Top shield launching structure and construction method thereof

By using prestressed steel strands in the starting structure of the top shield to connect the reaction seat system and the working well foundation pit, the overall stress system is formed, and the insufficient top thrust in the back or in the air during long-distance top shield construction is solved. The problem ensures the stable operation and construction safety of the shield machine.

CN118997774AActive Publication Date: 2024-11-22CCFEB CIVIL ENG
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
CN202410988920.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-23
Publication Date
2024-11-22
Estimated Expiration
2044-07-23

AI Technical Summary

Technical Problem

During long-distance shield construction, the back is facing water or in the air, resulting in insufficient thrust, which is difficult for the existing technology to effectively solve this problem.

Method used

A top shield starting structure was designed, including the working well foundation pit, internal support system and reaction seat system. The reaction seat system is connected to the working well foundation pit through prestressed steel strands to form an overall stress system to ensure that The shield header can still provide sufficient thrust in the back of the water or in the air.

Benefits of technology

The reverse tension of the prestressed steel strand effectively offsets the top thrust received by the top shield reaction seat bearing, so that the top shield machine can still provide sufficient top thrust at the back facing water or in the air, solving the top thrust The problem of insufficient improvements in construction reliability and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997774A_ABST
    Figure CN118997774A_ABST
Patent Text Reader

Abstract

The invention discloses a top shield starting structure and a construction method thereof. The top shield starting structure comprises a working well foundation pit, an inner supporting system and a counter-force seat system. The counter-force seat system is arranged on the back face, in the tunneling direction of the top shield machine, of the working well foundation pit, the counter-force seat system comprises a top shield counter-force seat bearing platform and a prestress reinforcing structure, the prestress reinforcing structure comprises a fastening block and a prestress steel strand, the first end of the prestress steel strand is fixed to the top shield counter-force seat bearing platform through the fastening block, and the second end of the prestress steel strand is fixed to the top shield counter-force seat bearing platform through the fastening block. The second end is fixed on a bottom plate of the working well foundation pit through a fastening block, and the prestressed steel strand is used for connecting the counter-force seat system with the working well foundation pit to form an integral stress system. According to the top shield launching structure, the top shield counter-force base bearing platform transmits force to the working well foundation pit bottom plate through the prestressed steel strands to form an overall stress system, and shield launching jacking thrust is provided, so that the problem that in top shield construction, the jacking thrust at the back near water or the free position is insufficient is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel construction, and in particular to a top shield launching structure and a construction method thereof. Background Art

[0002] With the rapid development of urban underground tunnel projects, a series of problems have arisen, such as repeated ground excavation, collapse caused by excessive settlement, and tense ground traffic environment. The top shield technology has gradually become popular because it integrates top pipe propulsion and shield excavation, and combines the advantages of top pipe and shield technology. As the construction environment becomes increasingly complex, in long-distance top shield construction, there will be situations where the back is facing water (facing air) and it is impossible to provide sufficient top thrust. How to solve the problem of insufficient top thrust at the back facing water (facing air) is an urgent problem to be solved in the field of top shield engineering. Summary of the invention

[0003] The invention provides a top shield launching structure to solve the technical problem of insufficient top thrust at a back water location (or air location) existing in long-distance top shield construction.

[0004] The present invention also provides a top shield launching structure construction method, which adopts the top shield launching structure.

[0005] According to one aspect of the present invention, there is provided a top shield starting structure, which is used to be arranged at a place where the back is close to water or air and to provide a top thrust for a top shield machine. The top shield starting structure includes a working well foundation pit, an internal support system and a reaction seat system; the internal support system is arranged at the working well foundation pit to support the pit wall of the working well foundation pit; the reaction seat system is arranged at the back of the working well foundation pit along the excavation direction of the top shield machine, the reaction seat system includes a top shield reaction seat support platform and a prestressed reinforcement structure, the prestressed reinforcement structure includes a fastening block and a prestressed steel strand, the first end of the prestressed steel strand is fixed to the top shield reaction seat support platform through the fastening block, the second end of the prestressed steel strand is fixed to the bottom plate of the working well foundation pit through the fastening block, the height of the first end of the prestressed steel strand is higher than the second end and forms a tensioning angle relative to the bottom plate of the working well foundation pit, and the prestressed steel strand is used to connect the reaction seat system with the working well foundation pit to form an overall force system.

