Construction method of fabricated dome
Through the unit and segmented installation method combined with three-dimensional simulation and Rhino modeling, fine-tuning components and fixed clamping components are used to solve the problems of difficulty in lifting the beam column and risk of high-altitude operations in dome construction, achieving efficient and safe Hoisting and assembly process.
Patent Information
- Application Number
- CN202411324734.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-23
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-09-23
AI Technical Summary
It is difficult to lift the columns for high-altitude operations during dome construction, and the wire rope is not rigid enough, which makes the track crane unable to be lifted at one time, and there are great construction risks for high-altitude operations.
Three-dimensional simulation and calculation software is used to simulate and analyze the entire construction process, combine Rhino modeling to extract key point position information, and adopt unit and segmented installation methods. By setting fine-tuning components and fixed clamping components on the top of the support tire frame, the entire use is used. The station monitors the angle of the reflector to adjust the angle to achieve efficient lifting and assembly.
It improves the efficiency of high-altitude operations and reduces construction risks. By fine-tuning the use of components and fixed clamping components, it reduces the difficulty of adjusting the track crane, ensuring the stability and safety of the components.
Smart Images

Figure CN119062119A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of dome construction, and in particular, to a construction method of an assembled dome. Background Art
[0002] For the dome, the current construction is carried out by assembling it in sections on the ground and then hoisting it for assembly. When hoisting and assembling it at high altitude, a supporting frame needs to be set up for support. The construction is difficult and there are also great construction risks during high-altitude operations.
[0003] The beam column is particularly prominent. The structure of the beam column is shown in the figure below. Figure 1 As shown, it is an irregular spatial structure with a high height and heavy weight of the entire component. At present, it is divided into upper and lower partitions, and then each partition is divided into multiple sections for hoisting and assembly. The difficulty of assembling the bottom layer is relatively low because it is supported by the ground and has good stability. When assembling from the second layer of beam column sections, the difficulty lies in: 1. It is an aerial operation and the construction is difficult; 2. During hoisting, due to the insufficient rigidity of the wire rope and the heavy weight and inertia of the component, the crawler crane cannot hoist it into place at one time and needs to be fine-tuned, which is difficult to do using a crawler crane; 3. Since it is the first section of the beam column that has just been welded, its bearing capacity is effective. Therefore, when fine-tuning, there is no stable support at the bottom, which further increases the difficulty of fine-tuning.
[0004] In view of this, those skilled in the art need to improve the existing construction methods. Summary of the invention
[0005] The main purpose of this application is to provide a construction method for an assembled dome, which achieves the efficiency of high-altitude hoisting and assembly and reduces construction risks.
[0006] In order to achieve the above objectives, in a first aspect, the present application provides a method for constructing an assembled dome, comprising the following steps: S1. Use 3D simulation software to simulate and analyze the entire construction process and formulate construction technology; S2, using Rhino modeling to perform in-depth modeling, and extracting position information of key points, wherein the position information includes the coordinates of the key points and the angles between the upper and lower adjacent key points; S3. The assembled dome is installed by combining unit-type and segmented installation, which includes the installation of beam columns, arch shells, flat shells and the removal of the frame. Each component is segmented and numbered according to the detailed drawings before processing; S4. The installation of the beam column is carried out by assembling the corresponding components in sections in the factory and assembling them after hoisting on site, which includes the installation of the first beam column section at the bottom, the second beam column section in the middle, and the third beam column section at the top. The first beam column section is hoisted in three sections in turn and cables are set for temporary fixation. After the hoisting is completed, the adjacent sections are welded and fixed by supplementary rods. The welding is staggered along the vertical direction. After the assembly and welding of the first beam column section is completed, a support frame is set, and a fine-tuning component is set on the top of the support frame, and a fixed clamping component is set on the fine-tuning component at the same time. At the same time, reflectors and temporary fixing components are set at the key points of the first beam column section, and reflectors are set at the key points of the corresponding second beam column section. The second beam column section is hoisted in four sections in turn. When hoisting, the lower part of the assembly unit of the second beam column section is hoisted to the top of the first beam column section. The key points are located at the key points, and the corresponding welding connection parts are set up on the temporary fixing component. The second section beam column unit is clamped by the fixed clamping component through the fine-tuning component, and the angle