Method for treating sludge collapse section of small-section tunnel
The tunnel reinforcement and grouting are carried out through the combined structure of the advance small conduit and pipe shed, combined with the adjustable temporary support steel arch frame, and the problems of low construction efficiency and high safety risks in the silt collapse treatment in small-section tunnel are solved, achieving high efficiency tunnel construction and rock reinforcement.
Patent Information
- Application Number
- CN202411063336.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2024-11-22
AI Technical Summary
When the silt collapses in small-section tunnels, it is difficult for the existing technology to efficiently treat the silt and reinforce the surrounding rock mass, resulting in low construction efficiency and high safety risks, temporary support is inconvenient for adjustment and movement, and it is impossible to quickly respond to changes in the construction site.
The tunnel is reinforced and blocked by a small forward conduit and pipe shed, and the cavity is filled and grouted through the combined structure of steel pipes and steel flower pipes to reinforce the rock body; the temporary support steel arch frame adopts an adjustable structure, including front support and rear support Support, providing a highly adjustable operating platform for enhanced support strength and stability.
Efficient filling and rock reinforcement of the silt collapse section of the small-section tunnel are achieved, reducing construction safety risks, ensuring the stability and safety of tunnel construction, and avoiding secondary disasters caused by water effects.
Smart Images

Figure CN118997790A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel construction, and in particular to a method for treating a silt collapse section in a small-section tunnel. Background Art
[0002] The face of a small-section tunnel collapses, and the steel arch frame near the face will gradually deform. According to analysis, the surrounding rock stability of the fault fracture zone revealed by the excavation is extremely poor, and the arch and side walls are prone to local block loss or overall collapse. The softened carbonaceous shale forms silt-like materials under the impact of water and spreads in the excavated tunnel section. According to on-site investigation and analysis and preliminary survey data, it is speculated that a large-scale fault zone will be encountered in front of the face. In view of the above phenomenon, it is necessary to deal with the collapse and strengthen the support of this section. At present, the common method for handling silt is to directly transport it outside the tunnel. However, due to the small working surface of the small-section tunnel, mechanical rail transportation is often used, so the efficiency of transporting silt is extremely low. In addition, the cavity area is simply filled without reinforcing the surrounding soil.
[0003] When silt collapse occurs, the primary support will be damaged and deformed. At this time, the deformed steel arch frames with deformed primary support need to be removed one by one, and then the initial support should be re-applied. When dismantling the deformed steel arch frame, temporary support needs to be set up at the planned demolition site before dismantling, so as to avoid tunnel collapse when dismantling the deformed steel arch frame. However, the existing tunnel support spacing is generally 0.6, 0.8, 1, and 1.2 meters. After the collapse occurs, the construction party generally re-installs temporary support at the intervals of 0.6, 0.8, 1, and 1.2 meters. This temporary support takes a long time to construct on site, and there are certain safety risks in the construction process. Moreover, this temporary support cannot be moved, and the height is not easy to adjust arbitrarily. Therefore, it is impossible to quickly adjust according to the actual situation of the construction site during the construction process. In addition, after the temporary support is laid out, operations such as grouting of the cavity are required, and an additional operating platform needs to be set up, which increases the workload.
[0004] In addition, when filling the cavity area, it is necessary to lay out small pipes in advance for grouting filling, but most of the small pipes are steel pipes, which cannot be used for tunnel cavity filling. Ordinary steel pipes are often used for cavity filling. Due to the complex on-site conditions and the poor geological conditions of the strata around the cavity, grouting reinforcement work is usually required. Although the steel pipe can be pulled out and reused after grouting, due to the uncertainty of the size of the steel pipe, different sizes of steel pipes must be made each time, or the excess steel pipes must be cut off after grouting, which is time-consuming and labor-intensive and causes a lot of waste. Summary of the invention
[0005] In view of the above-mentioned problems, the present invention aims to provide a method for treating a silt collapse section in a small-section tunnel, which can fill the cavity in the silt collapse section in the small-section tunnel and reinforce the surrounding rock mass to reduce the safety risk during the construction process.
