Pavement paving control method based on laser measurement
Through the pavement paving control method based on laser measurement, the three-dimensional coordinate system and weighted summing technology are used to solve the problem of uneven paving of viaducts and curved roads, and the matching of pavement shape and design shape and construction smoothness are achieved. .
Patent Information
- Application Number
- CN202411139826.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-20
- Publication Date
- 2024-12-03
AI Technical Summary
In pavement construction, especially pavement at viaducts and bends, the pavement is uneven due to the design considerations such as drainage and vehicle turning, and it is difficult for the existing technology to effectively spread out shapes that meet the design requirements.
Using the pavement paving control method based on laser measurement, by establishing a three-dimensional coordinate system, measuring and modeling the pavement height equation in real time, using weighted summing to determine the paving shape along the pavement width direction, adjusting the scraper shape to match the design shape .
The matching of pavement shape and design shape is achieved, construction errors and design errors are taken into account, and the flatness and construction smoothness are ensured.
Smart Images

Figure CN119061762A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of road paving, and in particular to a road paving control method based on laser measurement. Background Art
[0002] In the process of road construction, concrete or asphalt needs to be paved. In the prior art, when paving the road, the road is usually paved by a paver. For roads with high flatness requirements, a paver is used for paving, which not only has a good paving effect, but also has a high paving effect.
[0003] However, for some roads, such as curves and viaducts, the road surface is not always flat during the design process due to factors such as drainage and overcoming the centrifugal force of vehicles turning. In the width direction of the road surface, it usually has a certain slope or curvature, that is, the road surface is not always a straight line in the cross section along the width of the road surface.
[0004] In summary, how to pave the road surface of an elevated bridge, especially the road surface where height changes and turns overlap, is one of the important issues that need to be solved urgently in this field. Summary of the invention
[0005] The purpose of the present invention is to provide a road paving control method based on laser measurement to solve the deficiencies in the prior art. It can directly pave a shape that meets the road design according to the design requirements and the different road heights.
[0006] The present invention provides a road paving control method based on laser measurement, which comprises the following steps:
[0007] S1, establish a three-dimensional coordinate system in the vertical plane with the starting position as the origin;
[0008] S2, determine the relationship between the road surface height along the paving direction and the road surface width direction;
[0009] S3, real-time measurement of the horizontal distance between the current paving position and the starting position;
[0010] S4, calculating a first height equation in the road width direction at the current paving position;
[0011] S5, performing three-dimensional laser measurement on the paving surface within a certain distance in front of the current paving position to obtain point cloud data; wherein the point cloud data includes the elevation of each measurement point;
[0012] S6, modeling the point cloud data, and obtaining a second height equation of the current position and a third height equation of the next position according to the model;
[0013] S7, determining a fourth height equation by weighted summation according to the first height equation at the current position, the second height equation and the third height equation at the previous position;
[0014] S8, adjusting the paving shape of the paver along the width direction of the road surface according to the fourth height equation.
[0015] As described above, in the road paving control method based on laser measurement, it is optional that: the relationship in step S2 is determined by the design dimensions of the road surface.
[0016] As described above, in the road paving control method based on laser measurement, it is optional that: in step S3, the starting position is the center of the paving starting position; and the horizontal distance measured in step S3 is the length of the center line of the road surface.
[0017] As described above, in the road paving control method based on laser measurement, it is optional that: the first height equation, the second height equation, the third height equation and the fourth height equation are all relationship equations of height along the width direction of the road surface.
[0018] As described above, in the pavement paving control method based on laser measurement, it is optional that: the relationship between the pavement height along the paving direction and the pavement width direction determined in step S2 is determined by the surface equation during design or is formed by fitting the coordinates of multiple points on the pavement.
[0019] As described above, in the road paving control method based on laser measurement, it is optional that: in step S7, before performing weighted summation, the second height equation and the third height equation are converted into the three-dimensional coordinate system.
[0020] As described above, the pavement paving control method based on laser measurement, wherein optionally: step S7 also includes, before weighted summation, correcting and judging the first height equation and the third height equation converted to the same coordinate system based on the second height equation, and performing weighted summation according to the judgment result.
[0021] The pavement paving control method based on laser measurement as described above, wherein the optional steps are: the independent variable range of the first height equation and the independent variable range of the third height equation are respectively judged with the independent variable range of the second height equation; when the independent variable range of the first height equation and the independent variable range of the third height equation are both less than the first deviation, weighted summation is performed according to the set weights; when the deviation between the independent variable range of the first height equation and the independent variable range of the second height equation is greater than the first deviation, the weight occupied by the first height equation is reduced and weighted summation is performed; when the deviation between the independent variable range of the third height equation and the second height equation and the independent variable range is greater than the first deviation, the weight occupied by the third height equation is reduced and weighted summation is performed.
