Distributed intelligent control system, method and related device
Through the intelligent distribution control system, the working parameters of biomass gasification furnaces and gas boilers are adjusted, and the problem of low biomass energy utilization efficiency is solved, and the efficient conversion of biomass energy and the improvement of heating efficiency is achieved.
Patent Information
- Application Number
- CN202411402031.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-09
- Publication Date
- 2024-11-26
AI Technical Summary
The utilization efficiency of biomass energy is not high, and the prior art is difficult to effectively improve the conversion and utilization efficiency of biomass energy.
Adopt a distributed intelligent control system, including biomass gasifier and gas boiler, and obtain target heating demand parameters through the controller, determine and adjust the working parameters of gas boilers and biomass gasifiers to improve the conversion efficiency and supply of biomass Thermal efficiency.
By dynamically adjusting the working parameters of gas boilers and biomass gasifiers, the deep integration of biomass energy can be achieved, the utilization efficiency and heating efficiency of biomass energy can be improved, and the user experience can be improved.
Smart Images

Figure CN119022355A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of intelligent manufacturing technology, and specifically to a distributed intelligent control system, method and related devices. Background Art
[0002] In life, there are many types of biomass, such as crops, weeds, wood, algae, etc. Usually, biomass can be used to convert into biomass energy, which is an important energy source for human survival. Specifically, biomass is first converted into biomass energy, and then converted into thermal energy through a gas boiler to achieve heating. At present, the utilization efficiency of biomass energy is not high. Therefore, how to improve the utilization efficiency of biomass energy needs to be solved urgently. Summary of the invention
[0003] The embodiments of the present application provide a distributed intelligent control system, method and related devices, which can improve the utilization efficiency of biomass energy.
[0004] In a first aspect, an embodiment of the present application provides a distributed intelligent control system, the distributed intelligent control system comprising: a biomass gasifier, a gas boiler, and a controller, wherein: The controller is used to obtain a target heating demand parameter; the target heating demand parameter includes at least one of the following: heating time period, heating purpose, and heating temperature; The gas boiler is used to determine a first operating parameter of the gas boiler corresponding to the target heating demand parameter; The biomass gasifier is used to determine a second operating parameter corresponding to the biomass gasifier according to the first operating parameter, and control the biomass gasifier to operate with the second operating parameter to convert biomass into biomass gas; The gas boiler is further used to operate with the first operating parameter to convert the biomass gas into heat to achieve heating, and collect temperature data of the gas boiler to obtain a plurality of temperature data; The controller is used to adjust the first operating parameter according to the multiple temperature data to obtain a target first operating parameter; adjust the second operating parameter according to the multiple temperature data to obtain a target second operating parameter, and send the target first operating parameter and the target second operating parameter to the gas boiler and the biomass gasifier, respectively, to control the gas boiler to operate with the target first operating parameter and the biomass gasifier to operate with the target second operating parameter.
[0005] In a second aspect, an embodiment of the present application provides a distributed intelligent control method, which is applied to a distributed intelligent control system, wherein the distributed intelligent control system includes: a biomass gasifier, a gas boiler, and a controller, and the method includes: Obtaining a target heating demand parameter through the controller; the target heating demand parameter includes at least one of the following: heating time period, heating purpose, and heating temperature; Determining, by means of the gas boiler, a first operating parameter of the gas boiler corresponding to the target heating demand parameter; Determining, by the biomass gasifier, a second operating parameter corresponding to the biomass gasifier according to the first operating parameter, and controlling the biomass gasifier to operate at the second operating parameter to convert biomass into biomass gas; The gas boiler operates with the first operating parameter to convert the biomass gas into heat to achieve heating, and collects temperature data of the gas boiler to obtain a plurality of temperature data; The controller adjusts the first operating parameter according to the multiple temperature data to obtain a target first operating parameter; the second operating parameter is adjusted according to the multiple temperature data to obtain a target second operating parameter, and the target first operating parameter and the target second operating parameter are sent to the gas boiler and the biomass gasifier respectively to control the gas boiler to operate with the target first operating parameter and the biomass gasifier to operate with the target second operating parameter.
[0006] In a third aspect, an embodiment of the present application provides a distributed intelligent control device, which is applied to a distributed intelligent control system. The distributed intelligent control system includes: a biomass gasifier, a gas boiler, and a controller. The distributed intelligent control device includes: an acquisition unit, a determination unit, a control unit, and an adjustment unit, wherein: The acquisition unit is used to acquire a target heating demand parameter through the controller; the target heating demand parameter includes at least one of the following: heating time period, heating purpose, and heating temperature; The determination unit is used to determine a first operating parameter of the gas boiler corresponding to the target heating demand parameter through the gas boiler; determine a second operating parameter corresponding to the biomass gasifier according to the first operating parameter through the biomass gasifier, and control the biomass gasifier to operate with the second operating parameter to convert biomass into biomass gas; The control unit is used to operate the gas boiler with the first operating parameters to convert the biomass gas into heat to achieve heating, and collect temperature data of the gas boiler to obtain multiple temperature data; The regulating unit is used to regulate the first operating parameter according to the multiple temperature data through the controller to obtain a target first operating parameter; regulate the second operating parameter according to the multiple temperature data to obtain a target second operating parameter, and send the target first operating parameter and the target second operating parameter to the gas boiler and the biomass gasifier, respectively, to control the gas boiler to operate with the target first operating parameter and the biomass gasifier to operate with the target second operating parameter.
[0007] In a fourth aspect, an embodiment of the present application provides an electronic device, comprising a processor, a memory, a communication interface, and one or more programs, wherein the one or more programs are stored in the memory and configured to be executed by the processor, and the program includes instructions for executing the steps in the second aspect of the embodiment of the present application.
[0008] In a fifth aspect, an embodiment of the present application provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program for electronic data exchange, wherein the computer program enables a computer to execute part or all of the steps described in the second aspect of the embodiment of the present application.
[0009] In a sixth aspect, an embodiment of the present application provides a computer program product, wherein the computer program product includes a non-transitory computer-readable storage medium storing a computer program, and the computer program is operable to cause a computer to execute some or all of the steps described in the second aspect of the embodiment of the present application. The computer program product may be a software installation package.
