Integral manufacturing method of curved steel arch bridge

By assembling the curved steel arch bridge in the workshop and then performing the exterior assembly, the problem of parts being easily affected by weather during the off-site assembly in the prior art is solved, and the assembly accuracy and manufacturing efficiency are improved.

CN118997014APending Publication Date: 2024-11-22NANTONG ZHENHUA HEAVY EQUIP MFG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411391809.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-08
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

In the existing method of manufacturing curved steel arch bridges, the assembly of parts manufactured in segments is easily affected by the weather when assembling off-site, and the equipment is insufficient, which affects the assembly accuracy.

Method used

The curved steel arch bridge is divided into arch ribs, hanging rods, side beams, vertical and horizontal connecting beams, and supporting beams. Part of the interior of the workshop is assembled and then transported to the exterior yard for assembly. The workshop resources are used to reduce the impact of exterior yard assembly and hoisting equipment.

Benefits of technology

It improves assembly accuracy, reduces the impact of field assembly and lifting equipment, and improves overall manufacturing efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997014A_ABST
    Figure CN118997014A_ABST
Patent Text Reader

Abstract

The invention provides an integral manufacturing method of a curved steel arch bridge, relates to the technical field of building structure construction, and solves the problems that in the prior art, the curved steel arch bridge manufacturing method mostly conveys parts manufactured in a segmented mode to a construction site to be spliced, so that the parts are easily influenced by off-site weather, meanwhile, off-site splicing equipment is few, and the construction cost is low. The influence on the assembly of parts with high requirements on the assembly precision of part sizes is large. According to the technical scheme, arch bridge components are reasonably divided, and part of the arch bridge components are transported to the outside for final assembly after being assembled in the field; workshop resources can be fully utilized, the influence of outfield total splicing weather and hoisting equipment is reduced, and meanwhile the splicing precision is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge manufacturing, and in particular to an integral manufacturing method for a curved steel arch bridge. Background Art

[0002] The curved steel arch bridge is a new type of structural form, which is characterized by a high-strength steel structure. Due to its complex geometric shape and large size, the overall manufacturing is difficult and has high requirements for processing equipment and technology. Therefore, it is mostly manufactured in sections. The manufacturing method in the existing technology mostly transports the parts manufactured in sections to the construction site for assembly, which is easily affected by the weather outside the site. At the same time, there are fewer assembly equipment outside the site, which has a greater impact on the assembly of parts with high assembly accuracy requirements for some sizes. Summary of the invention

[0003] Therefore, the present invention solves the technical problem that the manufacturing methods of curved steel arch bridges in the prior art mostly transport the various parts manufactured in sections to the construction site for assembly, which is easily affected by the weather outside the site and there are fewer assembly equipment outside the site, which has a greater impact on the assembly of parts with high assembly accuracy requirements for some sizes. The present invention provides an overall manufacturing method for a curved steel arch bridge, which reasonably divides the arch bridge components, assembles some of them on site and then transports them to the off-site for final assembly, fully utilizing workshop resources, reducing the impact of weather and lifting equipment on the final assembly outside the site, and improving assembly accuracy.

[0004] The present invention provides a method for integrally manufacturing a curved steel arch bridge, comprising the following steps:

[0005] S1: The curved steel arch bridge is divided into arch ribs, hangers, side beams, longitudinal and transverse connecting beams, and support beams;

[0006] S2: Independent processing of arch ribs, hangers, side beams, longitudinal and transverse connecting beams, and support beams;

[0007] S3: After the arch ribs and side beams are assembled in the workshop, they are transported to the field together with the hangers, longitudinal and transverse connecting beams, and support beams for assembly.

[0008] Preferably, in step S2, the arch rib is segmented into 29 small segments for processing; the arch rib material is S690QL.

[0009] Preferably, the average length of a single segment arch rib is 3000mm-4000mm, the cross-section is 1000*1000mm, the four corner welds are all full penetration welds, the four edges and the hanger connecting plate are all full penetration welds, the hanger connecting plate material is S690QL, and hanger connecting plates are provided on the sides of single segment arch ribs to facilitate subsequent hanger installation.

[0010] Preferably, when processing a single segment arch rib, first position the two arch rib bottom plates and then install the partition tooling, and then install the other two arch rib bottom plates. After welding the arch rib, remove the partition tooling. The partition tooling can ensure the welding accuracy of the single segment arch rib.

