By setting up a combined structure of reinforced concrete layer and thermal insulation layer on the roof, the problem of easy falling off of the building thermal insulation layer is solved, the structural strength and waterproofing effect are improved, the service life is extended and safety risks are reduced.

CN119062075APending Publication Date: 2024-12-03JIANGSU GUANGYUE ENERGY SAVING TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411456858.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-18
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

The problem of building insulation and thermal insulation layers being prone to fall off has threatened the safety and service life of the building, and it affects energy efficiency and living comfort.

Method used

By setting up a reinforced concrete layer on the roof and placing the insulation layer between the base layer and the reinforced concrete layer, combining structures such as limit reversal, flow holes and tiles, the bonding strength is enhanced and the fall off is prevented.

Benefits of technology

It effectively reduces the possibility of breaking and falling off of the insulation layer due to temperature difference, corrosion and other reasons, extends its service life, improves the overall strength and waterproofing effect of the building, and avoids property losses and personal injury.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119062075A_ABST
    Figure CN119062075A_ABST
Patent Text Reader

Abstract

The invention provides a roof heat preservation structure and a preparation method, relates to the technical field of building construction, and mainly aims to improve the mounting firmness of a heat preservation and insulation layer and reduce the possibility that the heat preservation and insulation layer falls off. The roof heat preservation structure comprises a base layer, a reinforced concrete layer and a heat preservation and insulation layer, the reinforced concrete layer is located above the base layer, and the heat preservation and insulation layer is arranged between the base layer and the reinforced concrete layer in an overlapped mode and connected with the base layer and the reinforced concrete layer. The base layer comprises a structural layer and a waterproof layer, and the waterproof layer is located between the structural layer and the heat preservation and insulation layer. According to the built-in heat preservation and insulation layer structure and the preparation method thereof, the installation firmness of the heat preservation and insulation layer is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a roof insulation structure and a preparation method thereof. Background Art

[0002] In the field of modern construction, the quality of thermal insulation plays a vital role in the energy efficiency and living comfort of buildings. With the continuous improvement of people's requirements for energy conservation and environmental protection, building insulation technology has been widely used. The main purpose of building insulation is to reduce the heat transfer inside and outside the building and reduce energy consumption. By installing thermal insulation materials on the exterior walls, roofs and other parts of the building to form an insulation layer, heat loss can be effectively blocked, so that the room remains warm in winter and cool in summer. Common insulation materials include polystyrene boards, rock wool, glass wool, etc. These materials have good thermal insulation properties and low thermal conductivity.

[0003] However, in actual application, the thermal insulation layer of buildings is prone to falling off. This problem poses a serious threat to the safety and service life of the building. There are many reasons for the falling off of the thermal insulation layer. On the one hand, the quality of thermal insulation materials varies. Some inferior thermal insulation materials are prone to aging and deformation during use, which leads to a decrease in the bonding strength with the base wall and eventually falls off. On the other hand, irregular operations during construction are also an important reason for the falling off of the thermal insulation layer. For example, improper treatment of the base wall, insufficient use of adhesives, and loose fixation of the insulation board may cause the thermal insulation layer to fall off in the future. In addition, the impact of the natural environment cannot be ignored. Long-term exposure to wind, sun, rain, snow, and frost will gradually age and damage the thermal insulation material, thereby reducing its bonding strength with the wall and increasing the risk of falling off.

[0004] The shedding of thermal insulation layer will not only affect the appearance and thermal insulation performance of the building, but also may threaten the safety of pedestrians. Therefore, how to solve the problem of easy shedding of thermal insulation layer has become an important issue facing the current construction industry. Summary of the invention

[0005] The object of the present invention is to provide a roof insulation structure and a preparation method to solve at least one of the above-mentioned technical problems, improve the installation firmness of the thermal insulation layer, and reduce the possibility of the thermal insulation layer falling off.

[0006] To achieve the above object, the present invention provides the following technical solutions: The invention provides a roof insulation structure, comprising a base layer, a reinforced concrete layer and a thermal insulation layer, wherein the reinforced concrete layer is located above the base layer; the thermal insulation layer is stacked between the base layer and the reinforced concrete layer and is connected to the base layer and the reinforced concrete layer respectively.