[0010] The implementation of the embodiments of the present application has the following beneficial effects: It can be seen that the distributed intelligent control system, method and related devices described in the embodiments of the present application, the distributed intelligent control system includes: a biomass gasifier, a gas boiler, and a controller, wherein the controller is used to obtain target heating demand parameters; the target heating demand parameters include at least one of the following: heating time period, heating purpose, and heating temperature; the gas boiler is used to determine the first working parameter of the gas boiler corresponding to the target heating demand parameter; the biomass gasifier is used to determine the second working parameter corresponding to the biomass gasifier according to the first working parameter, and control the biomass gasifier to work with the second working parameter to convert the biomass into biomass gas; the gas boiler is also used to work with the first working parameter to convert the biomass gas into heat to achieve heating, and collect temperature data of the gas boiler to obtain multiple temperature data; the controller is used to adjust the first working parameter according to the multiple temperature data to obtain the target first working parameter; the second working parameter is controlled according to the multiple temperature data Adjustment is performed to obtain the target second working parameter, and the target first working parameter and the target second working parameter are sent to the gas boiler and the biomass gasifier respectively, so as to control the gas boiler to work with the target first working parameter and the biomass gasifier to work with the target second working parameter. Firstly, the corresponding working parameters of the gas boiler can be configured based on the heating demand to ensure the heating efficiency. Secondly, the second working parameters corresponding to the biomass gasifier can be determined based on the corresponding working parameters of the gas boiler, and the biomass gasifier and the gas boiler can be controlled to work based on the corresponding working parameters. Thirdly, the temperature data of the gas boiler can be collected. The temperature data reflects the stability and safety of the gas boiler to a certain extent. The working parameters of the biomass gasifier and the gas boiler can be dynamically adjusted based on the stability and safety of the gas boiler, so that the gas boiler and the biomass gasifier are deeply integrated, thereby improving the utilization efficiency of biomass energy based on user needs, ensuring heating efficiency, and improving user experience. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0012] Figure 1 It is a structural schematic diagram of a distributed intelligent control system provided by an embodiment of the present application; Figure 2 It is a flow chart of a distributed intelligent control method provided in an embodiment of the present application; Figure 3 It is a structural schematic diagram of an electronic device provided in an embodiment of the present application; Figure 4 It is a block diagram of the functional units of a distributed intelligent control device provided in an embodiment of the present application. DETAILED DESCRIPTION
[0013] The terms "first", "second", etc. in the specification and claims of this application and the above-mentioned drawings are used to distinguish different objects, rather than to describe a specific order. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but in a possible example also includes steps or units that are not listed, or in a possible example also includes other steps or units inherent to these processes, methods, products or devices.
[0014] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0015] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0016] In the embodiment of the present application, the distributed control system (DCS) is a key component of modern industrial automation and is widely used in many fields such as electricity, chemical industry, petroleum, metallurgy, etc. Of course, it can also be applied to application scenarios related to biomass gas.
[0017] See also Figure 1 , Figure 1 : is a structural schematic diagram of a distributed intelligent control system provided by an embodiment of the present application. As shown in the figure, the distributed intelligent control system includes: a biomass gasifier, a gas boiler, and a controller, wherein: The controller is used to obtain a target heating demand parameter; the target heating demand parameter includes at least one of the following: heating time period, heating purpose, and heating temperature; The gas boiler is used to determine a first operating parameter of the gas boiler corresponding to the target heating demand parameter; The biomass gasifier is used to determine a second operating parameter corresponding to the biomass gasifier according to the first operating parameter, and control the biomass gasifier to operate with the second operating parameter to convert biomass into biomass gas; The gas boiler is further used to operate with the first operating parameter to convert the biomass gas into heat to achieve heating, and collect temperature data of the gas boiler to obtain a plurality of temperature data; The controller is used to adjust the first operating parameter according to the multiple temperature data to obtain a target first operating parameter; adjust the second operating parameter according to the multiple temperature data to obtain a target second operating parameter, and send the target first operating parameter and the target second operating parameter to the gas boiler and the biomass gasifier, respectively, to control the gas boiler to operate with the target first operating parameter and the biomass gasifier to operate with the target second operating parameter.
[0018] In the embodiment of the present application, the target heating demand parameter may include at least one of the following: heating time period, heating purpose, heating temperature, heating range, etc., which are not limited here.
[0019] In a specific implementation, the controller can obtain the target heating demand parameters, and then, based on the heating demand, configure the corresponding working parameters to ensure the heating efficiency.
[0020] The first operating parameter of the gas boiler may include at least one of the following: operating current, operating voltage, operating power, operating pressure, operating mode, etc., which are not limited here.
[0021] The second operating parameter of the biomass gasifier may include at least one of the following: operating current, operating voltage, operating power, operating pressure, operating mode, biomass attribute information, etc., which are not limited here. The biomass attribute information may include at least one of the following: biomass type, biomass particle size, biomass humidity, biomass temperature, biomass feeding speed, biomass purity, etc., which are not limited here.
[0022] In a specific implementation, a mapping relationship between preset heating demand parameters and the operating parameters of the gas boiler can be pre-stored, and then, based on the mapping relationship, the first operating parameter of the gas boiler corresponding to the target heating demand parameter can be determined, and then, based on the heating demand, the corresponding operating parameters can be configured to ensure the heating efficiency.
[0023] Among them, since the gas boiler and the biomass gasifier complement each other and influence each other, the mapping relationship between the preset working parameters of the two can be pre-stored, and then the biomass gasifier can determine the second working parameter of the biomass gasifier corresponding to the first working parameter based on the mapping relationship between the two, and control the biomass gasifier to work with the second working parameter to convert biomass into biomass gas. In this way, based on the correlation between the gas boiler and the biomass gasifier, the working parameters of the biomass gasifier corresponding to the working parameters of the gas boiler can be determined, and the gas boiler and the biomass gasifier can be integrated to ensure heating efficiency and improve user experience. Biomass can include at least one of the following: crops, weeds, wood, algae, etc., which are not limited here.
[0024] Among them, the gas boiler is also used to work with the first working parameters to convert biomass gas into heat to achieve heating. A temperature sensor can be set inside the gas boiler, and the temperature data of the gas boiler is collected through the temperature sensor to obtain multiple temperature data. The temperature data reflects the stability and safety of the gas boiler to a certain extent.
[0025] Next, the controller can adjust the first working parameter according to multiple temperature data to obtain the target first working parameter. In this way, the working parameters of the gas boiler can be dynamically adjusted based on the stability and safety of the gas boiler, making the gas boiler work more stably and safely. The second working parameter can then be adjusted according to multiple temperature data to obtain the target second working parameter, further making the gas boiler work more stably and safely.
[0026] Then, the target first operating parameter and the target second operating parameter can be sent to the gas boiler and the biomass gasifier respectively to control the gas boiler to operate with the target first operating parameter and the biomass gasifier to operate with the target second operating parameter, so that the gas boiler and the biomass gasifier are deeply integrated, thereby ensuring the heating efficiency and improving the user experience.
[0027] In the specific implementation, a centralized control method can be adopted to set up a distributed control system (DCS) to complete the unified monitoring, control, alarm, interlocking protection, etc. of the distributed intelligent control system, that is, the system composed of biomass gasification device + gas boiler, etc., to ensure the safe, reliable and economical operation of the unit.
[0028] Among them, the biomass gasification device is a biomass gasification furnace, and the biomass gasification furnace may include an induced draft fan, a gasification furnace blower, a feeding machine, and a fuel crushing device. The feeding machine provides biomass, the fuel crushing device crushes the biomass, the induced draft fan guides the air, and the gasification furnace blower introduces the air into the cavity of the biomass gasification furnace, so as to realize the chemical reaction between the crushed biomass and the air in the cavity and obtain the corresponding biomass gas.
[0029] The gas boiler may include a boiler blower, through which air is introduced to chemically react the biomass gas with the air to achieve heating.