[0011] Preferably, during the assembly process of the arch rib workshop in step S3, 29 small segments are first assembled into 5 large segments indoors. During the assembly process, the small segments are hoisted onto the arch rib large segment assembly line frame, and the hanger connecting plate is assembled. After the second segment is assembled with the hanger connecting plate, symmetrical welding is performed, and then the large segment is transported to the field for assembly.

[0012] Preferably, the longitudinal and transverse connecting beams in step S2 are I-beam structures, and the I-beam components are prefabricated in advance.

[0013] Preferably, the specific processing steps of the support beam in step S2 are as follows:

[0014] S21: Arrange the crossbeams to assemble the tire frame. The tire frame is made of a standard tire frame and is precisely adjusted with a tooth plate. The tire frame is longitudinally arranged at the position of the partition inside the support crossbeam;

[0015] S22: Hoist the crossbeam bottom plate to the assembly cradle, position and adjust the position, check the vertical and horizontal reference lines of the bottom plate unit and the partition assembly line. The cradle should be arranged longitudinally at the partition position inside the support crossbeam to ensure that the cradle is aligned with the rib plate structure;

[0016] S23: The middle cross bridge is positioned and assembled towards the partition, and the partition is hoisted to the bottom plate unit assembly line. The partition unit and the bottom plate are positioned and welded, and the process support for welding the partition unit is installed before the hook can be loosened;

[0017] S24: Position and assemble the longitudinal bridge partition, hoist the longitudinal bridge partition to the partition assembly line on the bottom plate, check the installation dimensions, spot weld and position, and fix with process supports; process supports are brackets that support inclined components to prevent such components from falling during welding;

[0018] S25: Position and assemble the cross bridge to the outer web, hoist the cross bridge to the outer web, and measure the diagonal size of the box opening to adjust the web positioning size;

[0019] S26: Position and assemble the inclined webs of the longitudinal bridge to the outside, hoist the inclined webs of the longitudinal bridge to the outside, spot weld the inclined webs and the transverse bridge webs, and support the outer webs with process braces;

[0020] S27: The longitudinal bridge is positioned and assembled toward the outer web plate, and a manhole is opened in the enclosed space inside the box to facilitate the entry and exit of personnel in the enclosed space for welding. After the welding of the internal space is completed, the manhole is blocked;

[0021] S28: Top plate positioning and assembly, top plate unit overall hoisting and positioning, completion of top plate and bulkhead, outer web welding;

[0022] S29: Hoisting, transportation, and painting. After the box body is welded, it is transported to the painting workshop using a hydraulic flatbed truck for sandblasting and painting, and the welding position is protected by paint.

[0023] Preferably, the side beams are manufactured in sections in a workshop according to the size of the entire bridge, and then transported as a whole to the outside site by a module vehicle, and the ring openings are directly matched and docked.

[0024] Preferably, the steps of installing the suspension rod in S3 are as follows:

[0025] S31: Measure the dimensions of the arch rib connection plate and the edge beam connection plate, trim the hanger rod margin and open the groove;

[0026] S32: The boom is hoisted by tooling. After the boom is hoisted into place, the upper and lower ends of the boom are adjusted to align with the connecting plate and fixed with a kama;

[0027] S33: The hangers are assembled and welded from the middle of the main bridge to both sides in sequence. The hangers are hoisted by a gantry crane. To ensure the hoisting strength, a 120T gantry crane can be used. The hangers are adjusted to the specified state through the coordination of the main and auxiliary hooks. After all the hangers are installed and welded, the force conversion of the entire arch rib bridge can be realized.

[0028] Preferably, the tooling of S32 is a detachable fixture, which can realize the installation of different suspension rods.

[0029] Compared with the prior art, the present invention has the following advantages:

[0030] 1. The overall manufacturing method of the curved steel arch bridge provided by the present invention reasonably divides the main parts of the curved steel arch bridge into five parts: arch ribs, hangers, side beams, longitudinal and transverse connecting beams, and support cross beams. Each part is independently processed to improve processing efficiency and reduce processing difficulty; the arch ribs and side beams with assembly accuracy requirements are assembled in the workshop to make full use of workshop resources and reduce the impact of weather and lifting equipment in the field; a total station is set in the workshop to accurately control the positioning size of each segment and strictly control the segment erection accuracy.

