Overpass bridge installation method
Through guide beam assist technology and flexible transport of self-propelled module transport vehicles, the problem of the inability to apply to cross-rail/river bridges is solved, rapid installation and low-impact construction are achieved, and traffic interference and road transformation are reduced.
Patent Information
- Application Number
- CN202411390403.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-08
- Publication Date
- 2024-11-29
AI Technical Summary
The existing SPMT module turning method cannot be applied to the installation of cross-rail/river bridges, and roads need to be closed during construction, resulting in greater traffic interference.
Using guide beam assist technology, the prefabricated bridge is gradually moved to both sides of the boundary by using a self-propelled module transport vehicle, reducing the length of the bridge cantilever, avoiding the setting of support structures within the boundary, achieving rapid erection, and flexibly transported through the self-propelled module transport vehicle , reduce the impact on roads and traffic.
The rapid installation of cross-rail/river bridges has been achieved, which reduces traffic interference during the pre-construction preparation and process, avoids road transformation and traffic organization breakdowns, and improves construction efficiency and safety.
Smart Images

Figure CN119041305A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bridge erection, and in particular to a method for installing a cross-line bridge. Background Art
[0002] The demolition and construction of urban bridges and highway cross-line bridges faces the problem of how to reduce traffic interference and social impact. Traditional cross-line bridge construction methods such as demolition, blasting, crane, and bridge erection machine have problems such as long traffic closure time and high safety risks. In recent years, the rapid bridge construction technology based on self-propelled modular transporters (SPMTs) has emerged, which can significantly reduce traffic interference and social impact, and has obvious economic and social benefits.
[0003] SPMT modular vehicles are widely used in the transportation of large, heavy, high and other special-shaped structures in manufacturing, petroleum, aerospace engineering, nuclear engineering, and bridge engineering. It has the characteristics of synchronous hydraulic jacking, movement, precise positioning and large carrying capacity, and can realize modular vehicle assembly and transportation of large-scale and large-tonnage structures. Self-propelled modular vehicles have irreplaceable advantages in the transportation of bridge components or bridges that are super long, super heavy, super high and super wide, which are not replaceable by other transportation methods: large load capacity, easy transportation; flexible steering; modular combination to improve the applicability of complex component transportation; can realize self-loading and unloading of large and heavy-loaded components; has an independent hydraulic suspension system, can overcome complex road conditions, and has strong adaptive ability.
[0004] However, the current bridge rapid replacement technology based on SPMT modular vehicles has the following problems:
[0005] (1) The SPMT train needs to cross the existing route and travel on the crossed road. However, for bridges across railways / rivers, the SPMT train cannot cross the railways / rivers.
[0006] (2) The SPMT method requires the road to be closed for a certain period of time during construction, and the structures on the road (such as the central dividing strip, etc.) must be modified to allow the SPMT trains to pass, which causes significant traffic disruption. Summary of the invention
[0007] The purpose of the present invention is to provide a method for installing a cross-line bridge to solve the problem that the SPMT method is not applicable to the installation of cross-railway / river bridges.
[0008] The above technical effects of the present invention are mainly achieved through the following technical solutions:
[0009] The present invention provides a method for installing a cross-line bridge, which is used to erect a prefabricated bridge on a limit. The method for installing a cross-line bridge comprises:
[0010] Step S1: Connecting a guide beam at one end of the bridge, using a plurality of first self-propelled module transport vehicles to lift the bridge and move it to a first side of the limit;
[0011] Step S2: each of the first self-propelled module transporters moves toward the limit until the guide beam crosses the limit;
[0012] Step S3: arranging a second self-propelled module transporter on a second side of the limit to support the end of the guide beam crossing the limit;
[0013] Step S4: each of the first self-propelled module transporters continues to drive the bridge and the guide beam to move until the bridge crosses the limit;
[0014] Step S5: Arrange a third self-propelled module transporter on the second side of the boundary to support the end of the bridge across the boundary.
[0015] The installation method of the cross-line bridge described in the present invention sets a guide beam, which reduces the cantilever length of the bridge itself and correspondingly reduces the bending moment of the cantilever end. The bridge can be erected without setting a corresponding supporting structure within the limit. During the pre-construction preparation and construction process, the existing road under the bridge is not occupied, and there is no need to modify the original ground road or interrupt the traffic organization, thereby reducing the impact on the existing traffic under the bridge.