[0007] In the technical solution provided by the present invention, by adjusting the position of the thermal insulation layer so that it is located between the base layer and the reinforced concrete layer, the possibility of damage and falling off of the thermal insulation layer due to temperature difference, corrosion and the like during the use of the building is effectively reduced, thereby avoiding property loss and personal injury caused by the falling off of the thermal insulation layer.

[0008] Based on the above technical solution, the present invention can also be improved as follows.

[0009] As a further improvement of the present invention, it also includes a limiting anti-ridge located on the base layer, the limiting anti-ridge is connected to the thermal insulation layer and the reinforced concrete layer, and is used to limit the reinforced concrete layer and the thermal insulation layer in the circumferential direction.

[0010] As a further improvement of the present invention, at least two guide holes are provided on the limit anti-step, and the guide holes are used to connect the thermal insulation layer with the external environment.

[0011] As a further improvement of the present invention, the reinforced concrete layer includes an inclined top wall that is at least partially inclined, and at least part of the limiting anti-step is arranged near an end of the inclined top wall that is inclined downward.

[0012] As a further improvement of the present invention, an airtightness detection hole is provided in the reinforced concrete layer.

[0013] As a further improvement of the present invention, the reinforced concrete layer includes a steel mesh and a degradable tube, and the degradable tube is arranged on the steel mesh to form the airtight detection hole.

[0014] As a further improvement of the present invention, a baffle is laid between the reinforced concrete layer and the thermal insulation layer.

[0015] As a further improvement of the present invention, it also includes tiles located on the side of the reinforced concrete layer facing away from the thermal insulation layer.

[0016] As a further improvement of the present invention, the base layer includes a structural layer and a waterproof layer, and the waterproof layer is located between the structural layer and the thermal insulation layer.

[0017] As a further improvement of the present invention, the waterproof layer includes a pipeline for vacuum detection.

[0018] The present invention also provides a method for preparing a roof insulation structure, which is used to prepare any of the above-mentioned roof insulation structures, comprising: preparing a reinforced concrete layer outside the base layer of the roof, and forming a thermal insulation layer between the reinforced concrete layer and the base layer.

[0019] As a further improvement of the present invention, the thermal insulation layer is a vacuum sealed cavity.

[0020] As a further improvement of the present invention, the thermal insulation layer is filled with a thermal insulation component, and the thermal insulation component includes at least one of a thermal insulation board and a foaming material.

[0021] Compared with the prior art, the roof insulation structure provided by the preferred embodiment of the present invention can effectively improve the structural strength of the insulation layer by adjusting the insulation layer to be located between the base layer and the reinforced concrete layer, realize the built-in insulation layer, reduce the possibility of the insulation layer being damaged or falling off due to temperature difference, corrosion and other reasons during the use of the building, and avoid property loss and personal injury caused by the falling off of the insulation layer. In order to further improve the bonding strength between the above-mentioned insulation layer and the base layer, the above-mentioned limit anti-ridge can also be provided with a diversion hole, and during construction, the arrangement space for arranging the insulation layer is pre-occupied by sand beads and the like, and a limit anti-ridge and a baffle are arranged outside it to facilitate the preparation of the reinforced concrete layer, and after the preparation of the reinforced concrete layer is completed, the occupying sand beads are discharged through the diversion hole, and after the sand beads are discharged, light foam concrete is injected into the corresponding space through the diversion hole to form the above-mentioned insulation layer, and at this time, the insulation layer can be more firmly combined with the base layer. By arranging a degradable tube in the reinforced concrete layer during processing, an airtightness detection hole for detecting airtightness can be formed in the prepared reinforced concrete layer, so as to further improve the waterproof sealing effect of the roof. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0023] Figure 1 It is a structural schematic diagram of a certain embodiment of the roof insulation structure provided by the present invention; Figure 2 yes Figure 1 Schematic diagram of the cross-sectional structure of the reinforced concrete layer; Figure 3A yes Figure 1 A schematic diagram of the structure in the first state during the processing; Figure 3B yes Figure 1 A schematic diagram of the structure in the second state during the processing; Figure 4 yes Figure 1 A schematic diagram of the structure of the limit anti-ridge in FIG. Figure 5 It is a structural schematic diagram of another embodiment of the roof insulation structure provided by the present invention.

