Urban central heating pipeline electric preheating installation method

By using length inspection devices and temperature sensors in the electric preheating installation of urban centralized heating pipelines, combined with auxiliary vehicles for rapid backfilling, the problems of excessive backfilling time and cracking of polyethylene outer casing were solved, achieving a highly efficient electric preheating installation effect.

CN119042409AInactive Publication Date: 2024-11-29HUANENG DAQING THERMOELECTRICITY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411137077.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2024-11-29
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the electric preheating installation of directly buried hot water insulation pipes for urban centralized heating, excessive backfilling time affects the backfilling quality, resulting in excessive elongation and shrinkage, and long-term open trenching time can easily cause the polyethylene outer casing to crack.

Method used

An electric preheating installation method for urban centralized heating pipelines is adopted, including steps S1 to S9. By installing length inspection devices and temperature sensors at both ends of the pipeline, the safe placement and temperature control of the electric preheating equipment are ensured. Backfilling and layered compaction are carried out in a timely manner, and auxiliary vehicles are used for rapid backfilling to prevent the pipeline from being exposed.

Benefits of technology

It effectively saves backfilling and insulation time, ensures backfilling quality, prevents cracking of polyethylene outer casing, meets design temperature and elongation requirements, and improves the effect of electric preheating installation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119042409A_ABST
    Figure CN119042409A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of urban heat supply, and provides an urban centralized heat supply pipeline electric preheating installation method which comprises the following steps: step 1, excavating a pipe ditch according to a general construction procedure, welding a pipeline, and performing flaw detection, pressing and joint heat preservation work; 2, accumulated water in the pipeline is completely discharged; 3, bolts are welded to the pipe ends of the pipelines to serve as binding posts; step 4, leveling an electric preheating equipment placement site; step 5, installing a temperature sensor; step 6, mounting a length inspection device at each of the two ends of the preheating pipe section; 7, plastic films are installed at the tail ends of the two sides of the pipeline for sealing, and a cable is connected with a steel pipe end binding post and electric preheating equipment; 8, after backfilling is completed within the set time, layered tamping must be conducted according to the design requirement; ninthly, after backfilling and tamping meet the design requirements, electric preheating equipment is turned off, and accessories are dismantled; the problem that in the prior art, the backfilling time is long is solved, and the good electric preheating installation effect is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of heating, and in particular to an electric preheating installation method for urban central heating pipelines. Background Art

[0002] At present, in my country's urban centralized heating direct buried hot water insulation pipes, electric preheating installation is widely used for the direct burial of large-diameter long-distance heating pipes, and according to the actual situation on site, the electric preheating installation method can be divided into open trench preheating method and covering soil preheating method. At present, the installation method of urban centralized heating direct buried hot water insulation pipes at home and abroad is mainly electric preheating installation. Generally speaking, when site conditions permit, the open trench preheating method will be preferred, but this method has major disadvantages. The backfill time is too long, which affects the backfill quality, and the open trench time is too long, which will easily cause the polyethylene outer casing to crack. Summary of the invention

[0003] The present invention provides an electric preheating installation method for urban centralized heating pipelines, which effectively solves the problem that soil needs to be backfilled to three quarters of the pipe diameter before electric preheating, and after the preheating reaches the acceptance conditions, the backfilling time of the backfill soil is too long, affecting the backfill quality, causing excessive elongation shrinkage and thus affecting the electric preheating quality, and the technical defect that the polyethylene shell of the pipeline is cracked due to a long open trench time before preheating. The invention provides a method that can save backfill insulation time to ensure the backfill quality and prevent the polyethylene jacket of the insulation pipeline from being cracked due to the long-term exposure of one quarter of the pipe diameter before preheating.

