Novel floating coupling and drifting method
By setting the impact sleeve and shear pin in the floating coupling, the cracking disk is broken by using the pressure difference, and the pump injection pressure is reduced by the isolation liquid and soluble dowels, the failure of the rupture disk during the pipe column is not complete during the downward entry of the pipe in the prior art is solved. The difficulty in controlling crushing and shear pins has achieved the improvement of the full diameter of the pipe column and construction safety.
Patent Information
- Application Number
- CN202310604046.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-26
- Publication Date
- 2024-11-26
AI Technical Summary
During the pipe column entry process, the existing floating couplings have problems such as not completely broken in the cracking disc, difficulty in controlling shear pins, high construction risk and cementing quality.
Design a new type of floating joint. By setting the impact sleeve and shear pin in the assembly part, the pressure difference between the upper and lower end surfaces of the impact sleeve is used to cut the shear pin, break the rupture disc, and reduce the pump injection pressure through the isolation fluid and soluble dowels. , ensure the full diameter of the pipe column.
The full diameter of the pipe column is achieved, the construction risk and cementing quality impact is reduced, the shear pin control is simplified, and the construction safety and efficiency are improved.
Smart Images

Figure CN119021595A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of oil and gas drilling and completion and reservoir transformation, and in particular, relates to a novel floating coupling and a floating coupling drivability method. Background Art
[0002] During the development of oil and gas wells, as exploration and development deepen, oil and gas wells face problems such as large water-to-vertical ratio and insufficient deadweight of the tubing due to the long horizontal section, which leads to large friction torque in the horizontal section and difficulty in lowering the tubing when the tubing is lowered.
[0003] The new floating coupling casing technology can effectively solve the problem of running the completion string in extended reach wells and long horizontal wells. This technology uses a new floating coupling to seal a section of air or low-density drilling fluid at the bottom of the casing string, so that the casing string is in a floating state in the mud of the large well deviated section or horizontal section, so as to reduce the friction between the casing string and the well wall. After the string is run into place, the closed section is opened to achieve smooth flow inside the string.
[0004] In the prior art, there is a new type of floating coupling with a rupture disc. This new type of floating coupling uses a rupture disc to seal a section of air or low-density drilling fluid. After the tubing is in place, the rupture disc is broken by directly holding pressure. However, the rupture disc may not be completely broken when the pressure is held, so that the tubing may not yet achieve full diameter. When the rupture disc is not completely broken, on the one hand, it will affect the passing performance of the cementing plug in subsequent work. When the fixed plug passes through, it will be damaged by the remaining rupture disc and cannot effectively scrape the residual cement in the tubing, thereby increasing the actual opening pressure of tools such as the differential pressure sleeve pre-installed in the tubing, and reducing the passing safety of other tools that need to pass through, etc., increasing the construction risk; on the other hand, it may completely destroy the cementing plug, seriously affecting the cementing quality, and even causing the cementing plug to fail due to impact pressure and sealing failure, resulting in cement reflux back into the wellbore, causing complex conditions in the wellbore.
[0005] In addition, in the prior art, there is another type of new floating coupling with a sliding sleeve rupture disc. This type of floating coupling is equipped with a movable rupture disc and a fixed impact sleeve. The rupture disc is arranged above the impact sleeve, and the impact sleeve and the rupture disc are fixed by shear pins. When the rupture disc needs to be broken, pressure is pumped from above the rupture disc to push the rupture disc to cut the shear pin and then hit the impact sleeve, thereby completely breaking the rupture disc. Although this technology can achieve full-diameter tubing, it must be ensured that the rupture disc will not be relatively displaced with the main tubing of the new floating coupling during the lowering process. In this structure, a large number of shear pins must be used to fix the rupture disc to ensure that the rupture disc works normally during the lowering process. Therefore, this structure requires a large number of shear pins, which are difficult to control, and are mostly distributed in multiple rows. Under the pressure of the mud in the well, the pins may be unevenly stressed and sheared prematurely, resulting in process failure, causing the tubing to fail to be smoothly lowered into place. The provision of multiple shear pins will require great pumping pressure in the process of breaking the rupture disk. Since the rupture disk bears the pressure to shear the shear pins, the rupture disk may break prematurely under such pumping pressure. Once the rupture disk breaks or the seal fails before the shear pin breaks due to an unexpected situation, the shear pins will not be able to shear off, resulting in the rupture disk being unable to hit the impact sleeve, thereby failing to achieve the full diameter of the pipe string, seriously affecting subsequent construction operations. Summary of the invention
[0006] In view of the technical problems mentioned above, the present invention aims to provide a new type of floating coupling, which can realize the full diameter of the pipe string and reduce the risk of work accidents.
