Novel rigid frame bridge corbel bracket mechanism, construction method and finished bridge linear deformation control method of novel rigid frame bridge corbel bracket mechanism
Through the new rigid bridge oxleg bracket mechanism and construction method, the use of reverse prepression and BIM optimization formwork installation has solved the problem of difficulty in controlling the safety of cantilever brackets and unstable concrete deformation in bridge construction, and the stability of the bracket has been achieved and concrete compactness.
Patent Information
- Application Number
- CN202411360434.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-27
- Publication Date
- 2024-11-26
AI Technical Summary
In bridge construction, especially in prefabricated assembly process, the safety of the cantilever brackets of steel structure beams is difficult to control, and there is a problem of instability in the single pouring of the cable-strengthening prestressed concrete continuous rigid beam part No. A0 block.
New rigid bridge ox leg bracket mechanism and construction method are adopted, including embedded shearing steel rods, upper support legs, upper support, lower support, truss and I-shaped steel, and pre-embedded steel rods and fine-rolled threaded steel Reverse prepression is carried out, combined with leveling observation and hierarchical loading, the deformation of the bracket is controlled, and template installation and prestressing arrangement are optimized through the BIM model.
The safety and stability of the cantilever bracket is achieved, the gap and inelastic deformation of the vertical rods of the bracket under pre-pressed load are eliminated, the compactness and linear deformation control of the concrete slurry are ensured, and the controllability of the construction process is improved.
Smart Images

Figure CN119021108A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bridge construction, and in particular to a novel rigid frame bridge corbel bracket mechanism, a construction method and a bridge linear deformation control method thereof. Background Art
[0002] At present, with the continuous development of bridge engineering construction and the unstoppable development of prefabricated assembly technology, steel structural beams are gradually replacing reinforced concrete structural beams. With their advantages of lightweight and standardized construction, they play a vital role in important bridge node positions, such as curved ramps and large-span bridge spans.
[0003] At present, the length of the A0 block segment of the cable-reinforced prestressed concrete continuous rigid frame beam is 20m, and the concrete volume is 1542.5m 3 The single-sided cantilever is 5.5m, the total pouring height is 13m, and the safety of the one-time pouring cantilever bracket is difficult to control.
[0004] To this end, the present invention proposes a novel rigid frame bridge corbel bracket mechanism, a construction method and a bridge linear deformation control method for solving the above problems. Summary of the invention
[0005] The object of the present invention is to provide a novel rigid frame bridge corbel bracket mechanism, a construction method and a bridge linear deformation control method thereof, so as to solve the problems raised in the above-mentioned background technology.
[0006] To achieve the above object, the present invention provides the following technical solutions: a novel bracket mechanism for a rigid frame bridge, comprising a shear steel bar embedded in two concrete members on one side away from each other, an upper support leg fixedly mounted on the shear steel bar, and the upper support leg is inclined, and an upper bracket is mounted on the top of the upper support leg;
[0007] A lower support and an upper support are arranged between the two concrete members, and a truss is installed between the lower support and the upper support;
[0008] A cushion block is arranged on the top of the upper bracket, and an I-beam is arranged on the top of the cushion block.
[0009] Preferably, mounting blocks are fixedly mounted on both sides of the bottom of the lower support, and the two mounting blocks are fixedly mounted on the two concrete members respectively by bolts.
[0010] Preferably, the upper bracket is fixedly welded to the upper support and fixedly installed on the shear steel rod; a lower support leg is welded to the bottom of the upper bracket, and the lower support leg is fixed on the concrete member and the lower support; there are multiple upper brackets, and the distance between two adjacent upper brackets is 0.1m.
[0011] Preferably, the lower support is formed by welding 4 3HM588X300 steels and a 2cm steel plate.
[0012] Preferably, the truss is made of 40a and 2I56a steel, and the shear steel rods penetrate 35 cm into the concrete.
[0013] A novel construction method for a rigid frame bridge bracket mechanism, the construction method comprising:
[0014] Step 1: When pouring the pier body concrete, pre-embed steel bars and draw the fine-rolled steel channels on the pier body in advance;
[0015] Step 2: Install the upper and lower supports of the corbel. The corbel support is a finished weldment, mainly welded from steel plates and section steel. The support is anchored to the pier body by three PSB830Φ32 fine-rolled threaded steel bars, and the threaded steel bars are tensioned;
[0016] Step 3: After the bracket is installed, the load-bearing support and the load-bearing beam are installed respectively. The load-bearing beam is hoisted one by one. Positioning rings are welded on the load-bearing beam and the cushion beam, and two steel wire ropes with a diameter of not less than 16 mm are passed through the positioning rings for hoisting;
[0017] Step 4: After the load-bearing beams are installed, the main trusses are installed. Each main truss is divided into two pieces. They are hoisted piece by piece on the site, and then the flat joints are installed to connect the trusses into a unified whole.
[0018] Step 5: The brackets of the cantilevered parts of the tower columns shall be pre-assembled on site in advance. The pre-assembly site must be flat and set out in advance. The positioning and assembly shall be carried out strictly according to the designed angle. After the assembly is completed, the pin position shall be temporarily fixed by welding a small steel plate. The brackets shall be hoisted one by one during the hoisting. After the installation is completed, the small steel plate shall be cut off to release the lock.