between the reflector of the first section beam column and the reflector of the second section beam column is monitored by the total station. By comparing with the design angle, the upper part of the assembly unit of the second section beam column is adjusted by adjusting the fine-tuning component. After the adjustment is completed, the lower part of the assembly unit of the second section beam column is completely inserted into the temporary fixing component through the fine-tuning component and welded and fixed, and then the upper part of the assembly unit of the second section beam column is welded and fixed to the top of the supporting tire frame. After the four sections of the second section beam column are hoisted and fixed, the assembly units of the adjacent second sections beam columns are finally welded by the supplementary rods. During welding, staggered welding and fixing are performed along the vertical direction. The five sections of the third section beam column are hoisted and welded and fixed in the same way as the second section beam column. S5. Install the vault. After the vault is completed, the vault shell is installed. The vault shell is assembled in 6 sections. Each section of the vault shell is embedded in the installed vault and the ring beam of the bundled column. During the process, the total station is used for tracking and measurement. After fine-tuning in place, the card plate is used to fix it. S6. Install the flat shell, which is divided into 16 sections for assembly. One end of the flat shell unit is welded and fixed to the temporary support, and the other section is fixed with a temporary card plate. During the process, a total station is used for full-time tracking and measurement; S7. Remove the supporting tire frame.
[0007] A further improvement is that the supporting frame includes a supporting main limb and a conversion beam fixedly arranged at the lower part of the supporting main limb, an embedded part is arranged at the lower part of the conversion beam, the embedded part is connected and fixed by means of D=14mm steel bars using embedded bars, a hot-rolled H-shaped steel is arranged on the top of the supporting main limb as its force transmission beam and load-sharing beam, and the upper part of the force transmission beam adopts HW200×200 hot-rolled H-shaped steel.
[0008] A further improvement is that the fine-tuning assembly includes a mounting frame detachably connected to the force transmission beam, a first connecting frame horizontally slidably arranged on the mounting frame, a second connecting frame horizontally slidably arranged on the first connecting frame, and a mounting plate vertically rotatably arranged on the second connecting frame, the sliding directions of the first connecting frame and the second connecting frame are perpendicular, and the fixed clamping assembly is arranged on the mounting plate.
[0009] As a further improvement, the fixed clamping assembly includes a first clamping plate, a second clamping plate, and a hydraulic cylinder driving the first clamping plate and the second clamping plate to slide relative to each other.
[0010] As a further improvement, the temporary fixing assembly comprises fixing plates welded to three sides of the key point, and the key point is a drum-shaped node of the beam column.
[0011] A further improvement is that the staggered welding in step S4 includes first numbering the welds to be welded, using FCAW-CO 2 Welding is carried out in a staggered manner from the middle to both ends after all data are checked and qualified before welding. The interlayer temperature is 100-250℃.
[0012] A further improvement is that after welding is completed, non-destructive testing is carried out after slow cooling for 24 hours, and the next process can only be carried out after passing the test.
[0013] A further improvement is that during lifting, a crawler crane is used, the wire rope angle is controlled between 45-60°, and the upper two lifting points are hoisted using one wire rope and the lower two lifting points are each equipped with a wire rope and a 5t fall chain.
[0014] As a further improvement, the dismantling of the supporting tire frame includes the dismantling of the temporary tire frame of the flat shell, the dismantling of the second section supporting tire frame of the bundle column, the dismantling of the arch shell supporting tire frame, and the dismantling method includes configuring multiple gas cutters to perform cutting, and the cutting amount is 10mm at a time.
[0015] The invention provides a construction method for an assembled dome. Compared with the prior art, the invention has the following beneficial effects: a fine-tuning mechanism and a fixed clamping assembly are arranged on the top of a supporting frame. When hoisting and assembling, only part of the second section of the beam column needs to be erected in the area of the temporary fixed assembly. Thus, the beam column below does not need to bear weight and only serves as a positioning function. The gravity of the beam column unit is still borne by the crawler crane, and then clamped by the fixed clamping assembly on the fine-tuning assembly. Then, a total station is used to monitor the angle between the two reflectors, and then compared with the design angle in the design drawing, so as to control the fine-tuning mechanism to adjust the angles of the two to the design angle, thereby avoiding adjusting the position of the component by the crawler crane and adjusting the position of the component by the fine-tuning mechanism, thereby improving the efficiency of high-altitude operations and reducing construction risks. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 is a schematic diagram of the beam column; Figure 2 This is a schematic diagram of the installation of the beam column; Figure 3 A schematic diagram of a tire support frame; Figure 4 Schematic diagram of temporary fixed components at key points.