[0016] The method for installing a cross-line bridge described in the present invention adopts a self-propelled modular transport vehicle to transport the bridge. The self-propelled modular transport vehicle is flexible in transportation and the number of self-propelled modular transport vehicles can be adjusted according to the actual length and weight of the bridge, thereby realizing the rapid erection of the cross-line bridge.
[0017] In a preferred embodiment of the present invention, after a third self-propelled module transporter is arranged on the second side of the boundary to support the bridge across the boundary, the present invention further comprises:
[0018] Step S6: dismantling the connection between the guide beam and the bridge and removing the guide beam by the second self-propelled module transporter.
[0019] In this embodiment, the guide beam is only a simple cantilever beam temporarily set up to assist in the erection of the bridge. After the bridge crosses the limit and completes the support, the guide beam can be removed by a self-propelled modular transport vehicle so that the bridge can be transported to its location in the subsequent process.
[0020] In a preferred embodiment of the present invention, after the connection between the guide beam and the bridge is dismantled and the guide beam is removed, the method further comprises:
[0021] Step S7: moving the first self-propelled module transporter and the third self-propelled module transporter at both ends of the bridge to move the bridge to a predetermined erection position;
[0022] Step S8: removing the first self-propelled module transporter and the third self-propelled module transporter at both ends of the bridge to respectively erect the two ends of the bridge on the prefabricated beam supports at both sides of the limit.
[0023] In this embodiment, after the guide beam is removed from the bridge, the bridge can be further transported to the erection position by a self-propelled modular transport vehicle, and then the bridge can be accurately lowered onto the prefabricated beam support (usually the bridge pier) by utilizing the precise positioning and synchronous lifting functions of the self-propelled modular transport vehicle.
[0024] In a preferred embodiment of the present invention, while the first self-propelled module transporter continues to drive the bridge and the guide beam until the bridge crosses the limit:
[0025] On the first side of the limit, in a direction away from the limit, removing each of the first self-propelled module transporters under the bridge one by one;
[0026] On the second side of the boundary, along the direction close to the boundary, the second self-propelled module transporters are added one by one under the guide beam to support the guide beam.
[0027] In this embodiment, when the bridge gradually moves from the first side to the second side above the limit, the first self-propelled modular transporters approaching the limit are gradually removed from the first side, that is, the first self-propelled modular transporters on the first side used to support the bridge are removed one by one to avoid the first self-propelled modular transporters interfering with the limit or needing to cross the limit; at the same time, second self-propelled modular transporters are gradually added to the second side to support the guide beam to avoid the guide beam on the second side affecting the movement of the bridge due to insufficient support.
[0028] In a preferred embodiment of the present invention, in the process of driving the bridge and the guide beam across the limit by the first self-propelled module transporter, the movement direction of the first self-propelled module transporter is perpendicular to the extension direction of the limit.
[0029] In this embodiment, regardless of whether the final erection and installation direction of the bridge is perpendicular to the extension direction of the limit, when the bridge is transported across the line by the first self-propelled modular transport vehicle, the moving direction of the bridge and the guide beam is made perpendicular to the extension direction of the limit, thereby reducing the length of the cantilever (bridge and / or guide beam) above the limit, thereby avoiding bending of the bridge or guide beam due to the excessive length of the cantilever (the part without support).
[0030] In a preferred embodiment of the present invention, the connected bridge and guide beam are located on the same straight line.
[0031] In this embodiment, the bridges and guide beams located on the same straight line enable the first self-propelled module transport vehicle, the second self-propelled module transport vehicle and the third self-propelled module transport vehicle to move synchronously along the same straight line during the transportation process, thereby reducing the difficulty of operation during the erection process.
[0032] In a preferred embodiment of the present invention, the first self-propelled module transporter, the second self-propelled module transporter and the third self-propelled module transporter include: a column; a hydraulic lifting system, which is arranged on the column to realize the lifting and lowering of the bridge or the guide beam; and a walking wheel group, which is arranged on the column to realize the steering and movement of the self-propelled module transporter.
[0033] In this embodiment, the support height of the columns formed by the steel pipe columns of the self-propelled module transporter can be flexibly adjusted to adapt to bridges of different structural forms such as equal height and variable height.
