Rapid installation and construction method for cantilever scaffold
Through the positioning and bearing capacity conduction components of the vertical pole positioning member and the top support combination, the problems of process stopping and bearing capacity conduction deviation in the construction of cantilever scaffolding are solved, and the independent stress and construction safety of cantilever members are improved , simplifies the construction process.
Patent Information
- Application Number
- CN202311135260.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-05
- Publication Date
- 2024-11-26
AI Technical Summary
The existing cantilever scaffolding construction methods have problems such as process stopping, repeated disassembly of external protective frames, and load-bearing capacity transmission deviation, resulting in low construction efficiency and high safety risks.
The positioning and bearing capacity conduction components are adopted for the combination of the upright pole positioning member and the top support to support the cantilever member and lock the upright pole positioning member to form an independent stress-bearing structure to avoid the erection of temporary frames above the cantilever layer and Demolition to ensure accurate load transmission and structural safety.
It realizes that the cantilever members participate in the load-bearing capacity sharing without adjusting the upper and lower frames, reduces the load of the lower frames, improves construction safety and efficiency, avoids repeated disassembly of the external protective frame, and maintains the normal operation of the scaffolding. performance.
Smart Images

Figure CN119021451A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to a building construction method, and in particular relates to a cantilever scaffolding rapid installation construction method. Background Art
[0002] At present, during the construction of high-rise buildings, a complete external safety protection system should be set up, usually using cantilever scaffolding. According to the project construction requirements, the concrete structure must reach a certain strength before installing the I-beam at the bottom of the cantilever scaffolding on the cantilever floor side beam side. Therefore, working conditions, structural strength, safety protection, construction period, etc. often require a suitable working method to balance the relationship between the parties. The current construction measures are mainly divided into two categories: the first category, when constructing the cantilever layer, only an external protective frame 1.8m beyond the working surface is erected on the basis of the lower frame to ensure the safety of the operation. After the floor construction is completed and the concrete structure strength meets the requirements for the installation of I-beams, the 1.8m external protective frame is removed to complete the cantilever external frame construction. After the upper pull or lower support structure is completed, the I-beam lower top return measure is cancelled, and it takes about 10 days to wait for the concrete to reach the strength; the second category, when constructing the cantilever layer, the external protective frame below the cantilever layer continues to be extended upward. After the concrete structure strength of the cantilever layer meets the requirements for the installation of I-beams, the extra external protective frame installed above the cantilever layer is removed, and the external frame construction starts again from the cantilever layer. While maintaining a normal construction rhythm, the lower frame of the cantilever layer needs to be additionally equipped with two and a half layers of protective frames, which increases the safety hazard of the lower frame, and relevant content needs to be considered in the calculation. Summary of the invention
[0003] The purpose of the present invention is to provide a cantilever scaffolding rapid installation construction method to overcome the shortcomings of the prior art such as process downtime, repeated erection and dismantling of external protective frames, and load-bearing capacity conduction deviation.
[0004] The technical solution adopted to achieve the purpose of the present invention is as follows: The invention provides a method for rapid installation and construction of a cantilever scaffold, comprising adopting a positioning and load-bearing force transmission component composed of a vertical pole positioning piece and a top support; firstly, the cantilever component is supported on a lower frame body by the top support, and then the upper frame body is supported on the cantilever component by the vertical pole positioning piece and locked with the top support; after the cantilever component is fixed on the cantilever layer, the top support is separated from the vertical pole positioning piece, thereby separating the cantilever component and the upper frame body from the lower frame body, so that the cantilever component forms an independent force-bearing structure supporting the upper frame body.
[0005] The top support includes a screw threadedly connected to the top end of the vertical pole of the lower frame and an upper groove arranged at the end of the screw; the vertical pole positioning piece includes an insertion rod matched with the bottom end of the vertical pole of the upper frame and a lower groove arranged at the bottom end of the insertion rod.
[0006] The cantilever member includes an I-beam fixed to the structural beam and plate of the floor structure through a back steel pad and anchor bolts.
