Basement exterior wall post-cast strip steel plate sealing construction method
By using a combined structure of 3mm thick steel plate and C22 steel bars, combined with expansion screws and double-sided welding technology, the problem of insufficient rigidity and strength of the outer wall casting tape structure is solved, and more efficient closure and waterproofing treatment is achieved, and construction efficiency is improved and security.
Patent Information
- Application Number
- CN202411185808.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-27
- Publication Date
- 2024-11-26
AI Technical Summary
The overall stiffness and strength of the retaining structure of the existing exterior wall rear casting strip are low, and are prone to deformation, cracking or collapse, affecting the closure and backfilling of the basement exterior wall.
The 3mm thick steel plate is used as the sealing structure of the rear casting tape. Two C22 steel bars are welded on both sides at equal spacing along the length of the steel plate. The steel plate is fixed with expansion screws along both ends of the rear casting tape, combining prefabricated sealing plate, double steel pipe back corrugation and pulling The screw assembly realizes the lifting and fixing of steel plates, and performs double-sided welding and waterproofing to ensure the stability and sealing of the structure.
The sealing strength and stability of the outer wall rear pouring strip is improved, the enclosure time is shortened, construction materials and human resources are saved, and the waterproofing and backfill of the basement structure is carried out smoothly.
Smart Images

Figure CN119021280A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of early blocking of a post-cast strip of a basement outer wall, and in particular relates to a steel plate sealing construction method for a post-cast strip of a basement outer wall. Background Art
[0002] In construction projects, post-cast joints in reinforced concrete structures are common to prevent structural damage caused by uneven settlement or thermal expansion. However, due to various factors affecting the sealing time of post-cast joints, they cannot be closed in time, hindering the normal backfill construction of the basement exterior walls. Therefore, temporary sealing measures for exterior wall post-cast joints are extremely important.
[0003] Currently, the more traditional temporary sealing method for exterior wall post-casting strips is to use precast concrete panels or brickwork retaining structures. These structures can be inserted into the underground exterior wall waterproofing layer and foundation trench backfill construction in advance. However, when used to seal the ultra-deep underground exterior wall post-casting strips in advance, the precast concrete panels and brickwork retaining structures have low overall rigidity and strength, making them prone to deformation, cracking, or collapse. This makes the installed precast panels or completed walls a source of danger. This patented construction method breaks with traditional methods and uses the exterior wall post-casting strip for temporary sealing.
[0004] A search revealed no inventions identical to this project. The two patents listed above, Patent Name 1: "Method for Preliminary Sealing of Exterior Wall Post-cast Joints," Patent Number: CN103615019A, utilize concrete-formed sealing panels to seal exterior wall post-cast joints. This allows for the panels to be prefabricated before sealing. When sealing is required, the panels are simply placed on the exterior of the exterior wall post-cast joint and secured to the joint. Patent Name 2: "A Preliminary Sealing Structure for Exterior Wall Post-cast Joints," Patent Number: CN214784228U, utilizes prefabricated sealing panels, double steel tube back ribs, and tension screw assemblies to seal gaps on the exterior side of the exterior wall post-cast joints. This facilitates the construction of basement exterior wall waterproofing, protective layers, and subsequent foundation pit backfill. This significantly shortens the waiting time for sealing the exterior wall post-cast joints, ensuring that the exterior walls of the basement structure are sealed as soon as waterproofing conditions are met, accelerating both basement sealing time and foundation pit backfill. Through comparison, this technology has invented a method for sealing basement exterior wall post-cast strips with steel plates. This method optimizes the traditional exterior wall post-cast strip sealing process, shortens construction time, and saves resources such as construction materials and manpower. The actual effect is superior to the traditional exterior wall post-cast strip sealing process, providing an important guarantee for the accuracy of subsequent experiments. This invention is novel, practical, and flexible, and conforms to the concept of sustainable development. This patent is eligible for patent application. Summary of the Invention
[0005] The purpose of the present invention is to provide a steel plate sealing construction method for the post-cast strip of the basement outer wall. By providing a steel plate sealing construction method for the post-cast strip of the basement outer wall, the technical problems in the prior art of low overall rigidity, low strength, and easy deformation, cracking or collapse of such retaining structures are solved.
