Fracturing sliding sleeve, well cementation casing pipe and perforation-free staged fracturing method
By designing a cementing casing that cooperates with a fracturing slip sleeve and a soluble bridge plug, the fracturing channel opening without extremes and the automatic melting of a soluble bridge plug is achieved, and the low fracturing efficiency of long horizontal well bridge plug perforation is solved. The problem of using civil explosives has improved the efficiency and safety of drilling and completion of unconventional oil and gas horizontal wells.
Patent Information
- Application Number
- CN202310604970.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-26
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2043-05-26
AI Technical Summary
In the existing unconventional oil and gas horizontal well drilling and completion technology, the fracturing efficiency of long horizontal well plug perforation plug is low. The use of civil explosive perforation bullets increases cost and safety risks, and it is difficult to meet the multi-stage fracturing needs. In addition, the later stage, the seating and sealing of the ball will increase the difficulty of the work.
A cementing casing used in combination with soluble bridge plugs was designed. The fracturing channel is opened without extremes by cutting pins and pressure transfer holes. The soluble bridge plug is automatically melted to avoid drilling, and the Perforation-free segmented fracturing.
It improves fracturing operation efficiency and reduces costs, reduces social security risks, and achieves efficient multi-stage fracturing operations without civil explosives.
Smart Images

Figure CN119021637A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of unconventional oil and gas horizontal well drilling and completion, and in particular to a fracturing sleeve, a cementing casing and a perforation-free staged fracturing method. Background Art
[0002] my country's unconventional oil and gas resources are rich and widely distributed. Long horizontal section horizontal well + bridge plug perforation combined fracturing is an important means and development measure for unconventional oil and gas development to increase production and improve efficiency. Usually, the number of long horizontal well bridge plug perforation combined fracturing sections exceeds 20, and each section has more than 6 perforations. In this way, an unconventional oil and gas horizontal well generally requires more than 100 perforations, and the perforating gun needs to be lifted and lowered to install ammunition more than 20 times, which makes the completion operation inefficient. In addition, the perforating bullets used for perforation are civil explosives. The large-scale use of perforating bullets will have a certain impact on social security and environmental protection and increase uncontrollable factors, and also increase the cost of oil and gas development.
[0003] To this end, people open the sliding sleeve by connecting a mechanical tool to the cementing casing, or by throwing a ball (throwing a dart to hold the pressure) to open the sliding sleeve. However, the mechanical tool needs to be lowered into a special switch tool, and each time the sliding sleeve is opened and closed, the drill needs to be pulled up and down, which increases the completion operation time; and the ball throwing (throwing a dart to hold the pressure) requires a pre-set sealing ball seat (dart seat), which is difficult to meet the fracturing needs of too many levels, and after the fracturing operation is completed, the sealing ball seat needs to be drilled out, which increases the difficulty of the completion operation and increases the operation cost. Summary of the invention
[0004] One of the purposes of the present invention is to provide a fracturing sliding sleeve, which can achieve zero step difference of cementing casing, and has high fracturing operation efficiency and low operation cost.
[0005] To achieve the above object, the technical solution of the present invention is as follows:
[0006] A fracturing sleeve is used in conjunction with a soluble bridge plug, the fracturing sleeve comprising an upper joint, a sleeve and an upper joint, the upper joint being circumferentially provided with a plurality of fracturing channel holes; the lower joint being sealed and connected to the upper joint, the lower joint being inserted into the upper joint and forming an annulus with the upper joint; the sleeve is fixed to the interior of the upper joint by a shear pin and is sealed and connected to the upper joint, for plugging the fracturing channel holes, the sleeve being inserted into the annulus and sealed and connected to the lower joint; a pressure transmission hole is also provided on the lower joint, the pressure transmission hole connecting the lower joint and the annulus.
[0007] Optionally, the annulus is filled with a hot-melt solid.
[0008] Optionally, an anti-blocking hole is also provided on the lower joint, and the anti-blocking hole connects the pressure transmission hole and the interior of the lower joint. A temporary plugging head is sealed in the anti-blocking hole, one end of the temporary plugging head is closed and protrudes from the anti-blocking hole, and the other end is inserted into the anti-blocking hole and connected with the pressure transmission hole.
