Integrated upward moving formwork

By introducing basket hanging tire rack and crane sling in the upstream mobile mold frame, the overall binding and molding of the steel cage is realized, which solves the problems of low construction efficiency and difficulty in quality control in the existing technology, and achieves efficient Beam making construction.

CN119021099APending Publication Date: 2024-11-26CHINA RAILWAY 11TH BUREAU GRP CORP LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411081899.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The existing upstream mobile formwork frames are inefficient in high-speed rail construction, insufficient labor utilization, long construction cycle, and difficult to control the quality of steel bars tied in the formwork frame, especially in mountainous construction conditions.

Method used

The integrated upstream mobile mold frame is designed, and the basket hanging tire rack is used for the overall binding of the steel cage, and a crane and a sling are equipped for the integral molding of the steel cage. The steel bars are tied to the concrete pouring, health and tensioning processes are used for the overall molding of the steel cage. In progress, the hanging basket tire can move as the mold frame as a whole.

Benefits of technology

The construction efficiency has been improved, the beam making period has been shortened, and the construction equipment that integrates the overall binding of steel bars and cast-in-place has been realized for the first time. The construction time of single holes has been shortened by about 5 days, and the construction efficiency has been increased by more than 25%.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021099A_ABST
    Figure CN119021099A_ABST
Patent Text Reader

Abstract

The invention provides an integrated ascending type movable formwork which comprises a main beam assembly, a supporting leg assembly, an outer formwork hanging assembly and an electrical assembly, an outer formwork is installed on the outer formwork hanging assembly, the outer formwork hanging assembly is hung below a main outrigger, a hanging basket jig frame assembly used for binding a whole reinforcement cage is installed on a rear guide beam in a hanging mode, and the hanging basket jig frame assembly is connected with the electrical assembly. Hoisting rails are arranged on the two inner sides of the rear guide beam and the main beam correspondingly, two crane carriages are installed on the hoisting rails, and the two crane carriages hoist the whole reinforcement cage into a mold through a sling. Steel bar binding and concrete bridge pouring, curing and tensioning procedures are carried out at the same time, the construction efficiency is high, and the construction period is short.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of upward movable mold frames, and in particular to an integrated upward movable mold frame. Background Art

[0002] Bridges are an important part of high-speed rail lines, accounting for more than 50%. How to quickly make and erect beams is the key to ensuring the construction period. The mobile formwork bridge-building machine is a construction machine that comes with its own formwork and uses abutments or piers as supports to cast bridges on site. Among them, the upward mobile formwork is not restricted by the clearance under the bridge during construction and has been widely used in bridge construction.

[0003] At present, the steel cages of the upward mobile formwork are pre-tied in the beam yard and then transported to the bridge construction site. As the high-speed rail construction advances towards the mountainous areas, the construction of the beam yard is becoming more and more difficult; and for construction projects with less than 150 beam holes, the economic efficiency of beam yard construction is not good. In addition, the existing mobile formwork bridge-building machine must carry out several construction processes in sequence for the in-situ cast-in-place construction of a single-hole bridge. Different types of work have a long waiting time, the labor force is not fully utilized, the construction period is long, the work efficiency is low, and the construction cost is high. Moreover, the steel bars are tied on-site in the formwork cavity, and quality control is difficult. Therefore, it is of great significance to invent an upward mobile formwork that can better improve construction efficiency. Summary of the invention

[0004] The present invention provides an integrated upward movable formwork, in which a hanging basket frame is arranged under the rear guide beam of the movable formwork for overall binding of a steel cage, and a lifting trolley and a hoist are equipped for overall placement of the steel cage into the mold, so that the binding of steel bars and the pouring, curing and tensioning processes of the concrete bridge can be carried out simultaneously, with high construction efficiency and short construction period, and the hanging basket frame can be moved through the hole along with the movable formwork as a whole.

[0005] The technical solution adopted to achieve the above-mentioned purpose of the present invention is:

[0006] An integrated upward mobile formwork frame at least includes a main beam assembly, a leg assembly, an outer formwork hanging assembly and an electrical assembly, wherein the leg assembly is installed at the bottom of the main beam assembly and supported on the bridge and the pier, wherein the main beam assembly includes a main beam and a rear guide beam, wherein two outer sides of the main beam are symmetrically connected to multiple groups of main cantilever beams, an outer formwork is installed on the outer formwork hanging assembly, and the outer formwork hanging assembly is hung below the main cantilever beam, thereby hanging the outer formwork below the main beam, and a hanging basket tire frame assembly for tying the steel cage as a whole is hung on the rear guide beam, wherein the hanging basket tire frame assembly includes a hanging basket tire frame, multiple groups of tire frame hangings and a fixed support component, and the hanging basket tire frame The structure is adapted to the structure of a section of a bridge box girder, the basket frame comprises an inner mold frame, a bottom mold plate and side mold frames symmetrically connected to both sides of the bottom mold plate, the inner mold frame is fixedly connected to the bottom mold plate; the basket frame is hung under the rear guide beam through a frame suspension, the height of the frame suspension is adjustable, and the height of the basket frame is adjusted; the basket frame is supported on the bridge beam surface by a fixed support assembly; lifting rails are provided on both inner sides of the rear guide beam and the main beam, two lifting trolleys are installed on the lifting rails, the two lifting trolleys travel along the lifting rails, and the steel cage is lifted as a whole from the bottom of the rear guide beam to the outer mold suspension assembly through a sling.

[0007] The fixed support assembly includes a plurality of spiral column feet distributed on both sides of the bottom of the basket tire frame, the tops of the spiral column feet are fixed to the basket tire frame by bolts, and the bottoms of the spiral column feet are configured as a triangular support base structure.

[0008] The two outer sides of the rear guide beam are symmetrically connected to multiple groups of auxiliary cantilever beams, the number of tire frame hanging groups is the same as the number of auxiliary cantilever beams, each group of tire frame hanging includes two tire frame hangings connected to a group of auxiliary cantilever beams, the tire frame hanging includes a tire frame hanging rod and an oblique support rod, the upper ends of each group of two tire frame hanging rods are hinged to the auxiliary cantilever beams, the lower ends of each group of two tire frame hanging rods are respectively fixedly connected to the two side mold tire frames of the hanging basket tire frame, the two ends of the oblique support rod are respectively hinged to the auxiliary cantilever beam and the tire frame hanging rod, the tire frame hanging rod and the oblique support rod are made of telescopic cylinders, the tire frame hanging rod and the oblique support rod are telescopic, and the height of the hanging basket tire frame is adjusted.

[0009] The hoist includes a hoisting frame and a suspension distributed and connected under the hoisting frame, the suspension is integrally connected to the steel cage, and two lifting trolleys are respectively connected to the two ends of the top of the hoisting frame; the hoisting frame includes connecting longitudinal beams, connecting cross beams, cross-linking beams, cantilever cross beams and longitudinal connecting beams, and two groups of connecting longitudinal beams and connecting cross beams are provided, and the two groups of connecting cross beams are respectively connected to the front and rear ends of the two groups of connecting longitudinal beams, and the connecting cross beams are connected to the lifting trolley, and the cross-linking beams are distributed and connected to the two groups of connecting longitudinal beams. Two groups of longitudinal connecting beams are provided, and the two groups of longitudinal connecting beams are connected to the outer sides of the two groups of connecting longitudinal beams through cantilever cross beams. There are multiple groups of cantilever cross beams distributed between the longitudinal connecting beams and the connecting longitudinal beams, and the cantilever cross beams are fixedly connected to the longitudinal connecting beams, and the cantilever cross beams are hinged to the connecting longitudinal beams and connected with cotter pins.

[0010] Two electric hoists capable of moving longitudinally and transversely are installed on the rear guide beam, and the electric hoists are located behind the two lifting trolleys to assist in the binding of the steel cage.