[0006] Furthermore, the fastening block is a first tooth block and a second tooth block, the first end of the prestressed steel strand is anchored on the first tooth block, and the first tooth block is fixed to the top shield reaction seat support platform by embedding reinforcement; the second end of the prestressed steel strand is anchored on the second tooth block, and the second tooth block is fixed to the bottom plate of the working shaft foundation pit; the first tooth block and the second tooth block are used to tension and lock the prestressed steel strand.

[0007] Furthermore, the long-distance top shield starting structure also includes a starting well foundation pit retaining structure, and the starting well foundation pit retaining structure includes a temporary guardrail and a drainage ditch arranged on the ground, retaining piles and water-stop piles arranged underground, and an inter-pile support structure is provided on one side of the retaining piles and the water-stop piles. The retaining piles and the water-stop piles are alternately arranged in sequence around the periphery of the working well foundation pit.

[0008] Furthermore, the reaction seat system also includes a reaction pile group, which is divided into two rows, the front row is a retaining pile that also serves as a reaction pile, and the rear row is a reaction pile. The top shield reaction seat cap is respectively connected to the retaining pile and the reaction pile and is supported and fixed by the retaining pile and the reaction pile.

[0009] Furthermore, the internal support system includes a crown beam, a reinforced concrete support structure and a steel support structure; the crown beam is used to connect the retaining piles and the top shield reaction seat pedestal into a whole; the reinforced concrete support structure is connected to the crown beam; the steel support structure is arranged below the reinforced concrete support structure, and a plurality of steel support structures arranged in parallel up and down are arranged in the pit wall of the working well foundation pit.

[0010] Further, the reinforced concrete support structure includes a concrete support and a concrete plate support, wherein the concrete support includes a first concrete support connecting two opposite sides of the pit wall of the working pit into a whole, and a second concrete support connecting two adjacent sides of the pit wall of the working pit into a whole, and the concrete plate support is used to support the corner of the pit wall of the working pit;

[0011] The steel support structure includes steel supports and steel plate angle supports. The steel supports include a first steel support that connects the opposite sides of the pit wall of the working pit into a whole, and a second steel support that connects the adjacent sides of the pit wall of the working pit into a whole. The steel plate angle support is used to support the corners of the pit wall of the working pit.

[0012] Furthermore, the internal support system also includes a steel purlin, which is installed on the inter-pile support structure, and the steel support structure is fixed to the pit wall of the working shaft foundation pit through the steel purlin.

[0013] Furthermore, the working well foundation pit also includes a working well main structure, which includes a bottom plate, hidden columns and an inner lining wall. A waterproof layer and a cushion layer are sequentially arranged under the bottom plate. The hidden columns are arranged around the working well to improve the integrity of the working well main structure.

[0014] Furthermore, the working shaft foundation pit also includes a top shield pipe and a top shield tunnel, and the top shield pipe and the top shield tunnel are arranged at the center position of the front side of the working shaft foundation pit along the excavation direction of the top shield machine.

[0015] According to another aspect of the present invention, there is also provided a top shield initial structure construction method, comprising the following steps:

[0016] (1) Level the site, construct retaining piles, water-stop piles and reaction piles; excavate the foundation pit, embed the connecting steel bars of the main structure of the working pit and the crown beam in the foundation pit, embed the steel casing and the first tooth block steel bars for positioning the prestressed steel strands, and cast the top shield reaction seat cap in the foundation pit;

[0017] (2) Continue to excavate the foundation pit, construct the pile top beam and reinforced concrete support structure, then excavate the earth layer by layer to the first steel support structure, construct the steel purlin, and fill the back of the purlin with quick-hardening fine stone concrete. Repeat the excavation construction until the last steel support structure, and finally excavate the earth layer by layer to the foundation pit bottom plate;

[0018] (3) Construct the bottom plate, reserve the second tooth block and the side wall and hidden column below the steel support structure, and then thread the prestressed steel strands. Anchor the two ends of the prestressed steel strands on the top shield reaction seat pedestal and the bottom plate of the working pit foundation pit, and then carry out the tensioning and anchoring procedures to complete the construction of the prestressed reinforced structure.

