Implementation method for preventing leakage and cracking of basement floor

By setting up a drainage structure between the basement floor slab and the ground floor, the problems of water seepage and cracking in the basement floor were solved, achieving a dry and aesthetically pleasing basement, reducing the risk of concrete cracking, and preventing the filter holes from becoming clogged.

CN119021256APending Publication Date: 2024-11-26CHINA FIRST METALLURGICAL GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411385293.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-30
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

Basement floors are prone to cracks and water seepage during construction due to water seepage from the foundation slab, leading to long-term water accumulation and dampness. Existing treatment methods are costly and affect aesthetics.

Method used

A drainage structure is installed between the structural base slab and the floor layer, including drilling filter holes in the drainage pipes, arranging the drainage pipes and covering them with filter material and steel mesh to form drainage and flow guidance measures to control seepage water from being discharged below the surface layer.

Benefits of technology

It effectively solves the problems of water seepage and cracking in basement floors, keeps the floors dry and aesthetically pleasing, reduces the risk of large-area concrete cracking, and avoids clogging of filter holes and adverse effects during construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021256A_ABST
    Figure CN119021256A_ABST
Patent Text Reader

Abstract

The invention relates to an implementation method for preventing leakage and cracking of a basement floor. The implementation method comprises the steps that water filtering holes are drilled in the lower half portion of a pipe body of a drainage pipe; constructing to form a drainage ditch according to the construction drawing, arranging a drainage pipe according to the anti-seepage requirement of the basement floor, and arranging one end, with a water outlet, of the drainage pipe above the drainage ditch; a filter screen is plugged into a water outlet of the drainage pipe, a cushion layer is poured at the end opening, close to the water outlet, of the drainage pipe, and the middle of a pipe body of the drainage pipe is wrapped with a water filtering material; a reinforcing mesh is laid on the upper portions of the drainage pipes, and then a floor layer wrapping the reinforcing mesh is formed on the reinforcing mesh in a pouring mode. The drainage structure is additionally arranged between the structural bottom plate and the terrace layer, so that the problems of water seepage and water stain of the terrace layer caused by water seepage of the structural bottom plate are solved; the drainage pipes can be flexibly arranged as required according to the actual water seepage condition of the basement bottom plate, so that water seepage of the bottom plate is controlled below the terrace, and the later forming attractiveness is not affected.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of basement construction, and in particular to an implementation method for preventing leakage and cracking of basement floors. Background Art

[0002] During the construction of building projects, there are cases where the concrete of some structural bottom slabs is not vibrated and compacted during construction or there is a certain amount of water seepage in the secondary and lower waterproof structures, resulting in cracks and water seepage in the basement bottom slab. Long-term water accumulation causes increased water pressure, resulting in cracks in the basement floor decorative surface. Most treatment methods are to remove the surface layer and grout the cracks in the basement bottom slab structure or to add open drainage ditches at the cracks, which are costly and affect the overall appearance. In view of the above problems, the present invention studies a construction method, which adds the above-mentioned drainage and anti-cracking functions between the structural bottom slab and the floor layer. Through this function, the seepage water is drained below the surface layer to prevent the seepage water from affecting the floor layer. Summary of the invention

[0003] In response to the above problems, a method for preventing basement floor leakage and cracking is now provided, which aims to solve the problem of long-term water accumulation and humidity in the basement caused by cracking and water seepage in the basement floor during the construction of the building, or to take drainage and diversion measures in advance during the design stage of the building's floor slab to ensure that the water seepage in the floor slab during the construction process is effectively handled, thereby meeting the requirements of a relatively dry and moisture-free basement and a crack-free and leakage-free floor surface.

[0004] The specific technical solutions are as follows:

[0005] The implementation methods for preventing leakage and cracking of basement floors include:

[0006] Drill water filter holes in the lower half of the drain pipe;

[0007] According to the construction drawings, form the drainage ditch, and then arrange the drainage pipe according to the need for anti-leakage of the basement floor, and set the end of the drainage pipe with the water outlet above the drainage ditch;

[0008] Insert the filter into the outlet of the drain pipe, and then pour a cushion layer at the end of the drain pipe near the outlet, and wrap the middle part of the drain pipe with the filter material;

[0009] A steel mesh is laid on the upper part of the drainage pipe, and then a floor layer covering the steel mesh is poured onto the steel mesh.

