Y-shaped steel connecting bridge and construction method thereof
By designing Y-shaped steel bridges and construction methods, the problems of single direction and poor shock absorption performance of the steel bridges in the airport terminal are solved, and the structure is stable, space optimization and operational efficiency are improved, ensuring convenient transfer and comfortable walking for passengers .
Patent Information
- Application Number
- CN202411208598.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-29
AI Technical Summary
The existing airport terminal has a single steel bridge direction, resulting in long passenger transit distance and time, low operational efficiency, and poor performance of existing shock absorption measures, which increases the weight of the bridge.
A Y-shaped steel bridge and its construction method are designed, using a Y-shaped bridge structure, connected to the embedded parts through support, setting up swing columns and multiple shock absorbers, and using shock-resistant spherical support and ball hinged recessed seats Improve the stability and shock absorption performance of the bridge body, and use segmented lifting to speed up the construction progress.
The connection structure of the airport's middle finger corridor has been optimized, the carrying capacity and space utilization have been improved, the transit distance and time of passengers have been shortened, the operational efficiency has been improved, and the passengers' walking comfort has been improved through shock absorbers.
Smart Images

Figure CN119041284A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and particularly relates to a Y-shaped steel bridge and a construction method thereof. Background Art
[0002] Most of the existing steel bridges at airport terminals are in the shape of a straight line and can only be connected from one location in the middle pier to another, with a single direction. As a result, the transfer distance and time between different flights are relatively long, the passenger throughput is small, and the airport operation efficiency is low.
[0003] The existing steel bridges usually use shock absorbers and concrete columns for shock absorption, which have poor shock absorption performance, cannot adapt to the deformation of the bridge structure, and will increase the weight of the bridge. Summary of the invention
[0004] In order to solve the above problems, the present invention provides a Y-shaped steel bridge and a construction method thereof.
[0005] The Y-shaped steel bridge of the present invention comprises: a bridge body, which is Y-shaped, and comprises a main line and two branch lines, and both ends of the bridge body are connected to support embedded parts through supports, and the support embedded parts are installed at the end of the middle finger corridor; a shock absorber, and there are multiple shock absorbers installed in the bridge body; a swing column, which is located below the middle position of the bridge body, the top of the swing column is connected to the bridge body, and the bottom of the swing column is connected to the floor beam.
[0006] The bridge body includes bridge section A, bridge section B, bridge section C, bridge section D, bridge section E and bridge section F. Bridge section F is located in the middle position, and the rocking column is located below bridge section F. Bridge section F is connected to bridge section E, bridge section B and bridge section D respectively. Bridge section B is also connected to bridge section A. Bridge section D is also connected to bridge section C. Bridge section E is connected to the end of the main line. Bridge section A and bridge section C are both connected to the end of the branch line. Shock absorbers are arranged in bridge section A, bridge section C and bridge section E.
[0007] The bearing is an earthquake-resistant spherical bearing, which includes a bidirectional movable bearing and a fixed bearing. The two bearings connected to bridge section E are both bidirectional movable bearings, and the two bearings connected to bridge section A and bridge section C are both a bidirectional movable bearing and a fixed bearing.
[0008] The bridge body is composed of a bridge deck, a bottom plate, a partition, a side beam, a web plate, a cantilever beam, a U-shaped stiffening rib and a plate stiffening rib. The bottom plate, two partitions, the bridge deck and two web plates are welded into a box-type component. The U-shaped stiffening rib runs through the box-type component along the length direction of the bridge deck and is arranged in the middle of the box-type component. The plate stiffening rib is arranged on both sides of the box-type component along the length direction of the bridge deck. The shock absorber is installed on two adjacent plate stiffening ribs.
[0009] The bottom ball joint recess of the swing column is fixedly connected to the embedded part in the floor beam, the bottom ball joint recess is connected to the bottom of the column through a safety bolt, the top of the column is connected to the top ball joint recess through a safety bolt, and the top ball joint recess is connected to the bridge body through a mounting ring.
