Aerial corridor lifting construction method
Through the secondary lift design and the use of stress distribution beams, the difficulty in lifting the corridor caused by the small space on the construction site is solved, and higher construction flexibility and safety are achieved, ensuring building quality and aesthetics.
Patent Information
- Application Number
- CN202411443583.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-16
- Publication Date
- 2024-12-03
AI Technical Summary
In the case of small space on the construction site and limited working surfaces, the steel structure corridor lifting construction has the problem that the lifting section cannot be assembled and upgraded in place at one time.
Using a secondary lift design, the corridor lifting and assembly are divided into two stages. Through the use of the stress-distribution beam and the rear embedded parts, the lifting process is decomposed, and trial lifting and comprehensive inspection are carried out before each lift to ensure that Improved accuracy and safety every time.
It improves construction flexibility and accuracy, reduces the weight and difficulty of single lifts, enhances structural stability and construction safety, and ensures building quality and aesthetics.
Smart Images

Figure CN119062121A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to an aerial corridor lifting construction method. Background Art
[0002] In the field of steel structure, the application of steel truss corridors has become increasingly popular in recent years, mainly due to the increasing demand for large-span, high-altitude connection structures in modern buildings. With the acceleration of urbanization, the construction scale of large public buildings, transportation hubs, urban complexes and other projects has continued to expand, and higher requirements have been put forward for the corridor structure connecting different buildings or floors. The overall lifting of the steel structure corridor is a relatively complete construction technology. At present, the more widespread and practical traditional construction method is to use hydraulic lifting technology to achieve a one-time overall lifting of the steel truss corridor to the target height and complete the installation. However, the prerequisite of this method is that a sufficiently large working surface must be provided on site, and the lifting section must be assembled and lifted in place at one time. However, in the case of small space and limited working surface on the construction site, the corridor lifting construction has the problem that the lifting trusses cannot be assembled and lifted in place at one time. Summary of the invention
[0003] The purpose of the present invention is to provide an aerial corridor lifting construction method in view of the deficiencies in the prior art, so as to solve the corridor lifting construction when the construction site space is small and the working surface is limited, and to effectively solve the problem that the projection surface of the lifting section covers different heights, the lifting trusses cannot be assembled all at once, and cannot be lifted into place at one time.
[0004] The technical solution of the present invention is a construction method for lifting an aerial corridor, comprising the following steps:
[0005] Step 1, secondary lifting design;
[0006] Determine the secondary lifting plan for the aerial corridor. According to the actual situation of the construction site, the distribution and stress of the aerial corridor trusses, divide the lifting and assembly of the aerial corridor into two stages, and determine the positions of the upper and lower hanging points for the two lifts to ensure that the corridor can be successfully installed to the designed elevation in two lifts;
[0007] Step 2: Install the force distribution beam;
[0008] A force distribution beam is set at the position that affects the primary lifting structure, and a support leg is welded at the bottom of the force distribution beam, and the support leg is connected to the main building structure through a rear embedded part;
[0009] Step 3: assemble the corridor;
[0010] Assemble the loose components into the first lifting section on the podium assembly frame arranged just below the projection of the corridor; according to the arrangement of the hanging points, complete the assembly of the first pre-assembled section, the second pre-assembled section and the third pre-assembled section, wherein the assembly of the first pre-assembled section is carried out above the force distribution beam, and the lower chord of the truss of the first pre-assembled section is connected and fixed to the force distribution beam through a clamping plate;
[0011] Step 4: Installation of lifting platform and lifting equipment;
[0012] Install lifting platforms on the assembled first pre-installed section, the second pre-installed section and the third pre-installed section respectively, and install lifting equipment on the lifting platforms of the first pre-installed section and the second pre-installed section according to the arrangement of the lifting points for one lifting, and the lifting equipment is connected to the lower lifting device installed on the first lifting section through a steel strand;
[0013] Step 5, one-time promotion;
[0014] Before the formal lifting, a trial lifting is carried out. The first lifting section is lifted off the podium assembly frame by the lifting equipment and lifted to the set height. After hovering and standing still for the set time, a comprehensive inspection is carried out. After all the inspections are normal, the formal lifting can be started;
[0015] Step 6: aerial force conversion and lifting point transfer;
[0016] After the first lifting section is lifted to the design elevation, it is welded to the first pre-installed section to form the second lifting section. After the welding is completed, the lifting platform and lifting equipment on the first pre-installed section are dismantled and transferred, and the installation of the lifting equipment on the third pre-installed section is completed according to the arrangement of the secondary lifting suspension points;
[0017] Step seven, secondary promotion;
[0018] After the lifting equipment is installed and checked, the second lifting section is separated from the force distribution beam and lifted to the set height under the tension of the steel strand. After the pre-lifting stage is suspended and left to stand for the set time, a comprehensive inspection is carried out. After all data are correct, the second lifting is officially started;
[0019] Step 8: Upgrade completed;
[0020] When the second lifting section is lifted to the design elevation by the second lifting, the two ends of the second lifting section are respectively docked with the second pre-installed section and the third pre-installed section, and the lifting is finally completed.
[0021] As a preferred embodiment, step two is further refined as follows: accurately drilling holes in the concrete columns and concrete slabs of the main building structure to fix the rear embedded parts; using full penetration welding to tightly connect the legs to the rear embedded parts; using a tower crane to hoist the force distribution beam to a predetermined position for precise installation; using a full penetration welding process for the force distribution beam and the legs to ensure that the connection is strong and gap-free.
