Automatic paint spraying room

By designing an automatic paint room, using a spray robot and an automatic paint supply system, combined with air supply, exhaust and air purification systems, the environmental problems and inefficiency caused by artificial paint in traditional paint rooms are solved, and unmanned operation is achieved. Health protection and efficient spraying effect.

CN118988636APending Publication Date: 2024-11-22ZHONGYU HEAVY SCI (BEIJING) TECH DEV CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411199658.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

Traditional painting rooms have harsh working environments due to manual painting operations, and the paint mist during workpiece painting is difficult to collect, causing staff to inhale paint smoke, affecting their health and inefficient.

Method used

An automatic paint spray room was designed, including a paint spray room, a paint supply room, a workpiece transportation system, an air supply system, an exhaust system, an air purification system and a central control system. The spraying operation is carried out by using a spray robot and an automatic paint supply system, and the spraying operation is performed through rotation. The mechanism realizes comprehensive spraying, and controls the environment through the air supply and exhaust systems, and sets up air purification and paint mist treatment systems to ensure the cleanliness of the operating environment.

Benefits of technology

Unmanned spray painting operations are achieved, the health of staff is protected, the work efficiency is improved, and the environment is effectively controlled through the automated system, ensuring the high-quality spraying effect of the workpieces.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118988636A_ABST
    Figure CN118988636A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of paint spray booths, in particular to an automatic paint spray booth. Comprising a room body, a paint spraying chamber and a paint supply chamber are arranged in the room body, and a workpiece inlet is formed in one end of the paint spraying chamber; an automatic paint spraying system is arranged in the paint spraying chamber, the automatic paint spraying system communicates with a paint supply system in the paint supply chamber through a paint spraying pipeline, a workpiece conveying system is arranged on one side of the automatic paint spraying system, a rotating mechanism is arranged on the workpiece conveying system, and a workpiece supporting device is arranged on the rotating mechanism; an air supply system and an exhaust system communicating with the interior of the paint spraying chamber are arranged on the outer side of the room body; a paint mist treatment system is arranged at the bottom of the paint spraying chamber, and a lighting system is further arranged in the paint spraying chamber. According to the automatic paint spraying room, paint spraying treatment can be automatically conducted on workpieces, the paint spraying operation can be completed without entering the paint spraying room by workers, the body health of the workers is protected, and the working efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of paint spraying rooms, in particular to an automatic paint spraying room. Background Art

[0002] A spray paint room, as the name implies, is a room where workpieces are sprayed and colored. A spray paint room is a device that provides a special environment for painting operations, which can meet the requirements of painting operations on temperature, humidity, light intensity, air cleanliness, etc. It can limit and treat the paint mist and organic waste gas generated during the painting operation before discharging, and is an environmentally friendly painting equipment.

[0003] In traditional spray painting rooms, workers usually spray paint on workpieces with handheld spray guns. Manual spray painting is time-consuming and laborious. In addition, the paint mist sprayed during spraying is easy to diffuse and difficult to collect, resulting in a bad working environment. Workers inhaling a large amount of paint smoke is likely to cause harm to their health. Therefore, the present invention is proposed. Summary of the invention

[0004] The object of the present invention is to provide an automatic spray paint room, which can automatically spray paint on workpieces, and the painting operation can be completed without the need for workers to enter the spray paint room, thereby protecting the health of the workers and improving work efficiency.

[0005] The present invention provides an automatic spray paint room, comprising a room body, wherein a spray paint room and a paint supply room are arranged inside the room body, and a workpiece entrance is arranged at one end of the spray paint room;

[0006] An automatic paint spraying system is provided inside the paint spraying room, and the automatic paint spraying system is connected to the paint supply system inside the paint supplying room through a paint spraying pipeline;

[0007] A workpiece transport system is provided on one side of the automatic painting system, a rotating mechanism is provided on the workpiece transport system, and a workpiece supporting device is provided on the rotating mechanism;

[0008] The outside of the room is provided with an air supply system and an exhaust system which are connected with the inside of the spray paint room;

[0009] A paint mist treatment system is provided at the bottom of the paint spraying room, and a lighting system is also provided inside the paint spraying room. It also includes an air purification system, a safety alarm system and a central control system. The central control system is connected to the automatic paint spraying system, the paint supply system, the workpiece transportation system, the rotating mechanism, the air supply system, the exhaust system, the safety alarm system and the lighting system.