[0024] In the figure: 1. Base layer; 11. Structural layer; 12. Waterproof layer; 2. Reinforced concrete layer; 21. Inclined top wall; 22. Air tightness detection hole; 3. Thermal insulation layer; 4. Limiting anti-ridge; 41. Diversion hole; 5. Baffle; 6. Tile; 7. Placeholder material. DETAILED DESCRIPTION

[0025] To make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be described in detail below. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other implementation methods obtained by ordinary technicians in this field without creative work belong to the scope of protection of the present invention.

[0026] In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", "third", etc., are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.

[0027] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.

[0028] The present invention provides a roof insulation structure, comprising a base layer 1, a reinforced concrete layer 2 and a thermal insulation layer 3, wherein the reinforced concrete layer 2 is located above the base layer 1; the thermal insulation layer 3 is stacked between the base layer 1 and the reinforced concrete layer 2 and is connected to the base layer 1 and the reinforced concrete layer 2 respectively.

[0029] The above-mentioned roof can be a flat roof or a sloping roof.

[0030] Specifically, in some embodiments, the above-mentioned reinforced concrete layer 2 includes an inclined top wall 21 that is at least partially inclined. At this time, the thickness of the above-mentioned reinforced concrete layer 2 at different positions can remain consistent or different; accordingly, the surface of the side of the base layer 1 of the roof with the above-mentioned inclined top wall 21 close to the reinforced concrete layer 2 can be a plane or an inclined surface, and this embodiment does not limit it.

[0031] See also Figure 1 , Figure 1 It is a structural schematic diagram of a certain embodiment of the roof insulation structure provided by the present invention.

[0032] In this embodiment, by adjusting the position of the thermal insulation layer 3 so that it is located between the base layer 1 and the reinforced concrete layer 2, the possibility of damage or falling off of the thermal insulation layer 3 due to temperature difference, corrosion, etc. during the use of the building is effectively reduced, thereby avoiding property loss and personal injury caused by the falling off of the thermal insulation layer 3.

[0033] The above-mentioned reinforced concrete layer 2 can provide effective physical protection for the thermal insulation layer 3, preventing the thermal insulation layer 3 from being damaged by natural factors such as external force impact, wind and rain, and ultraviolet radiation, which helps to extend the service life of the thermal insulation layer 3; it can also prevent the thermal insulation layer 3 from being damaged by accidents such as animal destruction and human trampling.

[0034] In addition to the above effects, the reinforced concrete layer 2 outside the thermal insulation layer 3 can also increase the overall strength and rigidity of the roof to a certain extent, improve the bearing capacity of the roof, and especially for a roof with a certain slope, better resist the gravity component and other external forces on the slope, and reduce the risk of deformation and cracking of the roof. At this time, the above-mentioned reinforced concrete layer 2 can provide a relatively stable working platform for the maintenance and renovation of the roof. When it is necessary to repair the roof, replace equipment or carry out other renovation projects, the reinforced concrete layer 2 can bear the weight of construction personnel and equipment, which is convenient for construction operations.

[0035] In addition, the reinforced concrete layer 2 can also serve as an auxiliary waterproof layer 12, and work together with other waterproof structures of the roof (such as the waterproof layer 12, etc.) to enhance the waterproof effect of the roof. Even if the main waterproof layer 12 is partially damaged in some parts, the reinforced concrete layer 2 can prevent moisture from penetrating into the thermal insulation layer 3 and the room to a certain extent, reducing the possibility of leakage.

[0036] As a further improvement of the present invention, it also includes tiles 6 located on the side of the reinforced concrete layer 2 facing away from the thermal insulation layer 3.

[0037] A plurality of tiles 6 can be laid on the roof in an overlapping manner, that is, the side of the reinforced concrete layer 2 facing away from the thermal insulation layer 3 , including the inclined top wall 21 .

[0038] The tile 6 has a certain waterproof effect, which can effectively prevent rainwater, snow water, etc. from invading the roof, protect the internal structure of the house from water erosion, and help guide rainwater, etc. to drain smoothly from the roof; in addition, the tile 6 also has a certain heat insulation performance, which can reduce the solar radiation heat entering the room in summer and reduce the indoor temperature; at the same time, it can also play a certain insulation role in winter and reduce the loss of indoor heat. In addition to the above effects, the tile 6 also has a certain decorative effect, which improves the overall appearance quality of the building and makes the house more distinctive and individual; the tile 6 can also withstand certain external force impacts, help protect the roof structure, such as branches blown down by the wind, hail, etc., and protect the roof base 1, thermal insulation layer 3 and reinforced concrete layer 2 from damage.