[0004] In order to solve the above technical problems, the present invention provides a method for installing electric preheating of urban central heating pipelines, comprising:

[0005] Step S1: excavating a pipe trench, welding the pipes, inspecting and pressurizing the pipes, and insulating the pipe joints;

[0006] Step S2: drain the accumulated water in the pipeline;

[0007] Step S3: welding bolts at the pipe ends of the pipeline as terminal posts;

[0008] Step S4: Level the site for placing the electric preheating equipment to ensure that the placement of the electric preheating equipment (commercially available model 945kw-70V*13500A) is dry and safe;

[0009] Step S5: installing a temperature sensor: opening an opening on the outer shell of the heating pipe at a first distance from the pipe end where the preheating device is placed on the pipe to install the temperature sensor, and the sensor probe of the temperature sensor is attached to and fixed on the surface of the pipe body of the heating pipe;

[0010] Step S6: A length inspection device is installed at both ends of the preheating pipe section to measure the elongation of the pipe. A length inspection device with a scaled ruler and a white line with a relative size to the ruler is installed at both ends of the water supply of the preheating pipe section to indicate the initial scale of the pipe before preheating;

[0011] Step S7: Install plastic film seals at both ends of the pipeline, connect the cable to the steel pipe end terminal and the electric preheating device; turn on the electric preheating device to preheat, record the initial temperature, and organize acceptance after the temperature reaches the acceptance standard;

[0012] Step S8: Backfill and compact in layers according to the design requirements, and complete the backfilling within the specified time of 24 hours. The backfilling must be compacted in layers according to the design requirements. If the shrinkage of the preheating section exceeds the design requirements due to the backfilling quality not meeting the design requirements, the preheating fails and needs to be reheated;

[0013] Step S9: After backfilling and compaction meet the design requirements, turn off the electric preheating equipment and remove the accessories.

[0014] Preferably, in step S3: the distance between each bolt is not less than 100 mm to facilitate the installation of cables, the bolt installation position is not less than 300 mm from the pipe end, and the bolts must be fully welded without any cold welds.

[0015] Preferably, the distance between the electric preheating equipment placement site and the pipe end terminal connection position shall not exceed 8 meters; the first distance is 12 meters.

[0016] Preferably, step S8 is executed based on the auxiliary vehicle, and the auxiliary vehicle includes: a driving motor, a convex wheel, a push block, and a conveyor belt; a seat body, a walking device is arranged at the lower end of the seat body, the driving motor is fixedly installed in the first installation cavity of the seat body, the output shaft of the driving motor is directly connected to the transmission shaft one, and the bevel gear one is installed on the transmission shaft one, and the upper and lower ends of the bevel gear one are respectively meshed with the bevel gear two and the bevel gear three, the bevel gear two is connected to the transmission shaft two, and the bevel gear three is connected to the transmission shaft three, and the first gear is fixedly installed on the transmission shaft three, the first gear and the idler gear are meshed with each other, and the idler gear and the second gear are meshed with each other, the second gear is fixedly installed on the transmission shaft four, and the first gear, the idler gear, and the second gear are installed in the second installation cavity; the second gear is used to drive the sealing device, and the transmission shaft two is used to drive the conveying device for conveying.

[0017] Preferably, a third mounting cavity is arranged on the seat body above the first mounting cavity, and a sealing device is installed in the third mounting cavity, the sealing device comprising: a transmission shaft four, a convex wheel, a push plate, a return spring, a push-pull rod one, and a push-pull rod two; a convex wheel is installed on the upper end of the transmission shaft four, the convex wheel contacts the push plate, the push plate is slidably installed in the slide groove, two return springs are connected to the left side of the push plate and the third mounting cavity, the right side of the push plate is connected to the push-pull rod two, the push-pull rod two is connected to the baffle, the baffle is installed at the bottom exit of the storage bin, a storage bin is arranged on the seat body at the upper part of the third mounting cavity, the right side of the push plate is connected to the push-pull rod one, the push-pull rod one is fixedly connected to the push block, the push block is located in the horizontal section of the backfill soil channel directly below the baffle, and a conveying device is arranged below the backfill soil channel.

