AGC (Automatic Generation Control) method for new energy of power grid of power system
By constructing a new energy AGC control model and using the multi-objective Harris Eagle optimization algorithm, the problem of action value estimation deviation in the power grid new energy AGC control is solved, and the accuracy and efficiency of the power grid new energy AGC control is achieved.
Patent Information
- Application Number
- CN202411066461.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2024-11-19
AI Technical Summary
The existing technology has overestimated and underestimated action values in the power grid new energy AGC control, resulting in low decision quality and the inability to accurately realize the power grid new energy AGC control.
By determining the objective function and constraints of new energy AGC control, a new energy AGC control model is constructed, and the multi-objective Harris Eagle optimization algorithm is used to optimize the objective function to obtain the power sent by the AGC main station to each new energy power station. Allocation plan.
It realizes the accuracy and efficiency of AGC control of new energy in power grids, overcomes the problem of estimation deviation of action value, and improves the quality of decision-making.
Smart Images

Figure CN118983877A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to power system automation, and in particular to an AGC control method for new energy sources in a power system power grid. Background Art
[0002] With the access of a large number of distributed power sources to the power grid, the disorderly access of large-scale new energy sources has brought new challenges to the stability of the power grid. The power generation control of the traditional power grid adopts PI control, and the power balance of the regional power grid is achieved through the proportional integral controller. The use of automatic generation control (AGC) to balance the power generation of the power plant and the load power on the user side is an important technology to keep the power grid frequency deviation value within the standard range and the interconnection line exchange power not exceeding the planned value.
[0003] In recent years, many scholars have devoted themselves to the research of AGC control methods for renewable energy in power grids and introduced reinforcement learning into power grid AGC controllers. The AGC control algorithm based on reinforcement learning has strong advantages in decision-making, self-learning and self-optimization, making it widely used in AGC control of renewable energy in power grids.
[0004] However, reinforcement learning always has the phenomenon of "overestimation" of action values during the exploration process, which leads to low decision quality. In fact, this problem is inevitable in all reinforcement learning that uses the maximum operator to estimate the next state value. In the prior art, Double DQN technology is generally used to solve the above problem. However, while this method solves the problem of overestimation of action values, it inevitably produces negative deviations and "underestimation" of action values, which is also not conducive to the intelligent agent to explore the optimal strategy, and thus cannot accurately realize the AGC control of new energy in the power grid. Summary of the invention
[0005] 1. Technical issues to be resolved
[0006] In view of the above-mentioned shortcomings of the prior art, the present invention provides a method for controlling the AGC of new energy in a power grid of an electric power system, which can effectively overcome the defect of the prior art that the AGC control of new energy in the power grid cannot be accurately realized.
[0007] (II) Technical solution
[0008] To achieve the above objectives, the present invention is implemented through the following technical solutions:
[0009] A method for controlling new energy AGC in a power system grid determines an objective function of the new energy AGC control and constraints of the new energy AGC control, builds a new energy AGC control model according to the objective function and constraints of the new energy AGC control, performs multi-objective optimization on the new energy AGC control model, and obtains a power distribution plan sent by an AGC master station to each new energy power station.
[0010] Preferably, the determining of the objective function of the new energy AGC control includes:
[0011] S11. Determine the grid regulation requirements;
[0012] S12, determining the remaining regulation amount of the power grid according to the regulation amount issued by the power grid and the execution status of the power grid units;
[0013] S13, according to the grid regulation demand and the remaining grid regulation amount, determine the regulation amount sent by the AGC master station;
[0014] S14, combining the output uncertainty of the new energy power station and the adjustment amount sent by the AGC master station, determining the first objective function of the new energy AGC control;
[0015] S15. Determine the second objective function of the new energy AGC control based on the prescribed mileage fee of the new energy power station unit.
[0016] Preferably, determining the grid regulation demand in S11 includes:
[0017] S111. Determine the power grid control deviation D according to the automatic power generation control mode of the power grid:
[0018] D = k1·a·Δf+k2·ΔTB;
[0019] Among them, Δf is the grid frequency deviation, k1 is the frequency component coefficient, a is the frequency deviation coefficient, ΔTB is the tie line deviation, and k2 is the tie line component coefficient;
[0020] S112, determining the grid regulation demand AD according to the grid control deviation D:
[0021] AD=C1+C2+C3;
[0022] Wherein, C1 is the proportional component, C1=b·D, b is the proportional component gain coefficient;
[0023] C2 is the integral component, C2=c·D I , D I is the integral component of the power grid control deviation D, c is the integral component gain coefficient;
[0024] C3 is the CPS component, C3=d·Δf', Δf' is the grid frequency deviation Δf after filtering, and d is the CPS component gain coefficient.