[0010] The construction method of the Y-shaped steel bridge of the present invention comprises the following steps:
[0011] S1. Install the embedded parts and supports at the ends of the main line and branch line;
[0012] S2. Install temporary support frame for swing column;
[0013] S3. Install the swing column;
[0014] S4. Set up temporary support frame for the bridge;
[0015] S5. Install the bridge body;
[0016] S6. Remove the temporary support frame for the bridge body and the temporary support frame for the swing column.
[0017] The order of installing the bridge body in S5 is to first install bridge section F, and then install bridge section B, bridge section A, bridge section E, bridge section D, and bridge section C in sequence. The order of setting the temporary support frame of the bridge body in S4 is to first set the lower temporary support frames of bridge section B, bridge section D, bridge section E, and bridge section F, and then set the lower temporary support frames of bridge section A and bridge section C.
[0018] The bridge section F needs to be assembled on the ground. The bridge section F is composed of four components. The inverted assembly is adopted during the assembly, that is, the panel faces downward and the bottom plate faces upward during the assembly process. After the assembly and welding are completed, an 80-ton truck crane is used to turn the bridge body over and then hoist it as a whole. During the assembly process, the bottom plate of the bridge deck is a loose piece, and the internal web, rib plate, and flange plate of the bridge body need to be welded before the loose pieces are sealed and welded.
[0019] The bridge section A, bridge section B, bridge section C, bridge section D, bridge section E and bridge section F are all welded by the following steps:
[0020] P1. Weld the bridge deck and side beams first;
[0021] P2. Weld the U-shaped stiffeners and plate stiffeners to the bridge deck;
[0022] P3. Compact the partition and U-shaped stiffening ribs tightly without welding;
[0023] P4. Then weld the web to the bridge deck and diaphragm respectively;
[0024] P5. Weld the cantilever beam to the bridge deck, side beam and web respectively;
[0025] P6. Finally, weld the bottom plate to the web and partition respectively.
[0026] The temporary support frame of the swing column includes a limiting ring and three supporting legs connected to the limiting ring. The three supporting legs are located below the limiting ring and are evenly arranged. The other ends of the supporting legs are fixed to the floor beams by bolts. The inner diameter of the limiting ring matches the outer diameter of the swing column.
[0027] The beneficial effects of the present invention are that the Y-shaped steel bridge of the present invention connects two places inside the central pier of the airport, has a stable structure, strong bearing capacity, optimizes space, facilitates passenger gathering and distribution, and facilitates internal transfers, which can shorten the transfer distance and time between different flights and improve airport operation efficiency; a swing column is used to support the middle position of the bridge body to play a supporting role, and multiple TMD shock absorbers are set in the bridge body to improve the comfort of passengers walking in the bridge body. The use of the segmented hoisting method speeds up the construction progress of the steel bridge and shortens the construction time. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a structural schematic diagram of the present invention.
[0029] Figure 2 It is a side view of the present invention.
[0030] Figure 3 It is a schematic diagram of the installation position of the support of the present invention.
[0031] Figure 4 A schematic structural diagram of the bridge section F of the present invention.
[0032] Figure 5 It is a schematic diagram of the welding steps of each bridge section of the present invention.
[0033] Figure 6 yes Figure 1 Cross-sectional view along the aa direction.
[0034] Figure 7 yes Figure 1 Cross-sectional view along bb direction.
[0035] Figure 8 yes Figure 1 Cross-sectional view along the cc direction.
[0036] Fig. 9 yes Figure 1 Cross-sectional view in dd direction.
[0037] Fig.10 yes Figure 1 Cross-sectional view in the ee direction.
[0038] Fig.11 yes Figure 1 Cross-sectional view along the ff direction.
[0039] Fig.12It is a structural schematic diagram of the bidirectional movable support of the present invention.
[0040] Fig.13 A schematic structural diagram of a fixed support according to the present invention.
[0041] Fig.14 The structure of the swing column of the present invention is schematically shown in FIG. Figure 1 .
