Production mold management method and system, electronic equipment and readable storage medium

By obtaining production scheduling plans and mold usage information, and automatically updating mold management tasks, the problem of opaque mold management and production scheduling plans information is solved, and mold management efficiency and product production efficiency are improved.

CN119026930APending Publication Date: 2024-11-26广域铭岛数字科技有限公司 +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202310607403.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-05-26
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

In the existing mold management, mold maintenance, maintenance, etc. rely on manual management, resulting in opaque information between mold management and production schedule, low management efficiency, and affect product production.

Method used

By obtaining production scheduling plans and mold usage information, setting mold management tasks and task trigger thresholds, automatically update mold work orders and production scheduling plans, and generating mold management records to realize information correlation and data updates between mold management and production scheduling plans.

Benefits of technology

It improves the management efficiency between mold management and production scheduling plan, improves product production efficiency, reduces manual entry and management personnel experience dependence, and ensures data accuracy and timeliness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119026930A_ABST
    Figure CN119026930A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of production management, and discloses a production mold management method and system, electronic equipment and a readable storage medium, and the method comprises the steps: obtaining a production scheduling plan and mold use information of a target mold, setting a mold management task and a task triggering threshold value of the target mold, and when the mold use information meets the task triggering threshold value, executing the mold management task; and taking the mold management work order corresponding to the task triggering threshold value as an updating basis, updating a mold operation work order and / or a production scheduling plan corresponding to the target mold, determining a work order execution state corresponding to the mold management work order in the mold management task, generating a mold management record of the target mold, and sending the mold management record to the target mold. Compared with the mode that mold management and production scheduling plans are updated depending on personal experience of managers, information association and data updating between the mold management and the production scheduling plans are achieved, so that the management efficiency between the mold management and the production scheduling plans is improved, and the production efficiency of products is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of production management, and in particular to a production mold management method, system, electronic equipment and readable storage medium. Background Art

[0002] As a tool for making molded objects, the mold has a specific contour or inner cavity shape. The use of a contour shape with a cutting edge can separate the blank according to the contour shape (punching). Since the mold is a precision tool with a complex shape and bears the expansion force of the blank, it has high requirements for structural strength, rigidity, surface hardness, surface roughness and processing accuracy. Therefore, with the continuous development of the mold industry, the maintenance, inspection, and repair of the mold has become an important task in the stamping workshop.

[0003] The existing mold maintenance work is to manually track the mold and then formulate corresponding maintenance and overhaul plans. Usually, information is manually entered, collected and sorted by the team leader, and tasks are issued offline. After the corresponding maintenance worker performs maintenance, the corresponding process personnel go to the site to confirm and record. However, since the mold is usually in the entire production plan, the maintenance and overhaul plan is relatively independent of the product's production schedule, and the data is not transparent. The mold management and production schedule are updated only based on the personal experience of the manager, resulting in low management efficiency between mold management and production schedule, affecting product production. Summary of the invention

[0004] In order to provide a basic understanding of some aspects of the disclosed embodiments, a brief summary is given below. The summary is not an extensive review, nor is it intended to identify key / critical components or delineate the scope of protection of these embodiments, but rather serves as a prelude to the detailed description that follows.

[0005] In view of the above-mentioned shortcomings of the prior art, the present invention discloses a production mold management method, system, electronic device and readable storage medium to improve the management efficiency between mold management and production scheduling.

[0006] The present invention provides a production mold management method, comprising: obtaining a production schedule and obtaining mold usage information of a target mold, wherein the production schedule includes a mold operation work order of the target mold; setting a mold management task for the target mold, and setting a task trigger threshold corresponding to the mold usage information for the mold management task, wherein the mold management task includes one or more mold management work orders; if the mold usage information meets the task trigger threshold, the mold operation work order and / or the production schedule are updated based on the mold management work order in the mold management task as an update basis; determining the work order execution status corresponding to the mold management work order, and generating a mold management record for the target mold according to the work order execution status.

[0007] Optionally, obtaining the mold usage information of the target mold includes: monitoring the target mold by a mold acquisition module arranged in the target mold, and generating a mold usage record of the target mold; transmitting the mold usage record to a preset data interaction module, wherein the data interaction module includes a database to be interacted with or an interface to be interacted with; if the data interaction module is the database to be interacted with, pulling the mold usage record from the database to be interacted with, and performing data statistics based on the pulled mold usage record to obtain the mold usage information of the target mold; if the data interaction module is the interface to be interacted with, performing data interaction with the interface to be interacted with through a preset client to obtain the mold usage record, and performing data statistics based on the mold usage record to obtain the mold usage information of the target mold.

[0008] Optionally, determining the work order execution status corresponding to the mold management work order includes: pre-setting the management authority corresponding to the mold management work order; determining the executor corresponding to the mold management work order from the personnel with the management authority, and issuing the mold management work order to the task list of the executor; and receiving the work order execution status input by the executor.