[0006] To solve the above technical problems, the present invention is achieved through the following technical solutions: The present invention is a method for sealing a basement exterior wall post-cast strip with a steel plate, comprising the following steps: Step 1: Process the exterior wall post-casting strip sealing steel plate; Step 2: Preparation before construction; Step 3: Remove and clean up debris in the post-cast zone; Step 4: rust removal, repair, correction, tying or repair welding of steel bars; Step 5: Lifting and fixing of closed steel plate; Step 6: Repeat step 5 until the post-casting strip is completely closed; Step 7: Double-sided welding of the joints of the closed steel plates of the post-casting strip; Step 8: Perform waterproofing; Step 9: Backfill construction of basement exterior wall.
[0007] Furthermore, the above-mentioned method for constructing a steel plate sealing of a basement exterior wall post-cast strip is characterized in that, in step one, a 3 mm thick steel plate is used as the post-cast strip sealing structure, two C22 steel bars are welded on both sides of the steel plate at equal intervals along the length direction of the steel plate, and the steel plate is fixed to the exterior wall surface with expansion screws at both ends of the post-cast strip, one end being a fixed end and the other end being a movable end, so as to meet the requirements of structural settlement and expansion.
[0008] Furthermore, the method for constructing a steel plate sealing construction method for the post-cast strip of the basement exterior wall is characterized in that, in step 2, before construction, the position of the steel plate to be fixed in the post-cast strip is first positioned and laid out to ensure that the position of the fixed steel plate is flat and vertical, and the number of steel bars, expansion bolts and tension screws to be used is calculated, and materials are prepared in advance.
[0009] Furthermore, the method for constructing a steel plate sealing strip of a basement exterior wall is characterized in that, in step three, when constructing the exterior wall, the deposited and loose concrete and floating slurry in the post-cast strip should be chiseled out and cleaned first, especially the concrete and steel plate mesh on both sides of the waterstop steel plate must be cleaned and flushed with a water gun until the pouring conditions are met before the next process can be carried out.
[0010] Furthermore, the above-mentioned method for enclosing the steel plate of the post-cast strip of the basement exterior wall is characterized in that, in step four, the steel bar rust removal includes rust removal of all steel bars, and after rust removal, the rust on the steel bars in the post-cast strip is rinsed clean with water, and the curved ones are straightened after rust removal. After acceptance by the supervision unit, the steel bars in the post-cast strip of the exterior wall are rust-removed and rinsed and poured immediately. If pouring cannot be done in time, all steel bars are rust-removed again before pouring the post-cast strip of the exterior wall.
[0011] Furthermore, the method for sealing the basement exterior wall post-cast strip steel plate is characterized in that in step 5, each section of the sealing steel plate is the length of a single-layer basement floor height, unit: m, and is hoisted to the exterior wall post-cast strip according to Figure 2 The method is to fix it on the outer wall of the basement.
[0012] Furthermore, the method for constructing a basement exterior wall post-cast strip sealing steel plate is characterized in that, in step six, step five is continuously repeated until the construction of the exterior wall post-cast strip sealing steel plate is completed.
[0013] Furthermore, the aforementioned method for sealing a basement exterior wall post-cast strip with steel plates is characterized by the following: in step seven, double-sided welding is performed at the joints of the steel plates sealing the post-cast strips of each exterior wall layer. The welds must be smooth and free of defects such as pores and slag inclusions. Any defects found must be repaired promptly. The weld height is generally close to that of the steel plate. When intermittent welding is used, the weld length and spacing must be uniform. When continuous welding is performed to seal the workpiece, the welds must be free of pores and sand holes. The weld height must not be less than the thickness of the steel plate.
[0014] Furthermore, the above-mentioned method for sealing the basement exterior wall with a steel plate is characterized in that, in step eight, the construction process of the mortar chamfering, waterproof additional layer, waterproof layer, and extruded board protective layer is as follows: first, the base layer is inspected and cleaned, then a 3.0+3.0 thick self-adhesive polymer modified asphalt membrane is laid, and finally a 50 thick XPS extruded polystyrene insulation board is pasted.