[0042] Fig.15 The structure of the swing column of the present invention is schematically shown in FIG. Figure 2 .
[0043] Fig.16 It is a segmented diagram of the bridge body of the present invention.
[0044] Fig.17 is the distribution of the four components of bridge section F Figure 1 .
[0045] Fig.18 is the distribution of the four components of bridge section F Figure 2 .
[0046] Fig.19 It is a structural schematic diagram of the temporary support frame for the bridge body of the present invention.
[0047] Fig. 20 It is a schematic diagram of the installation of the temporary support frame of the swing column of the present invention.
[0048] Fig.21 It is a side view of the deformation joint of the present invention.
[0049] Fig. 22 Schematic diagram of the pre-camber of the present invention.
[0050] Reference numerals:
[0051] Bridge body 1; branch line 2; main line 3; deformation joint 4; swing column fulcrum 5; swing column 6; swing column embedded part 601; bottom ball joint recess 602; top ball joint recess 603; safety bolt 604; column 605; stiffening ring plate 606; mounting ring 607; limit ring tenon 608; plug plate 609; swing column temporary support frame 610;
[0052] Floor beam 7; support embedded part 8; support 9; bidirectional movable support 901; fixed support 902; upper top plate 911; stainless steel slide plate 1 912; plane slide plate 1 913; middle plate 914; stainless steel slide plate 2 915; plane slide plate 2 916; spherical slide block 917; spherical shell slide plate 918; base 919;
[0053] Bridge deck 10; side beam 11; partition 12; U-shaped stiffening rib 13; plate stiffening rib 14; cantilever beam 15; bottom plate 16; web 17; shock absorber 18; temporary bridge support frame 19. DETAILED DESCRIPTION
[0054] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be understood as limiting the present invention.
[0055] like Figure 1-Figure 22 As shown, the Y-shaped steel bridge of the present invention comprises: a bridge body 1, a shock absorber 18 and a rocking column 6. The bridge body 1 is Y-shaped and comprises a main line and two branch lines. Both ends of the bridge body 1 are connected to the support embedded parts 8 through supports, and the support embedded parts are installed at the end of the middle finger corridor. There are multiple shock absorbers 18 installed in the bridge body 1. They are used to reduce the vibration response of the bridge body 1, that is, to play a shock absorbing role on the bridge body, and also to improve the walking comfort of passengers. The rocking column 6 is located below the middle position of the bridge body 1, the top of the rocking column 6 is connected to the bridge body 1, and the bottom of the rocking column 6 is connected to the floor beam 7. The rocking column 6 has a supporting function and is used to improve the anti-lateral displacement stiffness and stability.
[0056] like Fig.16 As shown, the bridge body 1 includes bridge section A, bridge section B, bridge section C, bridge section D, bridge section E and bridge section F. Bridge section F is located in the middle position, and the rocking column 6 is located below bridge section F. Bridge section F is connected to bridge section E, bridge section B and bridge section D respectively, bridge section B is also connected to bridge section A, bridge section D is also connected to bridge section C, bridge section E is connected to the end of the main line, bridge section A and bridge section C are both connected to the end of the branch line, and shock absorbers 18 are arranged in bridge section A, bridge section C and bridge section E.
[0057] like Figure 6-Figure 11 As shown, the bridge body 1 is composed of a bridge deck 10, a bottom plate 16, a partition 12, a side beam 11, a web 17, a cantilever beam 15, a U-shaped stiffening rib 13 and a plate stiffening rib 14. The bottom plate 16, two partitions 12, the bridge deck 10 and the two webs 17 are welded into a box-type component. The U-shaped stiffening rib 13 penetrates the box-type component along the length direction of the bridge deck 10 and is arranged in the middle of the box-type component. The plate stiffening rib 14 is arranged on both sides of the box-type component along the length direction of the bridge deck 10. The shock absorber 18 is installed on two adjacent plate stiffening ribs 14.
