Monitoring method and system applied to foundation pit engineering

By employing data acquisition, cloud platform processing, and automated early warning systems in foundation pit engineering, the problems of unreal-time monitoring and insufficient accuracy in existing technologies have been solved, achieving efficient and accurate construction safety monitoring and early warning, thus ensuring construction safety and project quality.

CN119021286APending Publication Date: 2024-11-26SHANGHAI CHENGYU ENVIRONMENTAL PROTECTION ENGINEERING CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411104380.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-13
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

Existing foundation pit engineering monitoring technologies cannot achieve high-frequency, high-precision real-time monitoring, and cannot effectively prevent construction safety risks. Furthermore, conventional manual monitoring methods are limited by equipment and environmental conditions, making it difficult to meet the needs of complex engineering conditions.

Method used

Data acquisition equipment is used to collect data on the foundation pit and its surrounding environment in real time. The data is then processed and analyzed through a cloud platform to generate a detection report. A data judgment device is used to identify abnormal data and trigger an early warning, thereby achieving automated monitoring and early warning.

Benefits of technology

It enables real-time and continuous monitoring of foundation pit projects, timely detection of abnormalities and issuance of early warnings, reduces construction safety risks, improves monitoring efficiency and accuracy, and supports the optimization of construction plans and safety management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021286A_ABST
    Figure CN119021286A_ABST
Patent Text Reader

Abstract

The invention provides a monitoring method and system applied to foundation pit engineering. The monitoring system mainly comprises data acquisition equipment, data transmission equipment, a cloud platform and a data judgment device, the invention mainly aims to improve the safety of engineering, improve the monitoring efficiency and precision, promote informatization construction and reduce the monitoring cost. Through the automatic monitoring and data analysis technology, the foundation pit monitoring system provides powerful support for safe construction of foundation pit engineering.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building construction monitoring, and in particular to a monitoring method and system for foundation pit engineering. Background Art

[0002] With the acceleration of urbanization and the increasing number of construction projects, the urban environment surrounding construction sites is becoming increasingly complex, necessitating greater attention to the adverse impacts of construction on surrounding municipal facilities, housing, and the environment. Foundation pit excavation is a major hazard during construction. Accidents can result in serious consequences such as cracking, leakage, collapse, landslides, and casualties.

[0003] Therefore, the background technology of the foundation pit engineering monitoring system is mainly based on the following requirements:

[0004] Improve monitoring technology:

[0005] In order to further promote the upgrading of the construction industry and take digital reform as the driving force, it is necessary to effectively promote "intelligent defense of urban underground space", improve the level of deep foundation pit monitoring technology at construction sites, and ensure the safety of deep foundation pit projects and surrounding environments.

[0006] Meet complex engineering conditions:

[0007] Foundation pit construction conditions are complex and pose significant safety risks. Conventional manual monitoring methods, constrained by measurement equipment and working conditions, cannot achieve high-frequency, high-precision monitoring. Therefore, advanced, reliable instruments and effective monitoring methods are needed to monitor the foundation pit retaining system and surrounding environment.

[0008] Ensure construction safety:

[0009] During foundation pit excavation, soil properties and the stress conditions of the support structure are constantly changing. To prevent damage to the surrounding environment and the foundation pit support itself, real-time online monitoring is necessary to provide data and information support to scientifically guide construction, reasonably modify designs, or promptly implement construction technical measures.

[0010] Promoting information-based construction:

[0011] The automated foundation pit monitoring system primarily consists of four components: the sensor side, the data collection side, the platform side, and the application side. Front-end sensors collect data in real time, while the data collection side performs data denoising and calculations, and transmits the data to a cloud server via the network. All data is verified by the gateway and displayed on the cloud platform. Multiple cloud platform accounts are available for user data viewing and analysis. This automated monitoring technology, based on the Internet of Things and cloud computing, integrates the collection and analysis of monitoring data into an intelligent information management system, significantly promoting information-based construction. Summary of the Invention

[0012] A monitoring method for foundation pit engineering, characterized in that the method comprises:

[0013] S1: The data acquisition equipment collects various monitoring data of the foundation pit and the surrounding environment in real time, performs preliminary processing on the collected data, and converts the data into a transmission format;

[0014] S2: The data transmission device transmits the collected data to the cloud platform, and the cloud platform stores the data through the data storage device;

[0015] S3: The data processing and analysis device in the cloud platform analyzes and processes the data in the data storage device, generates a test report, and transmits the test report to the data judgment device;

[0016] S4: The data judgment device analyzes the detection report. If there is any abnormality in the detection report, the abnormal data is transmitted to the early warning device, and the early warning device transmits the abnormal data to relevant personnel.

[0017] Preferably, the data acquisition equipment collects various detection data of the foundation pit and the surrounding environment in real time, performs preliminary processing on the collected data, and converts the data into a transmission format, including:

[0018] S11: The data acquisition device collects various monitoring data of the foundation pit and the surrounding environment in real time, including settlement, tilt, cracks, soil pressure, and groundwater level, and sets parameters for the data acquisition device, including the acquisition range and acquisition frequency;

[0019] S12: The data acquisition device performs preliminary processing on the collected data and converts the data into a transmission format. The preliminary data processing includes data cleaning, data verification and data compression.

[0020] Preferably, the data transmission device transmits the collected data to the cloud platform, and the cloud platform stores the data through a data storage device, including:

[0021] S21: The data transmission device uploads the collected data to the cloud platform, and the cloud platform pre-processes the data, including data sorting and data formatting;

[0022] S22: The cloud platform transmits the pre-processed data to a data storage device, and the data storage device stores the data.

[0023] Preferably, the data processing and analysis device in the cloud platform analyzes and processes the data in the data storage device, generates a test report, and transmits the test report to the data judgment device, including:

[0024] S31: The data processing and analysis device analyzes the data in the data storage device and obtains final analysis data, wherein the data analysis includes the settlement and horizontal displacement of the foundation pit slope top, the surrounding surface settlement, the groundwater level, and soil parameters;

[0025] S32: The data processing and analysis device generates a test report based on the analysis results, and transmits the test report to the data judgment device.