[0019] Step 6: After the trusses and corbels are installed, demoulding pads, beams, and racks are installed layer by layer. During the installation process, they must be arranged strictly according to the designed spacing. At the same time, the elevation and flatness of the components must be carefully checked. For areas with gaps, thin steel plates are used for padding and welded to fix.
[0020] A novel bridge linear deformation control method for a bracket bracket mechanism of a rigid frame bridge is provided, and the bridge linear deformation control method is as follows:
[0021] S1: The pre-compression of the 0# block bracket of the continuous rigid frame adopts the counter-pre-compression of the pier top, and the PSB930Φ32 fine-rolled threaded steel is embedded in the integral pouring of the pier body concrete; the end of the counter-pressure frame is locked by the fine-rolled threaded steel, and the other end is provided with a jack to provide a counter-force, and the support system is pre-compressed under the action of the counter-force;
[0022] S2: Deformation observation: During construction, for some main support points of the load, a level is used to observe before loading, after loading, and during preloading to understand their deformation, so as to facilitate the control of the construction process; the preloading is divided into three loadings of 60%, 100%, and 120% according to 1.2 times the deadweight of the first cast beam section. The measuring points are arranged at the top of the bracket. In the transverse direction, the measuring points are arranged at the middle position of the bottom plate, web plate, and flange plate of the section according to the structural form of the section. After the bracket preloading is completed, the settlement value of the measuring point is measured every 2 hours. When the average settlement value of each observation point is not greater than 2mm for two times, the next level of loading can be carried out. After the third level of loading, it is stopped for 24 hours and then graded unloading begins; when the preloading load is unloaded, it is unloaded step by step according to the graded loading and preloading, and the settlement is observed during the unloading process. The graded unloading observation point is the same as the settlement observation point during loading. According to the actual loading and unloading measured data, the loading and unloading process deformation curves of each measuring point are drawn, and the elastic deformation of the bracket is calculated, which is used as the basis for setting the pre-camber;
[0023] S3: Formwork installation: Due to the different types of formwork for the lower tower column, tower pier consolidation and upper tower column during the main tower construction, it is difficult to control the positioning of the formwork tie rods and embedded parts during the construction process. Through the optimization simulation analysis of the BIM model, the problems existing in the position of embedded parts and tie rods and the conversion process of climbing formwork are determined and optimized; at the consolidation of the tower beam, due to the narrow working plane, the installation of the bridge tower side formwork and tie rod installation is difficult and difficult to locate, that is, the bridge tower side formwork at the tower beam consolidation is converted from the climbing formwork system at the lower tower to continue to climb upward;
[0024] S4: Steel bar installation: Steel bars are mainly composed of transverse beam steel bars, bottom plate steel bars, web steel bars and top plate steel bars according to their locations. Steel bars are processed centrally in the steel bar processing workshop and tied and formed on site.
[0025] S5: Prestressed installation: longitudinal prestressing is set on the beam body, transverse prestressing is set on the tower beam consolidation section and the cable beam anchoring crossbeam, vertical prestressing is set on the beam body in the local area on both sides of the main tower, the longitudinal prestressing tendons of the beam body adopt 19-15.2 high-strength low-relaxation steel strands, and the inner diameter 120mm metal corrugated pipe is used for drilling, the anchor system adopts clip-type anchors, the tensioning adopts YCW650B jacks, and the tensioning and anchoring adopts matching machinery and equipment.
[0026] Preferably, the instrument for settlement observation in step S2 is a DSZ2 level instrument. Four things need to be fixed during settlement observation: fixed observers; fixed instruments and leveling rods; fixed rear sight points; fixed time; and the elevation value of the top of the bracket in step S2 is finally adjusted to: design elevation value + design pre-arch value + pre-compression elastic deformation.
[0027] Preferably, the vacuum grouting process is used during the construction of step S5. The pipeline is positioned by a cross-shaped steel frame. The positioning steel bars are firmly welded to the steel frame with a spacing of 0.5m and a curve section of 0.3m. If the pipeline position collides with the skeleton steel bars, the pipeline position is ensured to remain unchanged, and only the steel bars are slightly moved to ensure the correct position of the pipeline. When encountering a conflict between the horizontal and vertical prestressed tendons, the adjustment principle is to first prestress the vertical prestress, then the horizontal prestressed tendons, and keep the longitudinal prestressed pipeline immobile.
[0028] Preferably, when the pier body concrete is poured as a whole, it is planned to be poured in three times through BIM modeling optimization, taking into account the positions of the longitudinal and transverse prestressed pipes. The first pouring is for the remaining part of the pier body to a position 5m above the bottom plate, the second pouring is for the web height, and the third pouring is for the top plate concrete. The surface is sprayed with high-pressure water guns in combination with manual chiseling, and joint steel bars are added.
