Method for controlling stability of power system after grid connection of new energy power station
By dividing the power system after the new energy power station is connected to the grid into a monitoring sub-region, collecting and analyzing operation data, calculating abnormal evaluation index, and optimizing power generation scheduling, the problem of stability control of the power system after the new energy power station is connected to the grid is solved, and the power system is realized The refined management and fault warning have improved energy utilization efficiency and power supply quality.
Patent Information
- Application Number
- CN202411161264.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-22
- Publication Date
- 2024-11-26
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
After the new energy power station is connected to the grid, the traditional power system stability analysis method is difficult to cover possible operating scenarios, resulting in an increase in the number of power electronic equipment in the power system, a decrease in the accuracy of fault warning, and it is difficult to detect and deal with power grid faults in a timely manner.
By dividing the power system after the new energy power station is connected to the grid into multiple monitoring sub-regions, collecting operation performance evaluation data, calculating the power grid operation abnormality evaluation index and power generation scheduling optimization index, analyzing the performance stability evaluation coefficient, and realizing refined management of the power system and abnormal feedback, optimize power generation scheduling to improve energy utilization efficiency.
It improves fault management efficiency, improves power supply quality, reduces manual intervention and human errors, reduces operation and maintenance costs, and ensures the safe and stable operation of the power system.
Smart Images

Figure CN119029935A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power safety control, and more specifically, to a method for controlling the stability of a power system after a new energy power station is connected to the grid. Background Art
[0002] With the continuous growth of global energy demand and the increasingly severe environmental problems, new energy power generation technologies represented by photovoltaic and wind power have been widely used. Improving the utilization rate of energy and the utilization rate of renewable resources will be the development direction of new energy in the future. New energy, such as wind energy and solar energy, has the characteristics of intermittent and volatile power generation. Only by fully coordinating and cooperating with each other after the new energy power field is connected to the grid can the safe and stable operation of the power grid be guaranteed.
[0003] In traditional power systems, power generation and power consumption are completed synchronously, and power plants will generate electricity according to user demand. However, in renewable energy power generation, it is difficult to ensure a balance between power generation and power consumption because renewable energy cannot be controlled autonomously. In order to ensure that the renewable energy power field is connected to the grid and maintains a stable operating state, a series of high-tech technical means are needed to realize the intelligent control of renewable energy.
[0004] However, there are still some shortcomings in its actual use. For example, the traditional power system stability analysis method is difficult to cover the possible operation scenarios of the power system after the new energy power station is connected to the grid. It is necessary to use big data and other technical means to establish a more accurate prediction model.
[0005] After the connection of new energy sources to the grid, the number of power electronic equipment in the power system has increased significantly, making it difficult to detect and warn of grid faults in a timely manner, resulting in a decrease in the accuracy of warnings and an increase in the difficulty of fault warnings. Summary of the invention
[0006] In order to overcome the above-mentioned defects of the prior art, an embodiment of the present invention provides a stability control method for a power system after a new energy power station is connected to the grid, which is used to solve the problems raised in the above-mentioned background technology.
[0007] To achieve the above object, the present invention provides the following technical solution: a method for controlling the stability of a power system after a new energy power station is connected to the grid, comprising:
[0008] Step S01: Power system area division: used to divide the power system after the new energy power station is connected to the grid into various monitoring sub-areas according to the functional characteristics of the electrically connected lines, and number the monitoring sub-areas of the power system after the new energy power station is connected to the grid.
[0009] Step S02: Power system operation data collection: used to collect the operation performance evaluation data of each monitoring sub-area of the power system after the new energy power station is connected to the grid. The power system operation data collection includes a new energy power generation data collection unit and a power grid dispatching capability data collection unit. The operation performance evaluation data includes new energy power generation data and power grid dispatching capability data.
[0010] Step S03: New energy power generation abnormality management: used to receive the operation performance evaluation data transmitted by the power system operation data collection step, calculate the power grid operation abnormality evaluation index of each monitoring sub-area of the power system after the new energy power station is connected to the grid according to the new energy power generation data collection unit, compare it with the preset power grid operation abnormality evaluation index, and process it.