[0026] Preferably, the data judgment device analyzes the test report, and if there is an abnormality in the test report, transmits the abnormal data to the early warning device, and the early warning device transmits the abnormal data to relevant personnel, including:

[0027] S41: The data judgment device analyzes the test report. If there is any abnormality in the test report, the abnormal data is transmitted to the early warning device;

[0028] S42: The early warning device issues a warning, and relevant personnel review and judge the abnormal data after receiving the alarm from the early warning device;

[0029] S43: After the relevant personnel complete the verification of the abnormal data, the abnormal event processing device is activated and the abnormal event processing personnel are notified. After the abnormal event processing personnel responds to the abnormal event processing device, they further process the abnormal event;

[0030] S44: The recording device records the abnormal event and stores it in the abnormal event record library.

[0031] A monitoring device used in foundation pit engineering, characterized in that the device comprises:

[0032] Data acquisition equipment: The data acquisition equipment collects various monitoring data of the foundation pit and the surrounding environment in real time, performs preliminary processing on the collected data, and converts the data into a transmission format;

[0033] Data transmission equipment: The data transmission equipment transmits the collected data to the cloud platform, and the cloud platform stores the data through a data storage device;

[0034] Cloud platform: The data processing and analysis device in the cloud platform analyzes and processes the data in the data storage device, generates a test report, and transmits the test report to the data judgment device;

[0035] Data judgment device: The data judgment device analyzes the test report. If there is any abnormality in the test report, the abnormal data is transmitted to the early warning device, and the early warning device transmits the abnormal data to relevant personnel.

[0036] Preferably, the data acquisition device includes:

[0037] Data acquisition device: The data acquisition device collects various monitoring data of the foundation pit and the surrounding environment in real time, including settlement, tilt, cracks, soil pressure and groundwater level, and sets parameters for the data acquisition device, including the acquisition range and acquisition frequency;

[0038] Data processing device: The data acquisition device performs preliminary processing on the collected data and converts the data into a transmission format. The preliminary data processing includes data cleaning, data verification and data compression.

[0039] Preferably, the data transmission device includes:

[0040] Data preprocessing device: The data transmission device uploads the collected data to the cloud platform, and the cloud platform preprocesses the data, including data sorting and data formatting;

[0041] Data storage device: The cloud platform transmits the pre-processed data to the data storage device, which stores the data.

[0042] Preferably, the cloud platform includes:

[0043] Data processing and analysis device: The data processing and analysis device analyzes the data in the data storage device and obtains the final analysis data, wherein the data analysis includes the settlement and horizontal displacement of the foundation pit slope top, the surrounding surface settlement, the groundwater level and the soil parameters;

[0044] Data transmission device: The data processing and analysis device generates a test report based on the analysis results and transmits the test report to the data judgment device.

[0045] Preferably, the data judgment device includes:

[0046] Test report analysis device: The data judgment device analyzes the test report. If there is any abnormality in the test report, the abnormal data will be transmitted to the early warning device;

[0047] Early warning device: The early warning device issues a warning, and relevant personnel review and judge the abnormal data after receiving the alarm from the early warning device;

[0048] Abnormal event processing device: After the relevant personnel complete the verification of abnormal data, the abnormal event processing device is activated and the abnormal event processing personnel are notified. After the abnormal event processing personnel respond to the abnormal event processing device, they further handle the abnormal event;

[0049] Recording device: The recording device records the abnormal event and stores it in the abnormal event record library.

[0050] The present invention provides the following beneficial effects: The monitoring system can continuously collect real-time data on key parameters during foundation pit construction, such as displacement, settlement, stress, earth pressure, and groundwater level. By analyzing this data in real time, the system can promptly detect anomalies and issue warning signals, enabling construction managers to quickly respond and take measures to prevent accidents from occurring or escalating. Foundation pit excavation is one of the riskiest operations in civil engineering, and even the slightest carelessness can lead to serious accidents such as collapses and landslides. The use of a monitoring system can significantly reduce safety risks during construction, ensuring the safety of construction workers and the surrounding environment by promptly identifying and addressing potential safety hazards. Monitoring data not only provides safety warnings but also provides an important basis for optimizing construction plans. By comparing actual monitoring data with expected values ​​in the design plan, construction managers can evaluate construction results and promptly adjust construction plans and parameter settings to achieve better results and economic benefits. The stability of foundation pit construction directly impacts the quality and safety of the entire building. The use of a monitoring system can ensure the stability of the foundation pit during construction, preventing structural damage caused by displacement and settlement, thereby improving the quality of the entire project. The monitoring system automatically records and stores large amounts of monitoring data, which is of great value for project acceptance, post-construction maintenance, and scientific research. Data analysis allows for the assessment of the long-term stability of foundation pit projects, making the foundation pit monitoring system a crucial component of information-based construction. By integrating information technology tools such as sensors, data acquisition equipment, data transmission networks, and analytical software into the monitoring system, intelligent management and control of foundation pit construction can be achieved, improving both efficiency and accuracy. BRIEF DESCRIPTION OF THE DRAWINGS

[0051] Figure 1 The monitoring method of the foundation pit engineering of the present invention DETAILED DESCRIPTION

[0052] The preferred embodiments of the present invention are described below with reference to the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.

[0053] One embodiment of the present invention provides a monitoring method for foundation pit engineering, characterized in that the method comprises:

[0054] S1: The data acquisition equipment collects various monitoring data of the foundation pit and the surrounding environment in real time, performs preliminary processing on the collected data, and converts the data into a transmission format;

[0055] S2: The data transmission device transmits the collected data to the cloud platform, and the cloud platform stores the data through the data storage device;

[0056] S3: The data processing and analysis device in the cloud platform analyzes and processes the data in the data storage device, generates a test report, and transmits the test report to the data judgment device;

[0057] S4: The data judgment device analyzes the detection report. If there is any abnormality in the detection report, the abnormal data is transmitted to the early warning device, and the early warning device transmits the abnormal data to relevant personnel.