[0018] Preferably, the conveying device includes: bevel gear four, transmission shaft two is connected to bevel gear four, bevel gear four and bevel gear five are meshed with each other, bevel gear five is fixedly connected to the driving pulley of the conveyor belt, and a backfill soil outlet is set at the output end of the conveyor belt.

[0019] Compared with the prior art, the present invention has the following beneficial effects:

[0020] 1. After the electric preheating of the preheated pipeline meets the requirements, the backfill insulation time will be greatly saved, and the backfill compaction quality can be guaranteed within the effective backfill time, avoiding the increase of shrinkage and thus affecting the effect of electric preheating.

[0021] 2. After each section of pipeline is welded and the insulation is completed, sand can be backfilled to the top of the pipe in time to prevent the polyethylene jacket of the insulation pipe from being cracked due to the temperature difference between day and night due to long-term exposure of the pipeline. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0023] Figure 1 It is a flow chart of a method for installing electric preheating of a city central heating pipeline provided by an embodiment of the present invention;

[0024] Figure 2 It is a structural schematic diagram of an auxiliary vehicle in a method for installing electric preheating of a city central heating pipeline provided by an embodiment of the present invention;

[0025] Figure 3 It is a partial enlarged view of the A area in the electric preheating installation method of a city central heating pipeline of the present invention;

[0026] Reference numerals:

[0027] In the figure: 1, seat; 2, shock absorbing device; 3, walking device; 4, bevel gear five; 5, bevel gear four; 6, transmission shaft two; 7, backfill soil outlet; 8, conveyor belt; 9, backfill soil channel; 10, push block; 11, push-pull rod two; 12, auxiliary vehicle; 1201, first installation cavity; 1202, second installation cavity; 1203, third installation cavity; 13, drive motor; 14, transmission shaft one; 15, bevel gear one; 16, bevel gear two; 17, bevel gear three; 18, transmission shaft three; 19, first gear; 20, idler; 21, second gear; 22, transmission shaft four; 23, convex wheel; 24, push plate; 25, reset spring; 26, push-pull rod one; 27, slide groove; 28, storage bin; 29, baffle. DETAILED DESCRIPTION

[0028] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be clearly and completely described below in conjunction with the drawings of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0029] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.

[0030] In addition, in the present invention, the descriptions of "first", "second", etc. are only used for descriptive purposes, and do not specifically refer to the order or sequence, nor are they used to limit the present invention. They are only used to distinguish components or operations described with the same technical terms, and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the technical solutions and technical features between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in the field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be considered that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.

[0031] The present invention provides the following embodiments

[0032] Example 1

[0033] The embodiment of the present invention provides a method for installing electric preheating of a city central heating pipeline. Figure 1 As shown, including:

[0034] The present invention is carried out according to the following steps:

[0035] Step S1: excavating a pipe trench, welding the pipes, inspecting and pressurizing the pipes, and insulating the pipe joints;

[0036] Step S2: To ensure the preheating effect, drain the accumulated water in the pipeline;

[0037] Step S3: Weld bolts at the pipe end of the pipeline as terminal posts. The distance between each bolt is not less than 100 mm to facilitate the installation of cables. The installation position is not less than 300 mm from the pipe end. The bolts must be fully welded without any cold welds.

[0038] Step S4: Level the site for placing the electric preheating equipment, and ensure that the placement of the electric preheating equipment (commercially available model 945kw-70V*13500A) is dry and safe; and the distance from the connection position of the pipe end terminal should not exceed 8 meters;

[0039] Step S5: installing a temperature sensor: an opening is made on the outer shell of the heating pipe at a first distance from the pipe end (preheating device end) where the preheating device end is placed on the pipe to install a temperature sensor (model PT100), and a sensor probe of the temperature sensor is attached and fixed to the surface of the pipe body of the heating pipe;

[0040] Step S6: A length inspection device is installed at both ends of the preheating pipe section to measure the elongation of the pipe. A length inspection device with a scaled ruler and a white line with a relative size to the ruler are installed at both ends of the water supply of the preheating pipe section to indicate the initial scale of the pipe before preheating;