[0022] The road paving control method based on laser measurement as described above, wherein, optionally: in step S8, the paving shape is adjusted by adjusting the shape of the scraper along the road width direction;
[0023] The scraper is a long strip of metal plate, and a plurality of height adjustment rods are provided along the length direction of the scraper. By adjusting the vertical position of the height adjustment rods, the purpose of adjusting the shape of the scraper along the length direction can be achieved;
[0024] The upper side of the scraper is connected to the paver via a plurality of elastic members.
[0025] Compared with the prior art, the present invention obtains the shape at the current moment as the target shape based on the designed shape of the road surface, the shape detected by laser during the paving process, and the shape at the current position predicted at the previous position, and adjusts the paving shape of the paver along the width direction of the road surface according to the thickness corresponding to the target shape. In this way, it can ensure that the shape of the road surface matches the designed shape, while taking into account the error between the actual construction and the designed shape, ensuring that the construction process can proceed smoothly. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a flow chart of the overall steps of the present invention;
[0027] Figure 2 is a flowchart of step S7 of the method proposed by the present invention;
[0028] Figure 3 It is a schematic diagram of the installation structure of the scraper proposed by the present invention.
[0029] Description of reference numerals:
[0030] 1-scraper, 2-first adjustment rod, 3-second adjustment rod;
[0031] 11-Mounting hole;
[0032] 31-first limiting portion, 32-first limiting portion. DETAILED DESCRIPTION
[0033] The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, but should not be construed as limiting the present invention.
[0034] In order to solve the problems in the prior art, the present invention proposes the following embodiments to solve the problems.
[0035] Embodiment 1,
[0036] Please refer to Figure 1 and Figure 2This embodiment provides a road paving control method based on laser measurement, which includes the following steps:
[0037] S1, establish a three-dimensional coordinate system in the vertical plane with the starting position as the origin. Specifically, establish a coordinate system (x, y, z) with the center line of the road surface width direction at the starting point as the origin, the road surface width direction at the starting point as the horizontal axis, the vertical direction as the vertical axis, and the line passing through the origin and perpendicular to the horizontal and vertical axes as the vertical axis.
[0038] S2, determine the relationship between the road surface height along the paving direction and the road surface width direction; specifically, the relationship between the road surface height along the paving direction and the road surface width direction refers to a coordinate system within the coordinate system (x, y, z). When the original coordinate system in which the relationship between the determined road surface height along the paving direction and the road surface width direction is located is not the newly established coordinate system (x, y, z), it is necessary to transform the relationship into the coordinate system (x, y, z) established in step S1.
[0039] In specific implementation, the relationship between the height along the paving direction and the road width direction is determined by the design size of the road surface. In some implementations, it can be determined by the relationship corresponding to the road surface determined during design, or it can be determined based on the three-dimensional model of the road surface. For example, multiple points can be extracted from the road surface of the designed three-dimensional model, and the multiple points extracted from the road surface can be fitted to obtain the relationship between the height along the paving direction and the road width direction.
[0040] S3, real-time measurement of the horizontal distance between the current paving position and the starting position. In specific implementation, the horizontal distance measured in step S3 is the length of the center line of the road surface. That is, in this step, the distance between the paving position and the starting position measured is not a straight-line distance, but a distance along the center line of the road surface length direction. In specific implementation, the horizontal distance can be determined by calculating the distance traveled by the center of the paver from the starting position to the current paving position.
[0041] S4, calculate the first height equation in the road width direction at the current paving position; in specific implementation, the first height equation is the relationship between the road design height and the road width at the current paving position. Specifically, the first height equation is determined by the relationship determined during the design. Specifically, first project the relationship corresponding to the road surface determined during the design onto the XOY plane to obtain the projection point corresponding to the center of the current paver, and the projection line of the center line of the paver parallel to the road width direction on the XOY plane, and make a vertical plane perpendicular to the XOY plane through the projection line. The intersection line of the vertical plane and the road surface is the first height equation. The first height equation represents the theoretical shape of the current paving position in the road width direction according to the designed road surface. In specific implementation, the first height equation is recorded as z=f1(x, y).
