponding carbon emission measurement model in the model database according to the carbon emission query information input by the user in the human-computer interaction interface, calculate the carbon emission information corresponding to the carbon emission query information, and display the carbon emission information through the human-computer interaction interface.
[0059] The working principle of the real-time measurement system for enterprise carbon emissions in this embodiment is as follows:
[0060] First, according to the relevant definitions of carbon emission measurement and the existing relevant formulas of carbon emission measurement, a carbon emission measurement model is pre-constructed, and the constructed carbon emission measurement model is stored in the model database of the carbon emission measurement system. Then, in the operation process of the enterprise, the carbon emission related data of each link in the operation process of the enterprise are collected in real time or according to the preset data collection frequency through various data entry systems, and the collected carbon emission related data are transmitted to the corresponding data collection port of the carbon emission measurement system and stored in the carbon emission related database. When the user needs to know the carbon emission information of the enterprise in any time period, the user inputs the corresponding time period information, product batch information and other carbon emission query information through the human-computer interaction interface. The carbon emission measurement unit calls the corresponding carbon emission related data in the carbon emission related database and the corresponding carbon emission measurement model in the model database according to the carbon emission query information input by the user, calculates the carbon emission information corresponding to the carbon emission query information, and displays the carbon emission information through the human-computer interaction interface.
[0061] The enterprise carbon emission real-time measurement system of this embodiment, each data entry system can be associated with the enterprise's production, finance, office and other management systems, and comprehensively collect carbon emission related data in real time or at a set frequency. It can achieve real-time and accurate measurement of carbon emissions and carbon footprints, and can also retrieve the total carbon emissions of production and office life in any time period, and can retrieve the carbon footprint emissions of any batch of products.
[0062] It should be noted that the carbon emission related data in this embodiment refers to relevant data that will affect the carbon emission results of the enterprise during the production and operation process of the enterprise, such as energy consumption of production equipment, energy consumption of cafeteria equipment, energy consumption of employee attendance methods, etc.
[0063] In one embodiment, the plurality of data entry systems comprises:
[0064] The production data entry system is used to enter the carbon emission-related data corresponding to the production stage of the enterprise's products;
[0065] Office life data entry system, used to enter carbon emission related data corresponding to the office life of enterprise employees;
[0066] The electricity data entry system is used to enter carbon emission related data of electricity in enterprise production activities and office life activities.
[0067] In one embodiment, the plurality of data entry systems further comprises:
[0068] The warehousing data entry system is used to enter the carbon emission related data corresponding to the warehousing stage of the enterprise's raw materials;
[0069] The carbon emission offset data entry system is used to enter carbon emission related data of relevant aspects adopted by enterprises to offset carbon emissions.
[0070] In one embodiment, the number of data entry ports of the production data entry system is the same as the number of processes in the enterprise product production stage, and each data entry port of each production data entry system is used to enter the carbon emission related data of the corresponding process.
[0071] In one embodiment, the carbon emission related data entered by the production data entry system includes:
[0072] The equipment power and on / off time information of the equipment used in each process, as well as the name and usage information of the auxiliary materials that will produce greenhouse gases in each process.
[0073] At the input port of each process, enter basic information such as the power of the equipment used for the production batch products (after the basic equipment information is entered, use the selection function later), the start and end time of use, and the name and amount of auxiliary materials that will produce greenhouse gases. The carbon emission metering unit automatically calculates the total carbon emissions of this stage, but does not convert the unit carbon emissions of the batch. When the batch of finished products is completed, the carbon emission metering unit automatically calls the carbon emissions generated by each process of the batch, calculates the unit carbon emissions in the production process, and superimposes it with the unit carbon emissions of the raw materials. The printable labels are product name, model specification, batch number, manufacturer, gate-gate unit carbon emissions, and cradle-gate unit carbon emissions.