[0022] Preferably, the rear implantation member includes a first rear implantation member and a second rear implantation member, the first rear implantation member is fixed to the concrete column by a chemical anchor bolt; the second rear implantation member is fixed to the concrete plate by a hoop;
[0023] The legs include a front leg and a rear leg, each of which is composed of a plurality of short columns; the front leg is welded to the first rear embedded component, the rear leg is welded to the second rear embedded component, and stiffening plates are welded on opposite sides of the lower end of the short column of the rear leg, and the stiffening plates are connected by fillet welds;
[0024] The force distribution beam comprises a front force distribution beam welded to the top of the front supporting leg and a rear force distribution beam welded to the top of the rear supporting leg.
[0025] Preferably, the construction of the second rear embedded part clamping the concrete slab is detailed as follows: after the corresponding positions of the concrete slabs on both sides are drilled, a steel plate is placed at the hole position on the upper part of the concrete slab and a simple operating frame is set up. After the steel wire rope on the operating frame is pierced through the holes, the assembled bolts and steel plates under the concrete slab are lifted as a whole and moved up to the bottom of the concrete slab. After the bolts pass through the concrete slab and its upper steel plate in turn, nuts are used to lock and fix them on the upper part of the bolts.
[0026] Preferably, a slot matching the lower chord of the truss of the first pre-assembled section is provided at the bottom of the card plate in step three, and the first pre-assembled section is assembled and positioned, and the lower chord of the truss of the first pre-assembled section is connected and fixed to the force distribution beam by utilizing the slot, and the card plate is fixed by double-sided fillet welds.
[0027] Preferably, the lifting platform in step 4 comprises: a column vertically fixed to the upper chord of the pre-installed section truss, a tension rod connected between the column and the upper chord of the pre-installed section truss, a lifting beam horizontally fixed to the top of the column, a diagonal brace and a horizontal rod connected between the lifting beam and the upper chord of the pre-installed section truss, and a stiffening plate is provided at each rod node;
[0028] The lifting device is a hydraulic lifter, and the hydraulic lifter is installed on the lifting platform by using a fixing plate; a guide frame is arranged on one side of the hydraulic lifter to facilitate the smooth export of the excess steel strands reserved at the top of the hydraulic lifter.
[0029] Preferably, the fixing plate includes a temporary fixing plate for the lifter and a temporary fixing plate for the bottom anchor, and each hydraulic lifter is provided with 4 temporary fixing plates for the lifter and 4 temporary fixing plates for the bottom anchor;
[0030] The temporary fixing plate for the lifter and the temporary fixing plate for the bottom anchor both include an A surface and a B surface in contact with the hydraulic lifter and a C surface welded to the lifting platform. The A surface and the B surface are polished smooth with a grinder to clamp the base of the hydraulic lifter.
[0031] As a preferred method, in the fifth pilot lifting stage, the first lifting section will be about 150mm away from the podium assembly frame, and will stay in the air for 12 hours for comprehensive inspection. After all inspections are normal, the formal lifting will begin;
[0032] Step 7: During the pilot lifting phase, the second lifting section will be about 150mm away from the force distribution beam, and will remain in the air for 12 hours for a comprehensive inspection. After all inspections are normal, the formal lifting will begin.
[0033] As a preferred embodiment, step six is refined as follows:
[0034] First, after lifting the first lifting section to the designed elevation, level the first lifting section and the first pre-installed section to be connected to ensure smooth docking;
[0035] Next, increase the traction force, and use a steel wire rope to pull down the chain at the end of the first lifting section away from the first pre-installed section and fix it to the wall of the main building structure, so as to take temporary fixing measures for the first lifting section after leveling;
[0036] Subsequently, the first post-installation section is welded between the first lifting section and the first pre-installation section, and the upper and lower chords of the first lifting section and the first pre-installation section are butt-welded, and the first lifting section and the first pre-installation section are tightly connected by welding to form a second lifting section; after the welding is completed, the lifting point is removed, and the lifting platform and lifting equipment on the first pre-installation section are removed and transferred;
[0037] Finally, according to the arrangement of the secondary lifting suspension points, the lifting equipment and lifting steel strands are installed on the third pre-installed section, and the steel strands are connected to the lower suspension device installed on the second lifting section to prepare for the secondary lifting.
[0038] Preferably, when the second lifting section in step eight is lifted to about 200 mm from the design elevation, the lifting is suspended, and each lifting point is fine-tuned to accurately lift the second lifting section to the designed position; the lifting equipment is suspended to maintain the aerial posture of the second lifting section, one end of the second lifting section is welded to the upper and lower chords of the second pre-installed section, and the second rear-installed section is welded between the two; the other end of the second lifting section is welded to the upper and lower chords of the third pre-installed section, and the third rear-installed section is welded between the two, so as to form a stable overall structure of the corridor; the lifting equipment is simultaneously decompressed until the steel strands are completely relaxed; the lifting equipment and the lifting platform are removed to complete the overall lifting and installation of the aerial corridor.
[0039] Compared with the prior art, the present invention has the following beneficial effects:
[0040] ⑴ By adopting the secondary lifting construction method, the sky corridor is decomposed into two stages of lifting, which makes the construction more flexible and can adapt to more complex construction environments and needs, such as construction needs under the conditions of small construction site space and limited working surface. It also effectively solves the problem that the projection surface of the lifting section covers different heights, the lifting trusses cannot be assembled all at once, and cannot be lifted into place at one time.