[0007] In view of the technical problems mentioned above, the present invention aims to propose a floating coupling diameter method, which can achieve full diameter of the pipe string and reduce the risk of work accidents.
[0008] According to the present invention, a new type of floating coupling is provided, comprising: an upper joint, the upper joint comprising a joint portion and an assembly portion, the inner diameter of the assembly portion being larger than the inner diameter of the joint portion; a lower joint arranged at the lower end of the assembly portion; a sealing assembly having a sealing fixed sleeve arranged in the assembly portion; and an impact sleeve arranged in the assembly portion through a shear pin; wherein the impact sleeve is arranged above the plugging assembly, and the area of the upper end pressure surface of the impact sleeve is larger than the area of the lower end pressure surface, so that the impact sleeve can shear the shear pin under pressure and hit the plugging assembly.
[0009] In one embodiment, the upper portion of the lower joint extends into the assembling portion and abuts against the blocking assembly.
[0010] In one embodiment, a connecting tube is sleeved between the impact sleeve and the assembly portion, the upper and lower ends of the connecting tube are respectively abutted against the joint portion and the blocking assembly, and the impact sleeve is fixedly connected to the connecting tube via a shear pin.
[0011] In one embodiment, the impact sleeve includes a first sleeve-fitting portion and a second sleeve-fitting portion, the outer diameter of the first sleeve-fitting portion is greater than the outer diameter of the second sleeve-fitting portion, and the inner diameter of the first sleeve-fitting portion is equal to the inner diameter of the second sleeve-fitting portion; the connecting tube includes a third sleeve-fitting portion and a fourth sleeve-fitting portion, the inner diameter of the third sleeve-fitting portion is greater than the inner diameter of the fourth sleeve-fitting portion; a seal is provided between the first sleeve-fitting portion and the third sleeve-fitting portion, and a seal is provided between the second sleeve-fitting portion and the fourth sleeve-fitting portion.
[0012] In one embodiment, the blocking assembly includes a base and a rupture disk fixedly disposed on the base, and the rupture disk is capable of sealing the base.
[0013] In one embodiment, a first step is provided on the inner wall of the base, the rupture disk is provided on the first step, and two ends of the rupture disk are respectively in contact with the step surface of the first step and the connecting tube.
[0014] In one embodiment, an end face sealing ring is provided between the rupture disk and the fourth sleeve-fitting portion.
[0015] In one embodiment, a second step is further provided on the inner wall of the base, and the inner diameter of the second step is greater than or equal to the outer diameter of the second sleeve portion.
[0016] In one embodiment, the rupture disk is made of a high-pressure resistant and brittle non-metallic material, which includes glass and ceramics. The rupture disk is cylindrical or spherical, and the shear pin is a soluble pin.
[0017] According to the present invention, a floating coupling flow method is also provided, which uses the new floating coupling provided by the present invention, comprising the following steps: pumping an isolation fluid for protecting the shear pin (33) into the floating coupling well section; pumping mud into the well, and increasing the pumping pressure to achieve flow.
[0018] Compared with the prior art, the present application has the following advantages.
[0019] When the tubing is lowered, the present invention isolates the mud through the rupture disk, seals a section of air or low-density drilling fluid between the new floating coupling and the connected tubing, and uses buoyancy to reduce the weight of the tubing entering the large well inclination section or horizontal section, thereby reducing the friction resistance of the tubing and helping the tubing to be smoothly lowered into place. In the present invention, the rupture disk is fixedly arranged in the assembly part, and the impact sleeve is only arranged in the assembly part through a small number of shear pins, which reduces the difficulty of pin control. In the process of crushing the rupture disk, the impact sleeve uses the end face pressure difference between its upper and lower ends to achieve displacement, shear the shear pins, hit the rupture disk, and then takes out the rupture disk debris in a circulating manner. Under this arrangement, even if the rupture disk explodes prematurely and fails, the impact sleeve can complete the displacement under the action of pressure and hit the rupture disk. The present invention can not only achieve the full diameter of the tubing after the rupture disk is crushed, but also reduce the construction risk, and at the same time has the characteristics of simple structure and convenient construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] The present invention will be described below with reference to the accompanying drawings.