[0011] The outrigger assembly includes a front outrigger, an auxiliary outrigger, a middle outrigger and a rear outrigger, and the four outriggers are sequentially mounted at the front end of the main beam, the middle of the main beam, the rear end of the main beam and the rear end of the rear guide beam;

[0012] The front outrigger comprises a front outrigger running mechanism, a front outrigger upper crossbeam, a front outrigger column, a front outrigger lifting cylinder, a front outrigger lower crossbeam, a front outrigger lateral movement cylinder, a front outrigger lateral movement beam and a front outrigger fixed crossbeam connected in sequence; the front outrigger running mechanism is connected to a front outrigger running track and a front outrigger hanging wheel track arranged on the main beam assembly, and the front outrigger running mechanism is driven by a reducer; the front outrigger column comprises an upper column and a lower column of the front outrigger, and the upper column and the lower column of the front outrigger are connected by a pin shaft and a cotter pin; the front outrigger lifting cylinder passes through the lower crossbeam of the front outrigger and is connected to the front outrigger The lower cross beam of the outrigger is fixedly connected, and the two ends of the front outrigger lifting cylinder are respectively fixedly connected to the front outrigger column and the front outrigger transverse beam; the front outrigger transverse beam is slidably connected to the front outrigger fixed cross beam, and the two ends of the front outrigger transverse cylinder are respectively connected to the front outrigger transverse beam and the front outrigger fixed cross beam, and the front outrigger transverse cylinder is extended and retracted to drive the front outrigger transverse beam to move laterally along the front outrigger fixed cross beam, and the front outrigger fixed cross beam is detachably anchored to the bridge pier through the front outrigger anchor rod; the upper cross beam of the front outrigger is longitudinally extended and connected to a support beam, and a front outrigger diagonal support cylinder is connected between the support beam and the front outrigger column;

[0013] The auxiliary leg comprises an auxiliary leg hinge seat, an auxiliary leg column, an auxiliary leg lifting cylinder, an auxiliary leg pad and an auxiliary leg rotating cylinder, wherein the auxiliary leg column is connected to the bottom of the main beam through the auxiliary leg hinge seat, the auxiliary leg lifting cylinder is connected to the bottom of the auxiliary leg column, and the auxiliary leg pad is connected to the bottom of the auxiliary leg lifting cylinder through a fine-tuning screw; the two ends of the auxiliary leg rotating cylinder are respectively connected to the main beam and the auxiliary leg column through an upper hinge seat and a lower hinge seat, and the auxiliary leg rotating cylinder is extended and retracted to drive the auxiliary leg to rotate around the main beam;

[0014] The middle outrigger is an O-shaped structure as a whole. The middle outrigger includes C-shaped outrigger columns symmetrically connected to both sides of the main beam, a middle outrigger lifting cylinder, a middle outrigger lower crossbeam, a middle outrigger running mechanism, a middle outrigger running track, a middle outrigger lateral movement cylinder, a middle outrigger pad and a supporting column. The top of the C-shaped outrigger column is fixedly connected to the main beam, the middle outrigger lower crossbeam is connected to the bottom of the two C-shaped outrigger columns, the middle outrigger running track is installed on the bridge beam surface, the middle outrigger running mechanism is installed at the bottom of the middle outrigger lower crossbeam and installed on the middle outrigger running track, and the middle outrigger running mechanism is reduced by The middle outrigger is driven by a speed machine; two middle outrigger lifting cylinders are connected to the bottom of the lower crossbeam to control the lifting and lowering of the middle outrigger, thereby controlling the installation or detachment of the middle outrigger running mechanism from the middle outrigger running track; the middle outrigger pad is installed on the bridge beam surface, and the middle outrigger transverse movement cylinder is connected between the middle outrigger lower crossbeam and the middle outrigger pad. When the middle outrigger running mechanism is installed and detached from the middle outrigger running track, the middle outrigger transverse movement cylinder is extended and retracted to drive the middle outrigger to move laterally; the top of the support column is rotatably hinged to the bottom of the main beam, and the bottom of the support column is detachably connected to the middle outrigger lower crossbeam;

[0015] The rear outrigger comprises a rear outrigger column, a rear outrigger lifting cylinder, a rear outrigger lower cross beam, a rear outrigger running mechanism and a rear outrigger running track which are connected in sequence. The rear outrigger column is fixedly connected to both sides of the rear guide beam, the rear outrigger running track is erected on the bridge beam surface, and the rear outrigger running mechanism is installed on the rear outrigger running track. When the middle outrigger is running, it drives the rear outrigger running mechanism to run along the rear outrigger running track.

[0016] Auxiliary tensioning tooling is installed on the front supporting legs and the middle supporting legs.

[0017] The outer formwork hanging assembly includes multiple groups of C-type hangings distributed on the main beam, wherein the number of groups of C-type hangings corresponds to the number of groups of main cantilever beams, and each group of C-type hangings includes two C-type hangings, which are respectively installed on the main cantilever beams through hydraulic transverse movement mechanisms and open and close relatively; the outer formwork is spliced ​​by the left outer formwork and the right outer formwork, which are respectively connected to all the left C-type hangings and the right C-type hangings through the formwork support cylinders, and the C-type hanging opens and closes, driving the left outer formwork and the right outer formwork to open and close. In the mold-closed casting state, the C-type hangings are closed, and the bottoms of each group of two C-type hangings are connected into a whole through connecting bolts, and the left outer formwork and the right outer formwork are connected into a whole; after the steel cage is put into the mold as a whole, a C-type hanging hanger is detachably connected between the main cantilever beam and the bottom of the C-type hanging, and the C-type hanging hanger is a through-cylinder type tensile hanger.

[0018] Attached vibrators are installed on both sides of the outer formwork; electric push-pull canopies are installed above the main beam and the rear guide beam; two hydraulic concrete placing machines are fixedly connected to the main beam; the upward movable formwork also includes a spray curing assembly, which includes a spray curing system for the formed box beam and a spray curing system for the cast-in-place beam surface. The spray curing system for the formed box beam includes a spray head A distributed in the box beam hole, a spray head B distributed on the beam surface, and a spray head C located on the outside and below the box beam, wherein the spray head C sprays The frame hanger and the spray frame are connected to the bottom of the tire frame suspension. The bottom of each set of tire frame suspension is connected to the spray frame hanger. The bottom of the spray frame hanger is connected to the spray frame, and the spray frame is located on the outside and bottom of the bridge box girder. Spray heads C are distributed on the spray frame, so as to carry out spray maintenance on the formed bridge box girder; the cast-in-place beam surface spray maintenance system includes spray heads D distributed on both sides of the top of the outer formwork, and spray heads A, spray heads B, spray heads C and spray heads D are all connected to water pipes, and the water pipes are connected to water pumps and water tanks, so as to carry out spray maintenance on the cast-in-place beam surface.

[0019] The front end of the main beam is connected to a front guide beam, and the main beam assembly adopts a double longitudinal beam structure; the main cantilever beam is a truss structure with a right-angled trapezoidal cross-section, and the main cantilever beam is fixed against the outer side surface of the main beam.

[0020] Compared with the prior art, the technical solution provided by the present invention has the following advantages:

[0021] (1) The integrated upward mobile formwork provided by the present invention is provided with a hanging basket frame under the rear guide beam of the mobile formwork for overall binding of the steel cage, and is equipped with a lifting trolley and a hoist for overall placement of the steel cage into the mold, so that binding of steel bars, assembly of inner formwork, etc., and the pouring, curing, and tensioning processes of the concrete bridge can be carried out simultaneously. Under the premise of ensuring the curing period of concrete, the construction period of a single hole of the formwork is 11-12 days, and the construction time of each hole is shortened by about 5 days, thereby increasing the construction efficiency of the mobile formwork by more than 25%, shortening the beam making period, and achieving high construction efficiency. Moreover, the hanging basket frame can be moved through the hole with the mobile formwork as a whole, realizing for the first time a beam making construction equipment that integrates overall binding of steel bars with cast-in-place.

[0022] (2) In the present invention, the front outrigger running mechanism adopts the form of an upper roller, and the front outrigger running mechanism and the middle outrigger running mechanism both adopt a reducer-driven roller structure. The rear outrigger is provided with a rear outrigger running track, and the middle outrigger running drives the rear outrigger running, which meets the construction period requirements of rapid beam making, and each outrigger can be installed in place through the hole by itself, reducing the investment in auxiliary equipment and reducing labor intensity; the front outrigger column can be extended and retracted by the front outrigger lifting cylinder, which can lower (raise) the height of the whole machine, facilitating the last span beam making of the equipment; the auxiliary outrigger adopts hydraulic rotation to facilitate the passage of the integral steel cage into the mold; the front outrigger and the middle outrigger can be moved laterally by the cylinder, which is convenient for the mold frame to pass through small curves on the plane; the C-type suspension is opened and closed by the hydraulic lateral movement cylinder, which is simple to operate; the lifting and lowering, lateral movement of the whole machine and the opening and closing of the C-type suspension are all hydraulically controlled, with smooth, safe and reliable movements.

