Distributed photovoltaic system comprehensive treatment method based on edge calculation
Through edge computing technology, intelligent regulation of overvoltage, photovoltaic reversal and islands is achieved in distributed photovoltaic systems, solving the distribution network problems caused by distributed photovoltaic access, and improving the stability and regulation accuracy of the system.
Patent Information
- Application Number
- CN202411193820.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-28
- Publication Date
- 2024-11-22
AI Technical Summary
Large-area access of distributed photovoltaics leads to overvoltage of distribution networks, photovoltaic reversal and island problems, affecting the safe and stable operation of distribution networks.
Adopt the comprehensive management method of distributed photovoltaic system based on edge computing, and directly control the photovoltaic inverter and smart switch through intelligent fusion terminals, realizing overvoltage processing, photovoltaic reversal processing and island backup protection, adopting single-point batch control mode and The comprehensive sequential regulation mode regulates the voltage and performs active and reactive power adjustment in group control.
It realizes rapid response and flexible adjustment to distributed photovoltaic systems, reduces the aging of distribution network equipment and the risks of electrical insulation damage, ensures the safe and stable operation of the distribution network, and improves the granularity of governance.
Smart Images

Figure CN119010191A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of photovoltaic control, and in particular to a comprehensive management method for a distributed photovoltaic system based on edge computing. Background Art
[0002] With the gradual implementation of the dual carbon goals, the high-frequency and disorderly access of new elements such as distributed photovoltaics, energy storage, and charging piles in the context of the new power system has brought more and more impacts and challenges to the large power grid. In particular, the access of distributed photovoltaics to the entire region has brought about overvoltage at the grid connection point, photovoltaic reverse transmission, and photovoltaic islands. In the distribution network system with a large amount of actual photovoltaic access, the problem of overvoltage is particularly prominent during the period of full photovoltaic power generation. The overvoltage of the distribution network will cause a series of problems such as accelerated aging of the equipment of the distribution line and serious damage to the electrical insulation, which seriously affects the safe and stable operation of the distribution network. Summary of the invention
[0003] As a key device for the terminal device perception and control strategy deployment of the distribution network, the intelligent fusion terminal in the substation area carries the important functions of the collection and access of terminal devices such as distributed photovoltaic, energy storage, charging piles and intelligent perception sensors in the substation area, a series of strategy deployments such as distribution network collection and control, as well as the transmission hub and regulation response on the master station side. In order to solve the problems caused by the large-scale access of distributed photovoltaics mentioned above and give full play to the edge computing capabilities of the intelligent fusion terminal in the substation area, on the premise of realizing the access of distributed photovoltaics based on the substation area fusion terminal, the present invention proposes a comprehensive management method of distributed photovoltaic systems based on edge computing to achieve smooth access of distributed photovoltaics under the background of new power systems.
[0004] The present invention provides a method for comprehensive management of a distributed photovoltaic system based on edge computing, wherein the distributed photovoltaic system includes a power distribution cloud master station, an intelligent fusion terminal, a plurality of photovoltaic panels, and a photovoltaic inverter and a photovoltaic intelligent switch corresponding to each photovoltaic panel, wherein the photovoltaic inverter, the photovoltaic intelligent switch and the intelligent fusion terminal are connected in communication and are directly controlled by the intelligent fusion terminal, and the intelligent fusion terminal is connected in communication with the power distribution cloud master station; The comprehensive treatment method of the present invention includes overvoltage treatment, photovoltaic reverse transmission treatment, island backup protection treatment, and group adjustment and control; Overvoltage handling includes: Overvoltage processing includes single-point batch control mode or comprehensive sequential control mode. In overvoltage processing, the voltage of the grid-connected point corresponding to each photovoltaic inverter is regularly collected, and the sliding average voltage is used as the actual voltage of the grid-connected point; the voltage of the grid-connected point is the three-phase average voltage value or the maximum phase voltage value; The single-point batch control mode includes the following: At each adjustment interval, check whether the actual voltage of each grid-connected point exceeds the voltage limit during this adjustment interval; when a grid-connected point has no voltage exceeding the voltage limit for n consecutive adjustment intervals, the power limit of the corresponding photovoltaic inverter is increased by a fine adjustment ratio after each adjustment interval, where n is a natural number greater than 1; For grid-connected points with voltage exceeding the limit, perform the following operations: S1: Set the power limit of the PV inverter corresponding to the grid-connected point to the current power