[0011] Step S04: New energy grid dispatch optimization: used to receive the operation performance evaluation data transmitted by the power system operation data collection step, calculate the power grid power generation dispatch optimization index of each monitoring sub-area of the power system after the new energy power station is connected to the grid according to the power grid dispatch capacity data collection unit, compare it with the preset power grid power generation dispatch optimization index, and process it.
[0012] Step S05: Power system stability assessment: Based on the power grid operation abnormality assessment index and power grid generation dispatch optimization index of each monitoring sub-area of the power system after the new energy power station is connected to the grid, the performance stability assessment coefficient of each monitoring sub-area of the power system after the new energy power station is connected to the grid is analyzed.
[0013] Step S06: Power system stability abnormality warning: used to receive the performance stability evaluation coefficient of each monitoring sub-area of the power system after the new energy power station is connected to the grid, compare it with the preset performance stability evaluation coefficient, and process it.
[0014] Step S07: Power system stability control: used to receive the number of the abnormal area transmitted in the power system stability assessment step, and calculate the power system stability control coefficient of the abnormal area monitoring sub-area of the power system after the new energy power station is connected to the grid based on the line length and power transmission efficiency of the electrical connection of the abnormal area monitoring sub-area of the power system after the new energy power station is connected to the grid.
[0015] Preferably, the specific division method of the power system area division is:
[0016] According to the functional characteristics of the electrical connection lines in the power system, the power system after the new energy power station is connected to the grid is divided into various monitoring sub-areas, and the monitoring sub-areas of the power system after the new energy power station is connected to the grid are numbered 1, 2, ...i, ...n in sequence.
[0017] Preferably, the power system operation data collection is specifically:
[0018] New energy power generation data acquisition unit: collects the current, voltage, and actual frequency of the power grid in each monitoring sub-area of the power system after the new energy power station is connected to the grid, marked as dl i ,dy i 、dp i , where i = 1, 2, ... n, i represents the number of the i-th monitoring sub-area;
[0019] Grid dispatching capability data collection unit: collects the transmission line utilization rate, energy storage capacity, and harmonic frequency of each monitoring sub-area of the power system after the new energy power station is connected to the grid, marked as ns respectively. i 、nr i 、nx i .
[0020] Preferably, the abnormal management of new energy power generation is specifically as follows:
[0021] Step S001: Obtain the load voltage, load current, and monitoring duration of each monitoring sub-area of the power system at the load end after the new energy power station is connected to the grid, marked as fl i 、fy i ,t i ;
[0022] Step S002: The calculation formula of the power grid operation abnormality evaluation index is:
[0023] where α i It is represented as the power grid operation abnormality evaluation index of the ith monitoring sub-area, fl i It is represented as the load voltage of the ith monitoring sub-area, fy i It is represented as the load current of the ith monitoring sub-area, dl i It is represented as the current of the i-th monitoring sub-area, dy i It is represented as the voltage of the ith monitoring sub-area, dp i denoted as the actual grid frequency of the ith monitoring sub-area, DP0 as the rated grid frequency, and t i It is represented as the monitoring duration of the ith monitoring sub-area, and e is represented as a natural constant.
[0024] Step S003: Obtain the grid operation abnormality assessment index of each monitoring sub-area of the power system after the new energy power station is connected to the grid, compare it with the preset grid operation abnormality assessment index, filter out the numbers of the monitoring sub-areas whose grid operation abnormality assessment index is greater than the preset grid operation abnormality assessment index, and send them to the security management personnel for review.
[0025] Preferably, the new energy grid dispatch optimization is specifically as follows:
[0026] Step S001: The calculation formula of the power grid generation dispatch optimization index is:
[0027] where β i It is represented as the power grid generation dispatch optimization index of the i-th monitoring sub-area, ns i It is expressed as the transmission circuit utilization rate of the ith monitoring sub-area, nr i It is represented as the energy storage capacity of the ith monitoring sub-area, nx i Expressed as the harmonic order of the i-th monitoring sub-area, NX 预 It is represented by the preset harmonic order, and n is represented by the number of monitoring sub-areas;
[0028] Step S002: Obtain the power grid generation dispatch optimization index of each monitoring sub-area of the power system after the new energy power station is connected to the grid, compare it with the preset power grid generation dispatch optimization index, screen out the number of the monitoring sub-area whose power grid generation dispatch optimization index is less than the preset power grid generation dispatch optimization index, mark it as an abnormal energy utilization efficiency area, and send it to the safety management personnel for power system optimization dispatching.
