Pipe network construction risk assessment method and system
Through real-time monitoring and risk assessment systems, the geological, environmental and human risk sources in pipeline construction are identified and controlled, and the risks and delay problems caused by various factors in construction are solved, and the construction safety and success rate are improved.
Patent Information
- Application Number
- CN202411225701.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-03
- Publication Date
- 2024-11-29
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the construction of the pipeline network, we face risks and delays caused by unfavorable geological conditions, underground pipeline conflicts, design errors, and other environmental and human factors, which will affect the safety and stability of the construction. The construction needs to be evaluated to avoid these risks.
Provide a pipeline construction risk assessment method and system to identify risk sources through real-time monitoring, determine risk factors, analyze and evaluate risk factors, and formulate risk strategies, including monitoring of geological, environmental and human risk sources, database association, and risk assessment models. and the formulation of control strategies.
Through real-time monitoring and identification of risk sources and formulation of control strategies, we can effectively identify and control potential risks, and improve project safety and the possibility of successful construction.
Smart Images

Figure CN119047835A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of pipeline network construction, and in particular relates to a pipeline network construction risk assessment method and system. Background Art
[0002] Pipeline network construction refers to the process of building, installing and maintaining various pipeline networks underground or above ground. These pipeline networks can be used to transport various media, such as water, natural gas, oil, chemicals, sewage, etc., to meet the needs of industrial, civil, agricultural and environmental protection fields. Pipeline network construction is a complex process that requires rigorous planning and construction to ensure the safety and efficient operation of the pipeline system. However, in actual operations, pipeline network construction faces various problems and risks, such as: unfavorable geological conditions leading to increased construction difficulty and risk, underground pipeline conflicts leading to increased construction risks and delays, design errors or construction defects affecting the safety and stability of the pipeline network, and other risks caused by environmental factors and / or human factors. Therefore, it is urgent to conduct risk assessment of pipeline network construction in order to avoid and eliminate the above-mentioned risks and influencing factors. Summary of the invention
[0003] The purpose of the present invention is to provide a pipeline network construction risk assessment method and system, which can be achieved through the following technical solutions: In a first aspect, an embodiment of the present application provides a pipeline network construction risk assessment method, comprising the following steps: Conduct real-time monitoring of pipeline construction areas and identify risk sources; determining risk factors based on the risk sources; Analyze and evaluate the risk factors; Develop risk strategies and implement controls on said risk factors; Among them, the risk sources include geological risk sources, environmental risk sources and man-made risk sources.
[0004] Preferably, the pipeline network construction area includes an above-ground area and an underground area, and the above-ground area is monitored for risks using a first monitoring method, and the underground area is monitored for risks using a second monitoring method.
[0005] Preferably, the identifying risk source specifically includes the following steps: Obtain monitoring information within the pipeline construction area; Analyze the monitoring information and classify it according to the monitoring content, and determine the monitoring area and monitoring method; Identify risk sources based on monitoring areas and monitoring methods.
[0006] Preferably, the risk factors in the geological risk sources include: geological structure, topography, groundwater, geological material characteristics, underground cavities, geological disaster history, geological environmental changes and underground pipelines; the risk factors in the environmental risk sources include: soil pollution, water pollution, ecological environment destruction, climate change and waste disposal; the risk factors in the man-made risk sources include: human operating errors, equipment failures, engineering design problems, poor construction management, poor construction supervision, man-made damage and equipment and device management problems.
[0007] Preferably, determining the risk factors specifically comprises the following steps: Establishing a risk database based on the risk sources; Correspondingly associating the risk source with the risk factor in the risk database; Using hash index and / or B+ tree index to search and determine risk factors in the risk database; Marking the found risk factors; A risk factor dataset is formed based on the markers.
[0008] Preferably, risk analysis and assessment is performed based on the risk factor data set, specifically comprising the following steps: performing data processing on the data in the risk factor data set; obtaining auxiliary data related to the risk factors; Assessing the harmfulness of the risk factor based on the auxiliary data and determining its risk level; Among them, the danger levels include level one risk, level two risk, level three risk and level four risk in descending order according to the degree of harm.