[0023] (3) In the present invention, tensioning auxiliary tooling is provided on the front legs and the middle legs, and auxiliary lifting tooling for the reverse transportation of the inner mold is also provided on the front legs. In addition, the C-type hanging hanger is a through-cylinder stretching hanger, which can quickly adjust the posture of the entire mold bed, greatly reducing the labor intensity of the mobile mold frame; by integrating the spray maintenance assembly, concrete hydraulic placing machine, attached vibrator and electric push-pull canopy, the quality of the mobile mold frame beam manufacturing reaches the effect of a prefabricated beam factory. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a side view of the integrated upward movable mold frame of the present invention;

[0025] Figure 2 It is a top view of the integrated upward movable mold frame of the present invention;

[0026] Figure 3 is a side view of the front leg of the present invention;

[0027] Figure 4 It is a front view of the front leg in the present invention;

[0028] Figure 5 The front view of the front leg in the present invention when it is in the final stride position

[0029] Figure 6 A side view of the auxiliary legs of the present invention being lowered and retracted;

[0030] Figure 7 This is a front view of the auxiliary legs of the present invention when they are lowered;

[0031] Figure 8 It is a side view of the middle leg of the present invention;

[0032] Fig. 9 It is a front view of the middle leg in the present invention;

[0033] Fig.10is a side view of the rear support leg of the present invention;

[0034] Fig.11 It is a front view of the rear supporting leg in the present invention;

[0035] Fig.12 It is a side view of the outer mold hanging assembly of the present invention;

[0036] Fig.13 It is a front view of the outer mold hanging assembly in the mold opening and through-hole state of the present invention;

[0037] Fig.14 It is a front view of the outer mold hanging assembly in the mold closing casting state in the present invention;

[0038] Fig.15 It is a side view of the tire frame assembly of the hanging basket in the present invention;

[0039] Fig.16 It is a front view of the tire frame assembly of the hanging basket in the present invention;

[0040] Fig.17 It is a side view of the entire steel cage being hoisted by the lifting trolley and the lifting device in the present invention;

[0041] Fig.18 It is a front view of the entire steel cage hoisted by the lifting trolley and the lifting device in the present invention;

[0042] Fig.19 It is a top view of the entire steel cage being lifted by the lifting trolley and the lifting device in the present invention;

[0043] Fig. 20 It is a front view of the lifting trolley and the lifting device in the present invention lifting the steel cage as a whole in the through-hole working condition;

[0044] Fig.21 This is a side view of the installation of the electric hoist in the present invention;

[0045] Fig. 22 This is the installation front view of the electric hoist in the present invention;

[0046] Fig.23 It is a schematic diagram of the structure of the electric sliding awning in the present invention when it is in a retracted state;

[0047] Fig.24 It is a schematic diagram of the structure of the electric push-pull awning in the present invention when it is in the unfolded state;

[0048] Fig.25 It is a schematic diagram of the arrangement of the electric sliding awning in the present invention;

[0049] Fig.26Schematic diagram of the arrangement of the spray head A and the spray head B in the spray curing assembly of the present invention, wherein (a) is a side view, (b) is a front view, and (c) is a top view;

[0050] Fig. 27 It is a schematic diagram of the arrangement of the spray head C in the spray curing assembly of the present invention, (b) is a main view;

[0051] Fig.28 Schematic diagram of the arrangement of the spray head D in the spray curing assembly of the present invention, (a) is a side view, (b) is a front view, and (c) is a top view;

[0052] Fig.29 The construction diagram of the integrated upward movable formwork in the present invention is shown in FIG. Figure 1 ;

[0053] Fig.30 The construction diagram of the integrated upward movable formwork in the present invention is shown in FIG. Figure 2 ;

[0054] Fig.31 The construction diagram of the integrated upward movable formwork in the present invention is shown in FIG. Figure 3 ;

[0055] Fig.32 The construction diagram of the integrated upward movable formwork in the present invention is shown in FIG. Figure 4 ;

[0056] Fig.33 It is a schematic diagram of the reverse transportation construction of the inner formwork in the present invention;

[0057] Fig.34 The construction diagram of the integrated upward movable formwork in the present invention is shown in FIG. Figure 5 ;

[0058] Fig.35 The construction diagram of the integrated upward movable formwork in the present invention is shown in FIG. Figure 6 ;

[0059] Fig.36 The construction diagram of the integrated upward movable formwork in the present invention is shown in FIG. Figure 7 ;

[0060] Fig.37 The construction diagram of the integrated upward movable formwork in the present invention is shown in FIG. Figure 8 ;

[0061] Fig.38 The construction diagram of the integrated upward movable formwork in the present invention is shown in FIG. Figure 9 ;

[0062] Fig.39 The construction diagram of the integrated upward movable formwork in the present invention is shown in FIG. Figure 10 ;

[0063] Fig.40 The construction diagram of the integrated upward movable formwork in the present invention is shown in FIG. Figure 10 one;

[0064] Fig.41 The construction diagram of the integrated upward movable formwork in the present invention is shown in FIG. Figure 10 two;

[0065] Fig.42 The construction diagram of the integrated upward movable formwork in the present invention is shown in FIG. Figure 10 three;

[0066] Fig.43 It is a schematic diagram of the construction of the integrated upward movable formwork turning around and bidirectional cast-in-place beams in the present invention;

[0067] In the figure: 100-bridge, 1001-just cast box girder, 200-bridge pier, 2001-0# pier, 2002-1# pier, 300-external formwork, 3001-left external formwork, 3002-right external formwork, 400-inner formwork, 500-reinforcement cage, 5001-reinforcement cage bottom plate and side plate, 5002-reinforcement cage top plate, 600-end formwork;

[0068] 1-main beam assembly, 11-front guide beam, 12-main beam, 13-rear guide beam, 14-main cantilever beam, 15-auxiliary cantilever beam, 16-front outrigger running track, 17-front outrigger hanging wheel track, 18-hoisting track;

[0069] 21-front outrigger, 211-front outrigger running mechanism, 212-front outrigger upper crossbeam, 213-front outrigger column, 2131-front outrigger upper column, 2132-front outrigger lower column, 2133-split pin, 214-front outrigger lifting cylinder, 215-front outrigger lower crossbeam, 216-front outrigger transverse cylinder, 217-front outrigger transverse beam, 218-front outrigger fixed crossbeam, 219-front outrigger diagonal support cylinder;

[0070] 22- auxiliary outrigger, 221- auxiliary outrigger hinge seat, 222- auxiliary outrigger column, 223- auxiliary outrigger lifting cylinder, 224- auxiliary outrigger pad, 225- auxiliary outrigger rotating cylinder, 226- upper hinge seat, 227- lower hinge seat, 228- fine-tuning screw;

[0071] 23-middle outrigger, 231-C-type outrigger column, 232-middle outrigger lifting cylinder, 233-middle outrigger lower crossbeam, 234-middle outrigger running mechanism, 235-middle outrigger running track, 236-middle outrigger transverse cylinder, 237-middle outrigger pad, 238-support column;

[0072] 24-rear outrigger, 241-rear outrigger column, 242-rear outrigger lifting cylinder, 243-rear outrigger lower crossbeam, 244-rear outrigger running mechanism, 245-rear outrigger running track;

[0073] 3-external mold hanging assembly, 31-C type hanging, 32-C type hanging suspension rod, 33-formwork supporting cylinder;

[0074] 4-basket tire frame assembly, 41-basket tire frame, 411-bottom mold, 412-side mold tire frame, 413-inner mold tire frame, 42-tire frame hanging, 421-tire frame hanging rod, 422-diagonal support rod, 43-spiral column foot, 44-ladder platform;

[0075] 51-lifting trolley, 52-sling, 521-hanging, 522-connecting longitudinal beam, 523-connecting cross beam, 524-cross beam, 525-cantilever cross beam, 526-longitudinal beam, 53-locking suspension rod, 54-auxiliary lifting tooling;

[0076] 6-electric hoist, 61-track beam, 62-beam running wheel set;

[0077] 71-Attached vibrator, 72-Electric push-pull canopy, 721-End beam motor, 722-Wind-resistant column, 73-Hydraulic concrete placing boom;

[0078] 8-spray maintenance assembly, 81-spray head A, 82-spray head B, 83-spray head C, 84-spray rack hanger, 85-spray rack, 86-spray head D, 87-water pipe, 88-water pump, 89-water tank;

[0079] 9-Tensioning auxiliary tooling. DETAILED DESCRIPTION

[0080] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.