[0029] Preferably, the calculation formula of the performance stability evaluation coefficient is:
[0030] where θ i Expressed as the performance stability evaluation coefficient of the i-th monitoring sub-area, α i It is expressed as the power grid operation abnormality evaluation index of the i-th monitoring sub-area, β i It is expressed as the power grid generation dispatch optimization index of the i-th monitoring sub-area.
[0031] Preferably, the abnormal warning of power system stability is specifically:
[0032] The performance stability evaluation coefficient of each monitoring sub-area of the power system after the new energy power station is connected to the grid is obtained, and compared with the preset performance stability evaluation coefficient. If the performance stability evaluation coefficient of a monitoring sub-area is less than the preset performance stability evaluation coefficient, it indicates that the performance of the power system in the monitoring sub-area is abnormal, and the number of the abnormal area is sent to the power system stability control step for further processing. Otherwise, it indicates that the performance of the power system in the monitoring sub-area is normal.
[0033] Preferably, the power system stability control is specifically:
[0034] Step S001: Obtain the length of the electrical connection line of the abnormal area monitoring sub-area of the power system after the new energy power station is connected to the grid, marked as P i ;
[0035] Step S002: Calculate the power transmission efficiency. The specific calculation formula is:
[0036] in Expressed as the power transmission efficiency of the ith monitoring sub-area, fl i It is represented as the load voltage of the ith monitoring sub-area, fy i It is represented as the load current of the ith monitoring sub-area, dl i It is represented as the current of the i-th monitoring sub-area, dy i It is represented as the voltage of the ith monitoring sub-area;
[0037] Step S003: Obtain the maximum and mean values of the performance stability evaluation coefficients of each monitoring sub-area of the power system after the new energy power station is connected to the grid, marked as θ max , Δθ;
[0038] Step S004: The calculation formula of the power system stability control coefficient is:
[0039] where ω i Expressed as the power system stability control coefficient of the ith monitoring sub-area, θ i Expressed as the performance stability evaluation coefficient of the i-th monitoring sub-area, θ max is represented by the maximum value of the performance stability evaluation coefficient, Δθ is represented by the mean value of the performance stability evaluation coefficient, P i It is represented as the line length of the electrical connection of the ith monitoring sub-area, It is represented as the power transmission efficiency of the i-th monitoring sub-area, μ1 and μ2 are respectively represented as the performance stability evaluation coefficient and the weight factor of the power transmission efficiency, and μ1+μ2=1.
[0040] Technical effects and advantages of the present invention:
[0041] 1. The present invention provides a stability control method for a power system after a new energy power station is connected to the grid. The method collects the operation performance evaluation data of each monitoring sub-area of the power system after the new energy power station is connected to the grid, calculates the power grid operation abnormality evaluation index of each monitoring sub-area of the power system after the new energy power station is connected to the grid according to the new energy power generation data collection unit, calculates the power grid power generation dispatch optimization index of each monitoring sub-area of the power system after the new energy power station is connected to the grid according to the power grid dispatch capability data collection unit, compares them with preset values respectively, screens out the number of the abnormal area, further analyzes to obtain the performance stability evaluation coefficient, and compares it with the preset performance stability evaluation coefficient. If the performance stability evaluation coefficient of a certain monitoring sub-area is less than the preset performance stability evaluation coefficient, it indicates that the performance of the power system in the monitoring sub-area is abnormal, and the number of the abnormal area is sent to the power system stability control step for further processing. Otherwise, it indicates that the performance of the power system in the monitoring sub-area is normal. The power system is divided into a plurality of monitoring sub-areas, and the evaluations are performed separately, which is helpful to realize the refined management of the power system, establish an abnormal feedback mechanism, improve the fault management efficiency, and improve the energy utilization efficiency by optimizing the power generation dispatch control, thereby ensuring the safe and stable operation of the power system.