[0006] In order to achieve the above object, the technical solution adopted by the present invention is as follows: A method for treating a silt collapse section in a small-section tunnel comprises the following steps: Step 1: Remove slag from the excavated tunnel section; Step 2: After the slag is discharged, the tunnel is reinforced with an advance small guide tube and a pipe shed; Step 3: Grouting is carried out through the advanced small pipe to block the water in the tunnel and backfill the cavity; Step 4: construct temporary supporting steel arch frames for the deformed section of the primary support, then dismantle the steel arch frames of the deformed section of the primary support frame by frame, and re-construct the initial support; Step 5: Lay drainage pipes on the tunnel arch and left and right side walls; Step 6: Spray concrete and carry out normal tunnel construction process.
[0007] Furthermore, in step one, water glass, cement, accelerator and fine sand are added to the muddy carbonaceous shale, and the mixture is stirred and solidified before slagging; the mass ratio of water glass, cement, accelerator and fine sand is 1:35~40:10~13:16~20.
[0008] Furthermore, the advanced small conduit described in step 2 includes a steel pipe and a steel flower pipe; The steel pipe is symmetrically divided into left and right halves along the central axis; The steel flower pipe is movably sleeved outside the steel pipe, and the steel flower pipe is also a two-half structure.
[0009] Further, the steel pipe includes a left half steel pipe, a right half steel pipe and two fasteners; Both ends of the left half steel pipe and the right half steel pipe are provided with slots; the fastener is located between two corresponding slots.
[0010] Furthermore, a hook for clamping with the steel pipe is provided on the inner side wall of the front end of the first steel flower pipe; the front end and the rear end of each steel flower pipe are inclined structures.
[0011] Furthermore, a groove is provided on the outer side wall of the steel pipe, and a block matching the groove is provided on the inner side wall of the steel flower pipe.
[0012] Furthermore, the temporary supporting steel arch frame described in step 4 includes a front support and a rear support of the same structure; The rear side of the front support is movably connected with a first operating platform with adjustable height, and the front side of the rear support is movably connected with a second operating platform with adjustable height, and the first operating platform and the second operating platform are detachably connected.
[0013] Further, the front support comprises a steel arch frame body and two support rods; The two support rods are respectively located at the bottom of both ends of the steel arch frame body; and a first connecting rod with adjustable height is detachably connected between the two support rods, and the first operating platform is detachably connected to the first connecting rod.
[0014] Furthermore, a second connecting rod with adjustable height is detachably connected between two supporting rods corresponding to each other of the front support and the rear support, and a third connecting rod for supporting the first operating platform and the second operating platform is detachably connected to the second connecting rod.
[0015] Furthermore, an adjusting screw is connected inside the support rod along the axial direction; The adjusting screw rod passes through the bottom of the supporting rod, and an adjusting nut is threadedly connected to the adjusting screw rod, and the adjusting nut is located below the supporting rod; and a moving wheel is provided at the bottom of the adjusting screw rod.
[0016] The beneficial effects of the present invention are: 1. The method for treating the collapsed silt section of a small-section tunnel of the present invention can fill the cavity of the collapsed silt section of a small-section tunnel by removing slag, reinforcing the tunnel, plugging water and backfilling the cavity, re-performing initial support and laying drainage pipes, and reinforcing the surrounding rock mass, thereby reducing the safety risks during the construction process, ensuring the stable progress of the tunnel construction, and preventing the occurrence of secondary disasters in the tunnel due to the action of water.
[0017] 2. The temporary support steel arch frame in the present invention adopts the method of front support and rear support cooperating with each other. By setting the first operating platform on the front support and the second operating platform on the rear support, it is convenient for construction workers to stand on the operating platform to perform other construction operations; and through the first operating platform and the second operating platform and the connecting ribs therebetween, the front support and the rear support can be tightened and connected, thereby increasing the strength of the entire temporary support steel arch frame. At the same time, the connecting ribs can play a role in filling the gap between the first operating platform and the second operating platform to prevent construction workers from falling from the gap between the first operating platform and the second operating platform.
[0018] 3. The first operating platform of the temporary supporting steel arch frame in the present invention is detachably connected to the first connecting rod, and both ends of the first connecting rod are provided with a first threaded section, and the first threaded section is provided with a first fastening nut. By adjusting the position of the first fastening nut on the first threaded section, the first connecting rod can be stably fixed on a front support of any width (any front support with different distances between the two support rods).
