House building project quantity and price integrated management system
By combining the PM system and the BIM5D system, the refined management of the quantity and price of the housing construction project is achieved, and the problems of unclear planning logic and difficult construction organization in the existing technology are solved, and the automatic project volume, output value, and material consumption is achieved. Computing and management.
Patent Information
- Application Number
- CN202411059917.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2024-11-29
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing PM system has fewer functions in the housing construction project module, which cannot achieve refined management of the quantity and price of the housing construction project. Moreover, the filling methods of the project quantity are diverse and cannot be combined with the progress plan, resulting in poor management.
A integrated management system for building construction projects was designed, combining PM system and BIM5D system, and by designing progress planning modules, scenario modules, construction progress collection modules, material consumption collection modules, etc., the correlation between progress planning and model is realized, and automatic extraction is performed. Project quantity and material demand form an integrated management plan for quantity and price.
It solves the problems of unclear planning logic, difficulty in organizing flow construction, and time-consuming and labor-intensive adjustment of plan changes, realizes automatic calculation of project volume, output value, and material consumption, and improves the refinement and efficiency of progress management.
Smart Images

Figure CN119047744A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction engineering, and in particular to a building construction engineering quantity-price integrated management system. Background Art
[0002] The PM system is a comprehensive management tool that aims to efficiently manage and control projects through a systematic approach. It covers the entire process from project initiation to project completion, including project planning, organization, guidance and control. The application of the PM system is not limited to engineering project management, but also includes software project management, resource management and other fields. By applying different management strategies and techniques, it ensures that the project can be completed on time, on budget and according to quality requirements.
[0003] At present, there are few functions in the PM system for the building construction project module, and the project quantity is reported in a variety of ways. In the process of managing the owner and subcontracting team, the process project quantity is extracted offline through the model, so as to realize the extraction and inspection and pricing of the settlement project quantity (construction, structure, electromechanical, etc.) of Party A and subcontracting, and provide data support for project settlement. The model is not combined with the schedule plan and related functional modules (materials, costs) in the PM system, and refined management cannot be carried out. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a building construction project quantity and price integrated management system, which can realize the refined management of building construction project quantity and price.
[0005] In order to solve the above technical problems, the technical solutions adopted by the present invention are as follows.
[0006] A building construction project quantity and price integrated management system, comprising a PM system and a BIM5D system and a mobile terminal that are communicatively connected to the PM system;
[0007] The BIM5D system includes a design schedule module for preparing a construction schedule and a scenario module connected to the design schedule module for building a scenario model according to the construction schedule;
[0008] The mobile terminal includes a construction progress collection module for reporting the actual construction progress on site and a material consumption collection module for reporting the actual consumption of materials on site;
[0009] The PM system includes a construction simulation module connected to the design schedule planning module and the construction progress acquisition module to realize the simulation of planned construction and actual construction, and an image progress display module connected to the construction simulation module to display the planned construction and actual construction simultaneously through a 3D display interface;
[0010] The PM system also includes a material requirement generation module connected to the scenario module to extract the structural engineering quantity, a material display module connected to the material requirement generation module and the material consumption collection module respectively to compare and display the required materials and consumed materials, a pricing file storage module for receiving imported pricing files, and an output value calculation and display module connected to the pricing file storage module and the material display module respectively to perform planned investment and actual investment calculation and comparative display.
[0011] Preferably, the PM system and the BIM5D system are respectively provided with a project ID mapping module for mapping project IDs to achieve association.
[0012] Preferably, the output end of the image progress display module is connected to the input end of the design progress planning module, and the design progress planning module adjusts the design construction progress plan according to the deviation between the actual construction displayed by the image progress display module and the planned construction.
[0013] Preferably, the mobile terminal further comprises a task display module connected to the output end of the design schedule module and used for displaying tasks.
[0014] Preferably, the design schedule module uses the Zebra schedule to prepare the construction schedule.
[0015] Preferably, the scenario module divides the engineering quantities from multiple dimensions, and the material requirement generation module extracts the structural engineering quantities from different dimensions as needed.
[0016] Due to the adoption of the above technical scheme, the technical progress achieved by the present invention is as follows.
[0017] The present invention solves the progress management problems such as unclear plan preparation logic, difficulty in organizing flow construction, and time-consuming and labor-intensive secondary adjustments of plan changes. By referring to the multi-graph linkage and logical interconnection functions of the zebra progress, it assists the initial planning of the project and the dynamic management during the process.