[0017] Among them: 1. Support tire frame; 2. Mounting frame; 3. First connecting frame; 4. Second connecting frame; 5. Mounting plate; 6. Hydraulic cylinder; 7. Temporary fixing assembly; 8. Key points. DETAILED DESCRIPTION
[0018] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiment of the present application will be clearly and completely described below in combination with the embodiment of the present application. Obviously, the described embodiment is only a part of the embodiment of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work should fall within the scope of protection of the present application.
[0019] It should be noted that the terms "first", "second" etc. of the specification and claims of the present application are used to distinguish similar objects, and need not be used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged in appropriate circumstances, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, the process, method, system, product or equipment comprising a series of steps or units need not be limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or equipment.
[0020] In addition, some of the above terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those of ordinary skill in the art, the specific meanings of these terms in this application can be understood according to specific circumstances.
[0021] In addition, the term "plurality" shall mean two or more.
[0022] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below in conjunction with the embodiments.
[0023] like Figure 2 As shown, a construction method of an assembled dome comprises the following steps: S1. Use 3D simulation software to simulate and analyze the entire construction process and formulate construction technology; S2, using Rhino modeling to perform in-depth modeling, and extracting position information of key points 8, wherein the position information includes coordinates of key points 8 and angles between upper and lower adjacent key points 8; S3. The assembled dome is installed by combining unit-type and segmented installation, which includes the installation of beam columns, arch shells, flat shells and the removal of the frame. Each component is segmented and numbered according to the detailed drawings before processing; S4. The installation of the beam column is carried out by assembling the corresponding components in sections in the factory and assembling them after hoisting on site, which includes the installation of the first beam column section at the bottom, the second beam column section in the middle, and the third beam column section at the top. The first beam column section is hoisted in three sections in turn and cables are set for temporary fixation. After the hoisting is completed, the adjacent sections are welded and fixed by supplementary rods. The welding is staggered along the vertical direction. After the assembly and welding of the first beam column section is completed, a support frame 1 is set, and a fine-tuning component is set on the top of the support frame 1, and a fixed clamping component is set on the fine-tuning component at the same time. At the same time, a reflector and a temporary fixing component 7 are set at the key point 8 of the first beam column section, and a reflector is set at the key point 8 of the corresponding second beam column section. The second beam column section is hoisted in four sections in turn. When hoisting, the lower part of the assembly unit of the second beam column section is hoisted to the first beam column section. The key point 8 of the beam column is set, and its corresponding welding connection part is set on the temporary fixing component 7. The second beam column unit is clamped by the fixed clamping component through the fine-tuning component, and the angle between the reflector of the first beam column and the reflector of the second beam column is monitored by the total station. By comparing with the design angle, the upper part of the assembly unit of the second beam column is adjusted by adjusting the fine-tuning component. After the adjustment is completed, the lower part of the assembly unit of the second beam column is completely inserted into the temporary fixing component 7 through the fine-tuning component and welded and fixed, and then the upper part of the assembly unit of the second beam column is welded and fixed to the top of the supporting tire frame 1. After the four sections of the second beam column are hoisted and fixed, the assembly units of the adjacent second beam columns are finally welded by the supplementary rods. During welding, staggered welding and fixing are performed along the vertical direction. The five sections of the third beam column are hoisted and welded and fixed in accordance with the second beam column. S5. Install the vault. After the vault is completed, the vault shell is installed. The vault shell is assembled in 6 sections. Each section of the vault shell is embedded in the installed vault and the ring beam of the bundled column. During the process, the total station is used for tracking and measurement. After fine-tuning in place, the card plate is used to fix it. S6. Install the flat shell, which is divided into 16 sections for assembly. One end of the flat shell unit is welded and fixed to the temporary support, and the other section is fixed with a temporary card plate. During the process, a total station is used for full-time tracking and measurement; S7, the supporting tire frame 1 is removed.