[0019] 4. The second connecting rod of the temporary supporting steel arch frame in the present invention connects the supporting rods corresponding to the front support and the rear support. By adjusting the position of the second fastening nut on the second threaded segment, the distance between the front support and the rear support can be adjusted. Moreover, a third connecting rod with an adjustable position is provided on the second connecting rod, which can support the first operating platform and the second operating platform, thereby ensuring the stability of the first operating platform and the second operating platform.
[0020] 5. The temporary supporting steel arch frame in the present invention is threadedly connected to an adjusting screw at the bottom of the supporting rod, and an adjusting nut is connected to the adjusting screw, so that the height of the steel arch frame body can be adjusted so that the steel arch frame body can fit closely with the arch top, thereby improving the supporting effect; a moving wheel is arranged at the bottom of the adjusting thread for easy movement.
[0021] 6. The advance small conduit structure of the present invention can provide advance support for cavities or caves that appear during tunnel construction through the cooperation of steel pipes and steel flower pipes, and can also inject grout into the cavities or caves through steel pipes to ensure the safety of tunnel construction. In addition, the advance small conduit structure can also be used for cavity filling and grouting reinforcement after tunnel collapse.
[0022] 7. The advanced small guide tube structure in the present invention divides the steel pipe into two halves, and the two halves are spliced together by fasteners. Under the action of the outer steel pipe, they can be spliced together. After the grouting of the cavity or cave is completed, the fasteners and the steel pipe can be pulled out successively without affecting the continued support function of the steel pipe. The steel pipe of the advanced small guide tube in the present invention is also a two-half structure. After the inner steel pipe is pulled out, grouting is injected into the steel pipe to reinforce the surrounding rock. Moreover, when grouting is injected into the steel pipe, the steel pipe can be stretched to both sides under the pressure of the slurry, thereby further reinforcing the rock mass. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 This is a schematic diagram of the construction positions of the pipe rack and the advance small guide pipe along the tunnel excavation direction in the first embodiment of the present invention.
[0024] Figure 2 The figure is a schematic diagram of the pipe roof construction position along the plane direction of the tunnel face in the first embodiment of the present invention.
[0025] Figure 3This is a schematic diagram of the pipe roof and steel cage structure in Example 1 of the present invention.
[0026] Figure 4 For the present invention Figure 3 Cross-section view in the AA direction.
[0027] Figure 5 This is a schematic diagram of the construction position of the initial support structure in Example 1 of the present invention.
[0028] Figure 6 This is a diagram showing the location of the drainage pipes in the first embodiment of the present invention.
[0029] Figure 7 This is a front view of the advanced small catheter structure in Example 2 of the present invention.
[0030] Figure 8 It is a side view of the internal structure of the advanced small catheter in the second embodiment of the present invention.
[0031] Fig. 9 This is the front view of the steel pipe structure in the second embodiment of the present invention.
[0032] Fig.10 It is a side view of the internal structure of the steel pipe in the second embodiment of the present invention.
[0033] Fig.11 This is the front view of the steel flower tube structure in Example 2 of the present invention.
[0034] Fig.12 This is a side view of the internal structure of the first steel flower tube in Example 2 of the present invention.
[0035] Fig.13 It is a side view of the internal structure of other steel flower tubes except the first one in Example 2 of the present invention.
[0036] Fig.14 It is a side view of the temporary supporting steel arch structure in the third embodiment of the present invention.
[0037] Fig.15 For the present invention Fig.14 A partial enlarged view of the structure of part B.
[0038] Fig.16 This is a front view of the front support structure in Example 3 of the present invention.
[0039] Fig.17 It is a top view of the temporary supporting steel arch structure in Example 3 of the present invention.
[0040] Fig.18 This is a side view of the first operating platform structure in Example 3 of the present invention.