[0041] Step S7: Install plastic film seals at both ends of the pipeline, connect the cable to the steel pipe end terminal and the electric preheating device; turn on the electric preheating device to preheat, record the initial temperature, and organize acceptance after the temperature reaches the acceptance standard;

[0042] Step S8: Backfill and compact in layers according to the design requirements, and complete the backfilling within the specified time of 24 hours. The backfilling must be compacted in layers according to the design requirements. If the shrinkage of the preheating section exceeds the design requirements due to the backfilling quality not meeting the design requirements, the preheating fails and needs to be reheated;

[0043] Step S9: After backfilling and compaction meet the design requirements, turn off the electric preheating equipment and remove the accessories.

[0044] The final acceptance is as follows:

[0045] 1. The initial startup temperature is 32.8℃, and the final heating temperature is 55.6℃, which meets the design requirements;

[0046] 2. Designed elongation: Actual elongation: Pipe end A = 146mm, end B = 143mm. Actual elongation is = 146 + 143 = 288mm, which meets the design requirements.

[0047] Results: The non-compensated electric preheating installation method for the directly buried hot water insulation pipeline for urban centralized heating of the present invention can meet the design temperature and elongation requirements, and is more suitable for the on-site construction of the directly buried hot water insulation pipeline for long-distance heating.

[0048] In step S3: the distance between each bolt is not less than 100 mm to facilitate the installation of the cable, the bolt installation position is not less than 300 mm from the pipe end, and the bolts must be fully welded without any cold welds.

[0049] The distance between the electric preheating equipment placement site and the pipe end terminal connection location shall not exceed 8 meters; the first distance is 12 meters.

[0050] The principle of electric preheating technology is to connect the electric preheating equipment to the working steel pipe through a cable to form a closed loop. The electric preheating power supply equipment (commercially available) converts the alternating current and 380v voltage input by the generator into high-current direct current and low-voltage electric energy to act on the preheating steel pipe section, and uses the principle of heating by the steel pipe's own resistance to heat the working steel pipe of the insulated pipeline to the designed preheating temperature. The power supply equipment converts the alternating current input by the generator into direct current, and the high voltage into low voltage. It uses the physical principle of electrical work (I is current, R is steel pipe resistance, and T is heating time) to generate heat energy to work on the working steel pipe of the insulated pipeline to reach the designed preheating temperature, release the thermal stress of the pipeline, and ensure stress safety during pipeline operation. The DC power work is stable, and the low-voltage operation will not cause safety hazards to people.

[0051] Conclusion: The backfill time is shortened, which ensures sufficient compaction during the backfill process. The backfill quality meets the density requirements and achieves a good electric preheating installation effect.

[0052] In summary, after the electric preheating of the present invention reaches the requirements, the backfill insulation time is greatly saved, and the backfill compaction quality can be guaranteed within the effective backfill time to avoid the increase of the shrinkage. After each section of the pipeline is welded and the insulation is completed, the sand can be backfilled to 300mm on the top of the pipe in time, which prevents the polyethylene jacket of the insulation pipeline from being cracked due to the temperature difference between day and night caused by the long-term exposure of the pipeline. The difficulty of the present invention is that after the electric preheating temperature reaches the design temperature, the elongation meets the design requirements;

[0053] The innovation of the present invention is that it not only meets the design requirements, but also saves backfilling time, ensures the quality of backfilling and compaction, and prevents the problem of long-term exposure and cracking of the outer casing of the pipeline.

[0054] After the electric preheating meets the requirements, the backfill insulation time is greatly saved, and the backfill compaction quality can be guaranteed within the effective backfill time to avoid increasing the shrinkage.

[0055] After each section of pipeline is welded and insulated, sand can be backfilled in time to 300mm from the top of the pipe to prevent the polyethylene jacket of the insulated pipe from cracking due to the temperature difference between day and night due to long-term exposure of the pipeline.