[0009] Preferably, the harmfulness of the risk factors is assessed by establishing a risk assessment model; the risk assessment model comprises a feature coding layer, a comprehensive risk assessment layer and a plurality of single risk assessment layers; wherein each single risk assessment layer in the plurality of single risk assessment layers corresponds to a risk factor in each risk source; Establishing the risk assessment model specifically includes the following steps: Acquire a number of monitoring samples, each monitoring sample including a regional feature of a monitoring area and a risk label; wherein the risk label is used to indicate a total risk score of the monitoring area and a plurality of individual risk scores corresponding to the risk source; Based on the regional characteristics of each monitoring sample in the plurality of monitoring samples and the total risk score in the risk label of each monitoring sample, the feature coding layer is trained to obtain a trained feature coding layer; wherein the trained feature coding layer includes a plurality of decision trees, wherein each non-leaf node of each decision tree corresponds to a regional feature; Based on the trained feature coding layer, obtain the feature coding results of each monitoring sample; The feature coding result of any first monitoring sample is determined based on the normalized processing result of the regional features corresponding to each node covered by the path between the leaf node and the root node of each decision tree; Training the comprehensive risk assessment layer based on the feature coding results of each monitoring sample and the total risk score in the risk label of each monitoring sample; For each single risk assessment layer in each single risk assessment layer, based on the feature coding results of each monitoring sample and the individual risk score corresponding to the risk type of the single risk assessment layer in the risk label of each monitoring sample, the single risk assessment layer is trained; The risk assessment model is established based on the trained feature coding layer, the comprehensive risk assessment layer and several single risk assessment layers.
[0010] Preferably, the risk factors are evaluated, specifically comprising the following steps: Obtain target features of the risk area to be assessed; Inputting the target feature into the feature coding layer of the risk assessment model to obtain a target feature coding result; Inputting the target feature coding results into the comprehensive risk assessment layer and each single risk assessment layer of the risk assessment model respectively; Obtaining the total risk score of the risk area to be assessed through the output of the comprehensive risk assessment layer; Through the output of each single risk assessment layer in each single risk assessment layer, a separate risk score of the risk factor of the risk area to be assessed corresponding to each single risk assessment layer is obtained.
[0011] Preferably, formulating the risk strategy specifically includes the following steps: sorting the total risk score and the individual risk score to obtain a first risk assessment score sequence and a second risk assessment score sequence; The first risk assessment score sequence and the second risk assessment score sequence are grouped, and the hazard degree and the proportion of high hazard levels of the risk factors in each group are calculated respectively; A risk strategy formulation model is constructed based on the preset risk control objectives, risk limit conditions between different groups, and the hazard control range threshold and high hazard level ratio threshold of risk factors in each group; The historical risk data information of the risk factors is obtained, the historical risk data information is input into the risk strategy formulation model, and the risk control strategies corresponding to different groups are output.
[0012] In a second aspect, an embodiment of the present application provides a pipeline network construction risk assessment system, which is applied to the pipeline network construction risk assessment method as described above, including a risk monitoring module, a risk identification module, a risk assessment module and a risk control module; The risk monitoring module is used to monitor the pipeline network construction area in real time; The risk identification module is used to identify risk sources and determine risk factors based on the risk sources; The risk assessment module is used to analyze and assess the risk factors; The risk control module is used to formulate risk strategies and control the risk factors; Among them, the risk sources include geological risk sources, environmental risk sources and man-made risk sources.
[0013] The beneficial effects of the present invention are: The present invention first monitors the pipeline construction area in real time and obtains the changes in the area in a timely manner; secondly, it identifies the areas / regions / locations where changes occur in the monitoring results, and identifies the risk sources therefrom, that is, identifying which category the source of the risk belongs to (specific categories include geological risk sources, environmental risk sources, and man-made risk sources); then, by analyzing and evaluating the risk factors, each type of risk source, each risk factor, and the risk level corresponding to each risk factor are determined, and then corresponding risk strategies are formulated according to the risk level to control the risk factors. The present invention identifies the risk sources by real-time monitoring of the construction area, and further generates and controls the risk control strategies by analyzing and evaluating the risk factors caused by the risk sources, effectively identifying, analyzing, and controlling potential risks, thereby improving the safety of the project and the possibility of successful completion of the construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] For better understanding and implementation, the technical solution of the present application is described in detail below with reference to the accompanying drawings.