[0041] Among them: 1-steel pipe, 101-left half steel pipe, 102-right half steel pipe, 103-slot, 104-fastener, 2-steel flower pipe, 3-hook, 4-groove, 5-block, 6-front support, 601-steel arch frame body, 602-support rod, 6021-first mounting hole, 6022-second mounting hole, 603-adjusting screw, 604-adjusting nut, 605-moving wheel, 7-rear support, 8-first operating platform, 9-second operating platform, 10-first connecting rod, 1001-first threaded section, 1002-first fastening nut, 11-arc snap ring, 12-second connecting rod, 1201-second threaded section, 1202-second fastening nut, 1203-support hole, 13-third connecting rod, 14-connecting rib. DETAILED DESCRIPTION
[0042] In order to enable those skilled in the art to better understand the technical solution of the present invention, the technical solution of the present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0043] Embodiment 1: Embodiment 1 provides a method for treating a silt collapse section in a small-section tunnel, comprising the following steps: Step 1: Remove slag from the excavated tunnel section; Specifically, for the muddy carbonaceous shale, water glass, cement, quick-setting agent and fine sand are added for stirring and solidification, and then the slag is discharged normally; solidification for 1m 3 The muddy carbonaceous shale needs to be solidified by adding 5kg of water glass, 185kg of cement, 55kg of quick-setting agent and 90kg of fine sand. The solidified rock mass is then transported out of the tunnel normally.
[0044] Step 2: After the slag is discharged, the tunnel is reinforced; After the slag is discharged, first drill holes at an angle of 30° into the cavity above the slag body within the arch of the tunnel to insert three (two 4.5m long and one 6m long) 125mm guide tubes as advance small guide tubes. The advance small guide tubes are used as channels for pumping concrete to backfill the cavity.
[0045] Then, pipe sheds are laid within the tunnel vault, as shown in the attached Figure 1 and 2 As shown in the figure, the specific parameters of the pipe shed are: using hot-rolled seamless steel pipes with a wall thickness of 6mm and a length of 108mm, a single pipe is 25m long, with a circumferential spacing of 25cm, and the pipe body is drilled with holes of 15mm in diameter and 25cm in distance. There are two holes in one section, and the holes are arranged in a staggered manner in a plum blossom shape to increase the slurry penetration capacity. The pipe head is processed into a cone for easy insertion. The external insertion angle of the pipe shed is 1°~3°.
[0046] Each of the pipe sheds is provided with a steel cage, which includes main bars and fixing rings. Figure 3and 4 As shown, the main reinforcement is made of 4C22, the fixing ring is made of 42 steel pipe, the wall thickness is 3.5mm, the fixing link is 5cm long, the spacing is 50cm, and it is welded and fixed to the main reinforcement.
[0047] Step 3: Water blocking and cavity backfilling.
[0048] After the pipe shed is installed, cement-water glass double slurry is injected through the advance small conduit, and the surrounding rock mass is reinforced in advance and part of the surrounding rock fissure water is blocked by the penetration effect of the slurry. After the grouting is completed and solidified, a 90-type concrete delivery pump is used to pump C20 concrete into the cavity through the advance small conduit to reduce the large-scale outflow of debris flow-like slag. The height of the pumped concrete should be 20cm higher than the shorter conduit (4.5m conduit). The longer conduit (6m conduit) is used for ventilation and drainage when pumping concrete.
[0049] Step 4: Initial support.
[0050] After the concrete pumped in step 3 solidifies, continue the initial support. Remove the steel arch frames in the deformed section of the initial support one by one and replace them with Ⅰ18 steel arch frames to form a closed ring with a spacing of 0.5m. Each steel arch frame is equipped with 4 42 foot lock anchor pipes and 4 middle 42 shoulder lock anchor pipes, which are arranged on both sides of the steel arch frame. Set radial middle 42 grouting small pipes on the side walls on both sides, with a spacing of 1.5m and a single length of 3m. Figure 5 shown.
[0051] In addition, before dismantling the steel arch frames of the deformed sections of the primary support one by one, temporary support steel arch frames are added near the planned demolition locations to ensure that the risk of further deformation is reduced when replacing the deformed steel arch frames of the primary support. After all the deformed steel arch frames of the primary support are replaced, the temporary support steel arch frames are dismantled.
[0052] Step 5: 108 steel pipe drainage pipes are laid out in the arch and left and right side walls, with a spacing of 1.5m and a hole depth of 3m. A filter layer is set inside the drainage pipe or geotextile is used for wrapping. Figure 6 shown.
[0053] Step 6: Spray concrete and carry out normal tunnel construction process.