[0030] Optionally, each of the multiple temperature data corresponds to a sampling moment; in adjusting the first operating parameter according to the multiple temperature data to obtain the target first operating parameter, the controller is specifically used to: Perform fitting according to the plurality of temperature data and corresponding sampling moments to obtain a fitting straight line and a fitting curve; Obtaining a target slope of the fitted straight line; Determine the extreme points of the fitting curve to obtain multiple extreme points; Determining a target mean and a target mean square error of the plurality of extreme value points; Obtaining a reference temperature corresponding to the target heating demand parameter; determining a first deviation between the target mean and the reference temperature; determining a first adjustment parameter corresponding to the first deviation; Adjust the first operating parameter according to the first adjustment parameter to obtain a reference first operating parameter; Determining a first fine-tuning parameter corresponding to the target mean square error; determining a second fine-tuning parameter corresponding to the target slope; Determine a target weight pair according to the multiple extreme value points and the target mean, wherein the target weight pair includes a target first weight and a target second weight; Determine a target fine-tuning parameter according to the target weight pair, the first fine-tuning parameter, and the second fine-tuning parameter; The reference first operating parameter is fine-tuned according to the target fine-tuning parameter to obtain the target first operating parameter.
[0031] In the embodiment of the present application, each temperature data among the multiple temperature data corresponds to a sampling moment, that is, the temperature data can be collected according to a preset time interval, and the preset time interval can be pre-set or system default.
[0032] In a specific implementation, multiple temperature data and corresponding sampling moments can be obtained for fitting, and fitting lines and fitting curves can be obtained, wherein each temperature data and the corresponding sampling moment can be regarded as a coordinate point, and multiple temperature data and corresponding sampling moments can be regarded as multiple coordinate points, and then the multiple coordinate points are projected to a coordinate system, the horizontal axis of which is time and the vertical axis is temperature data, and then the multiple coordinate points are fitted to obtain fitting curves and fitting lines. The fitting curve reflects the working stability of the gas boiler, and the fitting line reflects the stability change trend of the gas boiler.
[0033] Among them, the target slope of the fitting line can be obtained, and the target slope reflects the stability change trend of the gas boiler. In the specific implementation, the extreme points of the fitting curve can be determined to obtain multiple extreme points, which can include maximum and minimum points. Then, the target mean and target mean square error of multiple extreme points can be determined. The mean reflects the average temperature data, and the mean square error reflects the working stability of the gas boiler.
[0034] Of course, the reference temperature corresponding to the target heating demand parameter can also be obtained. Different heating demand parameters can correspond to different temperatures. The first deviation between the target mean and the reference temperature can also be determined. The first deviation = (target mean - reference temperature) / reference temperature. The first deviation reflects the gap between the actual temperature and the heating demand, and also reflects the adjustment direction to a certain extent. Then, the mapping relationship between the preset deviation and the adjustment parameter can be pre-stored. Then, based on the mapping relationship, the first adjustment parameter corresponding to the first deviation can be determined, and then the first working parameter can be adjusted according to the first adjustment parameter to obtain the reference first working parameter. The reference first working parameter = (1 + first adjustment parameter) * first working parameter. In this way, the heating demand can be further met and the control intelligence and control accuracy of the distributed intelligent control system can be improved.
[0035] In a specific implementation, a mapping relationship between a preset mean square error and a fine-tuning parameter can be pre-stored, and then a first fine-tuning parameter corresponding to a target mean square error can be determined based on the mapping relationship. A mapping relationship between a preset slope and a fine-tuning parameter can also be pre-stored, and a second fine-tuning parameter corresponding to the target slope can be determined based on the mapping relationship. To a certain extent, the mean square error reflects the working stability of the gas boiler, and the slope reflects the stability change trend of the gas boiler.
[0036] Next, a target weight pair can be determined based on multiple extreme points and a target mean, the target weight pair including a target first weight and a target second weight. Specifically, a first number of extreme points that is less than the target mean and a second number of extreme points that is greater than or equal to the target mean can be determined. The target first weight and the target second weight are determined based on the first number and the second number, that is, the target first weight = the first number / (the first number+the second number), the target second weight = the second number / (the first number+the second number), and then the target fine-tuning parameter is determined based on the target weight pair, the first fine-tuning parameter, and the second fine-tuning parameter. The target fine-tuning parameter = the first fine-tuning parameter * the target first weight + the second fine-tuning parameter * the target second weight. The target mean is to a certain extent It can be regarded as a baseline, based on which the working stability of the gas boiler can be further determined, and then the weight pair can be accurately determined based on the working stability of the gas boiler. Based on the weight pair, the working stability of the gas boiler and the stability change trend of the gas boiler can be accurately quantified as fine-tuning parameters. Finally, the reference first working parameter can be fine-tuned according to the target fine-tuning parameter to obtain the target first working parameter. The target first working parameter = (target fine-tuning parameter + 1) * reference first working parameter. In this way, the working parameters of the gas boiler can be deeply adjusted on the basis of ensuring the stability of the gas boiler, making it more stable and better meeting the heating demand, which helps to improve the control intelligence and control accuracy of the distributed intelligent control system.
[0037] Optionally, in the aspect of adjusting the second operating parameter according to the plurality of temperature data to obtain a target second operating parameter, the biomass gasifier is specifically used for: Determine the absolute value of the difference between two adjacent temperature data in the plurality of temperature data to obtain a plurality of temperature absolute difference values; determining a minimum value among the plurality of absolute temperature differences; Obtaining the target sampling time corresponding to the minimum value; Acquire temperature data located after the target sampling time among the plurality of temperature data to obtain at least one temperature data; determining a target standard deviation for the at least one temperature data; Determining a target optimization parameter corresponding to the target standard deviation; The second operating parameter is optimized according to the target optimization parameter to obtain the target second operating parameter.
[0038] In an embodiment of the present application, the absolute value of the difference between two adjacent temperature data in a plurality of temperature data can be determined to obtain a plurality of absolute temperature differences, that is, the temperature data at a previous sampling moment can be subtracted from the temperature data at a later sampling moment to obtain a corresponding temperature difference, and then the absolute value of the temperature difference is taken to obtain the absolute temperature difference, and then the minimum value among the plurality of absolute temperature differences is determined, and the target sampling moment corresponding to the minimum value is obtained. The target sampling moment corresponding to the minimum value reflects the starting moment when the gas boiler tends to a stable state. Then, the temperature data located after the target sampling moment in the plurality of temperature data can be obtained to obtain at least one temperature data. The at least one temperature data is the temperature data of the gas boiler in a stable working state, and to a certain extent, it can reflect the working stability of the gas boiler.
[0039] Next, a target standard deviation of at least one temperature data can be determined, and a mapping relationship between a preset standard deviation and an optimization parameter can be pre-stored. Furthermore, a target optimization parameter corresponding to the target standard deviation can be determined based on the mapping relationship, and then the second working parameter can be optimized according to the target optimization parameter to obtain a target second working parameter, where the target second working parameter = (1 + target optimization parameter) * reference second working parameter. In this way, while ensuring the stability of the gas boiler, the working parameters of the biomass gasifier can be deeply adjusted to make it more stable and better meet the heating demand, which helps to improve the control intelligence and control accuracy of the distributed intelligent control system.
[0040] Optionally, in determining the first operating parameter of the gas boiler corresponding to the target heating demand parameter, the gas boiler is specifically used for: Determining the reference operating parameters corresponding to the target heating demand parameters according to the mapping relationship between the preset heating demand parameters and the operating parameters of the gas boiler; Acquire a first attribute parameter of the gas boiler; Determining a target delivery pipeline between the biomass gasifier and the gas boiler; Acquire target pipeline parameters corresponding to the target delivery pipeline; determining a first compensation parameter corresponding to the first attribute parameter; determining a second compensation parameter corresponding to the target pipeline parameter; The reference operating parameter is compensated by using the first compensation parameter and the second compensation parameter to obtain the first operating parameter.