[0025] Preferably, in S12, determining the remaining regulation amount of the power grid according to the regulation amount issued by the power grid and the execution status of the power grid units includes:
[0026] According to the regulation amount issued by the power grid and the execution status of the power grid units, the remaining regulation amount AQ of the power grid is determined:
[0027]
[0028] Among them, AQ Ti is the target output of the i-th grid unit, AQ Ni is the current output of the i-th grid unit, AQ Ci is the regulation amount issued by the power grid received by the i-th power grid unit, e is the regulation coefficient, e<1, and n is the number of power grid units.
[0029] Preferably, in S13, determining the regulation amount sent by the AGC master station according to the grid regulation demand and the remaining grid regulation amount includes:
[0030] According to the grid regulation demand AD and the grid remaining regulation quantity AQ, determine the regulation quantity AQ' sent by the AGC master station:
[0031] AQ'=AD+AQ.
[0032] Preferably, in S14, the first objective function of the new energy AGC control is determined in combination with the output uncertainty of the new energy power station and the adjustment amount sent by the AGC master station, including:
[0033] S141. Calculate the output uncertainty of new energy power stations ε j :
[0034]
[0035] Among them, ε j is the output uncertainty of the j-th renewable energy power station, P jt , P' jt are the actual maximum power that can be generated and the predicted maximum power that can be generated of the j-th renewable energy power station at time t, respectively. j is the installed capacity of the j-th new energy power station, and m is the number of detection moments;
[0036] S142, combined with the output uncertainty of new energy power stations ε j And the AGC master station sends the adjustment value AQ' to determine the first objective function F1 of the new energy AGC control:
[0037]
[0038] Among them, p jt is the actual power of the jth renewable energy power station at time t, and s is the number of renewable energy power stations.
[0039] Preferably, in S15, based on the prescribed mileage fee of the new energy power station unit, the second objective function of the new energy AGC control is determined, including:
[0040] Based on the stipulated mileage fee E of the new energy power station unit j , determine the second objective function F2 of new energy AGC control:
[0041]
[0042] Among them, E j is the prescribed mileage fee for the j-th renewable energy power station unit.
[0043] Preferably, the multi-objective optimization solution of the new energy AGC control model is performed to obtain a power distribution scheme sent by the AGC master station to each new energy power station, including:
[0044] The multi-objective Harris Hawk optimization algorithm MOHHO is used to perform multi-objective optimization on the first objective function F1 and the second objective function F2, and the power distribution scheme sent by the AGC master station to each new energy power station that meets the constraints is obtained, including:
[0045] S21, randomly generate a Harris hawk population of a certain size and initialize its parameters;
[0046] S22, updating the prey escape energy in the current iteration according to the number of iterations and the initial prey escape energy, and determining whether to enter the global search phase or the local search phase according to the prey escape energy;
[0047] S23, updating the positions of the eagles in the population according to different algorithm stages;
[0048] S24, using the objective function to evaluate each eagle and calculate the corresponding fitness value;
[0049] S25. Use the non-dominated sorting method to sort the eagles in the population and identify the Pareto frontier;
[0050] S26, judging whether the iteration termination condition is met, if not, returning to S22, otherwise taking the current Pareto frontier as the power allocation scheme sent by the AGC master station to each new energy power station that meets the constraint condition.
[0051] Preferably, in S22, judging whether to enter the global search phase or the local search phase according to the prey escape energy includes:
[0052] If the prey escape energy |E|≥1, the global search phase begins, during which the eagle randomly explores the search space to find a potential better solution;
[0053] If the prey escape energy |E| is less than 1, the local search phase is entered, during which the eagle moves toward the optimal solution or randomly selected non-dominated solution in the Pareto frontier and conducts a detailed search to accelerate the convergence process.