[0054] Embodiment 2: Based on the first embodiment, the second embodiment provides a preferred structure of the advanced small catheter described in step two.
[0055] Specifically, as attached Figure 7-13As shown, the advanced small conduit structure includes a steel pipe 1 and a steel flower pipe 2 sleeved outside the steel pipe 1. The steel pipe 1 is symmetrically divided into left and right halves along the central axis, namely a left half steel pipe 101 and a right half steel pipe 102, both ends of the left half steel pipe 101 and the right half steel pipe 102 are provided with slots 103, and a fastener 104 is provided between the left half steel pipe 101 and the right half steel pipe 102, the fastener 104 is in contact with the left half steel pipe 101 and the right half steel pipe 102 but not connected, and the left half steel pipe 101, the right half steel pipe 102 and the two fasteners 104 form a complete circular tubular structure.
[0056] The steel flower pipe 2 is sleeved outside the steel pipe 1, and the length of the steel flower pipe 2 is less than the length of the steel pipe 1. The steel flower pipe 2 is also a two-half structure. A barbed hook 3 is provided on the inner wall of the front end of the first steel flower pipe 2. The steel flower pipe 2 can be clamped on the front end of the steel pipe 1 through the hook 3. When the steel pipe 1 and the steel flower pipe 2 are inserted into the soil at the front end at the same time, under the action of the hook 3, the steel pipe 1 and the steel flower pipe 2 will not be separated.
[0057] In order to ensure the firmness of the connection between the steel tube 2 and the steel tube 1, a groove 4 is provided on the outer wall of the steel tube 1, and a clamping block 5 is fixed on the inner wall of the steel tube 2. The clamping block 5 is a small steel block, which is directly welded and fixed on the inner wall of the steel tube 2. Through the mutual cooperation of the clamping block 5 and the groove 4, the steel tube 2 and the steel tube 1 can be prevented from being separated when the steel tube 2 and the steel tube 1 are inserted into the soil at the front end.
[0058] It should be noted that, in this embodiment, the outer diameter of the steel pipe 1 is slightly smaller than the inner diameter of the steel flower pipe 2. When the steel flower pipe 2 is sleeved outside the steel pipe 1, butter is applied between the steel flower pipe 2 and the steel pipe 1, which can make the two fit tightly together and facilitate the steel pipe 1 to be pulled out of the steel flower pipe 2.
[0059] Preferably, in order to ensure close contact between two adjacent steel flower pipes 2 and prevent separation between the two when inserted into the soil, an inclined structure is provided at the end of each of the steel flower pipes 2, and the front end of the steel flower pipe 2 is a thin-front-thick-rear inclined structure, and the rear end is a thick-front-thin-rear inclined structure, so that the front and rear steel flower pipes 2 can fit tightly without affecting the insertion into the soil.
[0060] In this embodiment, the length of each steel pipe 1 is 25 meters, and the length of each steel flower pipe is 5 meters.
[0061] When the advanced small conduit structure of this embodiment is used, firstly, two fasteners 104 are installed with the left half steel pipe 101 and the right half steel pipe 102 to form a complete circular tubular structure; then the first steel flower pipe 2 is clamped at the front end of the steel pipe 1 to fix the fasteners 104 with the left half steel pipe 101 and the right half steel pipe 102. Grease the contact between the fasteners 104 and the left half steel pipe 101 and the right half steel pipe 102.
[0062] Drive the steel pipe 1 and the steel flower pipe 2 into the soil together. Every 5 meters deeper, install the next section of the steel flower pipe 2 around the steel pipe 1. The second and subsequent sections of the steel flower pipe 2 and the steel pipe 1 are limited by the groove 4 on the outer wall of the steel pipe 1 and the block 5 on the inner wall of the steel flower pipe 2. The adjacent sections of the steel flower pipe 2 are tightly fitted by the inclined structure. When installing the steel flower pipe 2, butter should also be applied between the steel flower pipe 2 and the steel pipe 1.