[0081] The structure of the integrated upward movable mold frame provided by the present invention is as follows: Figure 1 As shown, it includes a main beam assembly 1, a leg assembly, an outer mold hanging assembly 3, a basket frame assembly 4, a lifting trolley 51, an electric hoist 6, as well as an electrical assembly, a hydraulic assembly and other auxiliary facilities.

[0082] In this embodiment, the main beam assembly adopts a three-span structure, including a front guide beam 11, a main beam 12 and a rear guide beam 13 connected in sequence. Figure 1 and Figure 2As shown, it not only satisfies the reserved area for installing the basket frame assembly for tying the steel cage, but also satisfies the advantages of quick hole-passing and good anti-tilting safety. The main beam assembly adopts a double longitudinal beam structure, which has good lateral stability and strong wind resistance. The two outer sides of the main beam are symmetrically connected to multiple groups of main cantilever beams 14. In this embodiment, there are five groups of main cantilever beams. The main cantilever beams are a truss structure with a right-angle trapezoidal cross-section. The main cantilever beams are fixed against the outer side of the main beam. Fig.13 The main cantilever beam is used for hanging the outer mold hanging assembly. The two outer sides of the rear guide beam are symmetrically connected to multiple groups of auxiliary cantilever beams 15. In this embodiment, six groups of auxiliary cantilever beams are provided. The auxiliary cantilever beam is a truss structure with a right-angled triangle cross section. A right-angled surface of the auxiliary cantilever beam is fixed against the outer side surface of the rear guide beam. Fig.16 , the auxiliary cantilever beam is used for hanging the basket tire frame assembly. In this embodiment, front outrigger running tracks 16 are provided on both sides of the bottom of the two longitudinal beams of the front guide beam and the main beam, front outrigger hanging wheel tracks 17 are provided on the bottom of the two outer sides of the two longitudinal beams of the front guide beam and the main beam (i.e. the outer sides of the two longitudinal beams), and hoisting tracks 18 for the running of the hoisting trolley are provided on the two inner sides of the main beam and the rear guide beam (i.e. the inner sides of the two longitudinal beams). The rear guide beam is a truss structure with a light weight, which reduces the support force on the bridge deck.

[0083] Furthermore, in this embodiment, the main beam and the outer formwork hanging assembly are designed to be symmetrical in the transverse direction, and only the front guide beam, the rear guide beam and the parts of the legs need to be replaced to quickly realize the U-turn and bidirectional construction. Fig.43 As shown, the difficulty of equipment transition is reduced and the cost of equipment transition is reduced.

[0084] The leg assembly is installed at the bottom of the main beam assembly and supported on the bridge 100 and the pier 200, so that the entire main beam assembly is placed above the bridge deck. The leg assembly includes a front leg 21, an auxiliary leg 22, a middle leg 23 and a rear leg 24. The four legs are installed at the front end of the main beam, the middle of the main beam, the rear end of the main beam and the rear end of the rear guide beam in sequence.

[0085] Front outrigger structure Figure 3 and Figure 4The front outrigger includes a front outrigger running mechanism 211, a front outrigger upper crossbeam 212, a front outrigger column 213, a front outrigger lifting cylinder 214, a front outrigger lower crossbeam 215, a front outrigger transverse cylinder 216, a front outrigger transverse beam 217 and a front outrigger fixed crossbeam 218. The front outrigger running mechanism includes a front supporting wheel group, a rear supporting wheel group, a hanging wheel group and a horizontal wheel group. The front outrigger running mechanism is driven by a reducer. The front outrigger running mechanism is connected to the front outrigger running track and the front outrigger hanging wheel track provided on the main beam assembly. The front outrigger running mechanism is driven by a reducer, so that the mobile formwork moves forward as a whole. During the through-hole operation, the initially tensioned beam body is not subjected to the heavy load of the bridge-building machine, so that the construction period requirements of rapid beam manufacturing are met. The upper roller assembly is fixed to the top of the upper crossbeam of the front leg, and the front leg column is fixed to the bottom of the upper crossbeam of the front leg. The front leg column includes an upper column 2131 of the front leg and a lower column 2132 of the front leg. The upper column of the front leg and the lower column of the front leg are connected by a pin shaft and a cotter pin 2133. When the front leg is in the last span, the lower column of the front leg can be disassembled to reduce the height of the front leg, which is suitable for the last span erection working condition, such as Figure 5 As shown. The front outrigger lifting cylinder passes through the front outrigger lower cross beam and is fixedly connected to the front outrigger lower cross beam. The two ends of the front outrigger lifting cylinder are respectively fixedly connected to the front outrigger column and the front outrigger transverse beam. The front outrigger lifting cylinder telescopes to adjust the height of the front outrigger. The front outrigger transverse beam is slidably connected to the front outrigger fixed cross beam. The two ends of the front outrigger transverse cylinder are respectively connected to the front outrigger transverse beam and the front outrigger fixed cross beam. The front outrigger transverse cylinder telescopes to drive the front outrigger transverse beam to move laterally along the front outrigger fixed cross beam. The front outrigger fixed cross beam is detachably anchored to the bridge pier through the front outrigger anchor rod. The front outrigger is an inverted triangle anti-overturning device. The upper edge of the front outrigger upper cross beam is longitudinally extended and connected to a support beam. The front outrigger diagonal support cylinder 219 is connected between the support beam and the front outrigger column.

[0086] The structure of the auxiliary legs is as follows Figure 6 and Figure 7 As shown, it includes an auxiliary leg hinge seat 221, an auxiliary leg column 222, an auxiliary leg lifting cylinder 223, an auxiliary leg pad 224 and an auxiliary leg rotating cylinder 225, wherein the auxiliary leg column is connected to the bottom of the main beam through the auxiliary leg hinge seat, the auxiliary leg lifting cylinder is connected to the bottom of the auxiliary leg column, and the auxiliary leg pad is connected to the bottom of the auxiliary leg lifting cylinder through a fine-tuning screw 228. The two ends of the auxiliary leg rotating cylinder are respectively connected to the main beam and the auxiliary leg column through an upper hinge seat 226 and a lower hinge seat 227, and the auxiliary leg rotating cylinder is extended and retracted to drive the auxiliary leg to rotate around the main beam. During the through-hole process, the auxiliary leg lifting cylinder and the auxiliary leg rotating cylinder are controlled to extend so that the auxiliary leg is supported on the bridge beam surface; during the casting process, the integral steel cage needs to pass through the mold, at this time, the auxiliary leg lifting cylinder is controlled to shrink, and then the auxiliary leg rotating cylinder is controlled to shrink, so that the auxiliary leg is turned over and retracted to the bottom of the main beam.