percentage. After each adjustment interval, set the power limit to be adjusted down by a coarse adjustment ratio until the voltage at the grid-connected point no longer exceeds the limit. S2: After each adjustment interval, the power limit is set to increase by a fine adjustment ratio until the voltage at the grid connection point exceeds the limit again; S3: After each adjustment interval, the power limit is set to be adjusted down by a fine adjustment ratio until the voltage at the grid connection point no longer exceeds the limit; Among them, the coarse adjustment ratio is greater than the fine adjustment ratio; The comprehensive sequential control model includes the following: At each adjustment interval, check whether the actual voltage of each grid-connected point exceeds the voltage limit during this adjustment interval; if the voltage of any grid-connected point exceeds the voltage limit, execute the down-regulation strategy; if the actual voltage of all grid-connected points does not exceed the voltage limit or the down-regulation strategy is executed Ndown times in succession, execute the callback strategy Nup times, where Ndown and Nup are natural numbers; Downward adjustment strategy: The photovoltaic inverters corresponding to the grid-connected points with voltage exceeding the limit are sorted from high to low according to the voltage value, and then the photovoltaic inverters are classified into single-phase and three-phase; First, manage the single-phase photovoltaic inverter: The power limit of the first single-phase photovoltaic inverter is set to the percentage of the current power, and the power limit is set to be adjusted down by a rough adjustment ratio; according to the interval of regular voltage collection, after the actual voltage of all photovoltaic inverters is updated once, it is determined whether the voltage of the second single-phase photovoltaic inverter is still over the limit. If so, the power limit of this single-phase photovoltaic inverter is set to the percentage of the current power, and the power limit is set to be adjusted down by a rough adjustment ratio; and so on, the remaining single-phase photovoltaic inverters are executed in sequence; Then manage the three-phase photovoltaic inverter: The power limit of the first three-phase photovoltaic inverter is set to the percentage of the current power, and the power limit is set to be adjusted down by a rough adjustment ratio; according to the interval of regular voltage collection, after the actual voltage of all photovoltaic inverters is updated once, it is determined whether the voltage of the second three-phase photovoltaic inverter is still over the limit. If so, the power limit of this three-phase photovoltaic inverter is set to the percentage of the current power, and the power limit is set to be adjusted down by a rough adjustment ratio; and so on, the remaining three-phase photovoltaic inverters are executed in sequence; Callback strategy: The photovoltaic inverters corresponding to the grid-connected points whose actual voltage is less than the return voltage threshold are sorted from low to high according to the voltage value, and then the photovoltaic inverters are classified into single-phase and three-phase; First, call back the three-phase photovoltaic inverter: For the first three-phase photovoltaic inverter, set the power limit to increase by a fine adjustment ratio; according to the interval of regular voltage collection, wait for the actual voltage of all photovoltaic inverters to be updated once, and then determine whether the actual voltage of the grid connection point corresponding to the second three-phase photovoltaic inverter is still less than the return voltage threshold. If so, set the power limit to increase by a fine adjustment ratio for this three-phase photovoltaic inverter; and so on, execute the remaining three-phase photovoltaic inverters in sequence; Then call back the single-phase photovoltaic inverter: For the first single-phase photovoltaic inverter, set the power limit to increase by a fine adjustment ratio; according to the interval of regular voltage collection, wait for the actual voltage of all photovoltaic inverters to be updated once, and then determine whether the actual voltage of the grid-connected point corresponding to the second single-phase photovoltaic inverter is still less than the return voltage threshold. If so, set the power limit to increase by a fine adjustment ratio for this single-phase photovoltaic inverter; and so on, execute the remaining single-phase photovoltaic inverters in sequence.
[0005] Preferably, the photovoltaic reverse transport process includes: The distribution transformer load rate of the substation is collected regularly, and the sliding average distribution transformer load rate is used as the actual distribution transformer load rate of the substation; At each adjustment interval, check whether the actual distribution transformer load rate in the substation is in the reverse direction during this adjustment interval, and whether the value is higher than the distribution transformer reverse load rate threshold. If so, perform the following operations on all PV inverters: The PV inverter sets the power limit as a percentage of the current power, and sets the power limit to be adjusted down by a fine adjustment ratio; if the power limit cannot be adjusted down, the corresponding PV smart switch will trip; At each adjustment interval, check whether the actual distribution transformer load rate in the substation is in the positive direction during this adjustment interval, and whether the value is higher than the distribution transformer positive return load rate threshold. If so, perform the following operations on all PV inverters: If the photovoltaic smart switch corresponding to the photovoltaic inverter is in a tripped state, close the photovoltaic smart switch, otherwise set the power limit to increase by a fine adjustment ratio.