[0041] ⑵By adopting the secondary lifting construction method, more accurate positioning and adjustment can be carried out during the construction process, making the two constructions more accurate, which is conducive to ensuring the overall quality and aesthetics of the building.
[0042] ⑶ Since the aerial corridor is divided into two stages, the weight and difficulty of a single lift are reduced, which helps to ensure the stability of the corridor structure during the lifting process and improves construction safety. A trial lift is carried out before each formal lift, and a comprehensive inspection is carried out after hovering and standing still. Only when all data are correct will the formal lift begin, further improving construction safety.
[0043] (⑷) By arranging a force distribution beam at the bottom of the first pre-installed section, the force distribution beam is fixed to the concrete columns and concrete slabs of the main building structure through legs and post-embedded parts, so that the concrete columns and concrete slabs of multiple post-embedded parts arrangement points can be effectively connected together to form a complete post-reinforcement structure at the bottom of the first pre-installed section. Through the post-reinforcement structure, the deadweight load of the corridor truss and the lifting reaction force can be evenly transferred to the dispersed concrete columns and concrete slabs during the lifting construction process, thereby increasing the load stability of the structural slab surface and effectively improving the bearing capacity of the main building structure during the lifting stage.
[0044] ⑸ The first rear embedded part is reinforced and bonded by chemical anchor bolts, which can ensure the connection strength between the first rear embedded part and the concrete column; the second rear embedded part is fixed to the concrete slab in the form of a hoop, which can not only ensure the connection strength between the second rear embedded part and the concrete slab, but also reinforce the concrete slab. Since the bottom steel plate of the second rear embedded part is fixed to the bottom of the concrete slab by a punching and hoisting construction method, compared with the prior art of installing the steel plate under the concrete slab, the punching and hoisting construction method has accurate positioning, simple operation and reduces construction costs, and is particularly beneficial to the construction of rear embedded part hoops for concrete slabs with very high floor heights. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] Figure 1 This is a flow chart of the construction of the aerial corridor lifting of the present invention;
[0046] Figure 2 This is a schematic diagram of the arrangement of lifting points of the aerial corridor of the present invention;
[0047] Figure 3 This is a schematic diagram of the state of the sky corridor of the present invention before one lifting;
[0048] Figure 4 This is a schematic diagram of the state of the sky corridor of the present invention when one lifting is completed;
[0049] Figure 5 This is a schematic diagram of the state of the aerial corridor of the present invention when the secondary lifting is completed;
[0050] Figure 6 This is a schematic diagram of the state after the aerial corridor lifting construction of the present invention is completed;
[0051] Figure 7 It is a schematic diagram of the arrangement of the force distribution beam of the present invention;
[0052] Figure 8 yes Figure 7 Schematic diagram of the middle AA section;
[0053] Fig. 9 yes Figure 7 Schematic diagram of the structure of the middle card board;
[0054] Fig.10 It is a schematic diagram of the arrangement of the rear implant of the present invention;
[0055] Fig.11 yes Fig.10 A schematic diagram of the structure of the first rear implant;
[0056] Fig.12 yes Fig.10 A top view of the connection between the second rear implant and the short column;
[0057] Fig.13 yes Fig.12 Schematic diagram of the middle AA section;
[0058] Fig.14 yes Figure 3 A partial enlarged view of the middle part;
[0059] Fig.15 is a schematic elevation view of a lifting platform of the present invention;
[0060] Fig.16 yes Fig.15 Schematic diagram of the middle AA section;
[0061] Fig.17 yes Fig.15 Schematic diagram of the middle BB section;
[0062] Fig.18 It is a schematic diagram of the connection between the hydraulic lifter and the guide frame of the present invention;
[0063] Fig.19 It is a structural schematic diagram of a temporary fixing plate of a lifter of the present invention;
[0064] Fig. 20 It is a structural schematic diagram of the bottom anchor temporary fixing plate of the present invention.
[0065] Main component symbols:
[0066] Corridor truss 1; first pre-installed section 11; second pre-installed section 12; third pre-installed section 13; first lifting section 14; second lifting section 15; first rear-installed section 16; second rear-installed section 17; third rear-installed section 18; reinforcement rod 19; force distribution beam 2; front force distribution beam 21; rear force distribution beam 22; leg 3; front leg 31; rear leg 32; first stiffening plate 321; rear embedded part 4; first rear embedded part 41; chemical anchor bolt 41 1; second rear embedded part 42; bolt 421; main building structure 5; concrete column 51; concrete slab 52; assembly frame 6; card plate 7; card slot 71; lifting platform 8; column 81; pull rod 82; lifting beam 83; diagonal brace 84; horizontal rod 85; lifting equipment 9; steel strand 91; lower sling 92; special bottom anchor 921; second stiffening plate 922; guide frame 93; temporary fixing plate 94 of lifter; temporary fixing plate 95 of bottom anchor. DETAILED DESCRIPTION
[0067] The present invention will be further described below in conjunction with the accompanying drawings:
[0068] See also Figure 1 As shown, the present invention provides a method for lifting and constructing an aerial corridor, comprising the following steps:
[0069] Step 1: Secondary improvement design.