[0007] The top support is arranged on the vertical pole of the lower frame through a screw rod, the I-beam of the cantilever member is supported on the vertical pole of the lower frame through the upper groove of the top support, the vertical pole of the upper frame is supported on the I-beam through the insertion rod and the lower groove of the vertical pole positioning piece, and the lower groove of the vertical pole positioning piece and the upper groove of the top support are locked by bolts. Beneficial Effects
[0008] Compared with the traditional construction method, the present invention has the following advantages: 1. In this method, after the cantilever member is placed on the top bracket of the positioning and load-bearing force transmission component, it plays a role in force transmission. By locking the vertical pole positioning piece connected to the upper frame and the top bracket connected to the lower frame, the load of the upper frame can be accurately transferred to the lower frame, and the external protection frame can continue to be erected. Through this measure, the erection and dismantling of temporary frames above the cantilever layer can be avoided for the sake of structural construction safety before the cantilever member is installed; 2. After the cantilever components are fixed to the floor structure, without adjusting the upper and lower frames, the cantilever components of the cantilever layer can participate in sharing the vertical bearing capacity, which can reduce the load borne by the lower frame and provide better safety protection for the lower frame; 3. After the upper frame system is formed and reaches the condition of independently bearing load, the upper and lower frames can be separated very conveniently, so that the cantilever components form an independent force-bearing structure and maintain the normal working performance of each section of the scaffolding.
[0009] The technical solution of the present invention is further described below in conjunction with the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0010] Figure 1 It is a cross-sectional view of the cantilever scaffolding in the present invention.
[0011] Figure 2 It is a structural schematic diagram of the cantilever member I-beam and the positioning and load-bearing force transmission components in the cantilever scaffolding.
[0012] In the figure: 1-cantilever member; 11-I-beam; 12-back steel pad; 13-anchor bolt; 2-diagonal tie rod assembly; 21-high-strength bolt; 22-round steel; 23-basket adjustment pipe; 24-connecting plate; 3-positioning and load-bearing transmission component; 31-vertical pole positioning piece; 311-insertion rod; 312-lower slot; 32-bolt; 33-top support; 331-upper slot; 332-screw; 4-lower frame; 41-vertical pole; 5-upper frame; 51-edge protection frame of structural construction working layer; 52-safety net; 53-vertical pole; 6-floor structure; 61-structural column; 62-structural beam and plate. DETAILED DESCRIPTION
[0013] See Figure 1 —— Figure 2 The cantilever scaffolding rapid installation construction method provided by the present invention includes installing the floor structure 6 of the cantilever scaffolding, the cantilever member 1 constituting the cantilever scaffolding, the inclined rod assembly 2, the positioning and bearing force transmission component 3, the lower frame 4, and the upper frame 5.
[0014] The floor structure 6 includes structural columns 61 , structural beams, and plates 62 .
[0015] The lower frame 4 includes a vertical rod 41 .
[0016] The upper frame 5 includes a structural construction working layer edge protection frame 51, a safety net 52, and a vertical pole 53; The cantilever member 1 includes an I-beam 11 fixed to the structural beam and plate 62 of the floor structure 6 through a back steel pad 12 and anchor bolts 13.
[0017] The diagonal brace assembly includes a connecting rod 22 that connects the structural beam of the floor structure 6, the plate 62 and the I-beam 11 through high-strength bolts 21 and connecting plates 24, and a basket adjustment pipe 23 that connects the two connecting rods 22 through threads.
[0018] The positioning and load-bearing force transmission component 3 includes a combined vertical pole positioning member 31 and a top support 33, and a bolt 32 that locks the top support 33 and the vertical pole positioning member 31. The top support 33 includes a screw rod 332 threadedly connected to the top end of the vertical pole of the lower frame 4 and an upper groove 331 provided at the end of the screw rod 332 and capable of cooperating with the cantilever component 1; the vertical pole positioning member 31 includes an insertion rod 311 cooperating with the bottom end of the vertical pole of the upper frame 5 and a lower groove 312 provided at the bottom end of the insertion rod 311 and capable of cooperating with the cantilever component 1.