[0054] Preferably, in S23, the positions of the eagles in the population are updated according to different algorithm stages, including:
[0055] In the global search phase, the eagles in the population update their positions based on a random position strategy or an average position strategy, which includes:
[0056] The position update based on the random position strategy is expressed as follows:
[0057] P k+1 =P r,k -r1·|P r,k -2r2·P k |;
[0058] Among them, P k is the position of the Harris Hawk at the kth iteration, P k+1 is the position of the Harris Hawk at the k+1th iteration, P r,k is the position of the Harris Hawk randomly selected at the kth iteration, r1 and r2 are both random numbers, r1, r2∈[0,1];
[0059] The position update based on the average position strategy is expressed as follows:
[0060]
[0061] Among them, P L is the position of the optimal solution in the current Pareto frontier, is the average position of the Harris hawk population at the kth iteration, P k+1 is the position of Harris Hawk at the k+1th iteration, ub and lb are the upper and lower bounds of the search space, r3 and r4 are random numbers, r3, r4∈[0,1];
[0062] In the local search phase, the eagles in the population adopt different siege strategies to update their positions based on the prey escape energy |E| and the escape probability λ, including:
[0063] If the prey escape energy |E|≥0.5 and the escape probability λ≥0.5, the eagles in the population adopt a soft siege strategy to update their positions;
[0064] If the prey escape energy |E|<0.5 and the escape probability λ≥0.5, the eagles in the population adopt a hard siege strategy to update their positions;
[0065] If the prey's escape energy |E|≥0.5 and the escape probability λ<0.5, the eagles in the population adopt a cumulative dive soft siege strategy to update their positions;
[0066] If the prey escape energy |E| is less than 0.5 and the escape probability λ is less than 0.5, the eagles in the population adopt a cumulative dive hard siege strategy to update their positions.
[0067] (III) Beneficial effects
[0068] Compared with the prior art, the present invention provides a method for controlling new energy AGC in a power system power grid, determines the objective function of the new energy AGC control and the constraints of the new energy AGC control, constructs a new energy AGC control model according to the objective function and the constraints of the new energy AGC control, and uses the multi-objective Harris Hawk optimization algorithm MOHHO to perform multi-objective optimization and solve the first objective function and the second objective function, and obtains a power distribution plan that meets the constraints and is sent by the AGC master station to each new energy power station, thereby accurately and efficiently realizing the AGC control of new energy in the power grid. BRIEF DESCRIPTION OF THE DRAWINGS
[0069] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0070] Figure 1 It is a schematic diagram of the process of the present invention;
[0071] Figure 2 It is a detailed schematic diagram of the present invention. DETAILED DESCRIPTION
[0072] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0073] A method for controlling new energy sources in an electric power system grid using AGC. Figure 1 and Figure 2As shown, the objective function of the new energy AGC control and the constraints of the new energy AGC control are determined, a new energy AGC control model is constructed according to the objective function and constraints of the new energy AGC control, and the new energy AGC control model is solved by multi-objective optimization to obtain the power distribution plan sent by the AGC master station to each new energy power station.
[0074] ① Determine the objective function of new energy AGC control, including:
[0075] S11. Determine the grid regulation requirements;
[0076] S12, determining the remaining regulation amount of the power grid according to the regulation amount issued by the power grid and the execution status of the power grid units;
[0077] S13, according to the grid regulation demand and the remaining grid regulation amount, determine the regulation amount sent by the AGC master station;
[0078] S14, combining the output uncertainty of the new energy power station and the adjustment amount sent by the AGC master station, determining the first objective function of the new energy AGC control;
[0079] S15. Determine the second objective function of the new energy AGC control based on the prescribed mileage fee of the new energy power station unit.
[0080] Specifically, determining the grid regulation requirements in S11 includes:
[0081] S111. Determine the power grid control deviation D according to the automatic power generation control mode of the power grid:
[0082] D = k1·a·Δf+k2·ΔTB;
[0083] Among them, Δf is the grid frequency deviation, k1 is the frequency component coefficient, a is the frequency deviation coefficient, ΔTB is the tie line deviation, and k2 is the tie line component coefficient;
[0084] S112, determining the grid regulation demand AD according to the grid control deviation D:
[0085] AD=C1+C2+C3;
[0086] Wherein, C1 is the proportional component, C1=b·D, b is the proportional component gain coefficient;
[0087] C2 is the integral component, C2=c·D I , D I is the integral component of the power grid control deviation D, c is the integral component gain coefficient;
[0088] C3 is the CPS component, C3=d·Δf', Δf' is the grid frequency deviation Δf after filtering, and d is the CPS component gain coefficient.