[0087] The structure of the middle leg is as follows Figure 8 and Fig. 9 As shown, the middle leg is an O-shaped structure as a whole, which is convenient for the whole steel cage to pass through the mold. The middle leg includes a C-shaped leg column 231 symmetrically connected to both sides of the main beam, a middle leg lifting cylinder 232, a middle leg lower beam 233, a middle leg running mechanism 234, a middle leg running track 235, a middle leg transverse cylinder 236, a middle leg pad 237 and a supporting column 238. The C-shaped leg column is composed of multiple sections of columns connected by a pin shaft and a cotter pin, and the height is adjustable. The top of the C-shaped leg column is fixedly connected to the main beam, the middle leg lower beam is connected to the bottom of the two C-shaped leg columns, the middle leg running track is installed on the bridge beam surface, the middle leg running mechanism is installed at the bottom of the middle leg lower beam, and is installed on the middle leg running track, the middle leg running mechanism is a supporting wheel group, and the middle leg running mechanism is driven by a reducer to move the middle leg running mechanism along the middle leg running track. There are two middle outrigger lifting cylinders connected to the bottom of the lower crossbeam to control the lifting and lowering of the middle outrigger, thereby controlling the installation or detachment of the middle outrigger running mechanism from the middle outrigger running track; the middle outrigger pad is installed on the bridge beam surface, and the middle outrigger transverse cylinder is connected between the middle outrigger lower crossbeam and the middle outrigger pad. When the middle outrigger running mechanism is installed and detached from the middle outrigger running track, the middle outrigger transverse cylinder is extended and retracted to drive the middle outrigger to move laterally. The top of the support column can be rotatably hinged to the bottom of the main beam, and the bottom of the support column is detachably connected to the lower crossbeam of the middle outrigger ( Fig. 9 The connection between the middle support column and the C-shaped support column has been removed, and the support column has been flipped to the bottom of the main beam). When the integral steel cage needs to pass through the mold, the support column flips to the bottom of the main beam to make room for the steel cage. When pouring concrete, the support column flips and supports between the main beam and the lower crossbeam of the middle support leg, and the middle support leg lifting cylinder is extended and retracted to support the middle support leg on the bridge. The flipping mechanism of the support column can be specifically referred to the auxiliary support leg. The front and middle legs of the mobile formwork can be moved horizontally by the cylinder, which is convenient for the mobile formwork to pass through small curves on the plane.

[0088] The structure of the rear legs is as follows Fig.10 and Fig.11As shown, it includes a rear outrigger column 241, a rear outrigger lifting cylinder 242, a rear outrigger lower cross beam 243, a rear outrigger running mechanism 244 and a rear outrigger running track 245 connected in sequence. The rear outrigger column is fixedly connected to both sides of the rear guide beam, the rear outrigger running track is erected on the bridge beam surface, and the rear outrigger running mechanism is installed on the rear outrigger running track. Unlike the front outrigger and the middle outrigger, the rear outrigger running mechanism has no driving power. When the middle outrigger is running, it drives the rear outrigger running mechanism to run along the rear outrigger running track. Specifically, the rear outrigger running track is made of I-shaped steel. The outrigger assemblies cooperate with each other, so that during the construction of the mobile formwork and the through-hole process, there is no need to add embedded parts to the beam body and the pier body. Each outrigger is safely transported by itself, without auxiliary equipment, and has the ability to safely cross rivers. Each outrigger is hydraulically floated to ensure that when the three outriggers are supported, each outrigger can stably support the beam surface.

[0089] The structure of the outer mold hanging assembly is as follows Figure 12 to Figure 14 As shown, it includes multiple groups of C-type hangers 31 distributed on the main beam, wherein the number of groups of C-type hangers corresponds to the number of groups of main cantilever beams. In this embodiment, the number of groups of C-type hangers is five, and each group of C-type hangers includes two C-type hangers, which are respectively installed on the main cantilever beam through a hydraulic transverse movement mechanism and are relatively opened and closed. The hydraulic transverse movement mechanism is a conventional technical means in the field and will not be described in detail here. In this embodiment, the outer formwork 300 is connected to the C-type suspension through a supporting assembly. The outer formwork is spliced ​​by a left outer formwork 3001 and a right outer formwork 3002. The left outer formwork and the right outer formwork are respectively connected to all left-side C-type suspensions and right-side C-type suspensions through a formwork supporting cylinder 33. The opening and closing of the C-type suspension drives the opening and closing of the left outer formwork and the right outer formwork. The formwork supporting cylinders are distributed on the outer formwork and the side and bottom. The formwork supporting cylinders on the side of the outer formwork are hingedly connected to the outer formwork and the C-type suspension. After the left outer formwork and the right outer formwork are molded, the formwork supporting cylinders are used to adjust the posture of the left outer formwork and the right outer formwork and the beam elevation position to form a precise outer formwork space. In the mold-closing casting state, the C-type suspension is closed, and the bottoms of each group of two C-type suspensions are connected as a whole through connecting bolts, and the left outer formwork and the right outer formwork are connected as a whole. When the steel cage is put into the mold as a whole, the C-type suspension hanger 32 can be detachably connected between the main cantilever beam and the bottom of the C-type suspension to transfer the concrete load to the main beam. Moreover, the C-type suspension hanger is a through-cylinder tension hanger, which can quickly adjust the posture of the installed inner formwork. In the mold opening and through-hole state, the connection between each group of two C-type suspensions is released, the connection between the left outer formwork and the right outer formwork is released, and the C-type suspension hanger is removed to avoid affecting the overall mold entry of the steel cage.

[0090] The structure of the basket tire frame assembly is as follows Fig.15 and Fig.16As shown, the basket tire frame assembly is suspended and installed on the auxiliary cantilever beam, and is used to bind the steel cage as a whole. The steel cage as a whole includes a steel cage 500, an inner template 400, an end template and a prestressed steel pipe. The basket tire frame assembly includes a basket tire frame 41, multiple sets of tire frame suspensions 42 and a fixed support component. The structure of the basket tire frame is adapted to the structure of a section of a bridge box girder. The basket tire frame includes an inner mold tire frame 413, a bottom template 411 and a side mold tire frame 412 symmetrically connected to both sides of the bottom template. The side mold tire frame is made of a truss. The inner mold tire frame is fixedly connected to the bottom template. Specifically, the inner mold tire frame is connected to the bottom template through a support beam. The bottom of the support beam is fixedly connected to the bottom mold tire frame. The top of the support beam is connected to a longitudinal slideway. The bottom of the inner mold tire frame is provided with an inner mold tire frame roller. The inner mold tire frame roller is installed on the longitudinal slideway to facilitate the push-pull positioning and installation of the inner mold tire frame. The basket tire frame is hung under the rear guide beam through the tire frame hanging, and the basket tire frame is supported on the bridge beam surface through the fixed support assembly; the number of tire frame hanging groups is the same as the number of auxiliary cantilever beam groups, and each group of tire frame hanging includes two tire frame hangings connected to a group of auxiliary cantilever beams, and the tire frame hanging includes a tire frame hanging rod 421 and a diagonal support rod 422. The upper ends of each group of two tire frame hanging rods are hinged to the auxiliary cantilever beam, and the lower ends of each group of two tire frame hanging rods are respectively fixedly connected to the two side mold tire frames of the basket tire frame. The two ends of the diagonal support rod are respectively hinged to the auxiliary cantilever beam and the tire frame hanging rod. The tire frame hanging rod and the diagonal support rod are made of telescopic cylinders. The tire frame hanging rod and the diagonal support rod are telescopic to adjust the height of the basket tire frame. The fixed support assembly includes a plurality of spiral column feet 43 distributed on both sides of the bottom of the basket tire frame. The tops of the spiral column feet are locked and fixed to the basket tire frame by bolts, and the bottom of the spiral column feet is set as a triangular support base structure. When tying the steel cage as a whole, the frame hanger rod and the diagonal brace rod are extended and retracted to support the spiral column foot on the bridge beam surface, and then the steel bars are tied; when passing through the hole, the frame hanger rod and the diagonal brace rod are extended and retracted to make the spiral column foot separate from the bridge beam surface, and the entire hanging basket frame assembly moves together with the main beam assembly. The hanging basket frame is connected to a ladder platform 44 for workers who tie the steel bars to enter the hanging basket frame.

[0091] There are two lifting trolleys installed on the hoisting rails of the main beam assembly. Figure 17 to Figure 19As shown, two lifting trolleys travel along the lifting track, and lift the integral steel cage from the bottom of the rear guide beam to the outer mold hanging assembly through the lifting device 52. The lifting device includes a lifting frame and a hanging 521 distributed and connected under the lifting frame, the hanging is integrally connected to the steel cage, and the two lifting trolleys are respectively connected to the two ends of the top of the lifting frame. Specifically, the hoisting frame includes connecting longitudinal beams 522, connecting cross beams 523, cross-linking beams 524, cantilever cross beams 525 and longitudinal connecting beams 526. There are two groups of connecting longitudinal beams and connecting cross beams. The two groups of connecting cross beams are respectively connected to the front and rear ends of the two groups of connecting longitudinal beams. The connecting cross beams are connected to the lifting trolley. The cross-linking beams are distributed and connected to the two groups of connecting longitudinal beams. There are two groups of longitudinal connecting beams. The two groups of longitudinal connecting beams are connected to the outer sides of the two groups of connecting longitudinal beams through cantilever cross beams. There are multiple groups of cantilever cross beams distributed between the longitudinal connecting beams and the connecting longitudinal beams. The cantilever cross beams are fixedly connected to the longitudinal connecting beams. The cantilever cross beams are hinged to the connecting longitudinal beams and connected with cotter pins. In order to avoid the C-type hanging boom, the cantilever cross beams and the longitudinal connecting beams can be flipped to the top of the hoisting frame (flipped 100°) for avoidance. Fig. 20 shown.