[0009] Optionally, a first shoulder is provided on the inner wall of the upper joint, and an end of the sliding sleeve away from the lower joint faces the first shoulder.
[0010] Optionally, the upper joint includes an axially connected upper connecting portion, an upper transition portion and an upper main body portion, the inner diameter of the upper main body portion is larger than the inner diameter of the upper transition portion to form the first shoulder, the lower joint includes an axially connected lower main body portion, a lower transition portion and a lower connecting portion, the lower transition portion and the lower main body portion are inserted into the upper main body portion and connected to the upper main body portion, the outer diameter of the lower transition portion is larger than the outer diameters of the lower connecting portion and the lower main body portion and forms a second shoulder between the lower main body portion, the inner diameter of the upper transition portion is the same as the inner diameter of the lower joint, and the length of the soluble bridge plug used for sealing is greater than the distance between the shoulder surface of the first shoulder and the lower main body portion.
[0011] Optionally, two openings of the pressure transmission hole are respectively opened on the inner wall of the lower transition portion and the shoulder surface of the second shoulder.
[0012] Optionally, a plurality of annular grooves are provided at both axial ends of the sliding sleeve, and a first sealing ring is placed in the groove to form a seal between the sliding sleeve and the upper joint.
[0013] Optionally, an annular groove is provided on the outer wall of one end of the lower joint in contact with the sliding sleeve, and a second sealing ring is placed in the groove to form a seal between the lower joint and the sliding sleeve.
[0014] Another object of the present invention is to provide a cementing casing, which includes a casing, a toe sleeve, a floating collar and the fracturing sleeve as described above, wherein multiple sections of the fracturing sleeve are alternately connected to multiple sections of the casing to form a casing string, the lower end of the casing string is connected to the toe sleeve, and the lower end of the toe sleeve is connected to the floating collar.
[0015] Another object of the present invention is to provide a perforation-free staged fracturing method, which is implemented by using the above-mentioned cementing casing, wherein the cementing casing includes a fracturing sleeve with a temporary plug, and the method specifically includes the following steps:
[0016] S1, lowering the cementing casing to a predetermined position in the well and performing normal cementing operations;
[0017] S2, in the later stage of cementing operation, the cementing plug displaces cement slurry into the annulus between the cementing casing and the wellbore, and cuts off the temporary plug when passing through the sliding sleeve, so that the pressure in the pipe is connected to the pressure transmission hole through the temporary plug;
[0018] S3, opening the toe end sliding sleeve by applying pressure at the wellhead, establishing a first section pipe internal and external communication channel and completing the first section fracturing operation;
[0019] S4, pumping the soluble bridge plug into the cementing casing to the lower joint of the fracturing sleeve that needs to be opened and above the temporary plugging head, and then pressurizing the wellhead to make the upper pressure of the soluble bridge plug higher than the lower pressure of the soluble bridge plug. When the pressure difference reaches a certain value, the thrust generated by the pressure difference shears the shear pin, and the sleeve moves downward to expose the fracturing channel hole, so as to establish a pressure channel and perform fracturing operations;
[0020] S5, repeating step S4, opening the fracturing sleeves in sequence from the bottom of the well to the wellhead and performing fracturing operations in each section until the fracturing operation is completed.