[0029] Preferably, the concrete is poured in sections that are symmetrical in front and back, symmetrical in the same position left and right, and horizontally layered from top to bottom, from the pier top to both ends; the pouring sequence in the longitudinal direction of the bridge is: pouring from the lowest point of the main pier top to both ends; the pouring sequence in the transverse direction of the bridge is: the connection between the bottom plate and the web plate, the bottom plate, the upper part of the web plate, the flange plate, and the top plate; horizontal layering and symmetrical pouring, each layer is about 30cm thick, and 10cm is inserted into the lower layer when vibrating the upper layer. The vibration time of each vibration point must be controlled, and no vibration should be missed or over-vibrated. At the same time, pay attention to the density of the points, and the spacing should not be greater than the vibration action radius; after the concrete is poured, timely measures should be taken to maintain Wet measures are used to cure the concrete. When the newly poured concrete has an exposed surface, the exposed surface concrete is first smoothed, and then the exposed surface is covered with geotextile or plastic film, and spray watering measures are taken in time to moisturize the concrete. During the concrete curing period, the core temperature of the concrete, the surface temperature, the ambient air temperature, relative humidity, wind speed and other parameters are measured regularly, and the curing system is adjusted in time according to the changes in the concrete temperature and environmental parameters. The internal and external temperature difference of the concrete is strictly controlled to meet the requirements, and at the same time, the on-site curing and storage of the concrete specimens cured at the same time are done well.
[0030] Compared with the prior art, the present invention has the following beneficial effects:
[0031] The cable-reinforced continuous rigid frame main beam segment corbel bracket mechanism and the corresponding bridge linear deformation control method designed in the present invention adopt corbel brackets and steel trusses as formwork supports, the outer formwork of the tower column utilizes the outer formwork of the climbing formwork and the truss, the inner and outer formworks of the beam body both adopt large steel formworks, and the casting is completed on the bracket in three steps. The cantilever bracket is safe and stable; and after pre-stressing, the bracket has basically eliminated the gap and inelastic deformation of each vertical rod of the bracket under the action of the pre-stressing load. At the same time, a one-time grouting process is adopted to ensure that the pressed cement slurry is full and dense, effectively control the linear deformation of the bracket, and facilitate the control work of the construction process. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 It is a schematic diagram of the structural connection of the bracket bracket mechanism of the rigid frame bridge of the present invention;
[0033] Figure 2 It is a schematic diagram of the connection of the truss structure of the present invention;
[0034] Figure 3 This is a flow chart of the bridge linear deformation control method of the present invention;
[0035] Figure 4 It is a schematic diagram of the process flow of the present invention.
[0036] In the figure: 1. Concrete parts; 2. Upper bracket; 3. Shear steel rod; 4. Lower support leg; 5. Upper support leg; 6. Pad; 7. I-beam; 8. Mounting block; 9. Lower support; 10. Upper support; 11. Truss. DETAILED DESCRIPTION
[0037] The technical solutions in the embodiments of the present invention are described clearly and completely below. The embodiments of the present invention and all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present invention.
[0038] Example 1: Please refer to Figure 1-Figure 2 A cable-stiffened continuous rigid frame main beam segment bracket bracket mechanism includes a shear steel bar 3 embedded in the side of two concrete members 1 away from each other, an upper support leg 5 is fixedly installed on the shear steel bar 3, and the upper support leg 5 is inclined, and an upper bracket 2 is installed on the top of the upper support leg 5; a lower support 9 and an upper support 10 are arranged between the two concrete members 1, and a truss 11 is installed between the lower support 9 and the upper support 10; here, a pad 6 is arranged on the top of the upper bracket 2, and an I-beam 7 is arranged on the top of the pad 6.
[0039] In the present invention, mounting blocks 8 are fixedly installed on both sides of the bottom of the lower support 9, and the two mounting blocks 8 are fixedly installed on the two concrete members 1 by bolts respectively; the upper bracket 2 is fixedly welded to the upper support 10 and fixedly installed on the shear steel rod 3; the bottom of the upper bracket 2 is welded with a lower support leg 4, and the lower support leg 4 is fixed on the concrete member 1 and the lower support 9; here the lower support 9 is composed of 4 3HM588X300 steels and 2cm steel plates welded together; there are multiple upper brackets 2, and the spacing between two adjacent upper brackets 2 is 0.1m; the truss 11 is made of 40a and 2I56a steels, and the shear steel rod 3 penetrates 35cm into the concrete.
[0040] Working principle of the present invention: 0# block is cast by cast-in-place bracket, bracket structure is bracket, bottom formwork is 15mm bamboo plywood, the lower part is 10cm×10cm square wood, web and pier body are fully paved (spacing 0.1m), spacing under the bottom plate is 0.2m; rack is I25 combination frame, spacing under web is 0.3m, spacing under the bottom plate is 0.6m; longitudinal beam is 2I56a steel, cross beam is 2I56a, 3I56a steel, vertical rod is 2I56a steel, bracket diagonal brace is 2[32a steel, bracket cross beam is 2I40a steel, bracket longitudinal beam is 2I56a steel. Use 2I40a, 2I56a steel, truss uses [40a, 2I56a steel, the bottom load-bearing beam of the truss is made of 4 3HM588X300 steel and 2cm steel plate welded together, the height of the combined structure is 1.448m, the bottom of the load-bearing beam uses a customized node box, the node box is 10cm wide and penetrates 26cm into the pier, each tower column outer node box is equipped with 4 40Cr material Φ90mm steel rods, the steel rods penetrate 35cm into the concrete, the two middle node boxes are equipped with 2 40Cr material Φ90mm steel rods, the steel rods penetrate 35cm into the concrete.