[0015] Furthermore, the above-mentioned method for sealing the basement exterior wall with a steel plate is characterized in that the specific construction method of step eight is as follows: (1) Clean up the debris remaining on the waterproof layer, check whether the waterproof layer has hollows, damage, cracks, etc., and report to the construction and supervision units in a timely manner; (2) Cold primer construction First, clean the qualified base layer and apply the treatment agent on it. The treatment agent should be sprayed evenly. After the base layer is dried, the waterproof membrane can be laid. (3) Laying of waterproof membrane The waterproofing membrane should be laid parallel or perpendicular to the ridge as required by the specification. We plan to lay the waterproofing membrane according to the actual situation of the grain warehouse, from low to high in the direction of the water flow, parallel to the ridge or out of the ridge. Before construction, the qualified base layer should be cleaned and the dust on the edges and corners should be blown away; Apply the base treatment agent evenly; After the base treatment agent dries, the parts of the roof waterproofing project that require additional layers should be treated according to the design requirements; Determine the order and direction of laying the coiled materials, mark the base layer, and then lay the coiled materials; Use a flame spray gun or a blowtorch to bake the angle between the bottom surface of the coil and the base layer. The blowtorch should be about 300mm away from the junction to liquefy the asphalt layer on the surface of the coil. Roll the coil forward while baking, and then use a pressure roller to press it to make it firmly bonded to the base layer or coil. Pay attention to the baking temperature and time so that the asphalt layer is in a molten state. The overlapping of coiled materials is carried out in the following manner: A. Long side overlap: The longitudinal overlap width of the roll material, single layer waterproofing ≥ 80mm, must be carefully operated, first melt the anti-adhesive layer and granular protective layer on the roll material to be overlapped, and at the same time melt the adhesive on both sides of the joint, then bond and exhaust, compact with a handheld roller, and there should be obvious asphalt strips; B. Short side overlap: Both ends of the roll must be fully bonded, and the overlap width of a single layer should be ≥100mm. The roll should be positioned and tested on the base layer. The roll laying plan should be determined according to the roll specifications, laying requirements, roof drainage slope, and detailed dimensions. C. When laying two adjacent rolls of materials on the same layer: the horizontal overlap should be staggered by more than 1500mm, and the upper and lower layers of rolls must not be pasted vertically to each other; the second waterproofing construction process is the same as the first layer, but it should be noted that the long side joints of the upper and lower layers of rolls should be staggered by at least one-third of the width, and the short side overlap joints should be staggered by at least 1.5m; D. Overlapping the short sides of the coiled material with slate sheets: It is necessary to remove the slate layer at the overlapping part. Heat the relevant part with a blowtorch on the coiled material and then scrape off the slate part with a trowel. After the roll material is laid, the overlapped parts, ends and the end parts of the roll material must be sealed. Sealing materials, sealing glue or cold bonding agent should be applied, and then smoothed to form a clear asphalt strip; (4) Finished product protection measures; After the first layer of roll material is laid and passed the inspection, protective measures should be taken for the waterproof layer; cross construction should be minimized to avoid damage to the waterproof layer; After the second layer of membrane is laid and passed the inspection, the subsequent construction process should try to avoid damaging the completed waterproof layer; (5) Before construction, the polystyrene foam board shall be laid out according to the design size of the entire exterior wall of the basement to achieve the purpose of saving materials and speeding up construction; the XPS extruded polystyrene insulation board shall be laid horizontally in the length direction to ensure continuous connection, and the upper and lower rows of boards shall be vertically staggered by 1 / 2 board length, and the local minimum staggered seam shall not be less than 200mm; the styrene foam board shall be pasted from the detailed nodes and the inner and outer corners to the middle; during construction, it is required to control the straightness of the basement exterior wall along the full height hanging line, and it is required to use the ink fountain to mark the bottom edge horizontal line and the 100mm control line in advance to ensure horizontal laying, and the laying in the section shall be carried out from bottom to top; (6) When laying, the XPS extruded polystyrene insulation board is directly pasted on the outer wall of the basement. During construction, the board seams should be squeezed tightly, the adjacent boards should be flush, the gap between the boards should not be greater than 2mm, and the height difference between the boards should not be greater than 1.5mm; cut the XPS extruded polystyrene insulation board according to the pre-arranged size (using an electric wire cutter or a paper cutter), and connect them vertically from the corners. The corners must be straight and complete along the full height of the building; (7) After the XPS extruded polystyrene insulation board is attached to the wall according to the above requirements, it should be repeatedly flattened with a 2m ruler to ensure its flatness and strong adhesion. The boards should be squeezed tightly together without any gaps; (8) The XPS extruded polystyrene insulation board at the opening of the embedded casing is not allowed to be pieced together with broken boards. It must be cut from a whole board. The cut edges must be straight, flat and square in size. Other joints should be more than 200mm away from the four sides of the opening.
[0016] Furthermore, the above-mentioned method for sealing the basement exterior wall with a steel plate is characterized in that, in step nine, the construction process of backfilling the basement exterior wall is as follows: cleaning the bottom of the foundation pit → inspecting the soil quality → spreading the soil in layers and raking it flat → tamping it to make it dense → leveling and acceptance.