[0058] The shock absorber 18 has two types of natural frequencies of 2.16Hz and 3.92Hz, and is installed at the corresponding position according to actual needs. The shock absorber with a natural frequency of 2.16Hz has a spring stiffness of 92.002kN / m, a resistance coefficient of 1.085kN·s / m, and a damping coefficient of 1.0; the shock absorber with a natural frequency of 3.92Hz has a spring stiffness of 303.013kN / m, a resistance coefficient of 1.969kN·s / m, and a damping coefficient of 1.0. The shock absorber is installed at the center of the bridge body 1, with the upper end fixedly connected to the plate stiffener 14 and the lower end fixed to the support 9.
[0059] Two or four shock absorbers with a natural frequency of 3.92 Hz can be arranged in bridge section E, and two or four shock absorbers with a natural frequency of 2.16 Hz can be arranged in bridge section A and bridge section C. The analysis of the model before and after finite element shock absorption shows that the shock absorbers can play a good shock absorption role and control the vibration caused by crowd excitation load within the range required by the specification.
[0060] like Figure 12-13 As shown, the bearing 9 is a seismic spherical bearing, which includes a bidirectional movable bearing 901 and a fixed bearing 902. Figure 3 As shown, the two supports 9 connecting the bridge section E and the main line end are both bidirectional movable supports 901, and the two supports at the connection between the bridge section A and the bridge section C and the branch line end are both a bidirectional movable support 901 and a fixed support 902. The sliding amount of the bidirectional movable support 901 along the longitudinal direction of the bridge is 100mm, and the sliding amount along the transverse direction of the bridge is 30mm. Therefore, if Fig.21 As shown, there are 100mm deformation joints at the connections between the middle finger corridor and the main line end of the bridge body and the branch line end of the bridge body.
[0061] like Fig.12 As shown, it is a structural schematic diagram of the bidirectional movable support 901, which includes, from top to bottom, an upper top plate 911, a stainless steel slide plate 912, a flat slide plate 913, an intermediate plate 914, a stainless steel slide plate 915, a flat slide plate 916, a spherical slider 917, a spherical shell slide plate 918 and a base 919. The flat slide plate 913 is stuck in the top middle groove of the intermediate plate 914, a limit baffle is provided on the lower edge of the upper top plate 911, an inward convex ring is provided on the lower edge of the intermediate plate 914, an outward convex block is provided on the top edge of the base 919, and the convex block cooperates with the convex ring. The stainless steel slider 915 is fixed to the inner top of the intermediate plate 914, a flat slide plate 916 is fixed in the top groove of the spherical slider 917, and a spherical shell slide plate 918 is arranged between the spherical slider 917 and the base 919.
[0062] Stainless steel slide plate 1 912 is fixed on the top plate 911. Stainless steel slide plate 1 912 and plane slide plate 1 913 can slide relative to each other. Spherical slider 917 and base 919 are arranged below the middle plate 914. The middle plate 914 and base 919 can move relative to stainless steel slide plate 1 912 along the X direction under the action of plane slider 1 913. Stainless steel slide plate 2 915 is fixed to the bottom surface of the middle plate 914. Planar slider 2 916 is arranged on the top surface of the spherical slider 917. Spherical slider 917 and base 919 can move relative to stainless steel slide plate 2 915 along the Y direction under the action of plane slider 2 916. There is a spherical groove on the top of the base 919. A spherical shell slide plate 918 is arranged in the spherical groove. The spherical shell slide plate 918 cooperates with the spherical slider 917 so that the spherical slider 917 can rotate slightly relative to the base.
[0063] Performance indicators and material performance parameters of bidirectional movable bearing 901:
[0064] 1. Vertical pressure: F1=1000kN; vertical tension: F2=150kN; rotation angle: θ=0.02ard.
[0065] The material of the top plate and base is G20Mn5N.