[0074] In one embodiment, the office life data entry system has two data entry ports, one of which is used to enter carbon emission related data on the attendance of enterprise employees, and the other is used to enter carbon emission related data on the dining of enterprise employees, wherein:
[0075] The carbon emission-related data of enterprise employee attendance includes the pre-entered information of each employee, attendance distance, transportation used, vehicle type, and employee clock-in information obtained through linkage with the attendance system;
[0076] The carbon emission-related data for corporate employee dining include the power of equipment used in the company canteen every day, equipment on / off time information, amount of natural gas used, name and weight of purchased food, and weight information of kitchen waste generated.
[0077] Enter each employee's information, attendance distance, means of transportation used, vehicle information (fuel vehicle or new energy), etc. in advance. This metering system is linked to the attendance system. When punching in, if the employee's attendance method is identified as a vehicle based on the employee information, the employee's transportation carbon emissions for that day will be automatically calculated based on the entered information. If it is not a vehicle, it will be classified as carpooling or public transportation, and the carbon emissions for that day will be ignored. In addition, based on the punching system, the fecal emissions generated by the number of people attending the meeting every day can be automatically calculated.
[0078] In calculating the carbon emissions from employees' meals, we input the equipment, model, power, start-up time and shutdown time used in the canteen every day; the amount of natural gas used; the name and weight of the food purchased; the weight information of kitchen waste generated, etc., and automatically calculate the company's daily carbon emissions from dining.
[0079] In one embodiment, the power data entry system has two data entry ports, one of which is used to enter power electricity data, and the other is used to enter life electricity data.
[0080] The electricity data entry system enters carbon emission-related data from electricity in corporate production activities and office life activities, including power electricity data and life electricity data.
[0081] By collecting the company's verified power electricity data and household electricity data separately, when calculating the product carbon footprint, it can be compared and verified with the production stage. The product power consumption entered at each port in the production process should be roughly equal to the power electricity value for that time period.
[0082] In one embodiment, the warehousing data entry system has 1 data entry port.
[0083] The carbon emission-related data corresponding to the raw material warehousing stage of the enterprise entered into the warehousing data entry system include:
[0084] Basic information of raw materials and the corresponding unit carbon emissions, basic information of transportation and the corresponding unit carbon emissions, as well as basic information of equipment used for pre-warehousing inspection and the corresponding unit carbon emissions.
[0085] In one embodiment, the basic information of raw materials includes the name, model specification, and batch number of the raw materials;
[0086] Basic transportation information includes the distance from the raw material manufacturer to the enterprise, transportation tools and transportation quantity;
[0087] The basic information of the equipment used for the pre-warehousing inspection includes the equipment power and equipment on / off time used for the pre-warehousing inspection.
[0088] In one embodiment, the carbon emission offset data entry system has a data entry port, and the carbon emission related data used by the enterprise to offset the carbon emission related aspects entered into the carbon emission offset data entry system include:
[0089] The types of new energy used and the corresponding usage, as well as the types of waste recycling and the corresponding recycling amounts.
[0090] Specifically, the carbon emission measurement model of the enterprise in any time period can be expressed as: the carbon emissions of the enterprise in any time period = indirect emissions from power electricity in any time period + indirect emissions from household electricity in any time period + emissions from production energy combustion + greenhouse gas fugitive emissions + canteen emissions, and the indirect emissions from power electricity in any time period, indirect emissions from household electricity in any time period, emissions from production energy combustion, greenhouse gas fugitive emissions and canteen emissions can all be calculated through the corresponding carbon emission measurement model and the carbon emission related data entered into the above-mentioned data entry system.