[0056] The present invention mainly examines the installation process of direct buried insulated hot water pipes. When the electric preheating technology is used, the design unit traditionally backfills the pipe with sand to three quarters of the pipe diameter before the electric preheating construction. Therefore, the following problems are caused:

[0057] 1. The long-term open trench before electric preheating caused the temperature difference between day and night in the polyethylene shell of the insulation pipe to crack, resulting in quality problems of the material, seriously affecting the quality of the project.

[0058] 2. After the electric preheating is completed, the electric preheating equipment is turned on to maintain the temperature until the entire section of the pipeline is backfilled. The insulation time is generally not more than 24 hours per kilometer of trench. Generally, the trench length is not less than 500 meters. It takes a long time to backfill from three-quarters of the pipeline to 300mm of the pipeline (general design requirements). It takes even longer to backfill the soil 1.4 meters above the top of the pipe. Therefore, due to the long backfilling time, the civil engineering unit often cannot ensure sufficient compaction during the backfilling process, and the backfill quality cannot meet the density requirements, resulting in excessive shrinkage, affecting the effect of the electric preheating installation.

[0059] The raw materials, length inspection device, sealing device, temperature sensor, cable and other equipment used in the present invention are all commercially available products; the length inspection device is a scale ruler with scales such as A-1 and A-2; the sealing device plastic film and temperature sensor are PT100.

[0060] The beneficial effects of the above technical solution are:

[0061] 1. It solves the problem that the length of each preheating section of the heating pipeline is generally very long, the welding and installation time is long, resulting in a quarter of the pipeline being exposed for a long time, and the polyethylene shell of the insulation pipeline cracking due to the temperature difference between day and night, which seriously affects the quality and life of the pipe.

[0062] 2. The pipe is backfilled with sand to 300mm from the top of the pipe, which solves the pipe quality problem caused by the temperature difference between day and night when the pipe is exposed. Because the sand is filled to 300mm from the top of the pipe before preheating, after the electric preheating is completed and the temperature and elongation design requirements are reached, the soil needs to be backfilled to 1.4 meters from the top of the pipe and compacted to meet the design quality requirements of the backfill. This is simple and efficient, which can meet the design requirements without damaging the pipe. After the welding of each section of the pipe is completed and the insulation is completed, the sand can be backfilled to the top of the pipe in time to prevent the polyethylene jacket of the insulation pipe from cracking due to the temperature difference between day and night due to long-term exposure of the pipe.

[0063] 3. Fill sand to three quarters of the pipe diameter before preheating, and backfill after preheating to the designed temperature and elongation. This greatly saves backfilling time (the time for filling sand from three quarters of the pipe diameter to 300mm on the top of the pipe is too long), and can fully guarantee the backfill quality within the effective time to avoid excessive shrinkage affecting the effect of electric preheating.

[0064] Example 2

[0065] On the basis of Example 1, Figure 1-Figure 3 As shown,

[0066] The step S8 is performed based on the auxiliary vehicle 12, which includes: a driving motor 13, a convex wheel 23 (cam), a push block 10, and a conveyor belt 8;

[0067] A seat body 1, a walking device 3 is arranged at the lower end of the seat body 1, the walking device 3 is connected to the shock absorbing device 2, the driving motor 13 is fixedly installed in the first installation cavity 1201 of the seat body 1, the output shaft of the driving motor 13 is directly connected to the transmission shaft 14, a bevel gear 15 is installed on the transmission shaft 14, the upper and lower ends of the bevel gear 15 are respectively meshed with the bevel gear 2 16 and the bevel gear 3 17, the bevel gear 2 16 is connected to the transmission shaft 2 6, the bevel gear 3 17 is connected to the transmission shaft 3 18, a first gear 19 is fixedly installed on the transmission shaft 3 18, the first gear 19 is meshed with the idler gear 20, the idler gear 20 is meshed with the second gear 21, the second gear 21 is fixedly installed on the transmission shaft 4 22, the first gear 19, the idler gear 20 and the second gear 21 are installed in the second installation cavity 1202;

[0068] The second gear 21 is used to drive the sealing device, and the transmission shaft 26 is used to drive the conveying device for conveying.