[0070] According to the characteristics of the project, a secondary lifting design was carried out, and the secondary lifting plan of the aerial corridor was determined. According to the actual situation of the construction site, the distribution and force of the aerial corridor trusses, the lifting and assembly of the aerial corridor was divided into two stages, and the positions of the upper and lower hanging points of the two lifts were determined to ensure that the corridor can be successfully installed to the designed elevation after two lifts. By dividing the lifting and assembly of the aerial corridor into two stages, it not only effectively reduces the potential damage to the floor by its own weight, but also cleverly solves the construction difficulties caused by the narrow site.
[0071] It should be noted that in order to facilitate the lifting and installation of the corridor truss structure, the corridor truss is divided into sections, namely, pre-installed section, post-installed section and lifting section. The pre-installed section needs to be installed before the truss structure is lifted, and the post-installed section needs to be installed after the truss structure is lifted into place. The lifting section is the lifting part of the truss.
[0072] In this embodiment, according to the actual situation of the construction site, the distribution and force of the aerial corridor trusses, the lifting and assembly of the aerial corridor are divided into two stages, and the positions of the upper and lower hanging points of the two lifts are determined to ensure that the corridor can be successfully installed to the designed elevation in two lifts; based on precise structural analysis and force calculation, the best force distribution and lifting effect are achieved.
[0073] like Figures 3 to 5 As shown, the corridor truss 1 is divided into a first pre-installed section 11, a second pre-installed section 12, a third pre-installed section 13, a first lifting section 14, a second lifting section 15, a first post-installed section 16, a second post-installed section 17, and a third post-installed section 18. Figure 3 As shown, the first pre-installed section 11, the second pre-installed section 12, and the third pre-installed section 13 are installed before lifting, and the second pre-installed section 12 and the third pre-installed section 13 are arranged at the same horizontal position; the first lifting section 14 is lifted in a lifting stage; Figure 4 As shown, the first rear-mounted section 16 is installed after the first lifting section 14 is lifted into place, and the first lifting section 14 is welded with the first pre-installed section 11 to form the second lifting section 15, which is lifted in the secondary lifting stage; Figure 5 As shown, the second rear-mounted section 17 and the third rear-mounted section 18 are installed after the second lifting section 15 is lifted into place.
[0074] like Figure 2 As shown, the hanging point positions include A101, A102, A103, A104, A105, A106, A107, A108, A205, A206, A207, A208; among them, A101, A102, A103, A104 are arranged on the second pre-installed section, A105, A106, A107, A108 are arranged on the first pre-installed section, and A205, A206, A207, A208 are arranged on the third pre-installed section.
[0075] Step 2: Install the force distribution beam.
[0076] See also Figures 7 to 13 As shown, a force distribution beam 2 is arranged at a position affecting the primary lifting structure, a support leg 3 is welded to the bottom of the force distribution beam 2, and the support leg 3 is connected to the main building structure 5 through a rear embedded part 4.
[0077] Specifically, holes are accurately drilled at corresponding positions on the concrete columns 51 and the concrete slabs 52 of the main building structure 5 to fix the rear embedded parts 4; the legs 3 are tightly connected to the rear embedded parts 4 by full penetration welding; the force distribution beam 2 is hoisted to the predetermined position with the help of a tower crane for precise installation; the force distribution beam 2 and the legs 3 are welded by full penetration welding to ensure that the connection is firm and gap-free.
[0078] See also Figures 10 to 13As shown, the rear implant 4 includes a first rear implant 41 and a second rear implant 42. The first rear implant 41 is fixed to the concrete column 51 by a chemical anchor 411. The chemical anchor 411 is post-reinforced and bonded to ensure the connection strength between the first rear implant 41 and the concrete column 51. The second rear implant 42 is fixed to the concrete slab 52 in the form of a hoop, which can not only ensure the connection strength between the second rear implant 42 and the concrete slab 52, but also reinforce the concrete slab 52.
[0079] The second rear embedded part 42 includes two steel plates which are clamped on the upper part and the bottom part of the concrete slab. The construction of the second rear embedded part 42 clamped on the concrete slab 52 is detailed as follows: after the corresponding positions of the concrete slabs 52 on both sides are drilled, the steel plates are placed at the holes on the upper part of the concrete slab 52 and a simple operating frame is set up. After the steel wire rope on the operating frame is used to punch holes, the assembled bolts 421 and the steel plates under the concrete slab are hoisted as a whole and moved up to the bottom of the concrete slab 52. After the bolts 421 pass through the concrete slab 52 and the upper steel plate thereof in turn, nuts are used to lock and fix them on the upper part of the bolts 421. Since the bottom steel plate of the second rear embedded part 42 is fixed to the bottom of the concrete slab 52 by the drilling and hoisting construction method, compared with the prior art of erecting a frame to install the steel plate under the concrete slab, the drilling and hoisting construction method has accurate positioning and is easy to operate, which is particularly beneficial to the construction of the rear embedded part clamp of the concrete slab with a very high floor height.
[0080] In this embodiment, if Fig.11 As shown, according to the calculation and chemical anchor specifications (Table 1) and bearing capacity characteristic values (Table 2), the first rear embedded part 41 is fixed with 18 M24 chemical anchors 411, the embedded plate specifications are 500×400×20, and the material is Q235B. According to the position of the concrete column and the hanging point on the corridor, the line positioning and drilling are carried out, and the chemical anchor 411 is post-reinforced and bonded to ensure the connection strength between the first rear embedded part 41 and the concrete column 51.