[0091] In order to better understand the present invention, the working principle of the enterprise carbon emission real-time measurement system of the present invention is described in detail below by taking a steel plant as an example:
[0092] In this embodiment, the carbon emission measurement system has 11 data collection ports, namely the 1st data collection port to the 11th data collection port, wherein the 1st data collection port is used to collect the carbon emission related data corresponding to the raw material warehousing stage of the enterprise entered by the warehousing data entry system, the 2nd data collection port to the 7th data collection port are used to collect the carbon emission related data of the 1st to 6th processes in the process of steel production S1 model products entered by the production data entry system, the 8th data collection port is used to collect the carbon emission related data of the attendance of the enterprise employees entered by the office life data entry system, the 9th data collection port is used to collect the carbon emission related data of the dining of the enterprise employees entered by the office life data entry system, the 10th data collection port is used to collect the carbon emission related data of the electricity in the production activities and office life activities of the enterprise entered by the electricity data entry system, including power electricity data and life electricity data, and the 11th data collection port is used to collect the carbon emission related data of the relevant aspects adopted by the enterprise to offset carbon emissions entered by the carbon emission offset data entry system.
[0093] The specific data collection and measurement methods are as follows:
[0094] The first data collection port:
[0095] Raw material purchase weight: 4000kg
[0096] Carbon emissions per unit of raw material producers:
[0097] From cradle to door: 2kg / CO2KG
[0098] Door to door: 1kg / CO2KG
[0099] Select the mode of transportation and energy use: car / diesel, car / gasoline, train, airplane, etc. The emission factors and low calorific values corresponding to different modes of transportation and energy use can use existing values. The specific emission factors and low calorific values corresponding to different modes of transportation and energy use can be summarized in the form of a table. The emission factors and low calorific values are automatically associated due to the selection of transportation modes and energy use. In the process of carbon emission and carbon footprint measurement, the corresponding emission factors and low calorific values are obtained by automatically looking up the table according to the corresponding transportation modes and energy use.
[0100] For example, the transportation distance is 2000km, the transportation method is heavy-duty vehicle, the fuel method is diesel, the fuel consumption is 20.0L / km, and the unit carbon emissions of raw material x1 are calculated.
[0101]
[0102] Among them, FCVi is the consumption (t), NCVi is the lower calorific value (GJ / t), CCi is the carbon content per unit calorific value (tC / GJ), and OFi is the carbon oxidation rate (%).
[0103] Then we can get:
[0104]
[0105] Then we can get:
[0106]
[0107] If there are other modes of transportation for purchasing raw materials, the above method should be used to calculate and add them together.
[0108] The carbon emissions per batch of raw materials x1 are calculated as follows:
[0109] Cradle to Gate:
[0110]
[0111] Gate to Gate:
[0112]
[0113] If the purchased raw materials include other raw materials x2, raw material x3, etc. in addition to x1, they should be calculated and entered into the system using the above method.
[0114] Note: Both cradle-to-gate data and gate-to-gate data need to be entered, because the carbon footprint of a product produced by the unit will be calculated later. If a certain raw material used does not have cradle-to-gate data, it will be automatically identified as the cradle-to-gate data of the product cannot be calculated.
[0115] Second data collection port:
[0116] To produce 2000kg of s1 model product, the weight of raw material x1 is 2500kg (Note: product name, model specification, batch number are used as unique identification)
[0117] The first step of the production process - smelting:
[0118] For example, the first process is smelting, two smelting furnaces:
[0119] The first melting furnace, 3t, fixed frequency, power 2000kw;
[0120] The second melting furnace, 500kg, variable frequency, power 350kw;
[0121] When starting production, the smelting process selects the equipment to be used (the first smelting furnace), and other energy is 0. The interface displays the information of the first smelting furnace:
[0122] Enter the boot time at the beginning: 2024 June 1st 9:30
[0123] Enter the end time at the end: 15:00, June 2, 2024
[0124] The device automatically calculates the usage time as 29.5 hours
[0125] The calculation model for this process emission (i.e. the carbon emission of the S1 model product during the production process) is as follows:
[0126] E 1-s1 =AD×EF
[0127] Among them, AD is the electricity amount and EF is the electricity emission factor.