[0042] 2. The present invention provides a method for controlling the stability of an electric power system after a new energy power station is connected to the grid. The method utilizes the power system stability control, obtains the line length of the electrical connection and the power transmission efficiency of the monitoring sub-area of the abnormal area of the power system after the new energy power station is connected to the grid, and calculates the power system stability control coefficient of the monitoring sub-area of the abnormal area of the power system after the new energy power station is connected to the grid. The voltage fluctuation and low power transmission efficiency that may be caused by the connection of new energy to the grid are effectively suppressed through the stability control strategy, the power supply quality is improved, the automation of data collection, processing, analysis and evaluation is realized, and the possibility of manual intervention and human errors is reduced, which helps to improve the efficiency and accuracy of the evaluation and reduce the operation and maintenance costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0043] Figure 1 It is a schematic diagram of the connection of the method steps of the present invention.
[0044] Figure 2 This is a schematic diagram of the power system operation data acquisition structure of the present invention. DETAILED DESCRIPTION
[0045] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0046] See also Figure 1 As shown, the present invention provides a method for controlling the stability of an electric power system after a new energy power station is connected to the grid, including power system area division, power system operation data collection, new energy power generation abnormality management, new energy power grid dispatch optimization, power system stability assessment, power system stability abnormality warning, and power system stability control.
[0047] The power system regional division is connected with the power system operation data collection, the power system operation data collection is connected with the new energy power generation abnormal management, the new energy power generation abnormal management is connected with the new energy power grid dispatch optimization, the new energy power grid dispatch optimization is connected with the power system stability assessment, the power system stability assessment is connected with the power system stability abnormal early warning, and the power system stability abnormal early warning is connected with the power system stability control.
[0048] Step S01: The power system area division is used to divide the power system after the new energy power station is connected to the grid into various monitoring sub-areas according to the functional characteristics of the electrically connected lines, and number the monitoring sub-areas of the power system after the new energy power station is connected to the grid.
[0049] In a possible design, the specific division method of the power system area division is:
[0050] According to the functional characteristics of the electrical connection lines in the power system, the power system after the new energy power station is connected to the grid is divided into various monitoring sub-areas, and the monitoring sub-areas of the power system after the new energy power station is connected to the grid are numbered 1, 2, ...i, ...n in sequence.
[0051] See also Figure 2 As shown, step S02: the power system operation data acquisition is used to collect the operation performance evaluation data of each monitoring sub-area of the power system after the new energy power station is connected to the grid, the power system operation data acquisition includes a new energy power generation data acquisition unit and a power grid dispatching capability data acquisition unit, and the operation performance evaluation data includes new energy power generation data and power grid dispatching capability data.
[0052] In a possible design, the power system operation data collection is specifically as follows:
[0053] New energy power generation data acquisition unit: collects the current, voltage, and actual frequency of the power grid in each monitoring sub-area of the power system after the new energy power station is connected to the grid, marked as dl i ,dy i 、dp i , where i = 1, 2, ... n, i represents the number of the i-th monitoring sub-area;
[0054] Grid dispatching capability data collection unit: collects the transmission line utilization rate, energy storage capacity, and harmonic frequency of each monitoring sub-area of the power system after the new energy power station is connected to the grid, marked as ns respectively. i 、nr i 、nx i .
[0055] Step S03: The new energy power generation abnormality management is used to receive the operation performance evaluation data transmitted by the power system operation data collection step, and calculate the power grid operation abnormality evaluation index of each monitoring sub-area of the power system after the new energy power station is connected to the grid according to the new energy power generation data collection unit, compare it with the preset power grid operation abnormality evaluation index, and process it.