[0042] S5, perform 3D laser measurement on the paving surface within a certain distance before the current paving position; obtain point cloud data; wherein the point cloud data includes the elevation of each measurement point. In this step, the purpose is to restrict the current paving shape by the shape of the paved road surface, so as to make the road surface more continuous and ensure the smoothness of the road surface. In the specific implementation, the paved road data is obtained by 3D laser.
[0043] S6, modeling the point cloud data, and obtaining the second height equation of the current position and the third height equation of the next position according to the model; in specific implementation, in order to process the point cloud data, the point cloud data can be uploaded to the server, and the point cloud can be processed by the software deployed in the server. The processing content includes deleting abnormal points and using the point cloud data for three-dimensional modeling. In specific implementation, the point cloud data can also be directly used for fitting to obtain the equation z=f2(x,y); obtain the second equation corresponding to the road surface height value corresponding to the current paving position, z=f2'(x,y). In specific implementation, the current paving position is projected in the XOY plane, and the elevation in the point cloud data corresponding to the obtained projection line is the equation z=f2'(x,y). In specific implementation, assuming that the current moment is moment t, and the next moment is moment t+1, at moment t, two equations will be obtained through the point cloud data, namely, the second height equation for characterizing the paving position corresponding to moment t and the third height equation for characterizing the paving position corresponding to moment t+1. Among them, the third height equation is an equation formed by the cloud, and the height equation at time t+1 corresponding to this equation is the third height equation corresponding to time t. Correspondingly, at time t-1, the third height equation corresponding to the paving position at time t can be obtained. That is, at the paving position corresponding to time t, two equations for characterizing the pavement shape at the paving position at time t can be obtained through point cloud data, namely, the second equation corresponding to the paving position at time t and the third equation of the paving position at time t predicted at time t-1. Therefore, at each moment, two equations can be obtained through point cloud data, the second equation at the current moment and the third equation at the previous moment, and the third equation at the previous moment is recorded as z=f3'(x,y).
[0044] S7, according to the first height equation of the current position, the second height equation and the third height equation of the previous position, the fourth height equation is determined by weighted summation; in order to ensure that paving can be carried out according to the designed shape and to ensure a certain accuracy, the first height equation, the second height equation and the third height equation of the previous position are fully utilized to obtain the fourth height equation, so that the paving shape can be controlled by the fourth height equation.
[0045] Specifically, the fourth height equation is:
[0046] z=a0f1(x,y)+a1f2'(x,y)+a3f3(x,y); where a0+a1+a2=1.
[0047] Theoretically, the ranges of the independent variables corresponding to the first height equation, the second height equation, and the third height equation should be consistent, but due to the existence of errors, the ranges of the independent variables will be different. Therefore, it is necessary to judge the errors of the first height equation, the second height equation, and the third height equation.
[0048] That is, step S7 specifically includes the following steps:
[0049] S71, converting the second height equation and the third height equation into the three-dimensional coordinate system; since the first height equation is originally in the three-dimensional coordinate system, through this step, the first height equation and the second height equation can be in the same coordinate system.
[0050] S72, the first height equation and the third height equation are corrected and judged based on the second height equation, and weighted summation is performed according to the judgment result. In specific implementation, the independent variable range corresponding to the second height equation is the points on a straight line, and the straight line is the projection of the current paving position on the XOY plane. That is, it can be considered that for the first height equation, its independent variable range is, y = k1x + b1, where, For the second height equation, the range of its independent variables is y=k2x+b2, where For the third height equation, the range of its independent variables is y=k3x+b3, where: That is, the range of the independent variable corresponds to a set of points on a line segment on the XOY plane, and the line segment represents the projection of the current paving in the XOY plane.
[0051] Due to construction errors and equipment accuracy issues, the independent variable ranges corresponding to the first height equation, the second height equation, and the third height equation are different. Therefore, the first height equation, the second height equation, and the third height equation need to be transformed. Since the second height equation reflects the actual paving position of the paver, the first height equation and the third height equation can be transformed based on the independent variable range of the second height equation, and the first height equation and the third height equation can be transformed to the projection line segment corresponding to the current position of the paver in the XOY plane.