[0021] Figure 1 A schematic diagram showing an initial state of an embodiment of a novel floating coupling according to the present invention is shown;
[0022] Figure 2 A schematic diagram showing a rupture disk of an embodiment of a novel floating coupling according to the present invention after being broken;
[0023] Figure 3 A schematic diagram of another embodiment of a rupture disk according to the invention is shown.
[0024] In the figure: 1, upper joint; 11, joint part; 12, assembly part; 2, plugging assembly; 21, base; 211, first step; 22, rupture disk; 31, impact sleeve; 311, first fitting part; 312, second fitting part; 32, connecting tube; 321, third fitting part; 322, fourth fitting part; 33, shear pin; 4, lower joint; 5, end face sealing ring.
[0025] In the present application, all drawings are schematic drawings, which are only used to illustrate the principles of the present invention and are not drawn according to the actual scale. DETAILED DESCRIPTION
[0026] The present invention will be described below with reference to the accompanying drawings.
[0027] In the present application, it should be noted that the direction of the wellhead approaching the well according to the present invention is described as "upstream", "upper end" or similar terms, that is, Figure 1 The left side is shown; the direction away from the wellhead is described as "downstream", "lower end" or similar terms, i.e. Figure 1 right side shown.
[0028] Figure 1 The structure of the new floating collar 100 according to the present invention is shown. Figure 1 As shown, the novel floating coupling 100 includes an upper joint 1, a lower joint 4, a plugging assembly 2 and an impact sleeve 31. The upper joint 1 includes a joint portion 11 and an assembly portion 12 arranged at the lower end of the joint portion 11, and the inner diameter of the assembly portion 12 is larger than the inner diameter of the joint portion 11. The lower joint 4 is sealed and arranged at the lower end of the assembly portion 12 by a threaded connection. It is easy to understand that both the upper joint 1 and the lower joint 4 can be connected to other downhole tubulars. The plugging assembly 2 and the impact sleeve 31 are both arranged in the assembly portion 12, wherein the plugging assembly 2 is sealed and fixedly arranged in the assembly portion 12, and the impact sleeve 31 is fixedly arranged in the assembly portion by a shear pin 33, and is located above the plugging assembly 2. In addition, the pressure area of the upper end of the impact sleeve 31 is larger than the pressure area of the lower end. When it is necessary to achieve full bore of the pipe string, pressure is pumped into the new floating coupling 100 from the direction of the wellhead. When the pressure difference between the upper and lower pressure surfaces of the impact sleeve 31 is greater than the rated pressure of the shear pin 33 under the same pressure, the shear pin 33 is sheared off, and the impact sleeve 31 will hit the plugging component 2, thereby breaking the plugging component 2 and achieving full bore. Under this setting, since the plugging component 2 no longer controls the cutting of the shear pin 33, even if the plugging component 2 fails, it will not affect the normal operation of the impact sleeve 31. In addition, the force-bearing area of the impact sleeve 31 is small, and under the same pressure, the pressure on the impact sleeve 31 is small, so the number of shear pins 33 required is small, which reduces the difficulty of controlling the shear pin 33 during the design and production process of the device, and also reduces the difficulty of pressure control during the pumping process.
[0029] According to a preferred embodiment of the present invention, a connecting tube 32 is sleeved between the impact sleeve 31 and the assembly part 12. The upper end of the connecting tube 32 abuts against the joint part 11, and the lower end abuts against the plugging assembly 2. The impact sleeve 31 is fixedly connected to the connecting tube 32 by the shear pin 33. Through such a setting of the connecting tube 32, on the one hand, the purpose of fixed connection between the impact sleeve 31 and the assembly part 12 by the shear pin can be achieved; on the other hand, it avoids directly installing the shear pin on the assembly part 12, thereby enhancing the overall strength and sealing of the assembly part 12. During the use of the device, the connecting tube 32 will also be subjected to axial forces, such as the force transmitted to the connecting tube 32 by the impact sleeve 31, and the force received due to the end face pressure difference of the connecting tube 32 itself, so the two ends of the connecting tube 32 can be fixed more firmly and reliably by abutting with other components.