[0019] The present invention has the following beneficial effects:

[0020] In the reaction seat system of the present invention, reinforcement is planted on the top shield reaction seat support to achieve effective connection between the fastening block and the reaction seat support, and at the same time, another fastening block is pre-buried in the bottom plate of the working well foundation pit, and the reaction seat system is connected to the working well foundation pit through prestressed steel strands to form a whole. The top shield reaction seat support transmits force to the bottom plate and the second tooth block to form an overall force system through the prestressed steel strands, so that the reverse tension of the prestressed steel strands offsets the top shield reaction seat support The thrust force received by the back can still provide sufficient thrust for the top shield machine when the back of the top shield reaction seat support is near water or air, thereby solving the problem of insufficient thrust at the back near water (air) in long-distance top shield construction.

[0021] In addition to the above-described purposes, features and advantages, the present invention has other purposes, features and advantages. The present invention will be further described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] The drawings constituting a part of this application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:

[0023] Figure 1 It is a structural schematic diagram of the top shield starting structure of a preferred embodiment of the present invention;

[0024] Figure 2 for Figure 1 The cross-section of the top shield originating structure along the AA direction is shown;

[0025] Figure 3 This is a schematic plan view of a prestressed reinforcement structure of a preferred embodiment of the present invention;

[0026] Figure 4 It is a schematic diagram of the concrete support plane of the shield starting shaft foundation pit of the preferred embodiment of the present invention;

[0027] Figure 5 It is a schematic plan view of the steel support of the shield starting shaft foundation pit of a preferred embodiment of the present invention;

[0028] Figure 6 A schematic cross-sectional view of a shield starting shaft foundation pit retaining structure according to a preferred embodiment of the present invention;

[0029] Figure 7 This is one of the schematic diagrams of the construction steps of the shield starting structure of the preferred embodiment of the present invention;

[0030] Figure 8 This is the second schematic diagram of the construction steps of the shield starting structure of the preferred embodiment of the present invention;

[0031] Fig. 9 This is the third schematic diagram of the construction steps of the shield starting structure of the preferred embodiment of the present invention;

[0032] Fig.10 This is the fourth schematic diagram of the construction steps of the shield starting structure of the preferred embodiment of the present invention;

[0033] Fig.11 This is the fifth schematic diagram of the construction steps of the shield starting structure of the preferred embodiment of the present invention;

[0034] Fig.12 This is the sixth schematic diagram of the construction steps of the shield starting structure of the preferred embodiment of the present invention;

[0035] Fig.13 This is the seventh schematic diagram of the construction steps of the shield starting structure of the preferred embodiment of the present invention;

[0036] Fig.14 This is the eighth schematic diagram of the construction steps of the shield starting structure of the preferred embodiment of the patent of the present invention.

[0037] Among them: 1-steel mesh; 2-early-strength shotcrete; 3-intercepting ditch; 4-guard pile; 5-water-stop pile; 6-crown beam; 7-concrete support; 8-steel support; 9-reaction pile; 10-top shield reaction seat cap; 11-prestressed steel strand; 12-lining wall; 13-hidden column; 14-bottom plate; 15-cushion; 16-waterproof layer; 17-first tooth block; 18-second tooth block; 19-steel casing; 20-anchor; 21-embedded reinforcement; 22-top shield pipe; 23-concrete slab support; 24-retaining wall; 25-temporary guardrail; 26-steel replacement support; 27-pile support; 28-top shield tunnel; 29-steel purlin; 30-steel plate angle support. DETAILED DESCRIPTION

[0038] The embodiments of the present invention are described in detail below with reference to the accompanying drawings. However, the present invention can be implemented in many different ways as defined and covered below.

[0039] See also Figures 1 to 6 The embodiment of the first aspect of the present invention provides a top shield starting structure, which is used to be set at a place where the back is close to water or air and provide a top thrust for the top shield machine. The top shield starting structure includes a working well foundation pit, an internal support system and a reaction seat system; the internal support system is set in the working well foundation pit to support the pit wall of the working well foundation pit; the reaction seat system is set on the back of the working well foundation pit along the excavation direction of the top shield machine, the reaction seat system includes a top shield reaction seat support platform 10 and a prestressed reinforcement structure, the prestressed reinforcement structure includes a fastening block and a prestressed steel strand 11, the first end of the prestressed steel strand 11 is fixed to the top shield reaction seat support platform 10 through the fastening block, the second end of the prestressed steel strand 11 is fixed to the bottom plate of the working well foundation pit through the fastening block, the height of the first end of the prestressed steel strand 11 is higher than the second end and forms a tensioning angle relative to the bottom plate of the working well foundation pit, the prestressed steel strand 11 is used to connect the reaction seat system with the working well foundation pit to form an overall force system.