[0009] Optionally, after the mold management work order is issued to the task list of the executor, the method also includes: if the work order execution status input by the executor is not received within a preset execution time period, generating work order reminder information corresponding to the mold management work order, and reminding the executor according to the work order reminder information.

[0010] Optionally, after generating the mold management record of the target mold according to the work order execution status, the method further includes at least one of the following: adding the mold usage information of the target mold to the preset mold history information, reacquiring the mold usage information of the target mold, and performing data statistics based on the mold history information to obtain the full life cycle usage information of the target mold; extracting the target management record from the mold management record according to a preset statistical time period, performing data statistics on the target management record to obtain management statistical data of the target mold, and judging whether the target mold needs to be replaced based on the comparison result between the management statistical data and preset standard data.

[0011] Optionally, the mold management task includes at least one of the following: a mold maintenance task, the mold management work order of the mold maintenance task includes one or more of a mold maintenance work order, a spare parts requisition work order, and a maintenance acceptance work order; a mold maintenance task, the mold management work order of the mold maintenance task includes one or more of a mold maintenance work order, a spare parts requisition work order, and a maintenance acceptance work order; a mold maintenance task, the mold management work order of the mold maintenance task includes one or more of a maintenance type determination work order, a mold maintenance work order, a spare parts requisition work order, and a maintenance acceptance work order.

[0012] Optionally, whether the mold usage information meets the task trigger threshold is determined by the following method, including: the mold usage information includes one or more of mold downtime, mold downtime records, mold downtime reasons, mold operation time, mold operation times and mold daily operation time; calculation is performed based on at least a part of the mold usage information to obtain the mold life indicator of the target mold, wherein the mold life indicator includes a maintenance life indicator and a maintenance life indicator; if the first preset condition, the second preset condition or the third preset condition is met, it is determined that the mold usage information meets the task trigger threshold, wherein the first preset condition includes that the maintenance life indicator is greater than the task trigger threshold corresponding to the mold maintenance task, the second preset condition includes that the maintenance life indicator is greater than the task trigger threshold corresponding to the mold maintenance task, and the third preset condition includes that the maintenance life indicator is greater than the task trigger threshold corresponding to the mold maintenance task.

[0013] The present invention provides a production mold management system, comprising: an acquisition module, used to acquire a production schedule and mold usage information of a target mold, wherein the production schedule includes a mold operation work order of the target mold; a setting module, used to set a mold management task of the target mold, and set a task trigger threshold corresponding to the mold usage information to the mold management task, wherein the mold management task includes one or more mold management work orders; an update module, used to update the mold operation work order and / or the production schedule based on the mold management work order in the mold management task if the mold usage information meets the task trigger threshold; and a generation module, used to determine the work order execution status corresponding to the mold management work order, and generate a mold management record of the target mold according to the work order execution status.

[0014] The present invention provides an electronic device, comprising: a processor and a memory; the memory is used to store a computer program, and the processor is used to execute the computer program stored in the memory, so that the electronic device executes the above method.

[0015] The present invention provides a computer-readable storage medium on which a computer program is stored: when the computer program is executed by a processor, the above method is implemented.

[0016] Beneficial effects of the present invention:

[0017] By obtaining the production schedule and the mold usage information of the target mold, and setting the mold management task and task trigger threshold of the target mold, when the mold usage information meets the task trigger threshold, the mold management work order corresponding to the task trigger threshold is used as the update basis, the mold operation work order and / or production schedule corresponding to the target mold is updated, and the work order execution status corresponding to the mold management work order in the mold management task is determined, and the mold management record of the target mold is generated. In this way, compared with relying on the personal experience of the management personnel to update the mold management and production schedule, when the mold usage information of the target mold meets the task trigger threshold, the mold management work order corresponding to the task trigger threshold is used as the update basis, the mold operation work order and / or production schedule corresponding to the target mold is updated, and the mold management record of the target mold is generated, thereby realizing the information association and data update between mold management and production schedule, improving the management efficiency between mold management and production schedule, and improving product production efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a structural schematic diagram of a system architecture for implementing a production mold management method in an embodiment of the present invention;

[0019] Figure 2 is a flow chart of a production mold management method in an embodiment of the present invention;

[0020] Figure 3 This is a structural diagram of a data flow framework of a production mold management method in an embodiment of the present invention.

[0021] Figure 4 is a flow chart of another production mold management method in an embodiment of the present invention;

[0022] Figure 5 It is a structural diagram of a production mold management system in an embodiment of the present invention;

[0023] Figure 6 is a schematic diagram of an electronic device in an embodiment of the present invention. DETAILED DESCRIPTION

[0024] The following describes the embodiments of the present invention through specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that the following embodiments and sub-samples in the embodiments can be combined with each other without conflict.