[0010] Furthermore, the water filter hole is located on the semicircular surface of the drain pipe, and after the drain pipe is arranged, the semicircular surface with the water filter hole faces the bottom plate.

[0011] Furthermore, the drainage pipe is arranged to be inclined from high to low from the other end away from the water outlet to the end with the water outlet.

[0012] Furthermore, the drainage pipe is a Φ50 pipe; the diameter of the water filter holes is 4-6mm, and the spacing is 45-55mm.

[0013] Furthermore, the cushion layer is formed by pouring C30 fine stone concrete.

[0014] Furthermore, the water filtering material is stone chips.

[0015] Furthermore, the outer periphery of the water filtration material is wrapped with an isolation net.

[0016] Furthermore, the left and right ends of the steel mesh extend to the left and right ends of the drainage pipe, and the front and rear extend to both sides above the cushion layer.

[0017] Furthermore, when pouring the floor layer, the middle part of the pipe body of the drainage pipe is poured first, and then the whole pipe is poured.

[0018] Furthermore, the floor layer is formed by pouring C25 fine stone concrete.

[0019] The beneficial effects of the above scheme are:

[0020] 1) In the present invention, a drainage structure is added between the structural bottom plate and the floor layer to solve the problem of water seepage and water stains on the floor layer caused by water seepage from the structural bottom plate;

[0021] 2) In the present invention, the drainage pipes can be flexibly arranged as needed according to the actual water seepage of the basement floor, so as to control the water seepage of the basement floor below the floor level without affecting the aesthetic appearance of the later molding;

[0022] 3) Using isolation nets to compact the stone chips and wrap the drainage pipes effectively reduces or even avoids the problems of stone chips solidification and clogging of drainage holes that may be caused during the subsequent concrete pouring process;

[0023] 4) The implementation method provided by the present invention has the effect of dispersing stress on large-area concrete, thereby effectively reducing the risk of cracking of large-area concrete. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a front view structural schematic diagram of the anti-leakage and cracking structure provided in an embodiment of the present invention;

[0025] Figure 2 It is a schematic cross-sectional structural diagram of the anti-leakage and cracking structure provided in an embodiment of the present invention.

[0026] In the attached figure: 1. bottom plate; 2. water filter material; 3. isolation net; 4. drainage pipe; 5. water filter hole; 6. filter net; 7. cushion layer; 8. floor layer; 9. drainage ditch; 10. steel mesh. DETAILED DESCRIPTION

[0027] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0028] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features in the embodiments may be combined with each other.

[0029] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments, but they are not intended to limit the present invention.

[0030] like Figure 1 , Figure 2 As shown, the implementation method of preventing basement floor leakage and cracking provided in the embodiment of the present invention includes:

[0031] Drill water filter holes 5 on the lower half of the Φ50PVC drainage pipe 4. To achieve both drainage and structural stability, the diameter of the water filter holes 5 on the Φ50PVC drainage pipe 4 is 4-6mm, and the spacing is 45-55mm.

[0032] According to the construction drawings, the drainage ditch 9 is constructed, and then the drainage pipe 4 is arranged as a whole according to the need for anti-leakage of the basement floor, forming a 6m×6m "well"-shaped pipe network, and one end of the drainage pipe 4 with a water outlet is arranged above the drainage ditch 9. In order to quickly discharge water, the drainage pipe 4 in the above pipe network is arranged to be inclined from high to low from the other end away from the water outlet to the end with the water outlet;

[0033] Insert the filter net 6 into the outlet of the drain pipe 4 to prevent foreign objects from clogging the outlet during subsequent construction or use, and then cast a cushion layer 7 at the end of the drain pipe 4 near the outlet to support one end of the drain pipe 4 with the cushion layer 7; place the isolation net 3 under the drain pipe 4, and then fill the gap between the drain pipe 4 and the bottom plate 1 with stone chips 2 above the isolation net 3, and bind the upper opening of the isolation net 3 to compact the stone chips 2;

[0034] A 600mm wide steel mesh 10 made of HRB400 is laid on the upper part of the drainage pipe 4, and then a floor layer 8 (which can be formed by pouring C25 fine stone concrete) covering the steel mesh 10 is cast on the steel mesh 10. Under the above structure, the steel mesh 10 can be used to effectively reinforce the area above the drainage ditch 9 (i.e. Figure 1 , Figure 2 The left and right ends of the steel mesh 10 shown extend to the left and right ends of the drainage pipe 4, and the front and rear extend to both sides above the cushion layer 1).