[0031] 2. The overall manufacturing method of the curved steel arch bridge provided by the present invention is to first position two arch rib bottom plates and then install the partition tooling when processing a single segment arch rib, and then install another two arch rib bottom plates. After welding the arch rib, the partition tooling is removed; the partition tooling is embedded in the arch rib segment and fixedly connected by pins, which is convenient for disassembly and reuse. The partition tooling can control the deformation of the arch rib welding to ensure the overall size of the small arch rib segment.

[0032] 3. The overall manufacturing method of the curved steel arch bridge provided by the present invention realizes the hoisting and installation of different types of hangers by designing a special adjustable and detachable clamp. The clamp is clamped on the hanger and the gantry crane lifts the clamp to reduce the possibility of deformation of the hanger. The hanger installation connects the hanger connecting plate on the arch rib with the hanger connecting plate on the lower side beam. After the hanger is installed, the transmission of force between the arch rib and the side beam is realized. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0034] Figure 1 This is a model diagram of a curved steel arch bridge of the present invention;

[0035] Figure 2 It is a schematic diagram of the partial structure after the arch rib, the hanger rod, the side beam, the longitudinal and transverse connecting beams, and the support beam are assembled in the present invention;

[0036] Figure 3 This is a schematic diagram of the partition tooling structure of the present invention;

[0037] Figure 4 This is a schematic diagram of the connection between the crossbeam bottom plate and the cross-bridge partition of the present invention;

[0038] Figure 5 It is a schematic diagram of the connection of the transverse bridge partition, the longitudinal bridge partition, the transverse bridge outer web, the longitudinal bridge outer inclined web, and the longitudinal bridge outer web of the present invention;

[0039] Figure 6 It is a schematic diagram of the top plate structure of the present invention;

[0040] Figure 7 It is a schematic diagram of the detachable clamp structure of the present invention;

[0041] Figure 8 This is a schematic diagram of a single-stage arch rib structure of the present invention;

[0042] Fig. 9 This is a schematic diagram of the single-section side beam structure of the present invention;

[0043] Description of reference numerals:

[0044] 1. Arch rib; 2. Hanger; 3. Side beam; 4. Longitudinal and transverse connecting beams; 5. Support beam; 6. Partition tooling; 7. Beam bottom plate; 8. Transverse bridge to partition; 9. Longitudinal bridge to partition; 10. Transverse bridge to outer web; 11. Longitudinal bridge to outer inclined web; 12. Longitudinal bridge to outer web; 13. Top plate; 14. Removable clamp. DETAILED DESCRIPTION

[0045] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0046] Example 1

[0047] The overall manufacturing method of the curved steel arch bridge provided in this embodiment includes the following steps:

[0048] S1: The curved steel arch bridge is divided into arch rib 1, hanger 2, side beam 3, longitudinal and transverse connecting beams 4, and support beam 5;

[0049] S2: independently process the arch rib 1, the hanger 2, the side beam 3, the longitudinal and transverse connecting beams 4, and the support beam 5;

[0050] S3: After the arch rib 1 and the side beam 3 are assembled in the workshop, they are transported to the field together with the hanger 2, the longitudinal and transverse connecting beams 4 and the support cross beam 5 for assembly.

[0051] like Figure 1 As shown in the figure, the main parts of the curved steel arch bridge are reasonably divided into five parts: arch rib 1, hanger 2, side beam 3, longitudinal and transverse connecting beam 4, and support cross beam 5. Each part is processed independently to improve processing efficiency and reduce processing difficulty; the arch rib 1 and side beam 3 with high assembly accuracy requirements are assembled in the workshop to make full use of workshop resources and reduce the impact of weather and hoisting equipment on the outdoor assembly; a total station is set up in the workshop to accurately control the positioning size of each segment and strictly control the segment erection accuracy. The lower structure of the whole bridge is a sheet side beam 3 structure. Conventional production uses a single segment to be completed and then assembled into a large segment. It is difficult to control the accuracy between segments. There are situations such as misalignment during the assembly process, and it cannot be adjusted. At the same time, the outdoor construction of the lower structure of the whole bridge is easily restricted by the weather and hoisting equipment, which will delay the construction period. In order to control the overall linear dimensions of the lower side beam 3 structure and improve the workshopization of field operations, the lower side beam segments are assembled into two groups in the workshop after processing, each group accounts for half of the overall side beam, and then transported to the field as a whole by a modular vehicle, and the ring mouths are directly matched and docked.

[0052] In this embodiment, in step S2, the arch rib 1 is segmented into 29 small segments for processing.