[0128] Then we can get:
[0129] E 1-s1 =(2000kW×29.5h)×0.5568tCO2 / MWh=32851.2kg / CO2e
[0130] Assume that on June 1, 2024, the first smelting furnace works for 14.5 hours and the second smelting furnace works for 10 hours; on June 2, 2024, the first smelting furnace works for 15 hours and the second smelting furnace works for 24 hours;
[0131] Then, on June 1, 2024, the carbon emissions of this process will be:
[0132] E 1-6.1 =(2000kW×14.5h+350kW×10h)×0.5568tCO2 / MWh=18.096kg / CO2eOn June 2, 2024, the carbon emissions of this process are:
[0133] E 1-6.2 =(2000kW×15h+350kW×24h)×0.5568tCO2 / MWh=21.38112kg / CO2e If the carbon emission measurement system needs to check the carbon emissions in June 2024, the production emission data of all data collection ports from June 1, 2024 to June 30, 2024 should be summarized. The same applies to the carbon emission data from June 15, 2024 to July 15, 2024.
[0134] The third data collection port:
[0135] The second step of the production process - electroslag
[0136] For example: There are 5 electroslag furnaces in the electroslag process
[0137] The first electric slag furnace, 200kw, 1t;
[0138] The second electric slag furnace, 200kw, 1t;
[0139] The third electroslag furnace, 150kw, 500kg
[0140] The 4th electroslag furnace, 150kw, 500kg
[0141] The 5th electroslag furnace, 150kw, 500kg
[0142] At the beginning of production, the electroslag process uses the 1st, 2nd, 3rd and 4th electroslag furnaces for processing at different time periods, and no other energy is used. The specific start and stop times of each electroslag furnace are as follows:
[0143] Furnace No. Boot time End Time Production time of s1 model products 1 2024-6-3 8:30 2024-6-3 14:30 7h 2 2024-6-3 10:00 2024-6-3 13:00 3h 3 2024-6-4 10:00 2024-6-4 13:00 3h 4 2024-6-4 10:00 2024-6-4 13:00 3h
[0144] The carbon emission calculation model for the s1 model product during the electroslag process is as follows:
[0145] E 2-s1 =AD×EF
[0146] Among them, AD is the electricity amount and EF is the electricity emission factor.
[0147] Then we can get:
[0148] E 2-s1 =(200kW×7h+200kW×3h+150kW×3h+150kW×3h)×0.5568tCO2 / MWh
[0149] =1614.72kg / CO2e
[0150] Assume that the daily working hours of each electroslag furnace are as follows:
[0151] time Channel 1 Channel 2 Channel 3 Channel 4 Channel 5 2024-6-1 8 8 10 10 10 2024-6-2 9 9 7 8 7
[0152] Then, on June 1, 2024, the carbon emissions of this process will be:
[0153] E 2-6.1 =(200kW×8h+200kW×8h+150kW×10h×3)×0.5568tCO2 / MWh
[0154] =4.2874kg / CO2e
[0155] On June 2, 2024, the carbon emissions of this process are:
[0156] E 2-6.2=(200kW×9h×2+150kW×7h×2+150kW×8h)×0.5568tCO2 / MWh
[0157] =3.8419kg / CO2e
[0158] If the carbon emission measurement system needs to check the carbon emissions in June 2024, the carbon emission data generated by all data collection ports from June 1, 2024 to June 30, 2024 should be summarized. The same applies to checking the carbon emission data from June 15, 2024 to July 15, 2024.
[0159] The 4th data collection port:
[0160] The third step of the production process - forging
[0161] For example: This process uses 1 natural gas heating furnace and 1 500kw forging machine.
[0162] When production starts, the natural gas flow meter bottom code is 0Nm3
[0163] At the end, the natural gas flow meter bottom code is 100Nm3
[0164] Production of s1 type products, start time: 2024-6-5 14:00
[0165] Shutdown time: 2024-6-5 20:00
[0166] Duration: 6h
[0167] Carbon emissions from the forging process of producing S1 products
[0168]
[0169] Among them, FCVi is the consumption (Nm 3 ), NCVi is the lower calorific value (GJ / 10,000 Nm3), CCi is the carbon content per unit calorific value (tC / GJ), and OFi is the carbon oxidation rate (%).