[0024] A further improvement is that the supporting tire frame 1 includes a supporting main limb and a conversion beam fixedly arranged at the lower part of the supporting main limb, an embedded part is arranged at the lower part of the conversion beam, the embedded part is connected and fixed by means of D=14mm steel bars using embedded bars, a hot-rolled H-shaped steel is arranged on the top of the supporting main limb as its force transmission beam and load-sharing beam, and the upper part of the force transmission beam adopts HW200×200 hot-rolled H-shaped steel.
[0025] like Figure 3As shown, a further improvement is that the fine-tuning assembly includes a mounting frame 2 detachably connected to the force transmission beam, a first connecting frame 3 horizontally slidably arranged on the mounting frame 2, a second connecting frame 4 horizontally slidably arranged on the first connecting frame 3, and a mounting plate 5 vertically rotatably arranged on the second connecting frame 4, the sliding directions of the first connecting frame 3 and the second connecting frame 4 are perpendicular, and the fixed clamping assembly is arranged on the mounting plate 5.
[0026] Preferably, the fixed clamping assembly comprises a first clamping plate, a second clamping plate, and a hydraulic cylinder 6 for driving the first clamping plate and the second clamping plate to slide relative to each other.
[0027] like Figure 4 As shown, preferably, the temporary fixing assembly 7 includes fixing plates welded to three sides of the key point 8, and the key point 8 is a drum-shaped node of the beam column.
[0028] In order to ensure the welding quality, the staggered welding described in step S4 includes first numbering the welds, welding using FCAW-CO2, and welding from the middle to both ends in a staggered manner after all data are checked and qualified before welding, with an interlayer temperature of 100 to 250°C.
[0029] In order to ensure the stability of the overall structure, non-destructive testing is carried out after slow cooling for 24 hours after welding is completed. The next process can only be carried out after passing the test.
[0030] For the sake of safety during hoisting operations, a crawler crane is used, and the wire rope angle is controlled between 45-60°. The upper two lifting points use one wire rope, and the lower two lifting points each use one wire rope with a 5t fall chain for hoisting.
[0031] In order to ensure the stability of the overall structure and avoid uneven force caused by excessive cutting, the dismantling of the supporting tire frame 1 includes the dismantling of the flat shell temporary tire frame, the dismantling of the second section supporting tire frame 1 of the bundle column, the dismantling of the arch shell supporting tire frame 1, and the dismantling method includes configuring multiple gas cutters to perform cutting, and the cutting amount is 10mm at a time.
[0032] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A method for constructing an assembled dome, characterized in that: The following steps are involved: S1. Use 3D simulation software to simulate and analyze the entire construction process and formulate construction technology; S2, using Rhino modeling to perform in-depth modeling, and extracting position information of key points, wherein the position information includes the coordinates of the key points and the angles between the upper and lower adjacent key points; S3. The assembled dome is installed by combining unit-type and segmented installation, which includes the installation of beam columns, arch shells, flat shells and the removal of the frame. Each component is segmented and numbered according to the detailed drawings before processing; S4. The installation of the beam column is carried out by assembling the corresponding components in sections in the factory and assembling them after hoisting on site, which includes the installation of the first beam column section at the bottom, the second beam column section in the middle, and the third beam column section at the top. The first beam column section is hoisted in three sections in turn and cables are set for temporary fixation. After the hoisting is completed, the adjacent sections are welded and fixed by supplementary rods. The welding is staggered along the vertical direction. After the assembly and welding of the first beam column section is completed, a support frame is set, and a fine-tuning component is set on the top of the support frame, and a fixed clamping component is set on the fine-tuning component at the same time. At the same time, reflectors and temporary fixing components are set at the key points of the first beam column section, and reflectors are set at the key points of the corresponding second beam column section. The second beam column section is hoisted in four sections in turn. When hoisting, the lower part of the assembly unit of the second beam column section is hoisted to the top of the first beam column section. The key points are located at the key points, and the corresponding welding connection parts are set up on the temporary fixing component. The second section beam column unit is clamped by the fixed clamping component through the fine-tuning component, and the angle between the reflector of the first section beam column and the reflector of the second section beam column is monitored by the total station. By comparing with the design angle, the upper part of the assembly unit of the second section beam column is adjusted by adjusting the fine-tuning component. After the adjustment is completed, the lower part of the assembly unit of the second section beam column is completely inserted into the temporary fixing component through the fine-tuning component and welded and fixed, and then the upper part of the assembly unit of the second section beam column is welded and fixed to the top of the supporting tire frame. After the four sections of the second section beam column are hoisted and fixed, the assembly units of the adjacent second sections beam columns are finally welded by the supplementary rods. During welding, staggered welding and fixing are performed along the vertical direction. The five sections of the third section beam column are hoisted and welded and fixed in the same way as the second section beam column. S5. Install the vault. After the vault is completed, the vault shell is installed. The vault shell is assembled in 6 sections. Each section of the vault shell is embedded in the installed vault and the ring beam of the bundled column. During the process, the total station is used for tracking and measurement. After fine-tuning in place, the card plate is used to fix it. S6. Install the flat shell, which is divided into 16 sections for assembly. One end of the flat shell unit is welded and fixed to the temporary support, and the other section is fixed with a temporary card plate. During the process, a total station is used for full-time tracking and measurement; S7. Remove the supporting tire frame.