[0021] The beneficial effects of the present invention are as follows: the fracturing sleeve of the present invention inserts the lower joint into the upper joint to form an annulus, and the soluble bridge plug can be seated at the part where the lower joint is inserted into the upper joint to achieve a sealing layer, and the part where the lower joint is inserted into the upper joint plays the role of a sealing ball seat in the existing fracturing sleeve, and the subsequent soluble bridge plug can automatically melt without drilling out; the fixed sleeve of the present invention adopts the above-mentioned fracturing sleeve to achieve zero step difference, and adopts the toe end sleeve to open the first section of the connecting channel inside and outside the pipe, the entire fracturing operation process does not require perforation, does not require the use of civilian explosives, and reduces social safety risks; the perforation-free staged fracturing method of the present invention has high operating efficiency and low operating cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 is a schematic diagram of the structure of a fracturing sliding sleeve in an embodiment of the present invention;
[0023] Figure 2 yes Figure 1 A schematic diagram of the enlarged structure at A in the middle;
[0024] Figure 3 yes Figure 1 A schematic diagram of the enlarged structure at B in the middle;
[0025] Figure 4 is a schematic diagram of the structure of a fracturing sleeve with a temporary plug cut off in an embodiment of the present invention;
[0026] Figure 5 is a schematic diagram of the structure of a soluble bridge plug being set in a fracturing sleeve in an embodiment of the present invention;
[0027] Figure 6is a schematic diagram of the structure of a fracturing sleeve when the fracturing channel hole is opened in an embodiment of the present invention;
[0028] Figure 7 Schematic diagram of the structure of the fracturing sleeve after the soluble bridge plug is melted in the embodiment of the present invention;
[0029] Figure 8 It is a schematic diagram of the structure of the cementing casing in an embodiment of the present invention.
[0030] In the figure, 10, fracturing sleeve; 11, upper joint; 111, upper connecting part; 112, upper transition part; 113, upper main body; 114, first shoulder; 115, fracturing channel hole; 12, inner bushing; 13, lower joint; 131, lower main body; 132, lower transition part; 133, lower connecting part; 134, second shoulder; 135, pressure transmission hole; 136, anti-blocking hole; 14, shear pin; 15, temporary plug; 16, first sealing ring; 17, second sealing ring; 18, third sealing ring;
[0031] 20. Casing;
[0032] 30. Toe end sliding sleeve;
[0033] 40. Floating hoop;
[0034] 50. Soluble bridge plug. DETAILED DESCRIPTION
[0035] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only parts related to the present invention, rather than all structures, are shown in the accompanying drawings.
[0036] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0037] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0038] In the description of this embodiment, the terms "upper", "lower", "left", "right" and other directions or positional relationships are based on the directions or positional relationships shown in the drawings, and are only for the convenience of description and simplified operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operate in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.
[0039] The ball-casting sleeve usually includes an outer tube, an inner sleeve and a shear pin. The outer tube is provided with a fracturing channel hole. The inner sleeve is fixed to the outer tube by the shear pin. When the shear pin is cut off, the inner sleeve can move axially relative to the outer tube, so that the fracturing channel hole is opened and the inner and outer spaces of the ball-casting sleeve are connected. The shear pin is cut off by throwing a sealing ball into the ball-casting sleeve. After the sealing ball is thrown, the pressure is held to open the fracturing channel hole. Generally, considering the coaxiality problem of the outer tube and the inner sleeve during processing, in order to ensure that the inner sleeve can move axially relative to the outer tube to open the fracturing channel hole, the length of the inner sleeve should not be too long. In order to make the sealing ball stay accurately in the inner sleeve, a sealing ball seat is provided on the inner wall of the inner sleeve, so that the sealing ball falls accurately on the inner sleeve. When the sealing ball is limited to the sealing ball seat, it can drive the inner sleeve to move axially, so as to open the fracturing channel hole. This makes it impossible to achieve the full diameter of the cementing casing, and the sealing ball seat needs to be drilled out later. The operation steps are cumbersome, and the number of fracturing stages is limited, making it difficult to meet the fracturing needs of too many stages.
[0040] To this end, the present invention provides a fracturing sleeve. The fracturing sleeve 10 is used in conjunction with a soluble bridge plug 50 . Figure 1-Figure 7A fracturing sleeve 10 is proposed in one of the embodiments of the present invention, and the fracturing sleeve 10 includes an upper joint 11, a lower joint 13, an internal sleeve 12 and a shear pin 14. The upper joint 11, the lower joint 13 and the internal sleeve 12 are all arranged as a cylindrical structure, wherein the first end of the upper joint 11 is connected to the external pipe joint, and the second end is sealed to the lower joint 13. The upper joint 11 is circumferentially provided with a plurality of fracturing channel holes 115, and the lower joint 13 at least partially extends into the upper joint 11 and forms an annular annulus with the upper joint 11. The internal sleeve 12 is fixed to the inside of the upper joint 11 by the shear pin 14, and is used for blocking the fracturing channel holes 115. In order to ensure that the internal sleeve 12 blocks the fracturing channel holes 115, a seal is arranged between the internal sleeve 12 and the upper joint 11. Exemplarily, multiple annular grooves are provided on the outer walls of the two axial ends of the inner bushing 12, and the first sealing rings 16 are placed in the grooves. When the shear pins 14 are not sheared off, the first sealing rings 16 are distributed on both sides of the fracturing channel hole 115 to form a seal between the inner bushing 12 and the upper joint 11. The end of the inner bushing 12 away from the first end of the upper joint 11 is inserted into the annulus, and the inner bushing 12 can shear the shear pins 14 under the pressure difference at both ends of the inner bushing 12 and slide axially toward the lower joint 13.