[0034] In a preferred embodiment of the present invention, a distribution beam or a pad is provided on the top of the column.
[0035] In a preferred embodiment of the present invention, the guide beam is a long strip truss structure formed by splicing metal parts, the bridge is a reinforced concrete structure, and the weight of the guide beam is less than the weight of the bridge.
[0036] In this embodiment, the light guide beam is used as a cantilever beam across the limit, thereby preventing the heavy bridge from forming a cantilever above the limit, which would cause the bridge to tilt during the crossing process.
[0037] In a preferred embodiment of the present invention, the boundary is a road or a river. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the prior art descriptions. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. In the drawings:
[0039] The accompanying drawings described herein are only for explanation purposes and are not intended to limit the scope of the present invention in any way. In addition, the shapes and proportional dimensions of the various components in the figures are only schematic, used to help understand the present invention, and are not specifically limited to the shapes and proportional dimensions of the various components of the present invention. Those skilled in the art can select various possible shapes and proportional dimensions to implement the present invention according to the teachings of the present invention.
[0040] Figure 1 It is a structural schematic diagram of the first state of the operation process of the overpass bridge installation method of the present invention;
[0041] Figure 2 It is a structural schematic diagram of the second state of the operation process of the overpass bridge installation method of the present invention;
[0042] Figure 3 It is a structural schematic diagram of the third state of the operation process of the overpass bridge installation method of the present invention;
[0043] Figure 4 It is a structural schematic diagram of a fourth state of the operation process of the overpass bridge installation method of the present invention;
[0044] Figure 5 It is a structural schematic diagram of the fifth state of the operation process of the overpass bridge installation method of the present invention;
[0045] Figure 6 It is a schematic structural diagram of the sixth state of the operation process of the overpass bridge installation method of the present invention;
[0046] Figure 7 It is a structural schematic diagram of the seventh state of the operation process of the cross-line bridge installation method of the present invention;
[0047] Figure 8 It is a structural schematic diagram of an eighth state of the operation process of the cross-line bridge installation method of the present invention;
[0048] Fig. 9 It is a structural schematic diagram of the ninth state of the operation process of the cross-line bridge installation method of the present invention.
[0049] Description of reference numerals:
[0050] 10. Bridge; 11. Guide beam; 12. Precast beam support;
[0051] 20. limit; 21. first side; 22. second side;
[0052] 31. The first self-propelled modular transport vehicle; 32. The second self-propelled modular transport vehicle; 33. The third self-propelled modular transport vehicle. DETAILED DESCRIPTION
[0053] In order to enable those skilled in the art to better understand the technical solutions in the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0054] It should be noted that when an element is referred to as being "disposed on" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only and are not intended to be the only embodiment.
[0055] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those generally understood by those skilled in the art of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.
[0056] like Figures 1 to 6 As shown, the present invention provides a method for installing a cross-line bridge, which is used to erect a prefabricated bridge 10 on a limit 20. The method for installing a cross-line bridge comprises the following steps:
[0057] Step S1: Connect the guide beam 11 at one end of the bridge 10, and use a plurality of first self-propelled module transporters 31 to lift the bridge 10 and move it to the first side 21 of the limit 20;
[0058] Step S2: each first self-propelled module transporter 31 moves toward the limit 20 until the guide beam 11 crosses the limit 20;
[0059] Step S3: a second self-propelled module transporter 32 is arranged on the second side 22 of the boundary 20 to support the end of the guide beam 11 crossing the boundary 20;
[0060] Step S4: Each first self-propelled module transporter 31 continues to drive the bridge 10 and the guide beam 11 to move until the bridge 10 crosses the limit 20;
[0061] Step S5 : A third self-propelled module transporter 33 is arranged on the second side 22 of the boundary 20 to support the end of the bridge 10 across the boundary 20 .
[0062] The method for installing a cross-line bridge described in the present invention provides a guide beam 11, which reduces the cantilever length of the bridge 10 itself and correspondingly reduces the bending moment at the cantilever end. The bridge 10 can be erected without providing a corresponding supporting structure above the limit 20. During the pre-construction preparation and construction process, the existing road under the bridge is not occupied, and there is no need to modify the original ground road or disconnect the traffic organization, thereby reducing the impact on the existing traffic under the bridge.