2. A method for constructing an assembled dome according to claim 1, characterized in that: The supporting frame includes a supporting main limb and a conversion beam fixedly arranged at the lower part of the supporting main limb. An embedded part is arranged at the lower part of the conversion beam. The embedded part is connected and fixed by means of D=14mm steel bars by embedding steel bars. A hot-rolled H-shaped steel is arranged on the top of the supporting main limb as its force transmission beam and load-sharing beam. The upper part of the force transmission beam adopts HW200×200 hot-rolled H-shaped steel.
3. A method for constructing an assembled dome according to claim 2, characterized in that: The fine-tuning assembly includes a mounting frame detachably connected to the force transmission beam, a first connecting frame horizontally slidably arranged on the mounting frame, a second connecting frame horizontally slidably arranged on the first connecting frame, and a mounting plate vertically rotatably arranged on the second connecting frame. The sliding directions of the first connecting frame and the second connecting frame are perpendicular, and the fixed clamping assembly is arranged on the mounting plate.
4. A method for constructing an assembled dome according to claim 3, characterized in that: The fixed clamping assembly includes a first clamping plate, a second clamping plate, and a hydraulic cylinder driving the first clamping plate and the second clamping plate to slide relative to each other.
5. The construction method of an assembled dome according to claim 1, characterized in that: The temporary fixing assembly includes fixing plates welded to three sides of the key point, and the key point is a drum-shaped node of the beam column.
6. The construction method of a prefabricated dome according to claim 1, characterized in that: The staggered welding in step S4 includes firstly numbering the welds to be welded, using FCAW-CO 2 Welding is carried out in a staggered manner from the middle to both ends after all data are checked and qualified before welding. The interlayer temperature is 100-250℃.
7. A method for constructing an assembled dome according to claim 6, characterized in that: After welding is completed, non-destructive testing is carried out after slow cooling for 24 hours. Only after passing the test can the next process be carried out.
8. The construction method of an assembled dome according to claim 1, characterized in that: During hoisting, a crawler crane is used, and the angle of the wire rope is controlled between 45-60°. The upper two lifting points use a through rope, and the lower two lifting points each use a wire rope with a 5t fall chain for hoisting.
9. The construction method of an assembled dome according to claim 1, characterized in that: The dismantling of the supporting tire frame includes the dismantling of the temporary tire frame of the flat shell, the dismantling of the second section supporting tire frame of the bundle column, the dismantling of the arch shell supporting tire frame, and the dismantling method includes configuring multiple gas cutters to perform cutting, and the cutting amount is 10mm at a time.
Citation Information
Patent Citations
Installing method of imitative-ecological umbrella-shaped single-layer latticed shell steel structure
CN106499193A
Construction method of multi-layer space curved surface reticulated shell skeleton supported membrane structure roofing
CN110499921A
Ring beam joint combination and assembly method
CN112324156A
Hoisting construction method for complex large-span steel roof
CN115467421A
Drum joint installation method, steel reticulated shell, and assembly unit construction method
WO2023206851A1