[0058] The working principle and advantages of the above technical solution are as follows: First, high-precision sensors are deployed at key locations throughout the foundation pit, including the retaining structure, support system, and groundwater level. These sensors can sense and measure various physical quantities, such as displacement, deformation, stress, strain, temperature, and water level. The received raw data is cleaned, de-noised, and calibrated to improve its accuracy and reliability. Furthermore, the data is time-synchronized and format-standardized to facilitate subsequent analysis and comparison. The sensors convert the sensed physical quantities into electrical or digital signals and transmit them to a monitor or data acquisition unit via internal circuitry or interfaces. The monitor or data acquisition unit is responsible for preliminary signal processing and uses wireless communication equipment, including 4G / 5G modules, to transmit the monitoring data from the monitor or data acquisition unit in real time to a remote data center or engineer's terminal device. This process typically involves data encoding, encryption, and compression to ensure fast and secure data transmission. The data center or engineer's terminal device receives and stores the transmitted monitoring data and then uses specialized data analysis software or platforms to perform multi-dimensional analysis on the processed data. This includes statistical analysis, trend analysis, spectrum analysis, and model prediction to reveal the deformation patterns, stability status, and potential risk factors of foundation pit projects. Preset thresholds for various monitoring parameters are determined based on the project's design requirements, geological conditions, and construction conditions. These thresholds typically represent safety boundaries or risk warning points for the project. The system compares monitoring data with pre-set thresholds in real time. If a parameter exceeds a threshold, an alert mechanism is immediately triggered. Alerts are sent to engineering personnel via various channels, including sound, light, text messages, and emails. The system also automatically records alert information and generates alert reports, providing a basis for subsequent accident investigation and response. The foundation pit monitoring system monitors key parameters of the foundation pit, such as displacement, settlement, tilt, and stress, in real time, ensuring real-time and accurate data. If a parameter is detected to be abnormal or exceeds a pre-set threshold, the system immediately issues an alert, prompting engineering personnel to take timely action and effectively prevent accidents. The system utilizes automated technology to automatically monitor and collect data from the foundation pit, significantly improving monitoring efficiency and accuracy. This reduces the potential for manual intervention and human error, thereby lowering labor costs. The sensors and data acquisition devices used in the monitoring system have undergone rigorous quality testing and reliability assessments to ensure the accuracy and reliability of the monitoring data. The system also features data backup and recovery capabilities to ensure data security and integrity. The system utilizes visualization technology to present monitoring data graphically, facilitating intuitive analysis and processing. This improves the efficiency and accuracy of data interpretation, helping engineers better understand the stability of foundation pit projects. Through real-time monitoring and early warning capabilities, the foundation pit monitoring system can promptly identify potential safety hazards and take appropriate measures to address them.This helps reduce risks during the construction process and minimizes personal injuries and economic losses caused by safety accidents.

[0059] In one embodiment of the present invention, the data acquisition device collects various detection data of the foundation pit and the surrounding environment in real time, performs preliminary processing on the collected data, and converts the data into a transmission format, including:

[0060] S11: The data acquisition device collects various monitoring data of the foundation pit and the surrounding environment in real time, including settlement, tilt, cracks, soil pressure, and groundwater level, and sets parameters for the data acquisition device, including the acquisition range and acquisition frequency;

[0061] S12: The data acquisition device performs preliminary processing on the collected data and converts the data into a transmission format. The preliminary data processing includes data cleaning, data verification and data compression.

[0062] The working principle and advantages of the above technical solution are as follows: Various sensors, such as displacement sensors, settlement sensors, earth pressure sensors, and water level sensors, are strategically placed within the foundation pit and its surroundings. These sensors can sense physical quantities in the environment, such as displacement, settlement, earth pressure, and water level, in real time. The sensors convert the sensed quantities into electrical or digital signals and transmit them to a data acquisition device via wired or wireless means. The data acquisition device receives these signals at a specific sampling frequency and converts them into a processable data format. The collected raw data may contain interference factors such as noise and outliers, which require data cleaning to remove these interference factors and improve data accuracy and reliability. The cleaned data is converted into a format suitable for subsequent processing and analysis. This includes standardizing data units and converting data types. To reduce bandwidth and storage requirements for data transmission, data compression can be performed. Compressed data retains the original information while being smaller and easier to transmit and store. The processed data is then converted into a format suitable for transmission. This typically involves encapsulating the data into a specific data packet or message format to maintain data integrity and consistency during transmission. Data acquisition equipment can collect data in real time and perform immediate preliminary processing, allowing engineering personnel to quickly obtain the latest status information on the foundation pit and its surroundings. This immediate feedback helps to promptly identify potential problems and implement appropriate countermeasures. Real-time data acquisition makes the monitoring process of foundation pit projects a dynamic one, enabling continuous and uninterrupted monitoring of changes in the pit, improving the continuity and accuracy of monitoring. Modern data acquisition equipment generally features high precision and stability, accurately capturing various test data on the foundation pit and its surroundings. This helps reduce data errors and improve data reliability. Preliminary processing, such as data cleaning and conversion, can further reduce noise and outliers in the data, improving data accuracy and usability. Data acquisition equipment typically has powerful data processing capabilities, enabling rapid preliminary processing of collected data and converting it into a format suitable for transmission. This reduces processing time before data transmission and improves work efficiency. Data acquisition equipment is generally flexible and adaptable, adaptable to different foundation pit project environments and monitoring requirements, helping to meet the diverse monitoring needs of foundation pit projects.

[0063] In one embodiment of the present invention, a data transmission device transmits collected data to a cloud platform, and the cloud platform stores the data through a data storage device, including:

[0064] S21: The data transmission device uploads the collected data to the cloud platform, and the cloud platform pre-processes the data, including data sorting and data formatting;

[0065] S22: The cloud platform transmits the pre-processed data to a data storage device, and the data storage device stores the data.