[0066] Strength design value f = 230N / mm 2 ,f v =135N / mm 2 (16mm≤plate thickness≤50mm)
[0067] Strength design value f = 220N / mm 2 ,f v =125N / mm 2 (50mm≤plate thickness≤75mm)
[0068] Strength design value f = 205N / mm 2 ,f v =120N / mm 2 (75mm≤plate thickness≤100mm)
[0069] Strength design value f = 185N / mm 2 ,f v =105N / mm 2 (100mm≤plate thickness≤150mm)
[0070] 2. Model of stainless steel plate: 06Cr17Ni12Mo2
[0071] 3. The material of the spherical slider and the flat slider is polytetrafluoroethylene, with a compressive strength of f y =30N / mm 2
[0072] 4. Design value of welding groove f f w =200N / mm 2 .
[0073] The length of the plane skateboard 913 is 210 mm, the thickness is 7 mm, the length of the spherical slider 917 is 225 mm, and the inner wall width of the middle plate 914 is 270 mm, which ensures that during the rotation, the sharp edge of the lower end of the spherical shell skateboard 918 does not contact the spherical slider 917, and will not damage the spherical slider 917. The spherical shell skateboard 918 will never collide with the side wall of the middle plate 914, ensuring smooth rotation.
[0074] The expansion radius of the spherical slider 917 is larger than that of the flat slider 913, so the pressure-bearing requirement is met;
[0075] like Fig.13 As shown, it is a fixed support 902, which includes, from top to bottom, an upper top plate 2, a stainless steel slide plate 3, a flat slide plate 3, a spherical slide plate 2, a spherical shell slide plate 2 and a base 2, and the materials and performance are the same as those of the bidirectional movable support.
[0076] The spherical slider and the spherical shell slider box realize the transmission and force release of the external force exerted on the bridge body to the pier part through the cooperation between the spherical shell slider and the spherical groove of the base. At the same time, when the horizontal component of the external force causes a horizontal relative displacement between the bridge body and the pier, the plane slider and the spherical slider are conducive to the relative sliding between the spherical shell slider and the bottom plate, thereby ensuring the consistent rotation performance of the seismic spherical bearing in all directions, so that the function of the seismic spherical bearing structure can be stably realized.
[0077] like Figure 14-15 As shown, the rocking column 6 includes a column body 605, a bottom ball joint recess 602, a top ball joint recess 603 and a mounting ring 607. The bottom and top of the column body 605 are both spheres and are respectively connected to the bottom ball joint recess 602 and the top ball joint recess 603. The bottom ball joint recess 602 is fixedly connected to the rocking column embedded part 601 in the floor beam 7. The bottom ball joint recess 602 is connected to the bottom of the column body 605 through a safety bolt 604. The top of the column body 605 is connected to the top ball joint recess 603 through a safety bolt 604. The top ball joint recess 603 is connected to the bridge body 1 through a mounting ring 607.
[0078] The mounting ring 607 is fixedly connected to the top ball joint recess 603 by welding. The top of the mounting ring 607 is installed at the swing column fulcrum 5 in the middle of the bridge section F. The outside of the top ball joint recess 603 is a truncated cone that is wide at the top and narrow at the bottom. The inside of the top ball joint recess 603 is provided with a spherical groove. The top of the spherical groove protrudes outward to form a boss. The mounting ring 607 is welded to the outer wall of the boss. The safety bolt 604 is installed at the bottom of the spherical groove. The top boss of the spherical groove cooperates with the limiting ring tenon 608. The limiting ring tenon 608 can be inserted into the boss of the top ball joint recess 603. The top of the limiting ring tenon 608 is welded to the plug plate 609, and the end of the plug plate 609 is welded to the inner wall of the mounting ring 607. The outer wall and the top of the mounting ring 607 are welded to the bridge body 1.
[0079] There is a through hole for the safety bolt 604 to pass through at the center of the bottom ball joint recess 602 and the top ball joint recess 603. The inner diameter of the through hole is larger than the outer diameter of the screw of the safety bolt 604. The safety bolt 604 passes through the through hole in the spherical grooves of the bottom ball joint recess 602 and the top ball joint recess 603 to connect with the ball at the end of the column 1.
[0080] A stiffening ring plate 606 is also provided inside the middle position of the column 605 .