[0035] In order to avoid the water filter hole 5 from being blocked, the water filter hole 5 in the present invention is located on the semicircular surface of the drain pipe 4, and after the drain pipe 4 is arranged, the semicircular surface of the water filter hole 5 faces the bottom plate 1, so that the solid impurities in the sewage can enter the drain pipe 4 after being filtered out by the stone chips 2, and then be quickly discharged through the drain pipe 4 to the drainage ditch 9, avoiding the problem of water seepage and water stains in the floor layer due to water seepage of the structural bottom plate 1, thereby controlling the leakage of the bottom plate 1 below the floor layer 8, and not affecting the aesthetic appearance of the later molding.

[0036] In the present invention, the isolation net 3 is used to compact the stone chips 2 and wrap the drainage pipe 4, which effectively reduces the problem of stone chips solidification and clogging of the water filter holes 5 that may be caused during the subsequent concrete pouring construction process.

[0037] In order to prevent the cushion layer 7 from damaging the relatively weak drainage pipe 4 while satisfying the supporting function for the drainage pipe 4, the cushion layer 7 in the present invention can be formed by pouring C30 fine stone concrete.

[0038] The above description is only a preferred embodiment of the present invention, and does not limit the implementation mode and protection scope of the present invention. For those skilled in the art, it should be aware that all solutions obtained by equivalent substitutions and obvious changes made using the description and illustrations of the present invention should be included in the protection scope of the present invention.

Claims

1. The implementation method of preventing leakage and cracking of basement floor is characterized by: include: Drill water filter holes in the lower half of the drain pipe; According to the construction drawings, form the drainage ditch, and then arrange the drainage pipe according to the need for anti-leakage of the basement floor, and set the end of the drainage pipe with the water outlet above the drainage ditch; Insert the filter into the outlet of the drain pipe, and then pour a cushion layer at the end of the drain pipe near the outlet, and wrap the middle part of the drain pipe with the filter material; A steel mesh is laid on the upper part of the drainage pipe, and then a floor layer covering the steel mesh is poured onto the steel mesh.

2. The method for preventing basement floor leakage and cracking according to claim 1 is characterized in that: The water filter hole is located on the semicircular surface of the drain pipe, and after the drain pipe is arranged, the semicircular surface with the water filter hole faces the bottom plate.

3. The method for preventing basement floor leakage and cracking according to claim 1 or 2, characterized in that: The drainage pipe is arranged in an inclined manner from high to low from the other end away from the water outlet to the end with the water outlet.

4. The method for preventing basement floor leakage and cracking according to claim 1 is characterized in that: The drainage pipe is a Φ50 pipe; the diameter of the filter holes is 4-6mm, and the spacing is 45-55mm.

5. The method for preventing basement floor leakage and cracking according to claim 1 is characterized in that: The cushion layer is formed by pouring C30 fine stone concrete.

6. The method for preventing basement floor leakage and cracking according to claim 1 is characterized in that: The filter material is stone chips.

7. The method for preventing basement floor leakage and cracking according to claim 6 is characterized in that: The outer periphery of the water filter material is wrapped with an isolation net.

8. The method for preventing basement floor leakage and cracking according to claim 1 is characterized in that: The left and right ends of the steel mesh extend to the left and right ends of the drainage pipe, and the front and rear extend to both sides above the cushion layer.

9. The method for preventing basement floor leakage and cracking according to claim 1, characterized in that: When pouring the floor layer, pour the middle part of the drainage pipe first, and then pour the entire pipe.

10. The method for preventing basement floor leakage and cracking according to claim 9, characterized in that: The floor layer is formed by pouring C25 fine stone concrete.