[0041] The fracturing channel hole 115 on the above-mentioned fracturing sleeve 10 is opened by the soluble bridge plug 50. The soluble bridge plug 50 can be pumped to the part where the lower joint 13 is inserted into the upper joint 11 and sealed. By pressurizing, the pressure in the fracturing sleeve 10 located above the soluble bridge plug 50 is higher than the pressure in the fracturing sleeve 10 located below the soluble bridge plug 50. When the pressure difference reaches a certain value, the internal sleeve 12 moves downward under the pressure, and the thrust pushes the internal sleeve 12 to cut the shear pin 14. The internal sleeve 12 moves downward to expose the fracturing channel hole 115, establish a pressure channel and perform fracturing operations. After the fracturing operation is completed, the soluble bridge plug 50 can automatically dissolve in the fracturing sleeve 10 without drilling, thereby improving the fracturing efficiency and reducing the operating cost. The soluble bridge plug 50 belongs to the prior art, and its sealing means will not be described in detail in this embodiment. It is understandable that the length of the lower joint 13 inserted into the upper joint 11 must be longer than the length of the internal liner 12, so as to ensure that the soluble bridge plug 50 falls into the lower joint 13 and is set in the lower joint 13, and the lower joint 13 is fixed relative to the upper joint 11, and there is no need to consider the coaxiality of the upper joint 11 and the lower joint 13. As for the specific length, it can be determined according to the overall length of the cementing casing. For example, the length of the lower joint 13 inserted into the upper joint 11 is not less than 2m.
[0042] According to the cementing design requirements, the cementing casing needs to be cemented first and then fracturing after it is lowered into the unconventional oil well. During the cementing process, drilling fluid and cement slurry need to be injected into the fixed sleeve in sequence. In order to prevent the cement slurry from entering the annulus and condensing to affect the subsequent movement of the internal liner 12, the internal liner 12 is sealed and connected to the lower joint 13. Figure 1 As shown, an annular groove is provided on the outer wall of the end of the lower joint 13 that contacts the inner bushing 12, and a second sealing ring 17 is placed in the groove. Of course, an annular groove can also be provided on the inner wall of the end of the inner bushing 12 that contacts the lower joint 13, and the second sealing ring 17 can be placed in the groove to achieve sealing between the inner bushing 12 and the lower joint 13.
[0043] On this basis, in order to prevent the inner liner 12 from moving unexpectedly, a pressure transmission hole 135 connecting the annulus and the lower joint 13 is provided on the lower joint 13. The pressure transmission hole 135 can balance the pressure on the upper and lower end surfaces of the inner liner 12 to avoid the generation of sliding shear force. The size of the pressure transmission hole 135 only allows liquids or gases with no or low viscosity to enter and exit. For example, cement slurry is not allowed to enter, while drilling fluid and gas are allowed to enter.
[0044] refer to Figure 1 as well as Figure 4-Figure 7 As shown, a first shoulder 114 is provided on the inner wall of the upper joint 11, and one end of the internal bushing 12 away from the lower joint 13 faces the shoulder surface of the first shoulder 114. When the drilling fluid or cement slurry enters the fracturing sleeve 10 from the first end of the upper joint 11, the impact on the internal bushing 12 can be reduced, and the pressure difference at both ends of the internal bushing 12 can be further reduced.