[0052] In the specific implementation, due to the accumulation of construction errors and the existence of equipment errors, specifically, the independent variable range of the first height equation and the independent variable range of the third height equation are judged respectively with the independent variable range of the second height equation. When the independent variable range of the first height equation and the independent variable range of the third height equation are both smaller than the first deviation, weighted summation is performed according to the set weight;
[0053] When the deviation between the independent variable range of the first height equation and the independent variable range of the second height equation is greater than the first deviation, the weight of the first height equation is reduced and a weighted sum is performed; when the deviation between the independent variable range of the third height equation and the second height equation and the independent variable range is greater than the first deviation, the weight of the third height equation is reduced and a weighted sum is performed. In practical applications, when the errors corresponding to the first height equation, the second height equation and the third height equation are too large, adjustments need to be made. Specifically, in this embodiment, correction judgment can be made through [x′1, x″1] corresponding to the first height equation, [x'2, x″2] corresponding to the second height equation, and [x'3, x″3] corresponding to the third height equation.
[0054] Specifically, the modified judgment formula is: and When at least one of the above formulas is satisfied, it indicates that the error is large and needs further adjustment. Specifically, when and When , the weight a0 needs to be reduced. Specifically, a0 can be transformed into Accordingly, a1 and a2 increase in equal proportion; that is, Likewise, when and When the weight a3 is reduced, the weight a2 can be transformed into Correspondingly, a0 and a1 increase in equal proportion. That is, When satisfied and When , it means that the error is small and the weighted sum can be directly performed. The weights used at this time are a0, a1 and a2. In a specific implementation, in a preferred implementation, the value of a0 is 0.3, the value of a1 is 0.4, and the value of a2 is 0.3.
[0055] S8, adjusting the paving shape of the paver along the width direction of the road surface according to the fourth height equation.
[0056] In specific implementation, the fourth height equation is the shape of the road surface at the current paving position, and the paver has a certain height. In order to accurately determine the paving thickness, it is also necessary to determine the height of the base surface before paving in the three-dimensional coordinates. In specific implementation, it can be determined by measuring the fourth height equation corresponding to the base surface to be paved. Specifically, the fourth height equation minus the corresponding base surface height is the paving thickness. In specific implementation, it can be used to judge whether the paving height meets the requirements. When the paving thickness does not meet the requirements, or the changing trend of the paving thickness will lead to the paving thickness at a certain moment in the future, the current paving thickness is adjusted in a smooth transition manner to change the changing trend of the current paving thickness. In the case of continuous changes in the road surface, ensure that the paving thickness meets the conditions.
[0057] Embodiment 2
[0058] This embodiment is a further improvement on the first embodiment, and the similarities are not repeated here, and only the differences are described below.
[0059] Please refer to Figure 3 This embodiment provides an adjustable scraper 1 for the method described in the first embodiment, so as to adjust the paving shape by adjusting the shape of the scraper 1 along the width direction of the road surface.
[0060] The scraper 1 is a long strip of metal plate. In a specific implementation, the long strip of metal plate is integrally formed. The thickness of the scraper 1 is not more than 3 cm, preferably 1 cm. The length of the scraper 1 is equal to the width of the road surface to be paved, and compensation plates are provided at both ends of the scraper 1. The scraper 1 is provided with a plurality of height adjustment rods along its length direction. By adjusting the vertical position of the height adjustment rods, the purpose of adjusting the shape of the scraper 1 along its length direction can be achieved; when the middle part of the scraper 1 is bent upward or downward, the distance between the two ends of the scraper 1 will become smaller, and the two ends are scraped flat by the compensation plate.
[0061] In a specific implementation, in order to ensure that the scraper 1 can exert a certain pressure on the road surface, the upper side of the scraper 1 is connected to the paver through a plurality of elastic members.
[0062] In a specific implementation, the number of adjustment rods is an odd number, one of which is located at the center of the length direction of the scraper 1, and is recorded as the first adjustment rod 2, and the other adjustment rods are recorded as the second adjustment rods 3. The first adjustment rod 2 and the second adjustment rod 3 are evenly distributed along the length direction of the scraper 1, and there is a certain amount of sliding between the other adjustment rods and the scraper 1, that is, the other adjustment rods have a sliding amount of 100-200 mm along the length direction of the scraper 1. Since the scraper 1 usually has a length ranging from several meters to more than ten meters, a certain curvature can be formed along its length direction.
[0063] The scraper 1 is provided with a mounting hole 11 corresponding to the second adjustment position, and the mounting hole 11 is a strip-shaped hole. The second adjustment rod 3 is provided with a first limiting portion 31 and a second limiting portion 32. The second adjustment rod 3 passes through the corresponding mounting hole 11, and the first limiting portion 31 and the second limiting portion 32 abut against the side surfaces at both ends of the mounting hole 11. In order to prevent concrete from entering the mounting hole 11, the first limiting portion 31 and the second limiting portion 32 can be arranged so that when the second adjustment rod 3 is located at any position corresponding to the mounting hole 11, the first limiting portion 31 and the second limiting portion 32 can both block the mounting hole 11 from both ends.