[0089] Specifically, in S12, the remaining regulation amount of the power grid is determined according to the regulation amount issued by the power grid and the execution status of the power grid units, including:
[0090] According to the regulation amount issued by the power grid and the execution status of the power grid units, the remaining regulation amount AQ of the power grid is determined:
[0091]
[0092] Among them, AQ Ti is the target output of the i-th grid unit, AQ Ni is the current output of the i-th grid unit, AQ Ci is the regulation amount issued by the power grid received by the i-th power grid unit, e is the regulation coefficient, e<1, and n is the number of power grid units.
[0093] Specifically, in S13, according to the grid regulation demand and the remaining grid regulation amount, the AGC master station determines the regulation amount to be sent down, including:
[0094] According to the grid regulation demand AD and the grid remaining regulation quantity AQ, determine the regulation quantity AQ' sent by the AGC master station:
[0095] AQ'=AD+AQ.
[0096] Specifically, in S14, the first objective function of the new energy AGC control is determined by combining the output uncertainty of the new energy power station and the adjustment amount sent by the AGC master station, including:
[0097] S141. Calculate the output uncertainty of new energy power stations ε j :
[0098]
[0099] Among them, ε j is the output uncertainty of the j-th renewable energy power station, P jt , P' jt are the actual maximum power that can be generated and the predicted maximum power that can be generated of the j-th renewable energy power station at time t, respectively. j is the installed capacity of the j-th new energy power station, and m is the number of detection moments;
[0100] S142, combined with the output uncertainty of new energy power stations ε j And the AGC master station sends the adjustment value AQ' to determine the first objective function F1 of the new energy AGC control:
[0101]
[0102] Among them, p jtis the actual power of the jth renewable energy power station at time t, and s is the number of renewable energy power stations.
[0103] Specifically, in S15, based on the prescribed mileage fee of the new energy power station unit, the second objective function of the new energy AGC control is determined, including:
[0104] Based on the stipulated mileage fee E of the new energy power station unit j , determine the second objective function F2 of new energy AGC control:
[0105]
[0106] Among them, E j is the prescribed mileage fee for the j-th renewable energy power station unit.
[0107] ② Perform multi-objective optimization on the new energy AGC control model to obtain the power distribution plan sent by the AGC master station to each new energy power station, including:
[0108] The multi-objective Harris Hawk optimization algorithm MOHHO is used to perform multi-objective optimization on the first objective function F1 and the second objective function F2, and the power distribution scheme sent by the AGC master station to each new energy power station that meets the constraints is obtained, including:
[0109] S21, randomly generate a Harris hawk population of a certain size and initialize its parameters;
[0110] S22, updating the prey escape energy in the current iteration according to the number of iterations and the initial prey escape energy, and determining whether to enter the global search phase or the local search phase according to the prey escape energy;
[0111] S23, updating the positions of the eagles in the population according to different algorithm stages;
[0112] S24, using the objective function to evaluate each eagle and calculate the corresponding fitness value;
[0113] S25. Use the non-dominated sorting method to sort the eagles in the population and identify the Pareto frontier;
[0114] S26, judging whether the iteration termination condition is met, if not, returning to S22, otherwise taking the current Pareto frontier as the power allocation scheme sent by the AGC master station to each new energy power station that meets the constraint condition.
[0115] Specifically, in S22, judging whether to enter the global search phase or the local search phase according to the prey escape energy includes:
[0116] 1) If the prey escape energy |E|≥1, the global search phase begins, during which the eagle randomly explores the search space to find a potential better solution;
[0117] 2) If the prey escape energy |E| is less than 1, the local search phase is entered. At this time, the eagle moves to the optimal solution or randomly selected non-dominated solution in the Pareto frontier and conducts a detailed search to accelerate the convergence process.
