Tubular pile sinking construction method, device and equipment for offshore mudflat photovoltaic project and medium
Through the method of accurate measurement, real-time positioning and accuracy correction in offshore tidal flat photovoltaic projects, the problem of low positioning accuracy of traditional pile drivers is solved, the pile sinking accuracy and construction stability are improved, and the long-term operation and economic benefits of photovoltaic projects are ensured. .
Patent Information
- Application Number
- CN202411143859.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-20
- Publication Date
- 2024-11-29
AI Technical Summary
In offshore tidal flat photovoltaic projects, the positioning accuracy of traditional pile drivers is low and there is a lack of real-time and accurate monitoring of the entire construction process of pipe piles, resulting in a large deviation in the accuracy of pile sinking, affecting the subsequent installation and construction of brackets and components.
By accurately measuring the coordinate values of pipe piles before construction, positioning and correcting deviations in real time during construction, re-testing and correction of accuracy parameters after construction, and using Beidou positioning equipment, positioning correction modules and shore total stations to achieve all-round and multi-stage accuracy control.
It significantly improves the accuracy of pile sinking, reduces rework, ensures the accurate position of pipe piles, and improves the stability and economic benefits of subsequent structural installation.
Smart Images

Figure CN119048008A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of pipe pile foundation construction, and in particular to a pipe pile sinking construction method, device, equipment and medium for an offshore tidal flat photovoltaic project. Background Art
[0002] Offshore tidal flat photovoltaic projects are resource-intensive projects, which usually use pile foundations (PHC pipe piles, steel pipe piles). There are a large number of pipe piles, brackets, components and other structures or components on the site. In large-scale projects, the number of pipe pile foundations can reach tens of thousands.
[0003] In offshore tidal flat photovoltaic projects, the pile sinking accuracy of the pipe pile foundation is crucial, which is directly related to the installation and stability of the upper photovoltaic brackets, components and other structures. At present, the pile foundation construction of photovoltaic projects in nearshore shallow waters mainly adopts vibrating pile drivers modified from amphibious excavators and pile drivers modified from small floating box platforms used in inland waters. Among them, small pile drivers are more widely used due to their high operating efficiency and flexible mobility, but due to their simple structure, light weight, high center of gravity, poor wind and wave resistance, and mainly use single equipment such as GPS or total station for pile foundation positioning control, the positioning and pile driving accuracy is low, and there is a lack of real-time and accurate monitoring of the entire construction process of pipe piles (before, during and after construction). The pile sinking accuracy often has a large deviation from the design value, and there is a lot of subsequent rework, which has a great impact on the subsequent installation and construction of brackets and components. Therefore, how to improve the accuracy of pile foundation construction is the difficulty and pain point of current offshore tidal flat photovoltaic projects. Summary of the invention
[0004] In view of this, the present invention provides a method, device, equipment and medium for pipe pile driving construction in an offshore tidal flat photovoltaic project, so as to solve the problems of low positioning accuracy of traditional pile drivers and lack of real-time and accurate monitoring of the entire pipe pile construction process, resulting in large deviations in pile driving accuracy.
[0005] In a first aspect, the present invention provides a method for pipe pile sinking construction of an offshore tidal flat photovoltaic project, which is applied to a pile driver, and the method comprises:
[0006] Determine the coordinate values of all pipe piles in the photovoltaic area to be constructed based on the coordinates of the preset characteristic points of the photovoltaic area to be constructed;
[0007] Based on the coordinate value of the pipe pile, the corresponding pile position of each pipe pile is located in real time to obtain the positioning points of the corresponding pile positions of all pipe piles;
[0008] The pile position is adjusted and verified based on the preset accuracy threshold and each positioning point, so that the pile driver sinks the pipe pile according to the adjusted and verified position;
[0009] When the pile sinking of all the positioning points is completed, the pile construction accuracy parameters of each pile are re-measured to obtain the re-measurement results;
[0010] The retest result is compared with the preset accuracy threshold to obtain the comparison deviation;
[0011] The pile construction accuracy parameters are corrected based on the comparison deviation.
[0012] The pipe pile driving construction method for offshore tidal flat photovoltaic projects provided by the present invention can effectively cope with complex offshore construction working environments such as tidal changes and wind and wave impacts of offshore tidal flat projects through an all-round and multi-stage precision control method such as accurate measurement of all pipe pile coordinate values before construction, real-time positioning and correction during construction, and re-measurement of pipe pile construction precision parameters after construction and correction and adjustment. It significantly improves the accuracy of pile driving and solves the problem of large deviations in pile driving accuracy caused by lack of real-time and accurate monitoring of the entire pipe pile construction process.
[0013] In an optional implementation, determining the coordinate values of all pipe piles in the photovoltaic area to be constructed based on the coordinates of preset feature points in the photovoltaic area to be constructed includes:
[0014] Determine the coordinate value of the first pipe pile based on the coordinates of the preset characteristic points of the photovoltaic area to be constructed;
[0015] The coordinate values of the remaining pipe piles except the coordinate value of the first pipe pile in the photovoltaic area to be constructed are determined based on the coordinate value of the first pipe pile, a preset transverse pile spacing threshold, and a preset longitudinal pile spacing threshold.
[0016] The method for pipe pile sinking construction of an offshore tidal flat photovoltaic project provided by the present invention first determines the coordinate value of the first pipe pile based on the coordinates of preset feature points in the photovoltaic area to be constructed, and determines the coordinate values of the remaining pipe piles in the photovoltaic area to be constructed except the coordinate value of the first pipe pile based on the coordinate value of the first pipe pile, a preset transverse pile spacing threshold, and a preset longitudinal pile spacing threshold. By conducting on-site investigation and measurement before construction, the purpose of obtaining the coordinate values of all pipe piles in the photovoltaic area to be constructed is achieved, providing a basis for subsequent positioning of the corresponding pile positions of the pipe piles.
[0017] In an optional implementation, the pile driver includes a Beidou positioning device, and real-time positioning is performed on the pile position corresponding to each pipe pile based on the pipe pile coordinate value, and the positioning points corresponding to the pile positions of all pipe piles are obtained, including:
[0018] Beidou positioning equipment is used to locate the coordinate value of the first pipe pile in real time to obtain the first pipe pile positioning point;
[0019] Beidou positioning equipment is used to perform positioning based on the positioning point of the first pipe pile and the corresponding pile positions of the coordinate values of the remaining pipe piles except the first pipe pile, so as to obtain the positioning points of the corresponding pile positions of the remaining pipe piles; the positioning point of the first pipe pile and the positioning points of the corresponding pile positions of the remaining pipe piles constitute the positioning points of the corresponding pile positions of all pipe piles.