[0010] Furthermore, the automatic painting system includes a painting robot, a spray gun is provided at the end of the painting robot, and the spray gun is connected to the paint supply system through a paint spray pipe.

[0011] Furthermore, the workpiece transport system comprises an electric slide rail, a slider is provided on the electric slide rail, the rotating mechanism is provided on the slider, and the rotating mechanism adopts an electric rotating table.

[0012] Further, the air supply system includes an air supply fan, the air supply fan is provided with an air suction port, the outlet of the air supply fan is connected to an air supply duct, the air supply duct is provided with an electric heating device, and the outlet of the air supply duct is connected to an air inlet at the top of the spray booth;

[0013] The exhaust system includes an exhaust fan, which is connected to the bottom of the paint spraying room, and an exhaust pipe is provided at the outlet of the exhaust fan, which is connected to the organic waste gas treatment device;

[0014] The air supply fan and the exhaust fan are respectively provided with air volume regulating valves, and the air supply fan, the exhaust fan and the air volume regulating valves are all connected to the central control system.

[0015] Furthermore, the air purification system includes a primary filter and a sub-high efficiency filter, the primary filter is arranged at the inlet of the air blower, a static pressure chamber is arranged at the top of the paint spraying room, and the sub-high efficiency filter is arranged at the bottom of the static pressure chamber.

[0016] Furthermore, a ground grille is provided at the bottom of the spray booth, and the surface of the ground grille is galvanized.

[0017] Furthermore, the paint mist treatment system comprises a dry filter box arranged at the bottom of the ground grille, the outlet of the dry filter box is connected to the exhaust fan, and a filter cotton is arranged at one end of the dry filter box close to the outlet.

[0018] Furthermore, the safety alarm system includes a pressure monitoring device, a combustible gas alarm device, and an organic waste gas concentration alarm device. The pressure monitoring device includes a wind pressure switch and a pressure difference measuring instrument arranged inside the paint spraying room. The inlet and outlet of the blower are respectively provided with the wind pressure switch; the combustible gas alarm device is respectively provided inside the paint spraying room and inside the exhaust duct.

[0019] Furthermore, an electric lifting door is provided at the workpiece entrance, an inspection door is provided on the side wall of the paint spraying room along the length direction; a safety door is provided on the side wall of the paint supply room along the width direction; and walking mechanisms are provided on both sides of the bottom of the room body.

[0020] Furthermore, the lighting system includes multiple groups of explosion-proof lamps, which are respectively arranged on the top and side walls of the paint spraying room. The explosion-proof lamps located on the top are installed at an angle of 45°, and the illumination of the explosion-proof lamps is ≥700Lux.

[0021] In summary, the technical solution provided by the present invention has the following advantages compared with the prior art:

[0022] The technical solution provided by the present invention is to arrange a workpiece transportation system inside the paint spraying room, so as to facilitate the direct transfer of the workpiece to the automatic paint spraying system, and use the automatic paint spraying system to spray the workpiece. The arranged rotating mechanism facilitates comprehensive spraying of the workpiece. The arranged air supply system, exhaust system, air purification system and paint mist treatment system meet the requirements of the paint spraying operation for the temperature, humidity and cleanliness of the environment, and can form a good working environment. The arranged central control system facilitates the staff to control each system. During the spraying operation, the staff only needs to operate the central control system and does not need to enter the paint spraying room, which protects the health of the staff and improves work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0024] Figure 1 This is a front view of the automatic spray paint room in the embodiment of the present invention;

[0025] Figure 2 A top view of an automatic spray paint room in an embodiment of the present invention;

[0026] Figure 3 It is a right view of the automatic spray paint room in the embodiment of the present invention.

[0027] Explanation of the reference numerals: 1-paint supply room; 2-paint spraying room; 201-static pressure room; 3-spraying robot; 4-electric slide rail; 5-slider; 6-rotating mechanism; 7-electric trolley; 8-ground grille; 9-dry filter box; 10-electric lifting door; 11-inspection door; 12-air blower; 1201-electric heating device; 13-exhaust fan; 14-exhaust duct; 15-safety door; 16-explosion-proof lamp. DETAILED DESCRIPTION

[0028] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0029] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0030] In addition, the terms "first" and "second" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, "multiple" means two or more, unless otherwise clearly and specifically defined. In addition, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal connection of two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0031] Example