[0041] In a specific implementation, the mapping relationship between the preset heating demand parameters and the working parameters of the gas boiler can be pre-stored, and then the reference working parameters corresponding to the target heating demand parameters can be determined according to the mapping relationship between the preset heating demand parameters and the working parameters of the gas boiler. In this way, the working parameters of the gas boiler corresponding to the user's needs can be preliminarily obtained.
[0042] The first attribute parameter of the gas boiler may include at least one of the following: the model of the gas boiler, the volume of the gas boiler, the internal structure parameters of the gas boiler, the energy conversion rate of the gas boiler, etc., which are not limited here.
[0043] In a specific implementation, the first attribute parameter of the gas boiler can also be obtained, and the target delivery pipeline between the biomass gasifier and the gas boiler can be determined, and then the target pipeline parameters corresponding to the target delivery pipeline can be obtained, wherein the target pipeline parameters can include at least one of the following: pipeline length, pipeline diameter, pipeline material, pipeline structure, pipeline thickness, etc., which are not limited here.
[0044] In a specific implementation, a mapping relationship between preset property parameters and compensation parameters can be pre-stored, and a first compensation parameter corresponding to the first property parameter can be determined based on the mapping relationship. A mapping relationship between preset pipeline parameters and compensation parameters can also be pre-stored, and a second compensation parameter corresponding to the target pipeline parameter can be determined based on the mapping relationship. Then, the reference working parameter can be compensated by the first compensation parameter and the second compensation parameter to obtain the first working parameter, that is, the first working parameter = (1 + first compensation parameter) * (1 + second compensation parameter) * reference working parameter.
[0045] In the embodiment of the present application, the first attribute parameter of the gas boiler is the performance of the gas boiler to a certain extent, and its performance affects its energy conversion rate to a certain extent. The target pipeline parameter corresponding to the target delivery pipeline reflects to a certain extent the delivery efficiency of the biomass gas and the connection performance between the biomass gasifier and the gas boiler. Furthermore, the working parameters of the gas boiler corresponding to the heating demand parameters can be compensated in combination with the gas boiler's own performance, the biomass gas delivery efficiency, and the connection performance between the biomass gasifier and the gas boiler, so that the working parameters of the compensated gas boiler are deeply consistent with its own conditions and connection conditions, which helps to integrate the gas boiler with the biomass gasifier, realize the linkage between the gas boiler and the biomass gasifier, ensure the heating efficiency, and improve the user experience.
[0046] Optionally, in determining the second operating parameter corresponding to the biomass gasifier according to the first operating parameter, the biomass gasifier is specifically used for: Determining the initial operating parameters corresponding to the biomass gasifier according to the first operating parameters; Acquiring a second attribute parameter of the biomass gasifier; Obtaining target environmental parameters of the biomass gasifier; determining a first influence coefficient corresponding to the second attribute parameter; determining a second influence coefficient corresponding to the target environmental parameter; A second operating parameter corresponding to the biomass gasifier is determined according to the first influence coefficient, the second influence coefficient and the initial operating parameter.
[0047] Among them, since the gas boiler and the biomass gasifier complement each other and influence each other, the preset mapping relationship between the working parameters of the two can be pre-stored, and then the biomass gasifier can determine the initial working parameters of the biomass gasifier corresponding to the first working parameter based on the mapping relationship between the two.
[0048] The second attribute parameter of the biomass gasifier may include at least one of the following: the model of the biomass gasifier, the internal structure of the biomass gasifier, the volume of the biomass gasifier, the weight of the biomass gasifier, etc., which are not limited here. The target environmental parameter of the biomass gasifier may include at least one of the following: ambient temperature, ambient humidity, internal pressure parameter, internal material, etc., which are not limited here.
[0049] In a specific implementation, the second attribute parameter of the biomass gasifier can be obtained, the target environmental parameter of the biomass gasifier can be obtained, and the mapping relationship between the preset attribute parameter of the biomass gasifier and the influence coefficient can be pre-stored. Then, the first influence coefficient corresponding to the second attribute parameter can be determined based on the mapping relationship, and the mapping relationship between the preset environmental parameter and the influence coefficient can be pre-stored. The second influence coefficient corresponding to the target environmental parameter can be determined based on the mapping relationship, and then the second working parameter corresponding to the biomass gasifier can be determined according to the first influence coefficient, the second influence coefficient and the initial working parameter, that is, the second working parameter corresponding to the biomass gasifier = (1 + first influence coefficient) * (1 + second influence coefficient) * initial working parameter. On the one hand, Since the gas boiler and the biomass gasifier complement each other and influence each other, the working parameters of the corresponding biomass gasifier can be adapted based on the working parameters of the gas boiler, thereby deeply integrating the gas boiler and the biomass gasifier. On the other hand, since the attribute parameters of the biomass gasifier reflect the performance of the biomass gasifier to a certain extent, the environmental parameters of the biomass gasifier reflect its working environment to a certain extent, and the working environment determines the biomass gasification capacity of the biomass gasifier to a certain extent, therefore, the working parameters of the biomass gasifier can be accurately optimized based on the performance of the biomass gasifier and the actual environment, so that the final working parameters of the biomass gasifier are in line with the actual situation, thereby ensuring the heating efficiency and improving the user experience.
[0050] Optionally, the biomass gasifier further includes a catalyst supply module, and the biomass gasifier is further specifically used for: determining a first catalyst corresponding to the current biomass; Obtaining a target internal pressure parameter of the biomass gasifier; determining a first supply parameter of the first catalyst corresponding to the second operating parameter; Determining a first feedback adjustment parameter corresponding to the target environmental parameter; determining a second feedback adjustment parameter corresponding to the target internal pressure parameter; Adjust the first supply parameter according to the first feedback adjustment parameter and the second feedback adjustment parameter to obtain a second supply parameter; The catalyst supply module is controlled to supply the first catalyst with the second supply parameter.
[0051] Among them, the first supply parameter may include at least one of the following: supply frequency, supply speed, supply dosage, supply position, supply duration, supply cycle, supply temperature, supply area, etc., which are not limited here.
[0052] In the embodiment of the present application, different biomasses may use different catalysts. The catalyst can increase the speed of chemical reactions to a certain extent. Specifically, a preset mapping relationship between biomass and catalysts may be pre-stored, and then the first catalyst corresponding to the current biomass may be determined based on the mapping relationship.
[0053] Of course, the target internal pressure parameters of the biomass gasifier can also be obtained. Different working parameters of biomass gasifiers require different catalysts. Therefore, the mapping relationship between the preset working parameters of the biomass gasifier and the supply parameters of the first catalyst can be pre-stored. Then, the first supply parameters of the first catalyst corresponding to the second working parameters can be determined based on the mapping relationship.