[0092] In order to facilitate the overall binding of the steel cage, two electric hoists 6 that can move vertically and horizontally are installed on the rear guide beam. Fig.21 and Fig. 22 As shown. The electric hoist is located at the rear of the lifting trolley. The specification of the electric hoist is 5t. The electric hoist can flexibly pick up materials in the longitudinal and transverse directions and transport them to the inside of the basket frame assembly to assist in the binding of the steel cage. Specifically, the electric hoist is installed on the rear guide beam through the track beam 61 and the beam running wheel group 62. The beam running wheel group is fixed on the track beam. The beam running wheel group is slidably connected to the rear guide beam and moves longitudinally along the rear guide beam. The electric hoist is installed on the track beam and moves laterally along the track beam.

[0093] In this embodiment, attached vibrators 71 are installed on both sides of the outer template. Figure 1 and Fig.13 , the vibration force is transmitted to the concrete through the external formwork, so that the overall molding quality of the concrete is better.

[0094] An electric push-pull canopy 72 is installed above the main beam and the rear guide beam, which can provide shade, rain protection, and fold to prevent floating, so as to prevent the outside weather from affecting the pouring of concrete and the binding of the steel cage, so as to achieve all-weather construction, improve the overall working efficiency of the bridge construction machine, and ensure the requirements of the total construction period. Each electric push-pull canopy is 36m long when unfolded, and 6-7m long when folded. The structural diagram of the electric push-pull canopy when folded and unfolded is shown in the figure below. Fig.23 and Fig.24As shown, the electric push-pull awning is driven to expand and retract by the end beam motor 721, and a wind-resistant column 722 is also provided at the fixed end of the electric push-pull awning. The H-shaped steel on the main beam is installed in reverse to prevent overturning. When there is a strong wind or typhoon warning, the electric push-pull awning should be bolted to the bolt connection point set on the main beam. In this embodiment, an electric push-pull awning is respectively provided at the rear end of the rear guide beam, the rear end of the main beam, and the front end of the main beam. The layout diagram of the electric push-pull awning is shown in FIG. Fig.25 shown.

[0095] Two hydraulic concrete placing machines 73 are fixedly connected to the main beam. After the steel cage is put into the mold as a whole, concrete is poured through the two hydraulic concrete placing machines. The hydraulic concrete placing machines are arranged at the front and rear ends of the main beam to meet the rapid placing construction needs of the entire pouring area.

[0096] In this embodiment, the upward movable formwork also includes a spray curing assembly 8, which includes a spray curing system for the formed box beam and a spray curing system for the cast-in-place beam surface. The spray curing system for the formed box beam includes a spray head A81 distributed in the box beam hole, a spray head B82 distributed on the beam surface, and a spray head C83 located outside and below the box beam. Fig.26 and Fig. 27 As shown. The spray head C is connected to the bottom of the tire frame suspension through the spray frame hanger 84 and the spray frame 85. Specifically, the bottom of each set of tire frame suspension is connected to the spray frame hanger, and the bottom of the spray frame hanger is connected to the spray frame, and the spray frame is located outside and below the bridge box girder. The spray head C is distributed on the spray frame, so as to spray and maintain the formed bridge box girder; the cast-in-place beam surface spray maintenance system includes spray heads D86 distributed on both sides of the top of the outer formwork, as shown Fig.28 As shown, sprinkler head A, sprinkler head B, sprinkler head C and sprinkler head D are all connected to water pipe 87, and the water pipe is connected to water pump 88 and water tank 89, so as to perform spray maintenance on the cast-in-place beam surface.

[0097] In this embodiment, a tensioning auxiliary tool 9 is installed on the front leg and the middle leg. Figure 1 and Figure 3 When the concrete strength of the beam reaches 80% of the design value, loosen the inner formwork, remove the end formwork and then start the initial tensioning. When the concrete strength and elastic modulus of the beam reach the design value, the final tensioning is carried out when the age is not less than 7 days.

[0098] The construction method of the integrated upward movable formwork provided by the present invention comprises the following steps: (1) the integrated upward movable formwork is placed in place through a hole on the bridge, and the initial state of the entire machine is prepared, such as Fig.29 As shown;

[0099] After the through-holes are in place, the front legs are supported on the front end of the main beam and 0# pier 2001, the auxiliary legs are rotated and retracted, the middle legs are supported on the rear end of the main beam and the front end beam surface of the newly cast box beam 1001, the rear legs are supported on the rear end of the rear guide beam and the beam surface of the newly cast box beam, and the C-type hanging suspends the outer formwork at the box beam to be cast;

[0100] In this embodiment, after the whole machine is through-hole in place, the formed box beam spray curing system is used to spray the beam body of the newly cast box beam. Fig.29 , including spray maintenance inside the box girder hole, on the beam surface, and on the outside and bottom of the box girder.

[0101] In this embodiment, the initial state is: the C-shaped hanging and the outer template are in a mold-joined state, the outer template is polished and a mold release agent is applied, and the steel cage is integrally molded;

[0102] When the whole machine is put in place for the first time, the steel cage is tied as a whole at the same time;

[0103] (2) Simultaneously carry out the pouring construction under the main beam and the steel cage binding construction under the rear guide beam, such as Figure 30 to Figure 34 As shown;

[0104] The pouring construction steps are as follows: (2.11) Put on the C-type hanging rod and adjust the elevation of the entire mold bed, see Fig.30 ;

[0105] (2.12) The hydraulic concrete placing machine is working to pour concrete and the vibrating assembly is started to assist in vibrating. Fig.30 Specifically, when pouring concrete, the pouring construction is carried out in longitudinal sections and in oblique (horizontal) layers. After the concrete pouring is completed, the bridge deck is leveled.

[0106] (2.13) After the initial setting of the concrete, the beam surface is sprayed and cured. In this embodiment, the spray curing is performed by the spray heads D distributed on both sides of the top of the outer formwork in the cast-in-place beam surface spray curing system. Fig.30 ;

[0107] At the same time, after the concrete pouring is completed, the lock between the sling and the rear guide beam is released, the two lifting trolleys and the sling are moved to the main beam, and the sling and the main beam are locked by locking the sling rod. Fig.31 ;

[0108] (2.14) When the concrete strength of the beam reaches 80% of the design value, loosen the inner formwork, remove the end formwork and start the initial tensioning;

[0109] (2.15) Remove the inner formwork, release the connection between the lifting trolley and the lifting device, and use the auxiliary lifting tooling 54 set at the lifting trolley and the front outrigger to transport the inner formwork and the end formwork to the reinforcement cage binding area. Fig.32 and Fig.33After the reverse transportation is completed, connect the lifting trolley and the sling, release the lock between the sling and the main beam, see Fig.34 At the same time, when the concrete strength and elastic modulus of the beam body reach the design value, the final tensioning is carried out when the age is not less than 7 days. Fig.35 ;

[0110] (2.16) After the final tensioning is completed, the longitudinal, vertical and transverse constraints of the external formwork shall be released. The release of constraints shall be carried out when the wind force is not greater than level 6;

[0111] The construction steps of steel cage binding are as follows: (2.21) two lifting trolleys and the slings are moved to the rear guide beam, and the slings are locked to the rear guide beam by locking the sling rod 53, see Fig.30 ;

[0112] (2.22) Adjust the basket frame assembly so that the spiral column foot at the bottom of the basket frame assembly is supported on the beam surface of the cast bridge. Fig.30 ;

[0113] (2.23) The material transporter (not shown) transports the materials required for the entire steel cage to the rear of the rear guide beam, and the electric hoist at the rear of the rear guide beam assists in unloading, see Fig.30 ;

[0114] (2.24) Tie the bottom plate and side plates of the steel cage 5001 to the basket frame, see Fig.31 ; In step (2.15), when the inner formwork and the end formwork are transported to the reinforcement cage binding area, the inner formwork is installed, the reinforcement cage top plate 5002 is tied, and the end formwork 600 is installed. Fig.32 and Fig.34 ; Install the prestressed steel pipe when tying the bottom plate, side plate and top plate of the steel cage to complete the tying and installation of the entire steel cage, see Fig.35 , the steel cage is tied and installed as a whole with the assistance of electric hoist;

[0115] After the overall binding of the steel cage is completed, if the pouring construction under the main beam is not completed, the construction of step (3.1) is carried out simultaneously.