[0066] The working principle and advantages of the above technical solution are as follows: The cloud platform parses received data packets, extracts valid data, and converts it into a format recognizable within the cloud platform. This step typically involves data decoding, format conversion, and verification. The cloud platform stores the processed data using data storage devices. These storage devices typically feature high capacity, high reliability, and high scalability. The cloud platform employs specific data structures to organize the stored data. These data structures support fast data retrieval and query operations, and ensure data consistency and integrity. To prevent data loss or corruption, the cloud platform regularly backs up stored data and develops appropriate data recovery strategies. In the event of data loss or corruption, the backup data can be used to restore normal system operations. Data transmission devices typically have high-speed transmission capabilities, enabling rapid transmission of collected data to the cloud platform. The cloud platform, through its robust network architecture and server performance, ensures efficient and stable data transmission. The cloud platform supports parallel processing, enabling simultaneous processing of data streams from multiple data transmission devices, significantly improving data processing and storage efficiency. The cloud platform also offers elastic scalability, automatically adjusting resource allocation based on changing data storage needs. As data volume increases, the cloud platform automatically increases storage resources to ensure smooth data storage. The cloud platform supports multiple deployment options, including public, private, and hybrid clouds. Users can choose the appropriate deployment method based on their needs, enabling flexible data storage and management. The cloud platform regularly backs up stored data to prevent data loss or corruption. In the event of data loss or corruption, the backup data can be used to quickly restore normal system operations. Users can remotely access the cloud platform via the internet to view and manage stored data. This convenience allows users to access the information they need anytime, anywhere, improving work efficiency. The cloud platform provides a unified management interface and tools, allowing users to easily manage and maintain stored data. This reduces management costs and improves management efficiency.

[0067] In one embodiment of the present invention, a data processing and analysis device in a cloud platform analyzes and processes data in a data storage device, generates a test report, and transmits the test report to a data judgment device, including:

[0068] S31: The data processing and analysis device analyzes the data in the data storage device and obtains final analysis data, wherein the data analysis includes the settlement and horizontal displacement of the foundation pit slope top, the surrounding surface settlement, the groundwater level, and soil parameters;

[0069] S32: The data processing and analysis device generates a test report based on the analysis results, and transmits the test report to the data judgment device.

[0070] The working principle and advantages of the above technical solution are as follows: An appropriate analysis algorithm is selected based on the characteristics of the foundation pit data and the analysis requirements. The preprocessed data is input into the selected algorithm for analysis. The analysis process may include various methods such as data clustering, classification, regression, and time series analysis to reveal hidden information and patterns in the foundation pit data. The algorithm output is then interpreted to assess the stability, safety, and potential risks of the foundation pit structure. Based on the data analysis results, a detailed inspection report is compiled. The report should include the data analysis method, process, results, conclusions, and recommendations. Relevant charts, images, and other supporting materials are also included. The generated inspection report undergoes a quality review to ensure its accuracy and completeness. The generated inspection report is sent to the data judgment device via a secure transmission mechanism. The data judgment device receives the inspection report transmitted from the cloud platform and performs parsing. Based on pre-set rules and algorithms, the data in the inspection report is further judged and analyzed. Based on the judgment results, the data judgment device generates corresponding feedback or response information. The cloud platform's powerful computing and data processing capabilities enable rapid processing and analysis of large amounts of foundation pit data, significantly reducing data processing time. The cloud platform's excavation data processing and analysis device utilizes advanced intelligent algorithms to deeply uncover hidden insights and patterns within excavation data, enhancing the accuracy and reliability of analysis. The cloud platform receives and processes excavation data from data storage devices in real time, ensuring its timeliness and accuracy. Efficient and accurate data processing and analysis provide strong support for the safety monitoring and management of excavation projects, improving project quality and efficiency.

[0071] In one embodiment of the present invention, the data judgment device analyzes the test report and transmits the abnormal data to the early warning device if the test report is abnormal. The early warning device transmits the abnormal data to relevant personnel, including:

[0072] S41: The data judgment device analyzes the test report. If there is any abnormality in the test report, the abnormal data is transmitted to the early warning device;

[0073] S42: The early warning device issues a warning, and relevant personnel review and judge the abnormal data after receiving the alarm from the early warning device;

[0074] S43: After the relevant personnel complete the verification of the abnormal data, the abnormal event processing device is activated and the abnormal event processing personnel are notified. After the abnormal event processing personnel responds to the abnormal event processing device, they further process the abnormal event;

[0075] S44: The recording device records the abnormal event and stores it in the abnormal event record library.

[0076] In foundation pit monitoring, a key monitoring target is the displacement of the support structure. The foundation pit monitoring device collects support structure displacement data in real time, inputs the calculated warning threshold into the monitoring system, and configures a corresponding warning mechanism. When the monitoring data reaches or exceeds the preset warning threshold, the system automatically triggers the corresponding level of warning and notifies relevant personnel to take appropriate measures, including:

[0077] Step 1: The foundation pit monitoring device collects the displacement data of the supporting structure in real time, and performs statistical analysis based on the historical monitoring data of the displacement of the supporting structure to determine the mean and standard deviation of the data, and obtains them through the following formula:

[0078]

[0079] Among them, m represents the average value of the historical monitoring data of the displacement of the supporting structure, s represents the standard deviation of the historical monitoring data of the displacement of the supporting structure, and x i represents the historical displacement value of a single support structure, n represents the number of measurements, and the displacement of the support structure can be obtained by the following formula:

[0080]

[0081] Where F represents the horizontal force acting on the support structure, L represents the length of the support structure, A represents the cross-sectional area of ​​the support structure, and k represents the soil-support structure interaction coefficient. The soil-support structure interaction coefficient is a parameter used to describe the interaction strength between the support structure and the surrounding soil. It is related to the soil properties. Good soil properties indicate high soil cohesion and a low Poisson's ratio, while poor soil properties indicate low soil cohesion and a high Poisson's ratio. When the soil properties are good, the value of k is smaller, and when the soil properties are poor, the value of k is larger.

[0082] Step 2: The early warning device sets three alarms according to the displacement, including primary alarm, intermediate alarm and high alarm, and the calculation formula of the alarm is as follows:

[0083] y1=m+z1×s

[0084] y2=m+z2×s

[0085] y3=m+z3×s

[0086] Wherein, y1 represents the primary alarm threshold, z1 represents the primary alarm coefficient set by the early warning device, y2 represents the intermediate alarm threshold, z2 represents the intermediate alarm coefficient set by the early warning device, y3 represents the advanced alarm threshold, z3 represents the advanced alarm coefficient set by the early warning device;

[0087] Step 3: When x<y1, the early warning device does not sound an alarm;

[0088] When x>y1, the early warning device issues a primary alarm;

[0089] When y1<x<y2, the early warning device issues a medium-level alarm;

[0090] When y2<x<y3, the early warning device issues a high-level alarm;

[0091] Wherein, x represents the displacement data of the supporting structure collected in real time by the foundation pit monitoring device.