[0063] The method for installing a cross-line bridge described in the present invention uses a self-propelled modular transport vehicle to transport the bridge 10. The self-propelled modular transport vehicle is flexible in transportation, and the number of self-propelled modular transport vehicles can be adjusted according to the actual length and weight of the bridge 10, thereby realizing the rapid erection of the cross-line bridge 10.
[0064] The specific process of each step of the overpass installation method of the present invention will be described in detail below.
[0065] Specifically, in step S1, Figure 1 As shown, before the construction of the bridge 10 across the line is carried out, the route for transporting the bridge 10 from the prefabrication site to the construction site is preplanned, one end of the prefabricated bridge 10 is connected to the guide beam 11 in the prefabrication site, and then three first self-propelled module transporters 31 are used to lift and support the bridge 10 and leave the prefabrication site. After that, the above-mentioned first self-propelled module transporters 31 are moved along the predetermined route, and then the above-mentioned bridge 10 and the guide beam 11 are transported to the construction site, and then transported to the first side 21 of the limit 20. Among them, the limit 20 can be a road (railway, highway, etc.), or a river. Of course, the number of first self-propelled module transporters 31 used for lifting and supporting the bridge 10 can be determined according to actual needs.
[0066] Preferably, the guide beam 11 is a long strip truss structure formed by splicing metal parts, the bridge 10 is a reinforced concrete structure, and the weight of the guide beam 11 is less than the weight of the bridge 10. The light guide beam 11 is used as a cantilever beam across the limit 20, thereby preventing the heavy bridge 10 from forming a cantilever above the limit 20, thereby causing the bridge 10 to tilt during the crossing process.
[0067] Specifically, in step S2, if Figure 1 and Figure 2 As shown, after the bridge 10 and the guide beam 11 are transported to the construction site, the directions of the guide beam 11 and the bridge 10 are turned so that the guide beam 11 faces the direction of the limit 20; then, each first self-propelled module transport vehicle 31 continues to be moved on the first side 21 until one end of the guide beam 11 crosses the limit 20 and extends to the second side 22 of the limit 20.
[0068] Specifically, in step S3, if Figure 2As shown, after the guide beam 11 crosses the limit 20, a second self-propelled module transporter 32 is arranged on the second side 22 of the limit 20, and the second self-propelled module transporter 32 lifts and supports one end of the guide beam 11, thereby forming a support structure on the first side 21 and the second side 22 of the limit 20, and releasing the cantilever structure formed by the guide beam 11 above the limit 20.
[0069] Specifically, in step S4, if Figures 3 to 5 As shown, the first self-propelled module transporter 31 is continuously used to transport the bridge 10 from the first side 21 to the second side 22. On the first side 21 of the limit 20, the first self-propelled module transporters 31 under the bridge 10 are removed one by one in a direction away from the limit 20; on the second side 22 of the limit 20, the second self-propelled module transporters 32 are added one by one under the guide beam 11 in a direction close to the limit 20 to support the guide beam 11.
[0070] During the process of gradually transferring the bridge 10 from the first side 21 to the second side 22 above the limit 20, the first self-propelled module transporters 31 approaching the limit 20 are removed one by one on the first side 21, that is, the first self-propelled module transporters 31 on the first side 21 of the limit 20 for supporting the bridge 10 are gradually removed to avoid interference between the first self-propelled module transporters 31 and the limit 20. At the same time, second self-propelled module transporters 32 are added one by one on the second side 22 of the limit 20 to support the guide beam 11 to avoid the guide beam 11 on the second side 22 from affecting the transfer of the bridge 10 due to insufficient support.
[0071] Specifically, in step S5, if Figure 5 As shown, after one end of the bridge 10 crosses the limit 20 and extends to the second side 22 of the limit 20, a third self-propelled module transporter 33 is set on the second side 22 of the limit 20 to support the end of the bridge 10; at this time, the bridge 10 crosses the limit 20, and the end located on the first side 21 of the limit 20 is lifted and supported by the first self-propelled module transporter 31, and the end located on the second side 22 of the limit 20 is lifted and supported by the third self-propelled module transporter 33.
[0072] The preferred implementation of the overpass installation method of the present invention will be further described below.