[0020] The pipe pile sinking construction method for an offshore tidal flat photovoltaic project provided by the present invention uses a Beidou positioning device to perform real-time positioning of the pile position corresponding to the coordinate value of the first pipe pile to obtain the positioning point of the first pipe pile, and performs positioning based on the first pipe pile positioning point and the corresponding pile positions of the coordinate values of the remaining pipe piles except the first pipe pile to obtain the positioning points of the corresponding pile positions of the remaining pipe piles, thereby achieving the purpose of accurately positioning the corresponding pile positions of all pipe piles.
[0021] In an optional embodiment, the pile driver further includes a positioning correction module and a handheld positioning device, and the pile position is adjusted and verified based on a preset accuracy threshold and each positioning point, so that the pile driver sinks the pipe pile according to the adjusted and verified position, including:
[0022] Aim the pile driver at the first pile positioning point;
[0023] Compare the preset accuracy threshold and the first pipe pile positioning point to see if they are consistent. If not, use the positioning correction module to adjust the pile position corresponding to the first pipe pile until they are consistent.
[0024] Use the pile driver to sink the first pipe pile according to the adjusted position;
[0025] Before reaching the designed elevation of pile driving, the pile position is rechecked based on the preset accuracy threshold using the positioning correction module and the handheld locator. If the recheck is inconsistent, the pile position is adjusted again until it is consistent.
[0026] The pile driver continues to sink the first pipe pile according to the verified and adjusted pile position until the sinking of the first pipe pile is completed;
[0027] After the first pipe pile is sunk, continue to sunk the pipe piles at the remaining positioning points until all the pipe piles are sunk.
[0028] The method for pipe pile driving construction of offshore tidal flat photovoltaic projects provided by the present invention uses a positioning correction module and a handheld positioning instrument to carry out real-time positioning and monitoring of the pile position during construction, collects data and performs analysis, corrects construction positioning deviations in a timely manner, achieves precise positioning, and indirectly improves the accuracy of pile driving.
[0029] In an optional embodiment, the pile driver further includes an onshore total station, and the pipe pile construction accuracy parameters include pile position, pile body verticality and pile sinking elevation;
[0030] The pile construction accuracy parameters of each pile are retested, and the retest results include:
[0031] The onshore total station is used to re-measure the pile position, pile body verticality and pile elevation of each pipe pile, and the re-measurement results of pile position data, pile body verticality data and pile elevation data are obtained.
[0032] In an optional implementation, the preset accuracy threshold includes a pile position threshold, a pile body verticality threshold, and a design elevation;
[0033] Compare the retest results with the preset accuracy threshold, and obtain the comparison deviation including:
[0034] Compare the pile position data with the pile position threshold to obtain a position comparison deviation;
[0035] Compare the pile body verticality data with the pile body verticality threshold to obtain the verticality comparison deviation;
[0036] Compare the pile driving elevation data with the design elevation to obtain the elevation comparison deviation.
[0037] The method for pipe pile driving construction of offshore tidal flat photovoltaic projects provided by the present invention promptly carries out re-measurement after construction, and adopts a shore total station to re-measure the pile position, pile body verticality and pile driving elevation of each pipe pile, so as to obtain the re-measurement results of pile position data, pile body verticality data and pile driving elevation data, and timely discover pipe piles with deviations, thereby providing a data basis for subsequent pile position adjustments.
[0038] In an optional implementation, correcting the pile construction accuracy parameter based on the comparison deviation includes:
[0039] Based on the position comparison deviation and verticality deviation, the pile position and pile body verticality are corrected by hydraulic jack, wire rope or pile pulling method until the pile position threshold and pile body verticality threshold are reached respectively;
[0040] Based on the elevation comparison deviation, the pile elevation is corrected by cutting or connecting piles until the design elevation is reached.
[0041] The pipe pile driving construction method for offshore tidal flat photovoltaic projects provided by the present invention adopts a hydraulic jack, a steel wire rope or a pile pulling method to correct the pile position and the verticality of the pile body based on the position comparison deviation and the verticality deviation, until the pile position threshold and the pile body verticality threshold are reached respectively; based on the elevation comparison deviation, the pile driving elevation is corrected by cutting or connecting the piles until the design elevation is reached, ensuring that each pipe pile can be accurately sunk into the predetermined position, which can significantly improve the accuracy of pile driving and effectively reduce the influence of the complex offshore environment on the pile driving accuracy, which is of great significance for the smooth installation of subsequent upper structures such as photovoltaic brackets and components, and ensuring the long-term stable operation of offshore tidal flat photovoltaic projects and improving economic benefits.
[0042] In a second aspect, the present invention provides a pipe pile sinking construction device for an offshore tidal flat photovoltaic project, which is applied to a pile driver, and the device comprises:
[0043] A pipe pile coordinate value determination module is used to determine the coordinate values of all pipe piles in the photovoltaic area to be constructed based on the coordinates of preset feature points in the photovoltaic area to be constructed;
[0044] The pipe pile positioning module is used to locate the corresponding pile position of each pipe pile in real time based on the pipe pile coordinate value, and obtain the positioning points of the corresponding pile positions of all pipe piles;
[0045] The pipe pile sinking module is used to adjust and verify the pile position based on a preset accuracy threshold and each positioning point, so that the pile driver sinks the pipe pile according to the adjusted and verified position;
[0046] The pipe pile construction accuracy parameter re-test module is used to re-test the pipe pile construction accuracy parameters of each pipe pile after the pipe pile sinking of all positioning points is completed, and obtain the re-test results;
[0047] A comparison module is used to compare the retest result with a preset accuracy threshold to obtain a comparison deviation;
[0048] The correction module is used to correct the pile construction accuracy parameters based on the comparison deviation.
[0049] In a third aspect, the present invention provides a computer device, comprising: a memory and a processor, the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the pipe pile sinking construction method for an offshore tidal flat photovoltaic project of the first aspect or any corresponding embodiment thereof by executing the computer instructions.