[0017] Furthermore, the above-mentioned method for sealing the basement exterior wall with a steel plate is characterized in that the specific construction method of step nine is as follows: (1) Before filling, the garbage and debris at the bottom of the foundation pit should be cleaned up, and the loose soil, mortar, gravel, etc. that have fallen back should be removed; (2) Check whether the moisture content of the backfill soil is within the control range. If the moisture content is too high, measures such as loosening, airing or evenly mixing dry soil can be adopted; if the moisture content of the backfill soil is too low, measures such as pre-watering and moistening can be adopted; (3) The backfill soil should be spread in layers. The thickness of each layer should be determined according to the soil quality, density requirements and machine performance. Generally, the thickness of each layer of soil spread by a frog-type rammer is 200-250mm; the thickness of each layer of soil spread by manual rammer should not exceed 200mm. After each layer is spread, it should be raked flat. (4) Each layer of backfill soil should be rammed at least three times. The ramming should be done with one ram and half a ram. The ramming should be connected, row by row, vertically and horizontally. If conditions are insufficient, water can be used to make the soil sink, which is the so-called "water ramming" method. (5) Backfilling of foundation pit should be carried out simultaneously on two opposite sides or all four sides.
[0018] The present invention has the following beneficial effects: 1. The biggest feature of the steel plate sealing construction method of the basement exterior wall post-cast strip of the present invention is that both ends of the steel plate are fixed to the exterior wall surface with expansion screws, one end is a fixed end and the other end is a movable end, so as to meet the requirements of structural settlement and expansion.
[0019] 2. Compared with the traditional method of sealing the post-cast strip of the basement exterior wall, the present invention is more convenient for processing and manufacturing, and is also conducive to lifting and saving materials.
[0020] 3. The present invention provides a method for enclosing the basement exterior wall with a steel plate, which is used to solve the technical problems of low overall rigidity, low strength, easy deformation, poor anti-floating performance, cracking or collapse of such retaining structures in the prior art. Of course, any product implementing the present invention does not necessarily need to achieve all of the advantages described above at the same time. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0022] Figure 1 The present invention is a basement exterior wall post-casting strip steel plate sealing construction method Closed structure construction details; Figure 2 This is a detailed construction drawing of the steel plate facade of the present invention; Figure 3 This is a detailed construction drawing of the steel plate exterior wall junction of the present invention. DETAILED DESCRIPTION
[0023] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making any creative efforts shall fall within the scope of protection of the present invention.
[0024] See also Figure 1-3As shown, the present invention is a method for sealing the basement exterior wall with a steel plate, comprising the following steps: Step 1: Process the exterior wall post-casting strip sealing steel plate; A 3mm thick steel plate is used as the enclosing structure of the post-cast strip. Two C22 steel bars are welded to the steel plate on both sides at equal intervals along the length of the steel plate. The steel plate is fixed to the exterior wall with expansion screws at both ends of the post-cast strip, with one end being the fixed end and the other end being the movable end, to meet the requirements of structural settlement and expansion.
[0025] Step 2: Preparation before construction; Before construction, first locate and lay out the position of the steel plate that needs to be fixed in the post-casting strip to ensure that the position of the fixed steel plate is flat and vertical, calculate the number of steel bars, expansion bolts and tension screws required, and prepare materials in advance.
[0026] Step 3: Remove and clean up debris in the post-cast zone; When constructing the exterior wall, the deposited and loose concrete and floating slurry in the post-pouring zone should be chiseled out and cleaned first, especially the concrete and steel mesh on both sides of the waterstop steel plate must be cleaned and flushed with a water gun until the pouring conditions are met before proceeding to the next process.
[0027] Step 4: rust removal, repair, correction, tying or repair welding of steel bars; Rebar rust removal includes rust removal of all steel bars. After rust removal, use water to rinse the rust on the steel bars in the post-casting zone. After rust removal, the curved ones should be straightened. After acceptance by the supervision unit, the exterior wall post-casting zone steel bars should be poured immediately after rust removal and flushing. If pouring cannot be done in time, all steel bars should be rust-free again before pouring the exterior wall post-casting zone.
[0028] Step 5: Lifting and fixing of closed steel plate; The length of each closed steel plate is the height of a single-layer basement, unit: m, and it is hoisted to the post-casting zone of the exterior wall according to Figure 2 The method is to fix it on the outer wall of the basement.