[0081] Table 1 Hilti HVA chemical anchor models
[0082]
[0083] Table 2 Characteristic values of bearing capacity of chemical anchors Characteristic values of bearing capacity: concrete C20 / 25–f ck,cube =25N / mm 2 , anchor bolt HAS 5.8
[0084]
[0085] like Figure 12 to Figure 13As shown, the second rear embedded part 42 is fixed by multiple M30 tension bolts 421, the bolts are 4.8-grade common bolts, double nuts are used on the upper part, and the bolt length is 1500mm. The second rear embedded part 42 includes two steel plates, the steel plate specifications are 1100*600*30, and the material is Q235B. According to the position of the hanging point on the concrete slab and the corridor, the positioning and drilling are performed. The second rear embedded part 42 is installed on the concrete slab 52 in the form of a hoop, that is, the upper and bottom of the concrete slab 52 are covered with steel plates and fixed with tension bolts 421.
[0086] See also Figure 8 As shown, the leg 3 includes a front leg 31 and a rear leg 32, and the front leg 31 and the rear leg 32 are both composed of several short columns; the front leg 31 is welded to the first rear embedded part 41, and the rear leg 32 is welded to the second rear embedded part 42, and the first stiffening plate 321 is welded on the opposite sides of the lower end of the short column of the rear leg 32, and the first stiffening plate 321 is used to increase lateral constraints and support to enhance the overall stability of the leg; the thickness of the stiffening plates is 12mm, and the first stiffening plate 321 is connected by a fillet weld with a weld foot size of 7mm.
[0087] See also Figure 4 As shown, the force distribution beam 2 includes a front force distribution beam 21 welded on the top of the front support leg 31 and a rear force distribution beam 22 welded above the rear support leg 32. Through the cooperation of the front force distribution beam 21 and the rear force distribution beam 22, the concrete columns and concrete slabs of multiple rear embedded parts arrangement points can be effectively connected together, that is, multiple scattered rear reinforcement points are connected together to form a complete rear reinforcement structure. Through the rear reinforcement structure, the self-weight load of the corridor truss and the lifting reaction force can be evenly transferred to the scattered concrete columns and concrete slabs during the lifting construction process, thereby increasing the load stability of the structural slab surface and effectively improving the bearing capacity of the main building structure during the lifting stage.
[0088] Step three: assemble the corridor.
[0089] See also Figure 3 As shown, the loose components are assembled into the first lifting section 14 on the podium assembly frame 6 arranged just below the projection of the corridor; according to the arrangement of the hanging points, the first pre-assembled section 11, the second pre-assembled section 12 and the third pre-assembled section 13 are assembled, wherein the assembly work of the first pre-assembled section 11 is carried out above the force distribution beam 2, and the truss lower chord of the first pre-assembled section 11 is connected and fixed to the force distribution beam 2 through the clamping plate 7;
[0090] See also Fig. 9As shown, a slot 71 is provided at the bottom of the card plate 7 which is compatible with the lower chord of the truss of the first pre-assembled section 11. The first pre-assembled section 11 is assembled and positioned. The slot 71 is used to connect and fix the lower chord of the truss of the first pre-assembled section 11 to the force distribution beam 2. The function of the card plate 7 is to serve as a temporary support during installation to ensure the positioning, installation and welding stability of the first pre-assembled section 11. The card plate 7 is fixed with a 10mm double-sided fillet weld.
[0091] Step 4: Installation of lifting platform and lifting equipment.
[0092] See also Figure 3 As shown, the lifting platforms 8 are installed on the assembled first pre-installed section 11, the second pre-installed section 12 and the third pre-installed section 13 respectively, and the lifting equipment 9 is installed on the lifting platforms 8 of the first pre-installed section 11 and the second pre-installed section 12 according to the arrangement of the lifting points for one lifting, and the lifting equipment 9 is connected to the lower lifting device 92 installed on the first lifting section 14 through the steel strand 91. Fig.14 As shown, the top of the lower hanger 92 is open to allow the steel strand 91 to extend inward and be connected and fixed to a special bottom anchor 921 provided inside the lower hanger 92 , and second stiffening plates 922 are provided on opposite sides of the lower end of the lower hanger 92 .
[0093] It is worth noting that the lifting lower hanging point is welded to the truss upper chord steel beam node of the first lifting section 14 through the lower hanging device 92. In order to reduce the deformation of the truss steel structure of the first lifting section 14 during lifting, a lifting reinforcement rod 19 is set at the truss lower chord and truss upper chord hanging point. The welding adopts full penetration welding, welds, etc. Level 1; connection between the reinforcement rod 19 and the lower chord of the truss or the upper chord of the truss 12mm thick stiffening plates are installed at all locations. The stiffening plate is connected to the structure with a fillet weld, and the weld foot size is 7mm. Since the lower hanging point is directly connected to the first lifting section and the lifting equipment, it is the key point to bear the vertical load of the entire suspended structure. By setting the reinforcement rod, the lower hanging point has sufficient strength and rigidity to ensure that during the lifting process, whether under static or dynamic loads, the load can be stably and reliably transmitted and dispersed to avoid damage caused by local stress concentration.