[0050] In a fourth aspect, the present invention provides a computer-readable storage medium having computer instructions stored thereon, the computer instructions being used to enable a computer to execute the pipe pile sinking construction method for an offshore tidal flat photovoltaic project of the first aspect or any corresponding embodiment thereof. BRIEF DESCRIPTION OF THE DRAWINGS
[0051] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0052] Figure 1 It is a schematic flow chart of a pipe pile sinking construction method for an offshore tidal flat photovoltaic project according to an embodiment of the present invention;
[0053] Figure 2 is a schematic flow chart of another method for pipe pile sinking construction of an offshore tidal flat photovoltaic project according to an embodiment of the present invention;
[0054] Figure 3 It is a schematic flow chart of another method for pipe pile sinking construction of an offshore tidal flat photovoltaic project according to an embodiment of the present invention;
[0055] Figure 4 It is a schematic flow chart of another method for pipe pile sinking construction of an offshore tidal flat photovoltaic project according to an embodiment of the present invention;
[0056] Figure 5 is a structural block diagram of a pipe pile sinking construction device for an offshore tidal flat photovoltaic project according to an embodiment of the present invention;
[0057] Figure 6 It is a schematic diagram of the hardware structure of a computer device according to an embodiment of the present invention. DETAILED DESCRIPTION
[0058] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.
[0059] According to an embodiment of the present invention, an embodiment of a method for pipe pile sinking construction in an offshore tidal flat photovoltaic project is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described may be executed in an order different from that shown here.
[0060] In this embodiment, a method for pipe pile sinking construction of an offshore tidal flat photovoltaic project is provided, which can be used for a pile driver. Figure 1 : is a flow chart of a pipe pile sinking construction method for an offshore tidal flat photovoltaic project according to an embodiment of the present invention. Figure 1 As shown, the process includes the following steps:
[0061] Step S101, determining the coordinate values of all pipe piles in the photovoltaic area to be constructed based on the coordinates of preset feature points of the photovoltaic area to be constructed.
[0062] Specifically, Figure 4As shown, this step is the operation before pile driving construction. Before construction, on-site investigation and measurement of the photovoltaic area to be constructed are carried out, underwater terrain scanning is carried out, geological conditions are understood, tidal laws and wind and wave characteristics are familiarized, and high-precision measuring instruments (such as total stations, levels, handheld locators (the handheld locator in this embodiment uses handheld RTK, Real-Time Kinematic, carrier phase differential locator) are used to determine the coordinate values of all pipe piles in the photovoltaic area to be constructed according to the preset feature point coordinates marked on the construction drawings, and accurate layout of the photovoltaic area to be constructed is achieved based on the pipe pile coordinate values. Accurate layout is to accurately layout a photovoltaic area to be constructed or the first pipe pile of a row, and the subsequent pipe pile sinking construction is carried out based on the "first pipe pile" as the benchmark.
[0063] It should be noted that after obtaining the coordinate values and precise layout of all pipe piles in the photovoltaic area to be constructed, a detailed construction plan should be formulated. Based on the underwater terrain scanning and precise layout results, combined with the requirements and actual conditions of the photovoltaic project, communication with the design unit should be carried out to fine-tune some pile positions in the drawings, clarify the sequence and method of pile sinking, and select appropriate construction equipment based on the geological survey results to ensure smooth construction.
[0064] Step S102: positioning the pile position corresponding to each pipe pile in real time based on the pipe pile coordinate value, and obtaining the positioning points of the pile positions corresponding to all pipe piles.
[0065] Specifically, Figure 4 As shown in the figure, before construction, the corresponding pile positions of the pipe piles are marked based on the pipe pile coordinate values, each pile position is numbered, and the accurate coordinate values of the corresponding pile positions of all pipe piles are input into the positioning system of the pile driver. The positioning system is used to locate and monitor the pile positions in real time to obtain the positioning points of the corresponding pile positions of all pipe piles.
[0066] Step S103, adjusting and verifying the pile position based on a preset accuracy threshold and each positioning point, so that the pile driver sinks the pipe pile according to the adjusted and verified position.
[0067] Specifically, the preset accuracy threshold includes pile position data, pile body vertical height data, etc. Figure 4 As shown, during construction, after the pile driver is in place, the pile position is fine-tuned based on the preset accuracy threshold and each positioning point, and the positioning system is used to review and calibrate the pipe pile position. The pile position data and the vertical height data of the pile body that are inconsistent with the review requirements are adjusted in time, so that the pile driver can sink the pipe pile according to the adjusted and reviewed position.
[0068] It should be noted that data recording and analysis should be done well during construction, and the data collected by the positioning system should be recorded and analyzed in real time. Through data analysis, deviations in the construction process can be discovered and corrected in a timely manner to improve pile driving accuracy.
[0069] Step S104, when the pile driving of all the positioning points is completed, the pile construction accuracy parameters of each pile are re-measured to obtain the re-measurement results.
[0070] Specifically, Figure 4 As shown in the figure, after the construction is completed, that is, after all the pipe piles are driven, high-precision measuring instruments (such as total stations and levels) are used to re-measure the pipe pile construction accuracy parameters such as pile position, pile body verticality and pile driving elevation to obtain the pile position, pile body verticality and pile driving elevation data.
[0071] Step S105, comparing the retest result with a preset accuracy threshold to obtain a comparison deviation.
[0072] Specifically, the pile sinking accuracy of pipe piles is considered from three dimensions: pile position (i.e., pile sinking coordinate value), pile body verticality, and pile sinking elevation. The relevant values will be specified in the construction drawings. For example, a photovoltaic project on offshore mudflats stipulates the following allowable deviations for pipe pile sinking: pile position deviation <10mm, center distance deviation of adjacent piles <40mm, pile sinking elevation deviation between -10mm and +0mm, and pile body verticality deviation <0.5%.
[0073] Carry out construction deviation adjustment, that is, compare the pile position, pile verticality and pile elevation data with the preset accuracy threshold (that is, the allowable deviation specified above) to obtain the comparison deviation.
[0074] Step S106, correcting the pile construction accuracy parameters based on the comparison deviation.