[0170] Then we can get:
[0171]
[0172] E 3-s1-2 =500kW×6h×0.5568tCO2 / MWh=1.6704tCO2e
[0173] E 3-s1 =(0.2162tCO2e+1.6704tCO2e)×1000=1886.619kgCO2e
[0174] Assume that on June 1, 2024, the natural gas furnace burns 500Nm 3 , the forging machine works for 10 hours;
[0175] Natural gas furnace burning natural gas 500Nm on June 2, 2024 3 , the forging machine works for 8 hours;
[0176] Then the carbon emissions of this process on June 1, 2024 are:
[0177]
[0178] If the carbon emission measurement system needs to check the carbon emissions in June 2024, the carbon emission data generated by all data collection ports from June 1, 2024 to June 30, 2024 should be summarized. The same applies to checking the carbon emission data from June 15, 2024 to July 15, 2024.
[0179] The fifth data acquisition port:
[0180] The fourth step in the production process - heat treatment
[0181] For example, this process has a tabletop heating furnace with a power of 520kw;
[0182] Production of s1 type products, start time 2024-6-6 8:30
[0183] End time 2024-6-6 14:30
[0184] Duration: 6h
[0185] Carbon emissions generated during the heat treatment process of producing s1 products:
[0186] E 4-s1 =520kW×6h×0.5568tCO2 / MWh=1737.216kgCO2e
[0187] Assumption: On June 1, 2024, the tabletop heating furnace runs for 15 hours
[0188] 2024-6-2, desktop heating furnace runs for 20 hours
[0189] Then, on June 1, 2024, the carbon emissions of this process will be:
[0190] E 4-6.1 =520kW×15h×0.5568tCO2 / MWh=4.343tCO2e
[0191] On June 2, 2024, the carbon emissions of this process are:
[0192] E4-6.2 =520kW×20h×0.5568tCO2 / MWh=5.7907tCO2e
[0193] If the carbon emission measurement system needs to check the carbon emissions in June 2024, the carbon emission data generated by all data collection ports from June 1, 2024 to June 30, 2024 should be summarized. The same applies to checking the carbon emission data from June 15, 2024 to July 15, 2024.
[0194] The sixth data acquisition port:
[0195] Production process No. 5 - Turning
[0196] For example: this process has a 5kw lathe;
[0197] Production of s1 type products, start time 2024-6-6 16:00
[0198] End time 2021-6-6 22:00
[0199] Duration: 6h
[0200] Carbon emissions from turning process in the production of s1 products:
[0201] E 5-s1 =5kW×6h×0.5568tCO2 / MWh=16.704CO2e
[0202] Assumption: On June 1, 2024, the turning process equipment will run for 10 hours;
[0203] 2024-6-2, the turning process equipment will run for 10 hours;
[0204] Then, on June 1, 2024, the carbon emissions of this process will be:
[0205] E 5-6.1 =5kW×10h×0.5568tCO2 / MWh=0.02784tCO2e
[0206] On June 2, 2024, the carbon emissions of this process are:
[0207] E 5-6.2 =5kW×10h×0.5568tCO2 / MWh=0.02784tCO2e
[0208] The 7th data collection port:
[0209] Production process step 6 - inspection
[0210] For example: this process has a 50w metallographic microscope, a 20kw universal testing tensile machine, and a 1.2kw direct-reading spectrometer. Two samples are taken from this batch of products, with 15 minutes for metallographic microscope, 15 minutes for tensile test, and 10 minutes for direct-reading spectrum.