[0069] A third installation cavity 1203 is provided on the seat body 1 above the first installation cavity 1201. A sealing device is installed in the third installation cavity 1203. The sealing device includes: a transmission shaft 4 22, a convex wheel 23, a push plate 24, a return spring 25, a push-pull rod 1 26, and a push-pull rod 2 11;

[0070] A convex wheel 23 is installed on the upper end of the transmission shaft four 22, and the convex wheel 23 contacts the push plate 24. The push plate 24 is slidably installed in the slide groove 27. The left side of the push plate 24 and the third installation cavity 1203 are connected to two return springs 25. The right side of the push plate 24 is connected to the push-pull rod two 11, and the push-pull rod two 11 is connected to the baffle 29. The baffle 29 is installed at the bottom outlet of the storage bin 28. The storage bin 28 is arranged on the upper part of the third installation cavity 1203 on the seat body 1. The right side of the push plate 24 is connected to the push-pull rod one 26, and the push-pull rod one 26 is fixedly connected to the push block 10. The push block 10 is located in the horizontal section of the backfill channel 9 directly below the baffle 29, and a conveying device is arranged below the backfill channel 9.

[0071] The conveying device includes: bevel gear four 5, the transmission shaft two 6 is connected to bevel gear four 5, the bevel gear four 5 and bevel gear five 4 are meshed with each other, the driving pulley of the conveyor belt 8 is fixedly connected to the bevel gear five 4, and the output end of the conveyor belt 8 is provided with a backfill soil outlet 7.

[0072] The beneficial effects of the above technical solution are:

[0073] 1. As described in step S8, backfill and layered compaction are carried out according to the design requirements, and the backfill must be completed within the specified time of 24 hours. Layered compaction must be carried out according to the design requirements. If the shrinkage of the preheating section exceeds the design requirements due to the backfill quality not meeting the design requirements, the preheating fails and needs to be reheated. Therefore, the backfill process must be fast and the backfill quality must be guaranteed. When digging the trench, the backfill sand is stored in the storage bin 28. At this time, the drive motor 13 is not turned on, the push plate 24 connected to the convex wheel 23 is located at the rightmost position, the baffle 29 is against the outlet below the storage bin 28, the reset spring 25 is in a stretched state, and the push block 10 is also in the rightmost position. The backfill sand will not fall, and the auxiliary vehicle 12 is in a ready state and placed on the site.

[0074] 2. Since the sand filling on the top of the pipe needs to reach 300mm from the top of the pipe before preheating the pipeline, after the pipeline welding is completed, the auxiliary vehicle 12 quickly lays the backfill sand along the trench, starts the drive motor 13, and the transmission shaft 14 drives the bevel gears 1, 2 and 3 to rotate, wherein the bevel gear 3 17 drives the first gear 19 in the second installation cavity 1202 to start rotating, and the idler gear 20 meshing with it drives the second gear 21 to transmit power to the transmission shaft 4 22, and the convex wheel 23 thereon rotates, and the push plate 24 starts to reciprocate under the elastic force of the reset spring 25, and the baffle 29 moves to the left to open the outlet of the storage bin 28. At this time, the push block 10 is also located at the leftmost position, and the backfill sand is discharged and falls into the horizontal section of the backfill soil channel 9. The next reciprocating motion will cause the baffle 29 to move to the right to resist the outlet of the storage bin 28. At this time, the push block 10 moves to the right to discharge the backfill sand in the horizontal section of the backfill soil channel 9 onto the conveyor belt 8.