[0073] According to one embodiment of the present invention, Figure 6 As shown, after a third self-propelled module transporter 33 is arranged on the second side 22 of the boundary 20 to support the bridge 10 across the boundary 20, the following further comprises:
[0074] Step S6 : dismantling the connection between the guide beam 11 and the bridge 10 and removing the guide beam 11 by the second self-propelled module transporter 32 .
[0075] Specifically, in step S6, if Figure 6 As shown, the guide beam 11 is only a simple cantilever beam temporarily set up to assist in the erection of the bridge 10. After the bridge 10 crosses the limit 20 and completes the support, the connection between the guide beam 11 and the bridge 10 can be dismantled, and the guide beam 11 can be removed by two second self-propelled module transporters 32, so that the position or angle of the bridge 10 can be adjusted in the subsequent process.
[0076] According to one embodiment of the present invention, Figures 7 to 9 As shown, after the connection between the guide beam 11 and the bridge 10 is dismantled and the guide beam 11 is removed, the following steps are further included:
[0077] Step S7: moving the first self-propelled module transporter 31 and the third self-propelled module transporter 33 at both ends of the bridge 10 to move the bridge 10 to a predetermined erection position;
[0078] Step S8: remove the first self-propelled module transporter 31 and the third self-propelled module transporter 33 at both ends of the bridge 10 to respectively erect both ends of the bridge 10 on the precast beam supports 12 at both sides of the limit 20 .
[0079] Specifically, in step S7, if Figure 7 As shown, after the guide beam 11 is removed from the bridge 10, since the erection direction of the bridge 10 is usually different from the extension direction of the bridge 10 during the transportation process in the above step S4, it is necessary to further adjust the position and direction of the bridge 10 by the first self-propelled module transporter 31 and the third self-propelled module transporter 33 until the bridge 10 moves to the predetermined erection position.
[0080] Specifically, in step S8, Figure 8 and Fig. 9 As shown, after the bridge 10 is adjusted into position again, the precise positioning and synchronous lifting functions of the self-propelled modular transport vehicle are utilized to precisely lower the bridge 10 onto the prefabricated beam support 12 (usually a bridge pier), thereby realizing the cross-line erection of the bridge 10 while avoiding any impact on the lower limit 20.
[0081] According to one embodiment of the present invention, in the process of driving the bridge 10 and the guide beam 11 across the limit 20 by the first self-propelled module transporter 31 , the movement direction of the first self-propelled module transporter 31 is perpendicular to the extension direction of the limit 20 .
[0082] Regardless of whether the final erection and installation direction of the bridge 10 is perpendicular to the extension direction of the limit 20, when the bridge 10 is transported across the line by the first self-propelled module transport vehicle 31, the moving direction of the bridge 10 and the guide beam 11 is made perpendicular to the extension direction of the limit 20, thereby reducing the length of the cantilever above the limit 20 (the cantilever formed by the guide beam 11 in step S2), thereby avoiding bending of the bridge 10 or the guide beam 11 due to the excessive length of the cantilever (the part without support).
[0083] According to one embodiment of the present invention, the connected bridge 10 and guide beam 11 are located on the same straight line; the bridge 10 and guide beam 11 located on the same straight line enable the first self-propelled module transport vehicle 31, the second self-propelled module transport vehicle 32 and the third self-propelled module transport vehicle 33 to move synchronously along the same straight line during the transportation process, thereby reducing the difficulty of operation during the erection process.
[0084] According to one embodiment of the present invention, the first self-propelled module transporter 31, the second self-propelled module transporter 32 and the third self-propelled module transporter 33 all include: a column; a hydraulic lifting system, which is arranged on the column to realize the lifting and lowering of the bridge 10 or the guide beam 11; and a running wheel set, which is arranged on the column to realize the steering and movement of the self-propelled module transporter. The support height of the column of the self-propelled module transporter can be flexibly adjusted to adapt to bridges 10 of different structural forms such as equal height and variable height.
[0085] Specifically, the column is composed of a plurality of steel pipe columns. The hydraulic lifting system is mainly composed of a plurality of hydraulic cylinders, which are usually located at the four corners or sides of the self-propelled module transporter and are responsible for the actual lifting action. The bridge is mainly lifted and lowered by the hydraulic system, and no support seat is provided on the top of the column. The walking wheel group, each walking wheel in the walking wheel group can be driven by a motor or a hydraulic system to provide strong traction. In a preferred embodiment, the self-propelled module transporter is equipped with a walking wheel group composed of a plurality of omnidirectional wheels (such as universal wheels), which can flexibly turn and move in a small space.