[0018] The present invention uses the BIM5D system to automatically connect the list, automatically extract the engineering quantity, and associate the progress plan with the model. The PM reads the data and logical relationship, and realizes the integrated quantity and price solution of automatically calculating the engineering quantity, output value, and material consumption through progress reporting. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a principle block diagram of the present invention;
[0020] Figure 2 It is a data docking principle diagram of the present invention;
[0021] Figure 3 A mind map for the present invention;
[0022] Figure 4 It is a schematic diagram of the collision between the schedule plan and the model of the present invention. DETAILED DESCRIPTION
[0023] The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0024] A housing construction project quantity and price integrated management system, combined with Figures 1 to 3 As shown, it includes PM system, BIM5D system and mobile terminal, among which PM system communicates and connects with BIM5D system and mobile terminal respectively; BIM5D system is also connected with mobile terminal. The system takes PM system as the main management system, and BIM5D system takes advantage of its own multi-model scenario visualization, schedule plan combination, quantity and price integration, and pushes relevant data to PM system to serve PM economic cost accounting; BIM5D is insufficient in the refined management of housing engineering companies, and corresponding design is carried out in PM system; both systems fulfill their responsibilities and count from one source. Mobile terminal is convenient for staff to carry, so that staff can check tasks and fill in information.
[0025] The BIM5D system includes a design schedule module and a scenario module, wherein the design schedule module is used to prepare a construction schedule; the scenario module is connected to the design schedule module, and the scenario module is used to build a scenario model according to the construction schedule, and the scenario module divides the engineering quantity from multiple dimensions, including the overall engineering quantity dimension, the construction flow section dimension, the time interval dimension, the construction plan dimension, the list dimension, the single component dimension and the measure dimension.
[0026] The mobile terminal includes a task display module, a construction progress collection module and a material consumption collection module, wherein the task display module is connected to the output end of the design schedule module, the task display module is used to display tasks; the construction progress collection module is used to report the actual construction progress on site; the material consumption collection module is used to report the actual consumption of materials on site.
[0027] The PM system includes a construction simulation module, a visual progress display module, a material demand generation module, a material display module, a pricing file storage module and an output value calculation and display module.
[0028] The construction simulation module is connected to the design schedule module and the construction progress acquisition module respectively, to extract the planned construction progress from the design schedule module and the actual construction progress from the construction progress acquisition module, and simulate the planned construction and actual construction. The visual progress display module is connected to the output end of the construction simulation module. The visual progress display module is used to display the planned construction and the actual construction at the same time through a 3D display interface, to realize the association and collision between the schedule plan and the model, to form a comparison between the planned schedule model and the actual time model, and then to visually display the deviation between the actual construction and the progress construction, to assist the material entry and inspection of the adjacent process, such as Figure 4 The output end of the image progress display module is also connected to the input end of the design progress plan module, and the design progress plan module adjusts the design construction progress plan according to the deviation between the actual construction and the planned construction displayed by the image progress display module.
[0029] The material demand generation module is connected to the scenario module to extract the structural engineering quantity on demand. Specifically, it can be extracted according to different dimensions, including overall engineering quantity, quantity extracted by construction flow section, quantity extracted by time interval, quantity extracted by construction plan, quantity extracted by list, quantity extracted by single component and quantity extracted by measure type. The material display module is connected to the material demand generation module and the material consumption collection module respectively, so as to compare and display the required materials and consumable materials. The pricing file storage module is used to receive the imported pricing files. The output value calculation and display module is connected to the pricing file storage module and the material display module respectively. The output value calculation and display module is used to calculate and compare the planned investment and actual investment.
[0030] The user accounts of the PM system and the BIM5D system are connected to ensure the unification of the user accounts of the two systems; single sign-on ensures seamless access to the two systems. The PM system and the BIM5D system are also equipped with project ID mapping modules, which are used to map project IDs, thereby realizing the association of projects in the PM system and the BIM5D system. System linkage startup - web page, client, web page jump and web page linkage, wake up the client.
[0031] Embodiment 1
[0032] Progress management (initial planning, process dynamics)
[0033] (1) Progress control requirements
[0034] The main problems at present are that the planning logic is unclear and incomplete, and the secondary adjustment of plan changes is time-consuming and laborious. Through the linkage of progress plan with Zebra network plan and Project data, the platform model is associated with the plan to carry out construction simulation, compare the planned progress model with the actual time model, and vividly display the progress deviation, to assist in the material entry and inspection plan of adjacent processes.
[0035] (2) Progress Solution
[0036] The design schedule module uses the Zebra schedule to carry out plan preparation, plan (initial planning, process dynamics) control, resource management, etc. Through the application functions such as overall plan, forward line, period plan, comparison, change analysis, etc., through time-scale network diagram (double-code network diagram), bar chart, logical network diagram (emphasizing the logical relationship between tasks), single-code network diagram), multi-diagram linkage, it assists in project planning and dynamic management during the construction process, and lays the foundation for subsequent collision detection.
[0037] Embodiment 2
[0038] Engineering quantity management
[0039] (1) Project Quantity - Material - Output Value Demand
[0040] 1) Engineering quantity requirements
[0041] This system realizes the functions of quantity management (upward progress, monthly actual completion, downward inspection, etc.) by accurately extracting the quantity of structural engineering works in multiple dimensions. The quantity of engineering works is the core and foundation of various businesses.