[0025] It should be noted that the illustrations provided in the following embodiments are only schematic illustrations of the basic concept of the present invention, and thus the drawings only show components related to the present invention rather than being drawn according to the number, shape and size of components in actual implementation. In actual implementation, the type, quantity and proportion of each component may be changed arbitrarily, and the component layout may also be more complicated.

[0026] In the following description, numerous details are discussed to provide a more thorough explanation of the embodiments of the present invention. However, it is obvious to those skilled in the art that the embodiments of the present invention can be implemented without these specific details. In other embodiments, well-known structures and devices are shown in the form of block diagrams rather than in detail to avoid making the embodiments of the present invention difficult to understand.

[0027] The terms "first", "second", etc. in the specification and claims of the embodiments of the present disclosure and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the terms used in this way can be interchanged where appropriate, so that the embodiments of the embodiments of the present disclosure described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions.

[0028] Unless otherwise stated, the term "plurality" means two or more.

[0029] In the embodiment of the present disclosure, the character " / " indicates that the preceding and following objects are in an "or" relationship. For example, A / B indicates: A or B.

[0030] The term "and / or" is a description of the association relationship between objects, indicating that three relationships can exist. For example, A and / or B means: A or B, or, A and B.

[0031] Combination Figure 1As shown, the embodiment of the present disclosure provides a system architecture for implementing a production mold management method, including a display layer, an agent layer, a gateway layer, a service layer, a plug-in layer, and a data layer; the display layer is used to display data through laptops, desktop computers, and mobile devices; the agent layer is used to provide load balancing and nginx clusters; the gateway layer is used to provide Getway clusters, request filtering, service fuses, request forwarding, dynamic routing, user authentication, interface current limiting and other services; the service layer includes a GUC user center module, a work order management module, a spare parts module, a data report module, a basic settings module, and a data log module; the plug-in layer is used to provide message queues, message centers, task scheduling, SkyWalking link monitoring, etc.; the data layer includes MySQL clusters, Redis clusters, MQ clusters, Minio clusters, etc.

[0032] Combination Figure 2 As shown, the embodiment of the present disclosure provides a production mold management method, including:

[0033] Step S201, obtaining a production schedule and obtaining mold usage information of a target mold;

[0034] Among them, the production schedule includes the mold work order of the target mold;

[0035] Step S202, setting a mold management task for the target mold, and setting a task triggering threshold corresponding to the mold usage information for the mold management task;

[0036] Among them, the mold management task includes one or more mold management work orders;

[0037] Step S203: if the mold usage information meets the task triggering threshold, the mold operation work order and / or production schedule is updated based on the mold management work order in the mold management task;

[0038] Step S204, determining the work order execution status corresponding to the mold management work order, and generating a mold management record of the target mold according to the work order execution status.

[0039] The production mold management method provided by the embodiment of the present disclosure is adopted. By obtaining the mold usage information of the production schedule and the target mold, and setting the mold management task and task trigger threshold of the target mold, when the mold usage information meets the task trigger threshold, the mold management work order corresponding to the task trigger threshold is used as the update basis, the mold operation work order and / or production schedule corresponding to the target mold is updated, and the work order execution status corresponding to the mold management work order in the mold management task is determined, and the mold management record of the target mold is generated. In this way, compared with relying on the personal experience of the management personnel to update the mold management and production schedule, by using the mold management work order corresponding to the task trigger threshold as the update basis when the mold usage information of the target mold meets the task trigger threshold, the mold operation work order and / or production schedule corresponding to the target mold is updated, and the mold management record of the target mold is generated, thereby realizing the information association and data update between mold management and production schedule, improving the management efficiency between mold management and production schedule, and improving product production efficiency.

[0040] Optionally, the mold usage information of the target mold is obtained, including: monitoring the target mold through a mold acquisition module set in the target mold, and generating a mold usage record of the target mold; transmitting the mold usage record to a preset data interaction module, wherein the data interaction module includes a database to be interacted or an interface to be interacted; if the data interaction module is a database to be interacted, then pulling the mold usage record from the database to be interacted, and performing data statistics based on the pulled mold usage record to obtain the mold usage information of the target mold; if the data interaction module is an interface to be interacted, then performing data interaction with the interface to be interacted through a preset client to obtain the mold usage record, and performing data statistics based on the mold usage record to obtain the mold usage information of the target mold.

[0041] In some embodiments, the mold acquisition module is pre-bound to a preset client; a start anchor point is set on the preset client to trigger a data acquisition module set on the mold to collect mold usage records of the target mold.

[0042] In some embodiments, the mold usage records of the target molds in the preset monitoring area are sent to the database to be interacted with in the form of responsive data, the responsive data is captured from the database to be interacted with through a scheduled task, and data consistency is ensured through a distributed lock, wherein the database to be interacted with includes one or more databases such as MySQL and PGSQL, and the distributed lock includes Redisson, etc.