[0032] An automatic spray paint room, such as Figure 1 , Figure 2 and Figure 3 As shown, it includes a room body, a partition is provided inside the room body, which divides the room body into a paint spraying room 2 and a paint supply room 1, and a workpiece entrance is provided at the end of the paint spraying room 2 away from the paint supply room 1; an automatic paint spraying system is provided inside the paint spraying room 2, and a paint supply system is provided inside the paint supply room 1, and the automatic paint spraying system is connected with the paint supply system through a paint spraying pipe; a workpiece transportation system is provided on one side of the automatic paint spraying system, a rotating mechanism 6 is provided on the workpiece transportation system, and a workpiece supporting device is provided on the rotating mechanism 6; an air supply system and an exhaust system connected with the interior of the paint spraying room 2 are provided on the outside of the room body; a paint mist treatment system is provided in the pit at the bottom of the paint spraying room 2, and a lighting system is also provided inside the paint spraying room 2, and also includes an air purification system, a safety alarm system and a central control system, and the central control system is connected with the automatic paint spraying system, the paint supply system, the workpiece transportation system, the rotating mechanism 6, the air supply system, the exhaust system, the safety alarm system, and the lighting system.

[0033] The automatic painting system includes a spraying robot 3, which is provided with a spray gun at the end thereof. The spray gun adopts an air atomizing automatic spray gun, which is connected to the paint supply system through a paint spray pipe, and the paint supply system adopts an automatic paint supply system. The automatic paint supply system has functions such as liquid level alarm, automatic stirring, flow control, paint filtration, and automatic cleaning. It is equipped with an automatic stirrer, a pressure gauge, etc. The paint is directly poured into a bucket after being manually mixed. A waste liquid recovery device is provided to avoid contamination of the spray room when the robot cleans the spray gun. The operation process of replacing the paint and treating the waste liquid can be realized without personnel entering the spray room. The spraying robot 3 adopts the Kawasaki KJ194 explosion-proof spraying robot, which is located in the middle of the spray room 2 near one end of the paint supply room 1. The spraying robot 3 is equipped with a robot teaching system and a control system. The spraying robot 3 should be equipped with a protective clothing seal (detachable) to prevent excess paint mist from depositing and affecting the operation of the equipment. The robot teaching system has a program storage function, which is stored in the PLC of the control system according to the type and part number of the workpiece. The painting data and parameters of each workpiece are also written into the PLC system through debugging. The operator only needs to input the workpiece number into the touch screen and turn on the paint start switch to automatically paint the workpiece.

[0034] The workpiece transport system is located on one side of the spray robot 3, including an electric slide rail 4 arranged along the length direction of the spray booth 2, a slider 5 is provided on the electric slide rail 4, a rotating mechanism 6 is installed on the slider 5, and the rotating mechanism 6 adopts an electric rotating table, which can achieve 0-360° rotation. A workpiece support device is installed on the electric rotating table. In order to achieve a complete spraying of the workpiece, the workpiece support device can adopt a three-point support method. The distance between the workpiece and the table of the electric rotating table is >500mm, and the working space of the spray robot 3 and the spray gun is reserved to ensure that the spray gun can spray paint in all directions without dead angles.

[0035] The spray booth 2 adopts the top fresh air supply and the bottom exhaust to ensure the slight negative pressure in the room. The air supply system includes a blower 12, which is provided with an air suction port, and the outlet of the blower 12 is connected to the air supply duct, and the outlet of the air supply duct is connected to the air inlet at the top of the spray booth 2. An electric heating device 1201 is provided on the air supply duct to meet the painting operation under harsh environmental conditions. When the ambient temperature is low, the electric heating device 1201 is started to heat the gas entering the spray booth 2. When the ambient temperature is normal, the electric heating device 1201 does not need to be started. The number of electric heating devices 1201 can be set as needed. The exhaust system includes an exhaust fan 13, the inlet of the exhaust fan 13 is connected to the pit at the bottom of the spray booth 2, the outlet of the exhaust fan 13 is connected to the exhaust pipe 14, the exhaust pipe 14 is connected to the organic waste gas treatment device, and the treated tail gas is discharged through the chimney.

[0036] Air volume regulating valves are installed on the air supply fan 12 and the exhaust fan 13 respectively, which are used to adjust the proportion and size of the air volume to ensure the wind speed requirements in the spray booth 2. The air volume regulating valve uses a flap type regulating valve, which is controlled by an electric actuator. The control systems of the air supply fan 12 and the exhaust fan 13 and the electric actuator of the air volume regulating valve are all connected to the central control system. The exhaust volume in the spray booth 2 is 110-120% of the supply volume, ensuring a slight negative pressure state in the room.