[0042] 2) Material requirements
[0043] According to the needs, the project quantity is extracted according to different dimensions such as on-site construction flow sections, construction components, and progress plans, and the construction plan is attached to generate the overall material plan, stage supply plan, and material supply curve, plan material procurement, and limit the material collection; generate the expected consumption of various structural materials, compare the actual consumption, and perform material savings and over-consumption analysis to provide a basis for project cost control.
[0044] 3) Output demand
[0045] Complete the budget work, generate the overall output value of the project (the output value determined by fees, taxes or owner's unit price approval is adjusted in the PM system), and realize the statistical output value by structure, construction flow section, schedule or any time interval to determine the income.
[0046] (2) Engineering quantity, list, materials, progress, quantity and price integrated solution
[0047] The BIM5D system is used to automatically connect lists, extract component quantities, and associate schedules with models to assist on-site technical management.
[0048] The PM system reads data and logic, associates with the team, and through progress reporting, forms functions such as automatic calculation of project quantity, output value, and material consumption to serve PM's economic accounting.
[0049] Embodiment 3
[0050] BIM Technology Application
[0051] (1) Quality management
[0052] 1) Visual display, simulating the construction of complex structures or working conditions, avoiding conflicts, and assisting in formulating reasonable construction plans;
[0053] 2) Various collision reports.
[0054] (2) Planning combined with construction scheduling management
[0055] Combined with the progress plan, it can be used for visual construction simulation, plan the peak usage of personnel and machinery, and assist in determining the time nodes for the intervention and withdrawal of personnel and equipment in each process to avoid idle machinery or idle personnel; it can also assist in planning to improve the utilization rate of turnover materials and assist in on-site flow construction.
[0056] (3) Other applications such as safety, quality, and technical management
[0057] BIM integration and model association will further improve the application level of daily safety, quality and technical management such as drawings, changes, plans, briefings, inspections and tests.
[0058] The present invention integrates user system, project mapping, and building construction engineering structure undertaking, and realizes the functions of web page jump and linkage, awakening the client and connecting with the system data system.
[0059] The present invention solves the progress management problems such as unclear plan preparation logic, difficulty in organizing flow construction, and time-consuming and labor-intensive secondary adjustments of plan changes. By referring to the multi-graph linkage and logical interconnection functions of the zebra progress, it assists the initial planning of the project and the dynamic management during the process.
[0060] The present invention uses the BIM5D system to automatically connect the list, automatically extract the engineering quantity, and associate the progress plan with the model. The PM reads the data and logical relationship, and realizes the integrated quantity and price solution of automatically calculating the engineering quantity, output value, and material consumption through progress reporting.
Claims
1. A building construction project quantity and price integrated management system, including a PM system, Features: It also includes a BIM5D system and a mobile terminal that communicate with the PM system; The BIM5D system includes a design schedule module for preparing a construction schedule and a scenario module connected to the design schedule module for building a scenario model according to the construction schedule; The mobile terminal includes a construction progress collection module for reporting the actual construction progress on site and a material consumption collection module for reporting the actual consumption of materials on site; The PM system includes a construction simulation module connected to the design schedule planning module and the construction progress acquisition module to realize the simulation of planned construction and actual construction, and an image progress display module connected to the construction simulation module to display the planned construction and actual construction simultaneously through a 3D display interface; The PM system also includes a material requirement generation module connected to the scenario module to extract the structural engineering quantity, a material display module connected to the material requirement generation module and the material consumption collection module respectively to compare and display the required materials and consumed materials, a pricing file storage module for receiving imported pricing files, and an output value calculation and display module connected to the pricing file storage module and the material display module respectively to perform planned investment and actual investment calculation and comparative display.
2. A building construction project quantity and price integrated management system according to claim 1, Features: The PM system and the BIM5D system are respectively provided with a project ID mapping module for mapping project IDs to achieve association.
3. A building construction project quantity and price integrated management system according to claim 1, Features: The output end of the image progress display module is connected to the input end of the design progress plan module, and the design progress plan module adjusts the design construction progress plan according to the deviation between the actual construction displayed by the image progress display module and the planned construction.
4. A building construction project quantity and price integrated management system according to claim 1, Features: The mobile terminal also includes a task display module connected to the output end of the design schedule module and used for displaying tasks.
5. A building construction project quantity and price integrated management system according to claim 1, Features: The design schedule module uses the Zebra schedule to prepare the construction schedule.
6. A building construction project quantity and price integrated management system according to claim 1, Features: The scenario module divides the engineering quantity from multiple dimensions, and the material demand generation module extracts the structural engineering quantity from different dimensions as needed.
Citation Information
Patent Citations
BIM5D-based project construction fine management method
CN110991882A
BIM technology-based construction engineering EPC cost and progress management system and management method
CN111275297A
Tunnel management platform taking construction organization as core
CN115456814A
Intelligent engineering management system and method based on GIS
CN115660567A
Project full life cycle monitoring management system
CN117689346A