Quick-change module for rock slope greening and mounting method
Through the design of flexible planting components and fixed components, the problem of intimate contact between substrate and slope surface in rock slope greening is solved, the survival rate and coverage of vegetation is improved, maintenance costs are reduced, and more efficient ecological restoration is achieved.
Patent Information
- Application Number
- CN202411183878.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-27
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-08-27
AI Technical Summary
In the existing rock slope greening technology, the intimate contact between the substrate and the slope surface leads to difficulty in growth and uneven vegetation coverage, resulting in short survival time of vegetation, long ecological restoration cycle and high maintenance costs.
Flexible planting components are adopted, including a containment cavity, substrate filling cavity and soil cavity, and targeted fixation through flexible abutment and fixation components (such as rotating joints and fixed piles) to improve the fit density between the substrate and the rock slope. And add soil improvers, water retention agents and anti-erosion agents to the planting components, and use mixed slurry and plastic film cavity walls to achieve one-time and fast planting.
It improves the survival rate of green plants and vegetation coverage, reduces maintenance costs, reduces the demand for later replacement and maintenance, and significantly improves the ecological restoration effect of rock slopes.
Smart Images

Figure CN119014242A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of slope greening in agriculture and forestry, and in particular to a quick-change module for rock slope greening, and also to an installation method. Background Art
[0002] Rock slope greening is a new ecological slope protection method that can effectively protect exposed slopes. It is combined with traditional engineering slope protection to effectively restore the ecological vegetation on the slope. In some road construction projects, fixed building construction projects, etc., exposed slopes left after earth excavation, especially rock slopes, need to be greened to restore and protect ecological vegetation. Common rock slope greening techniques include stacking bags greening method, hanging nets and directly spraying greening nutrient materials greening method, and imported soil planting belt greening method. The slopes of the aforementioned slope greening methods cannot withstand the erosion of rainwater, and the vegetation is easily washed away. They have low drought resistance and poor greening effects.
[0003] In the prior art, the authorization announcement date is February 24, 2023, the authorization announcement number is CN113812283B, and the name is a Chinese invention patent for a rock slope greening vegetation system, which discloses a grid frame fixed on the slope surface, and each grid of the grid frame forms a filling area for filling planting materials. The planting material filled in the filling area is a soft foam material, and the plant seeds are covered under the surface of the soft foam material.
[0004] The aforementioned technology has the advantages of stable structure and strong water and fertilizer retention, but the overall planting survival rate needs to rely closely on soft foam materials, resulting in uncontrollable survival rate, and the subsequent maintenance and replacement costs are high. Summary of the invention
[0005] Through research, the inventors found that the existing rock slope greening treatment is prone to the problem that the substrate is not in close contact with the slope surface, resulting in growth difficulties, and the vegetation coverage is uneven, which is not conducive to grid soil fixation. The above problems will ultimately lead to a short survival time of green plants on rock slopes and a long ecological recovery cycle, which will in turn cause high maintenance costs.
[0006] The purpose of this application is to provide a quick-change module and installation method for rock slope greening, which solves the technical problem that the existing technology cannot reduce the maintenance cost of rock slopes while improving the survival rate of green plants through an integrated planting method and a targeted fixing method based on rock slopes.
[0007] According to one aspect of the present application, a quick-change module and installation method for rock slope greening are provided, including a flexible planting component, the flexible planting component including a accommodating cavity, a substrate filling cavity and a soil cavity, the upper and lower ends of the substrate filling cavity are flexibly abutted against the accommodating cavity, the soil cavity is flexibly abutted against the substrate filling cavity, and the accommodating cavity includes at least one group of first storage cavities for seed storage and at least one group of second storage cavities for culture solution storage.
[0008] In some embodiments, the soil cavity is rotatably connected to an end thereof away from the end flexibly abutting against the substrate filling cavity with a fixing component.
[0009] In some embodiments, the fixing assembly includes a rotating joint and a fixing pile rotatably connected to the rotating joint.
[0010] In some embodiments, the fixing pile forms an angle α with the bottom end surface of the soil cavity, and the value of α is: 0°≤α<90°.
[0011] In some embodiments, the soil cavity is a telescopic cavity.
[0012] In some embodiments, the substrate filling cavity is filled with a soil conditioner, a water retaining agent, an anti-corrosion agent, and water.