[0030] In a specific embodiment, the impact sleeve 31 includes a first fitting portion 311 and a second fitting portion 312 arranged at the lower end of the first fitting portion 311, the outer diameter of the first fitting portion 311 is greater than the outer diameter of the second fitting portion 312, and the inner diameter of the first fitting portion 311 is equal to the inner diameter of the second fitting portion 312; the connecting tube 32 includes a third fitting portion 321 and a fourth fitting portion 322 arranged at the lower end of the third fitting portion 321, the inner diameter of the third fitting portion is greater than the inner diameter of the fourth fitting portion; a seal is arranged between the first fitting portion and the third fitting portion, and a seal is arranged between the second fitting portion and the fourth fitting portion. In this arrangement, the upper end pressure surface of the impact sleeve 31 is the upper end surface of the first sleeve part 311, and the lower end pressure surface of the impact sleeve 31 is the lower end surface of the second sleeve part 312. Under the same pressure, the axial pressure on the upper end surface of the first sleeve part 311 is greater than the axial pressure on the lower end surface of the second sleeve part 312, so that the impact sleeve 31 can cut off the shear pin 33 and hit the plugging assembly 2 under the action of the pumping pressure. The area difference between the upper end surface of the first sleeve part 311 and the lower end surface of the second sleeve part 312 can be enlarged or reduced according to actual use requirements, which can be achieved by adjusting the inner and outer diameters of the two.
[0031] It is easy to understand that there is no sealed connection between the upper end of the impact sleeve 31 and the joint part 11, so the upper end and the lower end of the impact sleeve 31 are subjected to equal pressure. The force generated by the compressed air in the closed annular space formed between the impact sleeve 31 and the connecting tube 32 is not enough to affect the movement of the impact sleeve 31.
[0032] In a specific embodiment, the plugging assembly 2 is fixedly arranged in the assembly portion 12 by abutting against other components. Specifically, the upper portion of the lower joint 4 extends into the assembly portion 12 and abuts against the lower end of the plugging assembly 2. In combination with the above embodiment, the upper end of the plugging assembly 2 abuts against the connecting tube 32. Thus, the plugging assembly 2 is fixed.
[0033] In a preferred embodiment, the plugging assembly 2 includes a base 21 and a rupture disk 22 fixedly mounted on the base. The axial length of the base 21 is greater than the axial length of the rupture disk 22, so that the plugging assembly 2 is more convenient to install into the upper joint 1. In addition, in order to enable the rupture disk 22 to withstand a certain pressure and be broken by the impact sleeve 31, the rupture disk is made of a high-pressure resistant and fragile non-metallic material, such as glass, ceramic, etc. In addition, in order to improve the pressure resistance of the rupture disk 22 of the same thickness, the rupture disk 22 is Figure 1 The cylindrical shape shown in FIG. 1 can also be configured as Figure 3 Other shapes such as spherical shell shown.
[0034] In a specific embodiment, a first step 211 is provided on the inner wall of the base 21, and the rupture disk 22 is provided on the first step 211. The cylindrical diameter of the first step 211, that is, the diameter of the rupture disk, is larger than the inner diameter of the connecting tube 32, so that the left end of the rupture disk 22 can abut against the connecting tube 32, and the right end of the rupture disk 22 abuts against the end surface of the first step 211. At the same time, in order to achieve a sealing effect for the rupture disk 22, a sealing ring can be provided between the contact surface of the rupture disk 22 and the first step 211 and / or the connecting tube 32. In this embodiment, a sealing groove is provided on the lower end surface of the connecting tube 32, and an end face sealing ring 5 is provided in the sealing groove. Providing the end face sealing ring 5 between the rupture disk 22 and the connecting tube 32 is more convenient than installing the sealing ring on the step surface of the first step 221. Installing the sealing ring on the step surface of the first step 221 will cause the overall outer diameter to expand. Figure 1 The sealing ring installation method shown can obtain a wider shoulder support and protect the weak boundary position of the rupture disk 22, and can also obtain a thicker impact sleeve 31 with greater impact strength, so that the floating coupling of the present invention not only has a full diameter of the entire pipe string, but also has a smaller tool outer diameter on the entire pipe string, which is convenient for the lowering of the pipe string.