[0006] Preferably, the island backup protection process includes: The intelligent fusion terminal detects the three-phase voltage and frequency of the substation. When it is detected that the three-phase voltage is lower than the set voltage threshold and the frequency is lower than the set frequency threshold, and the duration reaches the set time threshold, it is judged that the substation is out of power and all photovoltaic intelligent switches are tripped; When the intelligent fusion terminal receives the remote control grid-connected command from the distribution cloud master station, it controls all photovoltaic intelligent switches to close.
[0007] Preferably, group adjustment and group control include: When the intelligent fusion terminal receives the remote control grid connection command from the power distribution cloud master station, it controls all photovoltaic intelligent switches to close; When the intelligent fusion terminal receives the remote control off-grid command from the power distribution cloud master station, it controls all photovoltaic intelligent switches to open; When the intelligent fusion terminal receives the active power and reactive power adjustment commands from the distribution cloud master station, it decomposes the commands and performs adjustment in proportion to the percentage of the rated active power / rated reactive power of each photovoltaic inverter in the entire substation; active power adjustment and reactive power adjustment are not performed at the same time, and active power adjustment is performed only after the reactive power adjustment process is completed; When the intelligent fusion terminal receives the command to release photovoltaic regulation from the distribution cloud master station, it restores all photovoltaic inverters to MPPT power generation mode.
[0008] Preferably, the adjustment interval is 10 minutes, and the value of n is 6.
[0009] Preferably, the interval of regular collection is 1 minute.
[0010] Preferably, the coarse adjustment ratio is 10% and the fine adjustment ratio is 2%.
[0011] Beneficial effects: The present invention adopts a distributed photovoltaic comprehensive management method based on the intelligent fusion terminal of the substation, which gives full play to the local edge computing capability of the substation's intelligent fusion, realizes rapid response to overvoltage and photovoltaic reverse transmission judgment and decision execution, and supports photovoltaic group adjustment and group control. The master station can send the active and reactive targets of the substation control to the fusion terminal, decompose the target value of the photovoltaic comprehensive management strategy, and decompose the instructions to the household. The photovoltaic control box installed on the inverter side realizes flexible adjustment of distributed photovoltaics, and the whole execution process is achieved within minutes, achieving better management effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 This is a structural diagram of a distributed photovoltaic system in an embodiment of the present invention. DETAILED DESCRIPTION
[0013] In order to make the purpose, features and advantages of the present invention more obvious and easy to understand, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the embodiments described below are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0014] A method for comprehensive management of a distributed photovoltaic system based on edge computing, wherein the distributed photovoltaic system includes a power distribution cloud master station, an intelligent fusion terminal, a plurality of photovoltaic panels, and a photovoltaic inverter and a photovoltaic intelligent switch corresponding to each photovoltaic panel, wherein the photovoltaic inverter, the photovoltaic intelligent switch and the intelligent fusion terminal are connected in communication and are directly controlled by the intelligent fusion terminal, and the intelligent fusion terminal is connected in communication with the power distribution cloud master station; like Figure 1 As shown in the figure, a possible distributed photovoltaic system is provided. Under the premise that the photovoltaic inverter and photovoltaic intelligent switch can be connected to the intelligent fusion terminal of the substation and accept the latter's regulation, the photovoltaic inverter communicates with the intelligent fusion terminal through 485 / HPLC communication mode, and the photovoltaic intelligent switch communicates with the intelligent fusion terminal through HPLC communication mode (embedded carrier module), and accepts the regulation of the intelligent fusion terminal, which can realize the rigid control / flexible regulation of the grid-connected and off-grid distributed photovoltaic equipment; the photovoltaic inverter acquisition serial port adapter module is added to realize the simultaneous acquisition of the communication stick and the fusion terminal. The intelligent fusion terminal uploads the data to the distribution cloud master station through the 4G / 5G network; on the distribution cloud master station platform side, through user information registration and graphic drawing, the distribution cloud master station can remotely monitor, display and regulate the on-site distributed photovoltaic.