[0013] In some embodiments, a leakage hole is opened on the outer circumference of the first storage cavity, and the hole diameter of the leakage hole is smaller than the particle diameter of the seeds placed inside the leakage hole.
[0014] In some embodiments, the second storage chamber is filled with a mixed slurry, wherein the mixed slurry consists of Nagaculata biloba, Tetraselmis obliquus, Spirulina platensis and deionized water.
[0015] In some embodiments, the walls of the first storage cavity and the second storage cavity are both made of plastic films.
[0016] According to another aspect of the present application, a method for installing a quick-change module for rock slope greening is provided, comprising the following method:
[0017] Step 1. Open the installation hole on the rock slope in advance;
[0018] Step 2. Press the fixing assembly into the mounting hole;
[0019] Step 3. Press the receiving cavity and the substrate filling cavity into the soil cavity;
[0020] Step 4. Adjust the angle between the fixed pile and the bottom end surface of the soil cavity so that the soil cavity abuts against the rock slope protection slope surface.
[0021] To summarize, the present application realizes a one-time quick rock slope protection green plant planting by pressing the accommodating cavity and the substrate filling cavity in the flexible planting component, which is effectively different from the step-by-step sequential processing of the prior art; at the same time, the present application adds fixed piles and rotating joints to achieve adjustment to adapt to the angle of the rock slope, increase the tightness of the fit between the substrate and the rock slope surface, and overcome the prior art method of fixing plants on a single vertical slope protection surface, which results in high replacement and maintenance costs and low survival rate of green plants. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0023] Figure 1 This is a schematic diagram of the quick-change module of the present application in an overall non-working state after being combined with the rock slope protection;
[0024] Figure 2 This is a schematic diagram of the overall working state after the quick-change module of the present application is combined with the rock slope protection;
[0025] Figure 3 It is a structural schematic diagram of the quick-change module of the present application;
[0026] Figure 4 is a schematic diagram of the accommodation cavity of the quick-change module of the present application;
[0027] Figure 5 It is a schematic diagram of the non-working state of another overall implementation mode after the quick-change module of the present application is combined with the rock slope protection.
[0028] Legend:
[0029] 1- rock slope; 2- flexible planting component; 21- accommodating cavity; 211- first storage cavity; 212- second storage cavity; 22- substrate filling cavity; 23- soil cavity; 24- rotating joint; 25- fixed pile; 3- fixed component. DETAILED DESCRIPTION
[0030] The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments.
[0031] This embodiment provides a quick-change module and installation method for rock slope greening. The quick-change module and installation method are already in the test use stage of small-scale rock slope protection. Figure 1-4 Describe together.
[0032] Example 1
[0033] The present embodiment provides a quick-change module for rock slope greening, including a flexible planting component 2, wherein the flexible planting component 2 includes a receiving cavity 21, a substrate filling cavity 22, and a soil cavity 23. It should be noted that the flexible planting component 2 in the present embodiment is of an integrally compressible type, that is, the receiving cavity 21 and the substrate filling cavity 22 are compressible. During operation, with the help of external force of construction personnel, the receiving cavity 21 and the substrate filling cavity 22 are pressed into the soil cavity 23 together, forming a soil cavity 23 as shown in the attached description. Figure 2 Status shown.
[0034] Furthermore, the upper and lower ends of the substrate filling cavity 22 are flexibly abutted against the accommodating cavity 21, and the soil cavity 23 is flexibly abutted against the substrate filling cavity 22. The accommodating cavity 21 includes at least one group of first storage cavities 211 for storing seeds and at least one group of second storage cavities 212 for storing culture fluid. Specifically, the upper and lower ends of the substrate filling cavity 22 are flexibly abutted against the accommodating cavity 21. During operation, the substrate filling cavity 22 will be pressed together when the accommodating cavity 21 is pressed by the outside world. Then, when the substrate filling cavity 22 is deformed by the external pressure, the accommodating cavity 21 at the lower end of the substrate filling cavity 22 is further compressed, and finally all of the above are pressed into the soil cavity 23 to form an attached cavity. Figure 2 It should also be noted that in this embodiment, the substrate and soil are mixed by pressing them into each other instead of mixing them directly. The intuitive result is that the pressed substrate will be more deeply mixed into the soil.
[0035] Furthermore, the substrate filling cavity 22 is filled with soil improver, water retainer, anti-corrosion agent and water. It should be noted that the preparation process of the soil improver is as follows:
[0036] Step 1. Add polylactic acid to a sodium hydroxide solution and stir. After stirring, add sodium citrate again and stir. Then add anhydrous ethanol and stir. Let stand and dry to obtain an intermediate product M.