[0040] The present invention sets a prestressed reinforcement structure in the reaction seat system, and strengthens the connection between each component through the prestressed reinforcement structure. The connection and anchoring between the tooth block and the reaction seat pedestal, and between the tooth block and the foundation pit bottom plate 14 are ensured by planting reinforcement bars 21, pre-reserved anchoring steel bars, etc., and the prestressed tensioning of the high-strength steel strands is controlled to provide sufficient and reliable top shield thrust under the premise of ensuring structural safety. The height of the first end of the prestressed steel strand 11 is higher than the height of the second end, and is used to transfer the force on the top shield reaction seat pedestal 10 to the working pit through the prestressed steel strand 11, so as to provide the shield initial jacking thrust. Specifically, the size of the reaction seat pedestal is related to the installation angle of the prestressed steel strand 11, and needs to be determined by calculation to adapt to different working environments and provide sufficient top shield thrust. The long-distance top shield launching structure at the back near the water of the present invention is particularly suitable for working environments such as the subway shield launching shaft, where the plane size of the working shaft is generally small, the tunnel is buried deep, and the geological conditions are complex. By adopting the split launching method, the construction difficulties under deep and complex geological conditions can be effectively solved. This structure can realize the smooth launching of the shield machine in a limited space, ensure the stability of the stratum at the end of the launching shaft, lay a solid foundation for subsequent safe construction, and achieve adaptability to complex geological conditions through optimized design, enhancing the feasibility and safety of the project.

[0041] See also Figure 1 and Figure 3 In an embodiment of the present invention, the prestressed reinforcement structure further includes a steel casing 19 and an anchor 20, and the prestressed steel strand 11 passes through the steel casing 19; the fastening block is a first tooth block 17 and a second tooth block 18, and the first end of the prestressed steel strand 11 is anchored on the first tooth block 17, and the first tooth block 17 is fixed on the top shield reaction seat 10 through the planting bar 21; the second end of the prestressed steel strand 11 is anchored on the second tooth block 18, and the second tooth block 18 is fixed on the bottom plate 14 of the working pit foundation; the first tooth block 17 and the second tooth block 18 are used for tensioning and locking the prestressed steel strand 11. The second tooth block 18 is reserved for anchoring steel bars when the bottom plate 14 of the working pit foundation is constructed. The steel casing 19 is embedded in the reaction seat cap, the inner lining wall 12 of the working pit foundation pit, and the second tooth block 18 before casting. The anchor 20 is embedded in the tooth block before casting. The second tooth block 18 is cast together with the reaction seat and the working pit bottom plate 14. After the second tooth block 18 reaches the design strength, the steel strand is bundled, tensioned, and anchored to form a prestressed reinforced structure.

[0042] The working principle of the prestressed reinforcement structure is as follows: the second tooth block 18 serves as the anchoring end of the prestressed steel strand 11. Through the embedded steel casing 19, it is convenient to insert the prestressed steel strand 11 and perform post-tensioning in the later stage. The second tooth block 18 provides a strong anchoring for the prestressed steel strand 11; the first tooth block 17 provides a tensioning and locking platform for the prestressed steel strand 11. The first tooth block 17 is formed as a whole with the top shield reaction seat 10 through the later embedded reinforcement 21. When the prestressed steel strand 11 is tensioned, the first tooth block 17 is pressed against the anchor 20. The prestressed steel strand 11 is temporarily installed with a through-type hydraulic jack, a tool anchor, a pad, etc. for tensioning and locking, and the force is transmitted to the bottom plate 14 of the working pit through the prestressed steel strand 11.

[0043] The lower part of the top shield reaction seat 10 is connected to a row of reaction piles 9 and a row of retaining piles 4, and a pressure is applied in advance to the upper part through the prestressed steel strands 11, so that the top shield reaction seat 10 can provide a safe, effective and reliable support reaction force during the top shield construction. Part of the reaction force is used to offset the pressure pre-applied to the reaction seat by the prestressed steel strands 11, and part is transmitted to the reaction piles 9. Due to the use of prestressed steel strands 11, the force model of the reaction piles 9 is changed from a cantilever beam to an over-determined beam, making the force on the reaction piles 9 more reasonable and improving the overall safety of the structure.