[0075] 3. After starting the drive motor 13, the bevel gear 2 16 drives the transmission shaft 2 6 to rotate. The bevel gear 4 5 is fixedly installed at the end of the transmission shaft 2 6 and also starts to rotate, driving the bevel gear 5 4 meshing therewith to rotate. The bevel gear 5 4 rotates the drive shaft connected to the conveyor belt 8 clockwise. The conveyor belt 8 discharges the backfill sand that falls thereon to the right to the backfill sand outlet 7, and falls into the trench to be backfilled. After the electric preheating is completed and reaches the design requirements of temperature and elongation, the soil needs to be backfilled to 1.4 meters from the top of the pipe. The backfill quality can be fully guaranteed within the effective time to avoid excessive shrinkage affecting the effect of electric preheating.

[0076] Example 3

[0077] On the basis of Example 1-2, Figure 1-3 As shown,

[0078] The elongation of the preheating pipe section is calculated based on the following formula:

[0079] ΔL=K1α·(t1-t0)·L+K2α·(t1-t0) 2 ·L+K3α·(t1-t0) 3 ·L

[0080] Wherein ΔL is the elongation of the preheating pipe section; α is the linear expansion coefficient of the preheating pipe steel; t0 is the initial temperature of the preheating pipe when the electric preheating equipment is turned on; t1 is the temperature of the preheating pipe after preheating; L is the length of the preheating pipe section (trench length); K1 is the correction coefficient of the ambient temperature to the preheating pipe (the value range of K1 is 0-1); K2 is the correction coefficient of the preheating pipe pressure (the value range of K2 is 0-1); K3 is the reference correction coefficient of the local soil thermal conductivity (the value range of K3 is 0-1);

[0081] After the acceptance is completed, the backfill must be completed within 24 hours in accordance with the design requirements and compacted layer by layer. After the backfill and compaction meet the design requirements, the machine is turned off and the accessories are removed.

[0082] The final acceptance is as follows:

[0083] 1. The initial startup temperature is 32.8℃, and the final heating temperature is 55.6℃, which meets the design requirements;

[0084] 2. Designed elongation: Actual elongation: Pipe end A = 146mm, end B = 143mm. Actual elongation is = 146 + 143 = 288mm, which meets the design requirements.

[0085] Results: The non-compensated electric preheating installation method for the directly buried hot water insulation pipeline for urban centralized heating of the present invention can meet the design temperature and elongation requirements, and is more suitable for the on-site construction of the directly buried hot water insulation pipeline for long-distance heating.

[0086] The beneficial effects of the above technical solution are:

[0087] According to the current urban heating pipeline, this calculation formula can accurately calculate the elongation of the preheating pipe section, providing a scientific basis for pipeline preheating. By considering the correction coefficient and environmental factors of the preheating pipeline, the calculation result is more in line with the actual situation. After acceptance, backfill and compaction in layers are carried out in time to ensure the stability and safety of the pipeline. At the same time, operations are carried out in accordance with design requirements to ensure the quality of the project. The steps of shutting down the machine and removing the accessories also enable the project to be successfully completed. The risk moving parts of the processing equipment to be monitored are determined, and real-time detection and evaluation are carried out during the preheating process of the preheating pipeline. Timely alarms are issued in case of abnormalities to avoid risk damage to the preheating pipeline and human injury.

[0088] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A method for installing electric preheating of urban central heating pipelines, characterized in that: The steps include: Step S1: excavating a pipe trench, welding the pipes, inspecting and pressurizing the pipes, and insulating the pipe joints; Step S2: drain the accumulated water in the pipeline; Step S3: welding bolts at the pipe ends of the pipeline as terminal posts; Step S4: Leveling the site for placing the electric preheating equipment; Step S5: installing a temperature sensor: opening an opening on the outer shell of the heating pipe at a first distance from the pipe end where the preheating device is placed on the pipe to install the temperature sensor, and the sensor probe of the temperature sensor is attached to and fixed on the surface of the pipe body of the heating pipe; Step S6: installing a length inspection device at both ends of the preheating pipe section to measure the elongation of the pipe; Step S7: Install plastic film seals at both ends of the pipeline, and connect the cable to the steel pipe end terminal and the electric preheating device; Turn on the electric preheating equipment to preheat, record the initial temperature, and organize acceptance after the temperature reaches the acceptance standard; Step S8: Backfill and compact in layers according to the design requirements, and complete the backfilling within the specified time of 24 hours. The backfilling must be compacted in layers according to the design requirements. If the shrinkage of the preheating section exceeds the design requirements due to the backfilling quality not meeting the design requirements, the preheating fails and needs to be reheated; Step S9: After backfilling and compaction meet the design requirements, turn off the electric preheating equipment and remove the accessories.