[0037] Step 2. Add magnesium chloride, copper sulfate and barium hypochlorite to deionized water and stir evenly, add the intermediate product M obtained in step 1, add ammonia water dropwise to react at a constant temperature, cool, centrifuge, wash and dry to obtain a secondary intermediate product N;
[0038] Step 3. The chitosan and acetic acid solution are mixed evenly to obtain a chitosan solution, ferulic acid is added to the chitosan solution to continue the reaction, and the intermediate product O is obtained after drying;
[0039] Step 4. Add the intermediate product N obtained in step 2 and the intermediate product O obtained in step 3 into deionized water, stir and then dry to obtain a soil conditioner.
[0040] Furthermore, a leakage hole is provided on the periphery of the first storage chamber 211, and the aperture of the leakage hole is smaller than the particle size of the seeds placed inside the leakage hole. The second storage chamber 212 is filled with a mixed slurry, and the mixed slurry is composed of Bispherical Algae, Oblique Tetrasegmentum, Platensis Spirulina and deionized water. The walls of the first storage chamber 211 and the second storage chamber 212 are both plastic films. Specifically, in this embodiment, a leakage hole is provided on the periphery of the first storage chamber 211, and the aperture of the leakage hole is smaller than the particle size of the seeds placed inside the leakage hole, in order to ensure that the seeds will not fall off by themselves after being placed in. Next, the second storage chamber 212 is filled with a mixed slurry, so that after being squeezed by the outside world, the seeds can be mixed with the mixed slurry to achieve seed pretreatment, which is different from the prior art, which needs to be a separate step process to cause the process to be complicated.
[0041] At the same time, the accommodating cavity 21 is set at both the upper and lower ends of the substrate filling cavity 22 in order to increase the vegetation coverage in the later stage and improve the overall fixing effect of the soil. In the prior art, in order to improve the fixing effect of the soil, an external grid paving is used for fixing, but it does not increase the vegetation coverage rate. The reason is that the grid paving is fixed by external force, and there are many influencing factors. The present embodiment relies on the density of natural growth of vegetation to fix the soil. Within a unit area, the higher the vegetation coverage rate, the better the soil fixation effect and the higher the vegetation survival rate.
[0042] Example 2
[0043] The technical features in this embodiment are basically the same as those recorded in the first embodiment. The same technical features and technical solutions are not repeated here. Only the differences between the second embodiment and the first embodiment are described here. The soil cavity 23 is rotatably connected to the end of the flexible abutment substrate filling cavity 22 with a fixing assembly 3. The fixing assembly 3 includes a rotating joint 24 and a fixing pile 25 rotatably connected to the rotating joint 24. The fixing pile 25 forms an angle α with the bottom end surface of the soil cavity 23, and the value is: 0°≤α<90°. Specifically, the fixing pile 25 and the bottom end surface of the soil cavity 23 are set at an angle, so that the quick-change module of this embodiment can be fixed on the rock slope protection more stably. In the prior art, the fixing is carried out in a manner perpendicular to the surface of the slope protection. Although the fixing is convenient, after a long time, due to the influence of gravity brought by the increase of vegetation, a gap is generated between the bottom of the vegetation planting and the surface of the slope protection, and it cannot fit closely, which eventually leads to growth difficulties and affects the survival rate of green plants. At the same time, due to the force, the cost of later repair and maintenance will also increase. The angled fixing method adopted in this embodiment can effectively realize the decomposition of gravity after the vegetation is added, reduce the probability of gaps, improve the fit between the bottom of the vegetation planting and the slope protection surface, and ultimately improve the survival rate of vegetation on the rock slope protection.
[0044] Example 3
[0045] The technical features of this embodiment are basically the same as those described in the second embodiment. The same technical features and technical solutions are not repeated here. Only the differences between the second embodiment and the third embodiment are described here. The soil cavity 23 is a telescopic cavity. Specifically, in this embodiment, the soil cavity 23 is telescopic in order to accommodate the accommodating cavity 21, so that the soil cavity 23 is attached as a whole. Figure 2 Status shown.