[0015] Figure 1 A flow chart of the steps of a pipeline network construction risk assessment method provided in an embodiment of the present application; Figure 2 A flowchart of the steps for identifying risk sources provided in an embodiment of the present application; Figure 3 A flowchart of the steps for determining risk factors provided in an embodiment of the present application; Figure 4 A schematic diagram of the structure of a pipeline network construction risk assessment system provided in an embodiment of the present application. DETAILED DESCRIPTION
[0016] In order to further explain the technical means and effects taken by the present invention to achieve the predetermined invention purpose, exemplary embodiments will be described in detail here, and examples thereof are shown in the accompanying drawings. When the following description refers to the drawings, unless otherwise indicated, the same numbers in different drawings represent the same or similar elements. The implementations described in the following exemplary embodiments do not represent all implementations consistent with the present application. Instead, they are only examples of methods and systems consistent with some aspects of the present application as detailed in the attached claims.
[0017] The terms used in this application are only for the purpose of describing specific embodiments and are not intended to limit this application. The singular forms of "a", "said" and "the" used in this application and the appended claims are also intended to include plural forms unless the context clearly indicates other meanings. It should also be understood that the term "and / or" used in this article refers to any or all possible combinations of one or more associated listed items.
[0018] The specific implementation methods, features and effects of the present invention are described in detail below in conjunction with the accompanying drawings and preferred embodiments.
[0019] Example 1 See also Figure 1 The present application provides a pipeline network construction risk assessment method, comprising the following steps: Conduct real-time monitoring of pipeline construction areas and identify risk sources; determining risk factors based on the risk sources; Analyze and evaluate the risk factors; Develop risk strategies and implement controls on said risk factors; Among them, the risk sources include geological risk sources, environmental risk sources and man-made risk sources.
[0020] Specifically, since pipeline construction is subject to the influence of multiple factors such as geological environment and human factors in actual operation, in order to eliminate the influence of the above risks on pipeline construction, this application first monitors the pipeline construction area in real time and obtains the changes in the area in a timely manner; secondly, the areas / regions / locations where changes occur in the monitoring results are identified, and the risk sources are identified, that is: identifying which category the source of the risk belongs to (specific categories include geological risk sources, environmental risk sources and human risk sources); then, by analyzing and evaluating the risk factors, each type of risk source, each risk factor and the risk level corresponding to each risk factor are determined, and then corresponding risk strategies are formulated according to the risk level to control the risk factors. This application identifies the risk sources by real-time monitoring of the construction area, and further generates risk control strategies and controls by analyzing and evaluating the risk factors caused by the risk sources, effectively identifying, analyzing and controlling potential risks, thereby improving the safety of the project and the possibility of successful completion of the construction.
[0021] In an embodiment provided in the present application, the pipeline construction area includes an above-ground area and an underground area, and a first monitoring method is used to perform risk monitoring on the above-ground area, and a second monitoring method is used to perform risk monitoring on the underground area; wherein the first monitoring method includes but is not limited to camera-video monitoring, laser scanning and three-dimensional modeling, remote sensing technology, drone monitoring and manual patrol monitoring, etc.; the second monitoring method includes but is not limited to underground geological survey, underground radar (Ground Penetrating Radar, GPR), non-destructive testing, water level monitoring, pipeline detection, and underground vibration and noise monitoring, etc.
[0022] Specifically, since the above-ground and underground pipeline construction have different requirements for monitoring technology and monitoring content, this embodiment divides the pipeline construction area into an above-ground area and an underground area; and since the above-ground area and the underground area have different properties and construction environments, this embodiment adopts different monitoring technologies to perform real-time monitoring on the above-mentioned two areas, specifically: adopting a first monitoring method including camera-video monitoring, laser scanning and three-dimensional modeling, remote sensing technology, drone monitoring and manual patrol monitoring to monitor the above-ground area; adopting a second monitoring method including underground geological survey, underground radar (Ground Penetrating Radar, GPR), non-destructive testing, water level monitoring, pipeline detection and underground vibration and noise monitoring to monitor the underground area; this embodiment separates the above-ground area and the underground area and adopts different technologies for monitoring respectively, which can comprehensively monitor all aspects of the construction process, including construction progress, quality, safety, etc., to ensure that the construction is fully controllable, thereby ensuring the safety, efficiency and quality of the construction to the greatest extent, while reducing various risks in the construction process.
[0023] In an embodiment provided in the present application, the above-ground area and the underground area are divided separately and divided into several local areas according to the area type.