[0086] Preferably, a distribution beam or a pad is provided on the top of the column; the pad can have a certain buffering effect on the bridge 10 and the guide beam 11, ensuring the stability of the transfer process, and the extension direction of the distribution beam is perpendicular to the length direction of the bridge 10, thereby increasing the support area of the bridge 10 in the width direction and ensuring the stability of the bridge 10 during transportation.
[0087] The specific embodiments described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific embodiment of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A method for installing a cross-line bridge, for erecting a prefabricated bridge (10) on a limit (20), characterized in that: The installation method of the overpass (10) comprises: Connecting a guide beam (11) at one end of the bridge (10), and using a plurality of first self-propelled module transport vehicles (31) to lift the bridge (10) and move it to a first side (21) of the limit (20); Each of the first self-propelled module transporters (31) moves toward the limit (20) until the guide beam (11) crosses the limit (20); A second self-propelled module transporter (32) is provided on a second side (22) of the boundary (20) to support the end of the guide beam (11) across the boundary (20); Each of the first self-propelled module transport vehicles (31) continues to drive the bridge (10) and the guide beam (11) to move until the bridge (10) crosses the limit (20); A third self-propelled module transporter (33) is arranged on the second side (22) of the boundary (20) to support the end of the bridge (10) across the boundary (20).
2. The method for installing a cross-line bridge according to claim 1, characterized in that: After a third self-propelled module transporter (33) is arranged on the second side (22) of the boundary (20) to support the bridge (10) across the boundary (20), the method further comprises: The connection between the guide beam (11) and the bridge (10) is dismantled and the guide beam (11) is removed by the second self-propelled module transporter (32).
3. The method for installing a cross-line bridge according to claim 2, characterized in that: After the connection between the guide beam (11) and the bridge (10) is dismantled and the guide beam (11) is removed, the method further comprises: Moving the first self-propelled module transport vehicle (31) and the third self-propelled module transport vehicle (33) at both ends of the bridge (10) to move the bridge (10) to a predetermined erection position; The first self-propelled module transport vehicle (31) and the third self-propelled module transport vehicle (33) at both ends of the bridge (10) are removed to respectively erect both ends of the bridge (10) on the prefabricated beam supports (12) at both sides of the limit (20).
4. The method for installing a cross-line bridge according to claim 1, characterized in that: While the first self-propelled module transporter (31) continues to drive the bridge (10) and the guide beam (11) until the bridge (10) crosses the limit (20): On the first side (21) of the limit (20), in a direction away from the limit (20), each of the first self-propelled module transporters (31) under the bridge (10) is removed one by one; On the second side (22) of the boundary (20), along the direction close to the boundary (20), the second self-propelled module transporters (32) are added one by one under the guide beam (11) to support the guide beam (11).
5. The method for installing a cross-line bridge according to claim 1, characterized in that: In the process of driving the bridge (10) and the guide beam (11) across the limit (20) by each of the first self-propelled module transporters (31), the movement direction of the first self-propelled module transporters (31) is perpendicular to the extension direction of the limit (20).
6. The method for installing a cross-line bridge according to claim 1, characterized in that: The connected bridge (10) and guide beam (11) are located on the same straight line.
7. The method for installing a cross-line bridge according to claim 1, characterized in that: The first self-propelled module transport vehicle (31), the second self-propelled module transport vehicle (32) and the third self-propelled module transport vehicle (33) all include: Column; A hydraulic lifting system, arranged on the column and used to realize the lifting and lowering of the bridge (10) or the guide beam (11); The traveling wheel set is arranged on the upright column and is used for realizing the steering and movement of the self-propelled module transport vehicle.
8. The method for installing a cross-line bridge according to claim 7, characterized in that: A distribution beam or a cushion block is arranged on the top of the column.
9. The method for installing a cross-line bridge according to claim 1, characterized in that: The guide beam (11) is a long strip truss structure formed by splicing metal parts, the bridge (10) is a reinforced concrete structure, and the weight of the guide beam (11) is less than the weight of the bridge (10).
10. The method for installing a flying bridge according to claim 1, characterized in that: The boundary (20) is a road or a river.