[0081] The construction method of the Y-shaped steel bridge of the present invention comprises the following steps:
[0082] S1. Install the embedded support parts 8 and support 9 at the ends of the main line and branch line;
[0083] S2. Install the temporary support frame 610 of the swing column: You need to install the swing column embedded part 601 first, the swing column embedded part 601 is fixed in the floor beam 7, and then the swing column temporary support frame 610 is installed around the swing column embedded part;
[0084] S3. Install the swing column: The bottom ball joint recess 602 of the swing column 6 is welded to the swing column embedded part 601, and the bottom of the column 605 of the swing column 6 is installed in the bottom ball joint recess 602 by the safety bolt 604;
[0085] S4. Set up temporary bridge support frame 19: first set up temporary support frames at the bottom of bridge section B, bridge section D, bridge section E, and bridge section F, and then set up temporary support frames at the bottom of bridge section A and bridge section C;
[0086] S5. Install the bridge body: first install the bridge section F, weld the top ball joint recess 603 and the mounting ring 607 of the swing column 6, and weld the top mounting ring 607 of the swing column 6 to the bottom of the bridge section F, and finally install the top of the column 605 in the top ball joint recess 603 through the safety bolt 604, and then install the bridge section B, bridge section A, bridge section E, bridge section D, and bridge section C in sequence;
[0087] S6. Dismantle the temporary bridge support frame 19 and the temporary swing column support frame 610.
[0088] S4 and S5 can be carried out alternately during implementation, such as setting up temporary support frames at the bottom of bridge sections B, D, E and F first, installing bridge section F, setting up temporary support frames at the bottom of bridge sections A and C, and then sequentially installing bridge section B, bridge section A, bridge section E, bridge section D and bridge section C. Finally, install the remaining bridge section structures.
[0089] The steel bridge was hoisted in 6 sections. Sections A, B, C, D and E were processed into whole components in the processing plant and transported to the site. Section F was separated in the factory according to the transportation width. After arriving at the site, the box was assembled into a whole and then hoisted. During the construction process, a truck crane (≤80t) was used to assemble and hoist the 7.88m floor of the middle finger corridor. Four lifting points were set for each section of the bridge body. An 80-ton truck crane was used for hoisting, and a 25-ton or 50-ton truck crane was used for assembly.
[0090] Bridge section F needs to be assembled on the ground before installation. Bridge section F consists of four components: 1#SCQ-2, 1#SCQ-3, 1#SCQ-4 and 1#SCQ-5. Fig.17 and Fig.18 As shown, Fig.17 For the panel facing up, Fig.18 The panel is facing downward. The assembly is inverted, that is, the panel is facing downward and the bottom plate is facing upward. After the assembly and welding are completed, an 80-ton truck crane is used to turn the bridge body over and then hoist it as a whole. During the assembly process, the bottom plate of the bridge deck is a scattered piece, and the internal web, rib plate, and flange plate of the bridge body need to be welded before the scattered pieces are sealed and welded.
[0091] like Figure 5 As shown, the four components of bridge section A, bridge section B, bridge section C, bridge section D, bridge section E and bridge section F are welded by the following steps:
[0092] P1. First weld the bridge deck 10 and the side beam 11;
[0093] P2. The U-shaped stiffener 13 and the plate stiffener 14 are welded to the bridge deck 10;
[0094] P3. Tighten and compact the partition 12 and the U-shaped stiffening rib 13 without welding;
[0095] P4. Then the web 17 is welded to the bridge deck 10 and the partition 12 respectively;
[0096] P5. The cantilever beam 15 is welded to the bridge deck 10, the side beam 11 and the web 17;
[0097] P6. Finally, weld the bottom plate 16 to the web 17 and the partition plate 12 respectively.