[0043] In some embodiments, the mold usage records of the target molds in the preset monitoring area are sent to the interface to be interacted through a transmission path, so that the preset client and the interface to be interacted interact with data through the HTTP protocol, wherein the preset client includes mobile phone APP, computer software, etc., and the interface to be interacted is established based on API.

[0044] In some embodiments, the process of obtaining the mold usage information is recorded in real time to form an operation log, and the operation log is displayed to monitor the data capture status of the target mold.

[0045] Optionally, the mold usage information includes one or more of the mold identification ID, the mold's geographical location, the mold downtime, the mold downtime record, the mold downtime reason, the mold operation time, the mold operation times, and the mold daily operation time.

[0046] In some embodiments, the target mold is a stamping mold, and the number of mold operations corresponding to the target mold is the number of mold stamping times.

[0047] Optionally, determining the work order execution status corresponding to the mold management work order includes: pre-setting the management authority corresponding to the mold management work order; determining the executor corresponding to the mold management work order from the personnel with management authority, and issuing the mold management work order to the task list of the executor; receiving the work order execution status input by the executor.

[0048] Optionally, after the mold management work order is issued to the task list of the executor, the method also includes: if the work order execution status input by the executor is not received within the preset execution time period, generating work order reminder information corresponding to the mold management work order, and reminding the executor according to the work order reminder information.

[0049] Optionally, after generating the mold management record of the target mold according to the work order execution status, the method also includes at least one of the following: adding the mold usage information of the target mold to the preset mold history information, re-acquiring the mold usage information of the target mold, and performing data statistics based on the mold history information to obtain the full life cycle usage information of the target mold; extracting the target management record from the mold management record according to a preset statistical time period, performing data statistics on the target management record to obtain management statistical data of the target mold, and judging whether the target mold needs to be replaced based on the comparison result between the management statistical data and the preset standard data.

[0050] In some embodiments, after each target mold completes a mold management task, the mold management task is accumulated again. Meanwhile, the mold history information of the target mold throughout its life cycle is still counted and recorded and will not be cleared.

[0051] Optionally, the mold management task includes at least one of the following: a mold maintenance task, wherein the mold management work order of the mold maintenance task includes one or more of a mold maintenance work order, a spare parts requisition work order, and a maintenance acceptance work order; a mold maintenance task, wherein the mold management work order of the mold maintenance task includes one or more of a mold maintenance work order, a spare parts requisition work order, and a maintenance acceptance work order; a mold maintenance task, wherein the mold management work order of the mold maintenance task includes one or more of a maintenance type determination work order, a mold maintenance work order, a spare parts requisition work order, and a maintenance acceptance work order.

[0052] In some embodiments, mold maintenance tasks and mold overhaul tasks require mold maintenance personnel to perform maintenance on the mold according to the maintenance and overhaul content configuration items, and to collect spare parts from the warehouse during the maintenance process.

[0053] In some embodiments, the mold maintenance task requires the mold management personnel to determine the maintenance type of the target mold, specify the maintenance personnel corresponding to the maintenance type, and the maintenance personnel fill in the maintenance plan and other information, and repair the target mold, and collect spare parts in the warehouse during the maintenance process.

[0054] In some embodiments, after the completion of mold maintenance tasks, mold inspection tasks and mold repair tasks, they need to be accepted and reviewed by the mold management personnel; after the acceptance and review is passed, the mold management record of the target mold is generated according to the work order execution status; the mold management records are counted according to the data averaging method to obtain statistical data of different dimensions to monitor whether the target mold needs to be replaced.

[0055] Optionally, whether the mold usage information meets the task trigger threshold is determined by the following method, including: calculating according to at least a part of the mold usage information to obtain the mold life indicator of the target mold, wherein the mold life indicator includes a maintenance life indicator and a maintenance life indicator; if the first preset condition, the second preset condition or the third preset condition is met, it is determined that the mold usage information meets the task trigger threshold, wherein the first preset condition includes that the maintenance life indicator is greater than the task trigger threshold corresponding to the mold maintenance task, the second preset condition includes that the maintenance life indicator is greater than the task trigger threshold corresponding to the mold maintenance task, and the third preset condition includes that the maintenance life indicator is greater than the task trigger threshold corresponding to the mold maintenance task.

[0056] In some embodiments, after obtaining the mold usage information of the target mold, the mold usage information is stored in a MySQL database; the mold usage information is counted to determine the mold life indicator of the target mold; when the mold usage information or the mold life indicator reaches a preset task trigger threshold, the mold management information is sent to the user, and the message is pushed to authorized managers and maintenance personnel to issue maintenance, care, and repair instructions.