[0024] Specifically, the pipeline construction area is divided into the above-ground area and the underground area. On this basis, this embodiment further divides the above-ground area and the underground area according to the type of each area (such as the pipeline construction project that the area is specifically responsible for, and the nature and type of the construction project). The above two areas are further divided into multiple local areas, and different monitoring methods are adopted in each area according to regional characteristics; and the above-ground area / underground area is the overall area relative to several local areas; this embodiment reflects and sets the pipeline construction area through "overall" and "local", so as to more carefully monitor the risks and changes in the area, thereby ensuring the accuracy and timeliness of risk monitoring.
[0025] See also Figure 2 In one embodiment provided in the present application, the risk source identification specifically includes the following steps: Obtain monitoring information within the pipeline construction area; Analyze the monitoring information and classify it according to the monitoring content, and determine the monitoring area and monitoring method; Identify risk sources based on monitoring areas and monitoring methods.
[0026] Specifically, monitoring information is obtained by real-time monitoring of the pipeline construction area. The monitoring information includes the monitoring area and the monitoring method adopted for the monitoring area. Since the construction area is divided into the above-ground area and the underground area, the monitoring area is also different from the above-ground area and the underground area. Therefore, the means adopted in the corresponding monitoring area will also be different, and each monitoring method / means is aimed at different risk sources. It can be seen that as long as the monitoring area and the corresponding monitoring method are determined, it is possible to determine which type or type of risk source it is. For example: when the monitoring area is a certain area underground, geological survey and / or underground radar and / or water level monitoring technology are required, which means that the risks that can be generated in the monitoring area are related to geology and groundwater, so it can be determined that the risk source belongs to the geological risk source. If you want to determine whether there are other risk sources in the area, further analysis is needed, but it can be determined that the main risk in the area is related to geology and is a geological risk source.
[0027] In an embodiment provided in the present application, the risk factors in the geological risk sources include: geological structure, topography, groundwater, geological material characteristics, underground cavities, geological disaster history, geological environment changes and underground pipelines and other risk factors related to geological structure; the risk factors in the environmental risk sources include: soil pollution, water pollution, ecological environment destruction, climate change and waste disposal, etc.; the risk factors in the man-made risk sources include: human operating errors, equipment failures, engineering design problems, poor construction management, poor construction supervision, man-made damage and equipment and device management problems.
[0028] See also Figure 3 In one embodiment provided in the present application, determining the risk factor specifically includes the following steps: Establishing a risk database based on the risk sources; Correspondingly associating the risk source with the risk factor in the risk database; Using hash index and / or B+ tree index to search and determine risk factors in the risk database; Marking the found risk factors; A risk factor dataset is formed based on the markers.
[0029] Specifically, this embodiment establishes a risk database based on the risk source, which is used to collect all the data and factors related to the risk source into one database, which is convenient for subsequent comprehensive risk identification and assessment, and can prioritize risks, thereby facilitating the effective allocation of resources and the formulation of risk management decisions; then, in the established database, the risk source and the risk factor are associated with each other, specifically: each risk source corresponds to multiple risk factors, if the risk source is regarded as a "set", then the above-mentioned many risk factors are "subsets" of the "set", and each risk source is a separate "set" with different properties, and the association between the two can facilitate subsequent search and positioning; then, a hash index or a B+ tree index or a combination of a hash index and a B+ tree index is used to search and determine the risk factors in the above-mentioned risk database, specifically: after the risk source is identified through monitoring information, the risk source is searched in the above-mentioned risk database, and the risk factors corresponding to the risk source are located and determined, and the level of the risk factor and which risk factor plays an important or decisive role in the risk source are judged in combination with the specific situation; finally, all the found risk factors are marked and a risk factor data set is generated. It should be noted that this embodiment uses hash index and B+ tree index for search, and the hash index can be used to ensure the query speed, and the B+ tree index can be used to ensure the query range. Therefore, one of the two can be selected for search according to the specific situation, and if the two are combined, the query speed and the query range can be guaranteed, so as to be applicable to more query situations.
[0030] In an embodiment provided in the present application, risk analysis and assessment is performed based on the risk factor data set, specifically comprising the following steps: Performing data processing on the data in the risk factor data set, including data cleaning, data conversion and data integration; Acquire auxiliary data related to the risk factor; the auxiliary data can provide auxiliary evidence for the risk factor and can reflect the nature, characteristics and harmfulness of the risk factor; Assessing the harmfulness of the risk factor based on the auxiliary data and determining its risk level; Among them, the danger levels include level one risk, level two risk, level three risk and level four risk in descending order according to the degree of harm.