[0211] Carbon emissions generated during the inspection phase of producing s1 products:
[0212] E 6-s1 =(50W×15min+20kW×15min+1.2kW×10min)×0.5568tCO2 / MWh=2.90232kgCO2e
[0213] Assume that on June 1, 2024, the metallographic microscope is used for 8 hours, the universal testing machine is used for 4 hours, and the direct reading spectrometer is used for 4 hours;
[0214] Then, on June 1, 2024, the carbon emissions of this process will be:
[0215] E 6-6.1 =(50W×8h+20kW×4h+1.2kW×4h)×0.5568tCO2 / MWh=0.04744tCO2e
[0216] The 8th data acquisition port:
[0217] Linked with the human resources system, the attendance distance and commuting method of each employee are recorded, such as public transportation, walking, self-driving fuel vehicles (fuel consumption), self-driving new energy vehicles, and clocking in at work. If the license plate is recognized and the vehicle type is matched with the system, the fuel vehicle will calculate the day's attendance traffic emissions. If the clock-in is not the license plate, it will be counted as public transportation or carpooling, and the day's attendance traffic emissions will not be calculated. Clocking in and out of get off work can calculate the number of people present on the day and the length of time they stay in the company.
[0218] For example: the company has 400 employees and 150 self-driving cars, including 100 fuel vehicles and 50 new energy vehicles. On June 1, 2024, the company has 370 employees on duty, 89 fuel vehicles have been identified, and the total attendance distance is 3560km. Employee A has an attendance distance of 40km. The fuel consumption of the fuel vehicle is 6.8L / 100km, and the fuel is gasoline.
[0219] (1) June 1, 2024, daily traffic emissions:
[0220]
[0221] The emissions from all commuting on that day are equal to the sum of the emissions of each employee who drives their own fuel vehicle.
[0222] (2) June 1, 2024, septic tank escape:
[0223] E 化粪池 =TOW×Bo×MCFj
[0224] Among them, TOW is the total amount of organic degradation, Bo is the maximum methane production capacity (unit: kgCH4 / kgBOD),
[0225] MCFj is the methane correction factor.
[0226]
[0227] If we calculate the carbon emissions of employee attendance on June 1, 2024:
[0228]
[0229] The 9th data collection port:
[0230] canteen
[0231] Input the weight of purchased vegetables, meat, and other foods. The emission factors corresponding to various foods can use existing values. The specific emission factors corresponding to different types of food can be summarized in a table. The emission factors are automatically associated. In the process of carbon emission and carbon footprint measurement, the corresponding emission factors are obtained by automatically looking up the table according to the corresponding food types.
[0232] For example: On June 1, 2024, 80kg of pork and 200kg of vegetables are prepared.
[0233] E 9-食堂1 =80kg×12.1kgCO2 / kg+200kg×2.0kgCO2 / kg
[0234] Enter the natural gas base number before the meal and the natural gas base number at the end of the meal, 2024-6-7 100Nm 3
[0235]
[0236] Enter the amount of kitchen waste per day, recycle it, and ignore the carbon emissions of this part.
[0237] E 9-食堂3 =0
[0238] The 10th data collection port:
[0239] Linked with the electricity meter to distinguish between power and household electricity;
[0240] Enter the power electricity time base code: the daily power consumption is 12000kwh (2024-6-1)
[0241] Enter the basic code of the daily electricity consumption: the daily electricity consumption is 1000kwh (2024-6-1)
[0242] Calculate the carbon emissions from electricity consumption on June 1, 2024:
[0243] E 10-6.1-1 =12000kWh×0.5568tCO2 / MWh=6.6816tCO2e
[0244] Calculate the carbon emissions from household electricity consumption on June 1, 2024:
[0245] E 10-6.1-1 =1000kWh×0.5568tCO2 / MWh=0.5568tCO2e
[0246] Calculation of indirect emissions from electricity on June 1, 2024:
[0247] E 10-6.1 =E 10-6.1-1 +E 10-6.1-2 =7.2384tCO2e
[0248] 11th data collection port:
[0249] Photovoltaic (self-generation and self-use, surplus electricity is connected to the grid)
[0250] Record the photovoltaic power generation base code: the photovoltaic power generation can be obtained
[0251] Record the base code of photovoltaic self-generation and self-use: the photovoltaic power for self-use can be obtained
[0252] Record the photovoltaic surplus power grid-connected basic code: available grid-connected power
[0253] Calculation of emission reduction, for example: On June 1, 2024, the photovoltaic surplus is 500 kWh
[0254] E 减排量 =500kWh×0.5568tCO2 / MWh=0.2784tCO2e
[0255] Then, the company's carbon emissions on June 1, 2024 are equal to the sum of the carbon emissions from the 1st data collection port to the 10th data collection port minus the emission reduction at the 11th data collection port.