[0045] In this embodiment, the upper joint 11 includes an axially connected upper connection part 111, an upper transition part 112 and an upper main body 113, the upper connection part 111 is used to connect an external pipe segment, and the upper transition part 112 plays a role in connecting the upper connection part 111 and the upper main body 113, the lower joint 13 includes a lower main body 131, a lower transition part 132 and a lower connection part 133, the lower connection part 133 is used to connect an external pipe segment, and the lower transition part 132 plays a role in connecting the lower connection part 133 and the lower main body 131, the lower transition part 132 and the lower main body 131 are inserted into the upper main body 113, and the outer wall of the lower transition part 132 is provided with an external thread, the inner wall of the upper main body 113 is provided with an internal thread hole, and the lower transition part 132 is screwed with the upper main body 113. To ensure sealing, a third sealing ring 18 is also provided between the lower transition part 132 and the upper main body 113.
[0046] The inner diameter of the upper main body 113 is larger than the inner diameter of the upper transition portion 112 to form a first shoulder 114, the outer diameter of the lower transition portion 132 is larger than the outer diameters of the lower connecting portion 133 and the lower main body 131 to cooperate with the upper joint 11 to form an annulus, and a second shoulder 134 is formed between the lower transition portion 132 and the lower main body 131. The inner diameter of the upper transition portion 112 is the same as the inner diameter of the entire lower joint 13, and the length of the soluble bridge plug 50 is larger than the distance between the shoulder surface of the first shoulder 114 and the lower main body 131, so that the soluble bridge plug 50 can smoothly pass through the inner liner 12 part and enter the lower joint 13.
[0047] When the soluble bridge plug 50 enters the fracturing sleeve 10 to open the fracturing channel hole 115, it is necessary to seal it at the upper position of the pressure transmission hole 135 of the lower joint 13 to prevent the annulus from continuing to communicate with the interior of the lower joint 13. In order to provide the soluble bridge plug 50 with a larger displacement difference when moving in the fracturing sleeve 10, the two openings of the pressure transmission hole 135 are respectively opened on the inner wall of the lower transition portion 132 and on the shoulder surface of the second shoulder 134.
[0048] During the cementing process, the cement slurry may block the pressure transmission hole 135 when passing through the fracturing sleeve 10, resulting in different pressures at the two axial ends of the internal liner 12, resulting in a pressure difference. For this reason, a hot-melt solid, such as paraffin, can be pre-filled in the annulus. During the process of lowering the cementing casing into the well, the temperature gradually increases, and the paraffin melts into liquid and fills the annulus to prevent the pressure difference at the two axial ends of the internal liner 12. It can be understood that the hot-melt solid should have a certain viscosity after melting, and it is difficult to flow out of the annulus through the pressure transmission hole 135. Only when the pressure difference at the two ends of the internal liner 12 reaches a level that can cut the shear pin 14, the melted hot-melt solid can flow out, and the melted hot-melt solid prevents the entry of cement slurry.
[0049] Alternatively, refer to Figure 3 As shown, the inner wall of the lower joint 13 is also provided with an anti-blocking hole 136 connected to the pressure transmission hole 135, and a temporary plug 15 is sealed in the anti-blocking hole 136. One end of the temporary plug 15 is closed and protrudes from the anti-blocking hole 136, and the other end is inserted into the anti-blocking hole 136 and connected to the pressure transmission hole 135. The closed end of the temporary plug 15 will be sheared off by the cementing plug of the fracturing sleeve 10 in the later stage of the cementing operation, so that the interior of the lower joint 13 is connected to the annulus again. The cementing plug is used to isolate cement slurry from drilling fluid or isolation fluid, which belongs to the prior art and will not be described in detail in this embodiment.
[0050] refer to Figure 8As shown, another embodiment of the present invention proposes a cementing casing, which includes a casing 20, a toe end sleeve 30, a floating collar 40 and the above-mentioned fracturing sleeve 10, wherein multiple sections of fracturing sleeves 10 are alternately connected to multiple sections of casing 20 to form a casing string, the lower end of the casing string is connected to the toe end sleeve 30, and the lower end of the toe end sleeve 30 is connected to the floating collar 40. The toe end sleeve 30 and the floating collar 40 are both prior art, wherein the toe end sleeve 30 opens the channel connecting the inside and outside of the cementing casing by pressurizing to complete the first stage of fracturing operation, so that the entire fracturing process can achieve perforation-free operation, high completion efficiency and low development cost. The number of fracturing sleeves 10 can be determined according to the number of fracturing layers, and is not limited here.