[0094] See also Figures 15 to 17As shown, the lifting platform 8 includes: a column 81 vertically fixed to the upper chord of the pre-installed section truss, a tie rod 82 connected between the column 81 and the upper chord of the pre-installed section truss, a lifting beam 83 horizontally fixed to the top of the column 81, a diagonal brace 84 and a horizontal rod 85 connected between the lifting beam 83 and the upper chord of the pre-installed section truss, wherein the diagonal brace 84 is located below the lifting beam 83 and is arranged parallel to the tie rod 82 to support the lifting beam 83; the horizontal rod 85 is located on one side of the lifting beam 83, and the horizontal rod 85 is arranged to prevent the lifting beam 83 from deformation or displacement during the lifting process, thereby reinforcing the lifting platform 8; all rods of the lifting platform 8 are connected by welding, and the welds are all full penetration welds with a weld grade of two; 16mm thick stiffening plates are arranged at the nodes of each rod to improve the strength and rigidity of the lifting platform 8, and the stiffening plates are connected by fillet welds with a weld foot size of 10mm.
[0095] See also Fig.18 As shown, the lifting device 9 is a hydraulic lifter, which is installed on the lifting platform 8 using a fixing plate; a guide frame 93 is arranged on one side of the hydraulic lifter to facilitate the smooth export of excess steel strands reserved at the top of the hydraulic lifter.
[0096] It is worth noting that during the lifting or lowering process of the hydraulic lifter, the top of the hydraulic lifter must reserve excess steel strands. If too many steel strands are reserved, it will have a great impact on the operation of the steel strands during the lifting or lowering process and the locking and opening of the hydraulic lifter's sky anchor and upper anchor. Therefore, each hydraulic lifter must be equipped with a guide frame in advance to facilitate the smooth export of the excess steel strands reserved on its top. The excess steel strands can be freely guided backward and downward along the lifting platform. One of the main functions of the guide frame is to ensure the precise guidance and stable control of the corridor truss steel structure during the lifting process. Through precisely designed guide devices, such as slide rollers or guide wheels, the guide frame can guide the corridor truss steel structure to rise smoothly along the predetermined path, effectively preventing safety accidents caused by deviation, shaking or tilting, and ensuring high precision and stability of the lifting operation.
[0097] In this embodiment, the material of the lifter guide frame 93 is P102×5 round tube, and the material is Q235B. The material can be replaced during on-site production, but the cross-sectional area and bending resistance shall not be lower than the original cross-sectional area.
[0098] See also Figures 19 to 20As shown, the fixing plate includes a temporary fixing plate 94 for the lifter and a temporary fixing plate 95 for the bottom anchor. Each hydraulic lifter is provided with four temporary fixing plates 94 for the lifter and four temporary fixing plates 95 for the bottom anchor. The temporary fixing plates 94 for the lifter and the temporary fixing plates 95 for the bottom anchor both include an A surface and a B surface in contact with the hydraulic lifter and a C surface welded to the lifting platform 8. The A surface and the B surface are polished smooth with a grinder to clamp the base of the hydraulic lifter. The C surface is welded with the lower lifting platform structure and must not contact the base of the lifter during welding. The temporary fixing plate for the lifter is made of Q235B.
[0099] Step five, one upgrade.
[0100] Before the formal lifting, a trial lifting is conducted. After the first lifting section 14 is about 150mm away from the podium assembly frame 6 by the lifting equipment 9, it is suspended and left to stand in the air for 12 hours for a comprehensive inspection. After all the inspections are normal, the formal lifting is started. During the lifting process, the first lifting section 14 is ensured to be lifted smoothly and safely. During the lifting process, personnel are assigned to track and observe each important node position to observe the stress of the steel rope during the lifting process and whether there are any abnormalities in the welding seams of the lifting points. During the overall lifting process, this posture is maintained until the first pre-installed section 11 of the first lifting.
[0101] Step six: aerial force conversion and lifting point transfer.
[0102] First, after the first lifting section 14 is lifted to the designed elevation, the first lifting section 14 and the first pre-installed section 11 to be connected are carefully leveled to ensure smooth docking. At this point, the initial lifting task is successfully completed.
[0103] Next, increase the traction force and use a wire rope to pull down the chain at the end of the first lifting section 14 away from the first pre-installed section 11 and fix it to the wall of the main building structure, so as to take temporary fixing measures for the leveled steel truss of the first lifting section 14, effectively eliminate the shaking caused by wind load, achieve a stable force balance state, and create favorable conditions for subsequent welding work.
[0104] Subsequently, the first rear-installed section 16 is welded between the first lifting section 14 and the first pre-installed section 11, and the upper and lower chords of the first lifting section 14 and the first pre-installed section 11 are welded together to tightly connect the first lifting section 14 and the first pre-installed section 11 through welding to form a stable whole, which serves as the second lifting section 15 for secondary lifting; after welding is completed, the lifting points are removed, and the lifting platform 8 and the lifting equipment 9 on the first pre-installed section 11 are removed and transferred.
[0105] Finally, according to the arrangement of the secondary lifting suspension point, the lifting equipment 9 and the lifting steel strand 91 are installed on the third pre-installed section 13, and the steel strand 91 is connected to the lower sling 92 installed on the second lifting section 15 to prepare for the secondary lifting. In order to reduce the deformation of the truss steel structure of the second lifting section 15 during lifting, lifting reinforcement rods 19 are also provided at the truss lower chord and truss upper chord suspension points. The second lifting section 15 begins to separate from the force distribution beam 2 under the tension of the steel strand 91, marking the official start of the secondary lifting work. During the entire process, the stress state and deformation of the structure are strictly monitored to ensure that each step of the operation is accurate and correct, providing a strong guarantee for the safe installation of the aerial corridor truss.