[0015] The present invention improves the overvoltage processing, photovoltaic reverse transmission processing, island backup protection processing, and group modulation and control in the prior art; The comprehensive treatment method of the present invention includes overvoltage treatment, photovoltaic reverse transmission treatment, island backup protection treatment, and group adjustment and control; Overvoltage handling includes single-point batch control mode or comprehensive sequential control mode; In the overvoltage processing, the voltage of the grid connection point corresponding to each photovoltaic inverter is regularly collected, and the sliding average voltage is used as the actual voltage of the grid connection point; in this embodiment, the interval of regular collection is 1 minute; the voltage of the grid connection point is the three-phase average voltage value or the maximum phase voltage value; The single-point batch control mode includes the following: At each adjustment interval, check whether the actual voltage of each grid-connected point exceeds the voltage limit within the adjustment interval; when a grid-connected point has no voltage exceeding the voltage limit for n consecutive adjustment intervals, the power limit of the corresponding photovoltaic inverter is increased by a fine adjustment ratio after each adjustment interval, where n is a natural number greater than 1. In this embodiment, the adjustment interval is 10 minutes, and the value of n is 6; For grid-connected points with voltage exceeding the limit, perform the following operations: S1: Set the power limit of the PV inverter corresponding to the grid-connected point to the current power percentage. After each adjustment interval, set the power limit to be adjusted down by a coarse adjustment ratio until the voltage at the grid-connected point no longer exceeds the limit. S2: After each adjustment interval, the power limit is set to increase by a fine adjustment ratio until the voltage at the grid connection point exceeds the limit again; S3: After each adjustment interval, the power limit is set to be adjusted down by a fine adjustment ratio until the voltage at the grid connection point no longer exceeds the limit; The coarse adjustment ratio is greater than the fine adjustment ratio. In this embodiment, the coarse adjustment ratio is 10% and the fine adjustment ratio is 2%.
[0016] This mode does not consider the topological distribution of each photovoltaic point, the distance from the station and other influencing factors. It performs single-point batch independent regulation on each single point according to the voltage problem of each grid-connected point, and uses coarse / fine adjustment to control overvoltage. The comprehensive sequential control model includes the following: At each adjustment interval, check whether the actual voltage of each grid-connected point exceeds the voltage limit during this adjustment interval; if the voltage of any grid-connected point exceeds the voltage limit, execute the down-regulation strategy; if the actual voltage of all grid-connected points does not exceed the voltage limit or the down-regulation strategy is executed Ndown times in succession, execute the callback strategy Nup times, where Ndown and Nup are natural numbers. In this implementation, the value of Ndown is 1 and the value of Nup is 1; Downward adjustment strategy: The photovoltaic inverters corresponding to the grid-connected points with voltage exceeding the limit are sorted from high to low according to the voltage value, and then the photovoltaic inverters are classified into single-phase and three-phase; First, manage the single-phase photovoltaic inverter: The power limit of the first single-phase photovoltaic inverter is set to the percentage of the current power, and the power limit is set to be adjusted down by a rough adjustment ratio; according to the interval of regular voltage collection, after the actual voltage of all photovoltaic inverters is updated once, it is determined whether the voltage of the second single-phase photovoltaic inverter is still over the limit. If so, the power limit of this single-phase photovoltaic inverter is set to the percentage of the current power, and the power limit is set to be adjusted down by a rough adjustment ratio; and so on, the remaining single-phase photovoltaic inverters are executed in sequence; Then manage the three-phase photovoltaic inverter: The power limit of the first three-phase photovoltaic inverter is set to the percentage of the current power, and the power limit is set to be adjusted down by a rough adjustment ratio; according to the interval of regular voltage collection, after the actual voltage of all photovoltaic inverters is updated once, it is determined whether the voltage of the second three-phase photovoltaic inverter is still over the limit. If so, the power limit of this three-phase photovoltaic inverter is set to the percentage of the current power, and the power limit is set to be adjusted down by a rough adjustment ratio; and so on, the remaining three-phase photovoltaic inverters are executed in sequence; Callback strategy: The photovoltaic inverters corresponding to the grid-connected points whose actual voltage is less than the return voltage threshold are sorted from low to high according to the voltage value, and then the photovoltaic inverters are classified into single-phase and three-phase. In this embodiment, the return voltage threshold is 2V; First, call back the three-phase photovoltaic inverter: For the first three-phase photovoltaic inverter, set the power limit to increase by a fine adjustment ratio; according to the interval of regular voltage collection, wait