[0029] Step 6: Repeat step 5 until the post-casting strip is completely closed; Continue to lift and fix the remaining closed steel plates until the entire post-casting strip is completely closed. After each steel plate is installed, perform a quick quality check to ensure that it is firmly fixed.
[0030] Step 7: Double-sided welding of the joints of the closed steel plates of the post-casting strip; Each exterior wall post-cast strip is welded on both sides at the joints of the sealed steel plates. The welds must be smooth and free of defects such as pores and slag inclusions. Any defects found must be repaired promptly. The weld height is generally close to the height of the steel plate. When using intermittent welding, the weld length and spacing should be uniform. When continuously welding sealed parts, the welds must be free of pores and sand holes. The weld height must not be less than the thickness of the steel plate.
[0031] Step 8: Perform waterproofing; The construction process of mortar chamfering, waterproof additional layer, waterproof layer, and extruded board protective layer is as follows: first, check and clean the base layer, then lay 3.0+3.0 thick self-adhesive polymer modified asphalt membrane, and finally paste 50 thick XPS extruded polystyrene insulation board; The specific construction methods are: (1) Clean up the debris remaining on the waterproof layer, check whether the waterproof layer has hollows, damage, cracks, etc., and report to the construction and supervision units in a timely manner; (2) Cold primer construction First, clean the qualified base layer and apply the treatment agent on it. The treatment agent should be sprayed evenly. After the base layer is dried, the waterproof membrane can be laid. (3) Laying of waterproof membrane The waterproofing membrane should be laid parallel or perpendicular to the ridge as required by the specification. We plan to lay the waterproofing membrane according to the actual situation of the grain warehouse, from low to high in the direction of the water flow, parallel to the ridge or out of the ridge. Before construction, the qualified base layer should be cleaned and the dust on the edges and corners should be blown away; Apply the base treatment agent evenly; After the base treatment agent dries, the parts of the roof waterproofing project that require additional layers should be treated according to the design requirements; Determine the order and direction of laying the coiled materials, mark the base layer, and then lay the coiled materials; Use a flame spray gun or a blowtorch to bake the angle between the bottom surface of the coil and the base layer. The blowtorch should be about 300mm away from the junction to liquefy the asphalt layer on the surface of the coil. Roll the coil forward while baking, and then use a pressure roller to press it to make it firmly bonded to the base layer or coil. Pay attention to the baking temperature and time so that the asphalt layer is in a molten state. The overlapping of coiled materials is carried out in the following manner: A. Long side overlap: The longitudinal overlap width of the roll material, single layer waterproofing ≥ 80mm, must be carefully operated, first melt the anti-adhesive layer and granular protective layer on the roll material to be overlapped, and at the same time melt the adhesive on both sides of the joint, then bond and exhaust, compact with a handheld roller, and there should be obvious asphalt strips; B. Short side overlap: Both ends of the roll must be fully bonded, and the overlap width of a single layer should be ≥100mm. The roll should be positioned and tested on the base layer. The roll laying plan should be determined according to the roll specifications, laying requirements, roof drainage slope, and detailed dimensions. C. When laying two adjacent rolls of materials on the same layer: the horizontal overlap should be staggered by more than 1500mm, and the upper and lower layers of rolls must not be pasted vertically to each other; the second waterproofing construction process is the same as the first layer, but it should be noted that the long side joints of the upper and lower layers of rolls should be staggered by at least one-third of the width, and the short side overlap joints should be staggered by at least 1.5m; D. Overlapping the short sides of the coiled material with slate sheets: It is necessary to remove the slate layer at the overlapping part. Heat the relevant part with a blowtorch on the coiled material and then scrape off the slate part with a trowel. After the roll material is laid, the overlapped parts, ends and the end parts of the roll material must be sealed. Sealing materials, sealing glue or cold bonding agent should be applied, and then smoothed to form a clear asphalt strip; (4) Finished product protection measures; After the first layer of roll material is laid and passed the inspection, protective measures should be taken for the waterproof layer; cross construction should be minimized to avoid damage to the waterproof layer; After the second layer of membrane is laid and passed the inspection, the subsequent construction process should try to avoid damaging the completed waterproof layer; (5) Before construction, the polystyrene foam board shall be laid out according to the design size of the entire exterior wall of the basement to achieve the purpose of saving materials and speeding up construction; the XPS