[0044] In the reaction seat system of the present invention, by planting reinforcement 21 on the top shield reaction seat support platform 10, the first tooth block 17 is effectively connected to the reaction seat support platform, and the second tooth block 18 is pre-buried in the bottom plate 14 of the working pit foundation pit, and the reaction seat system is connected to the working pit foundation pit through the prestressed steel strand 11 to form a whole. The top shield reaction seat support platform 10 transmits force to the bottom plate 14 and the overall force system formed by the second tooth block 18 through the prestressed steel strand 11, so that the reverse tension of the prestressed steel strand offsets the top shield reaction seat support platform The thrust force received by the back of the top shield reaction seat support platform does not need to be supported, so that the back of the top shield reaction seat support platform can still provide sufficient thrust for the top shield machine when it is near water or air, thereby solving the problem of insufficient thrust at the back near water (air) in long-distance top shield construction.

[0045] See also Figure 6In an embodiment of the present invention, the long-distance top shield starting structure also includes a starting well foundation pit retaining structure, which includes a temporary guardrail 25, a water interception ditch 3, a retaining wall 24, a retaining pile 4, a water stop pile 5, and a pile support 27, and an anchor spraying support structure between piles. The retaining piles 4 and the water stop piles 5 are alternately arranged around the periphery of the working well foundation pit, and a pile support 27 structure is provided on one side of the retaining piles 4 and the water stop piles 5. Part of the retaining piles 4 under the top shield reaction seat 10 act as reaction piles 9 to provide part of the reaction force. The retaining wall 24 is located above the crown beam 6, and its function is to prevent surface water from flowing into the foundation pit; the temporary guardrail 25 and the intercepting ditch 3 at the edge of the foundation pit are used for safety protection and to intercept, guide and collect surface water respectively; the retaining piles 4 adopt the drilling and grouting technology, and their function is to withstand the soil side pressure after the excavation of the starting well foundation pit; the inter-pile support 27 adopts the structure of steel mesh 1 plus early-strength shotcrete 2 to limit the collapse of the soil between the piles; the water-stop piles 5 adopt high-pressure rotary jet piles of cement mortar to prevent the softening and collapse of the soil around the foundation pit due to groundwater; the soil behind the top shield starting line piles is reinforced with high-pressure rotary jet piles to improve the integrity of the retaining piles 4 and the soil behind the piles, so as to realize the pile-soil coordinated force during the top shield construction.

[0046] In an embodiment of the present invention, the reaction seat system also includes 9 groups of reaction piles, and the reaction piles 9 groups are divided into two rows. The front row is the retaining piles 4 which also serve as reaction piles 9, and the rear row is the reaction piles 9. The diameter of the rear row reaction piles 9 is 1.2-1.5 times that of the front row. The top shield reaction seat base 10 is respectively connected to the retaining piles 4 and the reaction piles 9 and is supported and fixed by the retaining piles 4 and the reaction piles 9. During the construction of the top shield, the reaction seat system is subjected to force as a whole, and the 9 groups of reaction piles are used to disperse the reaction force of the top shield reaction seat base 10.

[0047] See also Figure 6 In an embodiment of the present invention, the internal support system includes a crown beam 6, a reinforced concrete support structure and a steel support structure; the crown beam 6 is used to connect the retaining pile 4 and the top shield reaction seat cap into a whole; the reinforced concrete support structure is connected to the crown beam 6; the steel support structure is arranged below the reinforced concrete support structure, and a plurality of steel support structures arranged in parallel up and down are arranged in the pit wall of the working pit foundation pit. The internal support system is used to provide a reliable support force for the foundation pit. After the retaining pile 4 is constructed and reaches the design strength, the retaining pile 4 is connected into a whole through the crown beam 6. The steel bars of the first reinforced concrete soil support are pre-buried in the crown beam 6 and connected to the stress-bearing steel bars of the crown beam 6 to ensure the integrity of the internal support system. According to the actual engineering, a plurality of steel support structures are reasonably arranged. The steel support structure consists of a round steel pipe, a steel purlin 29, a node, a rib plate, a purlin joint, a supporting corbel and a fixing, wherein the height range where the steel purlin 29 contacts the retaining pile 4 should be filled with fast-hardening fine stone concrete to ensure that the purlin is in close contact with the pile and the force is evenly transmitted.