for the actual voltage of all photovoltaic inverters to be updated once, and then determine whether the actual voltage of the grid connection point corresponding to the second three-phase photovoltaic inverter is still less than the return voltage threshold. If so, set the power limit to increase by a fine adjustment ratio for this three-phase photovoltaic inverter; and so on, execute the remaining three-phase photovoltaic inverters in sequence; Then call back the single-phase photovoltaic inverter: For the first single-phase photovoltaic inverter, set the power limit to increase by a fine adjustment ratio; according to the interval of regular voltage collection, wait for the actual voltage of all photovoltaic inverters to be updated once, and then determine whether the actual voltage of the grid-connected point corresponding to the second single-phase photovoltaic inverter is still less than the return voltage threshold. If so, set the power limit to increase by a fine adjustment ratio for this single-phase photovoltaic inverter; and so on, execute the remaining single-phase photovoltaic inverters in sequence; The comprehensive sequential control mode is regulated according to the voltage level (voltage level reflects the distance and the factors affecting overvoltage) and the photovoltaic type (single-phase, three-phase). Single-phase overvoltage is controlled first, and the three-phase imbalance caused by single-phase overvoltage causes other three-phase inverters to delay the judgment of overvoltage, thereby reducing the comprehensive distributed photovoltaic power limit; then the three-phase overvoltage is controlled, and the voltage value is sorted, and the high voltage overvoltage value is controlled first, and then the low voltage overvoltage value is controlled.
[0017] Photovoltaic reverse transmission processing includes: The distribution transformer load rate of the substation is collected regularly, and the sliding average distribution transformer load rate is used as the actual distribution transformer load rate of the substation; At each adjustment interval, check whether the actual distribution transformer load rate in the substation is in the reverse direction during this adjustment interval, and whether the value is higher than the distribution transformer reverse load rate threshold. If so, perform the following operations on all PV inverters: The PV inverter sets the power limit as a percentage of the current power, and sets the power limit to be adjusted down by a fine adjustment ratio; if the power limit cannot be adjusted down, the corresponding PV smart switch will trip; At each adjustment interval, check whether the actual distribution transformer load rate in the substation is in the positive direction during this adjustment interval, and whether the value is higher than the distribution transformer positive return load rate threshold. If so, perform the following operations on all PV inverters: If the photovoltaic smart switch corresponding to the photovoltaic inverter is in the tripped state, close the photovoltaic smart switch, otherwise set the power limit to increase by a fine adjustment ratio; Island backup protection processing includes: The intelligent fusion terminal detects the three-phase voltage and frequency of the substation. When it is detected that the three-phase voltage is lower than the set voltage threshold and the frequency is lower than the set frequency threshold, and the duration reaches the set time threshold, it is judged that the substation is out of power and all photovoltaic intelligent switches are tripped; When the intelligent fusion terminal receives the remote control grid connection command from the power distribution cloud master station, it controls all photovoltaic intelligent switches to close; Group adjustment and control include: When the intelligent fusion terminal receives the remote control grid connection command from the power distribution cloud master station, it controls all photovoltaic intelligent switches to close; When the intelligent fusion terminal receives the remote control off-grid command from the power distribution cloud master station, it controls all photovoltaic intelligent switches to open; When the intelligent fusion terminal receives the active power and reactive power adjustment commands from the distribution cloud master station, it decomposes the commands and performs adjustments in proportion to the percentage of the rated active power / rated reactive power of each photovoltaic inverter in the entire substation; active power adjustment and reactive power adjustment are not performed at the same time, and active power adjustment is performed only after the reactive power adjustment process is completed.
[0018] When the intelligent fusion terminal receives the command to release photovoltaic regulation from the distribution cloud master station, it restores all photovoltaic inverters to MPPT power generation mode.
[0019] Through the implementation of the above-mentioned edge computing strategy based on intelligent terminals in the substation, the most core comprehensive control strategies of overvoltage, photovoltaic reverse transmission, distributed photovoltaic island backup protection and group control in the distributed photovoltaic grid-connected process are realized. The above strategy is combined with the intelligent perception of the operating status of the substation transformer to realize the stable and safe operation of the microgrid under the background of the new power system, and realizes the comprehensive management of distributed photovoltaic grid-connected based on edge computing and can improve the granularity of comprehensive management and control.