[0075] Specifically, if deviations are found in the pile driving accuracy, timely measures should be taken to make adjustments. The specific operations are as follows: when deviations occur in the pile position and the verticality of the pile body, hydraulic jacks and wire ropes can be used to correct the pile position and the verticality of the pile body until the pile position threshold and the pile body verticality threshold are reached respectively; when deviations occur in the pile driving elevation, the pile driving elevation can be corrected by cutting or connecting the piles; when the overall deviation of the pipe pile is too large and the above correction methods cannot make the pipe pile meet the design requirements, the method of pulling out the pile and re-injecting it can be used for processing, but it needs to be evaluated and confirmed by the design unit.
[0076] It should be noted that quality assessment and summary are required after construction, quality assessment of pile sinking accuracy during construction, and summary of experience and lessons. Improvement measures and suggestions are proposed for existing problems and deficiencies, providing reference and reference for subsequent pile sinking operations of the project.
[0077] The pipe pile driving construction method for offshore tidal flat photovoltaic projects provided in this embodiment can effectively cope with complex offshore construction environments such as tidal changes and wind and wave impacts in offshore tidal flat projects, by accurately measuring the coordinate values of all pipe piles before construction, real-time positioning and correction during construction, and re-measuring and correcting the pipe pile construction accuracy parameters after construction. It significantly improves the accuracy of pile driving and solves the problem of large deviations in pile driving accuracy caused by the lack of real-time and accurate monitoring of the entire pipe pile construction process.
[0078] In this embodiment, a method for pipe pile sinking construction of an offshore tidal flat photovoltaic project is provided, which can be used for a pile driver. Figure 2 : is a flow chart of a pipe pile sinking construction method for an offshore tidal flat photovoltaic project according to an embodiment of the present invention. Figure 2 As shown, the process includes the following steps:
[0079] Step S201, determining the coordinate values of all pipe piles in the photovoltaic area to be constructed based on the coordinates of preset feature points of the photovoltaic area to be constructed.
[0080] Specifically, the above step S201 includes:
[0081] Step S2011, determining the coordinate value of the first pipe pile based on the preset feature point coordinates of the photovoltaic area to be constructed.
[0082] Among them, a large number of pipe piles, as many as tens of thousands, are set up in the photovoltaic area to be constructed. The pipe piles are constructed by area. The coordinate value of the first feature point of a construction area or a row will be marked in the construction drawing, and the absolute coordinate value of the first pipe pile will be determined based on the coordinate value of the first feature point.
[0083] Step S2012, determining the coordinate values of the remaining pipe piles in the photovoltaic area to be constructed except the coordinate value of the first pipe pile based on the coordinate value of the first pipe pile, the preset transverse pile spacing threshold and the preset longitudinal pile spacing threshold.
[0084] Specifically, after the coordinate value of the first pipe pile is determined, the coordinate values of the remaining pipe piles in the photovoltaic area to be constructed except the coordinate value of the first pipe pile are determined based on the coordinate value of the first pipe pile, the preset transverse pile spacing threshold, and the preset longitudinal pile spacing threshold. For example, the transverse spacing threshold of the pipe piles in a certain offshore photovoltaic project is 6.5m, and the longitudinal spacing threshold is 8.4m.
[0085] Step S202: positioning the pile position corresponding to each pipe pile in real time based on the pipe pile coordinate value, and obtaining the positioning points of the pile positions corresponding to all pipe piles.
[0086] Specifically, the pile driver includes a Beidou positioning device, and the above step S202 includes:
[0087] Step S2021, using Beidou positioning equipment to perform real-time positioning on the pile position corresponding to the coordinate value of the first pipe pile to obtain the positioning point of the first pipe pile.
[0088] Specifically, two Beidou positioning devices are installed on the platform of each pile driver for precise positioning and verification. The Beidou positioning devices are used to perform real-time positioning of the pile position corresponding to the coordinate value of the first pipe pile to obtain the positioning point of the first pipe pile.
[0089] Step S2022, using Beidou positioning equipment to perform positioning based on the positioning point of the first pipe pile and the corresponding pile positions of the coordinate values of the remaining pipe piles except the first pipe pile, to obtain the positioning points of the corresponding pile positions of the remaining pipe piles; the positioning point of the first pipe pile and the positioning points of the corresponding pile positions of the remaining pipe piles constitute the positioning points of the corresponding pile positions of all pipe piles.
[0090] Step S203, adjusting and verifying the pile position based on a preset accuracy threshold and each positioning point, so that the pile driver sinks the pipe pile according to the adjusted and verified position.
[0091] Specifically, the pile driver also includes a positioning correction module and a handheld positioning device;
[0092] It should be noted that the pile driver also includes a main body, a platform module, a pile driving module, a measurement and positioning module, and a stabilization module; among which: the platform module includes two pontoons, a generator and an electric paddle. The two pontoons are arranged in parallel and connected to provide a support platform for the entire pile driver operation; the generator provides all the electrical energy for the platform module, and the electric paddle provides power for the movement of the platform module. The pile driving module includes a truss pole, a pile hammer and a control system. The pile driving module is a key equipment of the pile driver. The truss pole provides track support for the longitudinal movement of the pile hammer. The pile hammer and the control system use the conversion of potential energy and kinetic energy to sink the pile into the sea to the designed elevation. The measurement and positioning module includes a GPS receiver, a front pile holding guide rod and a fixed rod. The GPS receiver is responsible for obtaining the pile position information and providing position navigation; the front pile holding guide rod uses the constructed pile as a fixed point to provide path support for the forward and backward movement of the pile driver to assist in positioning; the fixed rod is located on the front and rear sides of the platform module, and is inserted into the underwater mud layer after reaching the predetermined position to play a fixing role. The stabilization module consists of two small stabilization boxes and their connection devices, that is, two small stabilization boxes are added on both sides of the two pontoons of the platform module. The stabilization pontoons are connected to the main body of the pile driver through pins to improve the pile driver's anti-overturning and anti-surge capabilities. During the pile driving process, the stable support platform can reduce the shaking caused by wind and waves, allowing the pile driver to more accurately control the verticality of the pipe pile and improve the construction quality of the pipe pile.
[0093] The above step S203 includes:
[0094] Step S2031, align the pile driver with the first pipe pile positioning point.
[0095] Specifically, at the beginning of construction, the pile driver is aligned with the first pipe pile positioning point, so that the pile driver is accurately positioned at the first pipe pile positioning point.
[0096] Step S2032, comparing the preset accuracy threshold and the first pipe pile positioning point to see if they are consistent, if not, using the positioning correction module to adjust the pile position corresponding to the first pipe pile until they are consistent.