[0053] In this embodiment, the average length of a single segment arch rib 1 is 3000mm-4000mm, the cross section is 1000*1000mm, the four corner welds are all full penetration welds, and the four sides and the connecting plates of the suspender 2 are all full penetration welds. However, the welding space is small, the material is S690QL high-strength steel, and the preheating temperature before welding needs to reach at least 120°. The welding is in summer, and the arch rib 1 welding space is small, and the construction personnel cannot operate in the box. Therefore, the overall restricted space is designed with welds and other strengths, and the four corner welds are changed to single-side groove partial penetration (the groove is opened on the outside of the box), with a penetration depth of 80%, which not only meets the structural strength but also facilitates the construction of personnel.

[0054] In this embodiment, when processing a single segment arch rib 1, first position the two arch rib 1 bottom plates and then install the partition tooling 6, and then install the other two arch rib 1 bottom plates. After welding the arch rib 1, remove the partition tooling 6. The partition tooling 6 is embedded in the segment of the arch rib 1 and fixedly connected by pins, which is convenient for disassembly and reuse. The partition tooling 6 can control the welding deformation of the arch rib 1 to ensure the overall size of the small segment of the arch rib 1. The outer dimensions of this detachable partition tooling 6 are designed according to the internal dimensions of the segment. It is mainly composed of 3 parts, and the parts are fixed by pins and bolts. The partition tooling 6 is assembled in advance and the outer dimensions are checked. The single-segment side beam 3 can also be supported internally with a tooling of corresponding size during welding.

[0055] In this embodiment, during the assembly process of the arch rib 1 in the workshop in step S3, 29 small segments are first assembled into 5 large segments indoors. During the assembly process, the small segments are hoisted onto the arch rib 1 large segment assembly line frame, one side of the arch rib 1 is welded to the connecting plate of the hanger 2, and then the other side of the arch rib 1 is welded, and then the large segments are transported to the field for assembly. For example, first assemble in the workshop into 4 large segments consisting of 6 small segments and 1 large segment consisting of 5 small segments. Set up a total station in the workshop to precisely control the positioning size of each segment and strictly control the segment erection accuracy. It is easier to control and adjust the positioning size of the segment ring mouth and the connecting plate of the hanger 2 in the workshop, reducing the number of ring mouth welding in the field. To ensure the fitting surface between the end of the arch rib 1 and the connecting plate of the hanger 2, a 16*2700*1600 inspection steel plate can be cut and hoisted to the end of the arch rib 1 segment to check whether the steel plate surface fits the groove surface. If it does not meet the requirements, it needs to be trimmed again to ensure the surface fit. When the side beam 3 and the arch rib 1 are assembled and welded, a connecting plate is set between the single segments to facilitate the connection with the hanger 2.

[0056] In this embodiment, the longitudinal and transverse connecting beams in step S2 are I-beam structures, and the I-beam components are prefabricated in advance.

[0057] In this embodiment, the specific processing steps of the support beam 5 in step S2 are as follows:

[0058] S21: Arrange the crossbeams to assemble the tire frame. The tire frame is made of a standard tire frame and is precisely adjusted with a tooth plate. The tire frame is longitudinally arranged at the position of the partition inside the support crossbeam 5;

[0059] S22: hoist the crossbeam bottom plate 7 to the assembly cradle, position and adjust the position, check the vertical and horizontal reference lines of the bottom plate unit and the partition assembly line, and the cradle should be arranged longitudinally at the partition position inside the support crossbeam 5 to ensure that the cradle is aligned with the rib plate structure;

[0060] S23: The middle cross bridge is positioned and assembled toward the partition 8, and the partition is hoisted to the bottom plate unit assembly line. The partition unit and the bottom plate are positioned and welded, and the process support for welding the partition unit is installed before the hook can be loosened;

[0061] S24: Position and assemble the longitudinal bridge partition 9, hoist the longitudinal bridge partition 9 to the partition assembly line on the bottom plate, check the installation dimensions, spot weld and position, and fix with process braces;

[0062] S25: The cross bridge is positioned and assembled toward the outer web 10, the cross bridge is hoisted toward the outer web 10, and the diagonal size of the box opening is measured to adjust the web positioning size;

[0063] S26: The longitudinal bridge outward inclined web 11 is positioned and assembled, the longitudinal bridge outward inclined web 11 is hoisted, the inclined web and the transverse bridge web are spot welded, and the outward web is supported by a process support;