[0064] In the straight state, the second adjusting rod 3 is tangent to the side of the corresponding mounting hole 11 close to the first adjusting rod 2. In the straight state, the center lines of the first adjusting rod 2 and the second adjusting rod 3 are basically located in the same plane, and the scraper 1 is in a horizontal state. When it is necessary to adjust the shape according to the fourth equation, the shape is adjusted by controlling the relative height of the first adjusting rod 2 and the second adjusting rod 3, and the paving thickness is adjusted by synchronously controlling the relative height of the first adjusting rod 2 and the second adjusting rod 3. When adjusting the shape of the scraper 1, the second adjusting rod 3 slides in the corresponding mounting hole 11 along the length direction of the scraper 1.
[0065] The above describes in detail the structure, features and effects of the present invention based on the embodiments shown in the drawings. The above is only a preferred embodiment of the present invention, but the present invention is not limited to the scope of implementation shown in the drawings. Any changes made according to the concept of the present invention, or modifications to equivalent embodiments with equivalent changes, which still do not exceed the spirit covered by the description and drawings, should be within the protection scope of the present invention.
Claims
1. A road paving control method based on laser measurement, characterized in that: The following steps are included: S1, establish a three-dimensional coordinate system in the vertical plane with the starting position as the origin; S2, determine the relationship between the road surface height along the paving direction and the road surface width direction; S3, real-time measurement of the horizontal distance between the current paving position and the starting position; S4, calculating a first height equation in the road width direction at the current paving position; S5, performing three-dimensional laser measurement on the paving surface within a certain distance in front of the current paving position to obtain point cloud data; wherein the point cloud data includes the elevation of each measurement point; S6, modeling the point cloud data, and obtaining a second height equation of the current position and a third height equation of the next position according to the model; S7, determining a fourth height equation by weighted summation according to the first height equation at the current position, the second height equation and the third height equation at the previous position; S8, adjusting the paving shape of the paver along the width direction of the road surface according to the fourth height equation.
2. The road paving control method based on laser measurement according to claim 1, characterized in that: The relationship in step S2 is determined by the design dimensions of the road surface.
3. The road paving control method based on laser measurement according to claim 2 is characterized in that: In step S3, the starting position is the center of the paving starting position; the horizontal distance measured in step S3 is the length of the center line of the road surface.
4. The road paving control method based on laser measurement according to claim 3 is characterized in that: The first height equation, the second height equation, the third height equation and the fourth height equation are all relationship equations of height along the width direction of the road surface.
5. The road paving control method based on laser measurement according to claim 2, characterized in that: The relationship between the road surface height along the paving direction and the road surface width direction determined in step S2 is determined by the surface equation during design or is formed by fitting the coordinates of multiple points on the road surface.
6. The road paving control method based on laser measurement according to claim 2 is characterized in that: In step S7, before performing weighted summation, the second height equation and the third height equation are converted into the three-dimensional coordinate system.
7. The road paving control method based on laser measurement according to claim 6 is characterized in that: Step S7 also includes, before weighted summation, correcting and judging the first height equation and the third height equation converted to the same coordinate system based on the second height equation, and performing weighted summation according to the judgment result.
8. The road paving control method based on laser measurement according to claim 6, characterized in that: The independent variable range of the first height equation and the independent variable range of the third height equation are respectively judged with the independent variable range of the second height equation. When the independent variable range of the first height equation and the independent variable range of the third height equation are both smaller than the first deviation, weighted summation is performed according to the set weight; when the deviation between the independent variable range of the first height equation and the independent variable range of the second height equation is greater than the first deviation, the weight of the first height equation is reduced and weighted summation is performed; when the deviation between the independent variable range of the third height equation and the second height equation and the independent variable range is greater than the first deviation, the weight of the third height equation is reduced and weighted summation is performed.
9. The road paving control method based on laser measurement according to any one of claims 1 to 8, characterized in that: In step S8, the paving shape is adjusted by adjusting the shape of the scraper (1) along the road width direction; The scraper (1) is a long strip of metal plate. The scraper (1) is provided with a plurality of height adjustment rods along its length direction. By adjusting the vertical positions of the height adjustment rods, the purpose of adjusting the shape of the scraper (1) along its length direction is achieved. The upper side of the scraper (1) is connected to the paver via a plurality of elastic members.