[0019] See Figure 1 —— Figure 2 , the method of the present invention comprises the following steps: Step 1: After the construction of the floor structure 6 of the cantilevered layer N-1 is completed, the lower frame 4 is erected, which specifically includes: 1.1 Base treatment of the lower frame 4: Place the base of the vertical pole 41 of the lower frame 4 below the cantilever layer N on the concrete basement top plate of the cantilever layer N-1 or on the I-beam 11 of the cantilever member 1 to ensure that the basic bearing capacity of the entire cantilever scaffolding meets the specifications and design requirements; 1.2 Positioning of the vertical pole 41 of the lower frame 4: According to the drawings and the pre-set installation position of the I-beam 11 on the cantilever layer N, set the corresponding position of the vertical pole 41 of the lower frame 4 to ensure that the top support 33 on the top of the vertical pole 41 is located on the same vertical plane as the I-beam 11 and the vertical pole positioning piece 31; Step 2: Before the construction of the floor structure 6 of the cantilever layer N, the cantilever member 1, the positioning and the bearing force transmission component 3 are installed on the lower frame 4, which specifically includes: 2.1 Erection of the lower frame 4: The lower frame 4 is erected in accordance with the design plan and specification requirements. When the lower frame 4 is erected to the bottom elevation of the I-beam 11 of the cantilever layer N is 300mm, the erection upwards is stopped; 2.2 Install the top support 33 and the vertical pole positioning piece 31 on the I-beam 11 to form a bearing capacity node: first insert the top support 33 at the top of the inner and outer rows of vertical poles 41 of the lower frame 4, then place the I-beam 11 in the upper groove 331 of the top support 33, and finally place the vertical pole positioning piece 31 on the upper part of the I-beam 11, so that the lower groove 312 of the positioning piece 31 is stuck on the I-beam 11 and cooperates with the upper groove 331 of the top support 33 to wrap the I-beam 11, and the upper groove 331 of the top support 33 and the vertical pole positioning piece are fixed. The lower groove 312 of 31 is locked with bolts 32, so that the top support 33 and the vertical pole positioning piece 31 are fixed on the I-beam 11 to form a bearing capacity node. A wooden wedge can be embedded between the waist plate of the I-beam 11 and the upper groove 331 of the top support 33 and the lower groove 312 of the vertical pole positioning piece 31 to further fix the top support 33 and the vertical pole positioning piece 31; at this time, the distance between the I-beam 11 and the outer side of the structural beam 62 of the cantilever layer N to be constructed is 200mm, which ensures the subsequent structural construction work space; The inner and outer rows of the upper frame 5 are installed and positioned by using the pole positioning piece 31, and the inner and outer rows of the poles 41 and the top support 33 of the lower frame 4 are used to support the I-beam 11 of the cantilever member 1 and the upper frame 5 on the I-beam 11; the top support 33 and the pole positioning piece 31 are locked to ensure that the upper frame 5 and the lower frame 4 above and below the I-beam 11 at the bearing capacity node effectively transmit the vertical bearing capacity, so as to prevent the cantilever scaffold from being offset or tilted during the subsequent installation process; Step 3: During the construction of the floor structure 6 of the cantilever layer N, the upper frame 5 on the cantilever member 1 is erected, which specifically includes: 3.1 Erection of the upper frame 5 on the cantilevered layer N: The upper frame 5 on the cantilevered layer N is erected according to the design plan and specification requirements, and the inner and outer rows of vertical poles 53 of the upper frame 5 are installed and fixed on the vertical pole positioning pieces 31 on the I-beam 11. Since the I-beam 11 has not been fixed on the structural beam 62 on the cantilevered layer N at this time, during the construction of the floor structure of the cantilevered layer N, only the basic height requirement of 1.8m for the outer protective frame 51 is met; Step 4: After the construction of the floor structure 6 of the cantilevered layer N is completed, the upper frame 5 is continued to be erected, the cantilevered member 1 is installed on the cantilevered layer N, and the structural floors are constructed cyclically until the inclined rod assembly 2 is set between the cantilevered member 1 and the floor structure of the cantilevered layer N+1, which specifically includes: 4.1 Pre-embedded anchor bolts 13: 4*M20 anchor bolts 13 are pre-embedded in the structural beams and plates 62 of the cantilever layer N to connect the I-beam 11 to the structural beams and plates 62; the pre-embedded anchor bolts are divided into the form of pre-embedded anchor bolts in the structure and reserved beam sleeves according to the width of the structural beams and plates 62. At this time, the steel anchor plate at one end of the I-beam 11 against the wall or the structural beam and plate 62 is 200mm away from the outside of the structural beam and plate 62. The position of the reserved holes on the steel anchor plate needs to be accurately compared to ensure the accuracy of pre-embedded anchor bolts 13; 4.2 Adjustment of I-beam 11 and erection of upper frame 5: After the pouring of cantilever layer N structure is completed, measurement and setting out, column reinforcement installation, and lifting of steel pipes of inner support frame will be started on the second day. After completing this part of the task, the concrete strength of cantilever