[0063] When the front end of the steel pipe 1 reaches the position in the cavity or the cave, cement-water glass double slurry is injected into the steel pipe 1, and the surrounding rock mass is reinforced in advance and part of the surrounding rock fissure water is blocked by the penetration effect of the slurry. After the grouting is completed, the two fasteners 104 are firstly pulled out from the steel pipe 2, and after the fasteners 104 are completely pulled out, the left half steel pipe 101 and the right half steel pipe 102 are moved toward each other, so that the block 5 is separated from the groove 4, and then the left half steel pipe 101 and the right half steel pipe 102 are also pulled out from the steel pipe 2; finally, a 90-type concrete delivery pump is used in the steel pipe 2 to pump C20 concrete into the cavity to reduce the large-scale outflow of debris flow-like slag and reinforce the surrounding rock mass. Since the steel pipe 2 is also a left and right half structure, when grouting is injected into the steel pipe 2, due to the slurry pressure, the steel pipe 2 can be opened to both sides to play a role in reinforcing the rock mass.
[0064] Embodiment three: Based on the first embodiment, the third embodiment provides a preferred structure of the temporary supporting steel arch frame described in step four.
[0065] Specifically, as attached Figure 14-18 As shown, the temporary support steel arch frame includes a front support 6 and a rear support 7, and the front support 6 and the rear support 7 have the same structure. The rear side of the front support 6 is movably connected to a first operating platform 8, and the front side of the rear support 7 is movably connected to a second operating platform 9. The first operating platform 8 and the second operating platform 9 are detachably connected, and the first operating platform 8 and the second operating platform 9 are used for construction workers to stand, so as to facilitate other operations after the temporary support is arranged, such as dismantling the deformed steel arch frame.
[0066] More specifically, taking the front support 6 as an example, the front support 6 includes a steel arch frame body 601, the steel arch frame body 601 adopts an I-beam structure, and the bottoms of both ends of the steel arch frame body 601 are connected with support rods 602. A first connecting rod 10 is movably connected between the two support rods 602, and one end of the first operating platform 8 is detachably connected to the first connecting rod 10. A plurality of first mounting holes 6021 connected left and right are opened on each of the support rods 602 along the axial direction, and the first mounting holes 6021 on the two support rods 602 correspond to each other, and both ends of the first connecting rod 10 are provided with a first threaded section 1001, and a first fastening nut 1002 is threadedly connected to the first threaded section 1001, and an arc-shaped clamping ring 11 is provided at one end of the first operating platform 8 close to the first connecting rod 10. According to the required height of the first operating platform 8, insert the first connecting rod 10 into the first mounting hole 6021 of the corresponding height, screw the first fastening nut 1002 onto the first threaded segment 1001 according to the distance between the two support rods 602 to fix the first connecting rod 10, and then clamp the arc-shaped clamping ring 11 at the end of the first operating platform 8 onto the first connecting rod 10.
[0067] The connection mode between the rear support 7 and the second operating platform 9 is exactly the same as the connection mode between the front support 6 and the first operating platform 8 .
[0068] Further, two second connecting rods 12 are detachably connected between the front support 6 and the rear support 7, and the second connecting rods 12 connect the corresponding support rods 602 on the front support 6 and the rear support 7. Each of the support rods 602 is provided with a plurality of second mounting holes 6022 connected front and back, and the second mounting holes 6022 are used to mount the second connecting rods 12, and the first mounting holes 6021 and the second mounting holes 6022 on each of the support rods 602 are staggered up and down. Both ends of the second connecting rod 12 are provided with second threaded sections 1201, and the second threaded sections 1201 are threadedly connected with second fastening nuts 1202. According to the installation height of the first connecting rod 10, the front support 6 and the rear support 7 are connected together by the second connecting rod 12 below the first connecting rod 10, and at this time, the first operating platform 8 and the second operating platform 9 are both located above the second connecting rod 12. It should be noted that two second fastening nuts 1202 are provided on the second threaded sections 1201 at both ends of the second connecting rod 12 to prevent the front support 6 and the rear support 7 from moving in a direction approaching each other.
[0069] In order to support the end of the first operating platform 8 away from the front support 6 and the end of the second operating platform 9 away from the rear support 7, a plurality of supporting holes 1203 are provided in the middle of the second connecting rod 12, and the third connecting rod 13 is threadedly connected to the inner thread of the supporting hole 1203. According to the length of the first operating platform 8 and the second operating platform 9, the third connecting rod 13 is threadedly connected to the corresponding supporting hole 1203, so that the bottom of the first operating platform 8 and the second operating platform 9 can be supported.