[0116] (3) Demolding and preparation of the whole machine for via hole status, such as Fig.36 and Fig.37 As shown;

[0117] (3.1) Move the hoisting trolley and the lifting device to the steel cage binding area, connect the lifting device to the steel cage as a whole, lift the steel cage as a whole by the hoisting trolley, and make the steel cage as a whole 15cm away from the hanging basket frame assembly. Lock the lifting device and the rear guide beam by locking the lifting rod, and adjust the hanging basket frame assembly so that the support rod at the bottom of the hanging basket frame assembly is 45cm away from the bridge beam surface. Fig.36 ;

[0118] (3.2) The lifting cylinders of the front legs, middle legs and rear legs are unloaded at the same time, so that the whole machine is lowered 15cm to be demoulded. Fig.37 ;

[0119] (3.3) Remove the C-type hanging rod, release the center seam connection between the outer formwork and the C-type hanging, and open the mold of the C-type hanging and the outer formwork. Fig.37 ;

[0120] (3.4) Check that the running mechanism and support status of the front outrigger, middle outrigger and rear outrigger are intact and prepare for the hole;

[0121] (4) The whole machine is in place through the holes, such as Figures 38 to 40 As shown;

[0122] (4.1) Start the middle outrigger travel mechanism and move the whole machine forward until the auxiliary outrigger is above the front end beam surface of the newly cast box girder. Fig.38 At this time, the front outrigger is anchored on the 0# pier through the front outrigger anchor rod, and the front outrigger, middle outrigger and rear outrigger support the whole machine. After the middle outrigger running mechanism starts to move forward, the main beam runs along the front outrigger running mechanism;

[0123] (4.2) The auxiliary outrigger is rotated and lowered to support the beam surface. The auxiliary outrigger supports the force. In this embodiment, the lifting cylinders of the auxiliary outrigger, the middle outrigger and the rear outrigger are all lifted up by 40 cm, so that the front outrigger is free. Fig.38 At this time, remove the anchor rod of the front outrigger to separate the front outrigger from the 0# pier, and use the auxiliary outrigger, middle outrigger and rear outrigger to support the whole machine;

[0124] (4.3) The front outrigger moves forward to pier 1# 2002 through the front outrigger walking mechanism and is in position. The front outrigger supports the force and the auxiliary outrigger rotates and retracts. Fig.39 , then anchor the front outrigger to pier 1#;

[0125] (4.4) Start the middle outrigger travel mechanism, and the whole machine moves forward until the front end of the main beam is located at the front outrigger. The lifting cylinders of the front outrigger, middle outrigger and rear outrigger work synchronously to lift the whole machine 15cm into place. The whole machine is in place after passing through the hole. Fig.40 ;

[0126] In this embodiment, when constructing a 32m beam, the whole machine moves forward 21.35m in step (4.1), and the whole machine moves forward 11.35m in step (4.4). The mobile formwork in this embodiment is also suitable for the construction of 24m standard beams and 30m and 27.2m non-standard beams.

[0127] (5) After the whole machine is in place, the newly cast box beam is sprayed and cured, corresponding to step (1); the C-type hanging and the outer formwork are molded together, and the center seam connection on the outer formwork and the C-type hanging is connected, such as Fig.41 As shown;

[0128] Unlock the lifting device and the rear guide beam, lift the steel cage into the mold with the lifting trolley, and adjust the whole machine to the initial state. Fig.42 As shown, the next construction cycle begins.

[0129] When the whole machine passes the continuous beam, it only needs to convert the front support leg to the last span support state, and then open the C-type suspension to a certain width and lock it, and the whole machine and the template can pass the continuous beam smoothly.

[0130] The integrated upward mobile formwork provided by the present invention pre-binds the steel cage as a whole at the hanging basket stand assembly, and then puts the whole into the mold through the steel cage overall hoisting assembly, so that the steel bar binding on the rear guide beam, the inner mold assembly, the prestressed steel pipe installation process and the concrete pouring, spray curing and tensioning process on the main beam are carried out simultaneously. The whole machine is divided into two front and rear working surfaces, the front part is the cast-in-place beam pouring area of ​​the formwork, and the rear part is the steel bar binding area, so as to realize the parallel working surface of steel bar binding and cast-in-place beam construction. Under the premise of ensuring the concrete curing period, the construction period of a single hole of the formwork is 11-12 days, which shortens the beam making period.

Claims

1. An integrated upward movable formwork, comprising at least a main beam assembly, a leg assembly, an outer formwork hanging assembly and an electrical assembly, wherein the leg assembly is installed at the bottom of the main beam assembly and supported on the bridge and the pier, wherein the main beam assembly comprises a main beam and a rear guide beam, wherein two outer sides of the main beam are symmetrically connected with a plurality of main cantilever beams, an outer formwork is installed on the outer formwork hanging assembly, and the outer formwork hanging assembly is hung below the main cantilever beam, thereby hanging the outer formwork below the main beam, wherein: A hanging basket frame assembly for binding the entire steel cage is hung on the rear guide beam, and the hanging basket frame assembly includes a hanging basket frame, multiple sets of frame hangings and fixed support components. The structure of the hanging basket frame is adapted to the structure of a section of a bridge box beam. The hanging basket frame includes an inner mold frame, a bottom mold plate and side mold frames symmetrically connected to both sides of the bottom mold plate, and the inner mold frame is fixedly connected to the bottom mold plate; the hanging basket frame is hung below the rear guide beam through the frame hanging, and the height of the frame hanging is adjustable to adjust the height of the hanging basket frame; the hanging basket frame is supported on the bridge beam surface by the fixed support component; hoisting rails are provided on both inner sides of the rear guide beam and the main beam, and two lifting trolleys are installed on the hoisting rails, and the two lifting trolleys travel along the hoisting rails, and the entire steel cage is hoisted from below the rear guide beam to the outer mold hanging assembly through the sling.

2. The integrated upward movable mold frame according to claim 1, characterized in that: The fixed support assembly includes a plurality of spiral column feet distributed on both sides of the bottom of the basket tire frame, the tops of the spiral column feet are fixed to the basket tire frame by bolts, and the bottoms of the spiral column feet are configured as a triangular support base structure.

3. The integrated upward movable mold frame according to claim 1, characterized in that: The two outer sides of the rear guide beam are symmetrically connected to multiple groups of auxiliary cantilever beams, the number of tire frame hanging groups is the same as the number of auxiliary cantilever beams, each group of tire frame hanging includes two tire frame hangings connected to a group of auxiliary cantilever beams, the tire frame hanging includes a tire frame hanging rod and an oblique support rod, the upper ends of each group of two tire frame hanging rods are hinged to the auxiliary cantilever beams, the lower ends of each group of two tire frame hanging rods are respectively fixedly connected to the two side mold tire frames of the hanging basket tire frame, the two ends of the oblique support rod are respectively hinged to the auxiliary cantilever beam and the tire frame hanging rod, the tire frame hanging rod and the oblique support rod are made of telescopic cylinders, the tire frame hanging rod and the oblique support rod are telescopic, and the height of the hanging basket tire frame is adjusted.