[0048] See also Figure 4 and Figure 5 Optionally, the reinforced concrete support structure includes a concrete support 7 and a concrete plate support 23, the concrete support 7 includes a first concrete support connecting the opposite sides of the pit wall of the working well foundation pit into a whole, and a second concrete support connecting the adjacent two sides of the pit wall of the working well foundation pit into a whole, and the concrete plate support 23 is used to support the corner of the pit wall of the working well foundation pit; the steel support structure includes a steel support 8 and a steel plate angle support 30, the steel support includes a first steel support connecting the opposite sides of the pit wall of the working well foundation pit into a whole, and a second steel support connecting the adjacent two sides of the pit wall of the working well foundation pit into a whole, and the steel plate angle support is used to support the corner of the pit wall of the working well foundation pit, and the steel support 8 and the steel plate angle support 30 are respectively arranged below the concrete support 7 and the concrete plate support 23, and are used to support the opposite side, adjacent side and corner of the pit wall of the working well foundation pit.

[0049] Optionally, the internal support system further includes a steel purlin 29, which is installed on the inter-pile support 27 structure, and the steel support structure is fixed in the working pit through the steel purlin 29. The inter-pile support 27 structure consists of a steel mesh 1 and early-strength shotcrete 2, and is mainly used to prevent soil and water loss between piles.

[0050] In an embodiment of the present invention, the working well foundation pit also includes a working well main structure, and the working well main structure includes a bottom plate 14, hidden columns 13 and an inner lining wall 12. A waterproof layer 16 and a cushion layer 15 are arranged in sequence under the bottom plate 14. The hidden columns 13 are arranged around the working well and are used to connect the starting well foundation pit retaining structure with the working well foundation pit. The hidden columns 13 are constructed together with the inner lining wall 12. After the foundation pit is excavated to the designed elevation, the cushion layer 15 and the waterproof layer 16 are constructed first, and then the bottom plate 14 is reinforced, the hidden columns 13 are pre-embedded and concrete is poured, and then the hidden columns 13 and the inner lining wall 12 are reinforced and concrete is poured to form the working well foundation pit.

[0051] Furthermore, the working pit foundation pit also includes a top shield pipe 22 and a top shield tunnel 28, and the top shield pipe 22 and the top shield tunnel 28 are arranged at the center of one side of the working pit foundation pit.

[0052] See also Figure 7-Figure 14 According to another aspect of the present invention, there is provided a method for constructing a long-distance top shield starting structure at a back water location, comprising the following steps:

[0053] (1) Level the site, construct intercepting ditches 3, temporary guardrails 25, drill holes on the ground, and construct reinforcement jet grouting piles, water stop piles 5, retaining piles 4, and reaction piles 9; see Figure 7 ;

[0054] (2) After the retaining structure and reaction piles 9 meet the design requirements, excavate to the bottom of the reaction seat cap, install the reaction seat reinforcement, and pre-embed the working well structure connecting reinforcement and the crown beam 6 connecting reinforcement, steel casing 19, and tooth block reinforcement to ensure that the reaction seat cap is connected to the crown beam 6 and the working well foundation pit to form a whole, and provide a tensioning and locking platform (first tooth block 17) for the prestressed steel strand 11, and then cast the reaction seat cap;

[0055] (3) Excavate the soil layer to the bottom elevation of the crown beam 6 and the reinforced concrete support structure, construct the crown beam 6 and reinforced concrete support structure on the top of the retaining pile 4, and when the reaction seat, crown beam 6 and reinforced concrete support structure reach the design strength, excavate the soil in layers to 500mm below the center line of the first steel support structure, hang a mesh and spray the pit wall concrete protection surface while excavating to prevent soil and water loss between the piles; install the steel support structure after constructing the steel purlin 29, and fill the back of the purlin with fast-hardening fine stone concrete to ensure that there is a large enough contact surface between the purlin and the retaining pile 4, so that the force transmission is more uniform and the structural force is more reasonable; after the fine stone concrete reaches the design strength, install the steel support 8 and tighten it; repeat the excavation construction until the last steel support 8, and then excavate the soil in layers to the bottom of the foundation pit; reserve 300mm of original soil for manual excavation, and spray the pit wall concrete protection surface while excavating; see Figure 8 ;