[0097] Specifically, the positioning correction module includes a hydraulic jack and a positioning rod with a certain thrust and telescopic stroke. One end of the positioning rod is connected with a sleeve, and the sleeve can rotate freely with the positioning rod as the axis; the other end is connected to the pontoon in the form of a pin, and can also rotate axially. After the positioning rod is inserted into the mud layer and fixed, it provides a movable stroke for the two pontoons to ensure that the position is adjusted with the positioning rod as the center to achieve precise positioning. Both ends of the hydraulic jack are connected to the tail of the pontoon and the middle of the positioning rod connecting device in the form of a pin. The hydraulic jack provides kinetic energy for the precise positioning of the two pontoons through the telescopic movement of the hydraulic rod.
[0098] Compare the preset accuracy threshold and the positioning point of the first pipe pile to see if they are consistent. If they are inconsistent, it means there is a deviation. The positioning correction module is used to adjust the pile position corresponding to the first pipe pile until they are consistent. The deviation correction is completed before the pile sinking construction process.
[0099] Step S2033, driving the pile driver to sink the first pipe pile according to the adjusted position.
[0100] Specifically, the pile driver is used to sink the first pipe pile according to the adjusted position, which improves the pile sinking accuracy, saves the pile sinking time, has low experience and technical requirements for the operator, and enables efficient use of resources.
[0101] Step S2034, before reaching the designed elevation of the pile driving, the pile position is rechecked based on the preset accuracy threshold using the positioning correction module and the handheld locator. If the recheck is inconsistent, the pile position is adjusted again until it is consistent.
[0102] Specifically, during the pile driving construction process, before reaching the designed elevation of the pile driving, the pile position corresponding to the first pipe pile is rechecked every 1m or 2m of the pile driving based on the preset accuracy threshold using a positioning correction module and a handheld locator. If the recheck is inconsistent, the pile position is adjusted again until it is consistent, thereby ensuring that the accuracy parameters of the pipe piles during the pile driving process meet the preset thresholds.
[0103] Step S2035, the pile driver continues to sink the first pipe pile according to the verified and adjusted pile position until the sinking of the first pipe pile is completed.
[0104] Step S2036, after the first pipe pile is sunk, continue to sunk the pipe piles at the remaining positioning points until all the pipe piles are sunk.
[0105] Specifically, after the first pipe pile is driven in, the pipe piles at the remaining positioning points are driven in accordance with steps S2031 to S2035 until all the pipe piles are driven in.
[0106] Step S204: After the piles of all the positioning points are sunk, the pile construction accuracy parameters of each pile are retested to obtain the retest results. Figure 1 Step S104 of the illustrated embodiment will not be described in detail here.
[0107] Step S205, compare the retest result with the preset accuracy threshold to obtain the comparison deviation. Figure 1 Step S105 of the illustrated embodiment will not be described in detail here.
[0108] Step S206: Correct the pile construction accuracy parameters based on the comparison deviation. Figure 1 Step S106 of the illustrated embodiment will not be described in detail here.
[0109] The pipe pile sinking construction method for offshore tidal flat photovoltaic projects provided in this embodiment first determines the coordinate value of the first pipe pile based on the preset feature point coordinates of the photovoltaic area to be constructed, and determines the coordinate values of all pipe piles in the photovoltaic area to be constructed based on the coordinate value of the first pipe pile, the preset horizontal pile spacing threshold and the preset longitudinal pile spacing threshold. By conducting on-site surveys and measurements before construction, the purpose of obtaining the coordinate values of all pipe piles in the photovoltaic area to be constructed is achieved, which provides a basis for the subsequent positioning of the corresponding pile positions of the pipe piles. By using Beidou positioning equipment to locate the pile position corresponding to the coordinate value of the first pipe pile in real time, the first pipe pile positioning point is obtained, and based on the first pipe pile positioning point and the corresponding pile positions of the coordinate values of the remaining pipe piles except the first pipe pile, the positioning points of the corresponding pile positions of the remaining pipe piles are obtained, and the purpose of accurately locating the corresponding pile positions of all pipe piles is achieved. By using a positioning correction module and a handheld positioning instrument to carry out real-time positioning and monitoring of the pile positions during construction, data and analysis are done well, and construction positioning deviations are corrected in time to achieve accurate positioning, which indirectly improves the accuracy of pile sinking.
[0110] In this embodiment, a method for pipe pile sinking construction of an offshore tidal flat photovoltaic project is provided, which can be used for a pile driver. Figure 3 : is a flow chart of a pipe pile sinking construction method for an offshore tidal flat photovoltaic project according to an embodiment of the present invention. Figure 3 As shown, the process includes the following steps:
[0111] Step S301, based on the coordinates of the preset feature points of the photovoltaic area to be constructed, the coordinate values of all the pipe piles in the photovoltaic area to be constructed are determined. Figure 1 Step S201 of the illustrated embodiment will not be described in detail here.
[0112] Step S302: Based on the coordinate values of the pipe piles, the corresponding pile positions of each pipe pile are located in real time to obtain the positioning points of the corresponding pile positions of all pipe piles. Figure 1 Step S202 of the illustrated embodiment will not be described in detail here.
[0113] Step S303, adjusting and rechecking the pile position based on the preset accuracy threshold and each positioning point, so that the pile driver sinks the pipe pile according to the adjusted and rechecked position. Figure 1 Step S203 of the illustrated embodiment will not be described in detail here.
[0114] Step S304, when the pile driving of all the positioning points is completed, the pile construction accuracy parameters of each pile are re-measured to obtain the re-measurement results.
[0115] Specifically, the pile driver also includes an onshore total station. The precision parameters of pipe pile construction include pile position, pile body verticality and pile driving elevation. The onshore total station is used to re-measure the pile position, pile body verticality and pile driving elevation corresponding to each pipe pile to obtain the re-measurement results of pile position data, pile body verticality data and pile driving elevation data.
[0116] Step S305, comparing the retest result with a preset accuracy threshold to obtain a comparison deviation.
[0117] Specifically, the preset accuracy threshold includes a pile position threshold, a pile body verticality threshold and a design elevation. The above step S305 includes:
[0118] Step S3051, comparing the pile position data with the pile position threshold to obtain a position comparison deviation.