[0070] Furthermore, a plurality of connecting ribs 14 are provided between the first operating platform 8 and the second operating platform 9. Both the first operating platform 8 and the second operating platform 9 adopt a steel mesh structure. By hooking the ends of the connecting ribs 14 on the steel mesh, the first operating platform 8 and the second operating platform 9 can be reinforced and connected. At the same time, the gap between the first operating platform 8 and the second operating platform 9 can be filled to prevent construction workers from falling from the gap between the first operating platform 8 and the second operating platform 9.
[0071] Furthermore, in this embodiment, the front support 6 and the rear support 7 are both configured as movable and height-adjustable structures, so as to facilitate the movement and height adjustment of the entire temporary support steel arch frame.
[0072] Specifically, an adjusting screw 603 is threadedly connected inside the support rod 602 along the axial direction, a mounting groove for connecting the adjusting screw 603 is provided at the bottom of the support rod 602, the adjusting screw 603 passes through the bottom of the support rod 602, and an adjusting nut 604 is threadedly connected to the adjusting screw 603. In this embodiment, the adjusting screw 603 can adopt a spiral ribbed steel bar structure, and its outer side wall can be threadedly matched with the adjusting nut 604. The lower part of the support rod 602 is a hollow steel pipe structure, and the inner diameter of the support rod 602 is slightly larger than the outer diameter of the adjusting screw 603, so that the support rod 602 can move up and down outside the adjusting screw 603. The adjusting nut 604 is not connected to the bottom of the support rod 602, but the adjusting nut 604 can support the support rod 602 through mutual contact. When the adjusting nut 604 is rotated upward, the support rod 602 will be lifted upward accordingly, thereby adjusting the height of the support rod 602 and the steel arch frame body 601.
[0073] It should be noted that when adjusting the height of the steel arch frame body 601 in the present invention, it is necessary to adjust the adjusting nuts 604 corresponding to the bottom of both ends of the steel arch frame body 601 at the same time to avoid the steel arch frame body 601 from tilting during unilateral adjustment, causing the support rod 602 on the other side to be stuck.
[0074] In addition, a moving wheel 605 is installed at the bottom of each adjusting screw 603. The two moving wheels 605 can realize the movement of the entire front support 6. The moving wheel 605 is a universal wheel with a brake and can be locked after moving to the desired position.
[0075] Preferably, a scale ruler can be set on the adjusting screw 603, and the settlement of the tunnel vault can be monitored in real time by observing the scale ruler corresponding to the adjusting nut 604 to avoid tunnel collapse during the removal of the deformed steel arch frame; if the settlement during the normal support period is too large, it can also be considered to replace different steel sections and re-support to avoid collapse.
[0076] The temporary support steel arch frame in this embodiment is used as a temporary support when the deformed steel arch frame is dismantled, and its specific operation process includes the following steps: Step 1: Before temporary support, connect the first operating platform 8 with the front support 6, and the second operating platform 9 with the rear support 7; Specifically, according to the required height of the first operating platform 8, the first connecting rod 10 is inserted into the first mounting hole 6021 of the corresponding height, and according to the distance between the two support rods 602, the first fastening nut 1002 is screwed on the first threaded section 1001 to fix the first connecting rod 10, and then the arc-shaped clamping ring 11 at the end of the first operating platform 8 is clamped on the first connecting rod 10. In the same way, the second operating platform 9 is connected to the rear support 7.
[0077] Step 2: Under the first connecting rod 10, the front support 6 and the rear support 7 are connected together through the second connecting rod 12, and then according to the length of the first operating platform 8 and the second operating platform 9, the third connecting rod 13 is threadedly connected to the corresponding supporting hole 1203 to support the bottom of the first operating platform 8 and the second operating platform 9; Step 3: Hook a connecting rib 14 between the first operating platform 8 and the second operating platform 9 to strengthen the connection strength between the first operating platform 8 and the second operating platform 9. At the same time, it can fill the gap between the first operating platform 8 and the second operating platform 9 to prevent construction workers from falling from the gap between the first operating platform 8 and the second operating platform 9.