[0064] S27: The longitudinal bridge is positioned and assembled toward the outer web 12, and a manhole is opened in the enclosed space inside the box body to facilitate the entry and exit of personnel in the enclosed space for welding. After the welding of the internal space is completed, the manhole is blocked;

[0065] S28: top plate 13 is positioned and assembled, the top plate 13 unit is hoisted and positioned as a whole, and the top plate 13 is welded with the partition plate and the outer web plate;

[0066] S29: Hoisting, transportation, and painting. After the box body is welded, it is transported to the painting workshop using a hydraulic flatbed truck for sandblasting and painting, and the welding position is protected by paint.

[0067] In this embodiment, the side beams 3 are manufactured in sections in a workshop according to the size of the entire bridge, and then transported as a whole to the field by a module vehicle, and the ring openings are directly matched and docked.

[0068] In this embodiment, the steps of installing the suspension rod 2 in S3 are specifically as follows:

[0069] S31: Measure the dimensions of the connecting plate of the arch rib 1 and the connecting plate of the side beam 3, trim the excess of the hanger rod 2 and open the groove;

[0070] S32: The suspender 2 is hoisted by tooling. After the suspender 2 is hoisted in place, the upper and lower ends of the suspender 2 are adjusted to align with the connecting plate and fixed with a kama;

[0071] S33: The hanger 2 is assembled and welded from the middle of the main bridge to both sides in sequence. The hanger 2 is hoisted by a gantry crane, and the hanger 2 is adjusted to a specified state through the coordination of the main and auxiliary hooks. After the hanger 2 is fully installed and welded, the force conversion of the entire bridge of the arch rib 1 can be realized.

[0072] In this embodiment, the tooling of S32 is a detachable clamp 14 .

[0073] The suspender 2 is mainly a slender steel strip structure with a thickness of 80mm-100mm and a length of 4-12 meters. The slender strip is seriously deformed during conventional hoisting, and its own structure is deformed and deformed by hoisting force, which seriously affects the installation of the completed bridge. By designing a special adjustable and detachable clamp 14, different types of suspenders 2 can be hoisted and installed, such as Figure 6 As shown, the right end of the detachable clamp 14 is clamped on the suspension rod 2, and the gantry crane lifts the left end of the detachable clamp 14 to reduce the possibility of deformation of the suspension rod 2. The suspension rod 2 is installed to connect the suspension rod 2 connecting plate on the arch rib 1 with the suspension rod 2 connecting plate on the lower side beam 3. After the suspension rod 2 is installed, the force transmission between the arch rib 1 and the side beam 3 is realized.

[0074] Example 2

[0075] In this embodiment, different from the above-mentioned embodiment, in the process of assembling the arch rib 1 in the workshop in step S3, 29 small segments are first assembled into 5 large segments indoors, and during the assembly process, the small segments are hoisted onto the arch rib 1 large segment assembly line frame, and the hanger 2 connecting plate is assembled. After the second segment is assembled with the hanger 2 connecting plate, symmetrical welding is performed, and then the large segments are transported to the field for assembly; the use of symmetrical welding can reduce welding deformation.

[0076] Obviously, the above embodiments are merely examples for the purpose of clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived therefrom are still within the scope of protection of the invention.

Claims

1. A method for integrally manufacturing a curved steel arch bridge, It is characterized in that The steps include: S1: The curved steel arch bridge is divided into arch ribs (1), hangers (2), side beams (3), longitudinal and transverse connecting beams (4), and support beams (5); S2: independently process the arch rib (1), the hanger (2), the side beam (3), the longitudinal and transverse connecting beams (4), and the support cross beam (5); S3: After the arch rib (1) side and beam (3) are assembled in the workshop, they are transported to the field together with the suspension rod (2), the longitudinal and transverse connecting beams (4) and the support cross beam (5) for assembly.

2. The method for manufacturing a curved steel arch bridge as claimed in claim 1, It is characterized in that In the step S2, the arch rib (1) is segmented into 29 small segments for processing.

3. The method for integrally manufacturing a curved steel arch bridge according to claim 2, It is characterized in that The average length of a single segment arch rib (1) is 3000mm-4000mm, the cross section is 1000*1000mm, the four corner welds are all full penetration welds, and the four sides and the connecting plate of the hanger (2) are all full penetration welds.