[0056] (4) Cast the bottom plate cushion layer 15, lay the waterproof layer 16, construct the bottom plate 14 (pre-embed the steel bars of the hidden column 13 and the tooth block steel bars), reserve the second tooth block 18 and the side wall and hidden column 13 below the steel support structure. After the bottom plate 14 and the side wall concrete reach the design strength, construct the replacement support steel pipe, remove the steel support 8, and place the steel replacement support 26 against the newly cast side wall to facilitate the subsequent construction of the upper side wall and hidden column 13; continue to construct the working pit side wall and temporary side wall to below the top reinforced concrete support structure, remove the replacement support steel pipe after the side wall concrete reaches the design strength; remove the reinforced concrete support structure, construct the remaining side wall, and after the main structure reaches the design strength, remove the reinforced concrete formwork to complete the construction of the remaining section of the side wall; after the main structure reaches the design strength, carry out the prestressed steel strand 11 bundle threading, tensioning, and anchor sealing processes to complete the construction of the prestressed reinforced structure; participate Figure 9-12 ;

[0057] (5) Load and pressurize the bottom plate 14 in the well to prevent the working well from floating up during tunnel excavation; hoist the tunnel top shield equipment, and use the reaction seat system to provide the top shield thrust to push forward (excavate); then hoist the tunnel pipe segment (piece); after the top shield is completed, remove the pressure, dismantle the temporary side wall (the temporary side wall acts as a temporary retaining wall, and is connected with the end wall and the reaction seat pedestal to form a finishing, and bear the force together), construct the well structure, and construct the top plate of the working well structure; then dismantle the part of the reaction seat concrete structure exposed on the existing ground; cover the top plate of the working well with soil and backfill, and restore the slope; dismantle the enclosure, and backfill the intercepting ditch 3, see Figure 13-14 .

[0058] The present invention can realize the smooth start of the shield machine in a limited space, and through specific processes and technical measures, it ensures the stability of the stratum at the end of the starting well, laying a solid foundation for subsequent safe construction. Through optimized design, it realizes adaptability to complex geological conditions and enhances the feasibility and safety of the project.

[0059] The above shows and describes the basic principles, main features and advantages of the present invention. The technicians in this industry should be aware that the present invention is not limited by the above embodiments. The above embodiments and descriptions only describe the basic principles of the present invention. Without departing from the design concept and scope of the present invention, the present invention can be further improved according to specific application conditions. These improvements are required to fall within the scope of the present invention. The scope of protection of the present invention is not limited by the attached claims and their equivalents.

Claims

1. A top shield launching structure is used to be set at the back near water or the back near air and provide top thrust for the top shield machine. It is characterized in that The top shield starting structure comprises a working pit, an internal support system and a reaction seat system; the working pit is used to provide a site for installing a top shield machine, the internal support system is arranged in the working pit and is used to support the pit wall of the working pit; the reaction seat system is arranged on the back side of the working pit along the excavation direction of the top shield machine, the reaction seat system comprises a top shield reaction seat support platform (10) and a prestressed reinforcement structure, the prestressed reinforcement structure comprises a fastening block and a prestressed steel strand (11), the first end of the prestressed steel strand (11) is fixed to the top shield reaction seat support platform (10) through the fastening block, the second end of the prestressed steel strand (11) is fixed to the bottom plate of the working pit through the fastening block, the first end of the prestressed steel strand (11) is higher than the second end and forms a tensioning angle relative to the bottom plate of the working pit, the prestressed steel strand (11) is used to connect the reaction seat system with the working pit to form an integral force system.

2. The top shield starting structure according to claim 1, It is characterized in that The fastening block comprises a first tooth block (17) and a second tooth block (18); the first end of the prestressed steel strand (11) is anchored on the first tooth block (17), and the first tooth block (17) is fixed on the top shield reaction seat support platform (10) through embedded reinforcement (21); the second end of the prestressed steel strand (11) is anchored on the second tooth block (18), and the second tooth block (18) is fixed on the bottom plate (14) of the working shaft foundation pit; the first tooth block (17) and the second tooth block (18) are used to tension and lock the prestressed steel strand (11).

3. The top shield initiating structure according to claim 1, It is characterized in that The top shield starting structure also includes a starting well foundation pit retaining structure, the starting well foundation pit retaining structure includes a temporary guardrail (25) and a diversion ditch (3) arranged on the ground, retaining piles (4) and water stop piles (5) arranged underground, and an inter-pile support structure is arranged on one side of the retaining piles (4) and the water stop piles (5), and the retaining piles (4) and the water stop piles (5) are arranged alternately in sequence around the outer circumference of the working well foundation pit.