[0020] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A comprehensive management method for distributed photovoltaic systems based on edge computing, characterized in that: The distributed photovoltaic system includes a power distribution cloud master station, an intelligent fusion terminal, a plurality of photovoltaic panels, and a photovoltaic inverter and a photovoltaic intelligent switch corresponding to each photovoltaic panel, wherein the photovoltaic inverter, the photovoltaic intelligent switch and the intelligent fusion terminal are connected in communication and are directly controlled by the intelligent fusion terminal, and the intelligent fusion terminal is connected in communication with the power distribution cloud master station; The comprehensive treatment method of the present invention includes overvoltage treatment, photovoltaic reverse transmission treatment, island backup protection treatment, and group adjustment and control; Overvoltage handling includes: Overvoltage processing includes single-point batch control mode or comprehensive sequential control mode. In overvoltage processing, the voltage of the grid-connected point corresponding to each photovoltaic inverter is regularly collected, and the sliding average voltage is used as the actual voltage of the grid-connected point; the voltage of the grid-connected point is the three-phase average voltage value or the maximum phase voltage value; The single-point batch control mode includes the following: At each adjustment interval, check whether the actual voltage of each grid-connected point exceeds the voltage limit during this adjustment interval; when a grid-connected point has no voltage exceeding the voltage limit for n consecutive adjustment intervals, the power limit of the corresponding photovoltaic inverter is increased by a fine adjustment ratio after each adjustment interval, where n is a natural number greater than 1; For grid-connected points with voltage exceeding the limit, perform the following operations: S1: Set the power limit of the PV inverter corresponding to the grid-connected point to the current power percentage. After each adjustment interval, set the power limit to be adjusted down by a coarse adjustment ratio until the voltage at the grid-connected point no longer exceeds the limit. S2: After each adjustment interval, the power limit is set to increase by a fine adjustment ratio until the voltage at the grid connection point exceeds the limit again; S3: After each adjustment interval, the power limit is set to be adjusted down by a fine adjustment ratio until the voltage at the grid connection point no longer exceeds the limit; Among them, the coarse adjustment ratio is greater than the fine adjustment ratio; The comprehensive sequential control model includes the following: At each adjustment interval, check whether the actual voltage of each grid-connected point exceeds the voltage limit during this adjustment interval; if the voltage of any grid-connected point exceeds the voltage limit, execute the down-regulation strategy; if the actual voltage of all grid-connected points does not exceed the voltage limit or the down-regulation strategy is executed Ndown times in succession, execute the callback strategy Nup times, where Ndown and Nup are natural numbers; Downward adjustment strategy: The photovoltaic inverters corresponding to the grid-connected points with voltage exceeding the limit are sorted from high to low according to the voltage value, and then the photovoltaic inverters are classified into single-phase and three-phase; First, manage the single-phase photovoltaic inverter: The power limit of the first single-phase photovoltaic inverter is set to the percentage of the current power, and the power limit is set to be adjusted down by a rough adjustment ratio; according to the interval of regular voltage collection, after the actual voltage of all photovoltaic inverters is updated once, it is determined whether the voltage of the second single-phase photovoltaic inverter is still over the limit. If so, the power limit of this single-phase photovoltaic inverter is set to the percentage of the current power, and the power limit is set to be adjusted down by a rough adjustment ratio; and so on, the remaining single-phase photovoltaic inverters are executed in sequence; Then manage the three-phase photovoltaic inverter: The power limit of the first three-phase photovoltaic inverter is set to the percentage of the current power, and the power limit is set to be adjusted down by a rough adjustment ratio; according to the interval of regular voltage collection, after the actual voltage of all photovoltaic inverters is updated once, it is determined whether the voltage of the second three-phase photovoltaic inverter is still over the limit. If so, the power limit of this three-phase photovoltaic inverter is set to the percentage of the current power, and the power limit is set to be adjusted down by a rough adjustment ratio; and so on, the remaining three-phase photovoltaic inverters are executed in sequence; Callback strategy: The photovoltaic inverters corresponding to the grid-connected points whose actual voltage is less than the return voltage threshold are sorted from low to high according to the voltage value, and then the photovoltaic inverters are classified into single-phase and three-phase; First, call back the three-phase photovoltaic inverter: For the first three-phase photovoltaic inverter, set the power limit to increase by a fine adjustment ratio; according to the interval of regular voltage collection, wait for the actual voltage of all photovoltaic inverters to be updated once, and then determine whether the actual voltage of the grid connection point corresponding to the second three-phase photovoltaic inverter is still less than the return voltage threshold. If so, set the power limit to increase by a fine adjustment ratio for this three-phase photovoltaic inverter; and so on, execute the remaining three-phase photovoltaic inverters in sequence; Then call back the single-phase photovoltaic inverter: For the first single-phase photovoltaic inverter, set the power limit to increase by a fine adjustment ratio; according to the interval of regular voltage collection, wait for the actual voltage of all photovoltaic inverters to be updated once, and then determine whether the actual voltage of the grid-connected point corresponding to the second single-phase photovoltaic inverter is still less than the return voltage threshold. If so, set the power limit to increase by a fine adjustment ratio for this single-phase photovoltaic inverter; and so on, execute the remaining single-phase photovoltaic inverters in sequence.