[0092] The working principle and advantages of the above technical solution are as follows: The data judgment device first receives the test report generated by the foundation pit data processing and analysis device. The intelligent analysis module built into the data judgment device automatically analyzes the received test report. During the analysis process, the data judgment device identifies abnormal data or abnormal conditions in the test report based on preset anomaly detection rules or algorithms. These abnormal conditions include data outside the normal range, sudden changes in trends, and increased risk levels. Once an abnormal condition is detected, the data judgment device immediately marks the abnormal data and extracts relevant abnormal information, including the type of abnormality, time of occurrence, and scope of impact. The data judgment device then transmits the marked abnormal data and related information to the early warning device via the internal network or a pre-set data transmission channel. The early warning device conducts further risk assessment on the received abnormal data to determine its urgency and potential impact. Based on the assessment results, the early warning device determines the corresponding warning level, including general warning and emergency warning. Based on the determined warning level, the early warning device generates a corresponding warning message and promptly sends it to relevant personnel. The warning message should include detailed information about the abnormal data, risk assessment results, recommended response measures, and emergency contact information. Relevant personnel promptly receive and review warning messages from the early warning device. After receiving the warning message, they further analyze and assess the anomaly to confirm its authenticity and severity. Based on the recommended countermeasures provided in the warning message and their own experience, they develop specific response measures and decision-making plans. Based on their analysis and decision-making, relevant personnel will promptly take action to address the anomaly. These actions may include on-site inspections, emergency repairs, adjustments to construction plans, and evacuation, minimizing the impact of the anomaly on the pit structure and personnel safety. When an anomaly is detected in the test report, the data judgment device quickly identifies and transmits the anomaly data to the early warning device, which in turn immediately communicates the anomaly information to relevant personnel. This rapid response mechanism helps identify problems promptly and reduces potential risks caused by delayed resolution. The automated and intelligent processing process significantly improves the efficiency of data processing and transmission. Compared to manual judgment and processing, this method can more quickly identify, evaluate, and transmit anomaly data, saving valuable time for subsequent response measures. The data judgment device uses intelligent algorithms to analyze the test report, enabling more accurate identification of anomalies. This algorithm-based analysis method is more objective and accurate than manual judgment, reducing human interference. During data transmission, multiple verification mechanisms, such as data encryption and integrity checks, may be implemented to ensure the accuracy and reliability of abnormal data. This ensures that when abnormal data reaches the relevant personnel, its accuracy and reliability are effectively guaranteed. Data judgment and early warning devices can comprehensively monitor foundation pit inspection reports and provide real-time monitoring of key indicators.This allows any anomaly to be detected and addressed promptly, regardless of where or when it occurs. The early warning device transmits the anomaly data to relevant personnel, who can then formulate countermeasures based on the anomaly data and their own experience. This data-driven decision-making approach is more scientific and accurate, helping to improve decision-making efficiency and quality. The timely identification and transmission of anomaly data allows for more rational allocation of resources, such as personnel, equipment, and supplies. This allows for the rapid mobilization of necessary resources to address anomalies, improving efficiency and effectiveness.

[0093] One embodiment of the present invention provides a monitoring device for use in foundation pit engineering, characterized in that the device comprises:

[0094] Data acquisition equipment: The data acquisition equipment collects various monitoring data of the foundation pit and the surrounding environment in real time, performs preliminary processing on the collected data, and converts the data into a transmission format;

[0095] Data transmission equipment: The data transmission equipment transmits the collected data to the cloud platform, and the cloud platform stores the data through a data storage device;

[0096] Cloud platform: The data processing and analysis device in the cloud platform analyzes and processes the data in the data storage device, generates a test report, and transmits the test report to the data judgment device;

[0097] Data judgment device: The data judgment device analyzes the test report. If there is any abnormality in the test report, the abnormal data is transmitted to the early warning device, and the early warning device transmits the abnormal data to relevant personnel.

[0098] The monitoring device used in the foundation pit project conducts a detailed survey of the project site and uses data acquisition equipment to collect data. Based on the on-site survey results and in combination with factors such as the foundation pit excavation depth, shape, area, and surrounding environment, an appropriate solution is selected from the database, including:

[0099] Step 1: The monitoring device obtains geological parameters around the foundation pit and inputs independent variables, and obtains an evaluation grade based on the independent variables and geological parameters. The independent variables include the length, width and depth of the foundation pit, the depth of the underground pipeline, and the slope of the land;

[0100] Step 2: The calculation formula of the evaluation level is as follows:

[0101] P1=f×cosθ×W

[0102] Where P1 represents the first evaluation level, f represents the bearing capacity of the soil where the foundation pit is located, W represents the soil permeability coefficient, W is a constant obtained through experiments, and θ represents the slope of the land surface;

[0103] And, f is obtained by the following formula:

[0104] f=f0+η b γ(b-3)+η d γ m (d-0.5)

[0105] Among them, f represents the actual value of the soil bearing capacity, f0 represents the soil bearing capacity of the foundation bottom, η b The foundation bearing capacity correction factor representing the foundation width, η d The foundation bearing capacity correction factor representing the embedment depth, η b and η d Obtained from the engineering safety technical disclosure table 5.2.4, γ represents the weight of the soil below the foundation bottom, γ m represents the weighted average density of each layer of soil above the foundation bottom surface by height, b represents the length of the smaller side of the foundation pit, and the value range is [3,6], d represents the burial depth of the foundation pit. In the above description, the foundation bottom surface refers to the bottom plane where the foundation of the foundation pit structure is in direct contact with the foundation soil, and γ m The calculation formula is as follows:

[0106]

[0107] Among them, γ i represents the bulk density of the i-th layer of soil, and hi represents the thickness of the i-th layer of soil.