4. The top shield initiating structure according to claim 3, It is characterized in that The reaction seat system also includes a reaction pile group, which is divided into two rows, the front row is a retaining pile (4), and the rear row is a reaction pile (9), and the top shield reaction seat support platform (10) is respectively connected to the retaining pile (4) and the reaction pile (9) and supported and fixed by the retaining pile (4) and the reaction pile (9).

5. The top shield initiating structure according to claim 3, It is characterized in that The internal support system comprises a crown beam (6), a reinforced concrete support structure and a steel support structure; the crown beam (6) is used to connect the retaining pile (4) and the top shield reaction seat support platform (10) into a whole; the reinforced concrete support structure is connected to the crown beam (6); the steel support structure is arranged below the reinforced concrete support structure, and a plurality of steel support structures arranged in parallel up and down are arranged in the pit wall of the working shaft foundation pit.

6. The top shield initiating structure according to claim 5, It is characterized in that The reinforced concrete support structure comprises a concrete support (7) and a concrete plate support (23), wherein the concrete support (7) comprises a first concrete support for connecting two opposite sides of the pit wall of the working pit into a whole, and a second concrete support for connecting two adjacent sides of the pit wall of the working pit into a whole, and the concrete plate support (23) is used to support the corner of the pit wall of the working pit; The steel support structure comprises a steel support (8) and a steel plate angle brace (30), wherein the steel support (8) comprises a first steel support for connecting two opposite sides of the pit wall of the working pit into a whole, and a second steel support for connecting two adjacent sides of the pit wall of the working pit into a whole, and the steel plate angle brace (30) is used to support the corner of the pit wall of the working pit.

7. The top shield initiating structure according to claim 6, It is characterized in that The internal support system also includes a steel purlin (29), which is installed on the inter-pile support structure, and the steel support structure is supported in the working pit foundation pit by the steel purlin (29).

8. The top shield initiating structure according to claim 1, It is characterized in that A main structure of the working well is also provided in the working well foundation pit, and the main structure of the working well comprises a bottom plate (14), concealed columns (13) and an inner lining wall (12). A waterproof layer (16) and a cushion layer (15) are provided in sequence below the bottom plate (14). The concealed columns (13) are arranged around the working well to improve the integrity of the main structure of the working well.

9. The top shield initiating structure according to claim 8, It is characterized in that The working pit foundation further comprises a top shield pipe (22) and a top shield tunnel (28), wherein the top shield pipe (22) and the top shield tunnel (28) are arranged at the center position of the front side of the working pit foundation along the excavation direction of the top shield machine.

10. A method for constructing a top shield starting structure, It is characterized in that Used for constructing the top shield starting structure according to any one of claims 1 to 9, the top shield starting structure construction method comprises the following steps: (1) Leveling the site, constructing retaining piles (4), water stop piles (5) and reaction piles (9); excavating a foundation pit, pre-embedding the connecting steel bars of the main structure of the working pit and the connecting steel bars of the crown beam (6) in the foundation pit, and pre-embedding the steel casing (19) for positioning the prestressed steel strand (11) and the first tooth block steel bar, and casting in the foundation pit to form a top shield reaction seat bearing platform; (2) The foundation pit is excavated continuously, and the pile top crown beam (6) and reinforced concrete support structure are constructed. Then, the earth is excavated layer by layer to the first steel support structure, and the steel purlin (29) is constructed. Quick-hardening fine stone concrete is filled behind the purlin. The excavation is repeated until the last steel support structure is reached. Finally, the earth is excavated layer by layer to the foundation pit floor. (3) The floor (14) is constructed, and the second tooth block (18) and the side wall and concealed column (13) below the steel support structure are reserved. Then, the prestressed steel strand (11) is bundled. The two ends of the prestressed steel strand are anchored to the top shield reaction seat cap and the bottom plate of the working pit foundation pit respectively. Then, the tensioning and anchoring processes are carried out to complete the construction of the prestressed reinforced structure.

Citation Information

Patent Citations

  • Shield before well construction method of underground comprehensive pipe gallery structure

    CN110306592A

  • Shield tunneling machine receiving platform applied in gob-side state and construction process

    CN110374612A

  • Safety construction method for digging shield shaft and vertical shaft deep foundation pit

    CN110820756A

  • Shield large-gradient launching construction method

    CN112324444A

  • Construction technology for tunneling first and then well in riverside water-rich sand layer

    CN116291499A