[0057] Combination Figure 3 As shown, the embodiment of the present disclosure provides a data flow framework of a production mold management method, including a mold business module, a data collection module and a work order process module;

[0058] The mold business system is used to manage the basic information and spare parts of the target mold, count the mold management records of the target mold, manage the production schedule, manage the punching records and line stop records of the target mold, and store the above information in the mold database (mold MySQL) of the data acquisition system;

[0059] The data collection system is used to collect the mold usage information of the target mold. At the same time, when the mold usage information meets the task trigger threshold, the mold management task corresponding to the task trigger threshold is sent to the work order process module;

[0060] The work order process module is used to arrange work order tasks according to the work order process module and to issue alarms for delayed mold management tasks.

[0061] The data flow framework of the production mold management method provided by the embodiment of the present disclosure is adopted. By obtaining the mold usage information of the production schedule and the target mold, and setting the mold management task and task trigger threshold of the target mold, when the mold usage information meets the task trigger threshold, the mold management work order corresponding to the task trigger threshold is used as the update basis, the mold operation work order and / or production schedule corresponding to the target mold is updated, and the work order execution status corresponding to the mold management work order in the mold management task is determined, and the mold management record of the target mold is generated. In this way, compared with relying on the personal experience of the management personnel to update the mold management and production schedule, by using the mold management work order corresponding to the task trigger threshold as the update basis when the mold usage information of the target mold meets the task trigger threshold, the mold operation work order and / or production schedule corresponding to the target mold is updated, and the mold management record of the target mold is generated, thereby realizing the information association and data update between the mold management and the production schedule, improving the management efficiency between the mold management and the production schedule, and improving the product production efficiency.

[0062] Combination Figure 4 As shown, the embodiment of the present disclosure provides a production mold management method, including:

[0063] Step S401, pre-setting a mold management task for a target mold, and setting a task triggering threshold corresponding to mold usage information for the mold management task;

[0064] Among them, the mold management task includes one or more mold management work orders;

[0065] Step S402, obtaining a production schedule and obtaining mold usage information of a target mold;

[0066] Among them, the production schedule includes the mold work order of the target mold;

[0067] Step S403, determining whether the mold usage information meets the task triggering threshold, if yes, jump to step S404, if no, jump to step S402;

[0068] Step S404, using the mold management work order in the mold management task as an update basis, updating the mold operation work order and / or production scheduling plan;

[0069] Step S405, determining whether the mold management task includes a mold maintenance task, if so, jump to step S06, if not, jump to step S407;

[0070] Among them, mold management tasks include mold repair tasks, mold maintenance tasks and mold overhaul tasks;

[0071] Step S406, determine the maintenance type of the target mold, and assign mold maintenance personnel to the mold maintenance task according to the maintenance type, and jump to step S408;

[0072] Step S407, assigning mold maintenance personnel to the mold management task, and jumping to step S408;

[0073] Step S408, determining whether the task completion information of the task executor is received within the preset time period, if yes, jump to step S409, if no, jump to step S412;

[0074] Among them, the task performers include mold maintenance personnel or mold repair personnel;

[0075] Step S409, assigning task acceptance personnel to the mold management task;

[0076] Step S410, determining whether the acceptance completion information of the task acceptance personnel is received within the preset time period, if yes, jump to step S411, if no, jump to step S413;

[0077] Step S411, determining the work order execution status corresponding to the mold management work order, and generating a mold management record of the target mold according to the work order execution status.

[0078] Step S412, issue an overdue warning to the task executor, and jump to step S408.

[0079] Step S413, issue an overdue warning to the task acceptance personnel, and jump to step S410.

[0080] The production mold management method provided by the embodiment of the present disclosure obtains the production schedule and the mold usage information of the target mold, and sets the mold management task and the task trigger threshold of the target mold. When the mold usage information meets the task trigger threshold, the mold management work order corresponding to the task trigger threshold is used as the update basis, the mold operation work order and / or the production schedule corresponding to the target mold is updated, and the work order execution status corresponding to the mold management work order in the mold management task is determined, and the mold management record of the target mold is generated. The advantages are as follows:

[0081] First, compared with relying on the personal experience of managers to update mold management and production scheduling, when the mold usage information of the target mold meets the task trigger threshold, the mold management work order corresponding to the task trigger threshold is used as the update basis, and the mold operation work order and / or production scheduling corresponding to the target mold is updated, and the mold management record of the target mold is generated, thereby realizing the information association and data update between mold management and production scheduling, improving the management efficiency between mold management and production scheduling, and improving product production efficiency;

[0082] Second, it can collect mold information in a timely and comprehensive manner, collect mold information through the database or transmit it to the mold APP database through API, monitor it regularly, and generate mold maintenance tasks when the threshold is reached. Mold users, managers and maintenance personnel can view it.