[0037] The air purification system adopts a two-stage filtration method, including a primary filter and a sub-high efficiency filter. The primary filter is located at the inlet of the blower 12. A static pressure chamber 201 is provided at the top of the spray booth 2, and the sub-high efficiency filter is located at the bottom of the static pressure chamber 201. The primary filter uses domestic high-quality non-woven cotton, which is a sheet structure and can effectively capture dust particles with a diameter greater than 15μm; the sub-high efficiency filter uses CC-600G precision filter cotton produced in the Netherlands. The filter cotton has a multi-layer structure and can filter 100% of dust above 5μm in the air. The sub-high efficiency filter is supported by a top net, which is welded with high-quality C-shaped steel and galvanized. It has good rigidity, no rust, and is easy to replace the top cotton.

[0038] The floor inside the spray booth 2 is provided with a ground grille 8, and the surface of the ground grille 8 is galvanized. The grille is made of 40mmx3mm flat steel placed vertically, with a steel plate spacing of 40mm, and round steel is used as a reinforcement rib, welded, and laid on a frame made of steel. The weight of a single grille is controlled to be 20Kg, which is convenient for taking out the grille, maintaining and repairing the equipment in the pit, and cleaning the pit.

[0039] The paint mist treatment system processes the paint mist generated during painting and adopts a two-pass bottom filtration method, such as Figure 3 As shown, it includes a dry filter box 9 arranged in a pit at the bottom of the ground grille 8. The outlet of the dry filter box 9 is connected to the exhaust fan 13. The end of the dry filter box 9 close to the outlet is provided with filter cotton to fully absorb the paint mist. The modular design is adopted for easy replacement and maintenance. The spray and exhaust gas generated by the spraying operation are treated by the dry filter box 9 and the filter cotton under the exhaust action of the exhaust fan 13, and then sent to the organic waste gas treatment device by the exhaust pipe 14. After being treated, it is discharged through the chimney. The organic waste gas treatment device can adopt the conventional waste gas treatment device in the prior art, such as zeolite molecular sieve adsorption + online desorption + catalytic combustion + exhaust pipe greater than 15m.

[0040] The safety alarm system includes a pressure monitoring device, a combustible gas alarm device, and an organic waste gas concentration alarm device. The pressure monitoring device monitors the pressure changes in the paint spray booth 2 at any time. When the pressure exceeds the set value, it alarms and forces the machine to shut down to prevent changes in the chamber structure. The pressure monitoring device can also indirectly monitor the working condition of the fan unit. The pressure monitoring system includes a wind pressure switch and a differential pressure measuring instrument arranged inside the paint spray booth 2. The differential pressure measuring instrument detects the pressure inside the paint spray booth 2. When the differential pressure reaches or exceeds the set value, it automatically alarms. Wind pressure switches are respectively provided at the inlet and outlet of the air blower 12. When the differential pressure is lower than the set value, the control system alarms and the air blower 12 automatically stops working.

[0041] Combustible gas alarm devices are respectively provided inside the spray booth 2 and inside the exhaust duct 14. Two probes are installed inside the spray booth 2 and one probe is installed inside the exhaust duct 14. The vapor volatilized by the flammable gas or flammable liquid is monitored. When the concentration reaches or exceeds the set alarm concentration, the alarm controller will sound an alarm to prompt the operator to take safety measures, thereby playing a role in ensuring the safe production of the factory, avoiding major fire and explosion accidents, and reminding that the exhaust gas exceeds the standard. The organic waste gas concentration alarm device is installed at the front end of the discharge outlet of the organic waste gas treatment device to detect the discharged waste gas and sound an alarm when it exceeds the set value.

[0042] The lighting system includes multiple groups of explosion-proof lamps 16, which are respectively arranged on the top and side walls of the spray booth 2. The explosion-proof lamps 16 located on the top are installed at a 45° angle, and the illumination of the explosion-proof lamps 16 is ≥700Lux. At the same time, an explosion-proof emergency lighting lamp is installed at the entrance of the workpiece.