[0118] Specifically, in S23, the positions of the eagles in the population are updated according to different algorithm stages, including:
[0119] A. In the global search phase, the eagles in the population update their positions based on a random position strategy or an average position strategy, including:
[0120] 1) The location update based on the random location strategy is expressed as follows:
[0121] P k+1 =P r,k -r1·|P r,k -2r2·P k |;
[0122] Among them, P k is the position of the Harris Hawk at the kth iteration, P k+1 is the position of the Harris Hawk at the k+1th iteration, P r,k is the position of the Harris Hawk randomly selected at the kth iteration, r1 and r2 are both random numbers, r1, r2∈[0,1];
[0123] 2) The position update based on the average position strategy is expressed as follows:
[0124]
[0125] Among them, P L is the position of the optimal solution in the current Pareto frontier, is the average position of the Harris hawk population at the kth iteration, P k+1 is the position of Harris Hawk at the k+1th iteration, ub and lb are the upper and lower bounds of the search space, r3 and r4 are random numbers, r3, r4∈[0,1];
[0126] B. In the local search phase, the eagles in the population adopt different siege strategies to update their positions based on the prey's escape energy |E| and the escape probability λ, including:
[0127] 1) If the prey escape energy |E|≥0.5 and the escape probability λ≥0.5, the eagles in the population adopt a soft siege strategy to update their positions;
[0128] 2) If the prey escape energy |E| < 0.5 and the escape probability λ ≥ 0.5, the eagles in the population adopt a hard siege strategy to update their positions;
[0129] 3) If the prey escape energy |E|≥0.5 and the escape probability λ<0.5, the eagles in the population adopt a cumulative dive soft siege strategy to update their positions;
[0130] 4) If the prey escape energy |E| is less than 0.5 and the escape probability λ is less than 0.5, the eagles in the population adopt a cumulative dive hard siege strategy to update their positions.
[0131] The technical solution of the present application determines the objective function of new energy AGC control and the constraints of new energy AGC control, constructs a new energy AGC control model according to the objective function and constraints of new energy AGC control, and uses the multi-objective Harris Hawk optimization algorithm MOHHO to perform multi-objective optimization solution on the first objective function and the second objective function, and obtains the power distribution plan sent by the AGC master station to each new energy power station that meets the constraints, thereby accurately and efficiently realizing the new energy AGC control of the power grid.
[0132] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements will not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for controlling new energy AGC in a power system grid. Features: Determine the objective function of new energy AGC control and the constraints of new energy AGC control, build a new energy AGC control model based on the objective function and constraints of new energy AGC control, and perform multi-objective optimization and solution on the new energy AGC control model to obtain the power distribution plan sent by the AGC master station to each new energy power station.
2. The power system grid new energy AGC control method according to claim 1, Features: The objective function of determining the new energy AGC control includes: S11. Determine the grid regulation requirements; S12, determining the remaining regulation amount of the power grid according to the regulation amount issued by the power grid and the execution status of the power grid units; S13, according to the grid regulation demand and the remaining grid regulation amount, determine the regulation amount sent by the AGC master station; S14, combining the output uncertainty of the new energy power station and the adjustment amount sent by the AGC master station, determining the first objective function of the new energy AGC control; S15. Determine the second objective function of the new energy AGC control based on the prescribed mileage fee of the new energy power station unit.
3. The power system grid new energy AGC control method according to claim 2, Features: S11 determines the grid regulation requirements, including: S111. Determine the power grid control deviation D according to the automatic power generation control mode of the power grid: D=k 1 ·a·Δf+k 2 ·ΔTB; Where Δf is the grid frequency deviation, k 1 is the frequency component coefficient, a is the frequency deviation coefficient, ΔTB is the tie line deviation, k 2 is the tie line component coefficient; S112, determining the grid regulation demand AD according to the grid control deviation D: AD=C 1 +C 2 +C 3 ; Among them, C 1 is the proportional component, C 1 =b·D, b is the proportional component gain coefficient; C 2 is the integral component, C 2 =c·D I , D I is the integral component of the power grid control deviation D, c is the integral component gain coefficient; C 3 is the CPS component, C 3 =d·Δf', Δf' is the grid frequency deviation Δf after filtering, and d is the CPS component gain coefficient.
4. The power system grid new energy AGC control method according to claim 3, Features: In S12, the remaining regulation amount of the power grid is determined according to the regulation amount issued by the power grid and the execution status of the power grid units, including: According to the regulation amount issued by the power grid and the execution status of the power grid units, the remaining regulation amount AQ of the power grid is determined: Among them, AQ Ti is the target output of the i-th grid unit, AQ Ni is the current output of the i-th grid unit, AQ Ci is the regulation amount issued by the power grid received by the i-th power grid unit, e is the regulation coefficient, e<1, and n is the number of power grid units.
5. The power system grid new energy AGC control method according to claim 4, Features: In S13, the AGC master station determines the regulation amount to be sent according to the grid regulation demand and the remaining regulation amount of the grid, including: According to the grid regulation demand AD and the grid remaining regulation quantity AQ, determine the regulation quantity AQ' sent by the AGC master station: AQ'=AD+AQ.