[0031] Specifically, this embodiment analyzes the above-mentioned risk factor data set, and first performs data processing before analysis, specifically: data cleaning: remove duplicate, invalid or erroneous data, and fill in missing values; data conversion: perform operations such as format conversion, normalization, and standardization on the data to make the data available for analysis; data integration: integrate the data in multiple data sources to form a complete data set; then obtain some auxiliary data related to the risk factors, for example: if the risk factor is a human operation error, then the corresponding auxiliary data includes an operation manual related to the operation, specific personnel arrangements, basic personnel information, personnel operation equipment, etc. These auxiliary data can reflect the specific circumstances and occurrence conditions of the human operation error from the side, and then determine whether the risk factor belongs to a more serious risk, whether it will cause significant losses, etc., so as to provide data support for subsequent decision-making; finally, this embodiment evaluates the degree of harm of the risk factor based on the above-mentioned auxiliary data and determines the risk level / danger level for it.
[0032] It should be noted that the above-mentioned danger levels are divided into level one risk, level two risk, level three risk and level four risk in descending order according to the degree of harm; among them, level one risk has the highest degree of harm, and level four risk has a relatively low degree of harm.
[0033] In an embodiment provided in the present application, the harmfulness of the risk factor is evaluated by establishing a risk assessment model; the risk assessment model includes a feature coding layer, a comprehensive risk assessment layer and a plurality of single risk assessment layers; wherein each single risk assessment layer in the plurality of single risk assessment layers corresponds to a risk factor in each risk source; Establishing the risk assessment model specifically includes the following steps: Acquire a number of monitoring samples, each monitoring sample including a regional feature of a monitoring area and a risk label; wherein the risk label is used to indicate a total risk score of the monitoring area and a plurality of individual risk scores corresponding to the risk source; Based on the regional characteristics of each monitoring sample in the plurality of monitoring samples and the total risk score in the risk label of each monitoring sample, the feature coding layer is trained to obtain a trained feature coding layer; wherein the trained feature coding layer includes a plurality of decision trees, wherein each non-leaf node of each decision tree corresponds to a regional feature; Based on the trained feature coding layer, obtain the feature coding results of each monitoring sample; The feature coding result of any first monitoring sample is determined based on the normalized processing result of the regional features corresponding to each node covered by the path between the leaf node and the root node of each decision tree; Training the comprehensive risk assessment layer based on the feature coding results of each monitoring sample and the total risk score in the risk label of each monitoring sample; For each single risk assessment layer in each single risk assessment layer, based on the feature coding results of each monitoring sample and the individual risk score corresponding to the risk type of the single risk assessment layer in the risk label of each monitoring sample, the single risk assessment layer is trained; The risk assessment model is established based on the trained feature coding layer, the comprehensive risk assessment layer and several single risk assessment layers.
[0034] Specifically, this embodiment establishes a risk assessment model in the above manner. On the one hand, it can realize the joint training of the task of assessing the comprehensive risk in the pipeline construction process and the task of assessing each single risk, which can reduce the cost and overhead of model training; secondly, the model obtained based on the training can simultaneously realize the assessment of the comprehensive risk of the monitoring area and the assessment of each single risk, thereby greatly improving the risk assessment efficiency of the monitoring area; on the other hand, this embodiment trains the risk assessment model and uses it to assess the harmfulness of the above-mentioned risk factors, so as to accurately obtain the harmfulness of each risk factor, which is convenient for the subsequent determination of the risk level according to the harmfulness and the formulation of corresponding risk strategies.
[0035] In an embodiment provided in the present application, the risk factors are evaluated, specifically comprising the following steps: Obtain target features of the risk area to be assessed; Inputting the target feature into the feature coding layer of the risk assessment model to obtain a target feature coding result; Inputting the target feature coding results into the comprehensive risk assessment layer and each single risk assessment layer of the risk assessment model respectively; Obtaining the total risk score of the risk area to be assessed through the output of the comprehensive risk assessment layer; Through the output of each single risk assessment layer in each single risk assessment layer, a separate risk score of the risk factor of the risk area to be assessed corresponding to each single risk assessment layer is obtained.