extruded polystyrene insulation board shall be laid horizontally in the length direction to ensure continuous connection, and the upper and lower rows of boards shall be vertically staggered by 1 / 2 board length, and the local minimum staggered seam shall not be less than 200mm; the styrene foam board shall be pasted from the detailed nodes and the inner and outer corners to the middle; during construction, it is required to control the straightness of the basement exterior wall along the full height hanging line, and it is required to use the ink fountain to mark the bottom edge horizontal line and the 100mm control line in advance to ensure horizontal laying, and the laying in the section shall be carried out from bottom to top; (6) When laying, the XPS extruded polystyrene insulation board is directly pasted on the outer wall of the basement. During construction, the board seams should be squeezed tightly, the adjacent boards should be flush, the gap between the boards should not be greater than 2mm, and the height difference between the boards should not be greater than 1.5mm; cut the XPS extruded polystyrene insulation board according to the pre-arranged size, and connect it vertically from the corner with staggered seams. The corner should be straight and complete along the full height of the building; (7) After the XPS extruded polystyrene insulation board is attached to the wall according to the above requirements, it should be repeatedly flattened with a 2m ruler to ensure its flatness and strong adhesion. The boards should be squeezed tightly together without any gaps; (8) The XPS extruded polystyrene insulation board at the opening of the embedded casing is not allowed to be pieced together with broken boards. It must be cut from a whole board. The cut edges must be straight, flat and square in size. Other joints should be more than 200mm away from the four sides of the opening.
[0032] Step 9: Backfill construction of basement exterior wall; The construction process of backfilling the basement exterior wall is as follows: clean the foundation pit bottom → inspect the soil quality → spread the soil in layers and rake it flat → tamp and compact it → level and inspect; The specific construction methods are: (1) Before filling, the garbage and debris at the bottom of the foundation pit should be cleaned up, and the loose soil, mortar, gravel, etc. that have fallen back should be removed; (2) Check whether the moisture content of the backfill soil is within the control range. If the moisture content is too high, measures such as loosening, airing or evenly mixing dry soil can be adopted; if the moisture content of the backfill soil is too low, measures such as pre-watering and moistening can be adopted; (3) The backfill soil should be spread in layers. The thickness of each layer should be determined according to the soil quality, density requirements and machine performance. Generally, the thickness of each layer of soil spread by a frog-type rammer is 200-250mm; the thickness of each layer of soil spread by manual rammer should not exceed 200mm. After each layer is spread, it should be raked flat. (4) Each layer of backfill soil should be rammed at least three times. The ramming should be done with one ram and half a ram. The ramming should be connected, row by row, vertically and horizontally. If conditions are insufficient, water can be used to make the soil sink, which is the so-called "water ramming" method. (5) Backfilling of foundation pit should be carried out simultaneously on two opposite sides or all four sides.
[0033] Throughout this specification, references to terms such as "one embodiment," "example," or "specific example" indicate that the specific features, structures, materials, or characteristics described in conjunction with that embodiment or example are included in at least one embodiment or example of the present invention. In this specification, schematic representations of these terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
[0034] The preferred embodiments of the present invention disclosed above are intended only to help illustrate the present invention. These preferred embodiments do not exhaustively describe all details, nor do they limit the present invention to the specific embodiments described. Obviously, many modifications and variations are possible based on the content of this specification. These embodiments are selected and described in detail in this specification to better explain the principles and practical applications of the present invention, thereby enabling those skilled in the art to better understand and utilize the present invention. The present invention is limited only by the claims and their full scope and equivalents.
Claims
1. A method for enclosing the steel plate of the post-cast strip of the basement exterior wall. Features: The method comprises the following steps: Step 1: Process the closed steel plate of the exterior wall post-cast strip; Step 2: Preparation before construction; Step 3: Remove and clean up the debris in the post-casting zone; Step 4: Rust removal, repair, correction, tying or repair welding of steel bars; Step 5: Lifting and fixing of closed steel plate; Step 6: Repeat step 5 until the post-casting strip is completely closed; Step 7: Double-sided welding of the joints of the post-casting belt closed steel plates; Step 8: waterproofing; Step 9: Backfill construction of basement exterior wall.