[0039] In some embodiments, the thickness of the reinforced concrete layer 2 is about 80 mm.

[0040] The reinforced concrete layer 2 is made of a mixture of steel bars and concrete. During preparation, a steel mesh can be bundled at a corresponding position as needed, and then concrete is poured to form the reinforced concrete layer 2.

[0041] The prepared reinforced concrete layer 2 can cooperate with the base layer 1 to form an upper and lower concrete structure layer 11 whose air tightness meets the requirements of building construction, and the thermal insulation layer 3 is located between the two.

[0042] In some embodiments, at least part of the side of the reinforced concrete layer 2 facing away from the base layer 1 forms the inclined top wall 21. According to the shape of the roof, when the roof is entirely sloped, the side of the reinforced concrete layer 2 facing away from the base layer 1 is entirely the inclined top wall 21; when only part of the roof is sloped, part of the side of the reinforced concrete layer 2 facing away from the base layer 1 is the inclined top wall 21 and part is the horizontal top wall. This embodiment does not limit the distribution region and distribution area of ​​the inclined top.

[0043] In order to facilitate the pouring preparation of the above-mentioned reinforced concrete layer 2, in some embodiments, a baffle 5 is laid between the above-mentioned reinforced concrete layer 2 and the thermal insulation layer 3. Figure 1 .

[0044] In addition, in this embodiment or other similar embodiments, the roof insulation structure also includes a limiting anti-step 4 located on the base layer 1, and the limiting anti-step 4 is connected to the thermal insulation layer 3 and the reinforced concrete layer 2, and is used to limit the reinforced concrete layer 2 and the thermal insulation layer 3 in the circumferential direction.

[0045] The above-mentioned limiting anti-ridge 4 can be used as a slurry retaining plate, which can not only help to withstand the lateral pressure of concrete poured on the roof slope, but also provide a certain stopping effect on the concrete, help block the concrete, and prevent the concrete from overflowing from the area to be poured during the pouring process.

[0046] As a further improvement of the present invention, the limiting anti-ridge 4 is located on one side of the reinforced concrete layer 2 in the circumferential direction, and the limiting anti-ridge 4 is arranged close to one end of the inclined top wall 21 which is inclined downward.

[0047] In some embodiments, the reinforced concrete layer 2 obtained by pouring is provided with an airtight detection hole 22. The structure of the airtight detection hole 22 can be found in Figure 2 The airtight detection hole 22 is used to cooperate with the waterproof monitoring system disclosed in the related art.

[0048] Specifically, a vacuum detection sensor can be installed outside the airtight detection hole 22. When in use, in addition to realizing the sealing and waterproofing construction of the reinforced concrete layer 2 during construction, the corresponding detection equipment can also be used to realize the long-term monitoring and detection of the waterproofing effect of the construction joint formed in the reinforced concrete layer 2.

[0049] The processing technology of construction joints is existing technology and will not be described in detail here.

[0050] In some embodiments, the reinforced concrete layer 2 includes a steel mesh and a degradable tube, and the degradable tube is arranged on the steel mesh to form an airtight detection hole 22.

[0051] The above-mentioned degradable tube can be naturally degraded after the concrete poured outside the steel mesh solidifies for a certain period of time, thereby forming the above-mentioned airtightness detection hole 22 for detecting the airtightness of the reinforced concrete layer 2. The above-mentioned airtightness detection hole 22 is a hollow tubular structure extending into the reinforced concrete layer 2, and one end thereof extending to the surface of the reinforced concrete layer 2 is a hole-shaped structure, and the hole-shaped structure is used to install airtightness detection equipment, such as a vacuum detection sensor, etc.

[0052] In some embodiments, in order to improve the bonding strength between the thermal insulation layer 3 and the base layer 1 and the reinforced concrete layer 2 , the thermal insulation layer 3 is prepared after the reinforced concrete layer 2 .

[0053] Specifically, at least two guide holes 41 are provided on the limiting anti-step 4, and the guide holes 41 are used to connect the thermal insulation layer 3 with the external environment.