[0054] Then, the mapping relationship between the preset environmental parameters and the feedback adjustment parameters can be pre-stored, and the first feedback adjustment parameters corresponding to the target environmental parameters can be determined based on the mapping relationship. In addition, the mapping relationship between the preset internal pressure parameters and the feedback adjustment parameters can be pre-stored, and then the second feedback adjustment parameters corresponding to the target internal pressure parameters can be determined based on the mapping relationship. The first supply parameter can be adjusted according to the first feedback adjustment parameter and the second feedback adjustment parameter to obtain the second supply parameter, that is, the second supply parameter = (1 + first feedback adjustment parameter) * (1 + second feedback adjustment parameter) * first supply parameter. Finally, the catalyst supply module can be controlled to supply the first catalyst with the second supply parameter. Not only can the first supply parameter of the corresponding first catalyst be configured based on the working parameters of the biomass gasifier, but also the environmental parameters reflect its working environment to a certain extent, and the internal pressure parameters reflect the working stability of the biomass gasifier to a certain extent. Then, the catalyst supply parameters can be dynamically feedback-adjusted in combination with the working environment and working stability of the biomass gasifier, thereby further improving the working efficiency of the biomass gasifier. In this way, it is helpful to ensure that the biomass can produce chemical reactions under the best catalytic effect, thereby ensuring the production efficiency of the biomass gas and the intelligence of the distributed intelligent control system.
[0055] It can be seen that the distributed intelligent control system described in the embodiment of the present application includes: a biomass gasifier, a gas boiler, and a controller, wherein the controller is used to obtain target heating demand parameters; the target heating demand parameters include at least one of the following: heating time period, heating purpose, and heating temperature; the gas boiler is used to determine the first working parameter of the gas boiler corresponding to the target heating demand parameter; the biomass gasifier is used to determine the second working parameter corresponding to the biomass gasifier according to the first working parameter, and control the biomass gasifier to work with the second working parameter to convert the biomass into biomass gas; the gas boiler is also used to work with the first working parameter to convert the biomass gas into heat to achieve heating, and collect temperature data of the gas boiler to obtain multiple temperature data; the controller is used to adjust the first working parameter according to the multiple temperature data to obtain the target first working parameter; adjust the second working parameter according to the multiple temperature data, The target second working parameter is obtained, and the target first working parameter and the target second working parameter are sent to the gas boiler and the biomass gasifier respectively, so as to control the gas boiler to work with the target first working parameter and the biomass gasifier to work with the target second working parameter. Firstly, the corresponding working parameters of the gas boiler can be configured based on the heating demand to ensure the heating efficiency. Secondly, the second working parameters corresponding to the biomass gasifier can be determined based on the corresponding working parameters of the gas boiler, and the biomass gasifier and the gas boiler can be controlled to work based on the corresponding working parameters. Thirdly, the temperature data of the gas boiler can be collected. The temperature data reflects the stability and safety of the gas boiler to a certain extent. The working parameters of the biomass gasifier and the gas boiler can be dynamically adjusted based on the stability and safety of the gas boiler, so that the gas boiler and the biomass gasifier are deeply integrated, thereby improving the utilization efficiency of biomass energy based on user needs, ensuring heating efficiency, and improving user experience.
[0056] See also Figure 2 , Figure 2 is a flow chart of a distributed intelligent control method provided by an embodiment of the present application, which is applied to Figure 1 The distributed intelligent control system shown in the figure includes: a biomass gasifier, a gas boiler, and a controller; as shown in the figure, the distributed intelligent control method includes: 201. Obtain target heating demand parameters through the controller; the target heating demand parameters include at least one of the following: heating time period, heating purpose, and heating temperature.
[0057] 202. Determine, by means of the gas boiler, a first operating parameter of the gas boiler corresponding to the target heating demand parameter.
[0058] 203. Determine, by the biomass gasifier, a second operating parameter corresponding to the biomass gasifier according to the first operating parameter, and control the biomass gasifier to operate with the second operating parameter to convert biomass into biomass gas.
[0059] 204. Operate the gas boiler with the first operating parameter to convert the biomass gas into heat to provide heat, and collect temperature data of the gas boiler to obtain a plurality of temperature data.
[0060] 205. The controller adjusts the first operating parameter according to the multiple temperature data to obtain a target first operating parameter; adjusts the second operating parameter according to the multiple temperature data to obtain a target second operating parameter, and sends the target first operating parameter and the target second operating parameter to the gas boiler and the biomass gasifier, respectively, to control the gas boiler to operate with the target first operating parameter and the biomass gasifier to operate with the target second operating parameter.
[0061] The specific description of the above steps 201 to 205 can refer to the above Figure 1 The description of the distributed intelligent control system described will not be repeated here.
[0062] It can be seen that the distributed intelligent control method described in the embodiment of the present application is applied to a distributed intelligent control system, which includes: a biomass gasifier, a gas boiler, and a controller, wherein the controller is used to obtain target heating demand parameters; the target heating demand parameters include at least one of the following: heating time period, heating purpose, and heating temperature; the gas boiler is used to determine the first working parameter of the gas boiler corresponding to the target heating demand parameter; the biomass gasifier is used to determine the second working parameter corresponding to the biomass gasifier according to the first working parameter, and control the biomass gasifier to work with the second working parameter to convert the biomass into biomass gas; the gas boiler is also used to work with the first working parameter to convert the biomass gas into heat to achieve heating, and collect temperature data of the gas boiler to obtain multiple temperature data; the controller is used to adjust the first working parameter according to the multiple temperature data to obtain the target first working parameter; the second working parameter is controlled according to the multiple temperature data The parameters are adjusted to obtain the target second working parameters, and the target first working parameters and the target second working parameters are sent to the gas boiler and the biomass gasifier respectively, so as to control the gas boiler to work with the target first working parameters and the biomass gasifier to work with the target second working parameters. Firstly, the corresponding working parameters of the gas boiler can be configured based on the heating demand to ensure the heating efficiency. Secondly, the second working parameters corresponding to the biomass gasifier can be determined based on the corresponding working parameters of the gas boiler, and the biomass gasifier and the gas boiler can be controlled to work based on the corresponding working parameters. Thirdly, the temperature data of the gas boiler can be collected. The temperature data reflects the stability and safety of the gas boiler to a certain extent. The working parameters of the biomass gasifier and the gas boiler can be dynamically adjusted based on the stability and safety of the gas boiler, so that the gas boiler and the biomass gasifier are deeply integrated, thereby improving the utilization efficiency of biomass energy based on user needs, ensuring heating efficiency, and improving user experience.
[0063] In accordance with the above embodiment, please refer to Figure 3 , Figure 3 It is a structural schematic diagram of an electronic device provided in an embodiment of the present application. As shown in the figure, the electronic device includes a processor, a memory, a communication interface and one or more programs, wherein the one or more programs are stored in the memory and configured to be executed by the processor. In the embodiment of the present application, the electronic device is applied to a distributed intelligent control system, and the distributed intelligent control system includes: a biomass gasifier, a gas boiler, and a controller. The program includes instructions for executing the following steps: Obtaining a target heating demand parameter through the controller; the target heating demand parameter includes at least one of the following: heating time period, heating purpose, and heating temperature; Determining, by means of the gas boiler, a first operating parameter of the gas boiler corresponding to the target heating demand parameter; Determining, by the biomass gasifier, a second operating parameter corresponding to the biomass gasifier according to the first operating parameter, and controlling the biomass gasifier to operate at the second operating parameter to convert biomass into biomass gas; The gas boiler operates with the first operating parameter to convert the biomass gas into heat to achieve heating, and collects temperature data of the gas boiler to obtain a plurality of temperature data; The controller adjusts the first operating parameter according to the multiple temperature data to obtain a target first operating parameter; the second operating parameter is adjusted according to the multiple temperature data to obtain a target second operating parameter, and the target first operating parameter and the target second operating parameter are sent to the gas boiler and the biomass gasifier respectively to control the gas boiler to operate with the target first operating parameter and the biomass gasifier to operate with the target second operating parameter.