[0041] In this embodiment, after the bracket is assembled, it is pre-stressed according to the designed force size and force distribution. The pre-stress is 1.2 times the constant load of the 0# block. It is observed in stages to measure the size of its elastic and inelastic deformation, and the strength and stability of the bracket are tested. The pre-arch of the bottom mold is set according to the elastic deformation of the bracket. After closing the side mold and end mold, the construction work of the 0# block can be carried out.
[0042] Example 2: Based on Example 1, please refer to Figure 3 The pre-compression of the 0# block bracket of the continuous rigid frame adopts the counter-pre-compression of the pier top, and the PSB930Φ32 fine-rolled threaded steel is embedded in the overall pouring of the pier body concrete; the end of the counter-pressure frame is locked by the fine-rolled threaded steel, and the other end is provided with a jack to provide a counter-force, and the support system is pre-compressed under the action of the counter-force;
[0043] Deformation observation: During construction, for some main load support points, use a level to observe before loading, after loading, and during preloading to understand their deformation, so as to facilitate the control of the construction process;
[0044] The preloading is divided into three loadings of 60%, 100%, and 120% according to 1.2 times the deadweight of the first cast beam section. The measuring point is arranged at the top of the bracket. In the transverse direction, the measuring point is arranged in the middle of the bottom plate, web plate, and flange plate of the section according to the structural form of the section. After the bracket preloading is completed, the settlement value of the measuring point is measured every 2 hours. When the average settlement value of each observation point is no more than 2mm for two times, the next level of loading can be carried out. After the third level of loading, it is stopped for 24 hours before the graded unloading begins;
[0045] When the preloading load is unloaded, the load is unloaded step by step according to the graded unloading method, and the settlement is observed during the unloading process. The graded unloading observation points are the same as the settlement observation points during loading. According to the measured data of loading and unloading, the deformation curves of the loading and unloading process of each measuring point are drawn, and the elastic deformation of the bracket is calculated, which is used as the basis for setting the pre-camber.
[0046] Formwork installation: Due to the different types of formwork for the lower tower column, tower pier consolidation and upper tower column during the main tower construction, it is difficult to control the positioning of the formwork tie rods and embedded parts during the construction process. Through the optimization simulation analysis of the BIM model, the problems existing in the position of embedded parts, tie rods and the conversion process of climbing formwork are determined and optimized; at the consolidation of the tower beam, due to the narrow working plane, the installation of the side formwork of the bridge tower and the installation of tie rods are difficult and difficult to locate, that is, the side formwork of the bridge tower at the consolidation of the tower beam is converted from the climbing formwork system at the lower tower and continues to climb upward;
[0047] Steel bar installation: Steel bars are mainly composed of transverse beam steel bars, bottom plate steel bars, web steel bars and top plate steel bars according to their locations. Steel bars are processed centrally in the steel bar processing workshop and tied and formed on site.
[0048] Prestressed installation: longitudinal prestress is set on the beam body, transverse prestress is set on the tower beam consolidation section and the cable beam anchor beam position, vertical prestress is set on the beam body in the local area on both sides of the main tower, the longitudinal prestressed tendons of the beam body adopt 19-15.2 high-strength low-relaxation steel strand, and the inner diameter 120mm metal corrugated pipe is used for drilling, the anchor system adopts clip-type anchor, the tensioning adopts YCW650B jack, and the tensioning and anchoring adopts matching machinery and equipment.
[0049] In the present invention, the central truss 11 is pre-stressed by setting 4 locations of fine-rolled threaded steel bars for locking, 13 bars at each location, and 4 locations of fine-rolled threaded steel bars for locking, 6 bars at each location. 4m long fine-rolled threaded steel bars and 1 double-layer L=10m3I630b I-beam 7 are used as shoulder beams; YCW-500B jacks are used, and the pre-stressing load is 120% of the amount of integrally poured concrete. According to the overall force analysis of the bracket, the large and small mileage directions of the brackets are pre-stressed according to the maximum support reaction force, that is, 63.7+63+67.9=194.6t. Double tops are used for ballasting when simulating pre-stressing through MADIS modeling. Each top is considered to be 100t; here, L=10.5m3I630b I-beam 7 is used as the shoulder beam in the center part, YCW-500B jack, and the preload is 120% of the amount of integral concrete poured. According to the overall force analysis of the support, the preload is based on the maximum support reaction force, that is, 1991.8t. When the MADIS modeling is used to simulate the preload, eight tops are used for load, and each top is considered to be 249t; the support reaction force at the corbel support is similar to the actual working condition; under the top force of the jack on the hollow part of the support, the downward pressure is transmitted at the other end through the lever principle, and the preload effect is played simultaneously.
[0050] In this embodiment, the instrument for settlement observation is DSZ2 level instrument. Four things need to be fixed during settlement observation: fixed observers; fixed instruments and level rods; fixed rear sight points; fixed time; the elevation value of the top of the bracket is finally adjusted to: design elevation value + design pre-arch value + pre-compression elastic deformation.
[0051] In this embodiment, vacuum grouting technology is used during construction. The pipeline is positioned by a cross-shaped steel frame, and the positioning steel bars are firmly welded to the steel frame, with a spacing of 0.5m and a curve section of 0.3m. If the pipeline position collides with the skeleton steel bars, the pipeline position is guaranteed to remain unchanged, and only the steel bars are slightly moved to ensure the correct position of the pipeline. When encountering a conflict between the horizontal and vertical prestressed tendons, the adjustment principle is to first prestress the vertical prestress, then the horizontal prestressed tendons, and keep the longitudinal prestressed pipeline immobile.