[0036] Specifically, this embodiment obtains the coding result by inputting the target features of the risk area to be assessed into the feature coding layer, and uses the coding result as the input of the comprehensive risk assessment layer and each single risk assessment layer, thereby obtaining the total risk score and the individual risk score respectively. By analyzing the total risk score, the risk situation of the corresponding pipeline construction area can be understood, and by analyzing the individual risk score, the risk situation in a specific "small area" within the corresponding construction area can be understood. From large to small ranges, the risks of the construction area are evaluated in all aspects, thereby providing accurate data support for the subsequent formulation of risk strategies and risk management.
[0037] In an embodiment provided in the present application, formulating the risk strategy specifically includes the following steps: sorting the total risk score and the individual risk score to obtain a first risk assessment score sequence and a second risk assessment score sequence; The first risk assessment score sequence and the second risk assessment score sequence are grouped, and the hazard degree and the proportion of high hazard levels of the risk factors in each group are calculated respectively; A risk strategy formulation model is constructed based on the preset risk control objectives, risk limit conditions between different groups, and the hazard control range threshold and high hazard level ratio threshold of risk factors in each group; The historical risk data information of the risk factors is obtained, the historical risk data information is input into the risk strategy formulation model, and the risk control strategies corresponding to different groups are output.
[0038] Specifically, for the formulation of risk strategies, this embodiment first obtains the above two score sequences by sorting, then calculates the degree of harm of risk factors in each group and the proportion of those with higher harm levels by grouping, and then builds a risk strategy formulation model based on multiple preset goals, constraints and control thresholds, and finally obtains historical risk data information of risk factors and inputs it into the model, and formulates corresponding risk control strategies according to the output of the model. This embodiment constructs a model with risk factors as features and outputs control strategies in the above manner, making the formulated risk control strategies more accurate and credible.
[0039] Example 2 See also Figure 4 , the embodiment of the present application provides a pipeline network construction risk assessment system, which is applied to the pipeline network construction risk assessment method as described above, including a risk monitoring module, a risk identification module, a risk assessment module and a risk control module; The risk monitoring module is used to monitor the pipeline network construction area in real time; The risk identification module is used to identify risk sources and determine risk factors based on the risk sources; The risk assessment module is used to analyze and assess the risk factors; The risk control module is used to formulate risk strategies and control the risk factors; Among them, the risk sources include geological risk sources, environmental risk sources and man-made risk sources.
[0040] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0041] The technicians in the relevant field can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example for illustration. In practical applications, the above-mentioned function allocation can be completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above. The functional units and modules in the embodiment can be integrated in a processing unit, or each unit can exist physically separately, or two or more units can be integrated in one unit. The above-mentioned integrated unit can be implemented in the form of hardware or in the form of software functional units. In addition, the specific names of the functional units and modules are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of this application. The specific working process of the units and modules in the above-mentioned system can refer to the corresponding process in the aforementioned method embodiment, which will not be repeated here.
[0042] Those skilled in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.
[0043] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention still fall within the scope of the technical solution of the present invention.
Claims
1. A pipeline network construction risk assessment method, characterized in that: The steps include: Conduct real-time monitoring of pipeline construction areas and identify risk sources; determining risk factors based on the risk sources; Analyze and evaluate the risk factors; Develop risk strategies and implement controls on said risk factors; Among them, the risk sources include geological risk sources, environmental risk sources and man-made risk sources.
2. A pipeline network construction risk assessment method according to claim 1, characterized in that: The pipeline network construction area includes an above-ground area and an underground area. The above-ground area is monitored for risks using a first monitoring method, and the underground area is monitored for risks using a second monitoring method.
3. A pipeline network construction risk assessment method according to claim 1, characterized in that: The identification of risk sources specifically includes the following steps: Obtain monitoring information within the pipeline network construction area; Analyze the monitoring information and classify it according to the monitoring content, and determine the monitoring area and monitoring method; Identify risk sources based on monitoring areas and monitoring methods.
4. A pipeline network construction risk assessment method according to claim 1, characterized in that: The risk factors of the geological risk sources include: geological structure, topography, groundwater, geological material characteristics, underground cavities, history of geological disasters, geological environmental changes and underground pipelines; the risk factors of the environmental risk sources include: soil pollution, water pollution, ecological environment destruction, climate change and waste disposal; the risk factors of the man-made risk sources include: human operating errors, equipment failures, engineering design problems, poor construction management, poor construction supervision, man-made damage and equipment and device management problems.