[0043] A video surveillance system is also set up in the spray booth 2, equipped with multiple explosion-proof surveillance cameras to monitor the on-site working status in real time. The video surveillance system is only connected to the computer brought by the equipment, and is equipped with 6 surveillance cameras, including 5 explosion-proof surveillance cameras and 1 ordinary surveillance camera. The camera is industrial-grade, 400W pixels, zoom control, high video resolution, clear image, good color reproduction, less noise under low illumination, and can automatically switch filters in daytime and night modes. The network cable uses Category 6 shielded cable, and the surveillance camera uses POE power supply. The video surveillance is only connected to the hard disk recorder, and the real-time video monitoring of the on-site working status. The line needs to be hidden in the operation area. If it cannot be hidden due to structural limitations, it must be beautiful and coordinated with the surrounding environment. The lines, power supplies and transmission equipment need to be industrial-grade protected. The aggregation line uses anti-corrosion sprayed metal wire troughs, the branches use galvanized iron pipes, and explosion-proof treatment pipelines are required locally.

[0044] An electric trolley 7 is provided outside the spray booth, and the electric trolley 7 adopts an AGV automatic transport vehicle, which is used to transport the workpiece into the spray booth 2 and transfer it to the workpiece support device of the electric rotating table. After the spray painting operation is completed, the electric trolley 7 transfers the workpiece out of the spray booth 2.

[0045] A hand-push access door 11 is installed at one end of the side wall in the length direction near the workpiece entrance of the paint spray booth 2. The door panel is made of 304 stainless steel and has a glass window on it to facilitate observation of the indoor working conditions. An electric lifting door 10 is installed at the workpiece entrance; a safety door 15 is set on the side wall in the width direction of the paint supply booth 1. A walking mechanism that can move on the ground can be set on both sides of the bottom of the room body, and it can be designed as an integral mobile paint spray booth. The room body is made of rock wool insulation steel plate and steel reinforcement. The thickness of the inner and outer wall color steel plate is 0.6mm. The color steel plate material is Q235. The insulation layer is filled with thermal insulation rock wool with a thickness of 50mm and a rock wool bulk density of 100kg / m. A temperature and humidity sensor is also installed inside the paint spray booth 2 to monitor the temperature and humidity inside the paint spray booth 2.

[0046] It is also equipped with an electrical control cabinet that is convenient for operating the central control system. The electrical control cabinet is arranged at a designated location. The central control system adopts PLC automatic control, and can also be manually operated, with automatic and manual operation gears. Manual control is used for debugging and maintenance of the device, and automatic control has the functions of automatic sequential start, operation, switching, and shutdown. After a fault, it can automatically cut off the power to ensure safe operation.

[0047] The electrical control equipment should be interlocked, the system should have self-diagnosis function, and the electrical control cabinet should be equipped with fault sound and light alarm. If the fan fails to operate or other faults occur, the main power supply can be automatically cut off, the machine can be automatically shut down, and an alarm can be issued. The central control system has safety protection functions, such as short-circuit protection. The electrical control cabinet should be dustproof and waterproof, and the minimum nominal value of the shell protection level should be IP44, and the explosion-proof level should not be lower than EXdⅡCT4. All electrical equipment configured in the spray paint room draws power from the electrical control cabinet, and an electric meter is installed in the cabinet, and a transparent window is made so that the power consumption can be read without opening the cabinet door to meet the environmental protection inspection requirements.

[0048] The operation mode of the automatic spray painting room provided by the present invention is as follows: before the painting operation, the electric trolley 7 in the workshop is used to transport the workpiece to the electric rotating table of the slider 5, the electric trolley 7 leaves the spray painting room 2, the central control system closes the electric lifting door 10, starts the air intake fan 12 and the exhaust fan 13, so that the pressure in the spray painting room 2 meets the spraying demand, and then starts the electric slide 4, the slider 5 moves to the side of the spraying robot 3, starts the automatic paint supply system and the automatic spray painting system, the spraying robot 3 uses a spray gun to spray the workpiece, and starts the electric rotating table to rotate at the same time, and sprays the workpiece comprehensively. The paint mist generated during the spraying process is treated by the paint mist treatment system, and then transported to the organic waste gas device for treatment by the exhaust fan 13 and the exhaust pipe 14, and discharged through the chimney after treatment. After the spraying work is completed, the electric lifting door 10 is opened, the electric slide 4 moves the slider 5 and the electric rotating table to the entrance of the workpiece, and the electric trolley 7 transfers the workpiece out of the spray painting room 2.