[0052] In this embodiment, when the pier body concrete is poured as a whole, it is planned to be poured in three times through BIM modeling optimization. Considering the positions of the longitudinal and transverse prestressed pipes, the first pouring is for the remaining part of the pier body to 5m above the bottom plate, the second pouring is for the height of the web plate, and the third pouring is for the top plate concrete. The surface layers are sprayed with high-pressure water guns in combination with manual roughening, and joint steel bars are added.
[0053] In this embodiment, the concrete pouring is divided into front-to-back symmetrical sections, left-to-right symmetrical sections, and upper-lower horizontal layers, from the pier top to both ends; the pouring sequence in the longitudinal direction of the bridge is: pouring from the lowest point of the main pier top to both ends; the pouring sequence in the transverse direction of the bridge is: the connection between the bottom plate and the web plate, the bottom plate, the upper part of the web plate, the flange plate, and the top plate; horizontal layering and symmetrical pouring, each layer is about 30cm thick, and 10cm is inserted into the lower layer when vibrating the upper layer. The vibration time of each vibration point must be controlled, and no vibration should be missed or over-vibrated. At the same time, attention should be paid to the density of the points, and the spacing should not be greater than the vibration action radius.
[0054] In this embodiment, after the concrete pouring is completed, moisturizing measures are taken in time to maintain the concrete. When the newly poured concrete has an exposed surface, the exposed surface concrete is first smoothed, and then the exposed surface is covered with geotextile or plastic film, and spraying watering measures are taken in time to maintain the concrete moisturizing. During the concrete curing period, the core temperature and surface temperature of the concrete as well as the ambient temperature, relative humidity, wind speed and other parameters are measured regularly, and the curing system is adjusted in time according to the changes in the concrete temperature and environmental parameters, and the internal and external temperature difference of the concrete is strictly controlled to meet the requirements. At the same time, the on-site curing and storage of the concrete specimens cured at the same time are well done.
[0055] The grouting materials of the grouting process in this embodiment are grouting agent, cement, and water, with a water-cement ratio of 1:0.32. The maximum delivery pressure of the ash pump is to ensure that the pressed cement slurry is full and dense, and its value is 0.5-0.6Mpa. The thick slurry is pressed out from the other end and the pressure is maintained for 5 minutes before the grouting valve can be removed.
[0056] In this embodiment, the pre-stressing of the continuous rigid frame 0# block bracket adopts the pier top counter-pre-stressing, and the PSB930Φ32 fine-rolled threaded steel is embedded in advance when the pier body concrete is poured as a whole; the end of the counter-stressing frame is locked by the fine-rolled threaded steel, and the other end is provided with a jack to provide a reaction force, and the support system is pre-stressed under the action of the reaction force; deformation observation: during construction, for some main support points of the load, a level is used to observe before loading, after loading, and during the pre-stressing process to understand its deformation, so as to facilitate the control of the construction process; the pre-stressing is divided into three loadings of 60%, 100%, and 120% according to 1.2 times the deadweight of the first poured beam section, and the measuring point It is arranged at the top of the bracket. According to the structural form of the cross section, the measuring points are arranged in the middle of the bottom plate, web and wing plate of the cross section in the transverse direction. After the bracket preload is loaded in stages, the settlement value of the measuring point is measured every 2 hours. When the average settlement value of each observation point is not more than 2mm for two times, the next level of loading can be carried out. After the third level of loading, it is stopped for 24 hours and then the graded unloading begins. When the preload is unloaded, it is unloaded step by step according to the graded loading and preloading, and the settlement is observed during the unloading process. The observation points of graded unloading are the same as the settlement observation points during loading. According to the measured data of loading and unloading, the loading and unloading data of each measuring point are drawn. The elastic deformation of the bracket is calculated based on the process deformation curve, which is used as the basis for setting the pre-camber; Formwork installation: Due to the different types of formwork at the lower tower column, tower pier consolidation and upper tower column during the main tower construction, it is difficult to control the positioning of the formwork tie rods and embedded parts during the construction process. Through the optimization simulation analysis of the BIM model, the problems existing in the position of embedded parts, tie rods and climbing formwork conversion process are determined and optimized; At the tower beam consolidation point, due to the narrow working plane, the installation of the bridge tower side formwork and tie rod installation is difficult and difficult to position, that is, the bridge tower side formwork at the tower beam consolidation point is converted from the climbing formwork system at the lower tower to continue to climb upward; Rebar installation: The steel bars are mainly composed of transverse beam steel bars, bottom plate steel bars, web steel bars and top plate steel bars according to their locations. The steel bars are processed centrally in the steel bar processing workshop and tied on site. Prestressed installation: longitudinal prestressing is set on the beam body, transverse prestressing is set on the tower beam consolidation section and the cable beam anchor beam position, vertical prestressing is set on the beam body in the local area on both sides of the main tower, the longitudinal prestressing tendons of the beam body adopt 19-15.2 high-strength and low-relaxation steel strands, and the holes are made of metal corrugated pipes with an inner diameter of 120mm, the anchoring system adopts clip-type anchors, the tensioning adopts YCW650B jacks, and the tensioning and anchoring adopts matching machinery and equipment.