[0108] The soil permeability coefficient refers to the measure of the ability of water to penetrate a unit area in a unit time. In the present invention, the soil permeability coefficient is obtained through a permeability test, which includes a penetration test, in which the rate of liquid infiltration in the soil is measured and the average permeability rate is calculated through multiple tests; and a pore irrigation test, in which water is injected into the soil pores, the change in the water level in the soil is measured over a certain period of time, and the soil permeability coefficient is calculated using the formula. The calculation formula is as follows:

[0109]

[0110] Where Q represents the volume of water passing through the soil, A represents the cross-sectional area of ​​water passing through the soil, L represents the vertical distance of water passing through the soil, and T represents the time of water passing through the soil.

[0111] The monitoring device obtains the depth d1 of the underground pipeline, and d<d1, obtains the shape, material, size, and construction period parameters of the foundation pit, and obtains the second judgment level P2 based on the parameters;

[0112] Step 3: The monitoring device selects construction plans that meet the conditions in the database according to P1 and P2, and presents the specific implementation plan to relevant personnel.

[0113] The working principles and advantages of the above technical solution are as follows: Soil sampling and testing are performed using geological exploration tools (such as drills and samplers). The surrounding environment is accurately measured using measuring instruments. Detailed site survey drawings are drawn and survey data is recorded. Sensors are strategically placed within the foundation pit support structure and surrounding environment. Sensor data is monitored in real time to ensure data continuity and accuracy. Preliminary processing, such as filtering and denoising, is performed on the collected data to improve data quality. A database containing various foundation pit technical solutions and case studies is established. These solutions should be categorized and organized according to different geological conditions, pit dimensions, and surrounding environments. Based on the site survey results and real-time data collected, the database is searched for solutions that match the current foundation pit engineering conditions. Multiple candidate solutions are evaluated and compared using algorithms or expert systems to select the optimal solution. Detailed site surveys and data collection provide accurate information about the foundation pit and its surrounding environment, such as geological conditions, groundwater levels, and the condition of surrounding buildings. This data provides a solid foundation for selecting a monitoring solution. Based on the specific characteristics of the foundation pit and surrounding environmental conditions, the monitoring plans selected from the database are more targeted and personalized, better meeting the needs of foundation pit monitoring. By analyzing and processing monitoring data, engineers can more accurately understand the actual conditions during foundation pit construction, providing strong support for construction design and decision-making. This helps optimize construction plans and improve construction efficiency and quality. The accumulation and analysis of monitoring data also provides an important basis for the continuous improvement of foundation pit construction technology. Through in-depth analysis of monitoring data, problems and deficiencies in construction can be identified and targeted improvement measures can be proposed.

[0114] In one embodiment of the present invention, the data acquisition device includes:

[0115] Data acquisition device: The data acquisition device collects various monitoring data of the foundation pit and the surrounding environment in real time, including settlement, tilt, cracks, soil pressure and groundwater level, and sets parameters for the data acquisition device, including the acquisition range and acquisition frequency;

[0116] Data processing device: The data acquisition device performs preliminary processing on the collected data and converts the data into a transmission format. The preliminary data processing includes data cleaning, data verification and data compression.

[0117] The working principle and advantages of the above technical solution are as follows: Various sensors, such as displacement sensors, settlement sensors, earth pressure sensors, and water level sensors, are strategically placed within the foundation pit and its surroundings. These sensors can sense physical quantities in the environment, such as displacement, settlement, earth pressure, and water level, in real time. The sensors convert the sensed quantities into electrical or digital signals and transmit them to a data acquisition device via wired or wireless means. The data acquisition device receives these signals at a specific sampling frequency and converts them into a processable data format. The collected raw data may contain interference factors such as noise and outliers, which require data cleaning to remove these interference factors and improve data accuracy and reliability. The cleaned data is converted into a format suitable for subsequent processing and analysis. This includes standardizing data units and converting data types. To reduce bandwidth and storage requirements for data transmission, data compression can be performed. Compressed data retains the original information while being smaller and easier to transmit and store. The processed data is then converted into a format suitable for transmission. This typically involves encapsulating the data into a specific data packet or message format to maintain data integrity and consistency during transmission. Data acquisition equipment can collect data in real time and perform immediate preliminary processing, allowing engineering personnel to quickly obtain the latest status information on the foundation pit and its surroundings. This immediate feedback helps to promptly identify potential problems and implement appropriate countermeasures. Real-time data acquisition makes the monitoring process of foundation pit projects a dynamic one, enabling continuous and uninterrupted monitoring of changes in the pit, improving the continuity and accuracy of monitoring. Modern data acquisition equipment generally features high precision and stability, accurately capturing various test data on the foundation pit and its surroundings. This helps reduce data errors and improve data reliability. Preliminary processing, such as data cleaning and conversion, can further reduce noise and outliers in the data, improving data accuracy and usability. Data acquisition equipment typically has powerful data processing capabilities, enabling rapid preliminary processing of collected data and converting it into a format suitable for transmission. This reduces processing time before data transmission and improves work efficiency. Data acquisition equipment is generally flexible and adaptable, adaptable to different foundation pit project environments and monitoring requirements, helping to meet the diverse monitoring needs of foundation pit projects.

[0118] In one embodiment of the present invention, the data transmission device includes:

[0119] Data preprocessing device: The data transmission device uploads the collected data to the cloud platform, and the cloud platform preprocesses the data, including data sorting and data formatting;

[0120] Data storage device: The cloud platform transmits the pre-processed data to the data storage device, which stores the data.

[0121] The working principle and advantages of the above technical solution are as follows: The cloud platform parses received data packets, extracts valid data, and converts it into a format recognizable within the cloud platform. This step typically involves data decoding, format conversion, and verification. The cloud platform stores the processed data using data storage devices. These storage devices typically feature high capacity, high reliability, and high scalability. The cloud platform employs specific data structures to organize the stored data. These data structures support fast data retrieval and query operations, and ensure data consistency and integrity. To prevent data loss or corruption, the cloud platform regularly backs up stored data and develops appropriate data recovery strategies. In the event of data loss or corruption, the backup data can be used to restore normal system operations. Data transmission devices typically have high-speed transmission capabilities, enabling rapid transmission of collected data to the cloud platform. The cloud platform, through its robust network architecture and server performance, ensures efficient and stable data transmission. The cloud platform supports parallel processing, enabling simultaneous processing of data streams from multiple data transmission devices, significantly improving data processing and storage efficiency. The cloud platform also offers elastic scalability, automatically adjusting resource allocation based on changing data storage needs. As data volume increases, the cloud platform automatically increases storage resources to ensure smooth data storage. The cloud platform supports multiple deployment options, including public, private, and hybrid clouds. Users can choose the appropriate deployment method based on their needs, enabling flexible data storage and management. The cloud platform regularly backs up stored data to prevent data loss or corruption. In the event of data loss or corruption, the backup data can be used to quickly restore normal system operations. Users can remotely access the cloud platform via the internet to view and manage stored data. This convenience allows users to access the information they need anytime, anywhere, improving work efficiency. The cloud platform provides a unified management interface and tools, allowing users to easily manage and maintain stored data. This reduces management costs and improves management efficiency.