[0256] Overall system for carbon emission measurement:
[0257] The user can input the carbon emission query information through the human-computer interaction interface. The carbon emission measurement unit calls the corresponding carbon emission related data in the carbon emission related database and the corresponding carbon emission measurement model in the model database according to the carbon emission query information input by the user, calculates the carbon emission information corresponding to the carbon emission query information, and displays the carbon emission information through the human-computer interaction interface.
[0258] Users can retrieve the carbon emissions of enterprises in any time period through the carbon emission measurement system, which is equal to the attendance emissions of the 8th data collection port + the canteen emissions of the 9th data collection port + the indirect electricity emissions of the 10th data collection port + the sum of the direct emissions of energy used in each production process during that time period.
[0259] Users can retrieve the carbon footprint of any product through the carbon emission measurement system. By entering the product name and production batch number, the system will directly retrieve the types of raw materials used in the product of that batch number and quote its unit carbon emissions and the carbon emissions generated by each process.
[0260] Example: Calculating the carbon footprint of an s1 product
[0261] ①Cradle-gate:
[0262] [2.2732kg / CO2kg×2500kg+(32851.2kgCO2+1614.72kgCO2+1886.619kgCO2+1737.216kgCO2+16.704kgCO2+2.90232kgCO2)] / 2000kg=21.896kgCO2e
[0264] ② Gate – Gate
[0265] (1.2732kg / CO2kg×2500kg+32851.2kgCO2+1614.72kgCO2+1886.619kgCO2+1737.216kgCO2+16.704kgCO2+2.90232kgCO2) / 2000kg=20.64kgCO2e
[0267] The present invention implements all or part of the processes in the above-mentioned embodiment method, and can also be completed by instructing the relevant hardware through a computer program. The computer program can be stored in a computer-readable storage medium. When the computer program is executed by the processor, the steps of each of the above-mentioned method embodiments can be implemented. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable medium may include: any entity or device capable of carrying the computer program code, recording medium, USB flash drive, mobile hard disk, disk, optical disk, computer memory, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), electric carrier signal, telecommunication signal and software distribution medium. It should be noted that the content contained in the computer-readable medium can be appropriately increased or decreased according to the requirements of legislation and patent practice in the jurisdiction. For example, in some jurisdictions, according to legislation and patent practice, computer-readable media do not include electric carrier signals and telecommunication signals.
[0268] Those skilled in the art will appreciate that, although some embodiments herein include certain features included in other embodiments but not other features, the combination of features of different embodiments is meant to be within the scope of the present invention and form different embodiments. For example, in the claims below, any one of the claimed embodiments may be used in any combination.
[0269] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A real-time carbon emission measurement system for an enterprise, characterized in that: It includes a carbon emission measurement system and multiple data entry systems. The carbon emission measurement system has a human-computer interaction interface, a model database, a carbon emission related database, a carbon emission measurement unit and multiple data collection ports. Each of the data entry systems has at least one data entry port. The data entry ports of each data entry system are connected to the data collection ports of the carbon emission measurement system in a one-to-one correspondence. The data entry system is used to collect carbon emission related data of each link in the enterprise operation process in real time or according to a preset data collection frequency; The carbon emission related database is used to store the carbon emission related data collected by the data entry system; The model database is used to store a pre-built carbon emission measurement model; The human-computer interaction interface is used to receive carbon emission query information input by a user and display carbon emission information corresponding to the carbon emission query information; The carbon emission measurement unit is used to call the corresponding carbon emission associated data in the carbon emission associated database and the corresponding carbon emission measurement model in the model database according to the carbon emission query information input by the user in the human-computer interaction interface, calculate the carbon emission information corresponding to the carbon emission query information, and display the carbon emission information through the human-computer interaction interface.