[0064] Optionally, each of the plurality of temperature data corresponds to a sampling moment; in the aspect of adjusting the first operating parameter according to the plurality of temperature data to obtain the target first operating parameter, the program includes instructions for executing the following steps: Perform fitting according to the plurality of temperature data and corresponding sampling moments to obtain a fitting straight line and a fitting curve; Obtaining a target slope of the fitted straight line; Determine the extreme points of the fitting curve to obtain multiple extreme points; Determining a target mean and a target mean square error of the plurality of extreme value points; Obtaining a reference temperature corresponding to the target heating demand parameter; determining a first deviation between the target mean and the reference temperature; determining a first adjustment parameter corresponding to the first deviation; Adjust the first operating parameter according to the first adjustment parameter to obtain a reference first operating parameter; Determining a first fine-tuning parameter corresponding to the target mean square error; determining a second fine-tuning parameter corresponding to the target slope; Determine a target weight pair according to the multiple extreme value points and the target mean, wherein the target weight pair includes a target first weight and a target second weight; Determine a target fine-tuning parameter according to the target weight pair, the first fine-tuning parameter, and the second fine-tuning parameter; The reference first operating parameter is fine-tuned according to the target fine-tuning parameter to obtain the target first operating parameter.
[0065] Optionally, in the aspect of adjusting the second operating parameter according to the plurality of temperature data to obtain a target second operating parameter, the program includes instructions for executing the following steps: Determine the absolute value of the difference between two adjacent temperature data in the plurality of temperature data to obtain a plurality of temperature absolute difference values; determining a minimum value among the plurality of absolute temperature differences; Obtaining the target sampling time corresponding to the minimum value; Acquire temperature data located after the target sampling time among the plurality of temperature data to obtain at least one temperature data; determining a target standard deviation for the at least one temperature data; Determining a target optimization parameter corresponding to the target standard deviation; The second operating parameter is optimized according to the target optimization parameter to obtain the target second operating parameter.
[0066] Optionally, in determining the first operating parameter of the gas boiler corresponding to the target heating demand parameter, the gas boiler is specifically used for: Determining the reference operating parameters corresponding to the target heating demand parameters according to the mapping relationship between the preset heating demand parameters and the operating parameters of the gas boiler; Acquire a first attribute parameter of the gas boiler; Determining a target delivery pipeline between the biomass gasifier and the gas boiler; Acquire target pipeline parameters corresponding to the target delivery pipeline; determining a first compensation parameter corresponding to the first attribute parameter; determining a second compensation parameter corresponding to the target pipeline parameter; The reference operating parameter is compensated by using the first compensation parameter and the second compensation parameter to obtain the first operating parameter.
[0067] Optionally, in determining the second operating parameter corresponding to the biomass gasifier according to the first operating parameter, the program includes instructions for executing the following steps: Determining the initial operating parameters corresponding to the biomass gasifier according to the first operating parameters; Acquiring a second attribute parameter of the biomass gasifier; Obtaining target environmental parameters of the biomass gasifier; determining a first influence coefficient corresponding to the second attribute parameter; determining a second influence coefficient corresponding to the target environmental parameter; A second operating parameter corresponding to the biomass gasifier is determined according to the first influence coefficient, the second influence coefficient and the initial operating parameter.
[0068] It can be seen that the electronic device described in the embodiment of the present application is applied to a distributed intelligent control system, which includes: a biomass gasifier, a gas boiler, and a controller, wherein the controller is used to obtain a target heating demand parameter; the target heating demand parameter includes at least one of the following: a heating time period, a heating purpose, and a heating temperature; the gas boiler is used to determine a first working parameter of the gas boiler corresponding to the target heating demand parameter; the biomass gasifier is used to determine a second working parameter corresponding to the biomass gasifier according to the first working parameter, and control the biomass gasifier to operate with the second working parameter to convert the biomass into biomass gas; the gas boiler is also used to operate with the first working parameter to convert the biomass gas into heat to achieve heating, and collect temperature data of the gas boiler to obtain multiple temperature data; the controller is used to adjust the first working parameter according to the multiple temperature data to obtain the target first working parameter; the second working parameter is adjusted according to the multiple temperature data Adjustment is performed to obtain the target second working parameter, and the target first working parameter and the target second working parameter are sent to the gas boiler and the biomass gasifier respectively, so as to control the gas boiler to work with the target first working parameter and the biomass gasifier to work with the target second working parameter. Firstly, the corresponding working parameters of the gas boiler can be configured based on the heating demand to ensure the heating efficiency. Secondly, the second working parameters corresponding to the biomass gasifier can be determined based on the corresponding working parameters of the gas boiler, and the biomass gasifier and the gas boiler can be controlled to work based on the corresponding working parameters. Thirdly, the temperature data of the gas boiler can be collected. The temperature data reflects the stability and safety of the gas boiler to a certain extent. The working parameters of the biomass gasifier and the gas boiler can be dynamically adjusted based on the stability and safety of the gas boiler, so that the gas boiler and the biomass gasifier are deeply integrated, thereby improving the utilization efficiency of biomass energy based on user needs, ensuring heating efficiency, and improving user experience.
[0069] Among them, the electronic device may include a processor, a control platform, a server, etc., which is not limited here.
[0070] Figure 4 It is a functional unit composition block diagram of a distributed intelligent control device 400 involved in an embodiment of the present application, which is applied to a distributed intelligent control system. The distributed intelligent control system includes: a biomass gasifier, a gas boiler, and a controller. The distributed intelligent control device 400 includes: an acquisition unit 401, a determination unit 402, a control unit 403 and an adjustment unit 404, wherein: The acquisition unit 401 is used to acquire a target heating demand parameter through the controller; the target heating demand parameter includes at least one of the following: heating time period, heating purpose, and heating temperature; The determining unit 402 is used to determine, through the gas boiler, a first operating parameter of the gas boiler corresponding to the target heating demand parameter; determine, through the biomass gasifier according to the first operating parameter, a second operating parameter corresponding to the biomass gasifier, and control the biomass gasifier to operate with the second operating parameter to convert biomass into biomass gas; The control unit 403 is used to operate the gas boiler with the first operating parameters to convert the biomass gas into heat to achieve heating, and collect temperature data of the gas boiler to obtain multiple temperature data; The regulating unit 404 is used to regulate the first operating parameter according to the multiple temperature data through the controller to obtain a target first operating parameter; regulate the second operating parameter according to the multiple temperature data to obtain a target second operating parameter, and send the target first operating parameter and the target second operating parameter to the gas boiler and the biomass gasifier, respectively, to control the gas boiler to operate with the target first operating parameter and the biomass gasifier to operate with the target second operating parameter.