2. A method for sealing the basement exterior wall post-cast strip with steel plate according to claim 1, It is characterized in that In step 1, a 3mm thick steel plate is used as the post-casting strip enclosing structure. Two C22 steel bars are welded to the steel plate on both sides at equal intervals along the length of the steel plate. The steel plate is fixed to the outer wall surface with expansion screws at both ends of the post-casting strip, one end is a fixed end, and the other end is a movable end, to meet the requirements of structural settlement and expansion; In step 2, before construction, first locate and lay out the position of the steel plate to be fixed in the post-casting belt to ensure that the position of the fixed steel plate is flat and vertical, calculate the number of steel bars, expansion bolts and tension screws to be used, and prepare materials in advance; In step three, when constructing the exterior wall, the deposited, loose concrete and floating slurry in the post-cast zone should be chiseled out and cleaned first, especially the concrete and steel mesh on both sides of the waterstop steel plate must be cleaned and flushed with a water gun until the pouring conditions are met before proceeding to the next process.
3. A method for sealing the basement exterior wall post-cast strip with steel plate according to claim 1, It is characterized in that In step 4, the steel bar rust removal includes all the steel bars rust removal. After rust removal, the steel bar rust in the post-casting strip is rinsed clean with water. After rust removal, the curved part should be straightened. After acceptance by the supervision unit, the exterior wall post-casting strip steel bar rust removal and flushing should be poured immediately. If it cannot be poured in time, all the steel bars should be rust-free again before pouring the exterior wall post-casting strip. In step 5, each section of closed steel plate is hoisted to the post-cast strip of the outer wall with a length equal to the height of the single-layer basement (unit: m) and fixed on the outer wall of the basement according to the method shown in Figure 2; In step six, step five is continuously repeated until the construction of the sealing steel plate of the exterior wall post-cast strip is completed.
4. A method for sealing the basement exterior wall post-cast strip with steel plate according to claim 1, It is characterized in that In step seven, double-sided welding is performed at the joints of the steel plates sealed by the post-cast strips of each layer of the exterior wall. The welds are required to be smooth during welding, and there must be no welding defects such as pores and slag inclusions. If defects are found, they must be repaired in time. The weld height is generally close to the steel plate. When intermittent welding is used, the weld length and interval should be uniform; when the sealing and continuous welding of the parts is performed, it is required that there should be no pores and sand eyes at the weld; when welding, the weld height must not be less than the thickness of the steel plate.
5. A method for sealing the basement exterior wall post-cast strip with steel plate according to claim 1, It is characterized in that In step eight, the construction process of mortar chamfering, waterproof additional layer, waterproof layer, and extruded board protective layer is to first inspect and clean the base layer, then lay 3.0+3.0 thick self-adhesive polymer modified asphalt membrane, and finally paste 50 thick XPS extruded polystyrene insulation board.
6. A method for sealing the basement exterior wall post-cast strip with steel plate according to claim 1, It is characterized in that Step 8 The specific construction method is: (1) Clean up the debris left on the waterproof layer, check whether the waterproof layer has hollows, damage, cracks, etc., and report to the construction and supervision units in a timely manner; (2) Cold primer construction First, clean the qualified base layer, and spray the treatment agent on the base layer. The treatment agent should be sprayed evenly. After the base layer is treated and dried, the waterproof membrane can be laid. (3) Laying of waterproof membrane The laying of waterproofing membranes should be parallel or perpendicular to the ridge according to the specification requirements. We plan to lay the waterproofing membranes according to the actual situation of the grain depot, from low to high in the direction of the water flow, parallel to the ridge or out of the ridge; Before construction, the qualified base layer should be cleaned and the dust on the edges and corners should be blown away; Apply the base treatment agent evenly; After the base treatment agent dries, the parts of the roof waterproofing project that require additional layers should be treated according to the design requirements; Determine the order and direction of laying the coiled materials, draw lines on the base layer, and then lay the coiled materials; Use a flame spray gun or a blowtorch to bake the angle between the bottom surface of the coil and the base layer. The blowtorch should be about 300mm away from the junction to liquefy the asphalt layer on the surface of the coil. Roll the coil forward while baking, and then use a pressure roller to press it to make it firmly bonded to the base layer or the coil. Pay attention to the baking temperature and time so that the asphalt layer is in a molten state. The overlapping of the coiled materials is carried out in the following manner: A. Long side overlap: The longitudinal overlap width of the roll material, single layer waterproofing ≥ 80mm, must be carefully operated, first melt the anti-adhesive layer and granular protective layer on the roll material to be overlapped, and melt the adhesive on both sides of the joint, then bond and exhaust, compact with a hand-held roller, and there