[0098] like Fig. 20 As shown, the temporary support frame 610 of the swing column includes a limiting ring and three legs connected to the limiting ring. The three legs are located below the limiting ring and are evenly arranged. The other ends of the legs are fixed to the floor beam 7 by bolts. The inner diameter of the limiting ring matches the outer diameter of the swing column 6. When installing the swing column 6, the column body 605 of the swing column 6 needs to be passed through the limiting ring, and then the column body 605 is welded to the bottom ball joint groove 602.
[0099] like Fig.19 The figure shows the structure of the bridge support frame 19. Since the steel bridge needs to be hoisted in sections, a temporary support frame needs to be set up during the construction process. The temporary support frame base is made of HN400*200*8*13 hot-rolled steel, the column is made of 200*10 square tube, and the diagonal brace is made of 16# I-beam. The support frame node connection is welded, and the base is fixedly connected to the floor concrete by M20 expansion bolts.
[0100] The steel box girder of a steel bridge has a large span. When the temporary support method is used for construction, in order to ensure the vertical curve of the steel box girder, the height of the temporary support should take into account the designed pre-camber during on-site installation. At the same time, the support deformation (including foundation settlement and support deformation, etc.) should be considered to set the support height. The pre-camber of this application is as follows: Fig. 22 shown.
[0101] Technical measures for support installation
[0102] (1) Selection of bearings: The seismic spherical bearings at the fixed end of the boarding bridge are divided into two-way movable bearings and fixed bearings. Before use, they must be installed in accordance with the requirements of the drawings. The installation direction of the bearings must comply with the requirements of the drawings and must be compared with the bearing nameplate model one by one before correct use.
[0103] (2) Support positioning: After the embedded parts are removed, use a total station to find the center point of the support, lay out the cross center line, and mark the center line on the support. During installation, ensure that the embedded parts layout completely coincides with the center line of the support mark.
[0104] (3) After the support is installed and the positioning is accepted, it is immediately welded to the embedded parts or steel columns. After welding is completed, the subsequent steel structure is installed.
[0105] (4) In order to ensure the stability of the support during the construction of the superstructure, temporary fixing measures will be taken between the support as a whole and the embedded parts after the support installation and welding is completed. After the installation of the boarding bridge superstructure is completed, the temporary fixing measures will be removed to ensure the normal use of the support function.
[0106] (5) For fixed bearings, remove the bearing connection device after the slope adjustment plate is welded; for unidirectional and bidirectional movable bearings, remove the bearing connection device and set the pre-bias value before welding the slope adjustment plate. After setting the bearing pre-bias value, the upper and lower movable parts of the bearing should be fixed as soon as possible. The fixing tooling should have high stability, and the fixing tooling parts should not be directly welded to the bearing.
[0107] Note that when welding the slope adjustment plate and the support, the four sides do not need to be fully welded to prevent welding deformation. The method of intermittent welding of the opposite sides can be adopted. Pay attention to the impact of the high temperature generated by welding on the internal silicone grease, Teflon plate or polymer plate. Try not to concentrate the heat on the top plate of the support. Perform anti-rust treatment after welding is completed.
[0108] In the description of the present invention, it is necessary to understand that the terms "center", "length", "width", "thickness", "up", "down", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0109] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features.
[0110] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0111] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0112] In the present invention, the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" etc. mean that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the described specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0113] Although the above embodiments have been shown and described, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations on the present invention. Changes, modifications, substitutions and variations of the above embodiments by those of ordinary skill in the art are all within the scope of protection of the present invention.
Claims
1. A Y-shaped steel bridge, characterized in that: include: The bridge body is Y-shaped and includes a main line and two branch lines. Both ends of the bridge body are connected to the support embedded parts through supports. The support embedded parts are installed at the end of the middle finger corridor. Shock absorbers, of which there are a plurality of shock absorbers installed in the bridge body; The swing column is located below the middle of the bridge body, the top of the swing column is connected to the bridge body, and the bottom of the swing column is connected to the floor beam.