[0071] Optionally, each of the multiple temperature data corresponds to a sampling time; in adjusting the first operating parameter according to the multiple temperature data to obtain the target first operating parameter, the adjusting unit 404 is specifically used to: Perform fitting according to the plurality of temperature data and corresponding sampling moments to obtain a fitting straight line and a fitting curve; Obtaining a target slope of the fitted straight line; Determine the extreme points of the fitting curve to obtain multiple extreme points; Determining a target mean and a target mean square error of the plurality of extreme value points; Obtaining a reference temperature corresponding to the target heating demand parameter; determining a first deviation between the target mean and the reference temperature; determining a first adjustment parameter corresponding to the first deviation; Adjust the first operating parameter according to the first adjustment parameter to obtain a reference first operating parameter; Determining a first fine-tuning parameter corresponding to the target mean square error; determining a second fine-tuning parameter corresponding to the target slope; Determine a target weight pair according to the multiple extreme value points and the target mean, wherein the target weight pair includes a target first weight and a target second weight; Determine a target fine-tuning parameter according to the target weight pair, the first fine-tuning parameter, and the second fine-tuning parameter; The reference first operating parameter is fine-tuned according to the target fine-tuning parameter to obtain the target first operating parameter.
[0072] Optionally, in the aspect of adjusting the second operating parameter according to the plurality of temperature data to obtain a target second operating parameter, the adjusting unit 404 is specifically configured to: Determine the absolute value of the difference between two adjacent temperature data in the plurality of temperature data to obtain a plurality of temperature absolute difference values; determining a minimum value among the plurality of absolute temperature differences; Obtaining the target sampling time corresponding to the minimum value; Acquire temperature data located after the target sampling time among the plurality of temperature data to obtain at least one temperature data; determining a target standard deviation for the at least one temperature data; Determining a target optimization parameter corresponding to the target standard deviation; The second operating parameter is optimized according to the target optimization parameter to obtain the target second operating parameter.
[0073] Optionally, in determining the first operating parameter of the gas boiler corresponding to the target heating demand parameter, the determining unit 402 is specifically configured to: Determining the reference operating parameters corresponding to the target heating demand parameters according to the mapping relationship between the preset heating demand parameters and the operating parameters of the gas boiler; Acquire a first attribute parameter of the gas boiler; Determining a target delivery pipeline between the biomass gasifier and the gas boiler; Acquire target pipeline parameters corresponding to the target delivery pipeline; determining a first compensation parameter corresponding to the first attribute parameter; determining a second compensation parameter corresponding to the target pipeline parameter; The reference operating parameter is compensated by using the first compensation parameter and the second compensation parameter to obtain the first operating parameter.
[0074] Optionally, in determining the second operating parameter corresponding to the biomass gasifier according to the first operating parameter, the determining unit 402 is specifically configured to: Determining the initial operating parameters corresponding to the biomass gasifier according to the first operating parameters; Acquiring a second attribute parameter of the biomass gasifier; Obtaining target environmental parameters of the biomass gasifier; determining a first influence coefficient corresponding to the second attribute parameter; determining a second influence coefficient corresponding to the target environmental parameter; A second operating parameter corresponding to the biomass gasifier is determined according to the first influence coefficient, the second influence coefficient and the initial operating parameter.
[0075] It can be seen that the distributed intelligent control device described in the embodiment of the present application is applied to a distributed intelligent control system, and the distributed intelligent control system includes: a biomass gasifier, a gas boiler, and a controller, wherein the controller is used to obtain a target heating demand parameter; the target heating demand parameter includes at least one of the following: a heating time period, a heating purpose, and a heating temperature; the gas boiler is used to determine a first working parameter of the gas boiler corresponding to the target heating demand parameter; the biomass gasifier is used to determine a second working parameter corresponding to the biomass gasifier according to the first working parameter, and control the biomass gasifier to operate with the second working parameter to convert the biomass into biomass gas; the gas boiler is also used to operate with the first working parameter to convert the biomass gas into heat to achieve heating, and collect temperature data of the gas boiler to obtain multiple temperature data; the controller is used to adjust the first working parameter according to the multiple temperature data to obtain the target first working parameter; The second working parameter is adjusted to obtain the target second working parameter, and the target first working parameter and the target second working parameter are sent to the gas boiler and the biomass gasifier respectively to control the gas boiler to work with the target first working parameter and the biomass gasifier to work with the target second working parameter. Firstly, based on the heating demand, the corresponding working parameters of the gas boiler can be configured to ensure the heating efficiency. Secondly, based on the corresponding working parameters of the gas boiler, the second working parameter corresponding to the biomass gasifier can be determined, and the biomass gasifier and the gas boiler can be controlled to work based on the corresponding working parameters. Thirdly, the temperature data of the gas boiler can be collected. The temperature data reflects the stability and safety of the gas boiler to a certain extent. The working parameters of the biomass gasifier and the gas boiler can be dynamically adjusted based on the stability and safety of the gas boiler, so that the gas boiler and the biomass gasifier are deeply integrated, thereby improving the utilization efficiency of biomass energy based on user needs, ensuring heating efficiency, and improving user experience.
[0076] It can be understood that the functions of each program module of the distributed intelligent control device of this embodiment can be specifically implemented according to the method in the above method embodiment. The specific implementation process can refer to the relevant description of the above method embodiment, which will not be repeated here.
[0077] An embodiment of the present application also provides a computer storage medium, wherein the computer storage medium stores a computer program for electronic data exchange, wherein the computer program enables a computer to execute part or all of the steps of any method described in the above method embodiments, and the above computer includes an electronic device.
[0078] The embodiment of the present application also provides a computer program product, the computer program product includes a non-transitory computer-readable storage medium storing a computer program, the computer program is operable to cause a computer to execute some or all of the steps of any method described in the method embodiment. The computer program product may be a software installation package, and the computer includes an electronic device.
[0079] It should be noted that, for the aforementioned method embodiments, for the sake of simplicity, they are all expressed as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the described order of actions, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required by the present application.
[0080] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0081] In the several embodiments provided in the present application, it should be understood that the disclosed device can be implemented in other ways. For example, the device embodiments described above are only schematic, such as the division of the above-mentioned units, which is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, and the indirect coupling or communication connection of devices or units can be electrical or other forms.
[0082] The units described above as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0083] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0084] If the above-mentioned integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable memory. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product. The computer software product is stored in a memory, including a number of instructions to enable a computer device (which can be a personal computer, server or network device, etc.) to execute all or part of the steps of the above-mentioned methods in each embodiment of the present application. The aforementioned memory includes: U disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), mobile hard disk, disk or optical disk and other media that can store program codes.
[0085] Those skilled in the art will appreciate that all or part of the steps in the various methods of the above embodiments may be completed by instructing related hardware through a program, and the program may be stored in a computer-readable memory, which may include a flash drive, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk, etc.
[0086] The embodiments of the present application are introduced in detail above. Specific examples are used in this article to illustrate the principles and implementation methods of the present application. The description of the above embodiments is only used to help understand the method and core idea of the present application. At the same time, for general technical personnel in this field, according to the idea of the present application, there will be changes in the specific implementation method and application scope. In summary, the content of this specification should not be understood as a limitation on the present application.
Claims
1. A distributed intelligent control system, It is characterized in that The distributed intelligent control system includes: a biomass gasifier, a gas boiler, and a controller, wherein: The controller is used to obtain a target heating demand parameter; the target heating demand parameter includes at least one of the following: heating time period, heating purpose, and heating temperature; The gas boiler is used to determine a first operating parameter of the gas boiler corresponding to the target heating demand parameter; The biomass gasifier is used to determine a second operating parameter corresponding to the biomass gasifier according to the first operating parameter, and control the biomass gasifier to operate with the second operating parameter to convert biomass into biomass gas; The gas boiler is further used to operate with the first operating parameter to convert the biomass gas into heat to achieve heating, and collect temperature data of the gas boiler to obtain a plurality of temperature data; The controller is used to adjust the first operating parameter according to the multiple temperature data to obtain a target first operating parameter; adjust the second operating parameter according to the multiple temperature data to obtain a target second operating parameter, and send the target first operating parameter and the target second operating parameter to the gas boiler and the biomass gasifier, respectively, to control the gas boiler to operate with the target first operating parameter and the biomass gasifier to operate with the target second operating parameter.