[0119] Specifically, the pile position threshold can be set to 10 mm. When the pile position is less than 10 mm, it means that the pile position meets the pile position threshold range. When the pile position is greater than 10 mm, 10 mm is subtracted from the pile position data to obtain the position comparison deviation.
[0120] Step S3052, compare the pile body verticality data with the pile body verticality threshold value to obtain the verticality comparison deviation. Specifically, the pile body verticality threshold value can be set to 0.5%. When the pile body verticality data is less than 0.5%, it means that the pile body verticality data meets the pile body verticality threshold range. When the pile body verticality data is greater than 0.5%, 0.5% is subtracted from the pile body verticality data to obtain the verticality comparison deviation.
[0121] Step S3053, comparing the pile driving elevation data with the design elevation to obtain the elevation comparison deviation.
[0122] Specifically, the design elevation can be set to -10mm to 0mm. When the pile elevation data is between -10mm and 0mm, it means that the pile elevation data meets the design elevation range. When the pile elevation data is greater than 0mm or less than -10mm, the pile elevation data is subtracted by 0mm or -10mm to obtain the elevation comparison deviation.
[0123] Step S306: correct the pile construction accuracy parameters based on the comparison deviation.
[0124] Specifically, the above step S306 includes:
[0125] Step S3061, based on the position comparison deviation and the verticality deviation, the pile position and the pile body verticality are corrected by using a hydraulic jack, a wire rope or a pile pulling method until the pile position threshold and the pile body verticality threshold are reached respectively.
[0126] Specifically, if the position comparison deviation and verticality comparison deviation are small, the pile position and pile body verticality corresponding to the pipe pile are corrected and adjusted based on the position comparison deviation and verticality deviation using hydraulic jacks or wire ropes until the pile position threshold and pile body verticality threshold are reached respectively. If the deviation is large, that is, it cannot be adjusted by correction, the pipe pile may be re-sunk by pulling out the pile, but it needs to be evaluated and confirmed by the design unit.
[0127] Step S3062, based on the elevation comparison deviation, the pile elevation is corrected by cutting or connecting the piles until the design elevation is reached.
[0128] Specifically, if the elevation data of the pile is higher than the design elevation, the pile cutting method can be adopted to cut off the higher part (while doing a good job of anti-corrosion on the pile end) to make it reach the design elevation; if the elevation data of the pile is lower than the design elevation, the pile connection method (the connection method is welding) can be adopted to re-drive the pile until the elevation data of the pile reaches the design elevation.
[0129] It should be noted that in actual projects, the control of pile elevation is essentially to ensure the smooth installation of subsequent upper structures such as photovoltaic brackets and components. When designing the upper structure, a certain error tolerance is usually reserved for the pile elevation deviation, generally -10cm to +10cm, that is, the pile elevation deviation within this range has no substantial impact on the installation of the upper structure.
[0130] The pipe pile driving construction method for offshore tidal flat photovoltaic project provided in the present embodiment timely conducts re-measurement after construction, and uses a shore total station to re-measure the pile position, pile body verticality and pile driving elevation of each pipe pile, so as to obtain the re-measurement results of pile position data, pile body verticality data and pile driving elevation data, and timely discovers pipe piles with deviations, and based on the position comparison deviation and the verticality deviation, uses a hydraulic jack, a wire rope or a pile pulling method to correct the pile position and the pile body verticality until the pile position threshold and the pile body verticality threshold are reached respectively; based on the elevation comparison deviation, the pile driving elevation is corrected by cutting or connecting piles until the design elevation is reached, so as to ensure that each pipe pile can be accurately sunk into the predetermined position, which can significantly improve the accuracy of pile driving, and can also effectively reduce the influence of the complex offshore environment on the pile driving accuracy, which is of great significance for the smooth installation of subsequent upper structures such as photovoltaic brackets and components, ensuring the long-term stable operation of offshore tidal flat photovoltaic projects, and improving economic benefits.
[0131] In this embodiment, a pipe pile sinking construction device for an offshore tidal flat photovoltaic project is also provided, which is used to implement the above-mentioned embodiments and preferred implementation modes, and the descriptions that have been made will not be repeated. As used below, the term "module" can implement a combination of software and / or hardware for a predetermined function. Although the devices described in the following embodiments are preferably implemented in software, the implementation of hardware, or a combination of software and hardware, is also possible and conceivable.
[0132] This embodiment provides a pipe pile sinking construction device for an offshore tidal flat photovoltaic project. Figure 5 As shown, including:
[0133] The pipe pile coordinate value determination module 501 is used to determine the coordinate values of all pipe piles in the photovoltaic area to be constructed based on the coordinates of preset feature points of the photovoltaic area to be constructed.
[0134] The pipe pile positioning module 502 is used to perform real-time positioning of the pile position corresponding to each pipe pile based on the pipe pile coordinate value, and obtain the positioning points of the pile positions corresponding to all pipe piles.
[0135] The pipe pile sinking module 503 is used to adjust and verify the pile position based on a preset accuracy threshold and each positioning point, so that the pile driver sinks the pipe pile according to the adjusted and verified position.
[0136] The pipe pile construction accuracy parameter re-testing module 504 is used to re-test the pipe pile construction accuracy parameters of each pipe pile after the pipe piles at all the positioning points are sunk, and obtain the re-testing results.
[0137] The comparison module 505 is used to compare the retest result with a preset accuracy threshold to obtain a comparison deviation.
[0138] The correction module 506 is used to correct the pile construction parameters based on the comparison deviation.
[0139] In some optional implementations, the pile coordinate value determination module 501 includes:
[0140] The first pipe pile coordinate value determining unit is used to determine the coordinate value of the first pipe pile based on the coordinates of preset feature points of the photovoltaic area to be constructed.
[0141] The second pipe pile coordinate value determination unit is used to determine the coordinate values of the remaining pipe piles in the photovoltaic area to be constructed except the coordinate value of the first pipe pile based on the coordinate value of the first pipe pile, a preset transverse pile spacing threshold and a preset longitudinal pile spacing threshold.
[0142] In some optional embodiments, the pile positioning module 502 includes:
[0143] The first pipe pile positioning unit is used to use Beidou positioning equipment to perform real-time positioning on the pile position corresponding to the coordinate value of the first pipe pile to obtain the positioning point of the first pipe pile.