[0083] Third, effectively grasp the mold status, improve production efficiency, form a mold life history, effectively convey the current mold information to mold managers, users and maintenance personnel, help users to perform mold maintenance, determine the management level of mold users, help users improve mold management level, and provide mold information for production scheduling, improve production scheduling efficiency, and improve production OEE;

[0084] Fourth, data collection through API or database is more accurate, reliable and timely than manual data entry or periodic maintenance, and can achieve unmanned operation and reduce labor costs;

[0085] Fifth, manage the mold according to the frequency of mold use and arrange mold maintenance reasonably to improve mold utilization, reduce the ineffective working time of maintenance personnel, and realize refined management of molds.

[0086] Combination Figure 5As shown, the embodiment of the present disclosure provides a production mold management system, including an acquisition module 501, a setting module 502, an update module 503, and a generation module 504. The acquisition module 501 is used to acquire a production schedule and acquire mold usage information of a target mold, wherein the production schedule includes a mold operation work order of the target mold; the setting module 502 is used to set a mold management task for the target mold, and set a task trigger threshold corresponding to the mold usage information to the mold management task, wherein the mold management task includes one or more mold management work orders; the update module 503 is used to update the mold operation work order and / or the production schedule based on the mold management work order in the mold management task if the mold usage information meets the task trigger threshold; the generation module 504 is used to determine the work order execution status corresponding to the mold management work order, and generate a mold management record of the target mold according to the work order execution status.

[0087] The production mold management system provided by the embodiment of the present disclosure is adopted, by obtaining the production schedule and the mold usage information of the target mold, and setting the mold management task and task trigger threshold of the target mold, when the mold usage information meets the task trigger threshold, the mold management work order corresponding to the task trigger threshold is used as the update basis, the mold operation work order and / or production schedule corresponding to the target mold is updated, and the work order execution status corresponding to the mold management work order in the mold management task is determined, and the mold management record of the target mold is generated. In this way, compared with relying on the personal experience of the management personnel to update the mold management and production schedule, by using the mold management work order corresponding to the task trigger threshold as the update basis when the mold usage information of the target mold meets the task trigger threshold, the mold operation work order and / or production schedule corresponding to the target mold is updated, and the mold management record of the target mold is generated, thereby realizing the information association and data update between mold management and production schedule, improving the management efficiency between mold management and production schedule, and improving product production efficiency.

[0088] Figure 6 The structure diagram of the computer system suitable for implementing the electronic device of the embodiment of the present application is shown. It should be noted that: Figure 6 The computer system 600 of the electronic device shown is only an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.

[0089] like Figure 6As shown, the computer system 600 includes a central processing unit (CPU) 601, which can perform various appropriate actions and processes according to the program stored in the read-only memory (ROM) 602 or the program loaded from the storage part 608 to the random access memory (RAM) 603, such as executing the method in the above embodiment. In the RAM 603, various programs and data required for system operation are also stored. The CPU 601, ROM 602 and RAM 603 are connected to each other through a bus 604. An input / output (I / O) interface 605 is also connected to the bus 604.

[0090] The following components are connected to the I / O interface 605: an input section 606 including a keyboard, a mouse, etc.; an output section 607 including a cathode ray tube (CRT), a liquid crystal display (LCD), etc., and a speaker, etc.; a storage section 608 including a hard disk, etc.; and a communication section 609 including a network interface card such as a LAN (Local Area Network) card, a modem, etc. The communication section 609 performs communication processing via a network such as the Internet. A drive 610 is also connected to the I / O interface 605 as needed. A removable medium 611, such as a magnetic disk, an optical disk, a magneto-optical disk, a semiconductor memory, etc., is installed on the drive 610 as needed so that a computer program read therefrom is installed into the storage section 608 as needed.

[0091] In particular, according to an embodiment of the present application, the process described above with reference to the flowchart can be implemented as a computer software program. For example, an embodiment of the present application includes a computer program product, which includes a computer program carried on a computer-readable medium, and the computer program includes a computer program for executing the method shown in the flowchart. In such an embodiment, the computer program can be downloaded and installed from a network through a communication section 609, and / or installed from a removable medium 611. When the computer program is executed by a central processing unit (CPU) 601, various functions defined in the system of the present application are executed.

[0092] It should be noted that the computer-readable medium shown in the embodiment of the present application can be a computer-readable signal medium or a computer-readable storage medium or any combination of the above two. The computer-readable storage medium can be, for example, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination of the above. More specific examples of computer-readable storage media can include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM), a flash memory, an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In the present application, a computer-readable signal medium may include a data signal propagated in a baseband or as part of a carrier wave, wherein a computer-readable computer program is carried. This propagated data signal can take a variety of forms, including but not limited to an electromagnetic signal, an optical signal, or any suitable combination of the above. A computer-readable signal medium may also be any computer-readable medium other than a computer-readable storage medium, which may send, propagate or transmit a program for use by or in conjunction with an instruction execution system, apparatus or device. A computer program contained on a computer-readable medium may be transmitted using any appropriate medium, including but not limited to: wireless, wired, etc., or any suitable combination of the above.