2. The system according to claim 1, It is characterized in that Each temperature data in the plurality of temperature data corresponds to a sampling time; in terms of adjusting the first operating parameter according to the plurality of temperature data to obtain the target first operating parameter, the controller is specifically used to: Perform fitting according to the plurality of temperature data and corresponding sampling moments to obtain a fitting straight line and a fitting curve; Obtaining a target slope of the fitted straight line; Determine the extreme points of the fitting curve to obtain multiple extreme points; Determining a target mean and a target mean square error of the plurality of extreme value points; Obtaining a reference temperature corresponding to the target heating demand parameter; determining a first deviation between the target mean and the reference temperature; determining a first adjustment parameter corresponding to the first deviation; Adjust the first operating parameter according to the first adjustment parameter to obtain a reference first operating parameter; Determining a first fine-tuning parameter corresponding to the target mean square error; determining a second fine-tuning parameter corresponding to the target slope; Determine a target weight pair according to the multiple extreme value points and the target mean, wherein the target weight pair includes a target first weight and a target second weight; Determine a target fine-tuning parameter according to the target weight pair, the first fine-tuning parameter, and the second fine-tuning parameter; The reference first operating parameter is fine-tuned according to the target fine-tuning parameter to obtain the target first operating parameter.
3. The system according to claim 2, It is characterized in that In the aspect of adjusting the second operating parameter according to the plurality of temperature data to obtain the target second operating parameter, the biomass gasifier is specifically used for: Determine the absolute value of the difference between two adjacent temperature data in the plurality of temperature data to obtain a plurality of temperature absolute difference values; determining a minimum value among the plurality of absolute temperature differences; Obtaining the target sampling time corresponding to the minimum value; Acquire temperature data located after the target sampling time among the plurality of temperature data to obtain at least one temperature data; determining a target standard deviation for the at least one temperature data; Determining a target optimization parameter corresponding to the target standard deviation; The second operating parameter is optimized according to the target optimization parameter to obtain the target second operating parameter.
4. A system according to any one of claims 1 to 3, It is characterized in that In the aspect of determining the first operating parameter of the gas boiler corresponding to the target heating demand parameter, the gas boiler is specifically used for: Determining the reference operating parameters corresponding to the target heating demand parameters according to the mapping relationship between the preset heating demand parameters and the operating parameters of the gas boiler; Acquire a first attribute parameter of the gas boiler; Determining a target delivery pipeline between the biomass gasifier and the gas boiler; Acquire target pipeline parameters corresponding to the target delivery pipeline; determining a first compensation parameter corresponding to the first attribute parameter; determining a second compensation parameter corresponding to the target pipeline parameter; The reference operating parameter is compensated by using the first compensation parameter and the second compensation parameter to obtain the first operating parameter.
5. The system according to claim 4, It is characterized in that In the aspect of determining the second operating parameter corresponding to the biomass gasifier according to the first operating parameter, the biomass gasifier is specifically used for: Determining the initial operating parameters corresponding to the biomass gasifier according to the first operating parameters; Acquiring a second attribute parameter of the biomass gasifier; Obtaining target environmental parameters of the biomass gasifier; determining a first influence coefficient corresponding to the second attribute parameter; determining a second influence coefficient corresponding to the target environmental parameter; A second operating parameter corresponding to the biomass gasifier is determined according to the first influence coefficient, the second influence coefficient and the initial operating parameter.
6. A distributed intelligent control method, It is characterized in that Applied to a distributed intelligent control system, the distributed intelligent control system includes: a biomass gasifier, a gas boiler, and a controller, the method includes: Obtaining a target heating demand parameter through the controller; the target heating demand parameter includes at least one of the following: heating time period, heating purpose, and heating temperature; Determining, by means of the gas boiler, a first operating parameter of the gas boiler corresponding to the target heating demand parameter; Determining, by the biomass gasifier, a second operating parameter corresponding to the biomass gasifier according to the first operating parameter, and controlling the biomass gasifier to operate at the second operating parameter to convert biomass into biomass gas; The gas boiler operates with the first operating parameter to convert the biomass gas into heat to achieve heating, and collects temperature data of the gas boiler to obtain a plurality of temperature data; The controller adjusts the first operating parameter according to the multiple temperature data to obtain a target first operating parameter; the second operating parameter is adjusted according to the multiple temperature data to obtain a target second operating parameter, and the target first operating parameter and the target second operating parameter are sent to the gas boiler and the biomass gasifier respectively to control the gas boiler to operate with the target first operating parameter and the biomass gasifier to operate with the target second operating parameter.
7. The method according to claim 6, It is characterized in that Each temperature data in the plurality of temperature data corresponds to a sampling time; and adjusting the first operating parameter according to the plurality of temperature data to obtain a target first operating parameter includes: Perform fitting according to the plurality of temperature data and corresponding sampling moments to obtain a fitting straight line and a fitting curve; Obtaining a target slope of the fitted straight line; Determine the extreme points of the fitting curve to obtain multiple extreme points; Determining a target mean and a target mean square error of the plurality of extreme value points; Obtaining a reference temperature corresponding to the target heating demand parameter; determining a first deviation between the target mean and the reference temperature; determining a first adjustment parameter corresponding to the first deviation; Adjust the first operating parameter according to the first adjustment parameter to obtain a reference first operating parameter; Determining a first fine-tuning parameter corresponding to the target mean square error; determining a second fine-tuning parameter corresponding to the target slope; Determine a target weight pair according to the multiple extreme value points and the target mean, wherein the target weight pair includes a target first weight and a target second weight; Determine a target fine-tuning parameter according to the target weight pair, the first fine-tuning parameter, and the second fine-tuning parameter; The reference first operating parameter is fine-tuned according to the target fine-tuning parameter to obtain the target first operating parameter.
8. The method according to claim 7, It is characterized in that The step of adjusting the second operating parameter according to the plurality of temperature data to obtain a target second operating parameter includes: Determine the absolute value of the difference between two adjacent temperature data in the plurality of temperature data to obtain a plurality of temperature absolute difference values; determining a minimum value among the plurality of absolute temperature differences; Obtaining the target sampling time corresponding to the minimum value; Acquire temperature data located after the target sampling time among the plurality of temperature data to obtain at least one temperature data; determining a target standard deviation for the at least one temperature data; Determining a target optimization parameter corresponding to the target standard deviation; The second operating parameter is optimized according to the target optimization parameter to obtain the target second operating parameter.
9. An electronic device, It is characterized in that The method comprises a processor and a memory, wherein the memory is used to store one or more programs and is configured to be executed by the processor, wherein the program comprises instructions for executing the steps in the method according to any one of claims 6 to 8.
10. A computer-readable storage medium, It is characterized in that A computer program for electronic data exchange is stored, wherein the computer program enables a computer to execute the method according to any one of claims 6 to 8.