4. The method for integrally manufacturing a curved steel arch bridge according to claim 2, It is characterized in that When processing a single segment arch rib (1), firstly two arch rib (1) bottom plates are positioned and then a partition tooling (6) is installed, and then another two arch rib (1) bottom plates are installed, and after the arch rib (1) is welded, the partition tooling (6) is removed.

5. The method for integrally manufacturing a curved steel arch bridge according to claim 4, It is characterized in that In the process of assembling the arch rib (1) in the workshop in step S3, 29 small segments are first assembled into 5 large segments indoors. During the assembly process, the small segments are hoisted onto the large segment assembly line frame of the arch rib (1), and the suspension rod (2) connecting plate is assembled. After the second segment is assembled with the suspension rod (2) connecting plate, symmetrical welding is performed, and then the large segment is transported to the field for assembly.

6. The method for integrally manufacturing a curved steel arch bridge according to claim 1, It is characterized in that In step S2, the longitudinal and transverse connecting beams are I-beam structures, and I-beam components are prefabricated in advance.

7. The method for integrally manufacturing a curved steel arch bridge according to claim 1, It is characterized in that The specific processing steps of the support beam (5) in step S2 are as follows: S21: Arrange the crossbeams and assemble the tire frame. The tire frame is made of a standard tire frame and is accurately adjusted with a tooth plate. The tire frame is longitudinally arranged at the position of the inner partition of the support crossbeam (5); S22: hoist the crossbeam bottom plate (7) onto the assembly frame, position and adjust the position, check the vertical and horizontal reference lines of the bottom plate unit and the partition assembly line, and the frame should be arranged longitudinally at the partition position inside the support crossbeam (5) to ensure that the frame is aligned with the rib plate structure; S23: The middle cross bridge is positioned and assembled towards the partition (8), and the partition is hoisted to the bottom plate unit assembly line. The partition unit and the bottom plate are positioned and welded, and the process support for welding the partition unit is installed before the hook can be released; S24: Positioning and assembling the longitudinal bridge partition (9), hoisting the longitudinal bridge partition (9) to the partition assembly line on the bottom plate, checking the installation dimensions, spot welding the partition and fixing it with a process support; S25: The cross bridge is positioned and assembled toward the outer web plate (10), the cross bridge is hoisted toward the outer web plate (10), and the diagonal dimensions of the box opening are measured to adjust the web plate positioning dimensions; S26: The longitudinal bridge outward inclined web plate (11) is positioned and assembled, the longitudinal bridge outward inclined web plate (11) is hoisted, the inclined web plate and the transverse bridge web plate are spot welded, and the outward web plate is supported by a process support; S27: The longitudinal bridge is positioned and assembled toward the outer web (12), and a manhole is opened in the enclosed space inside the box body to facilitate personnel to enter and exit the enclosed space for welding. After the welding of the internal space is completed, the manhole is blocked; S28: Positioning and assembling the top plate (13), hoisting and positioning the top plate (13) unit as a whole, and completing welding of the top plate (13) with the partition plate and the outer web plate; S29: Hoisting, transportation, and painting. After the box body is welded, it is transported to the painting workshop using a hydraulic flatbed truck for sandblasting and painting, and the welding position is protected by paint.

8. The method for integrally manufacturing a curved steel arch bridge according to claim 1, It is characterized in that The side beams (3) are manufactured in sections in a workshop according to the size of the entire bridge, and then transported as a whole to the field via a module vehicle, with the ring openings directly matched and docked.

9. The method for integrally manufacturing a curved steel arch bridge according to claim 1, It is characterized in that The specific steps of installing the suspension rod (2) in S3 are as follows: S31: Measure the dimensions of the connecting plate of the arch rib (1) and the connecting plate of the side beam (3), trim the excess of the suspender rod (2) and open a groove; S32: The suspension rod (2) is hoisted by a tooling. After the suspension rod (2) is hoisted in place, the upper and lower ends of the suspension rod (2) are adjusted to align with the connection plate and fixed by a cama. S33: The hangers (2) are assembled and welded in sequence from the middle of the main bridge to both sides. The hangers (2) are hoisted by a gantry crane. The hangers (2) are adjusted to a specified state through the coordination of the main and auxiliary hooks. After the hangers (2) are fully installed and welded, the force conversion of the entire bridge of the arch rib (1) can be realized.

10. The method for integrally manufacturing a curved steel arch bridge according to claim 9, It is characterized in that The tooling of S32 is a detachable clamp (14).