[0106] Step seven, secondary improvement.
[0107] After the lifting equipment 9 is installed and checked, under the pulling force of the steel strand 91, the second lifting section 15 is moved about 150 mm away from the force distribution beam, and then stays in the air for 12 hours to hover and stand still in the pre-lifting stage for a comprehensive inspection. After all data are correct, the second lifting officially begins.
[0108] Step 8: Upgrade completed.
[0109] When the second lifting section 15 is lifted to a distance of about 200 mm from the design elevation, the lifting is stopped, and each lifting point is fine-tuned to accurately lift the second lifting section 15 to the design position, ensuring that the second lifting section 15 is stably docked with the second pre-installed section 12 and the third pre-installed section 13; the lifting device 9 stops working to maintain the aerial posture of the second lifting section 15, one end of the second lifting section 15 is welded to the upper and lower chords of the second pre-installed section 12, and the second rear-installed section 17 is welded between the two; the other end of the second lifting section 15 is welded to the upper and lower chords of the third pre-installed section 13, and the third rear-installed section 18 is welded between the two, thereby forming a stable overall structure of the aerial corridor; the lifting device 9 is decompressed synchronously until the steel strand 91 is completely relaxed; the lifting device 9 and the lifting platform 8 are removed to form a structure as shown in the figure. Figure 6 The sky corridor structure shown completes the overall lifting and installation of the sky corridor.
[0110] The aerial corridor lifting construction method provided by the present invention adopts a secondary lifting construction method to decompose the aerial corridor into two stages of lifting, so the construction flexibility is stronger and can adapt to more complex construction environments and requirements, such as construction requirements under the conditions of narrow construction site space and limited working surface, and effectively solves the problem that the projection surface of the lifting section covers different heights, the lifting trusses cannot be fully assembled at one time, and cannot be lifted into place at one time; by adopting the secondary lifting construction method, more accurate positioning and adjustment can be performed during the construction process, so that the two constructions have higher accuracy, which is conducive to ensuring the overall quality and aesthetics of the building; because the aerial corridor is decomposed into two stages, the weight and difficulty of a single lift are reduced, which helps to ensure the stability of the corridor structure during the lifting process, and the construction safety is higher; before each formal lifting, a trial lift is carried out, and a comprehensive inspection is carried out after hovering and standing still. After all data are correct, the formal lifting begins, further improving the construction safety.
[0111] The above description is only a preferred embodiment of the present invention. All equivalent changes and modifications made within the scope of the claims of the present invention should fall within the scope of the claims of the present invention.
Claims
1. A construction method for lifting an aerial corridor, characterized in that: The following steps are involved: Step 1, secondary lifting design; Determine the secondary lifting plan for the aerial corridor. According to the actual situation of the construction site, the distribution and stress of the aerial corridor trusses, divide the lifting and assembly of the aerial corridor into two stages, and determine the positions of the upper and lower hanging points for the two lifts to ensure that the corridor can be successfully installed to the designed elevation in two lifts; Step 2: Install the force distribution beam; A force distribution beam is set at the position that affects the primary lifting structure, and a support leg is welded at the bottom of the force distribution beam, and the support leg is connected to the main building structure through a rear embedded part; Step 3: assemble the corridor; Assemble the loose components into the first lifting section on the podium assembly frame arranged just below the projection of the corridor; according to the arrangement of the hanging points, complete the assembly of the first pre-assembled section, the second pre-assembled section and the third pre-assembled section, wherein the assembly of the first pre-assembled section is carried out above the force distribution beam, and the lower chord of the truss of the first pre-assembled section is connected and fixed to the force distribution beam through a clamping plate; Step 4: Installation of lifting platform and lifting equipment; Install lifting platforms on the assembled first pre-installed section, the second pre-installed section and the third pre-installed section respectively, and install lifting equipment on the lifting platforms of the first pre-installed section and the second pre-installed section according to the arrangement of the lifting points for one lifting, and the lifting equipment is connected to the lower lifting device installed on the first lifting section through a steel strand; Step 5, one-time promotion; Before the formal lifting, a trial lifting is carried out. The first lifting section is lifted off the podium assembly frame by the lifting equipment and lifted to the set height. After hovering and standing still for the set time, a comprehensive inspection is carried out. After all the inspections are normal, the formal lifting can be started; Step 6: aerial force conversion and lifting point transfer; After the first lifting section is lifted to the design elevation, it is welded to the first pre-installed section to form the second lifting section. After the welding is completed, the lifting platform and lifting equipment on the first pre-installed section are dismantled and transferred, and the installation of the lifting equipment on the third pre-installed section is completed according to the arrangement of the secondary lifting suspension points; Step seven, secondary promotion; After the lifting equipment is installed and checked, the second lifting section is separated from the force distribution beam and lifted to the set height under the tension of the steel strand. After the pre-lifting stage is suspended and left to stand for the set time, a comprehensive inspection is carried out. After all data are correct, the second lifting is officially started; Step 8: Upgrade completed; When the second lifting section is lifted to the design elevation by the second lifting, the two ends of the second lifting section are respectively docked with the second pre-installed section and the third pre-installed section, and the lifting is finally completed.
2. The aerial corridor lifting construction method according to claim 1 is characterized in that: Step 2 is broken down into the following steps: accurately drill holes in the concrete columns and concrete slabs of the main building structure to fix the embedded parts; use full penetration welding to tightly connect the legs to the embedded parts; use a tower crane to hoist the force distribution beam to the predetermined position for precise installation; use full penetration welding between the force distribution beam and the legs to ensure that the connection is strong and gap-free.