[0078] Step 4: Move the front support 6 and the rear support 7 to the position where temporary support is required via the moving wheel 605, then turn the adjusting nut 604 to lift the support rod 602 and the steel arch frame body 601 upwards, and adjust the height of the steel arch frame body 601 to be close to the arch top.
[0079] The above shows and describes the basic principles, main features and advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.
Claims
1. A method for treating a silt collapse section in a small-section tunnel, characterized in that: The following steps are involved: Step 1: Remove slag from the excavated tunnel section; Step 2: After the slag is discharged, the tunnel is reinforced with an advance small guide tube and a pipe shed; Step 3: Grouting is carried out through the advanced small pipe to block the water in the tunnel and backfill the cavity; Step 4: construct temporary supporting steel arch frames for the deformed section of the primary support, then dismantle the steel arch frames of the deformed section of the primary support frame by frame, and re-construct the initial support; Step 5: Lay drainage pipes on the tunnel arch and left and right side walls; Step 6: Spray concrete and carry out normal tunnel construction process.
2. The method for treating a silt collapse section of a small-section tunnel according to claim 1 is characterized in that: In step 1, water glass, cement, accelerator and fine sand are added to the muddy carbonaceous shale, and the mixture is stirred and solidified before slagging; the mass ratio of water glass, cement, accelerator and fine sand is 1:35~40:10~13:16~20.
3. The method for treating a silt collapse section in a small-section tunnel according to claim 1 is characterized in that: The small leading conduit in step 2 comprises a steel tube (1) and a steel flower tube (2); The steel pipe (1) is symmetrically divided into left and right halves along the central axis; The steel flower tube (2) is movably sleeved outside the steel tube (1), and the steel flower tube (2) is also a two-half structure.
4. The method for treating a silt collapse section in a small-section tunnel according to claim 3 is characterized by: The steel pipe (1) comprises a left half steel pipe (101), a right half steel pipe (102) and two fasteners (104); Both ends of the left half steel pipe (101) and the right half steel pipe (102) are provided with slots (103); the fastener (104) is located between two corresponding slots (103).
5. The advanced small conduit structure for the karst development section of a tunnel according to claim 4 is characterized in that: A hook (3) for clamping with the steel pipe (1) is provided on the inner side wall of the front end of the first steel flower pipe (2); the front end and the rear end of each steel flower pipe (2) are both inclined structures.
6. The advanced small conduit structure for the karst development section of a tunnel according to claim 5, characterized in that: A groove (4) is provided on the outer side wall of the steel pipe (1), and a clamping block (5) matching the groove (4) is provided on the inner side wall of the steel flower pipe (2).
7. The advanced small conduit structure for the karst development section of a tunnel according to claim 1 is characterized by: The temporary supporting steel arch frame described in step 4 includes a front support (6) and a rear support (7) having the same structure; The rear side of the front support (6) is movably connected to a first operating platform (8) with adjustable height, and the front side of the rear support (7) is movably connected to a second operating platform (9) with adjustable height. The first operating platform (8) and the second operating platform (9) are detachably connected.
8. The advanced small conduit structure for the karst development section of a tunnel according to claim 7, characterized in that: The front support (6) comprises a steel arch frame body (601) and two support rods (602); The two support rods (602) are respectively located at the bottom of both ends of the steel arch frame body (601); and a first connecting rod (5) with adjustable height is detachably connected between the two support rods (102), and the first operating platform (3) is detachably connected to the first connecting rod (5).
9. The advanced small conduit structure for the karst development section of a tunnel according to claim 8, characterized in that: A second connecting rod (12) with adjustable height is detachably connected between two supporting rods (602) corresponding to each other of the front support (6) and the rear support (7), and a third connecting rod (13) for supporting the first operating platform (8) and the second operating platform (9) is detachably connected to the second connecting rod (12).
10. The advanced small conduit structure for the karst development section of a tunnel according to claim 9, characterized in that: An adjusting screw (603) is connected inside the support rod (602) along the axial direction; The adjusting screw (603) passes through the bottom of the supporting rod (602), and an adjusting nut (604) is threadedly connected to the adjusting screw (603), and the adjusting nut (604) is located below the supporting rod (602); and a moving wheel (605) is provided at the bottom of the adjusting screw (603).