2. A method for installing electric preheating of urban central heating pipelines according to claim 1, characterized in that: In step S3: the distance between each bolt is not less than 100 mm to facilitate the installation of the cable, the bolt installation position is not less than 300 mm from the pipe end, and the bolts must be fully welded without any cold welds.

3. A method for installing electric preheating of urban central heating pipelines according to claim 1, characterized in that: The distance between the electric preheating equipment placement site and the pipe end terminal connection location shall not exceed 8 meters; the first distance is 12 meters.

4. The method for installing electric preheating of urban central heating pipelines according to claim 1 is characterized in that: Step S8 is performed based on the auxiliary vehicle (12), and the auxiliary vehicle (12) includes: a conveyor belt (8), a push block (10), a drive motor (13), and a convex wheel (23); A seat body (1), a walking device (3) is arranged at the lower end of the seat body (1), the driving motor (13) is fixedly mounted in a first mounting cavity (1201) of the seat body (1), the output shaft of the driving motor (13) is directly connected to a transmission shaft (14), a bevel gear (15) is mounted on the transmission shaft (14), the upper and lower ends of the bevel gear (15) are respectively meshed with a bevel gear (16) and a bevel gear (17), the bevel gear (16) is connected to the transmission shaft (6), the bevel gear (17) is connected to the transmission shaft (18), a first gear (19) is fixedly mounted on the transmission shaft (18), the first gear (19) is meshed with an idler gear (20), the idler gear (20) is meshed with a second gear (21), the second gear (21) is fixedly mounted on a transmission shaft (22), the first gear (19), the idler gear (20) and the second gear (21) are mounted in a second mounting cavity (1202); The second gear (21) is used to drive the sealing device, and the second transmission shaft (6) is used to drive the conveying device to convey.

5. A method for installing electric preheating of urban central heating pipelines according to claim 4, characterized in that: A third installation cavity (1203) is arranged on the seat body (1) above the first installation cavity (1201), and a sealing device is installed in the third installation cavity (1203), the sealing device comprising: a push-pull rod 2 (11), a transmission shaft 4 (22), a convex wheel (23), a push plate (24), a return spring (25), and a push-pull rod 1 (26); A convex wheel (23) is installed at the upper end of the transmission shaft four (22), and the convex wheel (23) contacts the push plate (24). The push plate (24) is slidably installed in the slide groove (27). The left side of the push plate (24) and the third installation cavity (1203) are connected to two return springs (25). The right side of the push plate (24) is connected to the push-pull rod two (11), and the push-pull rod two (11) is connected to the baffle plate (29). The baffle plate (29) is installed at the bottom outlet of the storage bin (28). A storage bin (28) is arranged on the seat body (1) at the upper part of the third installation cavity (1203). The right side of the push plate (24) is connected to the push-pull rod one (26), and the push-pull rod one (26) is fixedly connected to the push block (10). The push block (10) is located in the horizontal section of the backfill channel (9) directly below the baffle plate (29), and a conveying device is arranged below the backfill channel (9).

6. A method for installing electric preheating of urban central heating pipelines according to claim 5, characterized in that: The conveying device comprises: a bevel gear four (5), the transmission shaft two (6) is connected to the bevel gear four (5), the bevel gear four (5) and the bevel gear five (4) are meshed with each other, the driving pulley of the conveyor belt (8) is fixedly connected to the bevel gear five (4), and the output end of the conveyor belt (8) is provided with a backfill soil outlet (7).