[0054] During actual construction, the above-mentioned limiting anti-step 4 with the guide hole 41 can be first set at the corresponding position of the base layer 1, and the limiting anti-step 4 is fixedly set on the base layer 1. Subsequently, the place-occupying material 7 (the place-occupying material 7 can be sand beads, river sand, etc.) is evenly laid on the corresponding surface of the roof for setting the thermal insulation layer 3, and the laying thickness of the place-occupying material 7 is the thickness of the thermal insulation layer 3. The baffle 5 is laid on the surface of the place-occupying material 7, and then the steel mesh is tied on the baffle 5, the degradable pipe is laid on the steel mesh, and then the concrete is poured. After the reinforced concrete layer 2 is prepared, the above-mentioned roof structure is as follows Figure 3AAs shown, the air tightness of the base layer 1 and the reinforced concrete layer 2 located on both sides of the thickness direction of the placeholder material 7 meet the design requirements. Subsequently, the placeholder material 7 laid in the previous construction can be discharged by opening the diversion hole 41 provided on the limit anti-ridge 4. Please refer to Figure 3B .

[0055] It should be noted that the above-mentioned guide hole 41 is arranged opposite to the place-occupying material 7 , and the guide hole 41 is always in a closed state before the place-occupying material 7 needs to be discharged.

[0056] In actual use, the guide hole 41 can be used to discharge the placeholder material 7. After the placeholder material 7 is discharged, a cavity structure is formed between the base layer 1 and the reinforced concrete layer 2. Figure 3B At this time, the guide hole 41 can be used for the operator to inject the foaming material into the cavity structure to form the thermal insulation layer 3.

[0057] Specifically, the structure of the above-mentioned limit anti-ridge 4 is as follows Figure 4 As shown, the number of the guide holes 41 on any one of the limiting anti-ridges 4 is 2-3. The number of the guide holes 41 and the distance between two adjacent guide holes 41 can be adjusted according to actual needs.

[0058] In some embodiments, the foaming material used to form the thermal insulation layer 3 may be rigid foam polyurethane, or other similar materials disclosed in related technologies. After the foaming material is injected into the cavity structure, it will form light foam concrete, and finally solidify to form the thermal insulation layer 3.

[0059] Rigid polyurethane foam has an extremely low thermal conductivity, generally between 0.020 - 0.024W / (m・K), which can effectively prevent the transfer of heat and greatly reduce the energy consumption of buildings. Rigid polyurethane foam also has good waterproof properties. Rigid polyurethane foam itself has a certain degree of waterproofness, and its closed-cell structure can prevent water penetration and avoid the decline of thermal insulation performance due to water intrusion; when used in combination with roof waterproofing membranes, it can form an integrated waterproof and thermal insulation system to improve the waterproof effect of the roof.

[0060] In some embodiments, the base layer 1 includes a structural layer 11 and a waterproof layer 12, and the waterproof layer 12 is located between the structural layer 11 and the thermal insulation layer 3. Figure 5 .

[0061] At this time, the thermal insulation layer 3 composed of rigid foam polyurethane can better cooperate with the waterproof layer 12 to further improve the waterproof effect of the roof slope.

[0062] As a further improvement of the present invention, the waterproof layer 12 includes a vacuum detection pipeline. The vacuum detection pipeline can be matched with the vacuum detection technology disclosed in the relevant technology to realize the detection and real-time monitoring of the waterproof effect of the waterproof layer 12, and provide data support for the detection and repair of the waterproof layer 12.

[0063] It can be understood that the roof insulation structure provided by the embodiment of the present invention can effectively improve the structural strength of the thermal insulation layer 3 by adjusting the thermal insulation layer 3 to be located between the base layer 1 and the reinforced concrete layer 2, realize the internalization of the thermal insulation layer 3, and reduce the possibility of damage and falling off of the thermal insulation layer 3 due to temperature difference, corrosion and the like during the use of the building, thereby avoiding property loss and personal injury caused by the falling off of the thermal insulation layer 3. In order to further improve the bonding strength between the thermal insulation layer 3 and the base layer 1, the above-mentioned limiting anti-ridge 4 can also be provided with a guide hole 41. During construction, the arrangement space for arranging the thermal insulation layer 3 is pre-occupied by sand beads or the like, and the limiting anti-ridge 4 and the baffle 5 are arranged outside it, so as to prepare the reinforced concrete layer 2; after the reinforced concrete layer 2 is prepared, the place-occupying material 7 is discharged through the guide hole 41, and after the place-occupying material 7 is discharged, light foam concrete is injected into the corresponding space through the guide hole 41 to form the above-mentioned thermal insulation layer 3. At this time, the thermal insulation layer 3 can be more firmly combined with the base layer 1. The above-mentioned reinforced concrete layer 2 can be formed with an airtightness detection hole 22 for detecting airtightness in the prepared reinforced concrete layer 2 by setting a degradable tube during processing, so as to further improve the waterproof sealing effect of the roof.