[0057] Embodiment 3: Based on Embodiment 1, the present invention also provides a method for constructing a bridge with a cable-reinforced continuous rigid frame main beam segment bracket bracket, please refer to Figure 4 , including the following steps:
[0058] Step 1: When pouring the pier body concrete, pre-embed steel bars and draw the fine-rolled steel channels on the pier body in advance;
[0059] Step 2: Install the upper and lower supports of the corbel. The corbel support is a finished weldment, mainly welded from steel plates and section steel. The support is anchored to the pier body by three PSB830Φ32 fine-rolled threaded steel bars, and the threaded steel bars are tensioned;
[0060] Step 3: After the bracket is installed, the load-bearing support and the load-bearing beam are installed respectively. The load-bearing beam is hoisted one by one. Positioning rings are welded on the load-bearing beam and the cushion beam, and two steel wire ropes with a diameter of not less than 16 mm are passed through the positioning rings for hoisting;
[0061] Step 4: After the load-bearing beams are installed, the main trusses 11 are installed. Each main truss 11 is divided into two pieces, which are hoisted piece by piece on the site, and then the flat joints are installed to connect the trusses 11 into a unified whole;
[0062] Step 5: The brackets of the cantilevered parts of the tower columns shall be pre-assembled on site in advance. The pre-assembly site must be flat and set out in advance. The positioning and assembly shall be carried out strictly according to the designed angle. After the assembly is completed, the pin position shall be temporarily fixed by welding a small steel plate. The brackets shall be hoisted one by one during the hoisting. After the installation is completed, the small steel plate shall be cut off to release the lock.
[0063] Step 6: After the installation of the truss 11 and the corbels is completed, the demoulding pads, beams, and racks are installed layer by layer. During the installation process, they must be arranged strictly according to the designed spacing. At the same time, the elevation and flatness of the components must be carefully checked. For areas with gaps, thin steel plates are used for padding and welded to fix.
[0064] In this embodiment, before the bracket is installed, check whether the bracket embedded parts are firmly buried and whether the bottom concrete is dense. When installing, first install the bracket according to the requirements of the construction design drawing.
[0065] In this embodiment, after the bracket is installed, an acceptance inspection is carried out, and the acceptance content includes the installation position of the bracket embedded parts, the bracket processing quality and the installation status. Check whether the size of the bracket is consistent with the design drawing, whether the weld is full and the welding quality, especially whether the weld height meets the requirements of the design drawing.
[0066] In this embodiment, the bracket is pre-stressed after installation, and the pre-stressing method is as follows: adopt the pier top counter-pre-stressing, and embed the PSB930Φ32 finely rolled threaded steel when the pier body concrete is integrally poured; the end of the counter-pressure frame is locked by the finely rolled threaded steel, and the other end is provided with a jack to provide a reaction force, and the support system is pre-stressed under the action of the reaction force; the central truss 11 is pre-stressed with 4 finely rolled threaded steel locking locations, 13 at each location, and the cantilevered part is set with 4 finely rolled threaded steel locking locations, 6 at each location, and 4m long finely rolled threaded steel is used, and 1 double-layer L=10m3I630b I-beam 7 is used as a shoulder beam;
[0067] YCW-500B jack is used, and the preloading load is 120% of the amount of integrally poured concrete. According to the overall force analysis of the support, the corbels in the large and small mileage directions are preloaded according to the maximum support reaction force, that is, 63.7+63+67.9=194.6t. Double tops are used for ballast when simulating preloading through MADIS modeling, and each top is considered to be 100t. The center part uses L=10.5m3I630b I-beam 7 as a shoulder beam, YCW-500B jack, and the preloading load is 120% of the amount of integrally poured concrete. According to the overall force analysis of the support, the corbels are preloaded according to the maximum support reaction force, that is, 1991.8t. Eight tops are used for ballast when simulating preloading through MADIS modeling, and each top is considered to be 249t. The support reaction force at the corbel support is similar to the actual working condition. Under the top force of the jack on the hollow part of the support, the downward pressure is transmitted at the other end through the lever principle, and the preloading effect is played simultaneously.
[0068] In this embodiment, the top of the pier body is roughened, and the pre-embedded steel bars in the pier body are straightened; the cross beams are made of 2I56a and 3I56a steel; the steel bars are Φ90mm steel bars made of 40Cr, and the steel bars penetrate 35cm into the concrete.