[0046] Example 4
[0047] The technical features of this embodiment are basically the same as those described in the first embodiment, and the same technical features and technical solutions are not repeated here. Only the differences between the fourth embodiment and the first embodiment are described here. Figure 5 Due to the differences in the shape of the rock slope and the environment in which it is located, the flexible planting assembly 2 can be arranged vertically, and the vegetation coverage rate and the vegetation survival rate can also be achieved.
[0048] In order to verify the vegetation survival rate of the above method, the inventors conducted experimental planting of rock slope protection in a specific area, and obtained the following Table 1:
[0049]
[0050] Table 1 Comparison of implant survival
[0051] It can be seen from Table 1 above that the quick-change module of this embodiment can significantly improve the survival rate of green plants.
[0052] In order to better illustrate the technical solution of the present application and to facilitate understanding, the present application also provides an installation method for a quick-change module for rock slope greening, the installation method comprising: step 1. pre-opening an installation hole on the rock slope 1; step 2. pressing the fixing component 3 into the installation hole; step 3. pressing the accommodating cavity 21 and the substrate filling cavity 22 into the soil cavity 23; step 4. adjusting the angle between the fixing pile 25 and the bottom end surface of the soil cavity 23 so that the soil cavity 23 is in full contact with the slope surface of the rock slope protection.
[0053] The above shows and describes the basic principles and main features of the present application and the advantages of the present application. For those skilled in the art, it is obvious that the present application is not limited to the details of the above exemplary embodiments, and the present application can be implemented in other specific forms without departing from the spirit or basic features of the present application. Therefore, no matter from which point of view, the embodiments should be regarded as exemplary and non-restrictive. The scope of the present application is defined by the attached claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present application. Any figure mark in the claims should not be regarded as limiting the claims involved.
[0054] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A quick-change module for rock slope greening, characterized in that: The invention comprises a flexible planting component (2), wherein the flexible planting component (2) comprises a containing cavity (21), a substrate filling cavity (22) and a soil cavity (23), wherein the upper and lower ends of the substrate filling cavity (22) are flexibly abutted against the containing cavity (21), the soil cavity (23) is flexibly abutted against the substrate filling cavity (22), and the containing cavity (21) comprises at least one group of first storage cavities (211) for storing seeds and at least one group of second storage cavities (212) for storing culture fluid.
2. The quick-change module according to claim 1, characterized in that: The soil cavity (23) is rotatably connected to an end thereof that is away from the end that flexibly abuts against the substrate filling cavity (22) with a fixing component (3).
3. The quick-change module according to claim 2, characterized in that: The fixing assembly (3) comprises a rotating joint (24) and a fixing pile (25) rotatably connected to the rotating joint (24).
4. The quick-change module according to claim 3, characterized in that: The fixing pile (25) and the bottom end surface of the soil cavity (23) form an angle α, and the value of α is: 0°≤α<90°.
5. The quick-change module according to claim 1 or 2, characterized in that: The soil cavity (23) is a telescopic cavity.
6. The quick-change module according to claim 1, characterized in that: The substrate filling cavity (22) is filled with a soil improver, a water retaining agent, an anti-corrosion agent and water.
7. The quick-change module according to claim 1, characterized in that: A leakage hole is provided on the outer circumference of the first storage cavity (211), and the diameter of the leakage hole is smaller than the diameter of the seeds placed in the leakage hole.
8. The quick-change module according to claim 1, characterized in that: The second storage chamber (212) is filled with a mixed slurry, which is composed of Bisphaerocephala, Tetrasphaera obliquus, Spirulina platensis and deionized water.
9. The quick-change module according to claim 1, characterized in that: The walls of the first storage cavity (211) and the second storage cavity (212) are both made of plastic films.
10. A method for installing a quick-change module for rock slope greening, characterized in that: Includes the following methods: Step 1. Pre-opening installation holes on the rock slope (1); Step 2. Press the fixing assembly (3) into the mounting hole; Step 3. Press the accommodating cavity (21) and the substrate filling cavity (22) into the soil cavity (23); Step 4: Adjust the angle between the fixing pile (25) and the bottom end surface of the soil cavity (23) so that the soil cavity (23) abuts against the rock slope protection surface.
Citation Information
Patent Citations
Revetment ecological restoration pad and revetment protection method
CN109162249A
Environment-friendly ecological slope protection structure and construction method thereof
CN114737521A
Seed-nutriment-soil sack greening device for high and steep rock slope
CN203905028U
Plant bag
CN205623407U
Ecological protection slope
CN209760260U