[0122] In one embodiment of the present invention, the cloud platform includes:

[0123] Data processing and analysis device: The data processing and analysis device analyzes the data in the data storage device and obtains the final analysis data, wherein the data analysis includes the settlement and horizontal displacement of the foundation pit slope top, the surrounding surface settlement, the groundwater level and the soil parameters;

[0124] Data transmission device: The data processing and analysis device generates a test report based on the analysis results and transmits the test report to the data judgment device.

[0125] The working principle and advantages of the above technical solution are as follows: An appropriate analysis algorithm is selected based on the characteristics of the foundation pit data and the analysis requirements. The preprocessed data is input into the selected algorithm for analysis. The analysis process may include various methods such as data clustering, classification, regression, and time series analysis to reveal hidden information and patterns in the foundation pit data. The algorithm output is then interpreted to assess the stability, safety, and potential risks of the foundation pit structure. Based on the data analysis results, a detailed inspection report is compiled. The report should include the data analysis method, process, results, conclusions, and recommendations. Relevant charts, images, and other supporting materials are also included. The generated inspection report undergoes a quality review to ensure its accuracy and completeness. The generated inspection report is sent to the data judgment device via a secure transmission mechanism. The data judgment device receives the inspection report transmitted from the cloud platform and parses it. Based on pre-set rules and algorithms, the data in the inspection report is further judged and analyzed. Based on the judgment results, the data judgment device generates corresponding feedback or response information. The cloud platform's powerful computing and data processing capabilities enable rapid processing and analysis of large amounts of foundation pit data, significantly reducing data processing time. The cloud platform's excavation data processing and analysis device utilizes advanced intelligent algorithms to deeply uncover hidden insights and patterns within excavation data, enhancing the accuracy and reliability of analysis. The cloud platform receives and processes excavation data from data storage devices in real time, ensuring its timeliness and accuracy. Efficient and accurate data processing and analysis provide strong support for the safety monitoring and management of excavation projects, improving project quality and efficiency.

[0126] In one embodiment of the present invention, the data determination device includes:

[0127] Test report analysis device: The data judgment device analyzes the test report. If there is any abnormality in the test report, the abnormal data will be transmitted to the early warning device;

[0128] Early warning device: The early warning device issues a warning, and relevant personnel review and judge the abnormal data after receiving the alarm from the early warning device;

[0129] Abnormal event processing device: After the relevant personnel complete the verification of abnormal data, the abnormal event processing device is activated and the abnormal event processing personnel are notified. After the abnormal event processing personnel respond to the abnormal event processing device, they further handle the abnormal event;

[0130] Recording device: The recording device records the abnormal event and stores it in the abnormal event record library.

[0131] The working principle and advantages of the above technical solution are as follows: The data judgment device first receives the test report generated by the foundation pit data processing and analysis device. The intelligent analysis module built into the data judgment device automatically analyzes the received test report. During the analysis process, the data judgment device identifies abnormal data or abnormal conditions in the test report based on preset anomaly detection rules or algorithms. These abnormal conditions include data outside the normal range, sudden changes in trends, and increased risk levels. Once an abnormal condition is detected, the data judgment device immediately marks the abnormal data and extracts relevant abnormal information, including the type of abnormality, time of occurrence, and scope of impact. The data judgment device then transmits the marked abnormal data and related information to the early warning device via the internal network or a pre-set data transmission channel. The early warning device conducts further risk assessment on the received abnormal data to determine its urgency and potential impact. Based on the assessment results, the early warning device determines the corresponding warning level, including general warning and emergency warning. Based on the determined warning level, the early warning device generates a corresponding warning message and promptly sends it to relevant personnel. The warning message should include detailed information about the abnormal data, risk assessment results, recommended response measures, and emergency contact information. Relevant personnel promptly receive and review warning messages from the early warning device. After receiving the warning message, they further analyze and assess the anomaly to confirm its authenticity and severity. Based on the recommended countermeasures provided in the warning message and their own experience, they develop specific response measures and decision-making plans. Based on their analysis and decision-making, relevant personnel will promptly take action to address the anomaly. These actions may include on-site inspections, emergency repairs, adjustments to construction plans, and evacuation, minimizing the impact of the anomaly on the pit structure and personnel safety. When an anomaly is detected in the test report, the data judgment device quickly identifies and transmits the anomaly data to the early warning device, which in turn immediately communicates the anomaly information to relevant personnel. This rapid response mechanism helps identify problems promptly and reduces potential risks caused by delayed resolution. The automated and intelligent processing process significantly improves the efficiency of data processing and transmission. Compared to manual judgment and processing, this method can more quickly identify, evaluate, and transmit anomaly data, saving valuable time for subsequent response measures. The data judgment device uses intelligent algorithms to analyze the test report, enabling more accurate identification of anomalies. This algorithm-based analysis method is more objective and accurate than manual judgment, reducing human interference. During data transmission, multiple verification mechanisms, such as data encryption and integrity checks, may be implemented to ensure the accuracy and reliability of abnormal data. This ensures that when abnormal data reaches the relevant personnel, its accuracy and reliability are effectively guaranteed. Data judgment and early warning devices can comprehensively monitor foundation pit inspection reports and provide real-time monitoring of key indicators.This allows any anomaly to be detected and addressed promptly, regardless of where or when it occurs. The early warning device transmits the anomaly data to relevant personnel, who can then formulate countermeasures based on the anomaly data and their own experience. This data-driven decision-making approach is more scientific and accurate, helping to improve decision-making efficiency and quality. The timely identification and transmission of anomaly data allows for more rational allocation of resources, such as personnel, equipment, and supplies. This allows for the rapid mobilization of necessary resources to address anomalies, improving efficiency and effectiveness.