[0056] In a possible design, the abnormal management of renewable energy power generation is specifically as follows:
[0057] Step S001: Obtain the load voltage, load current, and monitoring duration of each monitoring sub-area of the power system at the load end after the new energy power station is connected to the grid, marked as fl i 、fy i ,t i ;
[0058] Step S002: The calculation formula of the power grid operation abnormality evaluation index is:
[0059] where α i It is represented as the power grid operation abnormality evaluation index of the ith monitoring sub-area, fl i It is represented as the load voltage of the ith monitoring sub-area, fy i It is represented as the load current of the ith monitoring sub-area, dl i It is represented as the current of the i-th monitoring sub-area, dy i It is represented as the voltage of the ith monitoring sub-area, dp i denoted as the actual grid frequency of the ith monitoring sub-area, DP0 as the rated grid frequency, and t i It is represented as the monitoring duration of the ith monitoring sub-area, and e is represented as a natural constant.
[0060] Step S003: Obtain the grid operation abnormality assessment index of each monitoring sub-area of the power system after the new energy power station is connected to the grid, compare it with the preset grid operation abnormality assessment index, filter out the numbers of the monitoring sub-areas whose grid operation abnormality assessment index is greater than the preset grid operation abnormality assessment index, and send them to the security management personnel for review.
[0061] Step S04: The new energy grid dispatching optimization is used to receive the operation performance evaluation data transmitted by the power system operation data collection step, and calculate the grid power generation dispatching optimization index of each monitoring sub-area of the power system after the new energy power station is connected to the grid according to the grid dispatching capacity data collection unit, and compare it with the preset grid power generation dispatching optimization index and process it.
[0062] In a possible design, the new energy grid dispatch optimization is specifically as follows:
[0063] Step S001: The calculation formula of the power grid generation dispatch optimization index is:
[0064] where β i It is represented as the power grid generation dispatch optimization index of the i-th monitoring sub-area, ns i It is expressed as the transmission circuit utilization rate of the ith monitoring sub-area, nr i It is represented as the energy storage capacity of the ith monitoring sub-area, nx i Expressed as the harmonic order of the i-th monitoring sub-area, NX 预 It is represented by the preset harmonic order, and n is represented by the number of monitoring sub-areas;
[0065] Step S002: Obtain the power grid generation dispatch optimization index of each monitoring sub-area of the power system after the new energy power station is connected to the grid, compare it with the preset power grid generation dispatch optimization index, screen out the number of the monitoring sub-area whose power grid generation dispatch optimization index is less than the preset power grid generation dispatch optimization index, mark it as an abnormal energy utilization efficiency area, and send it to the safety management personnel for power system optimization dispatching.
[0066] Step S05: The power system stability assessment is based on the power grid operation abnormality assessment index and the power grid generation dispatch optimization index of each monitoring sub-area of the power system after the new energy power station is connected to the grid, and the performance stability assessment coefficient of each monitoring sub-area of the power system after the new energy power station is connected to the grid is obtained by analysis.
[0067] In a possible design, the calculation formula of the performance stability evaluation coefficient is:
[0068] where θ i Expressed as the performance stability evaluation coefficient of the i-th monitoring sub-area, α i It is expressed as the power grid operation abnormality evaluation index of the i-th monitoring sub-area, β i It is expressed as the power grid generation dispatch optimization index of the i-th monitoring sub-area.
[0069] Step S06: The power system stability abnormality warning is used to receive the performance stability evaluation coefficient of each monitoring sub-area of the power system after the new energy power station is connected to the grid, compare it with the preset performance stability evaluation coefficient, and process it.
[0070] In a possible design, the abnormal power system stability warning is specifically:
[0071] The performance stability evaluation coefficient of each monitoring sub-area of the power system after the new energy power station is connected to the grid is obtained, and compared with the preset performance stability evaluation coefficient. If the performance stability evaluation coefficient of a monitoring sub-area is less than the preset performance stability evaluation coefficient, it indicates that the performance of the power system in the monitoring sub-area is abnormal, and the number of the abnormal area is sent to the power system stability control step for further processing. Otherwise, it indicates that the performance of the power system in the monitoring sub-area is normal.
[0072] Step S07: The power system stability control is used to receive the number of the abnormal area transmitted in the power system stability assessment step, and calculate the power system stability control coefficient of the power system abnormal area monitoring sub-area after the new energy power station is connected to the grid based on the line length and power transmission efficiency of the electrical connection of the power system abnormal area monitoring sub-area after the new energy power station is connected to the grid.