[0064] The present invention also provides a method for preparing a roof insulation structure, which is used to prepare any of the above-mentioned roof insulation structures, comprising: preparing a reinforced concrete layer 2 outside a base layer 1 of the roof, and forming a thermal insulation layer 3 between the reinforced concrete layer 2 and the base layer 1.

[0065] Specifically, the thermal insulation layer 3 may be a chamber structure filled with an appropriate amount of placeholder material 7, or may be a vacuum sealed chamber. The vacuum sealed chamber may be a vacuum chamber formed by vacuuming with negative pressure after the placeholder material 7 is discharged. After the vacuum chamber has been used for a certain period of time and has failed due to air leakage, a foaming material or the like may be injected into the chamber to fill the cavity formed by the vacuum sealed chamber to form a solid thermal insulation layer 3, thereby realizing secondary repair of the thermal insulation layer 3.

[0066] In other embodiments, the thermal insulation layer 3 may be provided by prefabricated thermal insulation panels filled in the corresponding spaces. Compared with other processing methods, this method can save the use of the placeholder material 7 and the discharge operation, which can greatly improve the preparation efficiency.

[0067] Furthermore, insulation material can be injected into the above-mentioned cavity with the prefabricated insulation board to fill the gaps formed between the prefabricated insulation board, the base layer 1 and the reinforced concrete layer 2, so as to further improve the bonding strength between the thermal insulation layer 3 and the base layer 1 and the reinforced concrete layer 2, and improve the sealing and sealing effect of the thermal insulation layer 3.

[0068] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A roof insulation structure, characterized in that: include: Grassroots; A reinforced concrete layer located above the base layer; The thermal insulation layer is stacked between the base layer and the reinforced concrete layer and is connected to the base layer and the reinforced concrete layer respectively.

2. The roof insulation structure according to claim 1, characterized in that: It also includes a limiting anti-ridge located on the base layer, the limiting anti-ridge is connected to the thermal insulation layer and the reinforced concrete layer, and is used to limit the reinforced concrete layer and the thermal insulation layer in the circumferential direction.

3. The roof insulation structure according to claim 2, characterized in that: At least two flow guide holes are arranged on the limit anti-step, and the flow guide holes are used to connect the thermal insulation layer with the external environment.

4. The roof insulation structure according to claim 2, characterized in that: The reinforced concrete layer includes an inclined top wall that is at least partially inclined, and at least a portion of the limiting anti-ridge is arranged near an end of the inclined top wall that is inclined downward.

5. The roof insulation structure according to claim 1, characterized in that: An airtight detection hole is provided in the reinforced concrete layer; And / or, a baffle is laid between the reinforced concrete layer and the thermal insulation layer; And / or, tiles are provided on the side of the reinforced concrete layer facing away from the thermal insulation layer.

6. The roof insulation structure according to any one of claims 1 to 5, characterized in that: The base layer comprises a structural layer and a waterproof layer, and the waterproof layer is located between the structural layer and the thermal insulation layer.

7. The roof insulation structure according to claim 6, characterized in that: The waterproof layer includes a pipeline for vacuum detection.

8. A method for preparing a roof insulation structure, characterized in that: Used to prepare the roof insulation structure according to any one of claims 1 to 7, characterized in that it comprises: A reinforced concrete layer is prepared outside the base layer of the roof, and a thermal insulation layer is formed between the reinforced concrete layer and the base layer.

9. The method for preparing a roof insulation structure according to claim 8, characterized in that: The thermal insulation layer is a vacuum sealed cavity.

10. The method for preparing a roof insulation structure according to claim 8, characterized in that: The thermal insulation layer is filled with a thermal insulation component, and the thermal insulation component includes at least one of a thermal insulation board and a foaming material.