[0093] The embodiments of the present disclosure further provide a computer-readable storage medium on which a computer program is stored. When the program is executed by a processor, any one of the methods in the embodiments is implemented.

[0094] The computer-readable storage medium in the embodiments of the present disclosure can be understood by ordinary technicians in the field: all or part of the steps of implementing the above-mentioned method embodiments can be completed by hardware related to the computer program. The aforementioned computer program can be stored in a computer-readable storage medium. When the program is executed, the execution includes the steps of the above-mentioned method embodiments; and the aforementioned storage medium includes: ROM, RAM, magnetic disk or optical disk and other media that can store program codes.

[0095] The electronic device disclosed in this embodiment includes a processor, a memory, a transceiver and a communication interface. The memory and the communication interface are connected to the processor and the transceiver and complete communication with each other. The memory is used to store computer programs, the communication interface is used to communicate, and the processor and the transceiver are used to run the computer program so that the electronic device executes each step of the above method.

[0096] In this embodiment, the memory may include a random access memory (RAM), and may also include a non-volatile memory (non-volatile memory), such as at least one disk memory.

[0097] The above-mentioned processor can be a general-purpose processor, including a central processing unit (CPU), a graphics processing unit (GPU), a network processor (NP), etc.; it can also be a digital signal processor (DSP), an application specific integrated circuit (ASIC), a field programmable gate array (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components.

[0098] The above description and accompanying drawings fully illustrate the embodiments of the present disclosure so that those skilled in the art can practice them. Other embodiments may include structural, logical, electrical, process and other changes. The embodiments represent possible changes only. Unless explicitly required, separate components and functions are optional, and the order of operation may vary. Parts and subsamples of some embodiments may be included in or replace parts and subsamples of other embodiments. Moreover, the words used in this application are only used to describe the embodiments and are not used to limit the claims. As used in the description of the embodiments and claims, unless the context clearly indicates, the singular forms of "a", "an" and "the" are intended to include plural forms as well. Similarly, the term "and / or" as used in this application refers to any and all possible combinations of listings containing one or more associated ones. In addition, when used in the present application, the term "comprise" and its variants "comprises" and / or comprising refer to the presence of a stated sub-sample, whole, step, operation, element, and / or component, but do not exclude the presence or addition of one or more other sub-samples, wholes, steps, operations, elements, components and / or groups of these. In the absence of further restrictions, the elements defined by the sentence "comprising a ..." do not exclude the presence of other identical elements in the process, method or device comprising the elements. In this article, each embodiment may focus on the differences from other embodiments, and the same and similar parts between the various embodiments may refer to each other. For the methods, products, etc. disclosed in the embodiments, if they correspond to the method part disclosed in the embodiments, then the relevant parts can refer to the description of the method part.

[0099] Those skilled in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software may depend on the specific application and design constraints of the technical solution. Technicians can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the embodiments of the present disclosure. Technicians can clearly understand that for the convenience and simplicity of description, the specific working process of the above-described system, device and unit can refer to the corresponding process in the aforementioned method embodiment, and will not be repeated here.

[0100] In the embodiments disclosed herein, the disclosed methods and products (including but not limited to devices, equipment, etc.) can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of units can be only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some sub-samples can be ignored or not executed. In addition, the coupling or direct coupling or communication connection between each other shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms. The units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the units may be selected according to actual needs to implement this embodiment. In addition, each functional unit in the embodiment of the present disclosure may be integrated in a processing unit, or each unit may exist physically alone, or two or more units may be integrated in one unit.

[0101] The flowchart and block diagram in the accompanying drawings show the possible architecture, function and operation of the system, method and computer program product according to the embodiment of the present disclosure. In this regard, each box in the flowchart or block diagram can represent a module, a program segment or a part of the code, and the module, the program segment or a part of the code contains one or more executable instructions for realizing the specified logical function. In some alternative implementations, the functions marked in the box can also occur in a different order from the order marked in the accompanying drawings. For example, two consecutive boxes can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, which can depend on the functions involved. In the description corresponding to the flowchart and the block diagram in the accompanying drawings, the operations or steps corresponding to different boxes can also occur in a different order from the order disclosed in the description, and sometimes there is no specific order between different operations or steps. For example, two consecutive operations or steps can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, which can depend on the functions involved. Each block in the block diagrams and / or flowcharts, and combinations of blocks in the block diagrams and / or flowcharts, may be implemented by a dedicated hardware-based system that performs the specified functions or actions, or may be implemented by a combination of dedicated hardware and computer instructions.