[0073] In a possible design, the power system stability control is specifically as follows:
[0074] Step S001: Obtain the length of the electrical connection line of the abnormal area monitoring sub-area of the power system after the new energy power station is connected to the grid, marked as P i ;
[0075] Step S002: Calculate the power transmission efficiency. The specific calculation formula is:
[0076] in Expressed as the power transmission efficiency of the ith monitoring sub-area, fl i It is represented as the load voltage of the ith monitoring sub-area, fy i It is represented as the load current of the ith monitoring sub-area, dl i It is represented as the current of the i-th monitoring sub-area, dy i It is represented as the voltage of the ith monitoring sub-area;
[0077] Step S003: Obtain the maximum and mean values of the performance stability evaluation coefficients of each monitoring sub-area of the power system after the new energy power station is connected to the grid, marked as θ max , Δθ;
[0078] Step S004: The calculation formula of the power system stability control coefficient is:
[0079] where ω i Expressed as the power system stability control coefficient of the ith monitoring sub-area, θ i Expressed as the performance stability evaluation coefficient of the i-th monitoring sub-area, θ max is represented by the maximum value of the performance stability evaluation coefficient, Δθ is represented by the mean value of the performance stability evaluation coefficient, P i It is represented as the line length of the electrical connection of the ith monitoring sub-area, It is represented as the power transmission efficiency of the i-th monitoring sub-area, μ1 and μ2 are respectively represented as the performance stability evaluation coefficient and the weight factor of the power transmission efficiency, and μ1+μ2=1.
[0080] In this embodiment, it should be specifically explained that the present invention collects the operation performance evaluation data of each monitoring sub-area of the power system after the new energy power station is connected to the grid, calculates the power grid operation abnormality evaluation index of each monitoring sub-area of the power system after the new energy power station is connected to the grid according to the new energy power generation data collection unit, and calculates the power grid power generation dispatch optimization index of each monitoring sub-area of the power system after the new energy power station is connected to the grid according to the power grid dispatch capacity data collection unit, and compares them with the preset values respectively, screens out the number of the abnormal area, further analyzes to obtain the performance stability evaluation coefficient, and compares it with the preset performance stability evaluation coefficient. If the performance stability evaluation coefficient of a certain monitoring sub-area is less than the preset performance stability evaluation coefficient, it indicates that the performance of the power system in the monitoring sub-area is abnormal, and the number of the abnormal area is sent to the power system stability control step for further processing. Otherwise, it indicates that the performance of the power system in the monitoring sub-area is normal. The power system is divided into multiple monitoring sub-areas and evaluated separately, which is helpful to realize the refined management of the power system, establish an abnormal feedback mechanism, improve the efficiency of fault management, and improve the energy utilization efficiency by optimizing the power generation dispatch control, thereby ensuring the safe and stable operation of the power system.
[0081] In this embodiment, it should be specifically explained that the present invention utilizes power system stability control to obtain the line length and power transmission efficiency of the electrical connection of the power system abnormal area monitoring sub-area after the new energy power station is connected to the grid, and calculates the power system stability control coefficient of the power system abnormal area monitoring sub-area after the new energy power station is connected to the grid. The voltage fluctuations and low power transmission efficiency that may be caused by the connection of new energy to the grid are effectively suppressed through the stability control strategy, the power supply quality is improved, the automation of data collection, processing, analysis and evaluation is realized, and the possibility of manual intervention and human errors is reduced, which helps to improve the efficiency and accuracy of the evaluation and reduce operation and maintenance costs.