4. The integrated upward movable mold frame according to claim 1, characterized in that: The hoist includes a hoisting frame and a suspension distributed and connected under the hoisting frame, the suspension is integrally connected to the steel cage, and two lifting trolleys are respectively connected to the two ends of the top of the hoisting frame; the hoisting frame includes connecting longitudinal beams, connecting cross beams, cross-linking beams, cantilever cross beams and longitudinal connecting beams, and two groups of connecting longitudinal beams and connecting cross beams are provided, and the two groups of connecting cross beams are respectively connected to the front and rear ends of the two groups of connecting longitudinal beams, and the connecting cross beams are connected to the lifting trolley, and the cross-linking beams are distributed and connected to the two groups of connecting longitudinal beams. Two groups of longitudinal connecting beams are provided, and the two groups of longitudinal connecting beams are connected to the outer sides of the two groups of connecting longitudinal beams through cantilever cross beams. There are multiple groups of cantilever cross beams distributed between the longitudinal connecting beams and the connecting longitudinal beams, and the cantilever cross beams are fixedly connected to the longitudinal connecting beams, and the cantilever cross beams are hinged to the connecting longitudinal beams and connected with cotter pins.

5. The integrated upward movable mold frame according to claim 1, characterized in that: Two electric hoists capable of moving longitudinally and transversely are installed on the rear guide beam, and the electric hoists are located behind the two lifting trolleys to assist in the binding of the steel cage.

6. The integrated upward movable mold frame according to claim 1, characterized in that: The outrigger assembly includes a front outrigger, an auxiliary outrigger, a middle outrigger and a rear outrigger, and the four outriggers are sequentially mounted at the front end of the main beam, the middle of the main beam, the rear end of the main beam and the rear end of the rear guide beam; The front outrigger comprises a front outrigger running mechanism, a front outrigger upper crossbeam, a front outrigger column, a front outrigger lifting cylinder, a front outrigger lower crossbeam, a front outrigger lateral movement cylinder, a front outrigger lateral movement beam and a front outrigger fixed crossbeam connected in sequence; the front outrigger running mechanism is connected to a front outrigger running track and a front outrigger hanging wheel track arranged on the main beam assembly, and the front outrigger running mechanism is driven by a reducer; the front outrigger column comprises an upper column and a lower column of the front outrigger, and the upper column and the lower column of the front outrigger are connected by a pin shaft and a cotter pin; the front outrigger lifting cylinder passes through the lower crossbeam of the front outrigger and is connected to the front outrigger The lower cross beam of the outrigger is fixedly connected, and the two ends of the front outrigger lifting cylinder are respectively fixedly connected to the front outrigger column and the front outrigger transverse beam; the front outrigger transverse beam is slidably connected to the front outrigger fixed cross beam, and the two ends of the front outrigger transverse cylinder are respectively connected to the front outrigger transverse beam and the front outrigger fixed cross beam, and the front outrigger transverse cylinder is extended and retracted to drive the front outrigger transverse beam to move laterally along the front outrigger fixed cross beam, and the front outrigger fixed cross beam is detachably anchored to the bridge pier through the front outrigger anchor rod; the upper cross beam of the front outrigger is longitudinally extended and connected to a support beam, and a front outrigger diagonal support cylinder is connected between the support beam and the front outrigger column; The auxiliary leg comprises an auxiliary leg hinge seat, an auxiliary leg column, an auxiliary leg lifting cylinder, an auxiliary leg pad and an auxiliary leg rotating cylinder, wherein the auxiliary leg column is connected to the bottom of the main beam through the auxiliary leg hinge seat, the auxiliary leg lifting cylinder is connected to the bottom of the auxiliary leg column, and the auxiliary leg pad is connected to the bottom of the auxiliary leg lifting cylinder through a fine-tuning screw. The two ends of the auxiliary outrigger rotation cylinder are connected to the main beam and the auxiliary outrigger column through an upper hinge seat and a lower hinge seat respectively. The auxiliary outrigger rotation cylinder is extended and retracted to drive the auxiliary outrigger to rotate around the main beam. The middle outrigger is an O-shaped structure as a whole. The middle outrigger includes C-shaped outrigger columns symmetrically connected to both sides of the main beam, a middle outrigger lifting cylinder, a middle outrigger lower crossbeam, a middle outrigger running mechanism, a middle outrigger running track, a middle outrigger lateral movement cylinder, a middle outrigger pad and a supporting column. The top of the C-shaped outrigger column is fixedly connected to the main beam, the middle outrigger lower crossbeam is connected to the bottom of the two C-shaped outrigger columns, the middle outrigger running track is installed on the bridge beam surface, the middle outrigger running mechanism is installed at the bottom of the middle outrigger lower crossbeam and installed on the middle outrigger running track, and the middle outrigger running mechanism is reduced by The middle outrigger is driven by a speed machine; two middle outrigger lifting cylinders are connected to the bottom of the lower crossbeam to control the lifting and lowering of the middle outrigger, thereby controlling the installation or detachment of the middle outrigger running mechanism from the middle outrigger running track; the middle outrigger pad is installed on the bridge beam surface, and the middle outrigger transverse movement cylinder is connected between the middle outrigger lower crossbeam and the middle outrigger pad. When the middle outrigger running mechanism is installed and detached from the middle outrigger running track, the middle outrigger transverse movement cylinder is extended and retracted to drive the middle outrigger to move laterally; the top of the support column is rotatably hinged to the bottom of the main beam, and the bottom of the support column is detachably connected to the middle outrigger lower crossbeam; The rear outrigger comprises a rear outrigger column, a rear outrigger lifting cylinder, a rear outrigger lower cross beam, a rear outrigger running mechanism and a rear outrigger running track which are connected in sequence. The rear outrigger column is fixedly connected to both sides of the rear guide beam, the rear outrigger running track is erected on the bridge beam surface, and the rear outrigger running mechanism is installed on the rear outrigger running track. When the middle outrigger is running, it drives the rear outrigger running mechanism to run along the rear outrigger running track.

7. The integrated upward movable mold frame according to claim 6, characterized in that: Auxiliary tensioning tooling is installed on the front supporting legs and the middle supporting legs.

8. The integrated upward movable mold frame according to claim 1, characterized in that: The outer formwork hanging assembly includes multiple groups of C-type hangings distributed on the main beam, wherein the number of groups of C-type hangings corresponds to the number of groups of main cantilever beams, and each group of C-type hangings includes two C-type hangings, which are respectively installed on the main cantilever beams through hydraulic transverse movement mechanisms and open and close relatively; the outer formwork is spliced ​​by the left outer formwork and the right outer formwork, which are respectively connected to all the left C-type hangings and the right C-type hangings through the formwork support cylinders, and the C-type hanging opens and closes, driving the left outer formwork and the right outer formwork to open and close. In the mold-closed casting state, the C-type hangings are closed, and the bottoms of each group of two C-type hangings are connected into a whole through connecting bolts, and the left outer formwork and the right outer formwork are connected into a whole; after the steel cage is put into the mold as a whole, a C-type hanging hanger is detachably connected between the main cantilever beam and the bottom of the C-type hanging, and the C-type hanging hanger is a through-cylinder type tensile hanger.

9. The integrated upward movable mold frame according to claim 1, characterized in that: Attached vibrators are installed on both sides of the outer formwork; electric push-pull canopies are installed above the main beam and the rear guide beam; two hydraulic concrete placing machines are fixedly connected to the main beam; the upward movable formwork also includes a spray curing assembly, which includes a spray curing system for the formed box beam and a spray curing system for the cast-in-place beam surface. The spray curing system for the formed box beam includes a spray head A distributed in the box beam hole, a spray head B distributed on the beam surface, and a spray head C located on the outside and below the box beam, wherein the spray head C sprays The frame hanger and the spray frame are connected to the bottom of the tire frame suspension. The bottom of each set of tire frame suspension is connected to the spray frame hanger. The bottom of the spray frame hanger is connected to the spray frame, and the spray frame is located on the outside and bottom of the bridge box girder. Spray heads C are distributed on the spray frame, so as to carry out spray maintenance on the formed bridge box girder; the cast-in-place beam surface spray maintenance system includes spray heads D distributed on both sides of the top of the outer formwork, and spray heads A, spray heads B, spray heads C and spray heads D are all connected to water pipes, and the water pipes are connected to water pumps and water tanks, so as to carry out spray maintenance on the cast-in-place beam surface.

10. The integrated upward movable mold frame according to claim 1, characterized in that: The front end of the main beam The main beam assembly is connected with a front guide beam and adopts a double longitudinal beam structure; the main cantilever beam is a truss structure with a right-angle trapezoidal cross section. The main cantilever beam is fixed against the outer side surface of the main beam.

Citation Information

Cited By

  • Upward self-propelled movable formwork for bridge construction and bidirectional construction method

    CN119195009A