5. A pipeline network construction risk assessment method according to claim 1, characterized in that: Determining the risk factors specifically includes the following steps: Establishing a risk database based on the risk sources; Correspondingly associating the risk source with the risk factor in the risk database; Using hash index and / or B+ tree index to search and determine risk factors in the risk database; Marking the found risk factors; A risk factor dataset is formed based on the markers.
6. A pipeline network construction risk assessment method according to claim 5, characterized in that: Performing risk analysis and assessment based on the risk factor data set specifically includes the following steps: performing data processing on the data in the risk factor data set; obtaining auxiliary data related to the risk factors; Assessing the harmfulness of the risk factor based on the auxiliary data and determining its risk level; Among them, the danger levels include level one risk, level two risk, level three risk and level four risk in descending order according to the degree of harm.
7. A pipeline network construction risk assessment method according to claim 1, characterized in that: The harmfulness of the risk factors is evaluated by establishing a risk assessment model; the risk assessment model includes a feature coding layer, a comprehensive risk assessment layer and a plurality of single risk assessment layers; wherein each single risk assessment layer in the plurality of single risk assessment layers corresponds to a risk factor in each risk source; Establishing the risk assessment model specifically includes the following steps: Acquire a number of monitoring samples, each monitoring sample including a regional feature of a monitoring area and a risk label; wherein the risk label is used to indicate a total risk score of the monitoring area and a plurality of individual risk scores corresponding to the risk source; Based on the regional characteristics of each monitoring sample in the plurality of monitoring samples and the total risk score in the risk label of each monitoring sample, the feature coding layer is trained to obtain a trained feature coding layer; wherein the trained feature coding layer includes a plurality of decision trees, wherein each non-leaf node of each decision tree corresponds to a regional feature; Based on the trained feature coding layer, obtain the feature coding results of each monitoring sample; The feature encoding result of any first monitoring sample is determined based on the normalized processing result of the regional features corresponding to each node covered by the path between the leaf node and the root node of each decision tree; Based on the feature coding results of each monitoring sample and the total risk score in the risk label of each monitoring sample, the comprehensive risk assessment layer is trained; For each single risk assessment layer in each single risk assessment layer, based on the feature coding results of each monitoring sample and the individual risk score corresponding to the risk type of the single risk assessment layer in the risk label of each monitoring sample, the single risk assessment layer is trained; The risk assessment model is established based on the trained feature coding layer, the comprehensive risk assessment layer and several single risk assessment layers.
8. A pipeline network construction risk assessment method according to claim 7, characterized in that: The risk factors are evaluated, specifically including the following steps: Obtain target features of the risk area to be assessed; Inputting the target feature into the feature coding layer of the risk assessment model to obtain a target feature coding result; Inputting the target feature coding results into the comprehensive risk assessment layer and each single risk assessment layer of the risk assessment model respectively; Obtaining the total risk score of the risk area to be assessed through the output of the comprehensive risk assessment layer; Through the output of each single risk assessment layer in each single risk assessment layer, a separate risk score of the risk factor of the risk area to be assessed corresponding to each single risk assessment layer is obtained.
9. A pipeline network construction risk assessment method according to claim 8, characterized in that: Formulating the risk strategy specifically includes the following steps: sorting the total risk score and the individual risk score to obtain a first risk assessment score sequence and a second risk assessment score sequence; The first risk assessment score sequence and the second risk assessment score sequence are grouped, and the hazard degree and the proportion of high hazard levels of the risk factors in each group are calculated respectively; A risk strategy formulation model is constructed based on the preset risk control objectives, risk limit conditions between different groups, and the hazard control range threshold and high hazard level ratio threshold of risk factors in each group; The historical risk data information of the risk factors is obtained, the historical risk data information is input into the risk strategy formulation model, and the risk control strategies corresponding to different groups are output.
10. A pipeline network construction risk assessment system, applied to the pipeline network construction risk assessment method according to any one of claims 1 to 9, characterized in that: It includes risk monitoring module, risk identification module, risk assessment module and risk control module; The risk monitoring module is used to monitor the pipeline network construction area in real time; The risk identification module is used to identify risk sources and determine risk factors based on the risk sources; The risk assessment module is used to analyze and assess the risk factors; The risk control module is used to formulate risk strategies and control the risk factors; Among them, the risk sources include geological risk sources, environmental risk sources and man-made risk sources.