[0082] Finally: The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A stability control method for the power system after the new energy power station is connected to the grid. It is characterized in that include: Step S01: power system area division: used to divide the power system after the new energy power station is connected to the grid into various monitoring sub-areas according to the functional characteristics of the electrically connected lines, and number the monitoring sub-areas of the power system after the new energy power station is connected to the grid; Step S02: Power system operation data collection: used to collect the operation performance evaluation data of each monitoring sub-area of the power system after the new energy power station is connected to the grid, the power system operation data collection includes a new energy power generation data collection unit and a power grid dispatching capacity data collection unit, and the operation performance evaluation data includes new energy power generation data and power grid dispatching capacity data; Step S03: New energy power generation abnormality management: used to receive the operation performance evaluation data transmitted by the power system operation data collection step, calculate the power grid operation abnormality evaluation index of each monitoring sub-area of the power system after the new energy power station is connected to the grid according to the new energy power generation data collection unit, compare it with the preset power grid operation abnormality evaluation index, and process it; Step S04: New energy grid dispatch optimization: used to receive the operation performance evaluation data transmitted by the power system operation data collection step, calculate the power grid generation dispatch optimization index of each monitoring sub-area of the power system after the new energy power station is connected to the grid according to the power grid dispatch capacity data collection unit, compare it with the preset power grid generation dispatch optimization index, and process it; Step S05: Power system stability assessment: Based on the power grid operation abnormality assessment index and power grid generation dispatch optimization index of each monitoring sub-area of the power system after the new energy power station is connected to the grid, the performance stability assessment coefficient of each monitoring sub-area of the power system after the new energy power station is connected to the grid is analyzed; Step S06: abnormal warning of power system stability: used to receive the performance stability evaluation coefficient of each monitoring sub-area of the power system after the new energy power station is connected to the grid, compare it with the preset performance stability evaluation coefficient, and process it; Step S07: Power system stability control: used to receive the number of the abnormal area transmitted in the power system stability assessment step, and calculate the power system stability control coefficient of the abnormal area monitoring sub-area of the power system after the new energy power station is connected to the grid based on the line length and power transmission efficiency of the electrical connection of the abnormal area monitoring sub-area of the power system after the new energy power station is connected to the grid.
2. According to claim 1, a method for controlling the stability of a power system after a new energy power station is connected to the grid, Features: The specific division method of the power system area division is as follows: According to the functional characteristics of the electrical connection lines in the power system, the power system after the new energy power station is connected to the grid is divided into various monitoring sub-areas, and the monitoring sub-areas of the power system after the new energy power station is connected to the grid are numbered 1, 2, ...i, ...n in sequence.
3. According to claim 2, a method for controlling the stability of a power system after a new energy power station is connected to the grid, Features: The power system operation data collection is specifically as follows: New energy power generation data acquisition unit: collects the current, voltage, and actual frequency of the power grid in each monitoring sub-area of the power system after the new energy power station is connected to the grid, marked as dl i ,dy i 、dp i , where i = 1, 2, ... n, i represents the number of the i-th monitoring sub-area; Grid dispatching capability data collection unit: collects the transmission line utilization rate, energy storage capacity, and harmonic frequency of each monitoring sub-area of the power system after the new energy power station is connected to the grid, marked as ns respectively. i 、nr i 、nx i .
4. According to claim 3, a method for controlling the stability of a power system after a new energy power station is connected to the grid, Features: The abnormal management of new energy power generation is specifically as follows: Step S001: Obtain the load voltage, load current, and monitoring duration of each monitoring sub-area of the power system at the load end after the new energy power station is connected to the grid, marked as fl i 、fy i ,t i ; Step S002: The calculation formula of the power grid operation abnormality evaluation index is: where α i It is represented as the power grid operation abnormality evaluation index of the ith monitoring sub-area, fl i It is represented as the load voltage of the ith monitoring sub-area, fy i It is represented as the load current of the ith monitoring sub-area, dl i It is represented as the current of the i-th monitoring sub-area, dy i It is represented as the voltage of the ith monitoring sub-area, dp i It is represented as the actual frequency of the power grid in the ith monitoring sub-area, DP 0 Expressed as the rated frequency of the power grid, t i It is represented as the monitoring duration of the ith monitoring sub-area, and e is represented as a natural constant. Step S003: Obtain the grid operation abnormality assessment index of each monitoring sub-area of the power system after the new energy power station is connected to the grid, compare it with the preset grid operation abnormality assessment index, filter out the numbers of the monitoring sub-areas whose grid operation abnormality assessment index is greater than the preset grid operation abnormality assessment index, and send them to the security management personnel for review.