3. The aerial corridor lifting construction method according to claim 2 is characterized in that: The rear implantation piece includes a first rear implantation piece and a second rear implantation piece. The first rear implantation piece is fixed to the concrete column by a chemical anchor bolt; the second rear implantation piece is fixed to the concrete plate by a hoop. The legs include a front leg and a rear leg, each of which is composed of a plurality of short columns; the front leg is welded to the first rear embedded component, the rear leg is welded to the second rear embedded component, and stiffening plates are welded on opposite sides of the lower end of the short column of the rear leg, and the stiffening plates are connected by fillet welds; The force distribution beam comprises a front force distribution beam welded to the top of the front supporting leg and a rear force distribution beam welded to the top of the rear supporting leg.
4. The aerial corridor lifting construction method according to claim 3 is characterized in that: The construction details of the second rear embedded part clamping the concrete slab are as follows: after the corresponding positions of the concrete slabs on both sides are drilled, a steel plate is placed at the hole position on the upper part of the concrete slab and a simple operating frame is set up. After the steel wire rope on the operating frame is pierced through the hole, the assembled screw rod and steel plate under the concrete slab are lifted as a whole and moved up to the bottom of the concrete slab. After the screw rod passes through the concrete slab and its upper steel plate in turn, a nut is used to lock and fix it on the upper part of the screw rod.
5. The aerial corridor lifting construction method according to claim 1 is characterized in that: In step three, a slot is provided at the bottom of the card plate that is compatible with the lower chord of the truss of the first pre-assembled section. The first pre-assembled section is assembled and positioned, and the lower chord of the truss of the first pre-assembled section is connected and fixed to the force distribution beam by using the slot. The card plate is fixed by double-sided fillet welds.
6. The aerial corridor lifting construction method according to claim 1 is characterized in that: The lifting platform in step 4 includes: a column vertically fixed to the upper chord of the pre-installed section truss, a tension rod connected between the column and the upper chord of the pre-installed section truss, a lifting beam horizontally fixed to the top of the column, a diagonal brace and a horizontal rod connected between the lifting beam and the upper chord of the pre-installed section truss, and a stiffening plate is provided at each rod node; The lifting device is a hydraulic lifter, and the hydraulic lifter is installed on the lifting platform by using a fixing plate; a guide frame is arranged on one side of the hydraulic lifter to facilitate the smooth export of the excess steel strands reserved at the top of the hydraulic lifter.
7. The aerial corridor lifting construction method according to claim 6 is characterized in that: The fixing plates include temporary fixing plates for the lifter and temporary fixing plates for the bottom anchor. Each hydraulic lifter is provided with 4 temporary fixing plates for the lifter and 4 temporary fixing plates for the bottom anchor. The temporary fixing plate for the lifter and the temporary fixing plate for the bottom anchor both include an A surface and a B surface in contact with the hydraulic lifter and a C surface welded to the lifting platform. The A surface and the B surface are polished smooth with a grinder to clamp the base of the hydraulic lifter.
8. The aerial corridor lifting construction method according to claim 1 is characterized in that: Step 5: Pilot lifting stage: After the first lifting section is about 150mm away from the podium assembly frame, it will stay in the air for 12 hours for comprehensive inspection. After all inspections are normal, the formal lifting will begin; Step 7: During the pilot lifting phase, the second lifting section will be about 150mm away from the force distribution beam, and will remain in the air for 12 hours for a comprehensive inspection. After all inspections are normal, the formal lifting will begin.
9. The aerial corridor lifting construction method according to claim 1 is characterized in that: Step 6 is broken down into: First, after lifting the first lifting section to the designed elevation, level the first lifting section and the first pre-installed section to be connected to ensure smooth docking; Next, increase the traction force, and use a steel wire rope to pull down the chain at the end of the first lifting section away from the first pre-installed section and fix it to the wall of the main building structure, so as to take temporary fixing measures for the first lifting section after leveling; Subsequently, the first post-installation section is welded between the first lifting section and the first pre-installation section, and the upper and lower chords of the first lifting section and the first pre-installation section are butt-welded, and the first lifting section and the first pre-installation section are tightly connected by welding to form a second lifting section; after the welding is completed, the lifting point is removed, and the lifting platform and lifting equipment on the first pre-installation section are removed and transferred; Finally, according to the arrangement of the secondary lifting suspension points, the lifting equipment and lifting steel strands are installed on the third pre-installed section, and the steel strands are connected to the lower suspension device installed on the second lifting section to prepare for the secondary lifting.
10. The aerial corridor lifting construction method according to claim 1 is characterized in that: When the second lifting section is lifted to about 200 mm from the design elevation in step 8, the lifting is stopped and each lifting point is fine-tuned to ensure that the second lifting section is accurately lifted to the design position; The lifting equipment stops working and maintains the aerial posture of the second lifting section. One end of the second lifting section is welded to the upper and lower chords of the second pre-installed section, and the second rear-installed section is welded between the two. The other end of the second lifting section is welded to the upper and lower chords of the third pre-installed section, and the third rear-installed section is welded between the two, thus forming a stable overall structure of the corridor. The lifting equipment is decompressed synchronously until the steel strands are completely relaxed. The lifting equipment and the lifting platform are dismantled to complete the overall lifting and installation of the aerial corridor.