[0069] In this embodiment, when the pier body concrete is poured, steel bars are embedded in the pier body in advance, and the fine-rolled steel channels are pulled; the upper and lower supports of the corbel are installed. The corbel support is a finished weldment, which is mainly welded by steel plates and steel sections. The support is anchored to the pier body as a whole by pulling with 3 PSB830Φ32 fine-rolled threaded steel bars, and the threaded steel bars are tensioned; after the corbel is installed, the load-bearing support and the load-bearing beam are installed respectively. The load-bearing beam is hoisted one by one, and a positioning ring is welded on the load-bearing beam and the cushion beam, and 2 steel wire ropes of not less than 16mm are passed through the positioning ring for hoisting; after the load-bearing beam is installed, the main truss 11 is installed, and each main truss 11 is divided into two pieces, which are hoisted one by one on the site, and then the flat joint is installed to connect the trusses 11 into a unified whole; the corbel brackets at the cantilevered parts of the tower columns are pre-assembled in advance on the site, and the pre-assembly site must be Level it, and lay out in advance, and position and assemble it strictly according to the designed angle. After the assembly is completed, a small steel plate is used to weld the pin position for temporary fixation. The hoisting is carried out one by one. After the installation is completed, the small steel plate is cut off to release the lock; after the truss 11 and the corbel are installed, the demoulding pads, beams, and racks are installed layer by layer. During the installation process, they must be arranged strictly according to the designed spacing. At the same time, the elevation and flatness of the components must be carefully checked. For the parts with gaps, thin steel plates are used for padding and welded to fix; after the bracket is assembled, it is pre-pressed according to the designed force size and force distribution. The pre-pressure is 1.2 times the constant load of the 0# block, and it is observed in stages to measure the size of its elastic and inelastic deformations, and the strength and stability of the bracket are tested, as well as the pre-arch of the bottom mold set according to the elastic deformation of the bracket. After the side mold and end mold are closed, the construction work of the 0# block can be carried out.
[0070] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A novel bracket mechanism for a rigid frame bridge, characterized in that: It comprises a shear-resistant steel bar (3) pre-buried on one side of two concrete members (1) away from each other, an upper support leg (5) is fixedly mounted on the shear-resistant steel bar (3), and the upper support leg (5) is arranged in an inclined manner, and an upper bracket (2) is mounted on the top of the upper support leg (5); A lower support (9) and an upper support (10) are arranged between the two concrete members (1), and a truss (11) is installed between the lower support (9) and the upper support (10); A cushion block (6) is arranged on the top of the upper bracket (2), and an I-beam (7) is arranged on the top of the cushion block (6).
2. A novel bracket mechanism for a rigid frame bridge according to claim 1, characterized in that: Mounting blocks (8) are fixedly mounted on both sides of the bottom of the lower support (9), and the two mounting blocks (8) are fixedly mounted on the two concrete members (1) respectively by bolts.
3. The novel bracket mechanism for a rigid frame bridge according to claim 1 is characterized in that: The upper bracket (2) is fixedly welded to the upper support (10) and fixedly mounted on the shear-resistant steel rod (3); a lower support leg (4) is welded to the bottom of the upper bracket (2), and the lower support leg (4) is fixed to the concrete member (1) and the lower support (9); there are multiple upper brackets (2), and the distance between two adjacent upper brackets (2) is 0.1 m.
4. The novel bracket mechanism for a rigid frame bridge according to claim 1 is characterized in that: The lower support (9) is formed by welding four 3HM588X300 steels and a 2cm steel plate; the truss (11) is made of 40a and 2I56a steels, and the shear steel rod (3) is inserted 35cm into the concrete.
5. A construction method for a novel rigid frame bridge bracket mechanism as claimed in any one of claims 1 to 4, characterized in that: The construction method is: Step 1: When pouring the pier body concrete, pre-embed steel bars and draw the fine-rolled steel channels on the pier body in advance; Step 2: Install the upper and lower supports of the corbel. The corbel support is a finished weldment, mainly welded from steel plates and section steel. The support is anchored to the pier body by three PSB830Φ32 fine-rolled threaded steel bars, and the threaded steel bars are tensioned; Step 3: After the bracket is installed, the load-bearing support and the load-bearing beam are installed respectively. The load-bearing beam is hoisted one by one. Positioning rings are welded on the load-bearing beam and the cushion beam, and two steel wire ropes with a diameter of not less than 16 mm are passed through the positioning rings for hoisting; Step 4: After the load-bearing beams are installed, the main trusses (11) are installed. Each main truss (11) is divided into two pieces, which are hoisted piece by piece on the site, and then the flat joints are installed to connect the trusses (11) into a unified whole; Step 5: The brackets of the cantilevered parts of the tower columns shall be pre-assembled on site in advance. The pre-assembly site must be flat and set out in advance. The positioning and assembly shall be carried out strictly according to the designed angle. After the assembly is completed, the pin position shall be temporarily fixed by welding a small steel plate. The brackets shall be hoisted one by one during the hoisting. After the installation is completed, the small steel plate shall be cut off to release the lock. Step 6: After the truss (11) and the bracket are installed, the demoulding pads, beams, and racks are installed layer by layer. During the installation process, they must be arranged strictly according to the designed spacing. At the same time, the elevation and flatness of the components must be carefully checked. For the gaps, thin steel plates are used for padding and welded to fix.