[0132] Obviously, those skilled in the art may make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if such changes and modifications fall within the scope of the claims and their equivalents, the present invention is intended to include such changes and modifications.

Claims

1. A monitoring method used in foundation pit engineering, It is characterized in that The method comprises: S1: The data acquisition equipment collects various monitoring data of the foundation pit and the surrounding environment in real time, performs preliminary processing on the collected data, and converts the data into a transmission format; S2: The data transmission device transmits the collected data to the cloud platform, and the cloud platform stores the data through a data storage device; S3: The data processing and analysis device in the cloud platform analyzes and processes the data in the data storage device, generates a test report, and transmits the test report to the data judgment device; S4: The data judgment device analyzes the detection report. If there is an abnormality in the detection report, the abnormal data is transmitted to the early warning device, and the early warning device transmits the abnormal data to relevant personnel.

2. A monitoring method for foundation pit engineering according to claim 1, It is characterized in that The data acquisition equipment collects various monitoring data of the foundation pit and the surrounding environment in real time, performs preliminary processing on the collected data, and converts the data into a transmission format, including: S11: The data acquisition device collects various detection data of the foundation pit and the surrounding environment in real time, wherein the various detection data include settlement, tilt, cracks, soil pressure and groundwater level, and sets parameters for the data acquisition device, wherein the parameter settings include a collection range and a collection frequency; S12: The data acquisition device performs preliminary processing on the collected data and converts the data after preliminary processing into a transmission format. The preliminary data processing includes data cleaning, data verification and data compression.

3. A monitoring method for foundation pit engineering according to claim 1, It is characterized in that The data transmission device transmits the collected data to the cloud platform, and the cloud platform stores the data through a data storage device, including: S21: The data transmission device uploads the collected data to the cloud platform, and the cloud platform preprocesses the uploaded data, wherein the preprocessing includes data sorting and data formatting; S22: The cloud platform transmits the pre-processed data to a data storage device, and the data storage device stores the data.

4. A monitoring method for foundation pit engineering according to claim 1, It is characterized in that The data processing and analysis device in the cloud platform analyzes and processes the data in the data storage device, generates a test report, and transmits the test report to the data judgment device, including: S31: the data processing and analysis device analyzes the data in the data storage device and obtains final analysis data, wherein the data analysis includes the settlement and horizontal displacement of the foundation pit top, the surrounding surface settlement, the groundwater level and soil parameters; S32: The data processing and analyzing device generates a test report according to the analysis result, and transmits the test report to the data judgment device.

5. A monitoring method for foundation pit engineering according to claim 1, It is characterized in that The data judgment device analyzes the test report, and if the test report is abnormal, transmits the abnormal data to the early warning device, and the early warning device transmits the abnormal data to relevant personnel, including: S41: The data judgment device analyzes the test report, and if the test report is abnormal, transmits the abnormal data to the early warning device; S42: The early warning device issues a warning, and after receiving the alarm from the early warning device, the relevant personnel review and judge the abnormal data; S43: After the relevant personnel complete the verification of the abnormal data, the abnormal event processing device is started and the abnormal event processing personnel are notified. After the abnormal event processing personnel respond to the abnormal event processing device, the abnormal event is further processed; S44: The recording device records the abnormal event and stores it in the abnormal event record library.

6. A monitoring device used in foundation pit engineering, It is characterized in that The device comprises: Data acquisition equipment: The data acquisition equipment collects various monitoring data of the foundation pit and the surrounding environment in real time, performs preliminary processing on the collected data, and converts the data into a transmission format; Data transmission equipment: the data transmission equipment transmits the collected data to the cloud platform, and the cloud platform stores the data through the data storage device; Cloud platform: The data processing and analysis device in the cloud platform analyzes and processes the data in the data storage device, generates a test report, and transmits the test report to the data judgment device; Data judgment device: The data judgment device analyzes the test report. If there is an abnormality in the test report, the abnormal data is transmitted to the early warning device, and the early warning device transmits the abnormal data to relevant personnel.

7. A monitoring device for foundation pit engineering according to claim 6, It is characterized in that The data acquisition device comprises: Data acquisition device: The data acquisition device collects various detection data of the foundation pit and the surrounding environment in real time, including settlement, tilt, cracks, soil pressure and groundwater level, and sets parameters for the data acquisition device, including the acquisition range and acquisition frequency; Data processing device: The data acquisition device performs preliminary processing on the collected data and converts the preliminarily processed data into a transmission format. The preliminary data processing includes data cleaning, data verification and data compression.

8. A monitoring device for foundation pit engineering according to claim 6, It is characterized in that The data transmission device comprises: Data preprocessing device: The data transmission device uploads the collected data to the cloud platform, and the cloud platform preprocesses the uploaded data, and the preprocessing includes data sorting and data formatting; Data storage device: The cloud platform transmits the pre-processed data to the data storage device, and the data storage device stores the data.

9. A monitoring device for foundation pit engineering according to claim 6, It is characterized in that The cloud platform includes: Data processing and analysis device: The data processing and analysis device analyzes the data in the data storage device and obtains the final analysis data, wherein the data analysis includes the settlement and horizontal displacement of the foundation pit slope top, the surrounding surface settlement, the groundwater level and the soil parameters; Data transmission device: The data processing and analysis device generates a test report based on the analysis results and transmits the test report to the data judgment device.

10. A monitoring device for foundation pit engineering according to claim 6, It is characterized in that The data judgment device comprises: Test report analysis device: The data judgment device analyzes the test report. If there is an abnormality in the test report, the abnormal data is transmitted to the early warning device; Early warning device: the early warning device issues a warning, and relevant personnel review and judge the abnormal data after receiving the alarm from the early warning device; Abnormal event processing device: After the relevant personnel complete the verification of abnormal data, the abnormal event processing device is started and the abnormal event processing personnel are notified. After the abnormal event processing personnel respond to the abnormal event processing device, they further process the abnormal event; Recording device: The recording device records the abnormal event and stores it in the abnormal event record library.