6. The power system grid new energy AGC control method according to claim 5, Features: In S14, the first objective function of the new energy AGC control is determined by combining the output uncertainty of the new energy power station and the adjustment amount sent by the AGC master station, including: S141. Calculate the output uncertainty of new energy power stations ε j : Among them, ε j is the output uncertainty of the j-th renewable energy power station, P jt , P' jt are the actual maximum power that can be generated and the predicted maximum power that can be generated of the j-th renewable energy power station at time t, respectively. j is the installed capacity of the j-th new energy power station, and m is the number of detection moments; S142, combined with the output uncertainty of new energy power stations ε j And the AGC master station sends the adjustment value AQ' to determine the first objective function F of the new energy AGC control 1 : Among them, p jt is the actual power of the jth renewable energy power station at time t, and s is the number of renewable energy power stations.
7. The power system grid new energy AGC control method according to claim 2, Features: In S15, based on the prescribed mileage fee of the new energy power station unit, the second objective function of the new energy AGC control is determined, including: Based on the stipulated mileage fee E of the new energy power station unit j , determine the second objective function F of new energy AGC control 2 : Among them, E j is the prescribed mileage fee for the j-th renewable energy power station unit.
8. The power system grid new energy AGC control method according to claim 1, Features: The multi-objective optimization solution of the new energy AGC control model is performed to obtain the power distribution plan sent by the AGC master station to each new energy power station, including: The multi-objective Harris Hawk optimization algorithm MOHHO is used to optimize the first objective function F 1 and the second objective function F 2 Perform multi-objective optimization to obtain the power distribution plan that satisfies the constraints and that the AGC master station sends to each renewable energy power station, including: S21, randomly generate a Harris hawk population of a certain size and initialize its parameters; S22, updating the prey escape energy in the current iteration according to the number of iterations and the initial prey escape energy, and determining whether to enter the global search phase or the local search phase according to the prey escape energy; S23, updating the positions of the eagles in the population according to different algorithm stages; S24, using the objective function to evaluate each eagle and calculate the corresponding fitness value; S25. Use the non-dominated sorting method to sort the eagles in the population and identify the Pareto frontier; S26. Determine whether the iteration termination condition is met. If not, return to S22. Otherwise, use the current Pareto frontier as the power allocation plan sent by the AGC master station to each new energy power station that meets the constraint condition.
9. The power system grid new energy AGC control method according to claim 8, Features: In S22, the global search phase or the local search phase is entered according to the prey escape energy, including: If the prey escape energy |E|≥1, the global search phase begins, during which the eagle randomly explores the search space to find a potential better solution; If the prey escape energy |E| is less than 1, the local search phase is entered, during which the eagle moves toward the optimal solution or randomly selected non-dominated solution in the Pareto frontier and conducts a detailed search to accelerate the convergence process.
10. The power system grid new energy AGC control method according to claim 9, Features: In S23, the positions of the eagles in the population are updated according to the different stages of the algorithm, including: In the global search phase, the eagles in the population update their positions based on a random position strategy or an average position strategy, which includes: The position update based on the random position strategy is expressed as follows: P k+1 =P r,k -r 1 ·|P r,k -2r 2 ·P k |; Among them, P k is the position of the Harris Hawk at the kth iteration, P k+1 is the position of the Harris Hawk at the k+1th iteration, P r,k is the position of the Harris Hawk randomly selected at the kth iteration, r 1 、r 2 are all random numbers, r 1 、r 2 ∈[0,1]; The position update based on the average position strategy is expressed as follows: Among them, P L is the position of the optimal solution in the current Pareto frontier, is the average position of the Harris hawk population at the kth iteration, P k+1 is the position of the Harris Hawk at the k+1th iteration, ub and lb are the upper and lower bounds of the search space, respectively, and r 3 、r 4 are all random numbers, r 3 、r 4 ∈[0,1]; In the local search phase, the eagles in the population adopt different siege strategies to update their positions based on the prey escape energy |E| and the escape probability λ, including: If the prey escape energy |E|≥0.5 and the escape probability λ≥0.5, the eagles in the population adopt a soft siege strategy to update their positions; If the prey escape energy |E|<0.5 and the escape probability λ≥0.5, the eagles in the population adopt a hard siege strategy to update their positions; If the prey's escape energy |E|≥0.5 and the escape probability λ<0.5, the eagles in the population adopt a soft siege strategy of cumulative dive to update their positions; If the prey escape energy |E| is less than 0.5 and the escape probability λ is less than 0.5, the eagles in the population adopt a cumulative dive hard siege strategy to update their positions.