[0049] The automatic spray paint room provided by the present invention is mainly used for the painting operations of the base, middle and top coats of pump products and their workpieces. The room body is integrally movable and is a fully sealed space, forming a limited place for painting operations. An air supply system, an exhaust system, an air purification system and a paint mist treatment system are provided to meet the requirements of the painting operation for the temperature, humidity and cleanliness of the environment, forming a good working environment. A central control system is configured for fully automatic operation, and can automatically complete the workpiece transfer and workpiece spraying, thereby protecting the health of the staff and improving work efficiency.

[0050] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. An automatic spray paint room, characterized in that: It comprises a room body, wherein a paint spraying room and a paint supply room are arranged inside the room body, and a workpiece entrance is arranged at one end of the paint spraying room; An automatic paint spraying system is provided inside the paint spraying room, and the automatic paint spraying system is connected to the paint supply system inside the paint supplying room through a paint spraying pipeline; A workpiece transport system is provided on one side of the automatic painting system, a rotating mechanism is provided on the workpiece transport system, and a workpiece supporting device is provided on the rotating mechanism; The outside of the room is provided with an air supply system and an exhaust system which are connected with the inside of the spray paint room; A paint mist treatment system is provided at the bottom of the paint spraying room, and a lighting system is also provided inside the paint spraying room. It also includes an air purification system, a safety alarm system and a central control system. The central control system is connected to the automatic paint spraying system, the paint supply system, the workpiece transportation system, the rotating mechanism, the air supply system, the exhaust system, the safety alarm system and the lighting system.

2. The automatic spray paint room according to claim 1, characterized in that: The automatic painting system comprises a painting robot, a spray gun is arranged at the end of the painting robot, and the spray gun is connected with the paint supply system through a paint spray pipe.

3. The automatic spray paint room according to claim 1, characterized in that: The workpiece transport system comprises an electric slide rail, a slider is arranged on the electric slide rail, the rotating mechanism is arranged on the slider, and the rotating mechanism adopts an electric rotating table.

4. The automatic spray paint room according to claim 1, characterized in that: The air supply system includes an air supply fan, the air supply fan is provided with an air suction port, the outlet of the air supply fan is connected to an air supply duct, an electric heating device is provided on the air supply duct, and the outlet of the air supply duct is connected to an air inlet at the top of the spray booth; The exhaust system includes an exhaust fan, which is connected to the bottom of the spray booth; an exhaust pipe is provided at the outlet of the exhaust fan, and the exhaust pipe is connected to the organic waste gas treatment device; The air supply fan and the exhaust fan are respectively provided with air volume regulating valves, and the air supply fan, the exhaust fan and the air volume regulating valves are all connected to the central control system.

5. The automatic spray paint room according to claim 4, characterized in that: The air purification system comprises a primary filter and a sub-high efficiency filter, wherein the primary filter is arranged at the inlet of the blower, a static pressure chamber is arranged at the top of the spray booth, and the sub-high efficiency filter is arranged at the bottom of the static pressure chamber.

6. The automatic spray paint room according to claim 5, characterized in that: A ground grille is provided at the bottom of the spray booth, and the surface of the ground grille is galvanized.

7. The automatic spray paint room according to claim 6, characterized in that: The paint mist treatment system comprises a dry filter box arranged at the bottom of the ground grille, the outlet of the dry filter box is connected to the exhaust fan, and filter cotton is arranged at one end of the dry filter box close to the outlet.

8. The automatic spray paint room according to claim 7, characterized in that: The safety alarm system includes a pressure monitoring device, a combustible gas alarm device, and an organic waste gas concentration alarm device. The pressure monitoring device includes a wind pressure switch and a pressure difference measuring instrument arranged inside the paint spraying room. The inlet and outlet of the blower are respectively provided with the wind pressure switch; the combustible gas alarm device is respectively provided inside the paint spraying room and inside the exhaust duct.

9. The automatic spray paint room according to claim 1, characterized in that: An electric lifting door is provided at the workpiece entrance, an inspection door is provided on the side wall of the spray paint room along the length direction; a safety door is provided on the side wall of the paint supply room along the width direction; and walking mechanisms are provided on both sides of the bottom of the room body.

10. The automatic spray paint room according to claim 1, characterized in that: The lighting system includes multiple groups of explosion-proof lamps, which are respectively arranged on the top and side walls of the paint spraying room. The explosion-proof lamps located on the top are installed at an angle of 45°, and the illumination of the explosion-proof lamps is ≥700Lux.