6. A method for controlling the linear deformation of a new type of rigid frame bridge bracket mechanism as claimed in any one of claims 1 to 5, characterized in that: The linear deformation control method of the bridge is: S1: The pre-compression of the 0# block bracket of the continuous rigid frame adopts the counter-pre-compression of the pier top, and the PSB930Φ32 fine-rolled threaded steel is embedded in the integral pouring of the pier body concrete; the end of the counter-pressure frame is locked by the fine-rolled threaded steel, and the other end is provided with a jack to provide a counter-force, and the support system is pre-compressed under the action of the counter-force; S2: Deformation observation: During construction, for some main support points of the load, a level is used to observe before loading, after loading, and during preloading to understand their deformation, so as to facilitate the control of the construction process; the preloading is divided into three loadings of 60%, 100%, and 120% according to 1.2 times the deadweight of the first cast beam section. The measuring points are arranged at the top of the bracket. In the transverse direction, the measuring points are arranged at the middle position of the bottom plate, web plate, and flange plate of the section according to the structural form of the section. After the bracket preloading is completed, the settlement value of the measuring point is measured every 2 hours. When the average settlement value of each observation point is not greater than 2mm for two times, the next level of loading can be carried out. After the third level of loading, it is stopped for 24 hours and then graded unloading begins; when the preloading load is unloaded, it is unloaded step by step according to the graded loading and preloading, and the settlement is observed during the unloading process. The graded unloading observation point is the same as the settlement observation point during loading. According to the actual loading and unloading measured data, the loading and unloading process deformation curves of each measuring point are drawn, and the elastic deformation of the bracket is calculated, which is used as the basis for setting the pre-camber; S3: Formwork installation: Due to the different types of formwork for the lower tower column, tower pier consolidation and upper tower column during the main tower construction, it is difficult to control the positioning of the formwork tie rods and embedded parts during the construction process. Through the optimization simulation analysis of the BIM model, the problems existing in the position of embedded parts and tie rods and the conversion process of climbing formwork are determined and optimized; at the consolidation of the tower beam, due to the narrow working plane, the installation of the bridge tower side formwork and tie rod installation is difficult and difficult to locate, that is, the bridge tower side formwork at the tower beam consolidation is converted from the climbing formwork system at the lower tower to continue to climb upward; S4: Steel bar installation: Steel bars are mainly composed of transverse beam steel bars, bottom plate steel bars, web steel bars and top plate steel bars according to their locations. Steel bars are processed centrally in the steel bar processing workshop and tied and formed on site. S5: Prestressed installation: longitudinal prestressing is set on the beam body, transverse prestressing is set on the tower beam consolidation section and the cable beam anchoring crossbeam, vertical prestressing is set on the beam body in the local area on both sides of the main tower, the longitudinal prestressing tendons of the beam body adopt 19-15.2 high-strength low-relaxation steel strands, and the inner diameter 120mm metal corrugated pipe is used for drilling, the anchor system adopts clip-type anchors, the tensioning adopts YCW650B jacks, and the tensioning and anchoring adopts matching machinery and equipment.
7. The method for controlling the linear deformation of a new type of rigid frame bridge bracket mechanism according to claim 6 is characterized in that: The instrument for settlement observation in step S2 is a DSZ2 level. Four things need to be fixed during settlement observation: fixed observers; fixed instruments and leveling rods; fixed rear sight points; fixed time; and the elevation value of the top of the bracket in step S2 is finally adjusted to: design elevation value + design pre-arch value + pre-compression elastic deformation.
8. The method for controlling the linear deformation of a new type of rigid frame bridge bracket mechanism according to claim 6 is characterized by: During the construction of step S5, a vacuum grouting process is adopted. The pipeline is positioned by a criss-cross steel frame. The positioning steel bars are firmly welded to the steel frame with a spacing of 0.5m and a curve section of 0.3m. If the pipeline position collides with the skeleton steel bars, the pipeline position is ensured to remain unchanged, and only the steel bars are slightly moved to ensure the correct position of the pipeline. When encountering a conflict between the transverse and vertical prestressed tendons, the adjustment principle is to first prestress the vertical prestress, then the transverse prestressed tendons, and keep the longitudinal prestressed pipeline stationary.
9. The method for controlling the linear deformation of a new type of rigid frame bridge bracket mechanism according to claim 6 is characterized in that: When pouring the pier body concrete as a whole, it was planned to be poured in three times through BIM modeling optimization. Considering the position of the longitudinal and transverse prestressed pipes, the first pouring was for the remaining part of the pier body to 5m above the bottom plate, the second pouring was for the web height, and the third pouring was for the top plate concrete. The surface layers were sprayed with high-pressure water guns and roughened manually, and joint steel bars were added.
10. The method for controlling the linear deformation of a new type of rigid frame bridge bracket mechanism according to claim 6, characterized in that: Concrete pouring is carried out in sections symmetrically front and back, symmetrically left and right, and horizontally in layers from top to bottom, from the pier top to both ends; the pouring sequence in the longitudinal direction is: pouring from the lowest point of the main pier top to both ends; the pouring sequence in the transverse direction is: the connection between the bottom plate and the web plate, the bottom plate, the upper part of the web plate, the flange plate, and the top plate; horizontal layering and symmetrical pouring, each layer is about 30cm thick, and when vibrating the upper layer, insert 10cm into the lower layer. The vibration time of each vibration point must be controlled, and no vibration should be missed or over-vibrated. At the same time, pay attention to the density of the points, and the spacing should not be greater than the vibration radius; after the concrete pouring is completed, take moisturizing measures in time The concrete is maintained. When the newly poured concrete has an exposed surface, the exposed surface concrete is first smoothed, and then the exposed surface is covered with geotextile or plastic film, and spray watering measures are taken in time to moisturize the concrete. During the concrete maintenance period, the core temperature of the concrete, the surface temperature, the ambient air temperature, relative humidity, wind speed and other parameters are measured regularly, and the maintenance system is adjusted in time according to the changes in the concrete temperature and environmental parameters. The internal and external temperature difference of the concrete is strictly controlled to meet the requirements. At the same time, the on-site maintenance and storage of the concrete specimens that are maintained at the same time are done well.