layer N reaches 5Mpa (about 20 hours), and the side formwork can be removed; loosen the bolts 32 of the top support 33 and the vertical pole positioning piece 31, adjust the position of I-beam 11 one by one, move it closer to the structural beam and plate 62 of cantilever layer N, and initially fix it with the anchor bolts 13, and tighten the bolts 32 of the top support 33 and the vertical pole positioning piece 31; if the concrete strength does not meet the requirements, move the I-beam 11 into place and temporarily put it aside, continue to erect the upper frame 5 of cantilever layer N, and continue to construct the floor structure 6 of cantilever layer N+1; 4.3 Fixing I-beam 11: When the concrete strength of cantilever layer N reaches 10Mpa (2-3 days), fix I-beam 11. During installation, the tightening torque of anchor bolt 13 must reach 117N•m. The tightening of anchor bolt 13 is an important control point for the installation of I-beam 11. The tightening should be completed in 24 hours in the first tightening, 50% tightening, and final tightening. When I-beam 11 is tightened with anchor bolt 13, square gasket must be used, and then the nut is tightened. 4.4 Install the inclined brace assembly 2: After the outer formwork is removed and the concrete strength reaches above 20Mpa, the inclined brace assembly 2 can be installed when the scaffolding frame is erected at a height of 3 layers. The inclined brace assembly 2 includes a connecting plate 24 provided on the I-beam 11 of the cantilever layer N as the lower hanging point, an embedded bolt 21 provided on the cantilever layer N+1 structure as the upper hanging point, two tie rods 22 connecting the upper and lower hanging points by bolts, and a basket adjustment tube 23 provided between the two tie rods 22; the basket adjustment tube 23 is adjusted to unload the tie rod 22. Before the inclined brace assembly 2 is installed, it is forbidden to stack materials and perform operations on the upper scaffold 5; Step 5, separating the positioning and load-bearing force transmission components 3 between the upper frame 5 and the lower frame 4 on the cantilevered layer N cantilevered member 1, so that the cantilevered member 1 forms an independent force-bearing structure, specifically including: 5.1 Separate the upper frame 5 and the vertical pole 41 of the lower frame 4 on the cantilevered layer N I-beam 11: loosen the bolt 32 between the top support 33 and the vertical pole positioning piece 31, reduce the protruding height of the top support 33 on the vertical pole 41, separate the upper frame 5 and the vertical pole 41 of the lower frame 4 on the I-beam 11 at this point, and make the I-beam 11 form an independent force-bearing structure.
[0020] The pole positioning member 31 in the present invention can also be made of existing pole latches welded with thin steel plates on both sides, and other parts are all existing scaffolds or existing components, which can simplify the processing procedures of the cantilever scaffold.
[0021] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the installation form and load conduction form of the present invention should be included in the protection scope of the present invention.
Claims
1. A cantilever scaffolding rapid installation construction method, characterized in that It includes a positioning and load-bearing force transmission component composed of a vertical pole positioning piece and a top support; the cantilever component is first supported on the lower frame by the top support, and then the upper frame is supported on the cantilever component by the vertical pole positioning piece and locked with the top support. When the cantilever component is fixed on the cantilever layer, the top support is separated from the vertical pole positioning piece, thereby separating the cantilever component and the upper frame from the lower frame, so that the cantilever component forms an independent force-bearing structure supporting the upper frame.
2. The cantilever scaffolding rapid installation construction method according to claim 1 is characterized by: The top support includes a screw threadedly connected to the top end of the vertical pole of the lower frame and an upper groove arranged at the end of the screw; the vertical pole positioning piece includes an insertion rod matched with the bottom end of the vertical pole of the upper frame and a lower groove arranged at the bottom end of the insertion rod.
3. The cantilever scaffolding rapid installation construction method according to claim 2 is characterized by: The cantilever member includes an I-beam fixed to the structural beam and plate of the floor structure through a back steel pad and anchor bolts.
4. The cantilever scaffolding rapid installation construction method according to claim 3 is characterized by: The top support is arranged on the vertical pole of the lower frame through a screw rod, the I-beam of the cantilever member is supported on the vertical pole of the lower frame through the upper groove of the top support, the vertical pole of the upper frame is supported on the I-beam through the insertion rod and the lower groove of the vertical pole positioning piece, and the lower groove of the vertical pole positioning piece and the upper groove of the top support are locked by bolts.
Citation Information
Patent Citations
Disc buckle type scaffold component suitable for tower crane wall-attached rod
CN114961225A
Novel bolt connection adjustable square steel tube cantilever scaffold and construction method
CN116623926A
Quick positioning device for profile steel builder's jack upright
CN203684642U
Beam-side pre-buried I-steel beam cantilever scaffold positioning safety supporting assembly
CN212984603U
Supporting scaffold
KR1020140079004A