2. According to the method of comprehensive management of distributed photovoltaic system based on edge computing in claim 1, it is characterized in that: Photovoltaic reverse transmission processing includes: The distribution transformer load rate of the substation is collected regularly, and the sliding average distribution transformer load rate is used as the actual distribution transformer load rate of the substation; At each adjustment interval, check whether the actual distribution transformer load rate in the substation is in the reverse direction during this adjustment interval, and whether the value is higher than the distribution transformer reverse load rate threshold. If so, perform the following operations on all PV inverters: The PV inverter sets the power limit as a percentage of the current power, and sets the power limit to be adjusted down by a fine adjustment ratio; if the power limit cannot be adjusted down, the corresponding PV smart switch will trip; At each adjustment interval, check whether the actual distribution transformer load rate in the substation is in the positive direction during this adjustment interval, and whether the value is higher than the distribution transformer positive return load rate threshold. If so, perform the following operations on all PV inverters: If the photovoltaic smart switch corresponding to the photovoltaic inverter is in the tripped state, close the photovoltaic smart switch, otherwise set the power limit to increase by a fine adjustment ratio.
3. According to a method for comprehensive management of distributed photovoltaic systems based on edge computing according to claim 1, it is characterized in that: Island backup protection processing includes: The intelligent fusion terminal detects the three-phase voltage and frequency of the substation. When it is detected that the three-phase voltage is lower than the set voltage threshold and the frequency is lower than the set frequency threshold, and the duration reaches the set time threshold, it is judged that the substation is out of power and all photovoltaic intelligent switches are tripped; When the intelligent fusion terminal receives the remote control grid-connected command from the distribution cloud master station, it controls all photovoltaic intelligent switches to close.
4. According to a method for comprehensive management of distributed photovoltaic systems based on edge computing according to claim 1, it is characterized in that: Group adjustment and control include: When the intelligent fusion terminal receives the remote control grid connection command from the power distribution cloud master station, it controls all photovoltaic intelligent switches to close; When the intelligent fusion terminal receives the remote control off-grid command from the power distribution cloud master station, it controls all photovoltaic intelligent switches to open; When the intelligent fusion terminal receives the active power and reactive power adjustment commands from the distribution cloud master station, it decomposes the commands and performs adjustment in proportion to the percentage of the rated active power / rated reactive power of each photovoltaic inverter in the entire substation; active power adjustment and reactive power adjustment are not performed at the same time, and active power adjustment is performed only after the reactive power adjustment process is completed; When the intelligent fusion terminal receives the command to release photovoltaic regulation from the distribution cloud master station, it restores all photovoltaic inverters to MPPT power generation mode.
5. According to a method for comprehensive management of distributed photovoltaic systems based on edge computing according to claim 1, it is characterized in that: The adjustment interval is 10 minutes and the value of n is 6.
6. According to a method for comprehensive management of distributed photovoltaic systems based on edge computing according to claim 1, it is characterized in that: The interval of periodic acquisition is 1 minute.
7. The method for comprehensive management of distributed photovoltaic systems based on edge computing according to claim 1, characterized in that: The coarse adjustment ratio is 10% and the fine adjustment ratio is 2%.
Citation Information
Cited By
Area voltage out-of-limit autonomous system and method based on active-reactive comprehensive control
CN119726760A