should be obvious asphalt strips; B. Short side overlap: Both ends of the coiled material must be fully bonded, and the overlap width, single layer width should be ≥100mm. The coiled material should be positioned and tested on the base layer. The coiled material laying plan should be determined according to the coiled material specifications, laying requirements, roof drainage slope, and detailed dimensions; C. When laying two adjacent rolls of the same layer: the horizontal overlap should be staggered by more than 1500mm, and the upper and lower layers of rolls are prohibited from being pasted vertically to each other; the second waterproofing construction process is the same as the first waterproofing, but it should be noted that the long side joints of the upper and lower layers of rolls should be staggered by no less than one-third of the width, and the short side overlap joints should be staggered by no less than 1.5m; D. Overlapping the short sides of the coiled material with slate sheets: It is necessary to remove the slate layer at the overlapped part, determine the position on the coiled material, heat the relevant part with a blowtorch, and then scrape off the slate part with a trowel; After the roll material is laid, the overlapped parts, ends and the end parts of the roll material must be sealed. Sealing materials, sealing glue or cold bonding agent should be applied, and then smoothed to form obvious asphalt strips; (4) Finished product protection measures; After the first layer of roll material is laid and passed the inspection, protective measures should be taken for the waterproof layer; cross-construction should be minimized to avoid damage to the waterproof layer; After the second layer of coiled material is laid and passed the inspection, the subsequent construction process should try to avoid damaging the completed waterproof layer; (5) Before construction, the polystyrene foam board layout shall be carried out according to the design dimensions of the entire exterior wall of the basement to achieve the purpose of saving materials and speeding up construction; the XPS extruded polystyrene insulation board shall be laid horizontally in the length direction to ensure continuous connection, and the upper and lower rows of boards shall be vertically staggered by 1 / 2 board length, and the local minimum staggered seam shall not be less than 200mm; the pasting of the polystyrene foam board shall be carried out from the detailed nodes and the inner and outer corners to the middle; during construction, it is required to control the straightness of the basement exterior wall along the full height hanging line, and it is required to use the ink fountain to mark the bottom edge horizontal line and the 100mm control line in advance to ensure horizontal laying, and the laying in the section shall be carried out from bottom to top; (6) When laying, the XPS extruded polystyrene insulation board is directly pasted on the outer wall of the basement. During construction, the board seams should be squeezed tightly, the adjacent boards should be flush, the gap between the boards should not be greater than 2mm, and the height difference between the boards should not be greater than 1.5mm; cut the XPS extruded polystyrene insulation board according to the pre-arranged size, and connect it vertically from the corners. The corners are required to be straight and complete along the full height of the building; (7) After the XPS extruded polystyrene insulation board is pasted to the wall according to the above requirements, it should be repeatedly flattened with a 2m ruler to ensure its flatness and firm bonding. The boards should be squeezed tightly without any seams; (8) The XPS extruded polystyrene insulation board at the opening of the embedded casing is not allowed to be pieced together with broken boards. It must be cut from a whole board. The cut edges must be straight, flat, and square in size. Other joints should be greater than 200mm from the four sides of the opening.
7. A method for sealing the basement exterior wall post-cast strip with steel plate according to claim 1, It is characterized in that In step nine, the construction process of backfill soil for the basement exterior wall is to clean the bottom of the foundation pit → inspect the soil quality → spread the soil in layers and rake it flat → tamp it tightly → level and inspect.
8. A method for sealing the basement exterior wall post-cast strip with steel plate according to claim 1, It is characterized in that The specific construction method of step nine is: (1) Before filling, the garbage and debris at the bottom of the foundation pit should be cleaned up, and the loose soil, mortar, gravel, etc. that have fallen back should be removed; (2) Check whether the moisture content of the backfill soil is within the control range. If the moisture content is high, measures such as loosening, drying or evenly mixing dry soil can be adopted; if the moisture content of the backfill soil is low, measures such as pre-watering and moistening can be adopted; (3) Backfill soil should be spread in layers. The thickness of each layer of soil should be determined according to the soil quality, density requirements and machine performance. Generally, the thickness of each layer of soil laid by a frog-type tamping machine is 200-250mm; the thickness of manual tamping is not more than 200mm. After each layer is spread, it should be raked flat. (4) Each layer of backfill soil should be tamped at least three times. The tamping should be done with one tamping and a half tamping. The tamping should be done in a continuous manner, row by row, vertically and horizontally. If conditions are insufficient, water can be used to make the soil sink. This is the so-called "water tamping" method. (5) Backfilling of foundation pit should be carried out simultaneously on two opposite sides or all four sides.