[0144] The second pipe pile positioning unit is used to use Beidou positioning equipment to perform positioning based on the positioning point of the first pipe pile and the corresponding pile positions of the coordinate values of the remaining pipe piles except the first pipe pile, to obtain the positioning points of the corresponding pile positions of the remaining pipe piles; the positioning point of the first pipe pile and the positioning points of the corresponding pile positions of the remaining pipe piles constitute the positioning points of the corresponding pile positions of all pipe piles.
[0145] In some optional embodiments, the pipe pile sinking module 503 includes:
[0146] The alignment unit is used to align the pile driver with the first pipe pile positioning point.
[0147] The position comparison and adjustment unit is used to compare whether the preset accuracy threshold and the positioning point of the first pipe pile are consistent. If they are inconsistent, the positioning correction module is used to adjust the pile position corresponding to the first pipe pile until they are consistent.
[0148] The first pipe pile sinking unit is used to drive the pile driver to sink the first pipe pile according to the adjusted position.
[0149] The position review and adjustment unit is used to review the pile position again based on the preset accuracy threshold and using the positioning correction module and the handheld locator before reaching the designed elevation of the pile. If the review is inconsistent, the pile position is adjusted again until it is consistent.
[0150] The second first pipe pile sinking unit is used for the pile driver to continue sinking the first pipe pile according to the verified and adjusted pile position until the sinking of the first pipe pile is completed.
[0151] The remaining pipe pile driving units are used to continue driving the pipe piles at the remaining positioning points after the first pipe pile driving is completed until all the pipe piles are driven.
[0152] In some optional embodiments, the comparison module 505 includes:
[0153] The first comparison unit is used to compare the pile position data with the pile position threshold to obtain a position comparison deviation.
[0154] The second comparison unit is used to compare the pile body verticality data with the pile body verticality threshold to obtain a verticality comparison deviation.
[0155] The third comparison unit is used to compare the pile driving elevation data with the design elevation to obtain the elevation comparison deviation.
[0156] In some optional implementations, the correction module 506 includes:
[0157] The first correction unit is used to correct the pile position and the verticality of the pile body based on the position comparison deviation and the verticality deviation by using a hydraulic jack, a wire rope or a pile pulling method until the pile position threshold and the pile body verticality threshold are reached respectively.
[0158] The second correction unit is used to correct the pile elevation based on the elevation comparison deviation by cutting or connecting the piles until the design elevation is reached.
[0159] The further functional description of each of the above modules and units is the same as that of the above corresponding embodiments and will not be repeated here.
[0160] The pipe pile driving construction device for the offshore tidal flat photovoltaic project in this embodiment is presented in the form of a functional unit, where the unit refers to an ASIC (Application Specific Integrated Circuit) circuit, a processor and memory that executes one or more software or fixed programs, and / or other devices that can provide the above functions.
[0161] The embodiment of the present invention also provides a computer device having the above Figure 5 The pipe pile sinking construction device for the offshore tidal flat photovoltaic project is shown.
[0162] See also Figure 6 , Figure 6 is a schematic diagram of the structure of a computer device provided by an optional embodiment of the present invention, such as Figure 6As shown, the computer device includes: one or more processors 10, a memory 20, and interfaces for connecting various components, including high-speed interfaces and low-speed interfaces. Various components are connected to each other using different buses for communication, and can be installed on a common mainboard or installed in other ways as needed. The processor can process the instructions executed in the computer device, including instructions stored in or on the memory to display the graphical information of the GUI on an external input / output device (such as, a display device coupled to the interface). In some optional embodiments, if necessary, multiple processors and / or multiple buses can be used together with multiple memories and multiple memories. Similarly, multiple computer devices can be connected, and each device provides some necessary operations (for example, as a server array, a group of blade servers, or a multi-processor system). Figure 6 A processor 10 is taken as an example.
[0163] The processor 10 may be a central processing unit, a network processor or a combination thereof. The processor 10 may further include a hardware chip. The hardware chip may be a dedicated integrated circuit, a programmable logic device or a combination thereof. The programmable logic device may be a complex programmable logic device, a field programmable gate array, a general purpose array logic or any combination thereof.
[0164] The memory 20 stores instructions executable by at least one processor 10, so that the at least one processor 10 executes the method shown in the above embodiment.
[0165] The memory 20 may include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required for at least one function; the data storage area may store data created according to the use of the computer device, etc. In addition, the memory 20 may include a high-speed random access memory, and may also include a non-transient memory, such as at least one disk storage device, a flash memory device, or other non-transient solid-state storage device. In some optional embodiments, the memory 20 may optionally include a memory remotely arranged relative to the processor 10, and these remote memories may be connected to the computer device via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0166] The memory 20 may include a volatile memory, such as a random access memory; the memory may also include a non-volatile memory, such as a flash memory, a hard disk or a solid state drive; the memory 20 may also include a combination of the above types of memory.
[0167] The computer device also includes an input device 30 and an output device 40. The processor 10, the memory 20, the input device 30 and the output device 40 may be connected via a bus or other means. Figure 6 The example of connecting through bus is taken in the following.
[0168] The input device 30 can receive input digital or character information, and generate key signal input related to the user settings and function control of the computer device, such as a touch screen, a keypad, a mouse, a track pad, a touch pad, an indicator bar, one or more mouse buttons, a trackball, a joystick, etc. The output device 40 may include a display device, an auxiliary lighting device (e.g., an LED) and a tactile feedback device (e.g., a vibration motor), etc. The above-mentioned display device includes but is not limited to a liquid crystal display, a light emitting diode, a display and a plasma display. In some optional embodiments, the display device can be a touch screen.
[0169] The embodiment of the present invention also provides a computer-readable storage medium. The method according to the embodiment of the present invention can be implemented in hardware, firmware, or can be implemented as a computer code that can be recorded in a storage medium, or can be implemented as a computer code that is originally stored in a remote storage medium or a non-temporary machine-readable storage medium and will be stored in a local storage medium through a network download, so that the method described herein can be stored in such software processing on a storage medium using a general-purpose computer, a dedicated processor, or programmable or dedicated hardware. Among them, the storage medium can be a magnetic disk, an optical disk, a read-only storage memory, a random access memory, a flash memory, a hard disk or a solid-state hard disk, etc.; further, the storage medium can also include a combination of the above types of memories. It can be understood that a computer, a processor, a microprocessor controller, or programmable hardware includes a storage component that can store or receive software or computer code. When the software or computer code is accessed and executed by a computer, a processor, or hardware, the method shown in the above embodiment is implemented.