[0035] In combination with the above embodiments, the assembly process of the present invention is as follows: first, install sealing rings in the sealing grooves of the impact sleeve 31 and the connecting tube 32 respectively, and assemble the impact sleeve 31 according to the Figure 1 The position shown is sleeved inside the connecting tube 32, and the shear pin is inserted from the outside of the connecting tube 32 to fix the impact sleeve 31 to the connecting tube 32, and then the end face sealing ring 5 is installed in the sealing groove of the connecting tube 32 to complete the assembly of the first part; then the rupture disk 22 is installed on the first step 211, and at the same time, the sealing ring for sealing with the assembly part is installed on the outer wall of the base 21 through the sealing groove to complete the installation of the second part; finally, the installed first part and second part are successively sent in from the lower end of the upper joint 1, and then the lower joint 4 is installed on the lower end of the upper joint 1. The sealing rings mentioned above and the sealing rings used in the sealing method include skeleton sealing rings, O-rings, etc.
[0036] According to a specific embodiment of the present invention, a second step 212 is further provided on the inner wall of the base 21, and the inner diameter of the second step 212 is greater than or equal to the outer diameter of the second sleeve portion 312. Figure 2 As shown, under this arrangement, after the impact sleeve 31 impacts the rupture disk 22 under pressure, the lower end of the impact sleeve 31 can pass over the rupture disk and reach Figure 2 The position shown can more effectively seal the remaining annular portion of the rupture disk 22.
[0037] The present invention can realize a variety of usage modes by controlling the strength of the shear pin 33. The method of using the rupture disk 22 to block a section of air or low-density drilling fluid to reduce the friction resistance during drilling is the same as the prior art. The main difference is the way the rupture disk 22 is broken after being pumped into place, as shown below.
[0038] Mode 1: When the strength of the shear pin 33 is relatively small, that is, the shear pin 33 breaks before the rupture disk 22 explodes. After the pump pressure is applied, the impact sleeve 31 moves downward under the pressure, and the shear pin 33 is sheared off by the impact sleeve 31. Subsequently, the impact sleeve 31 hits the rupture disk 22. The impact of the impact sleeve 31 causes a weak point on the rupture disk 22 that matches the contour of the impact sleeve 31. After increasing the pump pressure, the rupture disk 22 explodes along the contour formed by the weak point to form fine particles, thereby achieving full diameter.
[0039] It is easy to understand that the high-pressure resistant and fragile non-metallic materials such as glass and ceramics used in this embodiment have the physical property that once a weak point appears, they will explode along the contour formed by the weak point when subjected to strong pressure again.
[0040] Method 2: When the strength of the shear pin 33 is greater than that of method 1, the shear pin 33 still breaks before the rupture disk 22 explodes. After the pump pressure is injected, the impact sleeve 31 moves downward under the pressure, and the shear pin 33 is sheared by the impact sleeve 31. Then, the impact sleeve 31 hits the rupture disk 22. The impact of the impact sleeve 31 causes a through hole on the rupture disk 22 that matches the contour of the impact sleeve 31. The part that breaks away from the rupture disk 22 after the impact is instantly broken into fine particles. The final result is Figure 2 In this way, even if the rupture disk 22 fails to blast prematurely before the shear pin 33 breaks, such as in an unexpected situation, the rupture disk 22 breaks under the pumping pressure lower than its rated strength, the impact sleeve 31 can still hit the rupture disk 22, which will not affect the realization of the full bore.
[0041] Method 3: When the strength of the shear pin 33 is greater than that of method 2, that is, after the pump pressure is injected, the impact sleeve 31 tends to move downward under the pressure, but the rupture disk 22 ruptures before the shear pin 33, that is, the main part explodes into fine particles, but there may be residual edges. After continued pressurization, the shear pin 33 is sheared off by the impact sleeve 31, and then the impact sleeve 31 hits the rupture disk 22. The impact of the impact sleeve 31 causes a through hole on the rupture disk 22 that matches the contour of the impact sleeve 31, so that the residual on the edge of the rupture disk 22 is broken into fine particles, and finally presents Figure 2 The effect shown is to achieve full bore.
[0042] In the third mode provided by the present invention, the shear pin 33 can only be broken by pumping pressure exceeding the bursting pressure of the rupture disk 22. Under such high-pressure pumping, the mud in the wellbore may be squeezed into the formation, polluting the energy reserves of the formation, thereby reducing the mining output. In order to solve this problem, the present invention provides another implementation method, which is specifically described in the fourth mode as follows.