Claims

1. A production mold management method, characterized in that: include: Obtaining a production schedule and obtaining mold usage information of a target mold, wherein the production schedule includes a mold operation work order of the target mold; Setting a mold management task for the target mold, and setting a task triggering threshold corresponding to the mold usage information for the mold management task, wherein the mold management task includes one or more mold management work orders; If the mold usage information meets the task triggering threshold, the mold operation work order and / or the production schedule are updated based on the mold management work order in the mold management task; Determine the work order execution status corresponding to the mold management work order, and generate a mold management record of the target mold according to the work order execution status.

2. The method according to claim 1, characterized in that Get the mold usage information of the target mold, including: Monitoring the target mold through a mold acquisition module arranged in the target mold, and generating a mold usage record of the target mold; Transmitting the mold usage record to a preset data interaction module, wherein the data interaction module includes a database to be interacted with or an interface to be interacted with; If the data interaction module is the database to be interacted with, the mold usage record is pulled from the database to be interacted with, and data statistics are performed according to the pulled mold usage record to obtain the mold usage information of the target mold; If the data interaction module is the interface to be interacted with, data interaction is performed with the interface to be interacted with through a preset client to obtain a mold usage record, and data statistics are performed based on the mold usage record to obtain mold usage information of the target mold.

3. The method according to claim 1, characterized in that Determining the work order execution status corresponding to the mold management work order includes: Pre-setting the management authority corresponding to the mold management work order; Determine the executor corresponding to the mold management work order from the personnel with the management authority, and send the mold management work order to the task list of the executor; Receive the work order execution status input by the executor.

4. The method according to claim 1, characterized in that: After sending the mold management work order to the task list of the executor, the method further includes: If the work order execution status input by the executor is not received within the preset execution time period, work order reminder information corresponding to the mold management work order is generated, and the executor is reminded according to the work order reminder information.

5. The method according to claim 1, characterized in that After generating the mold management record of the target mold according to the work order execution status, the method further includes at least one of the following: Adding the mold usage information of the target mold to the preset mold history information, reacquiring the mold usage information of the target mold, and performing data statistics according to the mold history information to obtain the full life cycle usage information of the target mold; Extract target management records from the mold management records according to a preset statistical time period, perform data statistics on the target management records to obtain management statistical data of the target mold, and determine whether the target mold needs to be replaced based on a comparison result between the management statistical data and preset standard data.

6. The method according to any one of claims 1 to 5, characterized in that: The mold management task includes at least one of the following: A mold maintenance task, wherein the mold management work order of the mold maintenance task includes one or more of a mold maintenance work order, a spare parts requisition work order, and a maintenance acceptance work order; A mold maintenance task, wherein the mold management work order of the mold maintenance task includes one or more of a mold maintenance work order, a spare parts requisition work order, and a maintenance acceptance work order; A mold maintenance task, wherein the mold management work order of the mold maintenance task includes one or more of a maintenance type determination work order, a mold maintenance work order, a spare parts requisition work order, and a maintenance acceptance work order.

7. The method according to claim 6, characterized in that Determining whether the mold usage information meets the task triggering threshold by the following method includes: The mold usage information includes one or more of mold downtime, mold downtime records, mold downtime reasons, mold operation time, mold operation times, and mold daily operation time; Calculating according to at least a portion of the mold usage information to obtain a mold life index of the target mold, wherein the mold life index includes a repair life index and a maintenance life index; If the first preset condition, the second preset condition or the third preset condition is met, it is determined that the mold usage information meets the task trigger threshold, wherein the first preset condition includes that the maintenance life indicator is greater than the task trigger threshold corresponding to the mold maintenance task, the second preset condition includes that the maintenance life indicator is greater than the task trigger threshold corresponding to the mold maintenance task, and the third preset condition includes that the maintenance life indicator is greater than the task trigger threshold corresponding to the mold maintenance task.

8. A production mold management system, characterized in that: include: An acquisition module, used to acquire a production schedule and mold usage information of a target mold, wherein the production schedule includes a mold operation work order of the target mold; A setting module, used to set a mold management task for the target mold, and set a task triggering threshold corresponding to the mold usage information to the mold management task, wherein the mold management task includes one or more mold management work orders; An updating module, configured to update the mold operation work order and / or the production schedule based on the mold management work order in the mold management task as an updating basis if the mold usage information meets the task triggering threshold; A generation module is used to determine the work order execution status corresponding to the mold management work order, and generate a mold management record of the target mold according to the work order execution status.

9. An electronic device, characterized in that: include: Processor and memory; The memory is used to store a computer program, and the processor is used to execute the computer program stored in the memory, so that the electronic device executes the method according to any one of claims 1 to 7.

10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the method according to any one of claims 1 to 7 is implemented.

Citation Information

Cited By

  • Mould full life cycle management system based on Internet of Things

    CN121303604A