[0051] In another embodiment of the present invention, a perforation-free staged fracturing method is provided, which is implemented by using the cementing casing. The fracturing sleeve 10 in the cementing casing includes a temporary plug 15. The method specifically includes the following steps:
[0052] S1. Lower the cementing casing to the predetermined position in the well and perform normal cementing operations (connect the circulation pipeline and cementing pipeline, circulation, cementing). The pressure on the upper and lower end surfaces of the internal liner 12 reaches pressure balance through the pressure transmission hole 135. The internal liner 12 has no sliding shear force and is in a static state relative to the upper joint 11.
[0053] S2, in the later stage of cementing operation, the cementing plug displaces cement slurry into the annulus between the cementing casing and the wellbore, and cuts off the temporary plug 15 when passing through the internal liner 12, so that the pressure in the pipe is connected to the pressure transmission hole 135 through the temporary plug 15;
[0054] S3, opening the toe end sliding sleeve 30 by applying pressure at the wellhead, establishing a first section pipe internal and external communication channel and completing the first section fracturing operation;
[0055] S4, pumping the soluble bridge plug 50 into the cementing casing to the lower joint 13 of the fracturing sleeve 10 that needs to be opened and above the temporary plug 15, and then pressurizing the wellhead to make the upper pressure of the soluble bridge plug 50 higher than the lower pressure of the soluble bridge plug 50, so that a pressure difference is formed at both ends of the internal liner 12 in the fracturing sleeve 10, thereby generating a thrust for sliding downward. When the pressure difference reaches a certain value, the thrust generated by the pressure difference shears the shear pin 14, and the internal liner 12 moves downward to expose the fracturing channel hole 115, thereby establishing a pressure channel and performing fracturing operations;
[0056] S5, repeat step S4, open the fracturing sleeve 10 from the bottom of the well to the wellhead in sequence and perform fracturing operations in each section until the fracturing operation is completed. The soluble bridge plugs 50 in each stage automatically dissolve in the wellbore over time without drilling and removal, thereby achieving full cementing casing perforation-free fracturing operations, improving the completion operation effect, and achieving the purpose of reducing development costs.
[0057] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, various obvious changes, readjustments and substitutions can be made without departing from the protection scope of the present invention. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.
Claims
1. A fracturing sleeve, used in conjunction with a soluble bridge plug (50), characterized in that: include: An upper joint (11), wherein the upper joint (11) is provided with a plurality of fracturing channel holes (115) in a circumferential direction; a lower joint (13) sealedly connected to the upper joint (11), wherein the lower joint (13) is inserted into the upper joint (11) and forms an annulus with the upper joint (11); An internal bushing (12) is fixed inside the upper joint (11) through a shear pin (14) and is sealed with the upper joint (11) to block the fracturing channel hole (115); the internal bushing (12) is inserted into the annulus to seal the annulus; A pressure transmission hole (135) is arranged on the lower joint (13) and connects the lower joint (13) and the annulus.
2. The fracturing sleeve according to claim 1, characterized in that: The annulus is filled with hot-melt solid.
3. The fracturing sleeve according to claim 1, characterized in that: The lower joint (13) is also provided with an anti-blocking hole (136), the anti-blocking hole (136) communicating with the pressure transmission hole (135) and the interior of the lower joint (13), a temporary plugging head (15) is sealed in the anti-blocking hole (136), one end of the temporary plugging head (15) is closed and protrudes from the anti-blocking hole (136), and the other end is inserted into the anti-blocking hole (136) and communicated with the pressure transmission hole (135).
4. The fracturing sleeve according to claim 1, characterized in that: A first shoulder (114) is provided on the inner wall of the upper joint (11), and one end of the inner bushing (12) away from the lower joint (13) faces the first shoulder (114).