[0043] Method 4: In a preferred embodiment, the shear pin 33 is a soluble pin made of a high-strength soluble material. Before installing the soluble pin, a solid solvent is first introduced into the pin hole where the soluble pin is installed for semi-filling, and then the soluble pin is installed into the pin hole. The floating coupling well section is set at the junction of the horizontal well and the vertical well. After the floating coupling is lowered, during the grouting process, it is necessary to first pump a section of isolation fluid into the floating coupling well section, and then pump in mud, that is, pump the isolation fluid to fill the horizontal well upstream of the floating coupling, and then pump in mud. The mud is isolated from the solid solvent and the soluble pin by the isolation liquid to prevent the solid solvent from being soaked in the mud and causing the soluble pin to dissolve prematurely. The specific working principle of this embodiment is as follows.
[0044] After the pumping pressure is applied, the rupture disk 22 ruptures before the soluble pin. After the rupture disk 22 explodes, the pre-pumped isolation fluid is displaced by the mud above and moves downward along the pipe string, rendering the isolation fluid ineffective, that is, the isolation fluid loses its protective effect on the solid solvent, and the solid solvent comes into contact with the mud. The solid solvent dissolves under the immersion of the mud, causing the soluble pin to dissolve quickly. When the soluble pin loses its strength due to dissolution, there is no need to increase the pumping pressure. The soluble pin can be sheared off by the liquid column pressure or circulating pressure of subsequent downhole operations, thereby accelerating the impact sleeve 31 downward and impacting the remaining part of the rupture disk 22 after the explosion, thereby achieving secondary crushing. After the impact sleeve 31 penetrates the rupture disk 22, the full diameter is achieved. In the case of low liquid column pressure or circulating pressure, even if the impact force generated by the impact sleeve 31 cannot completely remove the remaining part of the rupture disk 22, the impact sleeve 31 can also squeeze and crush the remaining part of the rupture disk 22 after the explosion through the pressure difference force that always exists in the pipe column (i.e., in the floating coupling). Since the remaining part of the rupture disk 22 after the explosion does not have integrity, the compressive strength is greatly reduced under the action of impact crushing, so that the remaining part can be crushed into fine particles through the extrusion action to achieve full diameter. Under this setting, on the one hand, the required pumping pressure does not need to exceed the explosion pressure of the rupture disk 22, thereby solving the problem that mud may invade the formation under high pressure; on the other hand, the shear pin 33 is a soluble pin, and the strength of the shear pin 33 is reduced by dissolving, which can more reliably complete the impact action of the impact sleeve 31 and avoid the situation that the shear pin 33 cannot be sheared under the pressure operation window.
[0045] It is easy to understand that the isolation fluid, high-strength soluble material and solid solvent are all existing materials. After the solid solvent comes into contact with the mud, it can promote the dissolution of the high-strength soluble material.
[0046] In order to further simplify the assembly of the present invention, the present invention also provides another embodiment of the plugging assembly 2, the connecting tube 32 and the lower joint 4. In this embodiment, the base 21 and the connecting tube 32 are integrated, and the bottom joint 4 is removed. Figure 1 The second step 212 of the middle base 21 and the part below it, and the upper end surface of the lower joint 4 are lengthened so that it can abut against the rupture disk 22. Through this arrangement, it is equivalent to reducing the base 21 part, simplifying the assembly difficulty of the present invention. Accordingly, a step is set at the upper end of the lower joint 4 to serve as the original second step.
[0047] According to the method of crushing the rupture disk provided by the present invention, the design strength of the shear pin 33 of the new floating coupling 100 provided by the present invention can be within a large range under the premise of being able to achieve full diameter, thereby reducing the design difficulty of the shear pin 33, and also reducing the impact force of the impact sleeve 31, preventing the tip of the impact sleeve 31 from being deformed or damaged under excessive impact tonnage, and reducing the performance requirements and control difficulty of the impact sleeve 31. In addition, the pumping pressure in the present invention can also be within a large range, thereby reducing the difficulty of controlling the pumping pressure. With the continuous increase in the depth and vertical depth of the wellbore, a rupture disk 22 with a higher pressure-bearing level is required. If the sliding sleeve rupture disk type floating coupling in the prior art is used, the control difficulty of the shear pin and the impact sleeve is further increased under a certain pressure operation window. Therefore, in order to reduce the construction difficulty, two rupture disks 22 with low pressure-bearing levels are usually used to be set at different well depths of the pipe string, and the pipe string is double-floated and lowered. However, the floating coupling described in the present invention can meet the full-diameter requirement of the pipe string after the rupture disk 22 with a high pressure-bearing level is crushed, so as to achieve the purpose of reducing costs and increasing efficiency. Of course, the present invention is also compatible with the above-mentioned double-floating lowering construction requirements, thereby further covering the string lowering requirements in deep wells, ultra-deep wells and other well conditions.