[0170] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.
Claims
1. A pipe pile sinking construction method for an offshore tidal flat photovoltaic project, characterized in that: Applied to a pile driver, the method comprises: Determine the coordinate values of all pipe piles in the photovoltaic area to be constructed based on the coordinates of the preset characteristic points of the photovoltaic area to be constructed; Based on the coordinate value of the pipe pile, the corresponding pile position of each pipe pile is located in real time to obtain the positioning points of the corresponding pile positions of all pipe piles; The pile position is adjusted and verified based on the preset accuracy threshold and each positioning point, so that the pile driver sinks the pipe pile according to the adjusted and verified position; When the piles of all the positioning points are sunk, the construction accuracy parameters of each pile are re-measured to obtain the re-measurement results; Comparing the retest result with a preset accuracy threshold to obtain a comparison deviation; The pipe pile construction accuracy parameters are corrected based on the comparison deviation.
2. The method according to claim 1, characterized in that: The method of determining the coordinate values of all pipe piles in the photovoltaic area to be constructed based on the coordinates of the preset characteristic points of the photovoltaic area to be constructed comprises: Determine the coordinate value of the first pipe pile based on the coordinates of the preset characteristic points of the photovoltaic area to be constructed; Based on the coordinate value of the first pipe pile, a preset transverse pile spacing threshold and a preset longitudinal pile spacing threshold, the coordinate values of the remaining pipe piles in the photovoltaic area to be constructed except the coordinate value of the first pipe pile are determined.
3. The method according to claim 2, characterized in that The pile driver includes a Beidou positioning device, and the real-time positioning of the pile position corresponding to each pipe pile is performed based on the pipe pile coordinate value, and the positioning points of the pile positions corresponding to all pipe piles are obtained, including: Beidou positioning equipment is used to locate the coordinate value of the first pipe pile in real time to obtain the first pipe pile positioning point; Using Beidou positioning equipment and positioning based on the first pipe pile positioning point and the corresponding pile positions of the remaining pipe piles except the first pipe pile, the positioning points of the corresponding pile positions of the remaining pipe piles are obtained; The first pipe pile positioning point and the positioning points of the corresponding pile positions of the remaining pipe piles constitute the positioning points of the corresponding pile positions of all pipe piles.
4. The method according to claim 3, characterized in that The pile driver also includes a positioning correction module and a handheld positioning instrument, which adjust and verify the pile position based on a preset accuracy threshold and each positioning point, so that the pile driver sinks the pipe pile according to the adjusted and verified position, including: Align the pile driver to the first pipe pile positioning point; Compare the preset accuracy threshold and the first pipe pile positioning point to see if they are consistent. If not, use the positioning correction module to adjust the pile position corresponding to the first pipe pile until they are consistent; Use the pile driver to sink the first pipe pile according to the adjusted position; Before reaching the designed elevation of pile driving, the pile position is rechecked based on the preset accuracy threshold using the positioning correction module and the handheld locator. If the recheck is inconsistent, the pile position is adjusted again until it is consistent. The pile driver continues to sink the first pipe pile according to the verified and adjusted pile position until the first pipe pile is sunk; After the first pipe pile is sunk, continue to sunk the pipe piles at the remaining positioning points until all the pipe piles are sunk.
5. The method according to claim 1, characterized in that The pile driver also includes an onshore total station, and the pipe pile construction accuracy parameters include pile position, pile body verticality and pile sinking elevation; The pile construction accuracy parameters of each pile are retested, and the retest results include: The onshore total station is used to re-measure the pile position, pile body verticality and pile elevation of each pipe pile, and the re-measurement results of pile position data, pile body verticality data and pile elevation data are obtained.
6. The method according to claim 5, characterized in that The preset accuracy thresholds include a pile position threshold, a pile body verticality threshold and a design elevation; The retest result is compared with a preset accuracy threshold, and the comparison deviation is obtained including: Comparing the pile position data with the pile position threshold to obtain a position comparison deviation; Comparing the pile body verticality data with the pile body verticality threshold to obtain a verticality comparison deviation; The pile driving elevation data is compared with the design elevation to obtain the elevation comparison deviation.
7. The method according to claim 6, characterized in that The correction of the pipe pile construction accuracy parameter based on the comparison deviation includes: Based on the position comparison deviation and the verticality deviation, the pile position and the pile body verticality are corrected by using a hydraulic jack, a wire rope or a pile pulling method until the pile position threshold and the pile body verticality threshold are reached respectively; Based on the elevation comparison deviation, the pile elevation is corrected by cutting or connecting piles until the design elevation is reached.
8. A pipe pile sinking construction device for an offshore tidal flat photovoltaic project, characterized in that: Applied to a pile driver, the device comprises: A pipe pile coordinate value determination module is used to determine the coordinate values of all pipe piles in the photovoltaic area to be constructed based on the coordinates of preset feature points in the photovoltaic area to be constructed; The pipe pile positioning module is used to locate the corresponding pile position of each pipe pile in real time based on the pipe pile coordinate value, and obtain the positioning points of the corresponding pile positions of all pipe piles; The pipe pile sinking module is used to adjust and verify the pile position based on a preset accuracy threshold and each positioning point, so that the pile driver sinks the pipe pile according to the adjusted and verified position; The pipe pile construction accuracy parameter re-test module is used to re-test the pipe pile construction accuracy parameters of each pipe pile after the pipe pile sinking of all positioning points is completed, and obtain the re-test results; A comparison module, used to compare the retest result with a preset accuracy threshold to obtain a comparison deviation; The correction module is used to correct the pipe pile construction accuracy parameters based on the comparison deviation.
9. A computer device, characterized in that: include: A memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the pipe pile sinking construction method for an offshore tidal flat photovoltaic project according to any one of claims 1 to 7 by executing the computer instructions.
10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a computer to execute the pipe pile sinking construction method for an offshore tidal flat photovoltaic project according to any one of claims 1 to 7.
Citation Information
Cited By
Pile foundation position rechecking device and method
CN119411586A
Prefabricated pier installation control method based on measurement image recognition
CN121032965A
Wharf pile sinking construction method under complex obstacle environment
CN121118224A