5. The fracturing sleeve according to claim 4, characterized in that: The upper joint (11) comprises an axially connected upper connecting portion (111), an upper transition portion (112) and an upper main body portion (113); the inner diameter of the upper main body portion (113) is greater than the inner diameter of the upper transition portion (112) to form the first shoulder (114); the lower joint (13) comprises an axially connected lower main body portion (131), a lower transition portion (132) and a lower connecting portion (133); the lower transition portion (132) and the lower main body portion (131) are inserted into the upper main body portion The lower transition portion (132) is connected to the upper main body (113) in the interior, the outer diameter of the lower transition portion (132) is greater than the outer diameter of the lower connecting portion (133) and the lower main body (131), and a second shoulder (134) is formed between the lower main body (131), the inner diameter of the upper transition portion (112) is the same as the inner diameter of the lower joint (13), and the length of the soluble bridge plug (50) is greater than the distance between the shoulder surface of the first shoulder (114) and the lower main body (131).
6. The fracturing sleeve according to claim 5, characterized in that: The two openings of the pressure transmission hole (135) are respectively opened on the inner wall of the lower transition portion (132) and the shoulder surface of the second shoulder (134).
7. The fracturing sleeve according to any one of claims 1 to 6, characterized in that: A plurality of annular grooves are provided at both axial ends of the inner bushing (12), and a first sealing ring (16) is placed in the groove to form a seal between the inner bushing (12) and the upper joint (11).
8. The fracturing sleeve according to any one of claims 1 to 6, characterized in that: An annular groove is provided on the outer wall of one end of the lower joint (13) in contact with the inner bushing (12), and a second sealing ring (17) is placed in the groove to form a seal between the lower joint (13) and the inner bushing (12).
9. Cementing casing, characterized in that: It comprises a casing (20), a toe-end sliding sleeve (30), a floating collar (40), and a fracturing sleeve (10) as claimed in any one of claims 1 to 8, wherein a plurality of sections of the fracturing sliding sleeve (10) are alternately connected to a plurality of sections of the casing (20) to form a casing string, the lower end of the casing string is connected to the toe-end sliding sleeve (30), and the lower end of the toe-end sliding sleeve (30) is connected to the floating collar (40).
10. A perforation-free staged fracturing method, characterized in that: The method is implemented by using the cementing casing as claimed in claim 9, wherein the cementing casing comprises a fracturing sleeve (10) with a temporary plug (15), and the method specifically comprises the following steps: S1, lowering the cementing casing to a predetermined position in the well and performing normal cementing operations; S2, at the later stage of cementing operation, the cementing plug displaces cement slurry into the annulus between the cementing casing and the wellbore, and cuts off the temporary plug (15) when passing through the internal liner (12), so that the pressure in the pipe is connected to the pressure transmission hole (135) through the temporary plug (15); S3, opening the toe end sliding sleeve (30) by applying pressure at the wellhead, establishing a communication channel between the first section of the pipe and the outside, and completing the first section of the fracturing operation; S4, pumping the soluble bridge plug (50) into the cementing casing to the lower joint (13) of the fracturing sleeve (10) that needs to be opened and above the temporary plug (15), then pressurizing the wellhead so that the upper pressure of the soluble bridge plug (50) is higher than the lower pressure of the soluble bridge plug (50), when the pressure difference reaches a certain value, the thrust generated by the pressure difference shears the shear pin (14), the internal sleeve (12) moves downward, exposing the fracturing channel hole (115), establishing a pressure channel and performing fracturing operations; S5, repeating step S4, opening the fracturing sleeve (10) in sequence from the bottom of the well to the wellhead and performing fracturing operations in each section until the fracturing operation is completed.
Citation Information
Patent Citations
Horizontal well cementing sleeve and method for measuring well cementing quality
CN104563957A
Bridge-plug-free multi-stage fracturing electric control switch intelligent sliding sleeve
CN110805410A
Casing string applying toe end sliding sleeve to full-drift-diameter sliding sleeve and using method thereof
CN111425148A
Toe end sliding sleeve device
CN113803024A
Blowout-prevention working valve barrel
CN201439700U