[0048] In the description of the present invention, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0049] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0050] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0051] Finally, it should be noted that the above is only a preferred embodiment of the present invention and does not constitute any limitation to the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for a person skilled in the art to modify the technical solutions described in the aforementioned embodiments or to replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A new type of floating coupling, characterized in that: include: An upper joint (1), the upper joint comprising a joint portion (11) and an assembly portion (12), the inner diameter of the assembly portion being greater than the inner diameter of the joint portion; A lower joint (4) arranged at the lower end of the assembling portion; A sealing component (2) which is fixedly sleeved in the assembly part in a sealed manner; An impact sleeve (31) is arranged in the assembly portion via a shear pin (33); Wherein, the impact sleeve is arranged above the blocking assembly, and the area of the upper pressure surface of the impact sleeve is larger than the area of the lower pressure surface, so that the impact sleeve can shear the shear pin under pressure and hit the blocking assembly.
2. The novel floating coupling according to claim 1 is characterized in that: The upper portion of the lower joint (4) extends into the assembly portion and abuts against the blocking component (2).
3. The new floating coupling according to claim 2 is characterized in that: A connecting tube (32) is sleeved between the impact sleeve (31) and the assembly portion (12), the upper and lower ends of the connecting tube respectively abutting against the joint portion (11) and the plugging assembly (2), and the impact sleeve is fixedly connected to the connecting tube via a shear pin.
4. The new floating coupling according to claim 3 is characterized in that: The impact sleeve (31) comprises a first sleeve-fitting portion (311) and a second sleeve-fitting portion (312), wherein the outer diameter of the first sleeve-fitting portion is greater than the outer diameter of the second sleeve-fitting portion, and the inner diameter of the first sleeve-fitting portion is equal to the inner diameter of the second sleeve-fitting portion; the connecting tube (32) comprises a third sleeve-fitting portion (321) and a fourth sleeve-fitting portion (322), wherein the inner diameter of the third sleeve-fitting portion is greater than the inner diameter of the fourth sleeve-fitting portion; a sealing member is provided between the first sleeve-fitting portion and the third sleeve-fitting portion, and a sealing member is provided between the second sleeve-fitting portion and the fourth sleeve-fitting portion.
5. The novel floating coupling according to claim 4 is characterized in that: The blocking assembly (2) comprises a base (21) and a rupture disk (22) fixedly arranged on the base, wherein the rupture disk is capable of sealing the base.
6. The novel floating coupling according to claim 5 is characterized in that: A first step (211) is provided on the inner wall of the base (21), the rupture disk (22) is provided on the first step (211), and two ends of the rupture disk are respectively in contact with the step surface of the first step and the connecting tube (32).
7. The novel floating coupling according to claim 6 is characterized in that: An end face sealing ring (5) is arranged between the rupture disk and the fourth sleeve-fitting portion.
8. The novel floating coupling according to claim 7 is characterized in that: A second step (212) is also provided on the inner wall of the base (21), and the inner diameter of the second step is greater than or equal to the outer diameter of the second sleeve-fitting portion (312).
9. The novel floating coupling according to any one of claims 1 to 8, characterized in that: The rupture disk (22) is made of a high-pressure resistant and brittle non-metallic material, which includes glass, ceramics, and resin. The rupture disk (22) is cylindrical or spherical, and the shear pin (33) is a soluble pin.
10. A floating collar diameter method, characterized in that: Using the new floating collar according to claim 9 comprises the following steps: Pumping a spacer fluid for protecting the shear pin (33) into the floating coupling well section; Pump mud into the well and increase the pumping pressure to achieve clearance.
Citation Information
Patent Citations
Floating coupling for casing pipe
CN108425640A
Breakable blind plate type floating coupling device, using method and preparation method of blind plate
CN112412342A
Floating nipple, floating lower tail pipe string and application of floating lower tail pipe string
CN115492536A
Drilling-free oil removal sleeve temporary plugging short section and application thereof
CN115492552A
Sleeve pipe floats coupling for oil and gas well cementation
CN206722773U
Cited By
Casing pipe floating coupling structure
CN120042475A
A casing floating collar structure
CN120042475B