2. The real-time measurement system for enterprise carbon emissions according to claim 1 is characterized in that: The plurality of data entry systems include: The production data entry system is used to enter the carbon emission-related data corresponding to the production stage of the enterprise's products; Office life data entry system, used to enter carbon emission related data corresponding to the office life of enterprise employees; as well as The electricity data entry system is used to enter carbon emission related data of electricity in enterprise production activities and office life activities.
3. The real-time carbon emission measurement system for enterprises according to claim 2 is characterized in that: The plurality of data entry systems also include: The warehousing data entry system is used to enter the carbon emission related data corresponding to the raw materials warehousing stage of the enterprise; and The carbon emission offset data entry system is used to enter carbon emission related data used by enterprises to offset carbon emissions.
4. The real-time measurement system for enterprise carbon emissions according to claim 2 is characterized in that: The number of data entry ports of the production data entry system is the same as the number of processes in the enterprise product production stage, and each data entry port of each production data entry system is used to enter the carbon emission related data of the corresponding process.
5. The real-time measurement system for enterprise carbon emissions according to claim 4 is characterized in that: The carbon emission related data entered into the production data entry system include: The equipment power and on / off time information of the equipment used in each process, as well as the name and usage information of the auxiliary materials that will produce greenhouse gases in each process.
6. The real-time measurement system for enterprise carbon emissions according to claim 2 is characterized in that: The office life data entry system has two data entry ports, one of which is used to enter the carbon emission related data of the enterprise employees' attendance, and the other is used to enter the carbon emission related data of the enterprise employees' dining. The carbon emission-related data of enterprise employee attendance includes the pre-entered information of each employee, attendance distance, transportation used, vehicle type, and employee clock-in information obtained through linkage with the attendance system; The carbon emission-related data for corporate employee dining include the power of equipment used in the company canteen every day, equipment on / off time information, amount of natural gas used, name and weight of purchased food, and weight information of kitchen waste generated.
7. The real-time measurement system for enterprise carbon emissions according to claim 2 is characterized in that: The power data entry system has two data entry ports, one of which is used to enter power electricity data, and the other is used to enter life electricity data. The electricity data entry system enters carbon emission-related data in the production activities and office life activities of the enterprise, including power electricity data and life electricity data.
8. The real-time measurement system for enterprise carbon emissions according to claim 3 is characterized in that: The warehousing data entry system has 1 data entry port. The carbon emission-related data corresponding to the raw material warehousing stage of the enterprise entered into the warehousing data entry system include: Basic information of raw materials and the corresponding unit carbon emissions, basic information of transportation and the corresponding unit carbon emissions, as well as basic information of equipment used for pre-warehousing inspection and the corresponding unit carbon emissions.
9. The real-time measurement system for enterprise carbon emissions according to claim 8 is characterized in that: The basic information of raw materials includes the name, model, specification and batch number of the raw materials; The basic transportation information includes the distance from the raw material manufacturer to the enterprise, the means of transportation and the transportation quantity; The basic information of the equipment used for the pre-warehouse inspection includes the power of the equipment used for the pre-warehouse inspection and the equipment on / off time.
10. The real-time measurement system for enterprise carbon emissions according to claim 3 is characterized in that: The carbon emission offset data entry system has a data entry port. The carbon emission offset data entry system enters the carbon emission related data used by the enterprise to offset the relevant aspects of carbon emissions, including: The types of new energy used and the corresponding usage, as well as the types of waste recycling and the corresponding recycling amounts.
Citation Information
Patent Citations
Iron and steel enterprise carbon emission monitoring method
CN114943480A
Method and system for measuring and calculating carbon emission of industrial park
CN115983671A
Multi-energy complementary enterprise power carbon emission factor conduction calculation method and system
CN116596329A
Carbon emission data monitoring method and system
CN118035310A
Carbon emission metering system combined with factory business digital model
CN118051559A
Cited By
Steel structural member carbon emission calculation method, device, equipment, medium and product
CN119809097A