5. According to claim 4, a method for controlling the stability of a power system after a new energy power station is connected to the grid, Features: The new energy grid dispatch optimization is specifically as follows: Step S001: The calculation formula of the power grid generation dispatch optimization index is: where β i It is represented as the power grid generation dispatch optimization index of the i-th monitoring sub-area, ns i It is expressed as the transmission circuit utilization rate of the ith monitoring sub-area, nr i It is represented as the energy storage capacity of the ith monitoring sub-area, nx i Expressed as the harmonic order of the i-th monitoring sub-area, NX 预 It is represented by the preset harmonic order, and n is represented by the number of monitoring sub-areas; Step S002: Obtain the power grid generation dispatch optimization index of each monitoring sub-area of the power system after the new energy power station is connected to the grid, compare it with the preset power grid generation dispatch optimization index, screen out the number of the monitoring sub-area whose power grid generation dispatch optimization index is less than the preset power grid generation dispatch optimization index, mark it as an abnormal energy utilization efficiency area, and send it to the safety management personnel for power system optimization dispatching.
6. A method for controlling the stability of a power system after a new energy power station is connected to the grid according to claim 5, Features: The calculation formula of the performance stability evaluation coefficient is: where θ i Expressed as the performance stability evaluation coefficient of the i-th monitoring sub-area, α i It is expressed as the power grid operation abnormality evaluation index of the i-th monitoring sub-area, β i It is expressed as the power grid generation dispatch optimization index of the i-th monitoring sub-area.
7. A method for controlling the stability of a power system after a new energy power station is connected to the grid according to claim 6, Features: The abnormal warning of power system stability is specifically: The performance stability evaluation coefficient of each monitoring sub-area of the power system after the new energy power station is connected to the grid is obtained, and compared with the preset performance stability evaluation coefficient. If the performance stability evaluation coefficient of a monitoring sub-area is less than the preset performance stability evaluation coefficient, it indicates that the performance of the power system in the monitoring sub-area is abnormal, and the number of the abnormal area is sent to the power system stability control step for further processing. Otherwise, it indicates that the performance of the power system in the monitoring sub-area is normal.
8. The method for controlling the stability of a power system after a new energy power station is connected to the grid according to claim 7, Features: The power system stability control is specifically as follows: Step S001: Obtain the length of the electrical connection line of the abnormal area monitoring sub-area of the power system after the new energy power station is connected to the grid, marked as P i ; Step S002: Calculate the power transmission efficiency. The specific calculation formula is: in Expressed as the power transmission efficiency of the ith monitoring sub-area, fl i It is represented as the load voltage of the ith monitoring sub-area, fy i It is represented as the load current of the ith monitoring sub-area, dl i It is represented as the current of the i-th monitoring sub-area, dy i It is represented as the voltage of the ith monitoring sub-area; Step S003: Obtain the maximum and mean values of the performance stability evaluation coefficients of each monitoring sub-area of the power system after the new energy power station is connected to the grid, marked as θ max , Δθ; Step S004: The calculation formula of the power system stability control coefficient is: where ω i Expressed as the power system stability control coefficient of the ith monitoring sub-area, θ i Expressed as the performance stability evaluation coefficient of the i-th monitoring sub-area, θ max is represented by the maximum value of the performance stability evaluation coefficient, Δθ is represented by the mean value of the performance stability evaluation coefficient, P i It is represented as the line length of the electrical connection of the ith monitoring sub-area, Expressed as the power transmission efficiency of the ith monitoring sub-area, μ 1 , μ 2 They are respectively expressed as the performance stability evaluation coefficient and the weight factor of the power transmission efficiency, and μ 1 +μ 2 =1.
Citation Information
Patent Citations
Power grid frequency stability evaluation method under multi-circuit direct-current simultaneous faults
CN112529373A
High-low voltage control monitoring system of photovoltaic substation based on constructional engineering
CN116914940A
Power flow calculation method for power distribution network with new energy grid connection
CN117318064A
Configuration operation method of energy storage system for new energy consumption
CN117879018A
Network-related performance remote test method and system for new energy station
CN118433059A
Cited By
Power dispatching method and system