2. The Y-shaped steel bridge according to claim 1, characterized in that: The bridge body includes bridge section A, bridge section B, bridge section C, bridge section D, bridge section E and bridge section F. Bridge section F is located in the middle position, and the rocking column is located below bridge section F. Bridge section F is connected to bridge section E, bridge section B and bridge section D respectively. Bridge section B is also connected to bridge section A. Bridge section D is also connected to bridge section C. Bridge section E is connected to the end of the main line. Bridge section A and bridge section C are both connected to the end of the branch line. Shock absorbers are arranged in bridge section A, bridge section C and bridge section E.
3. The Y-shaped steel bridge according to claim 2, characterized in that: The bearing is an earthquake-resistant spherical bearing, which includes a bidirectional movable bearing and a fixed bearing. The two bearings connected to bridge section E are both bidirectional movable bearings, and the two bearings connected to bridge section A and bridge section C are both a bidirectional movable bearing and a fixed bearing.
4. The Y-shaped steel bridge according to claim 2, characterized in that: The bridge body is composed of a bridge deck, a bottom plate, a partition, a side beam, a web plate, a cantilever beam, a U-shaped stiffening rib and a plate stiffening rib. The bottom plate, two partitions, the bridge deck and two web plates are welded into a box-type component. The U-shaped stiffening rib runs through the box-type component along the length direction of the bridge deck and is arranged in the middle of the box-type component. The plate stiffening rib is arranged on both sides of the box-type component along the length direction of the bridge deck. The shock absorber is installed on two adjacent plate stiffening ribs.
5. The Y-shaped steel bridge according to claim 4, characterized in that: The rocking column comprises a column body, a bottom ball joint recess and a top ball joint recess, wherein the bottom ball joint recess is fixedly connected to the embedded parts in the floor beam, the bottom ball joint recess is connected to the bottom of the column body through a safety bolt, the top of the column body is connected to the top ball joint recess through a safety bolt, and the top ball joint recess is connected to the bridge body through a mounting ring.
6. A construction method for a Y-shaped steel bridge as claimed in any one of claims 1 to 5, characterized in that: The following steps are involved: S1. Install the embedded parts and supports at the ends of the main line and branch line; S2. Install temporary support frame for swing column; S3. Install the swing column; S4. Set up temporary support frame for the bridge; S5. Install the bridge body; S6. Remove the temporary support frame for the bridge body and the temporary support frame for the swing column.
7. The construction method of the Y-shaped steel bridge according to claim 6 is characterized by: The order of installing the bridge body in S5 is to first install bridge section F, and then install bridge section B, bridge section A, bridge section E, bridge section D, and bridge section C in sequence. The order of setting the temporary support frame of the bridge body in S4 is to first set the temporary support frames of bridge section B, bridge section D, bridge section E and the lower part of bridge section F, and then set the lower temporary support frames of bridge section A and bridge section C.
8. The construction method of the Y-shaped steel bridge according to claim 7 is characterized in that: The bridge section F needs to be assembled on the ground. The bridge section F is composed of four components. The inverted assembly is adopted during the assembly process, that is, the panel faces downward and the bottom plate faces upward. After the assembly and welding are completed, an 80-ton truck crane is used to turn the bridge body over and then hoist it as a whole.
9. The construction method of the Y-shaped steel bridge according to claim 7, characterized in that: The bridge section A, bridge section B, bridge section C, bridge section D, bridge section E and bridge section F are all welded by the following steps: P1. Weld the bridge deck and side beams first; P2. Weld the U-shaped stiffeners and plate stiffeners to the bridge deck; P3. Compact the partition and U-shaped stiffening ribs tightly without welding; P4. Then weld the web to the bridge deck and diaphragm respectively; P5. Weld the cantilever beam to the bridge deck, side beam and web respectively; P6. Finally, weld the bottom plate to the web and partition respectively.
10. The construction method of the Y-shaped steel bridge according to claim 6, characterized in that: The temporary support frame of the swing column includes a limiting ring and three supporting legs connected to the limiting ring. The three supporting legs are located below the limiting ring and are evenly arranged. The other ends of the supporting legs are fixed to the floor beams by bolts. The inner diameter of the limiting ring matches the outer diameter of the swing column.